    Supplier APQP: Four Phases

    APQP -> Phase 1 APQP -> Phase 2 APQP -> Phase 3

    Supplier Kick-Off and Planning Product/Process Realization Pre-PPAP

    Identify MEI and Supplier team

    contacts/roles/responsibilities

    Create and/or review DFMEA as appropriate

    depending upon design resp.Pre-production run

    Communicate and initiate Key Supplier Metrics Develop process flow chart (diagram). Process capability study

    Initial Supplier Program plan and timingCreate & review preliminary process flow

    diagram, PFMEA, and Control Plan.Finalize PCM: prepare for Safe Launch

    Conduct Cross-functional component design

    review (doc is located in GSQM)

    Finalize PCM & use document for any pre-

    product part runs.Finalize PFMEA and Control Plan

    Create preliminary Product Characteristics Matrix

    (PCM) - Safe Launch PlanConfirm tooling and gage construction progress. Review Supplier Ramp Plan

    APQP Requirements Develop Process Instructions Launch Readiness Audit: document key met

    Equipment Tooling & gage concept/design

    review.Finalize Process capability study Plan

    Re-qualify equipment, tooling & gaging as it

    moves between supplier site(s)

    Review MEI PPAP Requirments with the supplier

    (per MEI PPAP Checklist)

    Validation review of "1st Off" tool/part

    condition(s). Address any issues that can't becontained w/n program timing. Appearance Approval (as appropriate)

    Review supplier's manufacturing feasibility

    document(s)Floor plan layout Supplier participates in Plant Readiness Rev

    Review preliminary capacity study & initial

    supplier master schedule plan

    Update previous phase open issues and key

    documentsReview status of Key Supplier Metrics

    Iniate Open Issues DocumentUpdate previous phase open issues and key

    documents.

    A= MEI SDE will coduct APQP 1 - 4 w/ Supplier

    B= MEI SDE will conduct APQP 1 and 4 w/ Supp

    C=

    PPAP only to SDE. Supplier is still responsib

    maintaining APQP 1-4.

    Component Criticality Rating

    Magna Electronics (MEI) - 4 Phases of APQP for Supplier Develo

    Date: 14 May, 2008

    Rev. A Magna Electronics APQP Woorkbook

  • 7/23/2019 APQP Workbook

    2/20

    Product

    Characteristics Matrix -

    Tier II

    The PCM is used initially to define and determine appropriate controls for special characteristics, other process critical

    features and customer touch points. This tab is used to define the process at MEI's direct supplier. Throughout the APQP

    phase of launch this form is used as the Pre-Launch Control Plan and also forms the basis for Safe Launch Planning.

    Product

    Characteristics Matrix -

    Sub-Supplier

    The use of this tab is identical to the functionality define above, with the exception that this is used to document the

    remaining supply chain's, below the Tier II supplier, impact on the critical features.

    Open Issues The action plan format used to document open issues, their actions and resolution throughout the APQP process. This

    combines several different action plans generated by different, individual tools into a single document.

    Contacts Lists the individuals involved in the component(s) launch, for both MEI and the supplier, and their respective contact

    information. This tab is optional and may be used as needed.

    Key Metrics Definitions Operational definitions for the twelve key metrics. Explains the metric and its method of calculation.

    MEI PPAP Checklist &Document ".ZIP"

    Folder

    It is an expectation of MEI that the PPAP Checklist is used for each new part submission to make sure that all requiredPPAP elements are submitted free of the errors that have been historical observed. MEI is confident that if the PPAP

    Checklist is used that it will help insure expedited PPAP approval. Please use the embedded PPAP ".ZIP folder" to

    make sure that all required PPAP elements are submitted in a softcopy format that helps with ease of review and

    document storage.

    Format to be used for a weekly summary of the inspection results from the Safe Launch Plan. This information will be

    used as part of the decision making process for the removal of the Safe Launch Controls.

    PCM - Weekly QOS

    Report

    Supplier APQP: Table of Contents

    Blank Time Line Suppliers are required to create a Master Time Line for the launch of the awarded component(s). It is expected that a

    Gantt chart is used as the format. For those suppliers who do not have software available to meet this requirement, a

    blank time line is provided for their use.

    Shows the 4 APQP Phases and the activities that occur within them.Cover

    Table of Contents Lists all of the forms and examples included in this workbook. The Worksheet with "Tabs" highlighted in YELLOW require

    supplier documentation and reporting back to MEI SDE.

    Supplier FeasibilityStatement

    In accordance with The Automotive Industry Action Group (AIAG) and OE specific requirements, the supplier's teamfeasibility commitment document initiates the MEI APQP process. Unless exceptions or concerns are communicated to

    MEI as part of the quoting process it is the assumption that the supplier will be providing product that is fully compliant to

    all applicable drawings and specifications.

    Supply Chain Map Form for showing multi-tier supply chain relationships involved in providing the component/assembly to MEI. The

    information documented here will also be used in the creation of the Product Characteristics Matrix (PCM).

