Appendices E - G-utilization Ratio
-
Upload
ignatius-samraj -
Category
Documents
-
view
215 -
download
0
Transcript of Appendices E - G-utilization Ratio
-
8/21/2019 Appendices E - G-utilization Ratio
1/169
City of Palo Alto Long Range Facilities Plan for the RWQCP
APPENDIX E - RWQCP CONDITION ASSESSMENT SUMMARY
-
8/21/2019 Appendices E - G-utilization Ratio
2/169
City of Palo Alto Long Range Facilities Plan for the RWQCP
APPENDIX G - SEISMIC EVALUATION OF THE PILESSUPPORTING THE INCINERATOR AND OPERATIONS
BUILDINGS TECHNICAL MEMORANDUM
-
8/21/2019 Appendices E - G-utilization Ratio
3/169
CITY OF PALO ALTO
REGIONAL WATER QUALITY CONTROL PLANT
FACILITY REPAIR AND RETROFIT PROJECT
SEISMIC EVALUATION OF THE PILES
SUPPORTING THE INCINERATOR AND
OPERATIONS BUILDINGS
-
8/21/2019 Appendices E - G-utilization Ratio
4/169
CITY OF PALO ALTO
REGIONAL WATER QUALITY CONTROL PLANTFACILITY REPAIR AND RETROFIT PROJECT
SEISMIC EVALUATION OF THE PILES SUPPORTING
THE INCINERATOR AND OPERATIONS BUILDINGS
TABLE OF CONTENTS
Page No.
1.0 PURPOSE ..................................................................................................................... 12.0 BACKGROUND ........................................................................................................... 1
2.1 Incinerator Building ............................................................................................ 12.2 Operations Building ............................................................................................ 5
3.0 SEISMIC EVALUATION .......................................................................................... 103.1 Seismic Evaluation Criteria .............................................................................. 10
3.2 Material Properties and Strengths ..................................................................... 113.3 Analysis Procedure ........................................................................................... 12
3.3.1 Mathematical Model .......................................................................... 123.3.2 Soil-Pile Interaction Modeling ........................................................... 133.3.3 Load Combinations ............................................................................ 17
4.0 FINDINGS .................................................................................................................. 174.1 Incinerator Building .......................................................................................... 17
4.1.1 Pile Capacity Check ........................................................................... 184.2 Operations Building .......................................................................................... 20
4.2.1 Pile Capacity Check ........................................................................... 214.3 Discussion ......................................................................................................... 21
5.0 RECOMMENDATIONS ............................................................................................ 225.1 Incinerator Building .......................................................................................... 235.2 Operations Building .......................................................................................... 26
6.0 CONCLUSIONS ......................................................................................................... 26
LIST OF APPENDICES
A – PhotographsB – Soil-Pile Interaction Analysis ResultsC E l ti C l l ti
-
8/21/2019 Appendices E - G-utilization Ratio
5/169
LIST OF TABLES
Table 1 Seismic Evaluation Parameters ........................................................................ 10Table 2 Material Properties - Piles ................................................................................ 11Table 3 Pile Lateral Spring Stiffness Values ................................................................. 16Table 4 Load Combinations .......................................................................................... 17Table 5 Analysis Results ............................................................................................... 18Table 6 Pile Shear Capacity Check - Incinerator Building ........................................... 20Table 7 Analysis Results ............................................................................................... 20Table 8 Pile Shear Capacity Check - Operations Building ........................................... 21
LIST OF FIGURES
Figure 1 Incinerator Building Floor Plan .......................................................................... 3Figure 2 Incinerator Building Elevations ......................................................................... 4Figure 3 Existing Pile Details ........................................................................................... 6Figure 4 Operations Building Floor Plan .......................................................................... 8
Figure 5 Operations Building Elevations ......................................................................... 9Figure 6 Incinerator Building Finite Element Model ..................................................... 14Figure 7 Operations Building Finite Element Model ..................................................... 15Figure 8 Site Response Spectra (Ground Acceleration versus Building Period) ........... 19Figure 9 Pile Addition to Existing Pilaster Foundation .................................................. 24Figure 10 Pile Addition to Existing Slab Edge ................................................................. 25
-
8/21/2019 Appendices E - G-utilization Ratio
6/169
City of Palo Alto
SEISMIC EVALUATION OF THE PILES SUPPORTINGTHE INCINERATOR AND OPERATIONS BUILDINGS
1.0 PURPOSE
The purpose of this report is to present the findings of our seismic evaluation of the existing piles
that support the Incinerator and Operations Buildings located at the Regional Water Quality
Control Plant (RWQCP) for the City of Palo Alto (City), California.
This evaluation was performed to advance the Facility Condition Assessment (FCA) report by
Kennedy/Jenks Consultants (December 19, 2006) that identified deficiencies in the lateral load
capacity of the piles at the Incinerator Building. The previous study was limited to a preliminary
type investigation of the Operations Building. No evaluation of the Incinerator Building was
made. Rather, it was assumed that the Incinerator Building piles lacked lateral capacity since the
Operations Building, which has a lower seismic load, was found to lack lateral pile capacity.
The current evaluation seeks to provide a more complete evaluation for the Incinerator Building
piles and to verify the preliminary findings for the Operations Building. This current evaluation
attempts to capture the building response to seismic loading by modeling the interaction of the
soil and the foundation. Such modeling accounts for the inherent flexibility of the foundation
interaction with the soil and allows for evaluation at generally larger seismic response periods
than response periods developed using the assumption that the foundation is rigidly attached to
the soil, the default approach taken in most evaluations. Larger response periods typically yield
lower seismic load demands.
Additionally, where the results of the evaluation indicate deficiencies in the lateral load resisting
capacity of the piles, recommendations for mitigation are provided.
2.0 BACKGROUND
The following set of drawings was reviewed for as-built information and was used to obtain the
necessary information for the evaluation of the piles:
Structural drawings of the Incinerator Building prepared by Jenks & Adamson Consulting
Sanitary & Civil Engineers, dated June 1969.
-
8/21/2019 Appendices E - G-utilization Ratio
7/169
floor of 44 feet. Two interior mezzanine levels at the south side of the building provide access to
equipment. The building also has a partial basement level for access to the bottom of the
incinerators. Photographs of the building are provided in Appendix A.
The roof of the building is constructed with a one-way spanning, cast-in-place concrete slab that
is 7 inches thick and supported by integral cast-in-place concrete joists and beams. The roof
framing is supported down to the foundation by a single line of rectangular concrete columns at
the interior of the building and by concrete pilasters at the perimeter.
The high mezzanine is located 24 feet above the finished floor on the south half of the building
extending across the full length. The floor area of the mezzanine is approximately 2,500 square
feet. The high mezzanine is constructed with a one-way spanning, cast-in-place concrete slab
that varies in thickness from 8 to 10 inches. The slab is supported by a system of integral
concrete joists and beams that are supported by a row of concrete columns that run along the
center of the building and concrete pilasters at the perimeter.
The low mezzanine is located in the southwest corner of the building and has an approximate
height above finished floor of 10 feet. The low mezzanine is relatively small and has a floor area
of 600 square feet. The floor is constructed with an 8-inch thick cast-in-place concrete slab that
is framed with concrete beams. The floor level is supported down to the foundation by concrete
pilasters and 8-inch thick concrete walls.
The perimeter wall of the building is constructed in a non-traditional configuration with large
tapered pilasters that protrude out from the exterior of the building by several feet at the base and
2 feet into the building. Four pilasters are located at the north and south walls, and two are
located at the east and west walls. The corners of the building are constructed with a concrete
column that is rounded to a 4-foot radius at the exterior of the building. The pilasters are
typically 26 inches thick. Concrete walls that are 9 inches thick fill in most of the gaps between
the panels and corners; however, a number of gaps are open and are covered by the building
finish system and associated framing. The exterior walls and open gaps are finished with a
combination of exposed concrete and corrugated steel panels. Refer to Figures 1 and 2 for thefloor plan and elevations of the building as depicted on the record drawings.
