AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation 9 th Annual European Nuclear Power Conference Budapest, June 30 th , 2014

Transcript of AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled...

Page 1: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation

9th Annual European Nuclear Power Conference Budapest, June 30th, 2014

Page 2: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

AREVA – Serving Utilities EPR™ Projects Status The Value of Experience

Page 3: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

3 All rights are reserved, see liability notice.

Worldwide nuclear capacity evolution scenario

WNA 2013 Reference scenario

The future of nuclear is still bright but depends on the industry’s ability to ensure highest levels of safety while optimizing economic performance

2. WEO scenarios based on gross output corrected by minus 5% to reflect net output

Page 4: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

4 All rights are reserved, see liability notice.

Safety is the Cornerstone of AREVA Strategy

Safety of our Customers

30+ solutions in Safety Analysis, Safety Upgrades and Safety Procedures

Safety of our Products

Safety of our Operations

Reduced accident frequency rate (# of accidents / million hours worked) from 6.6 in 2004 to 1.7 in 2011

A wide new-generation reactor portfolio that offers the highest safety features

Supporting utilities in demonstrating and upgrading the safety of their fleet

Maintaining the highest level of safety throughout the lifecycle of our nuclear facilities

Page 5: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

5 All rights are reserved, see liability notice.

AREVA never stopped designing, building and licensing

Sample of our last constructions since the 80's

CHINON B1 PWR 900 MWe

FLAMANVILLE 1 PWR 1 300 MWe

TRILLO 1 PWR 1 000 MWe

ISAR 2 KONVOI PWR 1 300 MWe

EMSLAND KONVOI PWR 1 300 MWe

NECKAR 2 KONVOI PWR 1 300 MWe

CHOOZ B1 PWR 1 500 MWe

CHOOZ B2 PWR 1 500 MWe

CIVAUX 1 PWR 1 500 MWe

CIVAUX 2 PWR 1 500 MWe

ANGRA 2 PWR 1 270 MWe

LING-AO 1 PWR 1 000 MWe

LING-AO 2 PWR 1 000 MWe OL 3 EPRTM 1 600 MWe

FA 3 EPRTM 1 600 MWe

TSN 1 EPRTM 1 600 MWe

TSN 2 EPRTM 1 600 MWe

1985 1990 1995 2000 2005 2010 1980

Page 6: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

6 All rights are reserved, see liability notice.

Reference year: 2010

O&M support

M&FE 98

North America 122

O&M support

M&FE 2

South America 4

O&M support

M&FE 15

United Kingdom 1

O&M support

M&FE 90

Asia 17

O&M support

M&FE 75

Europe, Middle East & Africa

72

O&M support

M&FE 3

Russia & CIS 5

O&M support

M&FE

Central Europe & Nordic Countries

35

36

M&FE

India 7

325 reactors for M&FE

257 reactors for O&M support

AREVA serves 360+ reactors

360+ Nuclear Reactors are served by AREVA

Track Record: OEM of ~ 100 NPPs

Page 7: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

7 All rights are reserved, see liability notice.

Main Technical Data

Thermal power

Net power

Thermal efficiency

Target design availability

Number of loops

Steam (secondary) pressure

Operation cycle length

Collective dose

Design service life

I&C

4,590 MWth

1,650 MWe

37%

92%

4

77 bar

up to 24 months

<0.5 manSievert/yr

60 yrs

Full digital

3,150 MWth

1,150 MWe

37%

92%

3

72 bar

up to 24 months

<0.5 manSievert/yr

60 yrs

Full digital

A wide PWR Reactor Portfolio to better serve Utilities’ Needs

Page 8: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

AREVA – Serving Utilities

EPR™ Projects Status The Value of Experience

Page 9: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

9 All rights are reserved, see liability notice.

4 EPR™ Reactor Units under Construction

Flamanville 3

Olkiluoto 3 Taishan 1&2

The World’s First Advanced Fleet to be deployed

Page 10: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

10 All rights are reserved, see liability notice.

EPR™ Projects Industrial Schemes

AREVA

AREVA

Siemens Heit kamp

AREV

A

BoP CW BCI TI CW BNI NSSS NI CI

AREVA

TVO

Bou

ygue

s

TVO

C

P

E

Operator

I&C

Leader / PM

Olkiluoto 3

Flamanville 3

AREVA EDF

Bou

ygue

s

EDF

Alst

om

EDF

Bou

ygue

s

EDF

AREVA

C

P

E