    Key Metrics Report Key Metrics contain those elements that contribute to a successful launch. This form allows for four reviews. The

    minimum requirement is to use the first two columns at APQP-2 and APQP-4. The APQP-3 report is generated during the

    first parts off run at the supplier's manufacturing location. This establishes a baseline performance on the process in its

    "as received" state. The APQP-4 report is generated at the time product is manufactured for the PPAP submission. Theadditional columns would either be used at the discretion of the SDE or based on circumstances that require additional

    reviews.

    Supply Chain Map

    Example

    An example of how a Supply Chain Map may appear for a typical metal component.

    Date: 14 May, 2008

    Revision: A

    Magna Electronics APQP WorkbookProcess Owner/Department:

    Chris Hempsall

    Approved by:

    Justin Reaume

  • 7/23/2019 APQP Workbook

    3/20

    Part No.: Date: ________________

    Rev. No.:

    YES NO

    ll

    l

    l

    l

    Conclusion:

    Feasible

    Feasible (Conditional)

    Not Feasible > Design revision required to produce product within the specified requirements.

    Issue # Open Close

    Name: Name:

    Title: Title:Signature:

    Date: Date:

    Name: Name:

    Title: Title:

    Date: Date:

    Considerations

    Is the product adequately defined (application requirements, etc.) to enable feasibility evaluation ?

    Can Engineering Performance Specifications be met as written?

    Review Considerations:

    Supplier Design Review Sign Off

    Part Name:

    Can product be manufactured without incurring any unusual:

    Costs for capital equipment?Costs for tooling?

    Alternative manufacturing methods?

    Can product be manufactured to tolerances specified on drawing?

    Can product be manufactured with Cpk's that meet requirements?

    Is there adequate capacity to produce product?

    Does the design allow the use of efficient material handling techniques?

    Are Cpk's greater than 1.33?

    Is the appropriate packaging available to protect the product during shipment? (Provide a proposal)

    Are special / uncommon materials required that are not readily available?

    > Product can be produced as specified with no revisions.

    Is statistical process control required on product?

    Is statistical process control presently used on similar products?

    Where statistical process control is used on similar products:

    Are the processes in control and stable?

    Corrective Actions / Resolution Plan

    Signature:

    Sign-Offs:

    Magna Electronics Supplier _____________________________

    Signature: Signature:

    ME and supplier product quality planning team has considered the following questions, not intended to be all-inclusive in performing a feasibility

    evaluation. The drawings and / or specifications provided have been used as a basis for analyzing the ability to meet all specified requirements. All

    "no" answers are supported with attached comments identifying our concerns and proposed changes to enable us to meet the specified requirements.

    > Changes recommended (see issues list below).

    Issues / Comments / Risks

  • 7/23/2019 APQP Workbook

    4/20

    02

    04

    06

    08

    10

    12

    14

    16

    18

    20

    22

    24

    26

    28

    30

    32

    34

    36

    38

    40

    42

    44

    46

    48

    50

    52

    02

    04

    06

    1.1 Design FMEA

    1.2 Preliminary Capacity Study reviewed

    1.3 Manufacturing Feasibility reviewed

    1.4 Component Design Review

    Product Characteristic Matrix initiated

    1.5 Key Supplier Metrics initiated

    1.6 Supplier Project timing plan

    1.7 Open Issues Action Plan created

    2.1 Measurement/ Testing equipment2.2 Preliminary Process Flow Chart Review

    2.3 Preliminary PFMEA Review

    2.4 Preliminary Control Plan Review

    2.5 Tool ing

    2.6 Capital equipment

    2.7 Training

    2.8 Process instructions

    2.9 Packaging

    2.10 Key Supplier Metrics reviewed

    3.1 ELV/IMDS

    3.2 Safe Launch Plan (PCM) finalized

    3.3 Sub-Supplier PPAP Approvals

    3.4 Supplier Ramp Plan

    3.5 Plant Readiness Review3.6 Launch Readiness Audit

    3.7 Appearance Approval Process (when applicable)

    3.8 Key Supplier Metrics reviewed

    4.1 PPAP

    4.2 Launch Readiness Audit

    4.3 Run at Rate

    4.4 Key Supplier Metrics reviewed

    4.5 OK to Launch Sign-Off

    5.1

    5.2

    5.3

    5.4

    5.5

    5.6

    5.7

    KEY: X Planned start O Planned completion + Act

    Supplier APQP: Four Phase Time Line (EXAMPLE)

    APQP

    PHASE

    OUTPUT

    Year 1

    3.

    Pre

    -PPAP

    4.

    Product/

    Process

    Validation&

    5.

    Other

    Requirements

    The Magna Electronics Supplier Advanced Product Quality Planning (APQP) process consists of 4 Phases. Essential to this process are 12 Key Supplier Metrics (KSM).

    reviewed during each of the following phases. The time line below illustrates the relationship between the 4 Phases, their deliverables and the Global Development & Prod

    This workbook consists of 9 forms in support of this process (the respective tab colors are highlighted in "yellow"). Suppliers are expected to use this process regardless oa PPAP package.

    1.

    SupplierKick-Off

    2.