The ground floor of the building is constructed with a cast-in-place concrete slab that varies in
thickness from 13 to 14 inches. The slab is framed with concrete grade beams that span in two
directions and are supported on driven piles. The record drawings indicate three different pile
-
8/21/2019 Appendices E - G-utilization Ratio
8/169
pa811f2-8510.ai
Figure 1INCINERATOR BUILDING FLOOR PLAN
INCINERATOR AND OPERATIONS BUILDINGS
PILE SEISMIC EVALUATIONCITY OF PALO ALTO
-
8/21/2019 Appendices E - G-utilization Ratio
9/169
-
8/21/2019 Appendices E - G-utilization Ratio
10/169
and are located below columns, pilasters, and grade beams. Figure 3 shows the three different
pile alternatives that were specified on the record drawings.
The basement is partial to the north side of the building and is located directly below the
incinerators and extends down approximately 8 feet below the finished floor level. Concrete
walls that are 15 inches thick form the perimeter of the basement. The floor slab of the basement
is similar to the ground floor level, except that it has a thickness that varies from 16 to 18 inches.
The building houses two incinerators that are supported at the grade level. Each incinerator has
an approximate height of 25 feet and a diameter of 19 feet. The incinerators are fabricated with a
steel exterior shell and with refractory brick at the interior. Each incinerator is mounted to the
building slab at grade level with six pairs of 1.5-inch-diameter anchor bolts. Space for a third
incinerator is provided at the east end of the building. Two elevated steel-framed mezzanines
provide access around both incinerators. The mezzanine is covered with punched metal plank
grating. Seismic evaluation of the incinerators was completed during the ongoing Long Range
Facilities Plan project.
The exterior of the building has heavy air scrubbing equipment located at the northwest side and
solids storage and handling facilities located at the south side.
The lateral load resisting system of the building is comprised of rigid concrete diaphragms at the
roof and elevated floor levels that transfer lateral loads generated in an earthquake in proportion
to the stiffness of the vertical lateral load-resisting elements. The vertical lateral load-resistingelements are comprised of the perimeter concrete walls and perpendicular pilasters that serve as
shear walls, transferring seismic loads between the elevated levels and the foundation. At the
foundation, lateral loads are transmitted from the soil to the building by the piles and their
connections to the ground floor framing. The piles are embedded directly into concrete grade
beams without any distinct pile caps.
2.2 Operations Building
The Operations Building was originally constructed in 1969 and has a square plan with a side
dimension of 63 feet. The building has two stories above grade with a total height of
approximately 24 feet above the finished floor. Around the entire building, the roof extends 5
feet over the second floor and the second floor extends 5 feet over the first floor The perimeter
-
8/21/2019 Appendices E - G-utilization Ratio
11/169
pa811f4-8510.ai
Figure 3EXISTING PILE DETAILS
INCINERATOR AND OPERATIONS BUILDINGS
PILE SEISMIC EVALUATIONCITY OF PALO ALTO
-
8/21/2019 Appendices E - G-utilization Ratio
12/169
The roof of the building is constructed with a 24-inch-deep concrete waffle slab that has a
4-inch-thick deck with ribs spaced on a 30-inch grid. The waffle slab spans in two directions andis supported at the interior by 18-inch-square concrete columns and at the perimeter by tapered
concrete pilasters that are 18 inches thick and nearly 8 feet long at the base.
The second floor of the building is constructed with a 9-inch thick concrete slab that spans in two
directions to integral concrete beams that are supported down to the foundation by square
concrete columns at the interior and tapered concrete pilasters at the perimeter of the building.
The perimeter wall of the building is constructed in a non-traditional configuration with large
tapered pilasters that protrude out from the exterior of the building by several feet at the base.
Two pilasters are located along each side of the building away from the corners. The corners of
the building cantilever at each level. The exterior of the building is finished with glazing at the
second floor and a combination of glazing and corrugated steel siding at the first floor. Refer to
Figures 4 and 5 for the floor plan and elevations of the building as depicted on the record
drawings.
The first floor of the building is constructed with a 9-inch thick concrete slab that spans in two
directions to grade beams that are supported by driven concrete piles. The record drawings
indicate three different pile alternatives that include a 12-inch-diameter, steel pipe-encased
concrete pile; a 15-inch-diameter, steel corrugated-encased concrete tapered pile; and a 12-inch-
square precast, prestressed concrete pile. It is not known which pile type was installed. The piles
are grouped in clusters of four below the four interior columns and spaced apart individually below the perimeter pilasters. Figure 3 shows the three different pile alternatives that were
specified on the record drawings.
The lateral load resisting system of the building is comprised of rigid concrete diaphragms at the
roof and elevated floor levels that transfer lateral loads generated in an earthquake in proportion
to the stiffness of the vertical lateral load-resisting elements. The vertical lateral load-resisting
elements are comprised of the perpendicular pilasters at the perimeter of the building, which
serve as shear walls, transferring seismic loads between the elevated levels and the foundation.
At the foundation, lateral loads are transmitted between the building and the soil by the piles and
their connections to the first floor framing. The piles are embedded directly into the concrete
grade beams without any distinct pile caps
-
8/21/2019 Appendices E - G-utilization Ratio
13/169
pa811f5-8510.ai
Figure 4OPERATIONS BUILDING FLOOR PLAN
INCINERATOR AND OPERATIONS BUILDINGS
PILE SEISMIC EVALUATIONCITY OF PALO ALTO
-
8/21/2019 Appendices E - G-utilization Ratio
14/169
pa811f6-8510.ai.ai
Figure 5OPERATIONS BUILDING ELEVATIONS
INCINERATOR AND OPERATIONS BUILDINGS
PILE SEISMIC EVALUATIONCITY OF PALO ALTO
-
8/21/2019 Appendices E - G-utilization Ratio
15/169
3.0 SEISMIC EVALUATION
Seismic evaluation of structures follows standards or guides, such as American Society of Civil
Engineers (ASCE) 31-03 “Seismic Evaluation of Existing Buildings” or ASCE 41-06 “Seismic
Rehabilitation of Existing Buildings.” ASCE 31-03 is intended to serve as a guide for the
preliminary seismic evaluation for buildings and structural members, whereas, ASCE 41-06 is a
standard that contains provisions for seismic rehabilitation of existing buildings. However, either
of these standards may be used for the purposes of a seismic evaluation, which is defined as a
process or methodology of evaluating deficiencies in a building. Since ASCE 41-06 is more
current and more comprehensive, it was used for the seismic evaluation of the building piles. The
acceptance criteria for the materials will bebased upon the procedures set forth in ASCE 41-06
and the relevant material standards, such as American Concrete Institute (ACI) 318-08 “Building
Code Requirements for Structural Concrete.”
3.1 Seismic Evaluation Criteria
Two different types of criteria can be used to define the seismic demand for an evaluation,
namely, probabilistic seismic hazard criteria and deterministic seismic hazard criteria. This
evaluation uses a probabilistic approach because it is the standard for building evaluation and
design. A deterministic approach requires a specific seismologic study that is beyond the scope
of this evaluation. Such an approach is highly sensitive to the attenuation relationship used to
estimate ground motion realized at a site.
A probabilistic seismic hazard approach considers all potential earthquake sources that can
significantly contribute to ground shaking at the site. For a given probability of occurrence, there
is an associated ground acceleration. Building codes and seismic evaluation standards
incorporate this approach when establishing seismic demand levels, which are consistent with
the level of ground shaking that has a 10-percent probability of being exceeded in a 50-year time
period. This level of ground shaking may also be regarded as having a return period of 475 years.
Table 1 contains the seismic evaluation parameters that were used to establish the seismic design
criteria associated with the probabilistic seismic hazard for this evaluation.