Operator

I&C

Leader / PM

BoP CW BCI TI CW BNI NSSS NI CI

Taishan 1&2

AREVA

CN

PEC

Chi

nese

C

W

cont

ract

or

CNPEC

Alstom CNPEC

Chi

nese

C

W

cont

ract

or

CNPEC

CNPEC CNPEC

AREVA

CGNPC

C

P

E

Operator

I&C

Leader / PM

BoP CW BCI TI CW BNI NSSS NI CI

Engineering and design Procurement and delivery of equipment Construction Instrumentation and Control Project Management Nuclear Steam Supply System Nuclear Island Civil Island Balance of NI Balance of CI Balance of Plant Civil Works

E – P – C –

I&C – PM –

NSSS – NI – CI –

BNI – BCI – BoP – CW –

Page 11: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

11 All rights are reserved, see liability notice.

Olkiluoto 3 Project Progress

2007 2013 2009 2011 2008 2010

Reactor Building

Containment Line -7 m to +16 m

Delivery of the Reactor

Pressure Vessel

Lifting of the Reactor Dome

Reactor Pressure Vessel introduced

All primary loop components installed

Fuel handling equipment installed

2012

CRDM installation

2014

Secondary hydrotest

done

86% Project progress on AREVA’s scope

I&C tests launched at

Test Bay Containment tightness test

Page 12: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

12 All rights are reserved, see liability notice.

Olkiluoto 3 Progress update – June 2014

Overall Project progress: 86% NI Construction progress: 88% completed NSSS installed 95% of piping installed 80% of the complete ventilation, electrical

installation and finishing works Diesel building installed at 50%

I&C Launch of the I&C Test Bay in Germany Detailed I&C: Approval of the overall I&C system

plan by STUK in April Commissioning 25% completed Medium voltage distribution operational on the 4

divisions Pools tested under water Fuel transfer systems tested in dry conditions Reactor containment tightness tested

Page 13: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

13 All rights are reserved, see liability notice.

Olkiluoto 3 moving towards completion: Construction completion phase

June ‘13 Secondary Hydrotests (SHT) performed

August ‘13 All normal & emergency medium voltage switchgears energized

Page 14: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

14 All rights are reserved, see liability notice.

Olkiluoto 3 moving towards completion: Construction completion phase

October ‘13 Containment Heat Removal System pump drive

October ‘13 Installation of the RPV closure head

Page 15: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

15 All rights are reserved, see liability notice.

3 major milestones reached during the first months of 2014

1. Full success of the Containment Tightness Tests on February 12, 2014

2. Validation by STUK of the overall I&C system plan (architecture) after more than 3 years in April 2014

3. Start of the I&C tests on April 1, 2014 at Test Bay in Germany at AREVA Platform as required by the Finnish Nuclear act (YVL)

Page 16: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

16 All rights are reserved, see liability notice.

Flamanville 3 Major Milestones

2007 2012 2009 2011 2008 2010

Signature of the contract

First concrete pouring

Installation of Safeguard system piping

Delivery of the first embedded tank (RPE)

Start of Piping Erection

Copyright EDF

Welding of first supports in safeguard buildings

Installation of the pressurizer relief tank

EBS pumps installed

p.16

2013

Pouring of the last containment ring

Dome lifting

RPV installed

2014

57% Project progress on AREVA’s scope

Page 17: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

17 All rights are reserved, see liability notice.

Flamanville 3 Progress update – June 2014

AREVA scope Engineering: 82% of complete scope Procurement: 89% overall progress Licensing: On-going activities for the preparation

of the Operating License Application file Primary equipments: Steam Generators,

Pressurizer, Primary Pump Casing, Reactor Pressure Vessel delivered on site

Piping: Erection ongoing since 2011 I&C: 100th operational I&C and first TXS I&C

cabinets installed on site Installation: Reactor Pressure Vessel introduced

Civil works (outside AREVA scope) >95% progress of civil work Polar crane installation and dome lifting (July