    Product/Production

    Realization

    Magna Electronics APQP Workbook

  • 7/23/2019 APQP Workbook

    5/20

    02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 02 04 06 0 8

    1.1 Design FMEA

    1.2 Preliminary Capacity Study reviewed

    1.3 Manufacturing Feasibility reviewed

    1.4 Component Design Review

    Product Characteristic Matrix initiated

    1.5 Key Supplier Metrics initiated

    1.6 Supplier Project timing plan

    1.7 Open Issues Action Plan created

    2.1 Measurement/ Testing equipment

    2.2 Preliminary Process Flow Chart Review

    2.3 Preliminary PFMEA Review

    2.4 Preliminary Control Plan Review

    2.5 Tool ing2.6 Capital equipment

    2.7 Training

    2.8 Process instructions

    2.9 Packaging

    2.10 Key Supplier Metrics reviewed

    3.1 ELV/IMDS

    3.2 Safe Launch Plan (PCM) finalized

    3.3 Sub-Supplier PPAP Approvals

    3.4 Supplier Ramp Plan

    3.5 Plant Readiness Review

    3.6 Launch Readiness Audit

    3.7 Appearance Approval Process (when applicable)

    3.8 Key Supplier Metrics reviewed

    4.1 PPAP

    4.2 Launch Readiness Audit

    4.3 Run at Rate

    4.4 Key Supplier Metrics reviewed

    4.5 OK to Launch Sign-Off

    5.1

    5.2

    5.3

    5.4

    5.5

    5.6

    5.7

    KEY: X Planned start O Planned completion + Actu

    5.

    Other

    Requirements

    3.

    Pre-PPAP

    4.

    Product/

    Process

    Validation

    &

    1.

    SupplierKick-Off

    2.

    Product/Pr

    oduction

    Realization

    Supplier APQP: Blank Time Line

    AP

    QP

    PHASE

    OUTPUT

    Year 1

  • 7/23/2019 APQP Workbook

    6/20

    Enter the number ofGREEN elements at

    the time of the report.

    Enter the total number of elements being

    tracked. There are 34 elements on the

    APQP Progress Report. For suppliers

    where the DFMEA does not apply subtract

    1. For suppliers who are not providing an

    Appearance item, subtract 1.

    Enter number of completed processinstructions at the time of the review.

    Enter total number of process instructions

    needed for serial production.

    Enter, as a decimal number, the ratio of

    total parts produced to good parts from

    the trial run.

    Enter the number '1,' which represents the

    production of 100% good, or usable, parts.

    The amount of available capacity at the

    time of the review. Enter result as a

    decimal number.

    The minimum amount of available capacityshould be 15% (85% utilization). Enter

    0.15

    Enter the number of characteristics, with

    a Ppk > 1.67, at the time of the review.

    Enter the total number of designated

    characteristics on the drawing.

    This is the total number of samples that

    passed all of the required testing at the

    time of the review.

    The should represent the total number of

    individual tests required times the number

    of samples, for each test, that is required.

    Total number of set-up, manufacturingand inspection instructions needed.

    Process Efficiency Measured in available capacity.

    Expectation for open capacity is 15%

    minimum. This is achieved by dividing

    Takt time into cycle time and subtractingthe result from 1.

    Results

    APQP Readiness

    DefinitionMetric

    Data is derived from the 'APQP Progress

    Report'. This metric tracks the

    percentage ofGREEN elements

    compared to the total number of

    elements being tracked.

    Process Instructions

    APQP: Key Supplier Metrics Operational Definitions

    First time Capability Percentage of good parts to the total

    number of parts produced during the Run

    at Rate.

    Test Achievement Total number of performance and

    materials tests that need to be conducted

    to meet the specifications shown on the

    drawing. This number is a combination

    of the number of unique tests multiplied

    by the number of samples required for

    the test.

    This section defines the Key Supplier Metrics that will be tracked throughout the four APQP Phases. Reviews will be held toward the end of each of the four

    phases. Review of these metrics, in the Phase 4, will take place before the final full PPAP approval

    Process Capabil ity The number of designated

    characteristics with a Ppk > 1.67.

    Goal

  • 7/23/2019 APQP Workbook

    7/20

    Results

    DefinitionMetric

    APQP: Key Supplier Metrics Operational Definitions

    This section defines the Key Supplier Metrics that will be tracked throughout the four APQP Phases. Reviews will be held toward the end of each of the four

    phases. Review of these metrics, in the Phase 4, will take place before the final full PPAP approval

    Goal

    Enter the appropriate stage of process

    implementation in regard to

    manufacturing for serial production.

    1. Prototype process is implemented; No

    released deviation of concession; No

    containment plan.

    2. Interim process implemented, with

    partial production intent process; No

    released deviation or concession; No

    containment plan.

    3. Prototype or partially implemented

    process; Released deviation or

    concession; No containment plan.

    4. Partial or fully implemented process;

    Released deviation or concession;Containment plan implemented.

    5. Fully implemented process; No

    deviation or concession required

    5. Fully implemented process; No deviation

    or concession required.

    The score achieved on the Launch

    Readiness Audit. Enter data as a

    decimal number.

    The minimum goal for full release for

    production is 90%. Goal is 100% and

    entered as "1".

    The number of approved sub-component

    and material PPAPs at the time of the

    report.

    The number of approved sub-component

    and materials making up the shipped

    component/material.

    The number of elements (or documents)

    completed for the PPAP package at the

    time of the review.

