APPENDIX R Copies of Presentation from Stakeholder...

74
Malingunde ESIA APPENDIX R Copies of Presentation from Stakeholder Meetings

Transcript of APPENDIX R Copies of Presentation from Stakeholder...

Page 1: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Malingunde ESIA

APPENDIX R Copies of Presentation from Stakeholder Meetings

Page 2: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

1

Malingunde Graphite ProjectMalingunde Graphite Project

Environmental and Social Impact Assessment (ESIA)

Stakeholder Information Meetings to Announce the Commencement of the ESIA Process4 – 8 December 2017

Lilongwe, Malawi

Overview

�Project team and roles�Purpose of meetings�Project background, location and description�ESIA status and process

Page 3: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

2

ĂSovereign Metals (Developer)�Andries Kruger�Reidwel Nyirenda

ĂDhamana Consulting (Principal Environmental Consultant)�Nanette Hattingh

ĂAecom(Social studies and stakeholder engagement) �Karien Lotter �Anelle Lotter

ĂC12(Social studies and stakeholder engagement)�Akeel Hajat�Arthur Kambombe�David Mussa

Project team

� Dhamana Consulting, AECOM and C12 are consulting firms with international experience in undertaking environmental and social studies and have been commissioned by Sovereign Metals to undertake the ESIA process for the project.

� Dhamana Consulting, AECOM and C12 have no private interest in the proposed Malingunde Project and operate independently to reflect both the interests and concerns of stakeholders and the mine.

The role of Dhamana Consulting, AECOM and C12

Page 4: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

3

1. Share information about the proposed Malingunde Project and the ESIA process

2. Discuss the best approach for engaging stakeholders during the ESIA

Discussion points

� Background to the proposed Malingunde Project

� Proposed activities

� Overview of ESIA process and timeframes

� Proposed stakeholder engagement and communication

Purpose of the meeting and discussion points

Background to the Malingunde Project

� Sovereign Metals Limited is an Australian publicly listed company primarily focussed on exploring for and developing natural flake graphite deposits in central Malawi.

� The Exclusive Prospecting Licence (EPL) covers an area of approximately 1 245km2 on the Lilongwe Plain in which the Malingunde project is located.

� McCourt is the applicant for the environmental authorisation for the Malingunde project.

Who is McCourt Mining and Sovereign Metals?

Page 5: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

4

Background to the Malingunde Project

� Studies undertaken to date indicate that the natural flake graphite deposit at Malingunde can yield ~ 44 000 tonnes of graphite concentrate per annum over an initial life-of-mine (LOM) of 17 years.

What is proposed?

The proposed Malingunde Project is located 15 km southwest of Lilongwe

Boma, and falls within the Lilongwe District of the Central Administrative Region

Graphite is used for the production of: � magnesia-carbon

bricks used in the steel industry

� rechargeable lithium-ion batteries for cell phones, laptops and electric vehicles

Background to the Malingunde Project

Location of the proposed Malingunde Project

- Project area will be ~ 300 �400 hectares in size

- 25 km from operating rail

- 20 km from a power station

- Near a potential water source

- Access to the proposed mine from Lilongwe is via the sealed section of the secondary road, S124, to Likuni and then the unsealed continuation of the S124 to the Kamuzu Dam turn-off

Page 6: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

5

Background to the Malingunde Project

� Open pit mining with traditional excavator and haul trucks will be used to mine the ore

� No drilling and blasting will be required

� Pits will be a maximum of 25 m deep and 150 m wide

� Excavated ore will be transported to the processing plant for treatment (scrubbing and flotation)

� The processed product will be transported on truck for 26 km to Kanengo train station (north of Lilongwe Boma) from where it will be railed to Nacala port in Mozambique for export.

Proposed activities

Background to the Malingunde Project

� A number of ore pits � Waste rock dump� Tailing storage facility� Low grade stockpile� Ore processing plant� Access roads to site� Raw water storage dam, process water storage dam, dirty

water storage dam and site water management infrastructure

� Workshops to service mining vehicles� Diesel fuel storage and filling stations for mine vehicles� Administration buildings, offices, ablution facilities and crib

rooms

Proposed infrastructure

Infrastructure location proposed for the northern extend of the project area, but the location will be informed by the studies undertaken

Page 7: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

6

Environmental and Social Impact Assessment (ESIA)

� Project Brief was completed and the Environmental Affairs Department (EAD) indicated in June 2017 that an ESIA is required in terms of Section 24 (1) of the Environmental Management Act (EMA).

� The Environmental Impact Assessment Guidelines (1997) published by the EAD identify projects for which an ESIA are mandatory in �List A� of the guidelines, which includes mining of minerals.

� McCourt will therefore be applying for environmental authorisation in respect of potential mining activities at Malingunde. The ESIA is undertaken in compliance with the Malawian legislation, the International Finance Corporation (IFC) Performance Standards and Equator Principles.

Status

Sovereign aims to complete all studies towards the end of 2018 to enable them to decide on whether the mine will be developed or not

Environmental and Social Impact Assessment (ESIA)

To identify and assess likely environmental and social impacts, and propose appropriate mitigation and management measures, as well as monitoring protocols.

What is an ESIA all about?

�Project Brief completed and EAD indicated an ESIA will be required

Project Brief (June 2017)

ͻ Project announcement �Draft Scoping Report - March 2018�Meetings�Final Scoping Report to EAD

Scoping Phase (December 2017 to March 2018)

�Specialist assessments undertaken�Draft ESIA Report - September 2018 �Meetings�Final ESIA Report to EAD

ESIA Phase (April to September 2018)

Page 8: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

7

Environmental and Social Impact Assessment (ESIA)

1. Scoping Phase

Draft Scoping ReportMarch 2018

� To identify likely environmental and social issues that require detailed investigation by specialists

� To develop the terms of reference for undertaking investigations in the ESIA Phase

Final Scoping Report to EAD for review

Meetings to review the report

Environmental and Social Impact Assessment (ESIA)

2. ESIA Phase

Draft ESIA ReportSeptember 2018

Specialist studies conducted based on the terms of references in the Scoping Report

Final ESIA Report to EAD for review

Meetings to review the report

Specialist studies to assess:- Fauna (animals and

fish) and flora (plants)- Wetlands- Surface water- Groundwater- Air quality- Noise- Vibration- Visual impact- Archaeology- Cultural heritage - Social impacts

Page 9: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

8

Environmental and Social Impact Assessment (ESIA)

Potential impacts of the Malingunde Project

The Malingunde Project is likely to have a range of impacts on the environment and the people living in the area.

Potential positive impacts

Job creationLocal

economic growth

Improved infrastructure

Social development

Environmental and Social Impact Assessment (ESIA)

Potential impacts of the Malingunde Project

The Malingunde Project is likely to have a range of impacts on the environment and the people living in the area.

Potential negative impacts

Loss of farm land Resettlement Water-related

impactsDust, noise, more traffic

Page 10: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

16/01/2018

9

Environmental and Social Impact Assessment (ESIA)

� Register as a stakeholder

� Communicate your questions and concerns in writing to AECOM, C12 and Sovereign

� Comment on information received (Draft Scoping Report and Draft ESIA Report)

� Attend public meetings held during the project (March and September 2018)

How can you participate and get involved?

Environmental and Social Impact Assessment (ESIA)

Who can you contact?

AECOMAnelle Lötter

Email: [email protected] Box 30523, CC3, Lilongwe, Malawi

C12Dorothy Mbendela, Email: [email protected], Tel: +265 998 521

663/+265 881 409 466

Website: http://sovereignmetals.com.au/building-malingunde/

Your comments are important!

Please share with us your concerns, questions and issues

Page 11: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping
Page 12: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

1

Kudziwa za Ntchito ya M¶godi waMiyala ya Mtengo wa patali ya

Graphite ku Malingunde

Kudziwa za Ntchito ya M¶godi waMiyala ya Mtengo wa patali ya

Graphite ku Malingunde

Kafukufuku wa momwe za Chilengedwe komanso Chikhalidwe cha anthuChingakhudzidwire ndi Nchitoyi

Misonkhano ya onse okhudzidwa komanso otengapo mbali pa ntchito yaM¶godi ku Malingunde, kuwadziwitsa za kuyamba kwa Kafukufuku wa

mmene ntchitoyi ingakhudzire za chilengedwe komanso chikhalidwe cha anthu

4 ± 8 December 2017Lilongwe, Malawi

Zofunika Kudziwa

�Maina a ogwira ntchito ndi ma udindo awo

�Cholinga cha misonkhano

�Mbiri ya Ntchito ya m�godi omwe ungadzakhazikitsidwe, Malo a m�godindi tsatanetsane wa Ntchito yonse

� Za pomwe ntchito ya kafukufuku ali komanso momwe ntchitoyiimagwilidwira

1

2

Page 13: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

2

ĂSovereign Metals (Eni Ntchito)�Andries Kruger�Reidwel Nyirenda

ĂDhamana Consulting (Wankulu Oyang¶anira za chilengedwe )�Nanette Hattingh

ĂAecom(Oyang¶anira za misonkhano yokumana ndiomwe ali okhudzidwa) �Karien Lotter �Anelle Lotter

ĂC12(Oyang¶anira za kafukufuku ndi misonkhanoyokumana ndi omwe omwe ali okhudzidwa)�Akeel Hajat�Arthur Kambombe�David Mussa

Project team

� Ma bungwe a Dhamana, AECOM and C12 ali ndi ukadaulo opanga kafukufukuwa za chilengedwe ndi chikhalidwe cha anthu mmaiko osiyanasiya pa dziko la pansi. Mabungwewa apatsidwa mphamvu ndi kampani ya Sovereign Metals kuti apange kafukufuku ounika mmene ncthito ya mg�odi ku Malingundeingakhudzile chikhalidwe ndi miyoyo ya anthu kapena za chilengedwe kudelaro..