Table 1 Seismic Evaluation ParametersS i i E l ti f th Pil S ti th I i t
-
8/21/2019 Appendices E - G-utilization Ratio
16/169
Table 1 Seismic Evaluation ParametersSeismic Evaluation of the Piles Supporting the Incinerator
and Operations Build ingsCity of Palo Alto
Parameter Value
Ss 1.50g
S1 0.62g
Fa 0.90
Fv 2.40
SDS 0.90gSD1 0.99g
Peak Ground Acceleration 0.46g
3.2 Material Properties and Strengths
As with any structural or seismic evaluation, two of the more important factors to consider are
the material properties and strengths. The properties and strengths of the materials were gathered
from a review of the record drawings for the Incinerator and Operations Buildings. No materialor destructive testing of any kind was employed to assess the actual in-situ strengths and
properties of the materials being evaluated. Where property values were not reported on the
original construction documents, values consistent with the age of construction and the materials
used were assumed. The properties used in the evaluation for the concrete piles are indicated in
Table 2.
Table 2 Material Properties - PilesSeismic Evaluation of the Piles Supporting the Incineratorand Operations Build ingsCity of Palo Alto
Property Value
Concrete
Compressive Strength, f’c 3,500 psi
Poisson’s Ratio 0.17
Modulus of Elasticity, E 3,150 ksi
Density 150 pcf
Steel Casing
-
8/21/2019 Appendices E - G-utilization Ratio
17/169
exposes the bottom side of foundation elements, which are located at least 3 feet below grade.
Employing material testing of the piles would involve a significant effort since the establishment
of material properties based on sampling and testing will require obtaining samples at numerouslocations.
Knowledge of the actual material strength can help establish higher capacities, but could also
result in reduced capacities. Typically constructed elements have higher capacities than those
assumed provided they are not in a deteriorated state. Decisions to employ testing are typically
made after an initial evaluation so as to avoid expending resources on a task that may not provide
any benefit. Further discussion of testing of materials is provided in Section 5.0 of this report.
3.3 Analysis Procedure
The evaluation of the building piles requires a structural analysis to estimate how the seismic load
demands impact the existing pile system. The capacity of the piles to resist horizontal loading is of
primary interest because shearing of the piles is considered to be a catastrophic type of failure
mechanism. Analysis procedures used in the seismic evaluation of buildings are typically of four types,
namely, linear static procedure (LSP), linear dynamic procedure (LDP), nonlinear static procedure (NSP),
and nonlinear dynamic procedure (NDP). The linear and nonlinear procedures differ in the assumptions
used for material behavior. Linear procedures assume that materials are elastic and respond in the same
manner for all load demand levels. Nonlinear procedures, on the other hand, attempt to capture the
varying response of materials when subjected to actions that create strains beyond the elastic limit.
Incorporating nonlinear and/or dynamic aspects into an analysis can increase the predictive accuracy, but
at significant cost in time and effort. Therefore, when appropriate, seismic evaluations are limited to
linear static procedures. Since the buildings in this evaluation are relatively short, dynamic effects are not
anticipated to have any significant contributions to a building’s response during an earthquake. Also, the
primary member capacity that is being evaluated is the shear capacity of the piles. The behavior of a
concrete pile, when loaded in shear is brittle and exhibits little to no nonlinear behavior. It is considered to
be a force-controlled action. Therefore, a linear static procedure was chosen for the analysis of both
buildings.
3.3.1 Mathematical Model
With any analysis procedure, a mathematical model that represents the structure is needed. For buildings,
mathematical models can be as simple as single vertical beam members or as complex as the actual
building itself with all of its members configured in a manner consistent with the structure. Accuracy will
be sacrificed using oversimplified models More refined mathematical models can yield significantly
-
8/21/2019 Appendices E - G-utilization Ratio
18/169
The modeling of the lateral support to the buildings, which is provided by the piles, significantly affects
the accuracy of the analysis. Most support conditions for seismic evaluations are assumed to be rigid, i.e.,
no flexibility, and do not account for any soil-pile interaction. To more accurately capture the response ofthe structure, the pile supports were modeled in a way that accounts for the anticipated soil-pile
interaction. This interaction yields somewhat longer building response periods, which can result in lower
seismic demand estimates compared to analyses that do not consider the soil-pile interaction. This
interaction is modeled by considering the connections of the building to the piles as linear spring
supports.
A graphic representation of the finite element model with the supports (piles) is provided on Figures 6
and 7 for the Incinerator and Operations Buildings, respectively.
3.3.2 Soil-Pile Interaction Modeling
As previously indicated, modeling of the soil-pile interaction can provide more accurate analysis results.
This approach dictates that the lateral support provided by the piles be modeled as springs. To incorporate
this behavior into the FEA, properties for these springs were needed. The spring stiffness is dependent
upon the pile size and stiffness, its assumed connection to the structure, and the properties of the soil that
the piles are embedded within. With all these factors considered, a geotechnical analysis was performed
for each building considering two different pile connections to the structure.
The two types of connections considered for the development of the soil-pile interaction properties are the
fixed-head and free-head conditions. The fixed-head condition assumes that the top of the pile remains
rigidly attached to the mat foundation and grade beam structure of the building. The free-head condition
assumes that the pile is free to rotate at the connection to the building. Each condition is significantly
different and results in different soil-pile interaction. Since actual conditions are neither fully rigid nor
fully free to rotate, the analysis solution is bounded by these two extreme conditions.
Since the installed pile type is not definitively known, the soil-pile analysis was carried out assuming that
the 12-inch-square concrete pile was installed. The stiffness of the piles was assumed to be 50 percent of
the full value to account for member cracking during actual load conditions.
The piles were analyzed using LPile, a specialized software package, to estimate the pile deflection, shear
force, and bending moment as a function of depth for piles at the Incinerator and Operations Buildings.
Also, analyses were run for both the fixed-head and free-head pile conditions. The soil was assumed to be
settled down from the bottom of the mat foundation and grade beams. This assumption is considered to
represent the softest condition that is likely to be present based on the available geotechnical data. The
results of the pile analyses are contained in Appendix B.
-
8/21/2019 Appendices E - G-utilization Ratio
19/169
pa811f7-8510.ai
Figure 6INCINERATOR BUILDING FINITE ELEMENT MODEL
INCINERATOR AND OPERATIONS BUILDINGS
PILE SEISMIC EVALUATIONCITY OF PALO ALTO
Linear
SupportSpring (Typ.)
-
8/21/2019 Appendices E - G-utilization Ratio
20/169
pa811f8-8510.ai
Figure 7OPERATIONS BUILDING FINITE ELEMENT MODEL
INCINERATOR AND OPERATIONS BUILDINGS
PILE SEISMIC EVALUATIONCITY OF PALO ALTO
Linear
SupportSpring (Typ.)
-
8/21/2019 Appendices E - G-utilization Ratio
21/169
The spring stiffness values used in the FEA of the buildings is indicated in Table 3. These values were
derived from the soil-pile analysis results. Since the analysis results are limited to lateral displacements of
1.0 inch and less, the reduced stiffness was estimated for larger displacements.
Table 3 Pile Lateral Spring Stiffness ValuesSeismic Evaluation of the Piles Supporting the Incineratorand Operations Build ingsCity of Palo Alto
Pile Head Condit ion Value
Incinerator Bui lding
Fixed 14.4 kip/in.
Free 4.8 kip/in.
Operations Building
Fixed 18.5 kip/in.
Free 7.3 kip/in.
It is important to note that the stiffness of the soil varies with the load applied. Generally, as the
lateral load on a pile increases, the soil stiffness decreases. However, the seismic load path is not
known. Therefore, it will not be known how or if soil stiffness degradation will occur.
Additionally, there are other foundation variables that will impact the building response. All of
these variables are difficult to assess at best. Therefore, it is advantageous to analyze the building
for the upper and lower bound soil properties to determine how sensitive the building response isto changes in assumed soil properties. For the buildings in this evaluation, it was determined that
the sensitivity to soil properties was rather low. The data provided by the geotechnical analysis is
considered to be a lower bounds estimate of the soil properties. At this lower bound estimate, the
building response was found to have a relatively short period. Therefore, it is not likely that the
softening effects of the soil will be substantial enough to allow for a reduced seismic load to the
building. As discussed previously, softer soil will generally increase the building period, which
can reduce the seismic demand.
