100% Design Community Meeting Please sign in on your mobile device: https//communitymeeting.ocps.net/ April 17, 2019 Pinar Elementary School

Transcript of April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power...

Page 1: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

100% Design Community Meeting

Please sign in on your mobile device: https//communitymeeting.ocps.net/

April 17, 2019

Pinar Elementary School

Page 2: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Pinar Elementary SchoolMeeting AgendaApril 17, 2019 6:00 PM

• Welcome – School Board Member Johanna López

• Introductions – Lauren Roth/ Facilities Communications

• Project Update – Architect – Contractor R. L. Burns

• Questions and Answers

• Adjournment

2

Page 3: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

LAKE COUNTYPOLK COUNTY

ORANGE COUNTYOSCEOLA COUNTY

North

Pinar Elementary School

Avalon Rd.

CURRY FORD RD

S. ECH

ON

LOC

KHATEE TR

.

S. CH

ICKASAW

TR.

S. ECH

ON

LOC

KHATEE TR

.

S. G

OLD

ENR

OD

RD

.

Surrounding Context

3

Page 4: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Existing Retention

AvalonR

d.

PO

WE

R E

AS

EM

EN

T

A N T H O N Y L A N E

CURRY WOODS CIRCLE

MATTILUCK CIRCLE

EXISTING SITE +/- 15.0 ACRES

EXISTING SCHOOL

PLAY FIELD

COVERED PLAY

COURTS

PLAYGROUND

EXIS

TIN

G B

LDG

TO

REM

AIN

north0’ 100’

EXISTING WETLANDS

MATTILUCK CIRCLE

CURRY WOODS CIRCLE

Site Aerial Map

Pinar Elementary School 4

Page 5: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

north

0’ 100’FRONT DOOR

Gate

ES CONCEPT INFORMATION:Parking: 140 carsStacking: 153 cars (30.6%)

PLANNING PARAMETERS:• 500 Student School with 500 Core• Current enrollment 412• Target +/-150 Parking• School currently has 1 bus• Bus loop accommodates 20 buses• Plan for 12 future portables

Fence

Gate

Gate

Final Site Plan

Pinar Elementary School

Parent Drop

Bike

Bike

1 STORYELEMENTARY

SCHOOL

Bus Drop

EXISTING CLASSROOM

BLDG.

Courts

Youth

TotRetention

Service

Retention

FUTURE

Play Field

CEP

5

TO C

HIC

KASA

W T

RAI

L

Page 6: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Exterior Elevation

8

Page 7: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Exterior Elevation

9

Page 8: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Exterior Elevation

10

Page 9: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Interior Spaces

11Pinar Elementary SchoolExample images from previous projects

ADMIN. RECEPTION ADMIN. RECEPTION

LOBBYLOBBY

Page 10: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Interior Spaces

12Pinar Elementary SchoolExample images from previous projects

ART

CLASSROOM MEDIA CENTER

MUSIC

Page 11: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Exterior Spaces

13Pinar Elementary SchoolExample images from previous projects

COVERED PLAY CANOPY PLAY LOTS

OUTDOOR COURTS

Page 12: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

• Water Spring Elementary• Deerwood Elementary School • Hungerford Elementary School • Maxey ES / Site 207-E-W-7• Laureate Park Elementary School• Meadow Woods Elementary School • Ventura Elementary School • Independence Elementary School• Eagle Creek Elementary School• John Young Elementary School • Shingle Creek Elementary School • Wheatley Elementary School

Previous OCPS Schools using the same/similar prototype

Pinar Elementary School 14

Page 13: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Sustainability

15Pinar Elementary School

Site• Native/low water plants – reduce water consumption• Low Impact Design (LID) stormwater design

Building• 10% more energy efficient than ASHRAE 90.1 standard• Lighting system and power outlets designed to turn lights and

power off in unoccupied spaces (energy reduction)• High Efficiency Chillers (10% energy reduction)• Light colored roof to reduce heat gain and improves energy

performance• Energy Star rated equipment• Water saving toilets, faucets, and fixtures• All classrooms in the new building have daylighting• Over 75% of ALL spaces in the new building have daylighting• Thermal efficient windows/glazing

• The new Pinar Elementary School is designed to meet Green Globes sustainable building standards. Sustainable Features Include:

Page 14: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Design, Permitting, Bidding

New Campus Construction (11 Months)

May 2020

August2018

June2019

Move-In

August2020

Schedule

Pinar Elementary School 16

Page 15: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

north

Phas

e Se

para

tion

Line

EXISTING CLASSROOM

BLDG.

ES CONCEPT INFORMATION:Parking: 140 carsStacking: 153 cars (30.6%)

Site Plan - Phase 1 & II May 2019 - August 2020

Pinar Elementary School

1 STORYELEMENTARY

SCHOOL

Bus Drop

FRONT DOOR

Service

Retention

CEP

Phas

e Se

para

tion

Line

17

0’ 100’

TO C

HIC

KASA

W T

RAI

L

Summer 2019

Summer 2019 Phase I – May 15, 2019 - August 15, 2019

Construct portion of pond and transfer fill to north side of site.Begin renovation in building 200

Phase II – August 15, 2019- May 20, 2020Complete the main building and portion of the parking and access drive

Page 16: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

north

0’ 100’FRONT DOOR

Gate

ES CONCEPT INFORMATION:Parking: 140 carsStacking: 153 cars (30.6%)

PLANNING PARAMETERS:• 500 Student School with 500 Core• Current enrollment 412• Target +/-150 Parking• School currently has 1 bus• Bus loop accommodates 20 buses• Plan for 12 future portables

Fence

Gate

Gate

Site Plan Phase III May 2020 - July 2020

Pinar Elementary School

Parent Drop

Bike

Bike

1 STORYELEMENTARY

SCHOOL

Bus Drop

EXISTING CLASSROOM

BLDG.

Courts

Youth

TotRetention

Service

Retention

FUTURE

Play Field

CEP

18

TO C

HIC

KASA

W T

RAI

L

Phase III – May 20, 2020 – July 15, 2020Complete the renovation of existing building 200 & 300Complete the access drive and pond on south side of property

Summer 2020

Sum

mer

20

20

Page 17: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

north

0’ 100’FRONT DOOR

Gate

ES CONCEPT INFORMATION:Parking: 140 carsStacking: 153 cars (30.6%)

PLANNING PARAMETERS:• 500 Student School with 500 Core• Current enrollment 412• Target +/-150 Parking• School currently has 1 bus• Bus loop accommodates 20 buses• Plan for 12 future portables

Fence

Gate

Gate

Site Plan Phase IV July 2020 -November 2020

Pinar Elementary School

Parent Drop

Bike

Bike

1 STORYELEMENTARY

SCHOOL

Bus Drop

EXISTING CLASSROOM

BLDG.

Courts

Youth

TotRetention

Service

Retention

FUTURE

Play Field

CEP

19

TO C

HIC

KASA

W T

RAI

L

Phase IV – July 15, 2020- November 23, 2020Demolish the existing building and complete playfields

Phase IV

Page 18: April 17, 2019 100% Design Community Meeting · 4/17/2019  · • Lighting system and power outlets designed to turn lights and power off in unoccupied spaces (energy reduction)

Questions & Answers

20Pinar Elementary School