� Ma bungwe a Dhamana Consulting, AECOM ndi C12 alibe cholowachilichonse pa ntchito ya mg�odi yomwe ingadzakhazikitsidwe ku Malingunde. Iwo adzaonetsetsa kuti kafukufukuyu wapangidwa mosakondera mbali iliyonse yokhudzidwa ndi nkhani ya mg�odiyi.

Ntchito za Dhamana Consulting, AECOM and C12

3

4

Page 14: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

3

1. Kudziwitsaanthu za ntchito ya mg�odi yomwe ingadzachitike ku Malingundekomanso za kafukufuku amene achitike.

2. Kukambirana za njira za bwino zopangira zokambirana ndi mbali zonsezokhudzidwa ndi kafukufukuyu komanso ntchito yomwe ingadzachitikeyi.

Mfundo Zokambirana

� Chiyambi cha ntchito ya mg�odi yomwe ingadzakhazikitsidwe ku Malingunde

� Zochitika zomwe zingadzakhalepo

� Tsatanetsane wa kafukufuku amene atachitike

� Za misonkhano yofotokozera anthu za nkhaniyi

Cholinga cha nsonkhano ndi mfundo zokambirana

Chiyambi cha ntchito ya mg¶odi yomwe ingadzakhazikitsidweku Malingunde

� Sovereign Metals Limited ndi kampani yokhazikika komanso yodziwika bwino pa ntchito zake ku Australia. Iwowa ali ndi chilolezo chofufuza komanso kukumbamiyala ya mtengo wa patali mu chigawo cha pakati kuno ku Malawi.

� Malo omwe kampaniyi idalandila chilolezo kuti angathe kukhala awo pa nthawiya ntchitoyi ndi okwana 1 245km2. Malowa ali mu chigwa cha boma la Lilongwe komwe Malingunde ikupezeka.

� A McCourt ndiwo adapempha chilolezo chopanga kafukufuku wa za chilengedwekomanso momwe anthu angakhudzidire ku malowa.

Kodi ma kampani a McCourt Mining ndi Sovereign Metals ndindani?

5

6

Page 15: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

4

Mbiri ya nkhani ya nchito ya mg¶di omwe ungadzakhale kuMalingunde

� Kafukufuku adasonyeza kuti pa malowa pakhoza kupezeka miyala ya graphite yokwana ma tani 44000 pa chaka kwa zaka zokwana khumi, sizanu ndimphambu ziwiri (17).

Zina zokhudza ku malowa

Mg�odi wa Malingunde ukuyembekezerekakudzakhala pa mtunda okwana ma

kilomita 15 kuzambwe kwa Mzinda waLilongwe.

Miyala ya Graphite imagwira ntchito izi: � Kusakanizira miyala

ina popanga zitsulo zasteel

� Kupangila ma batile a ma foni a mmajakomanso ma galimotooyendera magetsi.

Mbiri ya nkhani ya mg¶odi omwe ungadzakhale kuMalingunde

Malo omwe mg¶odi ungadzakhazikitsidwe ku Malingunde- Malo onse a ntchitoyi ndi

okula mahekita apakati pa ~ 300ndi 400.

- Ma kilomita 25 kuchokera pa malo a njanji yomweikugwira nchito

- Ma kilomita 20 kuchokera pa malo a mphamvu ya magetsi

- Ali pafupi ndi komwekungapezeke madzi

- Ku maloku kungafikidwepodzera mseu wa tala wa kuLikuni, kudzalowa mu nsewuwa fumbi opita ku taniofu yaKamuzu dam

7

8

Page 16: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

5

Mbiri ya nkhani ya mg¶odi omwe ungadzakhale kuMalingunde

� Mayenje adzakumbidwa ndi ma trakitala ndipomiyala idzanyamulidwa ndi ma galimotoakuluakulu onyamula dothi.

� Sipadzafunika kuboola miyala ndi kuphulitsama bomba.

� Kuya kwa mayenje sikudzadutsa mulingo wama mita 25 komanso sadzadutsa mulingo wama mita 150 mu litali kapena mu lifupi.

� Miyala yokumbidwa idzatengedwa kupita kumakina ochapila.

� Miyala yonse yochapidwa bwino idzatengedwakupita ku Kanego pa mtunda okwana ma kilomita 26, komwe idzakwezedwa sitima yapa njanje pa ulendo opita ku doko la Nacala.

Ntchito zomwe zidzagwiridwe

Mbiri ya nkhani ya mg¶odi omwe ungadzakhale kuMalingunde

� Mayenje a miyala angapo� Malo otaya miyala yosafunika� Malo otaya zinyatsi zochokera mu fakitare� Malo osungila miyala yofunikira koma osati kwenikweni� Fakitare yotsukira kapena kuyengela miyala� Misewu yofikira kapena kutulukira pa malopa� Damu la madzi ogwilitsira ntchito, malo osungila madzi

omwe agwilitsidwa ntchito , ndi zipangizo zoonetsetserakutimadzi onse a pa malopa akusamalidwa bwino

� Garaja yokonzera ma galimoto ndi makina ena ogwritsidwantchito pa mg�odi

� Malo osungila mafuta a dizilo kapena petulo� Mdadada wa ma ofesi osiyanasiya a anthu ogwira ntchito

pa malopa

Zomwe zidzamangidwa pa malopa

Pali maganizo oti zinthu izi zidzamangidweku mpoto kwa malowa. Komabekafukufuku ndiye adzanenebwino lomwe za ,malo a bwino kumangapo zinthuzi.

9

10

Page 17: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

6

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

� Zonse zounika momwe ntchito ya mgodi ingadzagwilidwire zinachitika ndipomwezi wa june chaka chino nthambi ya boma yoona za chilengedwe(Environmental Affairs Department (EAD) adati nkofunika kuchita kayekafukufuku wa momwe ntchitoyi ingadzakhudzire chikhalidwe cha anthu kapenaza chilengedwe. Izi ndi malinga ndi malamulo a dziko, gawo 24 ndime yoyambaya malamulo a za chilengedwe.( Section 24 (1) of the Environmental Management Act (EMA).

� Ndondomeko za kayendetsedwe ka a kafukufuku okhudza momwe ntchitozosiyanasiyana zimakhudzira za chilengedwe omwe adakhazikitsidwa mnchakacha 1997, amasonyeza ntchito zonse zomwe zingafunike kafukufukuzisadayambe. Ntchito ya migodi ndi imodzi mwa ntchito zomwe zimafunikakafukufuku otereyu.

� Motsatila malamulo a bomawa a McCourt adzapempha zilolezo zonse komansokuchita zonse zofunika ntchitoyi isadayambe.

Momwe zilili pakadali pano

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

Kafukufukuyu ndi ofuna kuona momwe ntchitoyi ingadzakhudzire za umoyo kapenachikhalidwe cha anthu komanso za chilengedwe m�delari.

Kodi kafukufukuyu ndi wa chiani?

�Izi zidachitika kale ndipo padapezeka kutikafukufuku adzafunika

Ndondomeko Ya MomweNtchito idzayendera

(June 2017)

ͻ Kulengeza za ntcito yomwe idzagwilidwa�Ripoti yoyamba ya kauniuni - March 2018�Misonkhano�Riopti yoyamba yomwe idzaperekedwa ku

boma

Gawo la Kauniuni(December 2017 mpaka March 2018)

�Kafukufuku ochitika ndi akatswiriosiyanasiyana�Repoti loyamba la kafukufuku -

September 2018 �Misonkhano�Ripoti lomaliza la kafukufuku

lidzaperekedwa ku Boma

Gawo La Kafukufuku(April to September 2018)

11

12

Page 18: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

7

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

1. Gawo la kauniuni

Repoti loyamba la kauniuni

March 2018

� Kuunika zonse za chilengedwe kapena zokhudza anthu zomwezingafunike kufufuzidwa mozama

� Kukhazikitsa ndondomeko yopangira kafukufukuyu

Ripoti lomaliza la Kauniuni loperekedwa

ku boma

Misonkhanoyokambirana za

repoti

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

2. Gawo la Kafukufuku

Ripoti loyamba la kafukufuku

September 2018

Akatswiri osiyanasiyana adzapanga kafukufuku molingana ndi ndondomeko zomwezidzakhazikitsidwa

Repoti lomaliza la kafukufuku lopita ku

boma

Misonkhanoyokambirana za

repoti

Akatswiri adzapangakafukufuku pa izi:- Zomera ndi nyama za pa

mtunda kapena mmadzi.- Ma dambo- Madzi a mu ziidikha- Madzi opezeka pansi pa

nthaka- Kugwira bwino ntchito kwa

mpweya- Phokoso- Kugwedezeka ka nthaka- Kagwilidwe bwino ntchito ka

maso- Za makedzana zopezeka

pofukula- Chikhalidwe chochokera kwa

makolo- Kusinthika kwa chikhalidwe

ndi zobwera

13

14

Page 19: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

8

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

Zokoma komanso zowawa zomwe zikhoza kudzabwera ndintchito ya m¶godiwu

Ntchito ya m�godi ku Malingunde yayenera kudzadzetsa kusintha kapenakuonongeka kwa chikhalidwe cha anthu komanso za chilengedwe

Zabwino zomwe ntchitoyi ingadzabweretse

Mwayi wantchito

Kukwera ka ntchito zachuma ku

delari

Chitukuko cha zomangamanga

Kukutuka kwaanthu

16 Presentation Title

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

Zokoma komanso zowawa zomwe zikhoza kudzabwera ndintchito ya m¶godiwu

Ntchito ya m�godi ku Malingunde yayenera kudzadzetsa kusintha kapenakuonongeka kwa chikhalidwe cha anthu komano za chilengedwe

Mavuto omwe angabwerendi ntchitoyi

Malo enaolima

akhozakudzakhala

mbaliimodzi yam�godiwu

Kusamutsidwakwa anthu ena

Mavutookhudzanandi madzi

Fumbi, phokoso ndikuchulukakwa ma galimoto

oyenda kumaloku

15

16

Page 20: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/8/2019

9

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

� Lembetsani ngati okhudzidwa kapenaotengapo mabli

� Tumizani nkhawa zanu ku AECOM, C12 ndiSovereign

� Tenganipo mbali powerenga ma ripoti onsea kafukufuku ndikuperekamaganizomolingana ndi zomwe mwawerengazo

� Dzatengeni mbali pa misonkhano yonseyomwe idzachitika yokhudzankhaniyi(miyezi ya March ndi September 2018)

Mungakhale bwanji gawo la ntchitoyi?