Each building has concrete basement walls that can potentially work in conjunction with the
piles to resist lateral loads. The passive resistance of near surface soils is considered to be
substantially less intense than that which can be developed for piles The profile of the east and
-
8/21/2019 Appendices E - G-utilization Ratio
22/169
Operations Building are similar. Therefore, the contribution of passive resistance at the basement
walls has been neglected in this evaluation.
3.3.3 Load Combinations
The seismic evaluation of the buildings requires use of the ASCE 41-06 load combinations with
a slight increase to the load factor for the dead load. The dead load factor was increased to
account for the relative uncertainty of the incinerator and other permanent equipment weight.
The combinations used in this evaluation are presented in Table 4, where D represents the weight
of the permanent structure and equipment, E represents the seismic loads, and L is for floor liveload. Additionally, these load combinations were applied in both orthogonal directions for each
building.
Table 4 Load CombinationsSeismic Evaluation of the Piles Supporting the Incineratorand Operations Build ingsCity of Palo Alto
Load Combination Factors
1 0.9D + 1.0E
2 1.2D + 1.0L + 1.0E
4.0 FINDINGS
Three analyses were run for each building. Each analysis considered a different potential pile
connection type, namely, the fixed-head condition, free-head condition, and pinned support. As
discussed previously, the fixed-head and free-head conditions account for the soil-pile interaction
and assume rigid and free connections to the foundation, respectively. The pinned support
assumption is a rigid support that does not include any soil-pile interaction effects. This
condition was modeled as a baseline to compare the softening effects that modeling the soil-pile
interaction yield.
4.1 Incinerator Building
The analysis results of primary interest are the horizontal reactions at the supports. These
reactions are the shear demand on the piles. The results are summarized in Table 5. The analysis
results are presented in Appendix C. Note that the results presented in Appendix C are for an
-
8/21/2019 Appendices E - G-utilization Ratio
23/169
Table 5 Analysis ResultsSeismic Evaluation of the Piles Supporting the Incinerator
and Operations Build ingsCity of Palo Alto
Pile Connect ion TypeBuilding Period
(sec) Average PileShear (kips)
Maximum PileShear (kips)
Fixed Head 0.7 56 76
Free Head 1.2 52 69
Pinned Support 0.2 to 0.3 56 76
Based on the analysis results, the building periods for the fixed-head and free-head conditions
are clearly longer than those estimated assuming the pile connections are pinned supports, which
does not consider any soil-pile interaction. Unfortunately, the increased periods are not
substantial enough to achieve any significant reduction in the seismic load. Figure 8 is a response
spectra for the buildings, which is simply a graph that shows the building acceleration,
equivalent to the seismic load, in percent gravity as a function of the building period. Building
periods greater than 1.10 seconds will generally realize a reduced seismic load because it isoffset from the general earthquake period. If the pile connections are free to rotate, the building
period is about 1.2 seconds and allows for a reduction in seismic load of about 7 percent. Since
this reduction is small compared to the large pile shear forces, the results for the fixed head are
used.
The total weight of the building is estimated to be 9,400 kips. The estimated seismic horizontal
force for the entire building is 8,460 kips. No system reduction factors were considered, sinceloading of the piles in shear is the primary means to transfer lateral load between the soil and the
building.
4.1.1 Pile Capacity Check
Since the pile type that is installed is not known, all three alternatives indicated on the record
drawings were checked against the seismic pile shear demand that was estimated in the analysis.The pile shear capacities were estimated in accordance with the provisions set forth in ACI 318-
08. In estimating the pile shear capacity, 50 percent of the average axial compression load, which
includes seismic loads, was considered. The results are presented in Table 6.
Th il h i l l d i i d i f (Phi f ) l
-
8/21/2019 Appendices E - G-utilization Ratio
24/169
1.00
1.20
1.40
1.60
0.00
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00
0.20
0.40
0.60
.
Sa (g) vs. T (sec)
T (sec)
Sa (g)
-
8/21/2019 Appendices E - G-utilization Ratio
25/169
Table 6 Pile Shear Capacity Check - Incinerator BuildingSeismic Evaluation of the Piles Supporting the Incineratorand Operations Build ingsCity of Palo Alto
Pile TypePile Shear
Demand (kips)Pile Shear
Capacity (kips)Demand-Capacity
Ratio
12-inch-squareprestressed concrete
56 33 1.7
15-inch-diameterconcrete
56 33 1.7
12-inch-diametersteel-encased concrete
56 24 2.3
Also, very little research has been done to more accurately assess the shear capacity of steel-
encased concrete piles.
The check of the piles suggests that the demand-capacity ratio (DCR) can be as high as 2.3,
which is a clear indication that the piles lack the needed shear strength to resist the seismic
loading. At this deficiency level, the piles are anticipated to shear off.
4.2 Operations Building
The analysis results of primary interest are the horizontal reactions at the supports. These
reactions are the shear demand on the piles. The results are summarized in Table 7. The analysis
results are presented in Appendix C. Note that the results presented in Appendix C are for an
event with a 2-percent probability of exceedance in a 50-year time period. This evaluation is for
an event with a 10-percent probability of exceedance in 50-years. Therefore, the results in Table
7 have been reduced by a factor of 1.5.
Table 7 Analysis ResultsSeismic Evaluation of the Piles Supporting the Incineratorand Operations Build ingsCity of Palo Alto
Pile Connect ion TypeBuilding Period
(sec) Average PileShear (kips)
Maximum PileShear (kips)
Fixed Head 0.6 55 59
Free Head 0.9 55 57
Pinned S pport 0 2 55 61
-
8/21/2019 Appendices E - G-utilization Ratio
26/169
The total weight of the building is estimated to be 3,068 kips. The estimated seismic horizontal
force for the entire building is 2,760 kips. No system reduction forces were considered, since
loading of the piles in shear is the primary means to transfer lateral load between the soil and the building.
4.2.1 Pile Capacity Check
Since the pile type that is installed is not known, all three alternatives indicated on the record
drawings were checked against the seismic pile shear demand that was estimated in the analysis.
The pile shear capacities were estimated in accordance with the provisions set forth in ACI 318-
08. In estimating the pile shear capacity, 50 percent of the average axial compression load, which
includes seismic loads, was considered. The results are presented in Table 8.
Table 8 Pile Shear Capacity Check - Operations BuildingSeismic Evaluation of the Piles Supporting the Incineratorand Operations Build ingsCity of Palo Alto
Pile TypePile Shear
Demand (kips)Pile Shear
Capacity (kips)Demand-Capacity
Ratio
12-inch-squareprestressed concrete
55 37 1.5
15-inch-diameter concrete 55 36 1.5
12-inch-diametersteel-encased concrete
55 27 2.0
The pile shear capacity was calculated assuming a capacity reduction factor (Phi-factor) equal to
unity. This check is considered to be a force-controlled action and no ductility or redundancy
was considered in the evaluation. The shear capacity of the steel-encased concrete was assumed
to be limited to the lower of the strength of the steel casing or the concrete. The steel is relatively
thin (less than 1/4-inch) and the condition is not known. Also, very little research has been done
to more accurately assess the shear capacity of steel-encased concrete piles.
The check of the piles suggests that the DCR can be as high as 2.0, which is a clear indication
that the piles lack the needed shear strength to resist the seismic loading. At this deficiency level,
the piles are anticipated to shear off.
-
8/21/2019 Appendices E - G-utilization Ratio
27/169
Lateral displacement of the building can be significant with excessive collateral and structural
damage. Rotation of the building in plan is also possible.
If the piles had sufficient strength to resist the calculated demands, building lateral deflections
would be significant, being on the order of several inches. At these deflection levels, damage to
connecting piping and other utilities should be anticipated. Additionally, the building may
experience permanent displacement and significant foundation damage.
The results obtained assume that the soil is capable of delivering the large seismic forces that
were estimated in this evaluation. Also, the buildings were not analyzed to evaluate overturning
effects that might include uplift on piles, compression on the piles, and vertical rotation of the
building. Such effects can lead to significant structural and collateral damage. For this
evaluation, net uplift was not identified in any of the analysis results. Furthermore, ASCE 31-03
allows for significant reduction in the calculated overturning actions at the foundation when
evaluating the foundation members.