2013) Inner structure completed Outer containment up to 42.00 m

Page 18: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

18 All rights are reserved, see liability notice.

Flamanville 3 Construction works entering the final phase

July ’13 Dome Lifting

October ’13 Reactor Vessel delivered to Flamanville site

Copyright EDF

Page 19: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

19 All rights are reserved, see liability notice.

Flamanville 3 Primary loop components delivery and installation

January ’14 Reactor Pressure Vessel installation in the Reactor Building

March ’14 Steam Generators delivered to Flamanville site

Copyright EDF

Page 20: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

20 All rights are reserved, see liability notice.

Taishan 1&2 EPR Project Major Milestones

First Concrete TS2 LOI to create a JV

in Nuclear Reactor Engineering

2007 2012 2009 2011 2008 2010

Signature of the Contract

First Concrete TS1

TS1 1st liner lifted

TS2 1st liner lifted

© Copyright TNPJVC

TS2: Dome lifted

2013

TS1 Installation of RPV internals

2014

TS1: All heavy components installed &

primary loop welded

TS2: 1st SG delivered

89% Project progress on AREVA’s scope

TS1: Dome lifted

TS1: RPV installed

Page 21: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

21 All rights are reserved, see liability notice.

Taishan 1 & 2 Progress update – June 2014

Taishan 1 Taishan 2

AREVA scope Procurement: 90% on extended scope including

purchasing, expediting, logistics Engineering: 91% completed Main components:

Unit 1: All primary heavy components installed Unit 2: Polar Crane commissioning completed Unit 2 : Heavy components manufactured and

hydro-tested Unit 2 : Pressurizer delivered to Taishan

Outside AREVA scope Unit 1: Emergency Diesel Generator Introduction Unit 1: Primary circuit welded Unit 1: IRWST hydro-tested Unit 1: RIS Accumulator Discharge Test Unit 1: RPV internals installed Unit 2: Reactor Building dome in place Unit 2: RPV installation preparation

Page 22: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

22 All rights are reserved, see liability notice.

Taishan 1 Primary loop completion

Copyright TNPJVC

Copyright TNPJVC

May ’14 Start of installation of the RPV internals

December ’12 All heavy eqp. installed & primary loop welded

July ’13 1st RCP arrived on site

Page 23: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

23 All rights are reserved, see liability notice.

Taishan 2 Delivery of heavy components

Copyright TNPJVC

November ’13 All SGs delivered on site

Copyright TNPJVC

April ’14 Pressurizer delivered on site

Copyright TNPJVC

Page 24: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

24 All rights are reserved, see liability notice.

New Build Update and Selected by AREVA Customers

New Build ongoing Negotiations New Build expected Tenders

Page 25: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

AREVA – Serving Utilities

EPR™ Projects Status

The Value of Experience

Page 26: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

26 All rights are reserved, see liability notice.

The Value of Experience: LICENSING

The EPR™ reactor: ► Construction license granted by Finnish, French

and Chinese Safety Authorities ► Final Design Acceptance confirmation issued by

the ONR in the UK in December 2012

The only Gen 3+ design submitted to the post– Fukushima European Safety checks

The EPR™ Reactor fully complies with WENRA objectives for New Power Reactors and is ready to comply with post–Fukushima requirements

This unique breadth and depth of design review strongly mitigates the licensing risk related to nuclear new build

国家核安全局 NNSA

2005

2007

2009

2012

Reviewed by reference Safety Authorities

LICENSING

Page 27: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

27 All rights are reserved, see liability notice.

A systematic process… There are more than 1600 Experience

feedbacks in the data base coming from current projects and our work on currently operating plants

… well established in the company: In 2011 alone, around 1 Experience

feedback per day has been captured

This unique project delivery experience has allowed AREVA to improve on all aspects of project execution Project management and organization Engineering Procurement Construction

