Appeal Decisions - Planning Jungle · 2016. 10. 8. · Dharam Marg, Hillfield Lane, Aldenham,...
Transcript of Appeal Decisions - Planning Jungle · 2016. 10. 8. · Dharam Marg, Hillfield Lane, Aldenham,...
http://www.planning-inspectorate.gov.uk
Appeal Decisions Inquiry held on 15 & 16 February 2011
Site visit made on 17 February 2011
by R O Evans BA(Hons) Solicitor MRTPI
an Inspector appointed by the Secretary of State for Communities and Local Government
Decision date: 29 March 2011
Appeal Ref: APP/N1920/A/10/2133063
International Society for Krishna Consciousness, Bhaktivedanta Manor,
Dharam Marg, Hillfield Lane, Aldenham, Watford, WD25 8EZ
• The appeal is made under section 78 of the Town and Country Planning Act 1990
against a refusal to grant planning permission.
• The appeal is made by Syamasundara Das against the decision of Hertsmere Borough Council.
• The application Ref TP/09/1913, dated 27 October 2009, was refused by notice dated 1 July 2010.
• The development proposed is erection of temporary wedding marquee between 6 June and 22 August 2010 and 22 May and 7 August 2011 and associated car parking
(amended description 29/04/10).
Appeal Ref: APP/N1920/X/10/2133093
International Society for Krishna Consciousness, Bhaktivedanta Manor,
Dharam Marg, Hillfield Lane, Aldenham, Watford, WD25 8EZ
• The appeal is made under section 195 of the Town and Country Planning Act 1990 as amended by the Planning and Compensation Act 1991 against a refusal to grant a
certificate of lawful use or development (LDC). • The appeal is made by Syamasundara Das against the decision of Hertsmere Borough
Council. • The application Ref TP/09/1885, registered 24 November 2009, was refused by notice
dated 9 July 2010.
• The application was made under section 192(1)(b) of the Town and Country Planning Act 1990 as amended.
• The development for which a certificate of lawful use or development is sought is temporary erection of marquee.
Appeal Ref: APP/N1920/C/10/2136252
International Society for Krishna Consciousness, Bhaktivedanta Manor,
Dharam Marg, Hillfield Lane, Aldenham, Watford, WD25 8EZ
• The appeal is made under section 174 of the Town and Country Planning Act 1990 as
amended by the Planning and Compensation Act 1991. • The appeal is made by Syamasundara Das against an enforcement notice issued by
Hertsmere Borough Council on 18 August 2010. • The Council's reference is EN/08/0271.
• The breach of planning control as alleged in the notice is without planning permission, the unauthorised development comprising: the erection of a marquee on the land
shown edged red on the attached plan, in excess of the 28 days in total in any calendar
year allowed under Schedule 2, Part 4, Class B of the General Permitted Development Order 1995.
• The requirements of the notice are to: a) Dismantle and remove from the land any marquee and all associated miscellaneous
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 2
items including but not limited to floorings and fixings within the red edged area
shown on the attached plan. b) No marquee or any moveable structures are to be erected or placed on the land
edged red shown on the attached plan for not (sic) more than 28 days in total in any calendar year as permitted under Schedule 2, Part 4, Class B of the General
Permitted Development Order 1995. c) No marquee or any moveable structures are to be erected or placed on the land
edged red shown on the attached plan without prior notification in writing to the
local Planning Authority of the date of erection or placing on the land of any marquee or any moveable structure.
• The periods for compliance with the requirements are a) 7 days, b) from the date on which this notice takes effect c) from the date on which this notice takes effect.
• The appeal is proceeding on the grounds set out in section 174(2)(a), (b), (c) and (f) of the Town and Country Planning Act 1990 as amended. The application for planning
permission deemed to have been made under section 177(5) of the Act as amended also falls to be considered.
Decisions
APP/N1920/A/10/2133063
1. I dismiss the appeal.
APP/N1920/X/10/2133093
2. I dismiss the appeal.
APP/N1920/C/10/2136252
3. I direct that the enforcement notice be corrected by:
• Substituting the plan attached to this decision for that attached to the
notice;
• In paragraph 3, by replacing the words “on the land shown edged red” with
the words “in the position shown hatched in blue”.