5.0 RECOMMENDATIONS
Based on the results of the evaluation, it is clear that the existing pile systems for both buildings
lack sufficient shear capacity to resist anticipated seismic loads from an earthquake having a
return period of 475 years. Failure of the pile system can lead to unpredictable behavior and
movement of the building. The foundation can be rehabilitated to provide the necessary shear
capacity to prevent such behavior. Federal Emergency Management Agency (FEMA) 547
“Techniques for the Seismic Rehabilitation of Existing Buildings” contains seismic retrofit
techniques and strategies for the vast majority of building vulnerabilities, including foundation
deficiencies. The cost of foundation rehabilitation is relatively high and disruptive. Therefore,
the consequences of foundation failure should be carefully evaluated to determine whether large
movements are unacceptable. The cost to repair damaged utilities and connections to the building
should be considered. If the foundation system were rehabilitated to resist the seismic shear
demands, displacement will still be relatively large and may still impose failures upon the building connections and utilities.
The basic vulnerability identified with the foundation is the lack of pile shear capacity. The
following strategies and variations thereof are available to address this type of deficiency:
-
8/21/2019 Appendices E - G-utilization Ratio
28/169
to the existing piles. A new pile system that is excessively stiff compared to the existing
piles may underutilize the existing pile system.
Removal of a significant amount of mass from the building to reduce the seismic load
demand. Reduction of mass will directly reduce the potential seismic load transferred to
the foundation. The high seismic base shears calculated in this evaluation will practically
eliminate this strategy as a viable alternative.
Although obvious, building replacement could be a viable alternative. If the cost to seismically
retrofit an older building is a substantial percent of the building replacement value, it may beeconomically advantageous to decommission the facility and replace it with a more efficient
system and structure. The building is already more than 40 years old and will require increased
maintenance in the future as the building continues age.
5.1 Incinerator Building
Addition of new concrete piles to supplement the existing foundation is recommended to prevent
shear failure of the existing pile system. Piles can be added around the perimeter of the building
and connected to a new extension of the foundation. It is estimated that a minimum addition of
forty 18-inch-diameter concrete piles will be required to achieve the necessary shear strength.
More piles may need to be added to address bending capacity limitations of the existing pile
system. The existing piles are 12 to 15 inches in diameter. Addition of any new piles will require
a minimum spacing of 4.5 feet from new and existing piles. The spacing of the existing piles
around the perimeter of the building is approximately 6 to 11 feet on center. Based on theexisting spacing, it appears that the addition of new piles around the perimeter is feasible. Piles
can also be added at the interior of the building; however, this will require large equipment
access, which might be limited by the size of the roll-up doors. A conceptual depiction of the
addition of new piles is shown on Figures 9 and 10 for pile additions made at the existing fins
and perimeter slab, respectively.
The existing conditions around the perimeter of the building will impose restrictions ornecessitate additional work so that piles can be successfully installed. The ash system, sludge
storage tanks, and chemical storage along the north and south sides of the building will limit
accessibility and complicate construction.
-
8/21/2019 Appendices E - G-utilization Ratio
29/169
New Pile Cap
Extension asrequired
New Piles, Typ 4
at each existingpilaster
-
8/21/2019 Appendices E - G-utilization Ratio
30/169
New Pile Cap
Extension as
required
New Piles, atSlab Edge
-
8/21/2019 Appendices E - G-utilization Ratio
31/169
Removal of mass can reduce the seismic load to the foundation. However, to make any
meaningful difference for the Incinerator Building, the mass would need to be able to be reduced
by approximately 60 percent. The weight of the ground floor alone exceeds the weight that
would not overload the piles in shear. Therefore, it is not practical to reduce the building weight
alone. To do so would require complete demolition of the building and foundation. A
combination of mass reduction with pile addition can help reduce the total number of
supplemental piles required.
5.2 Operations BuildingAddition of new concrete piles to supplement the existing pile foundation is recommended to
mitigate the identified vulnerability. It is estimated that a minimum addition of twelve 18-inch-
diameter concrete piles will be required to achieve the necessary shear strength. Additional piles
may need to be provided to address bending capacity limitations of the existing pile system. The
existing piles around the perimeter of the building are located below the existing fin walls. Based
on the existing locations, it appears that the addition of new piles around the perimeter isfeasible. Addition of piles at the interior plan of the building does not appear feasible since
access of heavy construction equipment is not practical. A conceptual depiction of the addition
of new piles will be similar to that shown on Figure 9.
The building is completely surrounded at the exterior by a shallow landscaping pond. Installation
of new piles will require the pond to be drained. Repairs to the pond system will likely be
required after any construction work.
Mass reduction of the building would necessitate demolition of the elevated levels and
reconstruction if this strategy were to be employed alone. Given the size of the building, mass
reduction does not appear to be a practical strategy to implement.
6.0 CONCLUSIONS
The seismic evaluation of the existing pile foundations for the Incinerator and Operations
Buildings reveals that the existing piles lack adequate shear capacity to safely resist the seismic
loads imparted by an earthquake with a level of ground shaking that has a 10-percent probability
of being exceeded in a 50-year time frame. Under this scenario, the piles are anticipated to shear
-
8/21/2019 Appendices E - G-utilization Ratio
32/169
building. If such behavior is determined to be unacceptable, rehabilitation of the existing
foundation can be achieved by adding new concrete piles with associated pile cap extensions
around the perimeter of each building. A rough order of magnitude cost for construction isestimated to be $1.1 million for both buildings. This estimate assumes that the building is
rehabilitated to meet the life safety performance level that is consistent with the design of new
buildings. Construction will involve mobilization, excavation around the buildings, installation
of additional piles, casting of pile caps, backfilling, repairing/restoring existing construction, etc.
A foundation rehabilitation design will require preparation of engineering plans and perhaps
additional investigation into the existing soils below each building. It should be emphasized thata rehabilitated foundation with adequate shear capacity may still result in relatively large lateral
displacements. Soil improvement may be a necessary part of a foundation rehabilitation design to
help reduce lateral displacements that may be deemed intolerable. The rough cost of soil
improvement techniques, such as injection grouting, has not been considered in this evaluation.
The building replacement cost for each building should be considered before embarking on a
rehabilitation program, as it may be economically advantageous to replace the existing buildings
with new construction that will have considerably longer service lives.
-
8/21/2019 Appendices E - G-utilization Ratio
33/169
City of Palo Alto
APPENDIX A - PHOTOGRAPHS
-
8/21/2019 Appendices E - G-utilization Ratio
34/169
Figure A-1
Incinerator Bldg: The east elevation. The walls of the building are constructed with steel-framed wall
panels and cast-in-place concrete.
-
8/21/2019 Appendices E - G-utilization Ratio
35/169
Figure A-3
Incinerator Bldg: The west elevation.
-
8/21/2019 Appendices E - G-utilization Ratio
36/169
Figure A-5
Incinerator Bldg: View of the roof looking from the west to the east. The roof is framed with a concrete slab
and beam system.
-
8/21/2019 Appendices E - G-utilization Ratio
37/169
Figure A-7
Incinerator Bldg: Entrance stair to the basement where access to the bottom of the furnaces is provided.
-
8/21/2019 Appendices E - G-utilization Ratio
38/169
Figure A-9
Incinerator Bldg: Solids dewatering equipment located at the high mezzanine level that occurs on the
south side of the interior of the building.
-
8/21/2019 Appendices E - G-utilization Ratio
39/169
Figure A-11
Incinerator Bldg: View of the concrete columns that support the roof level and high mezzanine down to
the foundation.
-
8/21/2019 Appendices E - G-utilization Ratio
40/169
Figure A-13
Incinerator Bldg: Interior of the building at ground level just north of the furnaces.
-
8/21/2019 Appendices E - G-utilization Ratio
41/169
Figure A-15
Operations Bldg: Northeast elevation. The exterior of the building is framed with steel-framed siding
panels and cast-in-place concrete cladding and fin walls.