Mungafunse ndani?

AECOMAnelle Lötter

Email: [email protected] Box 30523, CC3, Lilongwe, Malawi

C12Imbani foni kwa a Dorothy Mbenderapa 0998 521663 kapena 0881

409 466Kapena atumizileni pa intaneti:[email protected]

Ma repoti onse a kafukufukuyu adzapezekanso pa intaneti iyi: http://sovereignmetals.com.au/building-malingunde/

Maganizo anu ndi ofunika kwambiri!

Chonde tumizani nkhawazanu, maganizo anu kapenachili chonse kwa

Kafukufuku oona za mmene mg¶odiwu ungakhundzire miyoyo kapenachikhalidwe cha anthu komanso za chilengedwe ku malowa

17

18

Page 21: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping
Page 22: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

1

Malingunde Graphite Project

Environmental and Social Impact Assessment

Stakeholder Meetings – Environmental Scoping Phase7 – 9 March 2018

Lilongwe, Malawi

�Sovereign Metals (Developer)• Julian Stephens• Andries Kruger• Reidwel Nyirenda

�Dhamana Consulting (Principal Environmental Consultant)• Nanette Hattingh

Aecom�(Stakeholder engagement)

Anelle Lotter•

C12�(Social studies and stakeholder engagement)

Chaitali• MukherjeeArthur • KambombeDavid • Mussa

Introductions: Project Team

Page 23: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

2

1. Share information about the proposed Malingunde Project and the environmental and social impact assessment (ESIA) process, focusing on the contents of the draft environmental scoping report (ESR).

2. Discuss the potential impacts and issues identified that require further assessment during the ESIA phase.

3. Review the terms of references (ToRs) for a variety of specialist studies to be undertaken.

4. Receive inputs to determine the extent of, and approach to, the ESIA phase.

5. Obtain comments and inputs from stakeholders.

Purpose of the Meeting and Discussion Points

• Sovereign is conducting technical studies, which will culminate in a feasibility study, to determine the viability of developing the natural flake graphite deposit at Malingunde. Studies undertaken to date indicate that deposit at Malingunde can potentially yield ~ 44 000 tonnes of graphite concentrate per annum over an initial life-of-mine (LOM) of 17 years.

• Sovereign has completed an economic scoping study and is currently undertaking a pre-feasibility study.

• Sovereign has also commenced an ESIA process as required in terms of the Environment Management Act (EMA), (Act No 19 of 2017).

• The ESIA is conducted in phases (an environmental scoping and ESIA phase) and is currently in the environmental scoping phase. The ESR is the main deliverable of this phase.

• If the Project is proven to be viable, Sovereign aims to bring the Project into construction in 2019.

Studies by Sovereign Metals Limited

Page 24: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

3

Sovereign Metals Limited is an Australian publicly listed company primarily •focussed on exploring for and developing natural flake graphite deposits in central Malawi.

McCourt Mining is a wholly owned subsidiary of Sovereign and the holder of the •Exclusive Prospecting Licence (EPL) in which the Project is located.

McCourt is the applicant for the environmental authorisation for the Project.•

Who is McCourt Mining and Sovereign Metals?

• Dhamana Consulting, AECOM and C12 (local Malawian consultancy)

are consulting firms with international experience in undertaking

environmental and social studies and have been commissioned by

Sovereign Metals to undertake the ESIA process for the project.

• Dhamana Consulting, AECOM and C12 have no private interest in the

proposed Malingunde Project and operate independently to reflect

both the interests and concerns of stakeholders and the mine.

The Role of Dhamana Consulting, AECOM and C12

Page 25: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

4

Development Activities Needed Before Mining Commences

Study / Item Completed? Timeframe

Economic Scoping Study Mid-2017

Pre-feasibility Study Mid-2018

ESIA (incl. Environmental Scoping Study) 4th Quarter 2018

Resettlement Action Plan 4th Quarter 2018

Definitive Feasibility Study 1st Quarter 2019

Mining License Mid-2019

Product Marketing Agreements Mid-2019

Decision to Mine Mid-2019

Project Execution Starts 3rd - 4th Quarter 2019

1. June 2017: Project Brief submitted and the Environmental Affairs Department (EAD) indicated that an ESIA will be required

2. December 2017: The ESIA study was announced• Stakeholder meetings were held (4 – 7 Dec 2017)• Background Information documents were distributed• Comments and inputs received from stakeholders were recorded in the

Comments and Responses Report (CRR)

3. March 2018: The draft ESR is available for review from 5 March – 13 April 2018• Non-technical summary of the ESR distributed• Stakeholder meetings (7 – 9 March 2018)• Comments and inputs will be considered and recorded in the CRR

4. May 2018: Submission of the Final ESR to EAD

Key Environmental Scoping Phase Milestones

Page 26: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

5

Location of the Malingunde Project

- Malingunde Project is located 15 km southwest of Lilongwe Boma, and falls within the Lilongwe District of the Central Administrative Region

- Project area will be ~ 300 – 400 hectares in size

- Access to the Project is from Lilongwe is via the sealed section of the secondary road, S124, to Likuni and then the unsealed continuation of the S124 to the Kamuzu Dam turn-off

- Located in close proximity to the villages of Kumalindi (Chitsulo) and Ndumila

- Directly north of Kamuzu Dam II

• Open pit mining with traditional excavator and haul trucks will be used to mine the ore.

• No drilling and blasting will be required.

• Pits will be a maximum of 25 m deep and 200 m wide.

• Excavated ore will be transported to the run-of-mine (ROM) pad and processing plant for treatment (scrubbing and flotation).

• Waste rock (material) will either be transported to the tailings storage facility or to the waste rock (material) dump.

• The produced concentrate will be transported on truck for 26 km to Kanengo train station (north of Lilongwe Boma) from where it will be railed to Nacala port in Mozambique for export.

Project Activities

Section 2 of the ESR for more information

Page 27: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

6

11 Presentation Title

- Open pits- Waste rock/material dump- Tailing storage facility- Ore processing plant- Site roads- Water storage dams- Site water management

infrastructure- Workshops- Diesel fuel storage- Administrative buildings,

offices, ablution facilities, crib rooms

Alternative locations proposed for the Project infrastructure components. Preferred layout will be informed by a number of technical and specialist studies

Conceptual Layout of the Malingunde Project

• Section 2(f) of the Environment Management Act (EMA), No. 19 of 2017 states that an ESIA is a legal requirement for any project that may significantly affect the environment and use of natural resources.

• The Environmental Impact Assessment Guidelines (1997) published by the EAD identify projects for which an ESIA are mandatory in ‘List A’ of the guidelines, which includes mining of minerals.

• In addition, the following will be considered:Ø Other relevant Malawian legislation, policies and standards. Ø In the absence of specific guidelines and standards under Malawi legislation,

good international industry practice (GIIP)Ø International guidelines and standards e.g. International Finance Corporation

(IFC) Performance Standards on Environmental and Social Sustainability (2012), the World Bank Group Environmental, Health and Safety Guidelines (2007) and the Equator Principles (Equator Principles Association, 2013).

Legislative Context

Section 3 of the ESR for more information

Page 28: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

7

Objectives of the scoping phase:ü Provide opportunity for all stakeholders to exchange information with the Project

team and express their views and concerns regarding the Project.ü Identify key issues and concerns that require further assessment during the ESIA

phase.ü Identify potential environmental and social issues that require detailed

investigation and assessment by specialists in the ESIA phase.ü Develop the ToR for specialist studies.ü Determine the extent of, and approach to, the ESIA.

Purpose of the ESR:ü Provides a description of the proposed Project (Section 2).ü Details information on the existing biophysical and social environment (Section 4). ü Identifies potential environmental and social issues that require detailed

assessment in the ESIA phase (Section 6).ü Defines the ToR for the required specialist studies (Section 7).

Environmental Scoping Report (ESR)

Soil:• Exposure and disturbance of soil. • Increased soil erosion.• Lack of topsoil for rehabilitation.

Potential Impacts and Issues for Consideration (Section 6)

Plants and Animals:• Loss of vegetation through clearing.• Displacement of fauna.• Loss of feeding and breeding sites.• Habitat degradation due to dust.• Impact through accidental contact with harmful substances.• Disturbance of fauna through noise and vibration.• Disruption of fauna migration patterns.• Invasion of alien vegetation.

Page 29: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

8

Wetlands:Loss of wetland habitat.•Sedimentation of • dambos.Impact on aquatic biodiversity.•

Potential Impacts and Issues for Consideration (Section 6)

Surface and Groundwater:• Decrease in surface water run-off.• Deterioration of water quality.• Groundwater inflow into open pits.• Impact on aquifers through pit dewatering.• Deterioration of groundwater quality.• Creation of acid mine drainage (AMD), although unlikely to occur.

