Archaeological Investigations of the West Shipyard Site · • Due Diligence Trench Work: July-...
Transcript of Archaeological Investigations of the West Shipyard Site · • Due Diligence Trench Work: July-...
Archaeological
Investigations of the
Vine Street Lot /
West Shipyard Site
Penny Pot Tavern & Landing and Griscom’s Academy
William L. Breton 1830
Vine and Water Streets
LATE-17TH CENTURY BEGINNINGSPenny Pot House and Landing / West Shipyard
SHIPBUILDING PERIOD ca. 1690 - 1760
○ 1690’s – James West established a Shipyard on a 100’ wide water lot north of Vine Street
○ 1720’s - Other shipwrights and related crafts people had taken up occupation of the project area
• Notable shipwrights included: Michael Hulings, James Porteus, Joseph Lynn, Charles West, William Taylor, Christopher Smith, and Jacob Casdorf.
1762
1750
MERCANTILE PERIOD ca. 1760 - 1850
○ Mid 18th century -Merchants began moving into the area as the city expanded north.
• Lumber merchants north of Wood Street steps, salt, flour, ship provisions, and commission merchants to the south.
• Landscape dotted by small alleys, stores and warehouse
○ By 1800 the wharves had largely been built out as far as modern Columbus Blvd.
1794 1800
GREAT CONFLAGRATION / RECONSTRUCTION
o July 9, 1850, a warehouse at 139 Water St., between Vine and Race Streets, caught fire igniting stores of saltpeter on the first floor
o Explosion spread the fire throughout the surrounding area; 367 houses and businesses destroyed; properties as far west as 4th Street, as far south as Race Street, and north beyond Callowhill were damaged.
o Damage from this fire totaled over $1.5 million in 1850
o Insurance records show that the entire Vine Street lot was destroyed.
o Site reconstructed over the next 2 years with new building configurations; Delaware Ave. extended north along the east side of the site.
1859
LATE 19TH CENTURY TO PRESENT
o By the 1870’s area between the rebuilt merchant houses infilled with a large market in the south.
o Fruit warehouse and domestic / commercial buildings replaced the lumber yard north of Wood Street
o By the early 20th century the whole block had been razed to establish a railyard for the Pennsylvania Railroad.
o By 1969 the property was acquired by the Hertz Rent-a-Car company; late 1980s all buildings removed and property converted to a municipal parking lot.
1895 1916
PRIOR ARCHAEOLOGICAL INVESTIGATIONS
CITY OF PHILADELPHIA - 1987
CITY OF PHILADELPHIA - 1987
DRWC / JOHN MILNER ASSOCIATES - 2012
Logs forming part of a grillage wharf.
Layer of woodworking waste and hardware.
DUE DILIGENCE WORK TO DATE
• Public Meeting 1 (Due Diligence Plan): May 23, 2019
• Due Diligence Trench Work: July- August 2019
• 2 Open Houses: July 26th and August 26th
• More than 170 attendees
• Public Meeting 2 (Report of Due Diligence Findings):
December 2nd, 2019
DUE DILIGENCE ARCHAEOLOGICAL TESTING PLAN
• Plan reviewed and approved by PHC and PA SHPO / PHMC;
• Intended to provide additional and more detailed information
about the types and distribution of archaeological resources
within the site;
• Data generated will be used to better inform construction plans
for the property and guide future data recovery investigations
and historic interpretation efforts
ARCHAEOLOGICAL STANDARDS TO BE APPLIED
• Adhere to established professional standards and practices, and
comply with the Pennsylvania Historical and Museum Commissions
Guidelines for Archaeological Investigations in Pennsylvania (2016)
• Assigned senior staff will meet the Secretary of the Interior’s
Standards for Archaeological Professionals
• Oversight performed by the Pennsylvania Historical and Museum
Commission (PHMC) and the Philadelphia Historical Commission
(PHC)
DUE DILIGENCE TESTING 2019
TESTING RESULTS
○ Due diligence testing results:
• 45 historical features documented
• 1556 artifacts collected
• More than 170 public visitors
TRENCH 1 FINDINGS
○ Trench 1
• Identified likely early 19th century wharf timbers (Context 17) in line with those identified by Weber in 1987.
• Feature 1/2 foundation complex at end of wharf timbers
• Woodworking debris from hewing timber at interface with former river bank
• Context 88 – Another hewn timber, perpendicular to the others and deeper
• Possible pilings from a pier
A view of the Feature 5 timber in profile showing its thickness and position
relative to the Feature 1/2 foundation.
Test Unit 1 Closing Plan View. Feature 1 /2
TRENCH 2 FINDINGS
○ Trench 2
• Foundation wall aligned with the western edge of Wood Street steps
South side of wall had associated pine floor with joist beneath
• Well feature capped by floor
• Large hewn beam with mortises and bevel cuts
TRENCH 3 FINDINGS
○ Encountered Stone Wall and Wood floor. Wall cut into fill.
• Additional stone walls beneath wood floor
• Wall supported by large stone flag spread footers
○ Southwest of wall was a well capped by mid 19th century fill
○ Several piles from a likely pier
○ Western end of the trench encountered disturbance from Hertz period tank, confirming accuracy of tank disturbance mapping
TRENCH 3 FINDINGS
TRENCH 4 FINDINGS
• Additional portion of Wall in alignment with that seen in Trench 3 but no floor
• Area built on a thick deposit of dredge spoil with coral
• Late 18th early 19th century foundation and brick porch
substantial quantity of largely intact late 18th and early 19th century ceramics
Southern end of Trench 4 Planview showing stone wall (Feature 42) and brick porch
( Feature 44)
TRENCH 4 FINDINGS
TRENCH 5 FINDINGS
OPEN HOUSE SITE VISITS
• July 26th and August 26th
• More than 170 attendees
INTERPRETATIONS
○ Throughout all three excavations virtually all artifacts found in all contexts pre-date 1850, the period of the Great Conflagration
• Subsequent Grading for Railroad and Parking Lot eliminated much of the evidence of the Late 19th century
○ Some foundations correspond with the post fire period like those in Trench 3 and possibly Trench 2
○ Earlier foundations related to the mercantile landscape of the late 18th and early 19th century survive
○ Additional grillage wharf related deposits survive south of Wood St.
○ Shipbuilding / waterfront woodworking evidence throughout entire site
○ Hertz lot building did not destroy early deposits.
ARCHAEOLOGICAL STANDARDS TO BE APPLIED
Preserve In Place
• Wherever possible significant archaeological resources will be preserved in place
and not impacted by proposed construction
Mitigation
• Where impacts cannot be avoided, disturbance to significant resources will be
mitigated by means of thorough archaeological documentation using state of the
art technologies and data gathering techniques
Report of Findings
• Information about the archaeological resources contained within the site will be
documented in a detailed professional report, which will be shared with the
public
NEXT STEPS
1. Due Diligence
a. Data Recovery Plan
2. Full Archaeological Investigation
a. Public Comment during PHC Review
b. Site Archaeological Investigation
1. Additional Public Engagement
Opportunities
3. Construction Monitoring
a. AECOM Archaeology Team On-Site
Monitoring throughout Excavation
4. Final Report
a. Publicly Available Document which will
Catalogue FindingsPhotos of President’s House Site Excavations, Independence Mall, 2007