APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. ·...
Transcript of APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. ·...
![Page 1: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/1.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
7th P
re-a
pp
lica
tio
n M
eeti
ng
1
5th
Pre
-ap
pli
cati
on
Rev
iew
Mee
tin
g
NON-PROPRIETARY
Response Time Analysis Technical Report
● Introduction
● Table of Contents for TeR
● Response Time Requirements
● Signal Path
● Response Time Allocation
● Response Time Analysis
● Conformance to BTP 7-21
![Page 2: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/2.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
1
Introduction
● NRC letter comments (Dec. 19, 2013)
Response Time Analysis TeR (APR1400-Z-J-N14003)
TS
![Page 3: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/3.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
2
Introduction
● KHNP plan proposed at the 13th PARM (Feb. 11, 2014) – TeR for response time allocation will be submitted. – TeR will include the following information;
• The allocated response time of individual components. • The sum of allocated response time does not exceed the total
response time requirement assumed in the safety analysis.
Response Time Analysis TeR (Cont’d)
![Page 4: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/4.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
3
Introduction
● Demonstrate that the total allocated response time does not exceed the corresponding response time requirement. – Define the safety system response time requirement for each trip
function. – Determine the safety system signal path for each trip function. – Allocate individual response time to each component on the
signal path. – Analyze safety system response time for each trip function.
● Provide conformance of the safety I&C system to BTP 7-21
Purpose of Response Time Analysis TeR
![Page 5: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/5.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
4
Introduction
● Response time analysis for the safety I&C system – Reactor trip response times described in DCD Tier 2 Table 7.2-5. – ESF response times described in DCD Tier 2 Table 7.3-7.
● Conformance of the safety I&C system to BTP 7-21 – Limiting response times – Digital computer timing requirements – Architecture – Design commitments – Performance verification – Use of cyclic real-time executive – Use of part-scale prototypes
Scope of Response Time Analysis TeR
![Page 6: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/6.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
5
Table of Contents for TeR
● 1. INTRODUCTION – 1.1 PURPOSE – 1.2 SCOPE
● 2. CODES AND STANDARDS ● 3. SAFETY I&C SYSTEM DESCRIPTION
– 3.1 SAFETY FUNCTIONS – 3.2 ASSUMPTIONS
● 4. RESPONSE TIME REQUIREMENTS ● 5. SIGNAL PATHS
Table of Contents
![Page 7: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/7.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
6
Table of Contents for TeR
● 6. RESPONSE TIME ALLOCATION – 6.1. LPP FOR REACTOR TRIP – 6.2. HPP FOR REACTOR TRIP – 6.3. LSGL FOR REACTOR TRIP – 6.4. HSGL FOR REACTOR TRIP – 6.5. LSGP FOR REACTOR TRIP – 6.6. HCP FOR REACTOR TRIP – 6.7. LRCF FOR REACTOR TRIP
Table of Contents (Cont’d)
![Page 8: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/8.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
7
Table of Contents for TeR
● 6. RESPONSE TIME ALLOCATION (Cont’d) – 6.8. HLPD FOR REACTOR TRIP
• 6.8.1 ENFMS Detector • 6.8.2 CEA Positions • 6.8.3 CEAC Penalty Factor
– 6.9. LDNBR FOR REACTOR TRIP • 6.9.1 ENFMS Detector • 6.9.2 CEA Positions • 6.9.3 Cold Leg Temperature
Table of Contents (Cont’d)
![Page 9: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/9.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
8
Table of Contents for TeR
● 6. RESPONSE TIME ALLOCATION (Cont’d) – 6.9. LDNBR FOR REACTOR TRIP (Cont’d)