I further direct that the notice be varied by:
• Deleting the second and third requirements;
• Replacing the first requirement with: “Dismantle and remove from the land
any marquee (and all associated miscellaneous items including but not
limited to floorings and fixings) save as may be permitted under the Town
and Country Planning (General Permitted Development) Order 1995 (as
amended) or by other express permission.”
• Replacing the times shown for compliance with a single period of 7 days
from the date on which the notice takes effect.
Subject to these corrections and variations, I dismiss the appeal, uphold the
enforcement notice, and refuse to grant planning permission on the application
deemed to have been made under section 177(5) of the 1990 Act as amended.
Reasons – Preliminary Matters
4. These appeals concern the erection of a marquee within the grounds of
Bhaktivedanta Manor, which is owned and occupied by the International
Society for Khrishna Consciousness, or ISKCON. Although the appeals are
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 3
brought in the name of an individual, he acts on behalf of ISKCON and for
convenience, my references to ‘the Appellants’ are to ISKCON.
5. The history of the Appellants’ occupation of the Manor is well known to the
parties and indeed to many in the community around it. To summarise the
salient background, the site as a whole runs to some 30 ha set between the
village of Letchmore Heath to the east and Hillfield Lane to the west. The main
buildings, including the Manor itself, a Grade II listed Victorian mansion, are
set towards the eastern end of the site. The principal planning permission
affecting it is that granted by the Secretary of State in 1996 for use of the
Manor as a residential and non-residential theological college and religious
community, together with use for public worship. The permission included the
construction of a new driveway and access to Hillfield Lane which is now the
sole active vehicular route into the site.
6. A number of other permissions have since been granted, for example for
agricultural buildings and polytunnels. Differing applications were also made in
relation to the erection of a marquee within the Manor grounds in 2004, 2005,
2007 and 2008. The last (ref TP/08/1595) was a similar application to that in
the present section 78 appeal, for an 11 week period in 2009. An appeal
against its refusal was later withdrawn following an inquiry.
7. There is no dispute that the marquee subject to these appeals was in place
during the first period specified in the section 78 appeal. The Appellants now
seek a certificate of lawfulness and a permission (if needed) only for its
erection for the second period specified. There would be nothing to prevent a
certificate issued under the section 195 appeal from specifying the temporary
period for which the erection would be lawful, should I so conclude. A
permission can be time limited by condition so I shall approach the section 78
appeal and the deemed application in the section 174 appeal accordingly, as
necessary.
8. The appeal on ground (b) was formally withdrawn at the inquiry and I make no
further comment on it. The circumstances in which the 2 applications came to
be determined after the start of the first period for which permission was
sought are known to the parties, and again, I need make no comment on it.
9. The Council accepted a proposed correction to the enforcement notice, to
substitute an amended plan to identify the actual position of the marquee more
accurately. As the parties are agreed on that, I shall amend the notice
accordingly. The allegation however is one of specified operational
development. I see no need therefore for the notice to refer to the purpose to
which the marquee has been or is intended to be put. Apart from a minor
correction to the second requirement indicated above, I shall address the
possible correction or variation of the requirements under the ground (f)
appeal.
The Marquee
10. The marquee was erected in 2010 in a paddock area approximately 100m to
the west of the Manor, beyond both a formal garden area and the north/south
access drive to the staff car park. Though since dismantled and removed, it is
intended that the same or very similar facility be provided in 2011. There is no
significant dispute about its form or composition. It measures some 36m long
by 15m wide, with sides 3m high and a ridge height of 5.5m. It thus has a
floor area of 540m2. It has an aluminium frame, from the application plans,
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 4
with 13 uprights along each side. From the Appellants’ single photograph,
these are secured to the ground by means of a plate which in turn is pegged at
least at the outer corners by 2 metal pegs estimated at 0.5m long (expressed
as 18” – 24”) and about 2cm (or 0.75”) thick. The uprights are shown as
connected horizontally just above ground level. Although there was no direct
evidence on the point, it is reasonable to assume they would be connected also
at higher levels to ensure stability and that there would be similar uprights
along the two end elevations, as suggested by the marks on the submitted
plans.