    The total number of required elements, or

    documents, required to be submitted.

    PPAP Package

    Completion

    Number of PPAP submission package

    elements completed compared to

    required number.

    Launch Readiness Audit

    This metric assesses the level of

    implementation of the full production

    intent process. Processes that are not

    fully implemented at the Start-of-

    Production require a deviation, or

    concession, to allow shipment. This

    document needs to clearly define the

    state of the process implementation,

    provide a time line for completing the

    implementation, list any non-conformities

    to the drawing and/or specifications, and

    a containment plan to keep those non-

    conformances from reaching MEI.

    Process Implementation -

    % Completed

    Sub-Component PPAP

    Approvals

    Number PPAPs approved for the

    purchased sub-components and

    materials that makes up the final shipped

    component/material, and that do not have

    any deviations, waivers, and/or

    concessions granted by any tier below

    MEI.

    A comprehensive audit tool's score,

    which assesses a process's state of

    preparation to meet serial production

    requirements.

  • 7/23/2019 APQP Workbook

    8/20

    Results

    DefinitionMetric

    APQP: Key Supplier Metrics Operational Definitions

    This section defines the Key Supplier Metrics that will be tracked throughout the four APQP Phases. Reviews will be held toward the end of each of the four

    phases. Review of these metrics, in the Phase 4, will take place before the final full PPAP approval

    Goal

    Enter the number corresponding to the

    completed stage from the list below.

    1. Has not received any production

    releases from using plant(s).

    2. Is receiving production releases from

    the using plant(s), but no production

    schedule or plan documented to meet

    those volumes orhas ramp plan, is

    receiving plant releases, but is not

    shipping to plan and/or releases .

    3. Has not received production releases

    from plant(s), but has created a

    preliminary planned based on quoted

    volumes and program timing.

    4. Is receiving production releases andhas created a plan, but production

    schedule does not reflect the plan.

    5. Is receiving production releases, has

    created a ramp plan and this plan is

    reflected in the production schedule.

    Enter the goal, Level 5-Is receiving

    production releases, has created a ramp

    plan and this plan is reflected in the

    production schedule.

    Enter number of completed stage at time

    of review.

    Enter the number '5' representing the

    completion of the PCM, less the exit from

    the Safe Launch Plan. This applies to

    situations where the PPAP will be

    submitted in a span of time from before

    SOP to 30 days after SOP.

    Enter the number '6' for situations where

    the SLP exit is required for closing APQP.

    Completion of the PCM is noted by

    Operations, i.e., plant, approval of the

    Safe Launch Plan portion of the form.

    Stages of completion are:

    1. MEI's supplier has completed the

    form, less SLP.

    2. MEI's supplier has completed their

    sub-supplier form, less SLP.

    3. Supplier section completed, including

    SLP.

    4. Sub-supplier section completed,

    including SLP.

    5. Characteristic Review signed off on

    both tabs.

    6. Complete sign-off on both tabs for

    "Safe Launch Exit Approval.

    Supplier Ramp Plan

    Safe Launch Plan (PCM)

    Deployment

    This element evaluates a supplier's ability

    to meet ramp-up timing and volumes.

  • 7/23/2019 APQP Workbook

    9/20

    Supplier Name: Supplier Location: Supplier Code:

    Part Number: Part Name: Revision Level:

    Component Priority Level: Lead Customer/Program: Report Date:

    SUPPLIER SIGN-OFF (MANAGER LEVEL)

    MEI SIGN-0FF

    Results

    #DIV

    Goal

    TargetProduction Preparation Influencing Factors

    Number of PPAP required documents required

    Complete Stage 5 by SOP 5

    Primary Indicator:

    Enter completed stage of PCM (see comments)

    Total number of instructions completed

    Ramp planned completed and shipping to releases

    Available capacity based on % of cycle time to Takt time

    achieved

    Maximum acceptable % of available capacity base on %cycle

    time to Takt time

    Total number of purchased sub-components/materials

    State of completed supplier ramp plan

    Number of PPAP required documents completed

    Total number of elements from 'Progress Report'

    Number of sub-components and materials PPAP approved

    Number of capable designated characteristics features

    Score achieved during event

    Goal is 100%.

    1. APQP Readiness

    2. Process Instructions

    6. Test AchievementNumber of tests passed

    7. Process Implementation -

    % Completed

    % of total tests

    Number of 'Progress Report' elements with Green status

    5

    MANUFACTURABILITY

    Total number of designated characteristics features

    Results from Run at Rate

    Ideal % of good parts3. First Time Capability

    Total number of instructions needed.

    Production volumes provided off production intent process

    High volume process or Interim Process wi th Concession

    5

    Production ControlPurch/Sales Quality DesignEngineering

    #DIV/0!Metrics Overall Score #DIV/0! #DIV/0!