• 6.9.4 Hot Leg Temperature • 6.9.5 Primary Coolant Pump Shaft Speed • 6.9.6 Reactor Coolant Pressure • 6.9.7 CEAC Penalty Factor
– 6.10. VOPT FOR REACTOR TRIP – 6.11. HLOGP FOR REACTOR TRIP
Table of Contents (Cont’d)
![Page 10: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/10.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
9
Table of Contents for TeR
● 6. RESPONSE TIME ALLOCATION (Cont’d) – 6.12. LPP FOR ESF ACTUATION
• 6.12.1 Safety Injection • 6.12.2 Containment Isolation
– 6.13. HCP FOR ESF ACTUATION • 6.13.1 Safety Injection • 6.13.2 Containment Isolation • 6.13.3 Main Steam Isolation
– 6.14. HHCP FOR ESF ACTUATION • 6.14.1 Containment Spray Pump • 6.14.2 Containment Isolation Valves Closed on CSAS
Table of Contents (Cont’d)
![Page 11: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/11.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
10
Table of Contents for TeR
● 6. RESPONSE TIME ALLOCATION (Cont’d) – 6.15. LSGP FOR ESF ACTUATION
• 6.15.1 Main Steam Isolation – 6.16. LSGL FOR ESF ACTUATION
• 6.16.1 Auxiliary Feedwater Pump (motor driven) • 6.16.2 Auxiliary Feedwater Pump (turbine driven)
– 6.17. HSGL FOR ESF ACTUATION • 6.17.1 Main Steam Isolation
– 6.18. CREVAS • 6.18.1 CREVAS Actuated Isolation Dampers • 6.18.2 Emergency Makeup ACU Fan
Table of Contents (Cont’d)
![Page 12: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/12.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
11
Table of Contents for TeR
● 6. RESPONSE TIME ALLOCATION (Cont’d) – 6.19 FHEVAS
• 6.19.1 FHEVAS Actuated Isolation Dampers • 6.19.2 Emergency Makeup ACU Fan • 6.19.3 Normal ACU Fan
– 6.20. CPIAS • 6.20.1 CPIAS Actuated Isolation Dampers • 6.20.2 High – Volume Purge Fan
Table of Contents (Cont’d)
![Page 13: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/13.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
12
Table of Contents for TeR
● 7. RESPONSE TIME ANALYSIS – 7.1. LPP FOR REACTOR TRIP – 7.2. HPP FOR REACTOR TRIP – 7.3. LSGL FOR REACTOR TRIP – 7.4. HSGL FOR REACTOR TRIP – 7.5. LSGP FOR REACTOR TRIP – 7.6. HCP FOR REACTOR TRIP – 7.7. LRCF FOR REACTOR TRIP
Table of Contents (Cont’d)
![Page 14: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/14.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
13
Table of Contents for TeR
● 7. RESPONSE TIME ANALYSIS (Cont’d) – 7.8. HLPD FOR REACTOR TRIP
• 7.8.1 ENFMS Detector • 7.8.2 CEA Positions • 7.8.3 CEA Penalty Factor
– 7.9. LDNBR FOR REACTOR TRIP • 7.9.1 ENFMS Detector • 7.9.2 CEA Positions • 7.9.3 Cold Leg Temperature
Table of Contents (Cont’d)
![Page 15: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/15.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
14
Table of Contents for TeR
● 7. RESPONSE TIME ANALYSIS (Cont’d) – 7.9. LDNBR FOR REACTOR TRIP (Cont’d)
• 7.9.4 Hot Leg Temperature • 7.9.5 Primary Coolant Pump Shaft Speed • 7.9.6 Reactor Coolant Pressure • 7.9.7 CEAC Penalty Factor
– 7.10. VOPT FOR REACTOR TRIP – 7.11. HLOGP FOR REACTOR TRIP
Table of Contents (Cont’d)
![Page 16: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/16.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
15
Table of Contents for TeR
● 7. RESPONSE TIME ANALYSIS (Cont’d) – 7.12. LPP FOR ESF ACTUATION
• 7.12.1 Safety Injection • 7.12.2 Containment Isolation
– 7.13. HCP FOR ESF ACTUATION • 7.13.1 Safety Injection • 7.13.2 Containment Isolation • 7.13.3 Main Steam Isolation
– 7.14. HHCP FOR ESF ACTUATION • 7.14.1 Containment Spray Pump • 7.14.2 Containment Isolation Valves Closed on CSAS
Table of Contents (Cont’d)
![Page 17: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/17.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
16
Table of Contents for TeR
● 7. RESPONSE TIME ANALYSIS (Cont’d) – 7.15. LSGP FOR ESF ACTUATION
• 7.15.1 Main Steam Isolation – 7.16. LSGL FOR ESF ACTUATION
• 7.16.1 Auxiliary Feedwater Pump (motor driven) • 7.16.2 Auxiliary Feedwater Pump (turbine driven