-
8/21/2019 Appendices E - G-utilization Ratio
42/169
Figure A-17
Operations Bldg: Southwest elevation.
-
8/21/2019 Appendices E - G-utilization Ratio
43/169
Figure A-19
Operations Bldg: Corner of the building with concrete cladding. The floors are framed with a cast-in-place
concrete waffle slab system.
-
8/21/2019 Appendices E - G-utilization Ratio
44/169
City of Palo Alto
APPENDIX B - SOIL-PILE INTERACTION ANALYSIS RESULTS
Jan 13, 2011, ground settled from pile cap
-
8/21/2019 Appendices E - G-utilization Ratio
45/169
figure titles_run01132011.docx 1 of 1 1/17/11, 8:07 AM
LPILE Results where ground has settled away from bottom of pile caps
Fi gur e 5a - Case 2B0 - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fr ee Head, Load vs Top Def l ect i on
Fi gur e 5b - Case 2B0 - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Free Head, Def l ect i on vs Dept h
Fi gur e 5c - Case 2B0 - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fr ee Head, Shear vs Dept h
Fi gur e 5d - Case 2B0 - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fr ee Head, Moment vs Dept h
Fi gur e 5e - Case 2B0 - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Free Head, Soi l React i on
Fi gur e 9a - Case 4D0 - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Free Head, Load vs Top Def l ect i on
Fi gur e 9b - Case 4D0 - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Free Head, Def l ect i on vs Dept h
Fi gur e 9c - Case 4D0 - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Free Head, Shear vs Dept h
Fi gur e 9d - Case 4D0 - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fr ee Head, Moment vs Dept h
Fi gur e 9e - Case 4D0 - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Free Head, Soi l React i on
Fi gur e 13a - Case 2B0x - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Load vs Top
Def l ect i on
Fi gur e 13b - Case 2B0x - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Def l ect i on vs Dept h
Fi gur e 13c - Case 2B0x - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Shear vs Dept h
Fi gur e 13d - Case 2B0x - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Moment vs Dept h
Fi gur e 13e - Case 2B0x - Oper Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Soi l React i on
Fi gur e 17a - Case 4D0x - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Load vs Top
Def l ect i on
Fi gur e 17b - Case 4D0x - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Def l ect i on vs Dept h
Fi gur e 17c - Case 4D0x - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Shear vs Dept h
Fi gur e 17d - Case 4D0x - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Moment vs Dept h
Fi gur e 17e - Case 4D0x - I nci Bl dg, Sof t Gr ound, 12i n SQ Pi l e, 50% Gr oss EI , Fi xed Head, Soi l React i on
Jan 13, 2011, ground settled from pile cap
2
-
8/21/2019 Appendices E - G-utilization Ratio
46/169
L a t e r a l L o a d
( k i p s )
1
2
3
4
5
6
7
8
9
1 0
1 1
1 2
Jan 13, 2011, ground settled from pile cap
-
8/21/2019 Appendices E - G-utilization Ratio
47/169
Lateral Deflection (in)
D e p t h
( f t )
-0.1 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0
5
1
0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
-
8/21/2019 Appendices E - G-utilization Ratio
48/169
Shear Force (kips)
D e p t h
( f t )
-8 -6 -4 -2 0 2 4 6 8 10 0
5
1
0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
-
8/21/2019 Appendices E - G-utilization Ratio
49/169
Bending Moment (in-kips)
D e p t h
( f t )
-100 -50 0 50 100 150 200 250 300 350 400 450 500 0
5
1
0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
M bili d S il R ti (lb /i )
-
8/21/2019 Appendices E - G-utilization Ratio
50/169
Mobilized Soil Reaction (lbs/in)
D e p t h
( f t )
-300 -250 -200 -150 -100 -50 0 50 100 150 200 0
5
1
0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
8
-
8/21/2019 Appendices E - G-utilization Ratio
51/169
L a t e r a l L o a d
( k i p s )
. 5
1
1 .
5
2
2 .
5
3
3 .
5
4
4 .
5
5
5 .
5
6
6 .
5
7
7 .
5
Jan 13, 2011, ground settled from pile cap
Lateral Deflection (in)
-
8/21/2019 Appendices E - G-utilization Ratio
52/169
Lateral Deflection (in)
D e p t h
( f t )
-0.1 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Shear Force (kips)
-
8/21/2019 Appendices E - G-utilization Ratio
53/169
Shear Force (kips)
D e p t h
( f t )
-8 -6 -4 -2 0 2 4 6 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Bending Moment (in-kips)
-
8/21/2019 Appendices E - G-utilization Ratio
54/169
Bending Moment (in kips)
D e p t h
( f t )
-100 -50 0 50 100 150 200 250 300 350 400 450 500 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Mobilized Soil Reaction (lbs/in)
-
8/21/2019 Appendices E - G-utilization Ratio
55/169
( )
D e p t h
( f t )
-400 -350 -300 -250 -200 -150 -100 -50 0 50 100 150 200 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
2 6
-
8/21/2019 Appendices E - G-utilization Ratio
56/169
L a t e r a l L o a d
( k i p s )
2
4
6
8
1 0
1 2
1 4
1 6
1 8
2 0
2 2
2 4
Jan 13, 2011, ground settled from pile cap
Lateral Deflection (in)
-
8/21/2019 Appendices E - G-utilization Ratio
57/169
D e p t h
( f t )
-0.1 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Shear Force (kips)
-
8/21/2019 Appendices E - G-utilization Ratio
58/169
D e p t h
( f t )
-10 -5 0 5 10 15 20 25 30 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Bending Moment (in-kips)
-
8/21/2019 Appendices E - G-utilization Ratio
59/169
D e p t h
( f t )
-1200 -1000 -800 -600 -400 -200 0 200 400 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Mobilized Soil Reaction (lbs/in)
-
8/21/2019 Appendices E - G-utilization Ratio
60/169
D e p t h
( f t )
-500 -450 -400 -350 -300 -250 -200 -150 -100 -50 0 50 100 150 200 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
1 9
-
8/21/2019 Appendices E - G-utilization Ratio
61/169
L a t e r a l L o a d
( k i p s )
2
3
4
5
6
7
8
9
1 0
1 1
1 2
1 3
1 4
1 5
1 6
1 7
1 8
Jan 13, 2011, ground settled from pile cap
Lateral Deflection (in)
-
8/21/2019 Appendices E - G-utilization Ratio
62/169
D e p t h
( f t )
-0.1 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Shear Force (kips)
-
8/21/2019 Appendices E - G-utilization Ratio
63/169
D e p t h
( f t )
-8 -6 -4 -2 0 2 4 6 8 10 12 14 16 18 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Bending Moment (in-kips)
-
8/21/2019 Appendices E - G-utilization Ratio
64/169
D e p t h
( f t )
-1200 -1000 -800 -600 -400 -200 0 200 400 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
Jan 13, 2011, ground settled from pile cap
Mobilized Soil Reaction (lbs/in)
500 450 400 350 300 250 200 150 100 50 0 50 100 150 200
-
8/21/2019 Appendices E - G-utilization Ratio
65/169
D e p t h
( f t )
-500 -450 -400 -350 -300 -250 -200 -150 -100 -50 0 50 100 150 200 0
5
1 0
1 5
2 0
2 5
3 0
3 5
4 0
City of Palo Alto
APPENDIX C EVALUATION CALCULATIONS
-
8/21/2019 Appendices E - G-utilization Ratio
66/169
APPENDIX C - EVALUATION CALCULATIONS
-
8/21/2019 Appendices E - G-utilization Ratio
67/169
-
8/21/2019 Appendices E - G-utilization Ratio
68/169
-
8/21/2019 Appendices E - G-utilization Ratio
69/169
-
8/21/2019 Appendices E - G-utilization Ratio
70/169
-
8/21/2019 Appendices E - G-utilization Ratio
71/169
-
8/21/2019 Appendices E - G-utilization Ratio
72/169
-
8/21/2019 Appendices E - G-utilization Ratio
73/169
-
8/21/2019 Appendices E - G-utilization Ratio
74/169
-
8/21/2019 Appendices E - G-utilization Ratio
75/169
-
8/21/2019 Appendices E - G-utilization Ratio
76/169
-
8/21/2019 Appendices E - G-utilization Ratio
77/169
-
8/21/2019 Appendices E - G-utilization Ratio
78/169
-
8/21/2019 Appendices E - G-utilization Ratio
79/169
-
8/21/2019 Appendices E - G-utilization Ratio
