ARAGON GEOTECHNICAL, INC.
Transcript of ARAGON GEOTECHNICAL, INC.
ARAGON GEOTECHNICAL, INC. Consultants in the Earth & Material Sciences
February 28, 2018Proposal No. SF -18- 1047
Hi -Desert Water District
55469 29 Palms HighwayYucca Valley, CA 92284
Attention: Ms. Samantha Mena
Subject: Response to Request for Proposal for Wastewater Reclamation
Project Phase I, Package C & D Collection System Construction
Town of Yucca Valley, California
Dear Ms. Mena:
In accordance with the instructions and proposal deadline enumerated in the District' s
Wastewater Reclamation Project Phase I, Package C & D RFQ/ RFP, Aragon Geotechnical
Inc. ( AGI) has prepared this cover letter, explanatory subsections, and required District
form submittals for the following items: Part 1 - Insurance Requirements Coverage Proof
Part 2 - Professional Service Agreement Comments
Part 3 - Exhibit " B" Soils and Materials Testing Fee SchedulePart 4 - Statement of Offer and Signature
All work will originate from AGI' s main office, with general contact information presented
below. We take pleasure in supplying highly personalized service, however, and will also
supply professional staff e- mail, cell phone, and other personal contact information ifawarded the work. It is our intent and goal to supply our clients with individualized
technical guidance that saves money, saves time, and avoids quality lapses for importantpublic infrastructure improvements.
AGI has performed similar services to those outlined in the RFQ/ RFP. Such services
include:
Task No. 1 - Soils and Asphaltic Pavement Compaction Testing
Provide a technician to perform Quality Assurance ( QA) compaction testingof soil and asphaltic materials in accordance to the project' s geotechnical
16801 Van Buren Blvd., Bldg. BRiverside, CA 92504
Tel: 951. 776. 0345 0 Fax: 951. 776. 0395
www.aragongeo. com
Aragon Geotechnical, Inc.
Response to RFQ - Phase I, Package C & D
Page No. 2
February 28, 2018
report, Town of Yucca Valley, and the District' s specifications. Task No. 2 - Materials Sampling
Sample representative material on- site and transport them to our laboratory
for testing. Results will be emailed to the Construction Manager and the
forwarded to the Town' s Inspector. Test results will include statio0n, date, time,
and testing data at a minimumTask No. 3 - Geotechnical Support
Provide geotechnical support at the request of the Construction Manager on
an " as -needed" basis.
Rask No. 4 - Final Compaction and Analysis Report
Prepare and submit a Final " Soils and Materials Testing Report" with
documentation of all reports and analysis results created under the quality
assurance monitoring during the construction of the project. The submittal will
rnncict of nne harm copy and one electronic Pnp file with the nnrrespnndingexcel file.
AGI is knowledgeable, experienced, and capable of providing responsive services to theDistrict. Please feel free to contact the undersigned, who will be the single person for
contact during the RFP review process and is the individual authorized to bind any
agreement, if you have any questions.
Respectfully submitted, Aragon Geotechnical, Inc.
C. Fernando Aragon,. E., M. S.
Geotechnical Engineer, G. E. 2994
After Hours, Weekends, and Emergency Contact Number: ( 909) 322- 1013
LAI I I/ CFA: la
Attachments
ARAGON GEOTECHNICAL, INC.
Aragon Geotechnical, Inc. Page No. 3
Response to RFQ - Phase I, Package C & D February 28, 2018
Part 1 - Insurance Requirements
An example Certificate of Insurance ( COI) is presented in the Attachments as instructed
by the PSA and meet the minimum levels of coverage. A detailed and project specific COIwill be provided if selected. This insurance will be maintained for the duration of this andfuture projects.
Part 2 - Professional Services Agreement ( PSA) Comments
AGI does not express any exceptions or conditions to the form of the District' s PSA.
Part 3 - Exhibit " B" Soils and Materials Testing Fee Schedule
A completed copy of the " Soils and Materials Testing Fee Schedule" is presented in theAttachments, entitled Exhibit " B".
Part 4 - Statement of Offer and Signature
This proposal was signed by an individual authorized to sign contracts, signature shownon prior page. Proposal pricing as presented for the requested scope of work shall remainfirm for a minimum of 90 days.
ARAGON GEOTECHNICAL, INC.
Aragon Geotechnical, Inc.
Response to RFQ - Phase I, Package C & D
Page No. 4
February 28, 2018
ARAGON GEOTECHNICAL, INC. Consultants in the Earth & Material Sciences
Attachments
ARAGON GEOTECHNICAL, INC.
ACt3R76
CCO CERTIFICATE OF LIABILITY INSURANCEDATE ( MM/ DD/ YYYY)
1! 30! 2018
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER( S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy( ies) must be endorsed. If SUBROGATION IS WAIVED, subject tothe terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to thecertificate holder in lieu of such endorsement( s).
PRODUCER
Dealey Renton and AssociatesLic. # 0020739
P. O. Box 10550
CONTACTNAME: Robin LeePHONE(AtC Na 714 427- 6810
FAX ). 714 427- 6818
E-MAILADDRESS, rlee@dealeyrenton. comINSURERS AFFORDING COVERAGE NAIC # Santa Ana CA 92711- 0550
INSURERA: Travelers Property Casualty Co of 25674
EACH OCCURRENCE $ 1, 000, 000
INSURED INSURERB: Admiral Insurance Company 24856
Aragon Geotechnical, Inc.