– 7.17. HSGL FOR ESF ACTUATION • 7.17.1 Main Steam Isolation
– 7.18. CREVAS • 7.18.1 CREVAS Actuated Isolation Dampers • 7.18.2 Emergency Makeup ACU Fan
Table of Contents (Cont’d)
![Page 18: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/18.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
17
Table of Contents for TeR
● 7. RESPONSE TIME ANALYSIS (Cont’d) – 7.19 FHEVAS
• 7.19.1 FHEVAS Actuated Isolation Dampers • 7.19.2 Emergency Makeup ACU Fan • 7.19.3 Normal ACU Fan
– 7.20. CPIAS • 7.20.1 CPIAS Actuated Isolation Dampers • 7.20.2 High – Volume Purge Fan
Table of Contents (Cont’d)
![Page 19: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/19.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
18
Table of Contents for TeR
● 8. REFERENCES ● APPENDIX A CONFORMANCE TO BTP 7-21
– A.1. LIMITING RESPONSE TIMES – A.2. DIGITAL COMPUTER TIMING REQUIREMENTS – A.3. ARCHITECTURE – A.4. DESIGN COMMITMENTS – A.5. PERFORMANCE VERIFICATION – A.6. USE OF CYCLIC REAL-TIME EXECUTIVE – A.7. USE OF PART-SCALE PROTOTYPES
Table of Contents (Cont’d)
![Page 20: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/20.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
19
Response Time Requirements
DCD Tier 2 Table 7.2-5 “Reactor Protective Instrumentation Response Time”
Reactor Trip Functions
No. Parameter Response Time (second)
1 Low Pressurizer Pressure (LPP) ≤1.15
2 High Pressurizer Pressure (HPP) ≤0.85
3 Low Steam Generator Level (LSGL) (Example 1) ≤1.25
4 High Steam Generator Level (HSGL) ≤1.15
5 Low Steam Generator Pressure (LSGP) ≤1.15
6 High Containment Pressure (HCP) ≤1.15
7 Low Reactor Coolant Flow (LRCF) ≤0.85
![Page 21: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/21.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
20
Response Time Requirements
Reactor Trip Functions (Cont’d)
No. Parameter Response Time
(second)
8 High Local Power Density (HLPD)
ENFMS Detector ≤0.65 (1)
CEA Positions ≤1.45 (2)
CEAC Penalty Factor (Example 2) ≤0.85 (2)
9 Low Departure from Nucleate Ratio (LDNBR)
ENFMS Detector ≤0.65 (1)
CEA Positions ≤1.45 (2)
Cold Leg Temperature ≤8.65 (3)
Hot Leg Temperature ≤8.65 (3)
Primary Coolant Pump Shaft Speed ≤0.45 (4)
Reactor Coolant Pressure ≤0.95 (5)
CEAC Penalty Factor ≤0.85 (2)
DCD Tier 2 Table 7.2-5 “Reactor Protective Instrumentation Response Time”
![Page 22: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/22.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
21
Response Time Requirements
DCD Tier 2 Table 7.2-5 “Reactor Protective Instrumentation Response Time” [Notes] (1) Neutron detectors are exempt from response time testing. The response time
of neutron flux signal portion of the channel is measured from the detector output or from the input of first electronic component in channel.
(2) Response time is measured from the output of the sensor. Acceptable CEA sensor response is demonstrated by compliance with Technical Specifications Subsection 3.3.1.
Reactor Trip Functions (Cont’d)
No. Parameter Response Time (second)
10 Variable Overpower Trip (VOPT) ≤0.55 (1)
11 High Logarithmic Power Level (HLOGP) ≤0.55 (1)
![Page 23: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/23.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
22
Response Time Requirements
DCD Tier 2 Table 7.2-5 “Reactor Protective Instrumentation Response Time” [Notes] (3) Response time is measured from the output of the resistance temperature
detector (sensor). RTD response time is measured at least once per 18 months. The measured response time of the slowest RTD is less than or equal to 8.0 seconds.
(4) The pulse transmitters measuring pump speed are exempt from response time testing. The response time is measured from the pulse shaper input.
(5) Response time is measured from the output of the pressure transmitter. The transmitter response time is less than or equal to 0.3 second.