11. Once in place, the frame is covered by white vinyl sheeting, with clear panels
along the eastern elevation and a pair of glazed metal framed doors at each
end. A floor described as thin timber panels is placed on the ground and
slotted together. A silk lining is hung internally and a stage measuring 8m x
4m is erected centrally on one side. Electricity is provided but no other
services. Erection of the marquee is carried out by the suppliers and is said to
take 2 days. The floor is then painted and with furniture installed on the fourth
day, it is ready for use by the fifth day. Dismantling and removal would take a
similar time as erection. There is nothing to contradict the Appellants’
evidence on these matters.
The Section 195 Appeal & Section 174 Appeal on Ground (c)
12. Introduction. As indicated, the section 195 appeal can be considered by
reference to the Appellants’ specified period. The section 174 appeal on
ground (c) however relates to the erection of the marquee (and its retention)
for an unspecified period in excess of 28 days. I shall address the distinction
between the 2 appeals as necessary below. Under both of them however the
issue is similar, whether what is alleged and proposed amounts to development
for which planning permission is required and if so, whether such a permission
exists.
13. The definition of “development” in section 55 of the 1990 Act includes the
“carrying out of building, engineering, mining or other operations in, on, over
or under land”. Section 55(1A) provides that “building operations” include
unspecified “other operations normally undertaken by a person carrying on
business as a builder”. The sub-section is not exclusive however so that
particular actions could still amount to “building operations” even if not within
its express provisions. The Town and Country Planning (General Permitted
Development) Order 1995 (“the GPDO”) also forms part of the legal
background, in particular Schedule 2, Part 4 which in certain circumstances
grants permission for temporary buildings and uses.
14. The question thus becomes one of whether the erection – a term incidentally
used by the Appellants themselves – of the marquee amounts to a building
operation. Following the Court of Appeal decision in Skerrits of Nottingham Ltd
v SSETR and LB Harrow 2000 JPL 1025 and earlier decisions, there was no
disagreement on the correct approach to this question being first to ask
whether the resulting ‘item’ was a building (though as noted in the JPL
commentary, it is possible for there to be ‘building operations’ which do not
create a ‘building’). Adopting that approach however, the word ‘building’ is
defined in section 336 as including “any structure or erection”, with three
primary factors identified by the courts as relevant to the question of what is a
building, namely size, permanence and physical attachment.
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 5
15. Inspector’s Assessment. It is clear from the Appellants’ own evidence that the
marquee is assembled and erected on site. Though the number of people
involved in that exercise was not stated, given its undisputed dimensions and
its composition, it must at the least involve a small team for it to be completed
within 2 or 3 days. It must also involve the use of hand tools and a degree of
skill and probably experience to ensure its stability. Similarly, to move it
requires its dismantling. Not least because the definition of building includes
any (my emphasis) erection, it might even be argued that one needs to look no
further in deciding that the exercise of erection alone amounted to a “building
operation”.
16. Given the agreed approach however, the marquee is large enough to be used
for weddings attended by up to 500 people seated, with a small stage. It is
larger in floor area alone than a great many dwellings and its height and bulk,
once covered, make it a substantial structure. On any continuum, it is far from
de minimis in size alone. Further, the frame is attached to the ground by at
least 52 steel pegs, with a probable further 10 or so at each end. Though I
cannot be certain of it, the positioning of the pegs on the outer corners of the
plate shown in the Appellants’ photograph suggests that there would be 2 also
in the opposite corners. The point was not taken up at the inquiry but even if
that supposition is wrong, the marquee clearly needs to be securely attached to
the ground by means other than its own weight to ensure it remains in place.
17. The issue of permanence has arisen in a number of the cases cited. The
evidence I accept shows that there has been no permanent physical change in
the character of the land, nor is there likely to be, by the marquee remaining in
place for an 11 week period. That however is not the determining factor.
Permanent does not mean ‘forever and a day’. As Schiemann L.J. put it in
Skerritts, in discussing how long a structure needed to be in place, his answer
was “for a sufficient length of time to be of significance in the planning
context.” Pill L.J. drew attention to the “degree of flexibility” in the approach to
permanence introduced in Barvis Ltd v SSE & Another (1971) 22 P & CR 710,
including the use of the expression “some degree of permanence” and the
concept of removal “by taking to pieces”. Morritt LJ went on to describe it as
“a matter of degree between the temporary and the everlasting.”