16801 Van Buren Boulevard
Riverside CA 92504
INSURERC:
INSURER D
GENERAL AGGREGATE $ 2, 000, 000
PRODUCTS - COMP/ OP AGG $ 2, 000, 000
INSURER E:
INSURER F:
AUTOMOBILE LIABILITY
X ANY AUTO
ALL OWNED SCHEDULED
X HIRED AUTOS
AUTOS
X NON - OWNEDAUTOS
CnVFRAGFS CFRTIFICATF NIIMRFR- 1533838413 RFVISInN Nt1MRFR-
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSRLTR TYPE OF INSURANCE INSD VIVO POLICY NUMBER
POLICY EFFMM/ DD/ YYYY
POLICY EXPMM/ DDtYYYY LIMITS
A X COMMERCIAL GENERAL LIABILITY
CLAIMS - MADE X OCCUR
X Contractual
68061-1962551 2/ 3/2018 2/ 3/ 2019 EACH OCCURRENCE $ 1, 000, 000DAMAGE TO RENTED
PREMISES Ea occurrence $ 1, 000,000
MED EXP ( Any one person) $ 10, 000
X BFPD. XCU PERSONAL BADV INJURY $ 1, 000,000
GEN' L AGGREGATE LIMIT APPLIES PER;
POLICY [] JECT D LOC
OTHER:
GENERAL AGGREGATE $ 2, 000, 000
PRODUCTS - COMP/ OP AGG $ 2, 000, 000
A AUTOMOBILE LIABILITY
X ANY AUTO
ALL OWNED SCHEDULED
X HIRED AUTOS
AUTOS
X NON - OWNEDAUTOS
BA8151 L133 2/ 3/ 2018 2/ 3/ 2019COMBINED SINGLE LIMIT $ Ea accident 1, 000,000
BODILY INJURY ( Per person) $
BODILY INJURY ( Per accident) $
PROPERTY DAMAGE $ Per accident
UMBRELLA LIAB
EXCESS LIAB
JOCCURCLAIMS - MADE
EACH OCCURRENCE $
AGGREGATE $
DED RETENTION $
A WORKERS COMPENSATIONAND EMPLOYERS' LIABILITY
Y / NANY PROPRIETOR/ PARTNER/ EXECUTIVE OFFICER/ MEMBER EXCLUDED?
Mandatory in NH) If yes, describe under
DESCRIPTION OF OPERATIONS below
N / A
UB5J594563 9/ 18/2017 9/ 18/ 2018 X STATUTE
EORHE. L. EACH ACCIDENT $ 1, 000, 000
E. L. DISEASE - EA EMPLOYEE $ 1, 000, 000
E. L. DISEASE - POLICY LIMIT $ 1, 000, 000
B Professional LiabilityClaims Made
E000004118001 12/ 9/ 2017 12/ 9/ 2018 per claim $ 1, 000, 000anni aggr $ 1, 000, 000
DESCRIPTION OF OPERATIONS / LOCATIONS! VEHICLES ( ACORD 101, Additional Remarks Schedule, may be attached if more space is required)
Evidence of Coverage in Force
For Proposal Use Onlyx
SSG\ I" RIR rLI1Lai 9 s r. c a rK a rurKarrniu
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
AUjHORIZED REPRESENTATIVE
a.r., vv._, ii 42p1988- 2014 ACORD CORPORATION. All rights reserved.
ACORD 25 (2014/01) The ACORD name and logo are registered marks of ACORD
Hi -Desert Water District' s Wastewater Reclamation Project
Phase I, Package C and D Collection System Construction
Soils and Materials Testing Fee Schedule
Item Qty. Unit Price/ Rate Total
Soil & AB Sieve Analysis 10 EA 120 1, 200Sand Equivalent 10 EA 90 900
Soil Maximum Density Test 200 EA 140 28, 000
Soil/ Asphalt Field Technician 400 HR 110 44, 000
Asphalt Concrete Coring HR
Concrete Inspector HR
Soil Samples Pickup & DeliveryTrips to Lab)
10 EA 40 400
Asphalt Concrete Gradation
Test
10 EA 250 2, 500
Asphalt Concrete Compacted
Max Density Test
9 EA 200 1, 800
Review Required Documents 1 LS 500 500
Attend Pre -Construction
Meeting ( Project Manager)
1 LS 500 500
Attend Additional Meetings 60 HR 110 6, 600
Support Staff 15 HR 50 750
Project Manager 25 HR 115 2, 875
Principal Engineer 5 HR 155 775
Final Geotechnical Report 1 LS 1, 500 1, 500Total: 92, 300
Considerations
1. This is a prevailing wage project. 2. work hours shall be estimated using a five ( S) day work week while assuming a rate of 400- 800 linear feet of pipeline
per day with applicable appurtenance installation. The typical rate of collection system pipeline installation is 200- 400
feet per day depending upon the depth of pipe and the contractor will be utilizing two construction headings toprovide the 400- 800 linear feet listed above. Depth of pipe should be considered when determining hours worked.
3. Overtime inspections performed in excess of 8 hours per day shall be paid at 1. 5 times the employee' s current rate. 4. The District will not pay for travel time, per diem, or mileage charges independent of the charges listed above. S. For Support Staff, Project Manager, Principal Engineer, and Final Geotechnical Report, Respondent shall complete the
number of hours as required and/ or lump sum rate as provided.