ENFMS : Ex-core Neutron Flux Monitoring System CEA : Control Element Assembly CEAC : Control Element Assembly Calculator
Reactor Trip Functions (Cont’d)
![Page 24: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/24.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
23
Response Time Requirements
DCD Tier 2 Table 7.3-7 “ESF Response Time”
Engineered Safety Features Actuation Functions
No. Function Initiating Signal Response Time
(second)(1)
1 LPP
Safety Injection (Example 3) ≤40
Containment Isolation CIAS actuated low volume purge valves
≤5
Other CIAS actuated valves ≤83.5(2) / 62.0(3)
2 HCP
Safety Injection ≤40
Containment Isolation CIAS actuated low volume purge valves
≤5
Other CIAS actuated valves ≤83.5(2) / 62.0(3)
Main Steam Isolation MSIS actuated MSIVs ≤6.35
MSIS actuated MFIVs ≤11.35
3 HHCP Containment spray pump ≤50.4(4),(6) / 28.5(5),(6)
Containment isolation valves closed on CSAS ≤73.5(2) / 52.0(3)
![Page 25: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/25.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
24
Response Time Requirements
DCD Tier 2 Table 7.3-7 “ESF Response Time”
Engineered Safety Features Actuation Functions (Cont’d)
No. Function Initiating Signal Response Time
(second)(1)
4 LSGP Main Steam Isolation MSIS actuated MSIVs ≤6.35
MSIS actuated MFIVs ≤11.35
5 LSGL Auxiliary feedwater pump (motor driven) ≤61.45(4)
Auxiliary feedwater pump (turbine driven) ≤61.45
6 HSGL Main Steam Isolation MSIS actuated MSIVs ≤6.35
MSIS actuated MFIVs ≤11.35
7 CREVAS Control room air intake radiation - High
CREVAS actuated isolation dampers
≤8.4(7),(8)
Emergency makeup ACU fan ≤5.0(7),(8),(9)
![Page 26: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/26.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
25
Response Time Requirements
DCD Tier 2 Table 7.3-7 “ESF Response Time”
[Notes] (1) PPS cabinet delays are included.
Engineered Safety Features Actuation Functions (Cont’d)
No. Function Initiating Signal Response Time
(second)(1)
8 FHEVAS Fuel handling area spent fuel pool area radiation – High
FHEVAS actuated isolation dampers
≤8.2(7),(8),(9)
Emergency makeup ACU fan ≤5.0(7),(8)
Normal ACU fan Not applicable
9 CPIAS
Containment upper operating area / operating area radiation - High
CPIAS actuated isolation valves
≤9.9(7),(8)
High – Volume purge fan Not applicable
![Page 27: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/27.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
26
Response Time Requirements
DCD Tier 2 Table 7.3-7 “ESF Response Time” [Notes] (2) A loss of offsite power. EDG starting delay is included. Response time includes
movement of valves and attainment of pump or blower discharge pressure. (3) Offsite power is available. EDG starting delay is not included. Response time
includes movement of valves and attainment of pump or blower discharge pressure.
(4) Same as No. 2. In addition, delays of load-sequencing are included. (5) Same as No. 3. In addition, delays of load-sequencing are included. (6) Spray line fill time is not included. (7) EDG starting delay is not included.
Engineered Safety Features Actuation Functions (Cont’d)
![Page 28: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/28.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
27
Response Time Requirements
DCD Tier 2 Table 7.3-7 “ESF Response Time” [Notes] (8) The response time of the radiation detectors is not included. The response
time of the radiation signal portion of the channel is measured from the detector output or from the input of the first electronic component in channel to closure of dampers/valves or start fans.
(9) Fan motor run-up time is not included since the building volume is too large to make a substantial change to pressure compared to the isolation function.
Engineered Safety Features Actuation Functions (Cont’d)
![Page 29: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/29.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
28
Response Time Requirements
DCD Tier 2 Table 7.3-7 “ESF Response Time” [Notes]
CIAS : Containment Isolation Actuation Signal MSIS : Main Steam Isolation Signal MSIV : Main Steam Isolation Valve HHCP : High-High Containment Pressure CSAS : Containment Spray Actuation Signal CREVAS : Control Room Emergency Ventilation Actuation Signal ACU : Air Cleaning Unit FHEVAS : Fuel Handling Area Emergency Ventilation Actuation Signal CPIAS : Containment Purge Isolation Actuation Signal
Engineered Safety Features Actuation Functions (Cont’d)
![Page 30: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/30.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
29
Signal Path
Reactor Trip Functions
No. Parameter Signal Path
1 LPP
Transmitter → APC-S → PPS → RTSS
2 HPP
3 LSGL (Example 1)
4 HSGL
5 LSGP
6 HCP
7 LRCF
![Page 31: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/31.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
30
Signal Path
Reactor Trip Functions (Cont’d)
No. Parameter Signal Path
8 HLPD
ENFMS Detector Neutron Detector → ENFMS → CPCS → PPS → RTSS
CEA Positions
RSPT → CPCS → PPS → RTSS CEAC Penalty Factor (Example 2)