18. The case of R (on the application of Hall Hunter Partnership) v FSS [2007] 2 P
& C R 5 concerned the erection of an extensive area of polytunnels for
agricultural purposes which it was found would remain in one particular location
for between three and seven months in any one year. The court held that the
inspector’s conclusion that even the shortest of those periods would be a
sufficient length of time to be of consequence in planning terms could not be
said to be unreasonable. The present case is not directly comparable but that
decision serves to illustrate that a structure can still be of consequence even if
only in place for a relatively short period of time. Further, the Appellants’
evidence is that they have erected a similar if not larger marquee for a similar
period and purpose every year since “at least 1999”, though in earlier years in
a different position to that in these appeals. The present appeals may involve
a specified period of time but against that background, it would be artificial to
see them wholly in isolation.
19. Once erected, this substantial marquee is undoubtedly a ‘structure’ in the
ordinary meaning of something assembled or constructed. It is an additional
facility which allows for large gatherings to be held while other activities take
place in the main building. The site is in both the Metropolitan Green Belt and
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 6
in part within a Conservation Area. Without going further into the planning
merits at this stage, its presence for 11 weeks of the year is at least capable of
being material in planning terms, both as to its physical impact and the
additional level of activity it facilitates. Looking at the evidence collectively,
because of its size, the works necessary to erect and dismantle it, its
attachment to the ground and the length of time it has been and is to be kept
in place, I conclude that the marquee is of significance in planning terms. As a
question of fact and degree therefore, it is, or would be, a building for present
purposes. It follows that its erection required or would require planning
permission. None has been granted for it and the section 195 appeal therefore
fails.
20. The way the enforcement notice is phrased raises another question. It refers
expressly to the erection of the marquee “in excess of the 28 days” allowed
under Schedule 2, Part 4, Class B of the GPDO. Class B is primarily concerned
with the temporary use of land but also permits “the provision on the land of
any moveable structures for the purposes of the permitted use”. The Council
sought no amendment to the notice to exclude the references to Class B. Their
view must therefore be taken to remain that the Appellants are entitled to avail
themselves of the 28 day period with the marquee in its last and proposed
position. Equally, it was not argued for the Appellants that if the marquee was
a “moveable structure” for the purposes of Class B, it was or could not be a
building within section 336 and therefore that its erection could not amount to
operational development. As I have concluded on the evidence that it was a
building however, whether it is a “moveable structure” for the purposes of
Class B might be open to question even allowing for the wide definition in
section 336.
21. That said, the acceptance of the availability of Class B rights does not prevent
the Council arguing that an express permission is required for the marquee to
be erected for a longer period than 28 days nor was there any submission to
that effect. Equally, the GPDO provisions do not mean that it is unnecessary to
carry out the sort of analysis set out above in order to determine whether
permission is required, particularly where permanence is directly material to
that question. Indeed, even if the 28 day provision is thought of as just ‘for
the avoidance of doubt’, the logical implication of it is that a longer period,
even for a “moveable structure”, is likely to be material in planning control
terms. More importantly, if the provision of the marquee is capable of being
permitted development within Class B, there is no doubt it was retained for
longer than the permitted 28 day period. Conversely, if its erection could not
fall within Class B, it still amounted to operational development for the reasons
given above. Either way therefore the breach of control alleged in the notice
has occurred even if the GPDO provisions are not applicable. For these reasons
as well therefore, the ground (c) appeal also fails.
The Section 78 Appeal and Ground (a) & Deemed Application in the
Section 174 Appeal
22. Main Issue & Planning Policy. The main issue is whether the erection of the
marquee amounts to inappropriate development within the Green Belt and if so
whether, very special circumstances nevertheless exist so as to justify it. As
PPG2 advises, such very special circumstances will not exist unless the harm by
reason of inappropriateness, and any other harm, is clearly outweighed by
other considerations.
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 7
23. Policy C1 of the Borough’s 2003 Local Plan remains in force. It sets out a
general presumption against inappropriate development in the Green Belt and
provides that that question should be assessed in accordance with section 3 of
PPG2. I have had due regard also to the more specific criteria in Policy C4.