    Signature

    Name (print)

    9. Sub-Component PPAP

    Approvals

    10. PPAP Package

    Completion

    11. Supplier Ramp Plan

    Man

    8. Launch Readiness Audit

    5. Process Capability

    12. Safe Launch Plan (PCM)

    Deployment

    MEI Internal Use only Commodity Mgr/Buyer

    SDE

    SQA

    Function Project Leader

    DLN

    K

    E

    Y

    M

    E

    A

    S

    U

    R

    E

    A

    B

    L

    E

    S PPAP

    Supplier APQP: Key Supplier Metrics Report

    Signature

    Signature

    Name (print)

    Name (print)

    Name (print)

    Signature

    4. Process Efficiency

  • 7/23/2019 APQP Workbook

    10/20

    Precision Forming

    Amarrillo, TX

    Airbag Reaction Can

    49019804A

    Stamping body, end

    caps, brackets

    TIER 4

    SUPPLIER

    TIER 2

    SUPPLIER

    TIER 3

    SUPPLIER

    Anaconda Steel

    Erie, PA

    C1038 Rod

    Steel Mill

    Zephyr Coatings

    Austin, TX

    E-Coat

    Dynamic Chemical

    Supplies

    Tulsa, OK

    Coating materials,

    solvents

    White & Jones

    Jackson, MI

    C1038 Rod

    Wire Draw, Anneal

    Fine Fasteners, Inc.

    Benton Harbor, MI

    M8x20 Weld Stud

    59039813A

    Cold Forming

    B&C Processing

    Georgetown, PA

    C1024 RodWire Draw, Anneal

    ABC Nut Co.

    Summit, NJ

    M8x15 Staking Nut

    59039812C

    Cold Forming

    AAA Heat Treat

    Frederick, MD

    Harden & Draw

    Kojak Heat Treat

    Benton Harbor, MI

    Harden & Draw

    Supplier APQP: Supply Chain Map - Example

    TIER 1 SUPPLIER

    Pacific Steel

    Los Angeles, CA

    C1024 RodSteel Mill

  • 7/23/2019 APQP Workbook

    11/20

    Supplier: Part Number: Date: Revision:

    TierTier IIME Receiving

    Operation

    OEM

    Customer

    upplier APQP: Supply Chain Map

    Tier V Tier IV Tier III

  • 7/23/2019 APQP Workbook

    12/20

    Part Name: Supplier

    Part Number/ Revision: Lo

    Project/ Program: MEI Using P

    Design CharacteristicLevel/

    Class

    DFMEA

    Sev.

    PFMEA

    Occ.

    PFMEA

    Det.RPN Control Method/ Equipment

    Date

    MEI SDE

    MEI Plant SQA

    Supplier Representative

    Date

    MEI SDE

    MEI Plant SQA

    Ch

    #

    MEI/ Supplier

    Name

    Name

    Position/ Title

    Supplier Representative

    Position/ Title

    TIER II - S

    Supplier APQP: Product Characteristic Matrix

  • 7/23/2019 APQP Workbook

    13/20

    Part Name: Supplier Name:

    Part Number/ Revision: Location:

    Project/ Program: MEI Using Plant(s):

    Design CharacteristicLevel/

    Class

    DFMEA

    Severity

    PFMEA

    Occurrence

    PFMEA

    DetectionRPN Control Method/ Equipment

    Gauge

    R&R

    % Tol

    Pp/ Ppk Freq./Size Con

    Date

    MEI SDE

    MEI Plant SQA

    Supplier Representative

    Date

    MEI SDEMEI Plant SQA

    Sub-Supplier Process Control

    Signature

    Signature

    Position/ Title

    Supplier Representative

    Position/ Title

    Safe Launch Exit A pprovals

    Character ist ic Review Ap proval

    #

    TRW/ Supplier

    Name

    Name

    Supplier APQP: Product Characteristic Matrix (Sub-Supplier)

  • 7/23/2019 APQP Workbook

    14/20

    Total WEEK W14

    71 Incidents 65

    9350 QTY 2350

    7594 PPM 27660

    FaultNo.

    Failure Mode Total Action Timing W14

    13 Abutment hole diameter 11 11

    2 Lining wear inspection hole diameter 10 10

    14 Nut thread check 7 7

    8 Wheel cylinder hole position 6 6

    3 Adjuster hole diameter 5 5

    6 Bearing case ID 5 5

    7 Wheel cylinder hole diameter 5 5

    5 Mounting holes diameter 4 4

    9 Brake cable hole position 3 3

    11 Threaded nut hole position 3 321 NO paint scratch and or contamination, Blistering, runs 2 2

    12 Abutment hole position 2 2

    20 No Cracks on backplate (visual boundary sample) 2 2

    16 Abutment and locating plate gap 0 0

    10 Brake cable hole diameter 0 0

    19 Locating abutment plate smooth surface 0 0

    17 Dust ring gap to backplate check 0 0

    18 Cable guide gap 0 0

    4 Mounting holes position 0 0

    15 Nut weld torque 0 0

    1 Hold down pin diameter 0 0

    Safe Launch Plan: Weekly QOS Report

    0

    5000

    10000

    15000

    20000

    25000

    30000

    0

    10

    20

    30

    40

    50

    60

    70

    W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29

    Incident

    Touch Point Incident & PPM Monitoring

    Incidents PPM

    Example

  • 7/23/2019 APQP Workbook

    15/20

    Supplier Name: Component Manufacturing Location: Supplier Code:

    MEI Part Number(s): Issued by:

    Customer Name: Customer Platform: MEI Product: Status:

    Action plan review

    Distribution:

    Status

    Da

    Launch ActivityLaunch Activity Date Date Launch Activity Date

    Source of IssueConcern / Problem / Open Issue

    Description

    Dates

    Date scheduled Date actual

    DueOpened

    Supplier APQP: Open Issues - Corrective Action Plan

    Item

    NumberAction

    Closed

  • 7/23/2019 APQP Workbook

    16/20

    Supplier Name: Supplier Location: Supplier Code:

    Part Number: Part Name: Revision Level:

    Component Priority Level: Lead Customer/Program: Report Date:

    PROGRAM MILESTONES

    PHASE/ELEMENT STATUS OVERVIEW

    20

    40

    60

    80

    100

    3.3 Supplier Ramp Plan

    Key Supplier Metrics reviewed

    3.6Appearance Approval Process

    (when applicable)

    3.4

    Packaging

    3.5 Launch Readiness Audit

    APQP

    PhaseStatus

    Element Issues / Recovery Plan

    DatePercent

    Complete

    Needed Committed Complete

    Manufacturing Feasibility reviewed

    C

    PPAP submission

    Start of Production

    ME PV Build

    1

    3

    Date Date

    CommittedEvent Event

    Design Freeze

    Needed Committed Completed Needed

    4

    Design FMEA

    Preliminary Capacity Study

    reviewed

    2

    First Off-Tool

    Capital equipment

    Measurement/ Testing equipment

    Key Supplier Metrics initiated

    Supplier Project timing plan

    Open Issues Action Plan created

    First Off-Process

    PPAP

    Launch Readiness Audit

    Key Supplier Metrics reviewed

    ELV/IMDS

    Safe Launch Plan finalized

    Plant Readiness Review

    2.3

    Run at Rate

    OK to Launch Sign-Off

    1.1

    1.2

    1.3

    1.5

    1.6

    1.7

    Key Supplier Metrics reviewed

    3.1

    3.2

    2.12

    2.11

    2.1

    2.2

    2.4

    2.9

    2.5

    2.7

    Component Design Review

    4.5

    3.7

    4.1

    4.2

    4.3

    4.4

    2.1

    2.13

    Training

    Process instructions

    Supplier APQP: Progress Report - Status Overview

    1.4

    Sub-Supplier PPAPs

    Launch Readiness Audit

    Tooling

    Initiate PCM (Safe Launch Plan)

    2.6 Process Flow Diagram

    2.8 Control Plan

    PFMEA

  • 7/23/2019 APQP Workbook

    17/20

    Magna Part Number: Description: Revision Level:

    Customer: Program: Product Line:

    Company Name: Product Line:

    Company Location: Using Location:

    Supplier Code: Reviewer:

    Contact Name: Phone: Review Date:

    Contact email: Disposition:

    No. 1 2 3 4 5

    1 S S S S R

    A.

    B.

    C.

    D.

    1.

    2.

    3.

    E.

    F.1.

    G.

    H.

    1.

    2.

    I.

    J.

    2 R S S * R

    A.

    B.

    3 R S S * R

    A.

    B.C.

    D.

    E.

    4 R R S * R

    A.

    5 R R S * R

    A.

    B.

    C.

    D.

    6 R R S * R

    A.B.

    C.

    7 R R S * R

    A.

    B.

    C.

    D.

    E.

    8 R S S * R

    PPAP Submission Checklist

    SUPPLIER INFORMATION MAGNA ELECTRONICS INFORMAT

    Document

    Part Submission Warrant

    PART NUMBER INCLUDED AND CORRECT. REVISION LEVEL INCLUDED AND CORRECT

    WEIGHT INCLUDED

    SUPPLIER MANUFACTURING INFORMATION COMPLETE, INCLUDING SUPPLIER CODE

    PPAP

    Submission

    Level

    A

    Required

    ELV/IMDS INFORMATION INCLUDED: The Magna Holly IMDS # is 9822

    CORRECT REASON FOR SUBMISSION BOX CHECKEDIF OTHER IS CHECKED, THAT THE CORRECT REASON FOR SUBMISSION IS NOTED

    CORRECT SUBMISSION LEVEL BOX IS CHECKED

    SUBMISSION INFORMATION COMPLETE.

    ALL APPROPRIATE BOXES CHECKED

    BUYER NAME INCLUDED

    APPLICATION INFORMATION INCLUDES MAGNA CUSTOMER AND PROGRAM

    SIGNATURE AREA IS COMPLETED AND CONTAINS ALL INFORMATION

    Design Records (Drawings, Specifications)

    A MARKED OR BALLOONED DRAWING IS ATTACHED. Note: All non reference print items and specs must be addressed.