![Page 32: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/32.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
31
Signal Path
Reactor Trip Functions (Cont’d)
No. Parameter Signal Path
9 LDNBR
ENFMS Detector Neutron Detector → ENFMS → CPCS → PPS → RTSS
CEA Positions RSPT → CPCS → PPS → RTSS
Cold Leg Temperature Temperature Sensor → CPCS → PPS → RTSS Hot Leg Temperature
Primary Coolant Pump Shaft Speed
RCPSSSS → CPCS → PPS → RTSS
Reactor Coolant Pressure Transmitter → APC-S → PPS → RTSS
CEAC Penalty Factor RSPT → CPCS → PPS → RTSS
![Page 33: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/33.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
32
Signal Path
[Notes]
APC-S : Auxiliary Process Cabinet – Safety CPCS : Core Protection Calculator System ENFMS : Ex-core Neutron Flux Monitoring System PPS : Plant Protection System RTSS : Reactor Trip Switchgear System RSPT : Reed Switch Position Transmitter RCPSSSS : Reactor Coolant Pressure Shaft Speed Sensing System
Reactor Trip Functions (Cont’d)
No. Parameter Signal Path
10 VOPT Neutron Detector → ENFMS → PPS → RTSS
11 HLOGP
![Page 34: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/34.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
33
Signal Path
Engineered Safety Features Actuation Functions
No. Function Initiating Signal Signal Path
1 LPP
Safety Injection (Example 3)
Transmitter → APC-S → PPS → ESF-CCS → Pump/Valve
Containment Isolation
CIAS actuated low volume purge valves
Other CIAS actuated valves
2 HCP
Safety Injection
Containment Isolation
CIAS actuated low volume purge valves
Other CIAS actuated valves
Main Steam Isolation
MSIS actuated MSIVs
MSIS actuated MFIVs
![Page 35: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/35.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
34
Signal Path
Engineered Safety Features Actuation Functions (Cont’d)
No. Function Initiating Signal Signal Path
3 HHCP Containment spray pump
Transmitter → APC-S → PPS → ESF-CCS → Pump/Valve
Containment isolation valves closed on CSAS
4 LSGP Main Steam Isolation
MSIS actuated MSIVs
MSIS actuated MFIVs
5 LSGL Auxiliary feedwater pump (motor driven)
Auxiliary feedwater pump (turbine driven)
6 HSGL Main Steam Isolation
MSIS actuated MSIVs
MSIS actuated MFIVs
![Page 36: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/36.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
35
Signal Path
Engineered Safety Features Actuation Functions (Cont’d)
No. Function Initiating Signal Signal Path
7 CREVAS Control room air intake radiation - High
CREVAS actuated isolation dampers
Transmitter → RMS → ESF-CCS → Damper/Fan/Valve
Emergency makeup ACU fan
8 FHEVAS Fuel handling area spent fuel pool area radiation – High
FHEVAS actuated isolation dampers
Emergency makeup ACU fan
Normal ACU fan
9 CPIAS
Containment upper operating area / operating area radiation - High
CPIAS actuated isolation valves
High – Volume purge fan
![Page 37: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/37.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
36
Response Time Allocation
Example 1: LSGL Reactor Trip Function
No. Equipment Allocated Response Time (second)
1 Transmitter
2 APC-S
3 PPS
4 RTSS
Total
Requirement 1.250
TS
![Page 38: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/38.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
37
Response Time Allocation
Example 2: CEAC Penalty Factor for HLPD
No. Equipment Allocated Response Time (second)
1 RSPT
2 CPCS
3 PPS
4 RTSS
Total
Requirement 0.850
TS
![Page 39: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/39.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
38
Response Time Allocation
Example 3: LPP ESF Actuation Function (SI)
No. Equipment Allocated Response Time (second)
1 Transmitter
2 APC-S
3 PPS
4 ESF-CCS
5 SI Pump
Total
Requirement 40.000
TS
![Page 40: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/40.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
39
Response Time Analysis
Example 1: LSGL Reactor Trip Function
TS
![Page 41: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/41.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
40
Response Time Analysis
Example 1: LSGL Reactor Trip Function (Cont’d) TS
![Page 42: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/42.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
41
Response Time Analysis
● PPS Response Time Analysis
Example 1: LSGL Reactor Trip Function (Cont’d)
TS
![Page 43: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/43.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
42
Response Time Analysis
● PPS Response Time Analysis (Cont’d)
Example 1: LSGL Reactor Trip Function (Cont’d)
TS
![Page 44: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/44.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
43
Response Time Analysis
Example 2: CEAC Penalty Factor for HLPD
TS
![Page 45: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/45.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
44
Response Time Analysis
Example 2: CEAC Penalty Factor for HLPD (Cont’d) TS