The Appellants contended that the marquee’s erection should not be considered
under paragraph 3.4 of PPG2, but under paragraph 3.12.
24. Inappropriateness. Paragraph 3.4 states that “the construction of new
buildings inside a Green Belt is inappropriate” unless for specified purposes
which do not include colleges, places of worship or (if a use in its own right)
the holding of weddings. PPG2 is a statement of government planning policy.
It is long established but post-dates the 1990 Act. Where a statutory definition
has been given for the purposes of the principal legislation, but none has been
given in the Guidance, and having held that the operational development
carried out resulted in a building, it would be inconsistent at best to hold that
some different definition should be applied for PPG2 purposes. That would be
so even without the wording of paragraph 3.12, the relevant part of which
states that the “statutory definition of development includes engineering and
other operations.” It continues “the carrying out of such (my italics) operations
and the making of material changes in the use of land are inappropriate
development unless they maintain openness and do not conflict with the
purposes of including land in the Green Belt.”
25. It follows from the above that the erection of the marquee falls to be
considered under paragraph 3.4. Even if that were not so, it fails to maintain
openness and represents an encroachment into the countryside at least whilst
it is in place. Where the fundamental aim of Green Belt policy is to prevent
urban sprawl by keeping land permanently open, even a structure in place for
11 weeks will prevent that permanent openness being maintained. The mere
fact that the marquee is intended to be a temporary structure does not prevent
it being inappropriate in Green Belt terms and I hold it to be so. As PPG2
advises, it is thus for the Appellants to show why permission should be
granted.
26. Impact on Openness and Purposes of the Green Belt. The marquee would be
partly screened by hedges around three sides. Its height, length and bulk
however would be readily apparent when seen from viewpoints to the north
and south, and most especially, as I saw, when approaching along the access
drive from the east. It would not be readily visible from public viewpoints
outside the Manor site, though would be fleetingly so from a public footpath to
the south and probably in some views from buildings to the north. Because of
the lie of the land and intervening vegetation and buildings it would not be
visible from outside the site to the east.
27. Partly because of its distance from the Manor itself and the village, but mainly
because of its temporary nature, it would have no lasting consequences for the
setting of the listed building or the Conservation Area. No objections indeed
were made on those counts. Even so, as already indicated, the structure would
detract from the openness of the Green Belt for as long as it was in place.
Further, a relative lack of visibility may mitigate its impact but is not of itself a
reason for permission to be granted; the same could be said of many
developments. The occasional sight of such marquees in the countryside I
accept is not uncommon in the summer months. In probably the vast majority
of cases however they are erected for the sort of short periods envisaged in the
GDPO, if not single events.
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 8
28. The level of additional activities the marquee facilitates must also be taken into
account. In summary, the Manor was said generally to be at its busiest in the
summer months. The holding of weddings causes difficulties in the
management of activities within the Temple room and elsewhere, where a
wedding may be seen by other visitors as a private function. Special
arrangements may therefore have to be made for them to visit the Temple
room while weddings are in progress. Even with a maximum of 250 wedding
guests in the main building, not all of them can be accommodated in the
Temple room during the ceremony and some have to observe from outside it or
by video link. Having the facility of the marquee thus enables not only the
normal Temple activities to continue unhindered but also the holding of
weddings for larger numbers of guests than can be catered for satisfactorily in
the main building. No more than 2 weddings per day are held, whether in the
main building or the marquee. I have no reason to doubt the thrust of this
evidence, but it was lacking in details both of day to day and other activities,
and the numbers of residents and visitors at different times of the year.
29. The provision of the marquee inevitably means that greater numbers of people
are likely to visit the site on days when larger weddings are held than when
they are held in the main building. In numbers alone, the Appellants limited
the bookings in 2010 as far as possible to 300 guests, as I understand them to
have done so far for 2011, following the submission of their planning
application. In 2008 however the average number of guests per marquee
wedding was 295, with 15 out of the total of 38 attended by 350 people or
more, and 5 of those with 450 or more. At the same time, 14 of the marquee
weddings were attended by between 50 and 250 guests, where the 2010
average for those in the main building was about 195.