Experience Feedbacks by Discipline

18%

44%

21%

6%

11% Procurement

Engineering Project management

Construction

Others

The Value of Experience: KNOWLEDGE MANAGEMENT

A Mature Field Experience Consolidation Process

KNOWLEDGE MANAGEMENT

Page 28: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

28 All rights are reserved, see liability notice.

The Value of Experience: GLOBAL PROJECT ORGANISATION

For the Taishan projects

50% Management Directors & Managers,

50% Engineering staff,

90% Procurement workforce,

have worked on the OL3 or FA3 projects

Proposals Projects

COMPETENT RESOURCES

CROSS - FERTILIZATION

Proposals Projects

COMPETENT RESOURCES

STANDARDS, METHODS, TOOLS

CROSS-FERTILIZATION

Project Management

Office Risk &

Opportunity Management

Contract Management

Schedule Management

Estimating

Lessons Learned

World PM Support

Organisation

Organisation Experienced Teams

Generic Organization Leveraging Experienced Teams

GLOBAL PROJECT ORGANISATION

Page 29: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

29 All rights are reserved, see liability notice.

The Value of Experience: ENGINEERING Standardisation on Early Engineering Activities

P&ID: Important input for layout in order to validate Civil Works (CW) interfaces

DSE stage 2: Important input for I&C

System description Stage 2 – First issue

NSSS engineering standardized and streamlined

System activities: Input data for other disciplines ready earlier and better defined

Number of engineering hours for NSSS completion

(for Taishan: estimate) Piping isometrics

Nb of revisions

OL3 TSN

- 60%

P&ID – First Issue

-36% -33% -70%

# months ENGINEERING

Page 30: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

30 All rights are reserved, see liability notice.

The Value of Experience: SUPPLY CHAIN Manufacturing of Heavy Components

Source: AREVA, average of the four Steam Generators for each unit

TS1

Pressure boundary & lower part sub-assembly

Tube sheet & lower shell

Shells subassembly

OL3

Hydraulic tests & preparation

_

Y1 Y2 Y3 Y4 Y5

Apr ’12 First two steam generators delivered on Taishan site

0

10

20

30

40

50

60

70

# months

OL3 TSN

- 40% ~5y

~3y

Pressure boundary & lower part sub-assembly

Tube sheet & lower shell

Shells subassembly

Hydraulic tests & preparation

SUPPLY CHAIN

Page 31: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

31 All rights are reserved, see liability notice.

The Value of Experience: INSTALLATION Welding of Primary Loop

Welding of the first SG completed

Welding of the second SG completed

Welding of the third SG completed

Welding of the fourth Steam Generator completed

OL3 TSN 1

Welding of SG1, Taishan

Welding Duration -30%

7

5

# months

INSTALLATION

Page 32: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

32 All rights are reserved, see liability notice.

The Value of Experience: PROCUREMENT Illustration on the Core Catcher

Delivery time core catcher protection layer1

1- Delivery time: from contract to delivery

Ceramic elements

# months

OL3 TSN

-68%

Included >1 year discussions about

docs & construction plans

FA3

<9

Delivery time core catcher cooling structure1

# months

OL3 TSN

-50%

FA3

<13

PROCUREMENT

Page 33: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

33 All rights are reserved, see liability notice.

The Value of Experience: CONSTRUCTION

6

4

13

TSN 1

24

47

First main milestones — Construction duration

12

16

9

10

OL 3

Dome lifting

Slab +1,5m

Start of inner containment

Gusset pouring

1 st concrete 1 st

# months

CONSTRUCTION

Page 34: AREVA, an unparalleled experience in building nuclear · PDF fileAREVA, an unparalleled experience in building nuclear reactors . ... 2005 . 2010 . Frank APEL: “AREVA, an unparalleled

Frank APEL: “AREVA, an unparalleled experience in building nuclear reactors” June 2014

34 All rights are reserved, see liability notice.

EPR reactor project delivery: An unique experience already leveraged

Engineering

Construction

Procurement Average procurement time

Construction duration from 1st concrete to dome lifting

Number of engineering hours on the NSSS scope

The EPR design and project delivery have reach industrial maturity

- 60%

- 50%

- 65%

Evolution between OL3 & Taishan

Thank You!