![Page 46: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/46.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
45
Response Time Analysis
● CPCS Response Time Analysis
Example 2: CEAC Penalty Factor for HLPD (Cont’d)
TS
![Page 47: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/47.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
46
Response Time Analysis
● CPCS Response Time Analysis (Cont’d)
Example 2: CEAC Penalty Factor for HLPD (Cont’d)
TS
![Page 48: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/48.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
47
Response Time Analysis
● CPCS Response Time Analysis (Cont’d)
Example 2: CEAC Penalty Factor for HLPD (Cont’d)
TS
![Page 49: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/49.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
48
Response Time Analysis
● PPS Response Time Analysis
Example 2: CEAC Penalty Factor for HLPD (Cont’d)
TS
![Page 50: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/50.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
49
Response Time Analysis
● PPS Response Time Analysis (Cont’d)
Example 2: CEAC Penalty Factor for HLPD (Cont’d)
TS
![Page 51: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/51.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
50
Response Time Analysis
Example 3: LPP ESF Actuation Function (SI) TS
![Page 52: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/52.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
51
Response Time Analysis
Example 3: LPP ESF Actuation Function (SI) (Cont’d) TS
![Page 53: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/53.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
52
Response Time Analysis
● PPS Response Time Analysis
Example 3: LPP ESF Actuation Function (SI) (Cont’d)
TS
![Page 54: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/54.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
53
Response Time Analysis
● PPS Response Time Analysis (Cont’d)
Example 3: LPP ESF Actuation Function (SI) (Cont’d)
TS
![Page 55: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/55.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
54
Response Time Analysis
● ESF-CCS Response Time Analysis
Example 3: LPP ESF Actuation Function (SI) (Cont’d)
TS
![Page 56: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/56.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
55
Response Time Analysis
● ESF-CCS Response Time Analysis (Cont’d)
Example 3: LPP ESF Actuation Function (SI) (Cont’d)
TS
![Page 57: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/57.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
56
Response Time Analysis
● ESF-CCS Response Time Analysis (Cont’d)
Example 3: LPP ESF Actuation Function (SI) (Cont’d)
TS
![Page 58: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/58.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
57
Response Time Analysis
● ESF-CCS Response Time Analysis (Cont’d)
Example 3: LPP ESF Actuation Function (SI) (Cont’d)
TS
![Page 59: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/59.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
58
Conformance to BTP 7-21
● Acceptance Criteria Limiting response times should be shown to be consistent with safety requirements (e.g., suppress power oscillations, prevent fuel design limits from being exceeded, prevent a non-coolable core geometry). Setpoint analyses and limiting response times should also be shown to be consistent. The reviewer should verify that limiting response times are acceptable to the organizations responsible for reactor systems, electrical systems, and plant systems before accepting the limiting response times as a basis for timing requirements.
Example: Limiting Response Times
![Page 60: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/60.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
59
Conformance to BTP 7-21
● Conformance
Example: Limiting Response Times (Cont’d)
TS
![Page 61: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/61.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
60
Conformance to BTP 7-21
● Conformance (Cont’d)
Example: Limiting Response Times (Cont’d)
TS
![Page 62: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/62.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
61
Plan for Further Meeting
● Plan for the PARM in August – Present draft TeR (if needed)
● Plan for the Pre-application Audit in October
– Present final TeR – Confirm NRC acceptability
Path Forward
![Page 63: APR1400-Z-J-EC-14003-NP, Response Time Analysis Technical … · 2014. 6. 11. · APR1400-Z-J-EC-14003-NP . Chapter 7 I&C . 3 . Introduction Demonstrate that the total allocated response](https://reader034.fdocuments.us/reader034/viewer/2022052409/6077affe9c4982102327f104/html5/thumbnails/63.jpg)
15
th P
re-a
pp
lica
tio
n R
evie
w M
eeti
ng
APR1400-Z-J-EC-14003-NP
Chapter 7 I&C
62
Summary
● Response time analysis – All reactor trip and ESF actuation functions of the safety I&C
system will be incorporated into the TeR.
● Conformance to BTP 7-21 – The conformances for all 7 acceptance criteria of BTP 7-21 will
be described in the TeR.
Summary of TeR