30. It is thus not just the structure of the marquee that encroaches further into the
Green Belt but also the activities associated with it, including additional vehicle
parking sometimes to the west of the marquee site. These applications must
also be seen in the context of the Manor as a whole and the other activities
taking place there, not least the holding of the important festival of
Janmashtami, that occurs very shortly after the marquee’s removal. The
evidence before me however is lacking in depth and detail on those matters.
31. Residential Amenity. The Council did not pursue any objection on the grounds
of harm to residential amenity, following the obtaining and discussion of noise
evidence at or after the previous inquiry. On that aspect, the site as a whole is
subject to an overriding condition in relation to noise levels emitted from it at 2
points on the eastern boundary. I have no reason to doubt the accuracy of the
readings taken by the Appellants’ expert witness. One resident at least
highlighted the fact that on 2 occasions1 the LAeq levels at ‘Point 1’ exceeded
the conditioned limit while a wedding was in progress. That does not
necessarily mean the wedding was the cause. The levels recorded at ‘Point 2’,
which is further away from the road outside, were noticeably lower. So too
were those recorded in the staff car park and close to the boundary of the
nearest residential property, both of them closer to the marquee than ‘Point 1’.
32. The figures recorded are no more than a record of what occurred at the time
the measurements were taken. Residents I do not doubt have on occasion had
cause to notice noise emanating from the site at times when weddings may
have been taking place, whether in the form of general hubbub, noise from
1 5 & 12 June 2009
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 9
vehicles, chanting or drum playing. Identifying a wedding as the source would
be difficult however, given the distances involved and lack of visibility from
most directions. More importantly, complaints appear to have tailed off if not
ceased altogether since the installation of sound limiting equipment in 2009,
though coincidentally, as above, the numbers attending were fewer in 2010
than in 2008. Amplified noise emanating from the marquee I consider can be
effectively controlled by condition. It is rather the perception of increased
activity and intermittent noise sources, again set in the context of all the other
activities that take place at the Manor, that could be a source at least of
irritation to some local residents. I do not however consider this so great a
harm that it would justify withholding permission, were it the only objection.
33. Other Matters. There was no objection from the Highways Authority on road
safety grounds. Although some residents complained of excessive traffic
locally, I likewise find no sustainable objection on this ground.
34. The Appellants not surprisingly drew attention to the officers’ recommendations
for approval on both the 2008 and 2009 applications. Different versions of the
first one were submitted but on the Green Belt analysis at least they were
consistent. The officer appears, at paragraph 10.1, to have reached no
conclusion on inappropriateness but concluded that because the marquee
would result in no long term effects on the openness of the Green Belt, that
was sufficient to outweigh any harm it might cause. For that reason alone, her
analysis at that time appears flawed.
35. In her second report however, the officer correctly concluded at paragraph
10.4 that the marquee would be inappropriate development. She then also
concluded that it would not result in a significant increase in activity over and
above that created by weddings at other times of year. As above, I have
reached a different conclusion on that aspect. She also stated that officers
accepted “the need” for the development and because there would be no long
term effects on the openness of the Green Belt, considered that ‘very special
circumstances’ had been made out. The officer concerned did not give
evidence at the inquiry and I am not clear on what basis “need” was assessed.
36. My attention was also drawn to a number of other temporary structures,
including larger marquees, within the Green Belt for which the Council have
granted permission. While consistency in decision making is undoubtedly
desirable, even if I was aware of all the considerations that gave rise to those
permissions, it would not follow that these appeals should necessarily be
allowed. Each case must be considered on its merits. Further, as implied
above, the fact that the Council or its officers reach a particular conclusion in a
given case does not necessarily mean the same conclusions would be reached
by others.
37. Any objections on the planning merits are tempered by the temporary nature
of the proposal. Given the Appellants’ evidence of a continuing if not
increasing demand for the facility however, it is only realistic to expect
repeated similar proposals if these permissions are granted (and assuming no
other provision is made). Be that as it may, limited or temporary harm is still
harm. It may not weigh as heavily against a development as permanent or
serious harm but it does not weigh in favour of it, if for no other reason than
that it cannot outweigh itself. I find that harm would be caused in particular to
the openness of the Green Belt, even if only while the marquee is in place.