Air Quality:• Increase in dust.• Increase in gaseous emissions.• Increase in greenhouse gases.

Noise and Vibration:• Increase in noise and vibration

Cultural Heritage Resources:• Disturbance of archaeological and

cultural heritage sites.• Disturbance of graves.

Traffic:• Increase in vehicle traffic – impact on

noise, road safety, illumination, road conditions.

Potential Impacts and Issues for Consideration (Section 6)

Visual:• Change in visual character and sense

of place.

Page 30: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

9

Potential Impacts and Issues for Consideration (Section 6)

Social:• Land acquisition and resettlement.• Creation of employment opportunities.• Population influx:

o lead to informal settlementso increased demand for local community serviceso poor sanitation practiceso pressure on land and water resourceso impact on community well-beingo increased risks related to transmission of communicable disease

• Improvement in social infrastructure.• Contribution to the economy.• Successful rehabilitation and closure disturbed areas.

The following studies will be undertaken as part of the ESIA phase and will focus on the Project area and the access route:

Specialist Studies in the ESIA Phase (Section 7)

Sovereign aims to complete all studies towards the end of 2018 to enable them to decide on whether the mine will be developed or not

• Terrestrial flora and fauna.

• Aquatic ecology.

• Soils and land capability.

• Surface water.

• Groundwater.

• Geochemistry (acid mine drainage).

• Air quality and greenhouse gas.

• Noise and vibration.

• Visual impact assessment.

• Social impact assessment.

• Resettlement action plan.

• Heritage and archaeology.

• Health impact assessment.

• Rehabilitation and closure plan.

For more details and ToRs on the various studies refer to Section 7 of the ESR.

Specialist studies will be conducted based on the ToRs described in the ESR

Page 31: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

10

Stakeholder Engagement (Section 5)

• Comments and Responses Report details issues raised to date – Appendix H of ESR.

• Stakeholder engagement will continue throughout the ESIA phase.

• Comments, issues and queries raised will inform the various studies and be incorporated in the Comments and Responses report.

• Grievance mechanism – Appendix G of ESR – will be implemented during the ESIA phase.

• Meetings to be held again on completion of the ESIA Report (4th Quarter 2018).

As part of the social impact assessment and data collection for the resettlement action plan, consultation will be undertaken at household

level. This consultation will commence in late April 2018.

Objectives of the ESIA

ü Define the existing social, cultural, economic and environmental conditions within the Project area.

ü Review feasible Project alternatives.

ü Identify and assess potential environmental and social impacts associated with the Project.

ü Identify practical and feasible mitigation measures to avoid or minimise the potential impacts of the Project, and to enhance the beneficial outcomes of the Project for the communities within the area.

ü Identify relevant monitoring protocols to ensure the mitigation and management measures are implemented effectively.

ü Develop a conceptual rehabilitation and closure strategy for the Project.

ü Develop a resettlement action plan.

Page 32: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/18/18

11

ESIA Schedule

• Project Brief completed and EAD indicated an ESIA will be required

Project Brief (June 2017)

• Project announcement

• Draft Scoping Report - March 2018

• Meetings

• Final Scoping Report to EAD

Scoping Phase (December 2017 to May 2018)

• Specialist assessments undertaken

• Draft ESIA Report – late 2018

• Meetings

• Final ESIA Report to EAD

ESIA Phase (June to December 2018)

ESR available for review from 5 March to 13 April 2018

AECOMAnelle Lötter

Email: [email protected] Box 30523, CC3, Lilongwe, Malawi

C12Grace Mpinganjira

Email: [email protected]: +265 998 521 663/+265 881 409 466

Website: http://sovereignmetals.com.au/building-malingunde/

Your comments are important!Please share with us your concerns, questions and issues

ESR available at:• Offices of C12 Consultants – Office Number 7, Skyband Complex, off Paul Kagame Rd, Lilongwe.

• Offices of the Environmental Affairs Department.• Lilongwe District Council Offices.• Masumbankhunda Traditional Authority.

Page 33: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping
Page 34: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

1

Ntchito ya Mg’odi Ku Malingunde

Kafukufuku wa momwe ntchito ya m’godi ingadzakhudzire zaChikhalidwe cha anthu komanso za chilengedewe

Misonkhano ya onse okhudzidwa – Gawo la Kauniuni wa zaChilengedwe.7 – 9 March 2018Lilongwe, Malawi

�Ochokera ku Kampani yaSovereign

� (Eni ntchito)• Andries Kruger• Reidwel Nyirenda

�Ochokera ku DhamanaConsulting

� (Wanmkulu oyang’anira za Chilengedwe)• Nanette Hattingh

�Ochokera ku Kampani ya Aecom� ( Owona za Okhudzidwa Onse)

• Anelle Lotter

�C12� (Owona za Kafukufuku wa chikhaliwe cha

anthu ndi za okhudzidwa onse)• Akeel Hajat• Arthur Kambombe• David Mussa

Kudziwa ogwira ntchito: Gulu la Pulojekiti

Page 35: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

2

1. Kufotokozerana zokhudza pulokekiti ya ku Malingunde ndi za ntchitoya kafukufuku, makamaka za lipoti yoyamba ya kauniuni wa momwentchitoyi ingakhudzire ntchito za chilengedwe.

2. Kukambirana za zoopsa zomwe zapezeka ndipo zofunika kuziunikabwino lomwe mu kafukufuku owona momwe ntchitoyi ingakhudzirechikhalidwe cha anthu komanso za chilengedwe m’delali

3. Kuunika ndondomeko zomwe opanga a kafukufuku osiyanasiyanaadzagwiritse ntchito.

1. Kutolera ndemanga za ndondomeko za bwino zomwe zingatsatidwepopanga kafukufuku owona momwe ntchito ingakhudzire chikhalidwecha anthu kapena za chilengedwe ku delali.

2. Kutolera maganizo ndi mfundo zosiyanasiyanas.

Cholinga cha Nsonkhano ndi Mfundo zokambirana

• A sovereign Metals akupanga akauniuni osiyanasiyana omwe adzaunikirandondomeko ya kafukufuku wa momwe ntchito ya m’godi idzakhudzire miyoyo ndichikhalidwe cha anthu komanso zachilengedwe. Kafukufukuyu adzathandizansokuunika ngati kuli kwa phindu kupita patsolo ndi ntchito ya mg’odi ku Malingunde. Kafukufuku adasonyeza kuti ku delali kungathe kupezeka Graphite olemera ma tani 44000 pa chaka, kwa zaka zokwana 17.

• Kampani ya Sovereign metals inamaliza kupanga kauniuni wa phindu lomwelingapezeke mu m’godi wa ku Malingunde. Pakadali pano kampaniyi ikuunika zazofunika kuchita poona za kuthekera kotsegula m’gdodi ku Malingunde.

• Kampani ya Sovereign yayambaponso kafukufuku owona momwe ntchito yamg’odi ingakhudzire za chikhalidwe cha anthu komanso za chilengedwe kuMalingunde

• Kafukufukuyu amachitika mmagawo awiri (Gawo lounika za chilengedwezopezeka kuderali komanso gawo la kafukufuku owona monwe ntchitoyiingadzakhudzire chikhalidwe cha anthu komansozachilengedwe.

• Ngati kungadzaoneke kuti nkotheka kupitilira ndi pulojekitiyi, ntchito yonseidzakhazikitsidwa mchaka cha 2019

Akafukufuku omwe apangidwa ndi a Sovereign Metals Limited

Page 36: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

3

Zofunika Kuchita Ntchito ya Mg’odiIsanayambike

Zofunika kuchita Zachitika kapena ayi? Nthawi Yochitika

Kauniuni wa zaChilengedwe ✔

Adachitika mkati mwachaka cha 2017

Kukonzekera kupangaKafukufuku ✖

Kudzachitika mkati ma chaka cha-2018

Kafukufuku wazachikhalidwe cha anthundi zachilengedwe

✖Adzachitika kumapeto kwachaka cha 2018

Dongosolo la Kusamutsaanthu ✖

Adzachitika kumapeto kwa chaka cha 2018

Kafukufuku omaliza ✖Adzachitika kumayambilirokwa chaka cha 2019.

Chilolezo cha Mg’odi ✖Chidzaperekedwa mkatimwa chaka cha 2019

Mgwilizano wakagulitsidwe ✖

Udzachitika mkati mwachaka cha 2019

Chiganizo chotsegulamg’odi ✖

Chidzachitika mkati mwachaka cha 2019

• Ma kampani a Dhamana Consulting, AECOM ndi C12 (yomwe ndi yaku Malawi) ndi akatswiri popereka upangiri okhudza zofufuza momwentchito za chitukuko zimakhudzira chikhaliwe ndi umoyo wa anthukomanso za chilengedwe ndipo apatsidwa udindo opangakafukufukuyu molingana ndi pulojekiti ya Graphite ku Malingunde.

• Makampani a Dhamana Consulting, AECOM ndi C12 ndi oima pa okhakomanso alibe cholowa kapena kutengapo mbali mu Pulojekiti ya kuMalingunde. Ma bungwewa sakondera mbali ili yonse, ofuna kutsegulamg’odi kapena anthu ndi mabungwe onse okhudzidwa ndi nkhaniyi.

Udindo wa makampani a Dhamana Consulting, AECOM ndiC12

Page 37: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

4

1. June 2017: Tsatanetsatane okhudza pulojekitiyi adapelekedwa ku nthambi ya bomayoona za Chilengedwe yomwenso idasonyeza kuti pakufunika kupanga kafukufukuowona momwe ntchitoyi ingadzakhudzire chikhalidwe cha anthu komanso zachilengedwe.

2. December 2017: Kulengezedwa kwa Kafukufuku woona momwe ntchitoyiingadzakhudzire chikhalidwe cha anthu komanso za chilengedwe.