    COPIES OF ALL REFERENCED SPECIFICATIONS ARE INCLUDED IN THE SUBMISSION (LEVEL 3 ONLY)

    THE SUBMISSION RESULTS AREA IS PROPERLY FILLED OUT AND THE PACKAGE REFLECTS THIS

    PACKAGE CONTENTS MUST REFLECT SUPPLIER'S STATEMENT OF COMPLIANCE

    FOR MULTIPLE TOOLS/CAVITIES/PROCESSES THAT THE INFORMATION IS NOTED IF APPLICABLE

    THE DECLARATION AREA CONTAINS THE RUN AT RATE INFORMATION

    ACTION PLAN INCLUDED IF REQUEST IS FOR DEVIATION/CONCESSION

    SIGNED AND DATED BY MAGNA ENGINEERING

    Customer Engineering Approval Documents

    IF PROCESS INCORPORATES UNRELEASED CHANGE, COPY OF ENGINEERING DOCUMENT INCLUDED

    Change Documents

    PART NUMBER LEVEL INCLUDED AND CORRECT. REVISION LEVEL INCLUDED AND CORRECT

    PART APPLICATION / PROGRAM / PLANTS IDENTIFIEDSPECIFIES TIME SPAN OR VOLUME AFFECTED

    AREAS OF CONCERN IDENTIFIED IN THE DFMEA ARE CARRIED OVER INTO THE PFMEA.

    Process Flow Diagram

    PART NUMBER LEVEL INCLUDED, CURRENT AND CORRECT. REVISION LEVEL INCLUDED AND CORRECTMUST START WITH RECEIVING AND FINISH WITH SHIPMENT OF MATERIAL

    Design FMEA

    PART NUMBER LEVEL INCLUDED, CURRENT AND CORRECT. REVISION LEVEL INCLUDED AND CORRECT

    DOES IT FOLLOW THE ENTIRE PROCESS AS SHOWN IN FLOW CHART?

    DO HIGH RPN FAILURE MODES HAVE ACTIONS SHOWN FOR IMPROVEMENT?

    WHERE APPROPRIATE, DO HIGH RPN FAILURE MODES HAVE ACTIONS SHOWN FOR IMPROVEMENT?

    ARE CONCERNS INCLUDED THAT WERE DISCOVERED IN EARLY STAGES?

    CRITICAL FEATURES IDENTIFIED ON THE PCM/SLP, BUT NOT ON THE DRAWING (CUSTOMER TOUCH POINTS,

    CRITICAL PROCESS CONTROLS, ETC.) ARE INCLUDED IN THE PFMEA AND HAVE RPN CALCULATED.

    PROCESS FLOW DIAGRAM IS ACCURATE

    Process FMEA

    PART NUMBER LEVEL INCLUDED, CURRENT AND CORRECT. REVISION LEVEL INCLUDED AND CORRECT

    DOES IT FOLLOW THE ENTIRE PROCESS AS SHOWN IN FLOW CHART?

    Dimensional Results

    PPAP Level 3 Unless MEI SDE directs "other"

  • 7/23/2019 APQP Workbook

    18/20

    A.

    B.

    C.

    D.

    E.

    F.

    G.

    11 R R S * R

    A.

    B.

    C.

    D.

    E.

    F.

    12 R S S * R

    A.

    B.

    13 R R S * R

    A.

    B.

    C.

    D.

    E.

    F.

    G.

    14 S S S * R

    15 R R R * R

    16 R S S * R

    17 R R R * R18 R R S * R

    19 R R S * R

    A.

    20 * * S * *

    A.

    B.

    C.

    D.

    E.21 * * S * *

    22 R R S * R

    23 * * S * *

    A.

    B.

    24 S S S S R

    A.

    B.

    25 S S S S R

    A.

    26 * * S S R

    A.

    CAPABILITY STUDY RESULTS ARE SUBMITTED ON THE PRODUCT CHARACTERISTICS MATRIX

    PPK's FOR ALL CHARACTERISTICS ARE GREATER THAN, OR EQUAL TO, 1.67.

    IF NO, A WRITTEN CORRECTIVE ACTION STATEMENT, FOR EACH, IS INCLUDED AND CONTAINMENT, WHEN

    FEASIBLE, IS 100% INSPECTION.

    RAW DATA IS INCLUDED FOR EACH STUDY

    (per MAGNA XXX)

    STUDIES ARE CONDUCTED FOR ALL CRITICAL AND SIGNIFICANT CHARACTERISTICS (EXCEPT DIMENSIONS

    WITH BONUS TOLERANCES). EACH STUDY MUST INCLUDE THE STUDY DATE.

    TEN (10) MEASUREMENTS FOR BONUS TOLERANCE DIMENSIONS ARE INCLUDED or PER MAGNA SDE DIRECTION

    WRITTEN CORRECTIVE ACTIONS ARE INCLUDED FOR GAGE R&R'S GREATER THAN 30%.

    THREE (3) OPERATORS, THREE (3) TRIALS ARE UTILIZED.

    FORMS ARE COMPLETELY FILLED OUT.

    WAS THE PROCESS CAPABILITY CALCULATED MADE OFF PARTS MADE FOR PPAP SUBMISSION?

    PROCESS AVERAGES MATCH FOR MULTIPLE CAVITIES, DIES AND TOOL PROCESSES.

    Measurement Systems Analysis (Gage R&R)

    STUDIES ARE INCLUDED (AND DATED) FOR GAGES USED TO MEASURE SIGNIFICANT AND CRITICAL DIMENSIONS.

    GAGE R& R FORM IS USED FROM MEASUREMENT ANALYSIS HANDBOOK.

    PART NUMBER LEVEL INCLUDED AND CORRECT. REVISION LEVEL INCLUDED AND CORRECT

    DOES CONTROL PLAN REFLECTS LAUNCH PRACTICE ITEMS?