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 10
38. Other Considerations. Given, as above, that the onus is on the Appellants to
show why permission should be granted, the question of ‘need’ for the
development has to be considered in order to assess whether the harm caused
is outweighed by other considerations. The obvious starting point for that
exercise is to look at the Secretary of State’s reasons for granting permission in
1996. Since he expressly disagreed with the Inspector’s approach on this
aspect, it is the former’s analysis which is relevant rather than the latter’s.
Considerable further guidance has since been given by the courts as to the
correct approach to the question of ‘very special circumstances’.
39. First, it was accepted that the Manor, given its history and associations, made
a special contribution to the spiritual and religious needs of the Hindu
community and that they should be given considerable weight. The extent and
nature of that contribution began to be questioned at this inquiry. As I made
clear however, a planning inquiry is not the appropriate forum for a theological
debate. The Manor is listed as a Temple by the Hindu Council UK. It has a
‘congregation’ of visitors and contributors estimated from ISKCON’s database
at 10,000. Up to 1000 people were said to visit on Sundays, with many
thousands more attending its annual festivals. These numbers alone
demonstrate that it continues to make the ‘special contribution’ found by the
Secretary of State. He went on to consider a number of other matters and
gave weight to the low chances of the Appellants finding a suitable alternative
(permanent) site. He had earlier pointed out however that the religious needs
of one section of the community are not of such paramount importance that
they can automatically override national or local planning policies.
40. The holding of weddings is as much a part of the Manor’s ‘public worship’
function as it would be for a Christian church, but in a sense the Appellants
have become the victims of their own success. They may not need to advertise
their wedding facilities but the extracts from their website go beyond simply
the informative to the promotional. Their President’s own evidence indeed is
that the Manor is promoted as a wedding venue2. While I have no reason to
think that the Appellants are motivated by anything other than their spiritual
beliefs and a desire to provide for their congregation, it is clear also that
significant charges are levied over and above any charity, or dakshina, to the
priests. Their case could only be assisted by a detailed financial analysis
demonstrating the use of the funds so generated.
41. That said, I also have no reason to question the Appellants’ evidence on the
importance of marriage in the Hindu tradition nor the value the participants
place on being married at the Manor. However, while it may be the desire or
even custom for some members of their congregation to invite large numbers
of people to weddings, there was no evidence either that this was a religious
necessity or obligation, nor that any weddings would not or could not be held
at the site nor that anyone would be prevented from visiting the Temple room
if these appeals are dismissed. Indeed, by limiting the numbers per booking,
the Appellants have already taken steps to deal with just that eventuality.
That may give rise to some inconvenience, but the function of the Manor as a
religious centre would not be undermined while the number of guests attending
weddings, on the evidence before me, appears to be largely a matter of
personal choice.
2 Para 23 of statement adopted by Srutidharma Das
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 11
42. Further, the larger weddings in particular appear to have been concentrated
historically on Fridays and Saturdays. While there may be understandable
reasons for that, it means the marquee has been under-used on other days.
Even with a total of 50 over the 11 week period, it would be possible for a large
proportion to be held within a marquee erected for the GPDO 28 day period.
That may mean some people would be deprived of their first choice of date but
not of the opportunity altogether. While again acknowledging the importance
of the Manor to some, save for a general reference to the number of Hindu
religious buildings nationally, there was little evidence of the availability and
suitability of other facilities within a reasonable distance.
43. Conclusions. The Appellants’ approach to these appeals limits their scope. The
erection of the marquee in 2011 may cause only limited and temporary harm
beyond its inappropriateness but the matters advanced in support of the
appeals I regard, on present evidence, as essentially personal and managerial
considerations to which I cannot attach great weight and which can very
largely be addressed in other ways. I am not therefore satisfied that the harm
by reason of inappropriateness and the other albeit limited harm I have
identified is outweighed by them. It follows that the very special circumstances
necessary to justify the development have not been made out.
44. Further, if not already clear, I do not consider it realistic to look at these
appeals in isolation in the light of the case history. There is every reason to
suppose that similar if not larger numbers of people will want to be married at
the Manor next year, the year after that and so on. I understand indeed that
the Appellants are considering the possibility of a year round facility but no
application for one has yet been made. To hold that this 11 week period will
result in no permanent harm may be true of itself but the same could be said
each year afterwards, so that the temporary harm becomes all but
institutionalised, or permanent for a particular if not growing number of weeks
per year. While future proposals and practice cannot be predicted with
certainty, this only adds further weight to the above conclusions.