• Misonkhano ndi onse okhudzidwa idachitika pa (4 – 7 Dec 2017)• Timabukhu tofotokoza dongosolo la pulojekiti yonse tidagawidwa kuti anthu

awerenge ndikudziwa tsatanetsane wa ntchito yonse. • Maganizo ochokera kwa onse okhudzidwa adalandilidwa ndikuikidwa mu lipoti ya

maganizo a anthu ndi mabungwe

3. March 2018: lipoti loyamba la kauniuni lidzakhala likupezeka kuti anthu awerengekuyambira pa 5 March mpaka pa 13 April

• Lipoti lopanda ndondomeko zozama loti aliyense akhoza kulimva lidatulutsidwandikugawidwa

• Misonkhano yokumana ndi onse okhudzidwa idzachitika kuyambira pa 7 mpaka pa 9 March, 2018.

• Maganizo a onse a okhuzidwa adzaikidwa mu lipoti kuti anthu awerenge komansokuti agwiritsidwe ntchito.

4. May 2018: Kupereka lipoti lipoti lomaliza la Kauniuni ku nthambi ya boma yoona zakasamalidwe a za Chilengedwe

Zinthu zazikulu zokhudza kauniuni wa za chilengedwe zomwezachitika kale

• Sovereign Metals Limited ndi Kampani yovomerezeka ndi boma ku Australia yomwe ili ndi chidwi chofunafuna komanso kutsegula migodi ya Graphite mchigawo cha pakati ku Malawi

• McCourt ndi nthambi yathunthu ya kampani ya Sovereign komanso yomwe ili ndichilolezo chapadera chongogwilizira cha umwini wa malo omwe pulojekitiyiingadzachitikire.

• Kampani ya MacCourt ndiyo idapempha chilolezo chopanga kafukufuku wammene mg’odi omwe ungadzabwerewu ungadzakhudzire chikhalidwe cha anthukomanso za chilengedwe.

Kodi a McCourt ndi a Soverign Metals ndi Ndani?

Page 38: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

5

Malo a Pulojekiti

- Pulojekiti ya Malingunde ili pa mtunda wa makilomita 15 kuzambwe kwa mzinda wa Lilongwe.

- Pulojekitiyi idzatenga malo okwanama hekitala a pakati pa 300 ndi400

- Msewu ofikira ku malowa ndi waphula wa S124 odzera ku Likuniomwe umakaphera mu nsewu wafumbi opita ku Kamuzu Dam.

- Malowa ali pafupi ndi midzi yaKumalindi (Chitsulo) ndi Ndumila

- Malowa ali kumpoto kwenikwenikwa Kamuzu Dam II

10 Presentation Title

- Malo otaya miyala yosafunika- Malo otayila zinyatsi

zochokera mu fakitale- Malo ochapira miyala ndi

kuyengera Graphite- Misewu- Ma damu osungira madzi- Malo a zipangiso zosamalilira

madzi- Nyumba zokonzeramo ma

galimoto- Malo osungila mafuta a

galimoto- Nyumba za ma ofesi,

zimbudzi ndi zina zofunika

Chisonyezo cha mmene zofunikiraszi zidzakhaliere pamalopa. Kayalidwe keneikeni ka zomangamangazi kadzadziwika bwino kutsogoloku zonse zikaunikidwa

bwino.

Dongosolo la momwe Pulojekiti ya Malingunde idzakhaliere

Page 39: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

6

• Mayenje okumbidwa mosaya kwambiriadzakumbidwa ndi ma trakitala ndipo dothilidzanyamulidwa ndi magalimoto onyamula dothi(mathipa).

• Sipadzafunika kuboola miyala kapena kuphulitsamabomba.

• Mayenje sadzakhala akuya mopitilira ma mita 25 kapena 200 mulitali.

• Miyala yokumbidwa idzanyamulidwa kupita ku malokomwe idzapukutidwa komanso kuchapidwa

• Miyala yosafunika idzataidwa ku malo otayakomiyala yosafunika kapena kumalo kotaya zinyatsizochokera ku fakitale.

• Graphite yense oyengedwa adzanyamulidwa pa magalimoto pa ulendo wa makilomita 26 kupita nayeku Kanengo komwe adzanyamulidwa pa sitima ya pa njanje pa ulendo opita ku doko la Nacala md’ziko la Mozambique

Mmene Ntchito idzagwilidwire pa malopa

Gawo 2 la lipoti la Kauniuni likufotokoza

zambiri

• Gawo lachiwili ndime ya (f) ya Malamulo a kasamalidwe ka zaChilengedwe a No. 19 omwe adavomerezedwa mnchaka cha 2017 akunena mosabisa kuti pamafunika kupanga kafukufuku wa momwentchito ya chitukuko ingakhudzire chikhalidwe cha anthu komanso zachilengedwe ntchitoyo isanayambike, makamaka ntchito zomwezikuoneka kuti zili ndi kuthekera koononga chikhalidwe cha anthukomanso za chilengedwe.

• Ma pulojekiti onse ofunika kafukufuku asadayambe adaikidwa mu ndondomeko zoyendetsera a kafukufuku onse a mmene ntchitozizingakhudzire chikhalidwe cha anthu komanso za chilengedwe.

• Zina zomwe zidzatsatidwa ndi izi:Ø Malamulo ena a dziko la Malawi omwe ndi ofunikanso ku ntchito ngati izi:. Ø Pomwe palibe malamulo mdziko muno, malamulo a dziko ovomelezeka ndi

maiko onse adzatsatidwa.Ø Malamulo ena omwe adzatsatidwa ndi monga a kayendetsedwe kabwino ka

za chuma, kayendetsedwe kabwino ka kafukufuku wa ntchito zomwezingakhudze chikhalidwe cha anthu komanso zachilengedwe, ndi ena otero.

Malamulo okhudza za Migodi

Gawo 3 la Kauniuni lilindi zambiri.

Page 40: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

7

Zolinga za gawo la Kauniuni wa za chilengedwe:ü Kupereka mwayi kwa onse okhudzidwa ndi nkhaniyi, anthu kapenanso a

mabungwe kuti agawane maganizo awo ndi omwe akuyendetsa ntchito yapulokeitiyi.

ü Kusanthula zinthu zikuluzikulu zofunika kuziunika mozama kupyolera mu kafukufuku owona momwe pulojekitiyi ingakhudzire chikhalidwe cha anthukomanso za chilengedwe.

ü Kusanthula zinthu zomwe zingakhudze chikhalidwe cha anthu komanso zachilengedwe kuti akadaulo azifufuze mozama.

ü Kuika ndondomeko zoti akadaulo opanga akafukufuku osiyanasiyana azitsatireü Kuika ndondomeko komanso mlingo wa kafukufuku.

Zolinga za Lipoti ya Kauniuni:ü Kupereka tsatanetsatane wa pulojekiti yonse (Gawo 2)ü Kupereka dongosolo la za chilengedwe zopezeka kuderako komanso za

chikhalidwe cha anthu (Gawo 4). ü Kuunika za chilengedwe komanso za chikhalidwe cha anthu zofunika kuziunika

bwino lomwe kupyolera mu kafukufuku (Gawo 6)ü Kukhazikitsa ndondomeko zoti akatswili osiyanasiyana azitsatire popanga

kafukufuku. (Gawo 7).

Lipoti ya Kauniuni wa za Chilengedwe

Nthaka:• Kufukuka kwa nthaka. • Kuchuluka kwa kukokoloka kwa

nthaka• Kutaika kwa nthaka yobwezeretsera

chilengedwe.

Mavuto odza ndi Pulojekiti ofuna Kuwaganizira Mozama(Gawo 6)

Zomera ndi nyama:• Kuonongeka kwa nkhalango.• Kusamuka kwa nyama chifukwa chakuonongeka kwa tchire• Kuonongeka kwa tchire momwe nyama zimadyamo komanso

kuswanilana.• Kuonongeka kwa malo okhala nyama chifuwa cha fumbi• Mavuto obwera pomwe nyama kapena zomera zakumana ndi

mankhwala osiyanasiyana ogwiritsidwa ntchito pa m’godi.• Kusokonezedwa kwa nyama chifukwa cha phokoso• Kusokonekera kwa nsamuko wa nyama omwe umachitika pa chaka.• Kuchuluka kwa zomera za chilendo

Page 41: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

8

Madambo:• Kuonongeka kwa madambo.• Kukwililika kwa madambo.• Kusokonekera kwa nyama zomwe

zimakhala modalirana.

Mavuto odza ndi pulojekiti ofunika kuwaganizira mozama(Gawo 6)

Madzi oyenda pamwamba komanso a pani pa nthaka:• Kuchepa kwa madzi oyenda mmitsinke kapena mmakhwawa.• Kuonongeka kwa ubwino wa madzi.• Kuyenda kwa madzi a pansi kulowa mmayenje .• Kusokonekera kwa a kasupe chifukwa cha kuchoka kwa madzi a mmayenje a

m’migodi.• Kuonongeka kwa madzi okhala pansi pa nthaka• Kupangika kwa madzi okhala ndi acid ngakhale kuti izi sizikuyembekezereka.

Ubwino wa mpweya:• Kuchuluka kwa fumbi.• Kuchuluka kwa utsi• Kuchuluka kwa mpweya oipa

Phokoso ndi kugwedezeka kwanthaka:• Kuchuluka kwa phokoso komanso

kugwedezeka kwa nthaka

Zachikhalidwe cha Makolo:• Kuonongeka kwa za chikhalidwe cha

makolo komanso za makedzanazopezeka pansi pa nthaka.