    DOES IT SHOW SAME REVISION LEVEL AS PFMEA?

    CONTROL PLAN ADDRESSES ALL SIGNIFICANT AND CRITICAL DIMENSIONS.

    Qualified Laboratory Documentation

    CERTIFICATE OF ACCREDITATION IS FROM A NATIONALLY RECOGNIZED ORGANIZATION.

    SCOPE OF ACCREDITATION IS INCLUDED.

    Control Plan

    Appearance Approval Report (As Appropriate)

    Bulk Materials Requirement Checklist (As Appropriate)

    Sample Product

    Master Sample

    CONTROL PLAN ADDRESSES THE ENTIRE PROCESS FROM RECEIPT OF MATERIAL TO SHIPPING PRODUCT.

    CONTROL PLAN INCLUDES ANNUAL REVALIDATION REQUIREMENTS.

    CRITICAL FEATURES IDENTIFIED ON THE PCM, BUT NOT ON THE DRAWING (CUSTOMER TOUCH POINTS, CRITICAL

    PROCESS CONTROLS, ETC.) ARE INCLUDED IN THE PFMEA AND HAVE RPN CALCULATED.

    Product Characteristic Matrix (per MAGNA XXX)

    ALL SUB-TIER SUPPLIERS HAVE BEEN INCLUDED BASED ON SUPPLY CHAIN MAP.

    ALL SIGNIFICANT AND CRITICAL DIMENSIONS ARE INCLUDED, AND FOLLOW BACK TO THE MANUFACTURING

    PROCESS THAT PRODUCES THEM.

    Checking Aids

    Compliance with Customer Specific Requirements

    DOCUMENT(S) DEMONSTRATING COMPLIANCE WITH ANY OEM SPECIFIC COMMUNICATED REQUIREMENTS.

    Additional MAGNA SPECIFICPPAP Requirements

    Packaging Plan and Sample Label (per MAGNA XXX)

    RUN-AT-RATE or Capacity Verification per MAGNA SDE DIRECTION (per MAGNA XXX)

    DOES THE SUPPLIER NEED TO INCREASE THEIR CAPACITY?

    ARE BOTTLENECKS IDENTIFIED AND RESOLVED? ARE THERE ANY TOOLING CONSTRAINTS?

    PFMEA RPN'S ARE INCLUDED FOR ALL INCLUDED DIMENSIONS.

    CUSTOMER TOUCH POINTS AND CRITICAL PROCESS CONTROLLED DIMENSIONS ARE INCLUDED.

    SAFE LAUNCH PLAN DOCUMENTS CONTROLS THROUGHOUT THE SUPPLY CHAIN UP TO MAGNA.

    Evidence of ELV / IMDS Approval

    APPLIES ONLY TO SUPPLIERS TO FOR WHICH THE COMMERCIAL SITUATION DOES NOT ALLOW

    FOR FULL DISCLOSURE.

    Critical process approval (Heat treat, plating)

    ARE THERE ANY CRITICAL SECONDARY PROCESSED THAT REQUIRES USE OF A RECOMMENDED SUPPLIER OR AMAGNA AUDIT BEFORE THEY ARE USED?

    Certification of Review** (per MAGNA XXX)

    Sub - contractor PPAP status

    IS THERE A PSW FOR EACH COMPONENT AND MATERIAL IDENTIFIED IN THE BOM AND OR PCM?

    ARE THE PSW'S FULLY APPROVED? IF NOT, IS THERE A MAGNA DEVIATION/CONCESSION FOR EACH PSW NOT

    FULLY APPROVED?

  • 7/23/2019 APQP Workbook

    19/20

    Instructions: For the submission of each Part Number, please utilize the MEI PPAP Checklist and insert the appropriate

    PPAP document into its respective folder within the Zip File Master. If a document is not relevant/required, submit

    an insert that notes that that element is not applicable. Examples are often AARs and DFMEAs.

    PPAP Submission Folder

  • 7/23/2019 APQP Workbook

    20/20

    Function Functio

    NameDept.

    Tel.

    Fax.

    E-mail

    Address/

    Location

    Name

    Dept.

    Tel.

    Fax.

    E-mail

    Address/

    Location

    Name

    Dept.

    Tel.

    Fax.

    E-mail

    Address/

    Location

    Name

    Dept.

    Tel.

    Fax.

    E-mail

    Address/

    Location

    Name

    Dept.Tel.

    Fax.

    E-mail

    Address/

    Location

    Name

    Dept.

    Tel.

    Fax.

    E-mail

    Address/

    Location

    Name

    Dept.Tel.

    Fax.

    E-mail

    Address/

    Location

    Chris Hempsall

    Purchasing

    810-603-4137

    [email protected]

    Project Management

    MEI Receiving Plant

    Quality

    MEI Receiving Plant

    Logistic & Packaging

    MEI Engineering

    MEI Purchasing

    Program Buyer

    Contact Information

    MEI Purchasing

    Commodity Buyer

    MEI APQP: Contacts- APQP TEAM

    MEI Supplier

    Development

    Engineering

    mailto:[email protected]:[email protected]