Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐1 RFTA #2015‐15‐040‐001
Appendix E ‐ Detailed Construction Cost Estimate An independent construction cost estimate was prepared based on the Basis of Design represented
in this report. Rider Levett Bucknall is a national cost estimating company with experience and
current cost history in the region. Their reporti is inculded here in its entirety (Figures E.1 though
E.8). The following (Table E.1 – RLB Report Summary of Amounts with Index of Figures) summary is
derived directly from the report (corrections to this report are noted below):
Table E.1 – RLB Report Summary of Amounts with Index of Figures (1) The RLB report did not include replacement of existing asphalt as described in 2.7 Site and Building
Systems. An amount of $172,317 (based on 32,000SF @ $3.75/SF, with mark‐ups) has been added to the RLB Site cost estimate.
(2) Line G3020‐76 has an incorrect area – area should be 6,700 SF. The cost difference, with associated markups, has been deducted from the RLB Administration cost estimate.
(3) This item was not provided with the RLB report. The amount included is based on a similar structure in Aspen (with escalation).
This estimate is based on the current, conceptual uderstanding of the project. This level of
estimating is affected by the signifcant potential to under‐react to cost issues, as well as to over‐
react based on a limted amout of information. A prudent, and conservative approach is used.
Nonetheless, the actual costs may vary as the project is developed further. Factors that can increase
costs include: the economy, additional detailed drawings and definition of systems, scope
packaging, contract award timing, and scope revisions. Factors that can improve costs include: the
economy, additional detailed drawings and definition of systems, and competative pricing by the
Design‐Build Contractor.
Report Cover & Assumptions Figure E.1 pages E‐2 through E‐4
Site $975,414 (1) Figure E.2 pages E‐5 through E‐6
Entrance Road $928,037 Figure E.3 pages E‐7 through E‐8
Surface Parking $376,559 Figure E.4 pages E‐9 through E‐10
Subtotal Site $2,280,010
RTC Bus & Car Parking Garage $38,938,445 Figure E.5 pages E‐11 though E‐15
Administration Building $5,349,398 (2) Figure E.6 pages E‐16 through E‐20
Subtotal RTC $44,287,843
Maintenance Faciltiy Addition $1,383,105 Figure E.7 pages E‐21 through E‐23
Maintenance Facility Renovation $928,037 Figure E.8 pages E‐24 through E‐25
Waste Enclosure $180,000 (3)
Subtotal Maintenance & Site Buildings $2,491,142
Total Construction Cost Estimate $49,058,995
![Page 2: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/2.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐2 RFTA #2015‐15‐040‐001
Figure E.1 – RLB Report Cover & Assumptions (image 1 of 3)
![Page 3: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/3.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐3 RFTA #2015‐15‐040‐001
Figure E.1 – RLB Report Cover & Assumptions (continued; image 2 of 3)
![Page 4: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/4.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐4 RFTA #2015‐15‐040‐001
Figure E.1 – RLB Report Cover & Assumptions (continued; image 3 of 3)
![Page 5: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/5.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐5 RFTA #2015‐15‐040‐001
Figure E.2 – RLB Site Construction Cost Estimate (image 1 of 2)
![Page 6: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/6.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐6 RFTA #2015‐15‐040‐001
Figure E.2 – RLB Site Construction Cost Estimate (continued; image 2 of 2)
![Page 7: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/7.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐7 RFTA #2015‐15‐040‐001
Figure E.3 – RLB Entrance Road Construction Cost Estimate (image 1 of 2)
![Page 8: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/8.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐8 RFTA #2015‐15‐040‐001
Figure E.3 – RLB Entrance Road Construction Cost Estimate (continue; image 2 of 2)
![Page 9: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/9.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐9 RFTA #2015‐15‐040‐001
Figure E.4 – RLB Surface Parking Construction Cost Estimate (image 1 of 2)
![Page 10: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/10.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐10 RFTA #2015‐15‐040‐001
Figure E.4 – RLB Surface Parking Construction Cost Estimate (continued; image 2 of 2)
![Page 11: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/11.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐11 RFTA #2015‐15‐040‐001
Figure E.5 – RLB RTC Bus & Car Parking Structure Construction Cost Estimate (image 1 of 5)
![Page 12: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/12.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐12 RFTA #2015‐15‐040‐001
Figure E.5 – RLB RTC Bus & Car Parking Structure Construction Cost Estimate (continued; image 2 of 5)
![Page 13: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/13.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐13 RFTA #2015‐15‐040‐001
Figure E.5 – RLB RTC Bus & Car Parking Structure Construction Cost Estimate (continued; image 3 of 5)
![Page 14: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/14.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐14 RFTA #2015‐15‐040‐001
Figure E.5 – RLB RTC Bus & Car Parking Structure Construction Cost Estimate (continued; image 4 of 5)
![Page 15: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/15.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐15 RFTA #2015‐15‐040‐001
Figure E.5 – RLB RTC Bus & Car Parking Structure Construction Cost Estimate (continued; image 5 of 5)
![Page 16: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/16.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐16 RFTA #2015‐15‐040‐001
Figure E.6 – RLB Administration Construction Cost Estimate (image 1 of 5)
![Page 17: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/17.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐17 RFTA #2015‐15‐040‐001
Figure E.6 – RLB Administration Construction Cost Estimate (continued; image 2 of 5)
![Page 18: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/18.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐18 RFTA #2015‐15‐040‐001
Figure E.6 – RLB Administration Construction Cost Estimate (continued; image 3 of 5)
![Page 19: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/19.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐19 RFTA #2015‐15‐040‐001
Figure E.6 – RLB Administration Construction Cost Estimate (continued; image 4 of 5)
![Page 20: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/20.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐20 RFTA #2015‐15‐040‐001
Figure E.6 – RLB Administration Construction Cost Estimate (continued; image 5 of 5)
![Page 21: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/21.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐21 RFTA #2015‐15‐040‐001
Figure E.7 – RLB Maintenance Facility Addition Construction Cost Estimate (image 1 of 3)
![Page 22: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/22.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐22 RFTA #2015‐15‐040‐001
Figure E.7 – RLB Maintenance Facility Addition Construction Cost Estimate (continued; image 2 of 3)
![Page 23: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/23.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐23 RFTA #2015‐15‐040‐001
Figure E.7 – RLB Maintenance Facility Addition Construction Cost Estimate (continued; image 3 of 3)
![Page 24: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/24.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐24 RFTA #2015‐15‐040‐001
Figure E.8 – RLB Maintenance Facility Renovation Construction Cost Estimate (image 1 of 2)
![Page 25: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/25.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐25 RFTA #2015‐15‐040‐001
Figure E.8 – RLB Maintenance Facility Renovation Construction Cost Estimate (continued; image 2 of 2)
![Page 26: Appendix E Detailed Construction Cost Estimate](https://reader031.fdocuments.us/reader031/viewer/2022013022/61d1954105d4bb64932bbcbb/html5/thumbnails/26.jpg)
Regional Transit Center Appendix E – Detailed Construction Cost Estimate Roaring Fork Transportation Authority Feasibility Study
November 16, 2016 page E‐26 RFTA #2015‐15‐040‐001
i RLB | Rider Levett Bucknall Construction Cost Estimate; Concept Design – Option 2 Final; Roaring Fork Transportation Authority; Glenwood Maintenance Facility (GMF); Glenwood Springs, CO.; dated October 18, 2016 (23 pages). Cost estimating has been conducted throughout this feasibility study process. The heading “Option 2” is an out of date reference that originated through the design studies conducted as a part of this report. Ultimately, “option 2” has been renamed “2016 Basis of Design”.