• Kuonongeka kwa mandaZoyenda pa nsewu• Kuchuluka kwa zoyenda pa misewu ya

m’delali zomwe zidzaonjeza phokoso, chipsezo cha ngozi za pa msewu komansokuonongeka kwa za misewu.

Mavuto odza ndi pulojekiti ofunika kuwaganizira mozama(Section 6)

Kaonekedwe:• Kusintha kwa kaonekewe ka malo.

Page 42: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

9

Mavuto odza ndi pulojekiti ofunika kuwaganizira mozama(Section 6)

Zokhudza chikhalidwe cha anthu:• Kutengedwa ndi kusamutsidwa malo pokhala.• Mwayi wa ntchito.• Kuchuluka kwa chiwerengelo cha anthu obwera:

o Kuchuluka kwa malo okhala anthu omangidwa mwa chisawawao Kuchuluka kwa anthu ofuna chithandizo cha bomao Kuchuluka kwa uveo Kuchuluka kwa ofuna zinthu zopezeka pa mtunda komanso mmadzio Kusokonekera kwa chikhalidwe cha anthu mmidzio Kuchuluka kwa matenda opatsilana

• Kuchuluka kwa ntchito za chitukuko.• Kuthandizira ku chuma cha boma.• Kubwezeretsedwanso kwa zonse zomwe zidaonongeka mmalo omwe adakhudzidwa.

Akafukufuku awa adzachitika ndipo adzakhala mbali imodzi ya kafukufuku owona momwe ntchito yamg’odi idzakhudzira chikhalidwe cha anthu komanso za chilengedwe . Kafukufukuyu adzachitikakumalo a pulojekiti komanso malo omwe a li mu nsewu opita ku malowa.

Akafukufuku ochitika ndi akadaulo osiyanasiyana (Gawo 7)

Kampani ya Sovereign ndi yofunitsitsa kuti kafukufuku yense amalizike kumapezo kwachaka cha 2018 kuti apange chiganizo chopitilira ndi ntchito ya mgodi kapena ayi.

• Nyama ndi zomera za pa mtunda.

• Nyama ndi zomera za mmadzi.

• Nthaka ndi chonde.

• Madzi a pa mtunda

• Madzi a pansi pa nthaka.

• Madzi okhala ndi acid.

• Kuonongeka kwa mpweya ndi mpweya oipa

• Phokoso ndi kugwedezeka kwa nthaka.

• Kusaona bwino patali kubwera chifukwa cha fumbi.

• Kafukufuku wa za chikhalidwe cha anthu.

• Dongosolo la kusamutsa anthu.

• Za chikhalidwe cha makolo zooneka komansozopezeka pansi pa nthaka

• Kafukufuku wa za umoyo

• Dongosolo la kasamutsidwe ka anthu komansola katsekedwe ka pulojekiti

Kuti mudziwe zambiri za ndondomeko zaa kafukufuku amenewa werengani gawo 7 la lipoti ya Kauniuni yemwe adachitika.

Akadaulo adzapanga kafukufuku molingana ndi ndondomeko zonse zomwe zaikidwa mu gawo 7 la lipoti ya kafukufuku

Page 43: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

10

Kukumana ndikukambirana ndi onse okhudzidwa (Gawo 5)

• Maganizo onse omwe anthu adapereka akupezeka mu gawo H la lipoti la Kauniuni yemwe adachitika.

• Zokambirana ndi anthu onse okhudzidwa zikhala zikuchitika mu nthawi yonseya kafukufuku wa mmene ntchitoyi idzakhudzira za chikhalidwe cha anthukomanso za chilengedwe.

• Maganizo onse komanso nkhawa zimene anthu ndi mabungwe angaperekezidzathandizira mu akafukufuku osiyanasiyana ndipo zidzaikidwa mu Lipoti yaMaganizo a anthu.

• Ndondomeko yotsata popereka chidandaulo: Gawo G – Lidzagwiritsidwantchito nthawi ya kafukufuku owona momwe ntchitoyi idzakhudzira miyoyo yaanthu komanso za chilengedwe.

• Misonkhano idzachitikanso pomaliza pa kafukufuku mundime yachinayi yachaka cha 2018 pamene lipoti la kafukufuku lidzatulutsidwa.

Ngati mbali imodzi ya kafukufuku owona mmwe ntchitoyi idzakhudzira chikhalidwe cha anthukafukufuku oona za kusamutsidwa kwa anthu adzachitika khomo ndi khomo. Izi zidzachitika

kumapeto kwa mwezi wa April, 2018.

Gawo la Kafukufuku owona momwe pulojekiti idzakhudzirechikhalidwe cha anthu komanso za chilengedwe.

Zolinga za Kafukufukuyu:

ü Kuunika momwe chikhalidwe cha anthu chilili pakadali pano, momwe zachuma ndi za chilengedwe zilili ku dela lomwe pulojekitiyi ingadzakhale

ü Kuunika ndondomeko zabwino zoyendetsera pulojekiti.

ü Kuunika komanso kusanthula zoopsa zomwe zingadzabwere ndi pulojekiti ndikukhudza chikhalidwe cha anthu komanso za chiengedwe.

ü Kusanthula zomwe zingatheke kuzichita pochepetsa ziopsezo zomwe pulojekiti ingadzabweretse

ü Kupeza njira zabwino zopangira kalondolondo owonetsetsa kuti njira zonse zoikidwa pofuna kuchepetsa zoopsa zobwera ndi pulojekiti zikuyenda bwino lomwe.

ü Kuika mmalo ndondomeko za bwino zotsekera mg’odi komanso kubwezeretsera zoonongeka zonse..

ü Kuika mmalo ndondomeo zabwino zosamutsila anthu mmalo omwe adzakhudzidwa ndi ntchito ya mg’odi.

Page 44: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/5/19

11

Ndondomeko ya kafukufuku owona momwe nthitoyiingakhudzire chikhalidwe cha anthu komanso zachilengedwe

• Dongosolo lonse la pulojekitilidafotokozedwa ndipo kudaonekwa kutiKafukufuku wa momwe ntchitoyiingakhudzire chikhalidwe cha anthukomanso za chilengedwe adzafunika.

Tsatanetsatane waPulojekiti(June 2017)

• Kulengeza za Pulojekiti• Lipoti loyamba la Kauniuni- March 2018• Misonkhano• Lipoti lomaliza la Kauniuni lopita ku nthambi ya

boma yowona za kuteteza za chilengedwe

Gawo la Kauniuni(December 2017 to May 2018)

• Kuchitika kwa kafukufuku wa akadauloosiyanasiyana

• Lipoti loyamba la kafukufuku – kumapeto kwachaka cha 2018

• Misonkhano• Lipoti lomaliza la kafukufuku lopita ku nthambi

ya boma yoona za kuteteza za chilengedwe

Gawo la Kafukufuku(June to December 2018)

Lipoti la Kauniuni lidzakhala likupezeka kuti anthu aliwerengekuyambira pa 5 March mpaka pa 13 April 2018

AECOMAnelle Lötter

Email: [email protected] Box 30523, CC3, Lilongwe, Malawi

C12Dorothy Mbendela, Email: [email protected], Tel: +265 998 521

663/+265 881 409 466

Website: http://sovereignmetals.com.au/building-malingunde/

Ndemanga zanu nzofunika!Chonde tifotokozereni maganizo anu, nkhawa zanu komanso mfundo zanu

Kopezeka lipoti la kauniuni:• Ofesi ya C12 Consultants – Office Number 7, Skyband Complex, off Paul Kagame Rd, Lilongwe.

• Ofesi ya Nthambi ya boma yowona zosamalira za chilengedwe.• Ma ofesi a Khonsolo ya Lilongwe.• Kwa Mfumu Masumbankhunda .

Page 45: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping
Page 46: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

1

Malingunde Graphite Project

2018 Fieldwork ProgramIn support of the definitive feasibility study and environmental and social impact assessment

Stakeholder Meetings

6 – 10 August 2018

Lilongwe, Malawi

1. Current status of the feasibility study program and environmental and social impact assessment (ESIA).

2. The 2018 fieldwork program to be undertaken, specifically exploration drilling.

3. Obtain comments and inputs from stakeholders about the resettlement action plan (RAP).

Purpose of the Meeting and Discussion Points

Page 47: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

2

Recap: The Malingunde Graphite Project

- Sovereign is determining the viability of developing a graphite mine at Malingunde

- Malingunde Project is located 15 km southwest of Lilongwe Boma, and falls within the Lilongwe District of the Central Region

- Project area will be ~ 300 – 400 hectares in size

- Access to the Project is from Lilongwe via the sealed section of the secondary road, S124, to Likuni and then the unsealed continuation of the S124 to the Kamuzu Dam turn-off

- Located in proximity to the villages of Kumalindi (Chitsulo), Kubale and Ndumila

- Directly north of Kamuzu Dam II

Before mining can commence, the geological, financial, environmental, social and engineering aspects must be evaluated to determine the viability of a project.

The project development phases (or mining life-cycle):

Project Development Phases

Economic Scoping Study

Pre-feasibility Study

Definitive Feasibility Study

Evaluation

Detailed Design and Engineering

Execution

Construction M ining

Discovery and Assessment

ExplorationResource Definition

Environmental and Social Impact Assessment

Resettlement Action Plan• Mapping• Drilling• Sampling

Further Exploration

Mid 2017 August 2018 March/April 2019 Mid 2019

Decision whether to proceed with

mining Submit Mining Right Application

Early 2013 Early 2020

Page 48: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

3

• Sovereign is still undertaking exploration and conducting various technical studies to evaluate the viability of developing the Project at Malingunde.

• An economic scoping study was completed in mid-2017 and the pre-feasibility study (PFS) will be completed towards the end of August 2018, after which Sovereign will commence a definitive feasibility study (DFS).