80/169
-
8/21/2019 Appendices E - G-utilization Ratio
81/169
-
8/21/2019 Appendices E - G-utilization Ratio
82/169
-
8/21/2019 Appendices E - G-utilization Ratio
83/169
-
8/21/2019 Appendices E - G-utilization Ratio
84/169
-
8/21/2019 Appendices E - G-utilization Ratio
85/169
-
8/21/2019 Appendices E - G-utilization Ratio
86/169
-
8/21/2019 Appendices E - G-utilization Ratio
87/169
-
8/21/2019 Appendices E - G-utilization Ratio
88/169
-
8/21/2019 Appendices E - G-utilization Ratio
89/169
-
8/21/2019 Appendices E - G-utilization Ratio
90/169
-
8/21/2019 Appendices E - G-utilization Ratio
91/169
-
8/21/2019 Appendices E - G-utilization Ratio
92/169
-
8/21/2019 Appendices E - G-utilization Ratio
93/169
-
8/21/2019 Appendices E - G-utilization Ratio
94/169
-
8/21/2019 Appendices E - G-utilization Ratio
95/169
-
8/21/2019 Appendices E - G-utilization Ratio
96/169
-
8/21/2019 Appendices E - G-utilization Ratio
97/169
-
8/21/2019 Appendices E - G-utilization Ratio
98/169
-
8/21/2019 Appendices E - G-utilization Ratio
99/169
-
8/21/2019 Appendices E - G-utilization Ratio
100/169
-
8/21/2019 Appendices E - G-utilization Ratio
101/169
-
8/21/2019 Appendices E - G-utilization Ratio
102/169
-
8/21/2019 Appendices E - G-utilization Ratio
103/169
-
8/21/2019 Appendices E - G-utilization Ratio
104/169
-
8/21/2019 Appendices E - G-utilization Ratio
105/169
-
8/21/2019 Appendices E - G-utilization Ratio
106/169
-
8/21/2019 Appendices E - G-utilization Ratio
107/169
City of Palo Alto Long Range Facilities Plan for the RWQCP
APPENDIX F – INCINERATORS – SEISMIC EVALUATION
TECHNICAL MEMORANDUM
-
8/21/2019 Appendices E - G-utilization Ratio
108/169
-
8/21/2019 Appendices E - G-utilization Ratio
109/169
CITY OF PALO ALTO
LONG RANGE FACILITIES PLAN FOR THE
RWQCP
TECHNICAL MEMORANDUMINCINERATORS – SEISMIC EVALUATION
DRAFT
City of Palo Alto
LONG RANGE FACILITIES PLAN FOR THE RWQCP
TECHNICAL MEMORANDUMINCINERATORS – SEISMIC EVALUATION
-
8/21/2019 Appendices E - G-utilization Ratio
110/169
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION AND SUMMARY ........................................................................ 1
2.0 BACKGROUND ......................................................................................................... 2
2.1 Existing Facilities............................................................................................. 22.2 Operations ........................................................................................................ 3
3.0 SEISMIC EVALUATION ........................................................................................... 3
3.1 Seismic Evaluation Criteria ............................................................................. 33.2 Historic Seismicity ........................................................................................... 8
3.3 Procedures ........................................................................................................ 8
4.0 CONCLUSIONS........................................................................................................ 22
LIST OF APPENDICES
A – Incinerator PhotographsB – Incinerator Seismic Stability Evaluation
LIST OF TABLES
Table 1 Faults Near City of Palo Alto ............................................................................. 6
Table 2 Seismic Evaluation Parameters per ASCE 7-05 ................................................ 7Table 3 Material Properties – Steel and Concrete ......................................................... 10
Table 4 Material Properties – Refractory Brick ............................................................ 11
Table 5 Hearth Analysis Temperatures ......................................................................... 14Table 6 Hearth Gravity Loads ....................................................................................... 14
Table 7 Hearth Loads and Load Combinations ............................................................. 15
Table 8 Normal Radial Stresses S 21
LIST OF FIGURES
Figure 1 Cross-sectional View of the Incinerator ............................................................. 4
Figure 2 Detailed Section of a Typical Elevated Hearth .................................................. 5
Figure 3 Map of the Peak Ground Acceleration for The 1989 Loma Prieta Earthquake.Courtesy Of The California Geological Survey ................................................. 9
Figure 4 The Finite Element Model of the Incinerator for the Anchorage Evaluation .. 11
-
8/21/2019 Appendices E - G-utilization Ratio
111/169
Figure 5 The Finite Element Model Developed for the Evaluation of the Hearths ........ 13
Figure 6 Depiction of Stresses Reported in the Finite Element Analysis ....................... 16Figure 7 Radial and Circumferential Stresses for Load Combination No. 1 (LC100) ... 17
Figure 8 Radial and Circumferential Stresses for Load Combination No. 2 (LC200) ... 18
Figure 9 Radial and Circumferential Stresses for Load Combination No. 3 (LC300). .. 19
Figure 10 Radial and Circumferential Stresses for Load Combination No. 5 (LC500) ... 20
Technical Memorandum
INCINERATORS – SEISMIC EVALUATION
1.0 INTRODUCTION AND SUMMARY
The City of Palo Alto (City) operates two multi-hearth furnaces (MHFs) to incinerate solids at
-
8/21/2019 Appendices E - G-utilization Ratio
112/169
The City of Palo Alto (City) operates two multi hearth furnaces (MHFs) to incinerate solids at
the Regional Water Quality Control Plant (RWQCP). The incinerators were originally fabricated
in 1971 and began operation in 1972 and are located within the Incinerator Building, which is a
concrete-framed building with a concrete steel-framed roof. The plant is located within a region
that is well known for its potential for large earthquakes. Therefore, buildings and large
equipment may, at any time, be subjected to strong ground motions without warning. As part of
the Long Range Facilities Plan (LRFP), the City requested Carollo Engineers, Inc. (Carollo) to
provide a description of the MHFs, an overview of the approach and procedures used, and
recommendations for addressing potential deficiencies identified.
Over the years, the design of buildings and non-building structures has improved considerably
with the advancement of knowledge within the fields of structural engineering and seismology.
As a result, structures designed and constructed within the last 20 to 30 years may be expected to
perform better than those constructed in an earlier time period. Furthermore, design standards
and guides for special structures, such as steel tanks and silos, have also evolved over the years
to include necessary seismic design provisions. The incinerators are considered to be a special
type of structure that is quite different than a typical tank due to the internal operations, materials
of construction, and the service conditions to which the structure will be subjected. As a result,
one would expect that a specific standard exists to address structural concerns, especially relatedto seismic design. However, due to the fact that solids incineration using MHFs has been
superceded by other technologies, such a standard did not develop. Additionally, the MHFs are
more than 40 years old. Consequently, given the age of the MHFs and lack of a design standard,
there is a need to more clearly understand what the seismic-related risks might be to both the life
safety of plant operators and to the operation of the solids handling process. Carollo was scoped
to evaluate the MHFs to identify potential seismic-related deficiencies of the structural
components.