• An environmental and social impact assessment (ESIA) process as required in terms of the Environment Management Act (No 19 of 2017) is underway.

• A decision on whether it is viable to develop a mine at Malingunde will only be taken around mid-2019 once the DFS and ESIA have been completed.

Project Development Activities

Economic scoping study

- 2017

Pre-feasibility study - Aug

2018

Definitive feasibility

study - 2019

• Project development activities required before mining can commence

Project Development Activities (2)

Page 49: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

4

• Two distinct phases - environmental scoping and ESIA phases.

• A draft environmental scoping report (ESR) was available from 5 March to 13 April 2018 for review and comment by stakeholders.

• A revised ESR was submitted to the Environmental Affairs Department on 11 May 2018

• The Environmental Affairs Department reviewed and approved the terms of reference for the ESIA Phase in June 2018

• Various specialist studies are being completed. These include:

• These studies will be included in the ESIA Report which will be available at the end of 2018

ESIA Process and Current Status

Social impact assessment Terrestrial fauna and flora Air quality and greenhouse gas

Wetlands Aquatic ecology Noise and vibration

Soils and land capability Surface water Resettlement action plan

Groundwater Archaeology and cultural heritage Visual impact assessment

Health risk assessment Mine closure plan

Recap: ESIA Schedule

• Project Brief completed and EAD indicated an ESIA will be required

Project Brief (June 2017)

• Project announcement • Draft Scoping Report - March 2018• Meetings• Final Scoping Report to EAD

Scoping Phase (December 2017 to May 2018)

• Specialist assessments undertaken• Draft ESIA Report – late 2018 • Meetings• Final ESIA Report to EAD

ESIA Phase (June to December 2018)

Page 50: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

5

• Specialist studies are dependent on baseline data collected about the environmental and social conditions in the Project area.

• The majority of the environmental and social fieldwork activities have now been completed.

• Surface and groundwater quality sampling and dust fallout monitoring will continue for the rest of 2018.

2018 Fieldwork Program - Environmental Activities

Surface water sampling Dust fallout

monitoring equipment

2018 Fieldwork Program – Drilling Activities

Page 51: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

6

Various exploration programs have been undertaken by Sovereign in the Malingunde area over the last few years as part of the feasibility studies.

To date the following activities have been undertaken:

Previous Exploration Activities

Type of DrillingNumber of

HolesMeters Purpose

Hand Augering 1 363 10 000 Exploration and resource drillingAir Core Drilling 348 11 596 Resource determinationCore Drilling 13 488 Metallurgical test workHydrological Drilling 16 548 Pump testing for groundwater modelling

The following drilling activities are planned for the remainder of 2018 (from mid August onwards):

• Continued low impact “hand-auger” drilling to test for additional graphite mineralisation in the Malingunde and other areas across the Lilongwe Plain.

• Approximately four water monitoring boreholes in the area of the proposed tailings storage facility (TSF) (Kavuma area).

• Approximately fourteen “diamond core” holes for geotechnical studies in the location of the TSF, the proposed plant site, and the proposed open pit areas.

• Approximately eighty “air core” holes for continued definition of the graphite resource at Malingunde and to test for further graphite mineralisation at depth on other regional targets..

2018 Fieldwork Program – Drilling Activities

Page 52: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

7

Examples of drilling activities

Hand-auger drilling

Air core drilling

The following drilling activities are planned for the remainder of 2018 (from mid August onwards):

• Approximately eight large diameter ~65 cm spiral auger holes to collect approximately 100 tonnes of material for metallurgical testing.

2018 Fieldwork Program – Drilling Activities

Equipment to be used in spiral auger holes

Page 53: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

8

• Sovereign will rehabilitate disturbed ground to pre-disturbance conditions as per agreement with the Department of Mines and the landholders.

Rehabilitation

• Before drilling activities commence, Sovereign with the Department of Lands, the Department of Agriculture and the Lilongwe District Council will conduct crop and land disturbance assessments.

• Disturbance allowances will be paid to affected landholders before the drilling activities commence.

• Disturbance allowances will be based on compensation rates determined by the relevant government departments.

Disturbance Allowances

Page 54: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

9

• Sovereign will proactively deal with any complaints during the 2018 fieldwork program as follows:

• Step 1: Complete a grievance form which will be logged in a grievance file for record-keeping purposes.

Grievance Mechanism

• Step 2: If the complaint cannot be dealt with immediately, the Sovereign representative will acknowledge receipt of a formal grievance in writing within three working days and state a probable date for resolving the grievance. If applicable, the Sovereign representative will provide a copy of the log form to the claimant.

Grievance Mechanism

Step 3: Grievances will be finalised within 30 days of receipt. If the Sovereign representative is unable to resolve the grievance, he/she will forward the grievance to the Sovereign Country Manager.

Page 55: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

10

Resettlement Action Plan

• Should the Project proceed, resettlement of some communities may need to be undertaken.

• Resettlement planning is required before any resettlement can take place. (Required by Malawian legislation and international best practice, specifically the International Finance Corporation’s (IFC) Performance Standard 5: Land Acquisition and Involuntary Resettlement).

• Outcomes of resettlement planning activities are captured in a resettlement action plan (RAP) document, which is submitted to the Ministry of Lands, Housing and Urban Development for review, comment and approval.

• Before approving a project’s ESIA and granting environmental authorisation a RAP must be submitted.

Resettlement Action Plan (RAP)

Page 56: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

11

The resettlement planning process for the project includes the following main activities:

• A baseline survey of the project area (April – June 2018).

• Consultation with households who may have to be resettled if the project continues, to discuss their preferences if they have to be resettled (August 2018).

• Submission of the baseline data to the Department of Valuation to calculate preliminary compensation rates for assets that may be lost as a result of resettlement (August 2018).

• Compilation of a draft RAP document and presentation of the document to stakeholders (end 2018).

• Submission of the RAP to the Ministry of Lands, Housing and Urban Development for comment and approval (end 2018).

Resettlement Planning Process

• Resettlement will only be undertaken if Sovereign decides to proceed with the project (approximately mid-2019), and once the RAP is approved

• Implementation can take a long time to complete, and will include the following steps (if approved):

• A verification survey by the Regional Department of Surveys and Valuation, to confirm the baseline information collected.

• Discussions with each household to confirm their assets, agree on the compensation package, and signing of a compensation certificate.

• Payment of compensation and preparation of a resettlement site (if relevant).• Physical resettlement and loss of access to assets such as agricultural fields.

• If resettlement is required, people will only move during 2020.

• Communities are encouraged to continue with their normal lives and activities, and cultivate their fields during the upcoming season.

• Not everyone who was surveyed from April to June 2018 may have to be resettled; the final Project design will aim to reduce resettlement as much as possible.

Steps Towards Potential Resettlement Implementation

Page 57: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

12

The resettlement process

January 2018

Legal review

April - June 2018

Baseline survey

August 2018

Consultation

August 2018

Baseline data to

Department of Valuation

End 2018

Compilation and

disclosure of RAP

document

End 2018

Submission of RAP to the Ministry of

Lands, Housing and

Urban Development

Estimated second half

of 2019

Verification survey

Estimated end 2019

Compensationcertificates

Estimated beginning

2020

Compensation payment and

preparation of a resettlement

site

Estimated mid to end

2020

Physical resettlement

and loss of access to

assets

Planning ImplementationDecision to mine

(expected mid 2019)

Next Steps and Closure

• Sovereign will contact the landholders who may be impacted by the drilling activities to make the necessary arrangements with them.

• An assessment will take place to determine the disturbance allowances to be paid.

• Drilling activities to commence mid-August 2018.

• ESIA Report will be available towards the end of this year and we will meet with you again to discuss the contents of the report.

Thank you for your participation

Page 58: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

4/22/19

13

Next Steps and Closure

AECOMAnelle Lötter

Email: [email protected] Box 30523, CC3, Lilongwe, Malawi

C12

Grace MpinganjiraEmail: [email protected]

Tel: +265 998 521 663/+265 881 409 466

Website: http://sovereignmetals.com.au/building-malingunde/

Your comments are important!Please share with us your concerns, questions and issues

Page 59: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Page Left Blank Intentionally

Page 60: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Pulojekiti ya Graphite(Chizire) ku

Malingunde

Ndondomeko ya ntchito mu 2018 Kuthandiza ndi kuunika mathero a kafukufuku wa mmene ntchitoyi idzakhudzire za zachilengedwe ndi chikhalidwe cha anthu. Misonkhano ya onse okhudzidwa 6 – 10 August 2018 Lilongwe, Malawi

Page 61: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

1.Mmene ziliri lero pa kafukufuku wa za chilengedwe ndi chikhalidwe cha anthu.

2.Ntchito yochitika pa malopo mu 2018 ya kauniuni ndikukumba kuti apeze miyala.

3.Kulandila ndemanga ndi zoonjezera kuchokera kwa onse okhudzidwa ndi zosamuka ndi kupezera anthu malo.