The seismic evaluation of the incinerators included a visit to the site on November 3, 2010, a
2.0 BACKGROUND
2.1 Existing Facilities
The two incinerators are located within the Incinerator Building and are approximately 25 feet inheight and nearly 19 feet in diameter. Furnace No.1 and Furnace No. 2 (the incinerators) are
situated along the north side of the building, with Furnace No. 1 closest to the west side of the
-
8/21/2019 Appendices E - G-utilization Ratio
113/169
g g,
building. The incinerators are constructed with an exterior steel shell that is 3/8-inch thick. The
shell is circumferentially spliced together with three bolted, steel plate sections that are of equal
length. The interior of each incinerator is comprised of six hearths. Each hearth is constructed
with a low-profile sprung arch of refractory brick material that relies upon the compressive
pressure between each brick to maintain stability against collapse. The supporting compressive
pressure between each brick is comprised of two components, namely, the weight of the bricks
and the interlocking pressure created by carefully fitting the bricks together during construction,
the latter pressure being difficult to estimate. The interior perimeter is constructed with a single
4.5-inch wide layer of refractory brick and a 9-inch thick layer of castable refractory material for
insulation, creating a total insulation thickness of 13.5 inches. This insulation also serves to
vertically support all of the hearth levels. The exterior shell is reinforced with an additional5/8-inch by 6-inch tall steel plate at each hearth level to provide the necessary resistance to the
thrust loading generated by the arch action of the hearth and the thermal expansion caused by
heating within. The reinforcing rings are spliced with bolts. The top and bottom of the
incinerators are framed with steel framing that is insulated with castable refractory.
A mechanical shaft is located at the center of the incinerator. The central shaft is fitted with
rabble arms at each hearth level to move the solids through the incinerator. The shaft is insulatedwith castable refractory. The hearth levels have alternating openings to allow the passage of
solids from the top to the bottom. The openings alternate from the center to the perimeter at each
subsequent hearth.
Each incinerator is mounted to the building slab at grade level with six pairs of 1.5-inch diameter
anchor bolts. For access to equipment, an 8-foot deep pit is located below the bottom of the
incinerators. Additional concrete piers provide support to the center drive mechanism andmechanical equipment. The foundation of the building is comprised of concrete piles that extend
down into the site soils.
2.2 Operations
The plant currently operates the incinerators on an annual alternating cycle where one is online
for a year while the other is off-line for maintenance and repair. At the time of the site visit in
November of 2010, Furnace No. 1 was in operation. Solids are introduced into the incinerator atthe top on a conveyor belt after passing through a belt-press filter. The solids are heated at
different temperatures at each hearth level to induce drying and combustion. The rabble arms
-
8/21/2019 Appendices E - G-utilization Ratio
114/169
different temperatures at each hearth level to induce drying and combustion. The rabble arms
constantly spread and move the solids across the hearth surface. Ash is collected at the bottom
hearth and extracted. The maximum normal operating temperature was reported by plant staff to
be approximately 1,500 degrees Fahrenheit, with spikes occasionally reaching 2,000 degrees
Fahrenheit. Heating is achieved by burning natural gas at select hearth levels.
Start-up and shutdown of the incinerator is performed over multiple days to avoid spalling from
boiling water and to avoid thermal shock to the interior materials, which can cause differential
expansion/contraction that can potentially destabilize the refractory brick resulting in a hearth
collapse. The refractory brick does not have the capacity to resist tensile forces since there is no
physical bond or connection between the individual bricks. This is understood to be an inherent
risk of operating a MHF. During heating the hearths expand, but are restrained by the exterior
steel shell, which causes the hearth to displace vertically at the center.
Excerpts from the record drawings of the incinerators are provided on Figures 1 and 2.
Photographs of the incinerators are contained in Appendix A.
3.0 SEISMIC EVALUATION
Seismic evaluation of structures typically follows a standard or guide, such as American Societyof Civil Engineers (ASCE) 31, “Seismic Evaluation of Existing Buildings.” Non-building
structures may have a specific design standard that can be used as a guide, such as American
Water Works Association (AWWA) D100 for prestressed concrete tanks. However, for the
incinerators, no such standard exists. Therefore, the seismic hazard used in the assessment and
the acceptance criteria for the materials will be based upon the principles contained in ASCE 7-
05, “Minimum Design Loads for Buildings and Other Structures,” and the relevant current
material standards, respectively.
3.1 Seismic Evaluation Criteria
-
8/21/2019 Appendices E - G-utilization Ratio
115/169
-
8/21/2019 Appendices E - G-utilization Ratio
116/169
Figure 2 Detailed Section of a Typical Elevated Hearth
California is in a region of the world that has experienced significant seismic events and is
therefore an area of high seismic risk. The primary source of California’s seismicity is derived
from its location, which straddles the North American and Pacific Plates, which are moving in
opposite longitudinal directions. The primary interface between the two plates is the San Andreas
Fault. The plate interactions also have created a host of complementary earthquake faults that
generally are parallel to the San Andreas Fault. Examples of these faults include the Newport-
Inglewood Fault in Southern California, the Hayward Fault in the Bay Area, and the Garlock
Fault in the Owens Valley.
Some significant historic damaging earthquakes include the 1857 Fort Tejon earthquake on the
San Andreas Fault, the 1906 Great San Francisco earthquake, the 1971 San Fernando earthquake,
the 1989 Loma Prieta earthquake, and the 1994 Northridge earthquake.
Some substantial faults that may influence the RWQCP site are indicated in Table 1. These faults
are those that are known to have been active within the last 11,000 years. Note that this list is not
meant to be comprehensive. Bear in mind that earthquakes are not confined to known or listed
faults. Seismologists are still actively identifying and cataloging new faults that were previously
unknown. The thrust fault that generated the 1994 Northridge earthquake was one such fault.
Two different types of criteria can be used to define the seismic demand for an evaluation,
Table 1 Faults Near City of Palo Alto (1)
Fault Name Distance from RWQCP Site (miles)
Monte Vista-Shannon 6.0
San Andreas 8.0
Hayward-Rodgers Creek 11.0
Calaveras 15 0
-
8/21/2019 Appendices E - G-utilization Ratio
117/169
Calaveras 15.0
San Gregorio 18.0
Sargent 24.0
Greenville 29.0
3.1.1 Probabilistic Criteria
A probabilistic seismic hazard approach considers all potential earthquake sources that can
significantly contribute to ground shaking at the site. For a given probability of occurrence, there
is an associated ground acceleration. Building codes and seismic evaluation standards
incorporate this approach when establishing seismic demand levels, which are consistent with
the level of ground shaking that has a 10-percent probability of being exceeded in a 50-year time period. This level of ground shaking may also be regarded as having a return period of 475 years.
Table 2 contains the seismic evaluation parameters obtained from ASCE 7-05.These parameters
were used to establish the seismic design criteria associated with the probabilistic seismic hazard
for this evaluation.
3.1.2 Deterministic Criteria
A deterministic approach is not used in this evaluation as it is beyond the scope of work.
Development of a deterministic approach requires a specific geologic and seismologic study. A
deterministic approach considers an earthquake of a particular magnitude that might occur along
a particular segment of a fault at a specified distance from the site. The particular earthquake
considered in a deterministic approach may be considered as the maximum credible event or an
event that has a greater potential to occur. Such an approach is often more suited for qualitativeevaluations, such as emergency response studies, or worst-case scenarios, as such events are less
likely to occur in any given time period and can result in significantly higher level forces for an
evaluation
Table 2 Seismic Evaluat ion Parameters per ASCE 7-05
Parameter Value
Soil Site Class E
Latitude 37º 27’ 11’’
Longitude -122º 6’ 40’’
Ss 1.50g
-
8/21/2019 Appendices E - G-utilization Ratio
118/169
Ss 1.50g
S1 0.62g
Fa 0.90
Fv 2.40
SDS 0.90g
SD1 0.99g
Peak Ground Acceleration 0.46g
Notes:
(1) g = vertical acceleration due to gravity at the Earth's surface
(2) Ss = mapped maximum credible earthquake, 5 percent damped, spectral response
acceleration parameter at short periods(3) S1 = mapped maximum credible earthquake, 5 percent damped, spectral response
acceleration parameter at 1 second
(4) Fa = short-period site coefficient
(5) Fv = long-period site coefficient
(6) SDS = design, 5 percent damped, spectral response acceleration parameter at shortperiods
(7) SD1 = design, 5 percent damped, spectral response acceleration parameter at 1 second
A previous geotechnical report prepared for an incinerator rehabilitation project at the RWQCP
in 1998 by CH2M Hill contains a