Zolinga za misonkhano ndi mfundo zokakambirana

Page 62: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Tsatanetsane wa ntchito zina za pulojekti zoti zichitike ntchitoyi isanayambe zasanjidwa motere:

Tsatanetsatane wa ntchito za pulojekiti

Zochitika Kodi amaliza? Nthawi yake

Kutambasula ndi kuona ngati pali phindu. ✔ Mkatikati mwa -2017

Malipoti oyamba a zachilengedwe ✔ May 2018

Kutambasula ndi kuona ntchito isanayambike

Atsala pang’ono kumaliza

August 2018

Lipoti loona mmene zingakhudzire za chilengedwe ndi chikhalidwe cha anthu

Zikupitirirabe Miyezi itatu yomaliza ya 2018

Mapulani osamutsa ndi kupezera anthu malo

Zikupitirira Miyezi itatu yomaliza ya 2018

Kafukufuku wotsiriza Miyezi itatu yoyambirira ya 2019

Kupanga chiganizo ngati mgodi uyenera kuyamba

Mkatikati mwa 2019

Kupempha kalata ya chilolezo choyambitsa mgodi

Mkatikati mwa 2019

Makalata amgwirizano wa msika. Mkatikati mwa 2019

Page 63: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Mapulogalamu angapo akauniuni amene a Sovereign achita pamalowa ku Malingunde muzaka zingapo zapitazo ngati mbali imodzi ya kafukufuku. Lero lino zimene zachitika ndi izi:

Zina zimene zachitika pa kauniuni

Kakumbidwe Kuchuluka

kwa maenje Mulingo Cholinga

Kuboola ndi manja 1 363 10 000 Kuboola kuti aone ngati pali Miyala ya mgodi

Kuboola ndi chida cha mphweya

348 11 596 Kutsimikiza ngati pali miyalayo

Kuboola motsimikiza 13 488 Kuyeza ngati miyaloyo ili yeniyeni Kuboola ndi kupeza madzi

16 548 Kuyeza ndi kuoona mmene alili madzi

Page 64: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Zomwe zachitika Kale: Ndondomeko ya kafukufuku wa za chilengedwe ndi za chikhalidwe cha anthu

• Kumaliza dongosolo la pulojetiki mwachidule ndipo a EAD anaonetsa kufunika kwa kafukufuku wa za chilengedwe ndi chikhalidwe cha anthu

Pulojekti mwachindunji (June 2017)

• Kulengeza za pulojekiti • Kulemba lipoti loyamba - March 2018 • Misonkhano • Lipoti lomaliza kutumiza ku EAD

Gawo loonetsa zofunikira zonse.

(December 2017 - May 2018)

• Kuunikira mwa ukadaulo kwachitika • Lipoti loyamba la kafukufuku wa za

chilengedwe ndi chikhalidwe cha anthu mapeto a 2018

• Misonkhano • Lipoti lomaliza kutumiza ku EAD

Gawo la kafukufuku wa za chilengedwe ndi

chikhalidwe cha anthu (June - December 2018)

Page 65: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

• Ukadaulo wozama adzachitika potengera zotsatira zimene apeza pa kafukufuku wozungulira malo a pulojekiti.

• Zochitika zambiri zokhudza za chilengedwe ndi chikhalidwe cha anthu zakwaniritsidwa.

• Kupima madzi a pamwamba ndi a pansi pa nthaka ndi kalondolondo woona za kuoopsya kwa fumbi zipitirira mpaka kumapeto a 2018.

Ntchito za pamalopo mu 2018 zokhudza za chilengedwe.

Kupima ubwino wa madzi

Zida za kalondolondo wa mfumbi

Page 66: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Zina zochitika zokhudza kukumba mgodi mu gawo lomaliza la 2018 (kuyambira mkatikati mwa August): • Kuboola maenje ndi manja mwa pango’nopang’ono kuti ayeze ngati ku Malingunde

kuli chizire chokwanira komanso ngati chikupezekanso malo ena ozungulira chigwa cha Lilongwe.

• Kuboola pafupifupi mijigo inayi yothandizira kalondolondo wa madzi pa malo amene

padzakhale posungira madzi otsukira miyala (Dela la Kavuma) • Kukumba pafupifupi maenje akulu mmwamba ndi osongoka pansi okwana khumi ndi

anai ndicholinga chofuna kuunika bwino miyala ya pansi, malo okhazikitsa makina, ndi malo odzakumba maenje a dzala.

• Kukumba pafupifupi maenje makumi asanu ndi atatu ndi makina a mpweya ndi

cholinga chofuna kuonetsetsa kuchuluka kwa chizire ku Malingunde ndi kuyesa kuchuluka kwake ndikukula kwa ndime.

• Kukumba timaenje tokwana tisanu ndi titatu tochotsapo dothi lokwana pafupifupi ma

tani 100 lochitila kafukufuku wa miyala.

Ntchito za pamalopo mu 2018 – Zochitika pokumba mgodi

Page 67: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Zitsanzo za mmene amakumbira

Kuboola ndi chida cha mmanja

Chida chozungulira choboola maenje

Kuboola ndi chida champweya

Page 68: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

• Asanayambe kukumba kwina kulikonse, a kampani ya Sovereign mothandizana ndi nthambi yoona za Malo, nthambi yoona za Ulimi ndi Khonsolo ya mzinda wa Lilongwe adzaunika ndi kuoona mmene ntchitoyi idzaonongere mbewu ndi malo a anthu

• Chipukuta misozi chidzaperekedwa kwa okhawo eni malo okhudzidwa ntchito yonse yokumba isanayambe.

• Chipukuta misozi zidzatengera mulingo umene adzapereke a mbali ya boma.

Chipukuta misozi

Kubwezeretsa chilengedwe

• A Sovereign adzakonzanso malowo kuti ayambenso kugwiritsidwa ntchito mopindulira anthu potsatira mgwirizano wa Nthambi yoona za Migodi ndi eni malo.

Page 69: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

• A Sovereign adzayankha dandaulo lina liri lonse pamene akugwira ntchito pamalowa mchaka chonse cha 2018 potsatira njira izi:

• Njira 1: Fomu ya madandaulo idzalembedwa ndi kuisunga bwinobwino kuchitira pa mawa.

Dongosolo la chipukuta misozi

Page 70: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Step 2: Ngati wodandaulayo sangathe kulandila yankho pompopompo, nthumwi ya kampani ya Sovereign idzaikira umboni kuti walandila dandaulo polemba kalata pasanathe masiku antchito atatu ndi kuyerekeza tsiku limene yanko lidzaperekedwe. Nthumwi idzapereka chikalata chofanana cha dandaulo kwa wodandaulayo ngati umboni.

Njira zomvera madandaulo

Step 3: Madandaulo onse adzayankhidwa pasanathe masiku makumi atatu. Ngati nthumwi ya Sovereign sikwanitsa kuyankha dandauloli, iye adzayenera kulitumiza kwa wa mkulu wa kampani ya Sovereign.

Page 71: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

• Ngati pulojekiti yagwira msewu, kusamutsa ndi kupezera anthu ena malo kudzachitika.

• Mapulani a mmene mungasamutsire anthu ndiofunika msamuko usanachitike. (Potsatira ndondomeko yabwino ya dziko la Malawi ndi maiko ena a kunja, makamaka nthambi yoona za chuma mfundo ya 5: Kupeza malo ndi kusamuka mochita kuuzidwa).

• Zotsatira zake anthu akasamutsidwa zionekeretu poyera mu chikalata chadongosolo cha kasamutsidwe ka anthu ndi kuwapezera malo chimene chidzaperekedwe ku unduna woona za malo, nyumba ndi chitukuko cha mmizinda kuti achiunike, apereke ndemanga ndi kuchivomereza.

Dongosolo lakasamutsidwe ndi kupezera anthu malo

• Asanavomereze za kafukufuku wa za chilengedwe ndi chikhalidwe cha anthu ndi kuvomereza pulojekiti, nthambi yoona za chilengedwe imafuna dongosolo la kasamutsidwe ka anthu kuti liperekedwe.

Page 72: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Tsatanetsatane wa kasamutsidwe ka anthu

January 2018

Kuoona malamulo

April - June 2018

Kuunguza mozama

August 2018

Kukambirana

August 2018

Kupereka zotsatira ku

nthambi yodziwa za mitengo ya

malo

Kumapeto a 2018

Kulemba ndi

kutulutsa chikalata cha

kasamutsidwe ndi kupezera anthu malo

Kumapeto a

2018 Kupereka

ndondomeko ya

kasamutsidwe ka anthu Ku unduna wa

malo, nyumba ndi chitukuko cha mmizinda

Mkatikati mwa gawo lachiwiri la

2019

Kutsimikiza zonse zomwe za unguzidwa

Kumapeto a 2019

Makalata a chipukuta

misozi

kumayambiriroa 2020

Kulipira

chipukuta misozi ndi

kukonza malo osamutsira

anthu

Chamkatikati ndi kumapeto

a 2020

Kusamutsa anthu ndi

kuletsa kudutsanso pamalopo

Dongosolo Kukhazikitsa

Chikonzero choyamba kukumba

(cha pakati)

Page 73: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Zotsatira zina ndi kutsekera mgodi

• A Sovereign adzakumana ndi eni malo onse amene adzakhudzidwa ndi ntchito yokumba mgodi kuti akambirane ndikugwirizana nawo.

• Padzakhala dongosolo lowerengera ndi kukhazikitsa ndalama zoti anthu alandire ngati chipukuta misozi.

• Ntchito yokumba mgodi idzayamba mkatikati mwa August 2018.

• Lipoti loona mmene ntchitoyi idzakhudzire za chilengedwe ndi chikhalidwe cha anthu lituluka kumapeto a chaka chino ndipo tidzayenera kuti tikumane nanu kuti tiunike za mulipotili. Zikomo chifukwa chakutenga

nawo mbali

Page 74: APPENDIX R Copies of Presentation from Stakeholder Meetingssovereignmetals.com.au/wp-content/uploads/2019/05/esia20.pdf · Draft Scoping Report - March 2018 Meetings Final Scoping

Zotsatira zina ndi kutsekera mgodi

AECOM Anelle Lötter

Email: [email protected] PO Box 30523, CC3, Lilongwe, Malawi

C12 Grace Mpinganjira

Email: [email protected] Tel: +265 998 521 663/+265 881 409 466

Website: http://sovereignmetals.com.au/building-malingunde/

Ndemanga zanu ndizofunika! Chonde tiuzeni nkhawa zanu, mafunso ndi mfundo zina