Section 174 Appeal on Ground (f)
45. The relevant statutory provisions relating to requirements are set out in section
173. Having considered the planning merits fully under the ground (a) appeal,
and given the nature of the allegation, the only issue under this ground is
whether the requirements go beyond what is necessary to remedy the breach
of control. The requirements as they currently stand need to be looked at
collectively.
46. Firstly, the notice alleges operational development. Not to require the
marquee’s removal would be to under-enforce and thus defeat the purpose of
the notice. The fact that the marquee has already been removed means only
that the first requirement has been met, not that its removal need not be
included in the notice. Further, the notice plan may require amendment to
identify the precise location of the marquee but the planning unit remains the
Manor grounds as a whole. The requirement therefore needs to attach to the
whole of the unit.
47. Secondly, section 173(9) provides that a notice shall “specify the period at the
end of which any steps are required to have been taken”. The second and third
requirements seek to impose continuing obligations in breach of that provision,
where part of the purpose of a notice is to bring finality to the matter. Thirdly,
the second requirement is unnecessary in any event where section 181(1)
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 12
provides that compliance with a notice shall not discharge it and section 181(3)
specifically affords continuing protection against the “reinstating or restoring
(of) buildings or works” so removed. Fourthly, the third requirement seeks to
impose an obligation that is not only unrelated to the remedying of the breach
but which goes beyond any condition imposed under the GPDO. It is thus
excessive also for that reason.
48. Fifthly, a notice cannot prevent development that is otherwise lawful. As
indicated, the Council’s acceptance of the availability of rights under Class B is
reflected in the allegation and in the second requirement. The reference to it
should thus be retained in the requirements as to remove it would be to risk
causing an injustice to the Appellants. That can be done with the addition of
suitable wording to the first requirement. The second and third requirements
should however be deleted. The appeal on this ground therefore succeeds to
that extent.
R O Evans
Appeal Decisions APP/N1920/A/10/2133063, APP/N1920/X/10/2133093, APP/N1920/C/10/2136252
http://www.planning-inspectorate.gov.uk 13
APPEARANCES
FOR THE APPELLANT:
Mr D Altaras of Counsel, instructed by Mr P Trevelyan, ABT
Planning & Highways Consultancy
He called:
Srutidharma Das Temple President, Bhaktivedanta Manor
Syamasundara Das Former Wedding Manager, Bhaktivedanta Manor
Mr M Sawyer DipAN
MIOA
Senior Consultant, Acoustical Investigation &
Research Organisation Ltd
Mr P Trevelyan MA MSc
DipTP MRTPI FIHT
MCILT
Principal, ABT Planning & Highways Consultancy
FOR THE LOCAL PLANNING AUTHORITY:
Mr R Walton of Counsel, instructed by the Head of Legal
Services
He called:
Mr P Smith BA(Hons)
DipTP MRTPI
Director, Brian Barber Associates, Chartered
Town Planning Consultants
INTERESTED PERSONS:
Mr D Lambert Chairman, Letchmore Heath Village Trust
Mr M Jeffries Resident, Hillfield Lane
Mr M Powell Former community member, Bhaktivedanta
Manor
Mr I Southern Resident, Letchmore Heath
Mr M Shaw Resident, Letchmore Heath
DOCUMENTS PRESENTED AT THE INQUIRY
1 Statement of Common Ground
2 Marquee Wedding Attendance Figures 2003-2008
3 Location plan re other permissions
4 Colour copy Appellants’ photograph of marquee
5 Committee reports re TP/08/1595
6 Minutes of Committee meeting 3/6/10
7 Additional extracts, Appellants website (Mr I Southern)
8 Extract, Hindu Council UK website (Mr M Jeffries)
9 Appellants’ “Strawberry festival” leaflet (Mr M Jeffries)
http://www.planning-inspectorate.gov.uk
Plan This is the plan referred to in my decision dated: 29 March 2011
by R O Evans BA(Hons) Solicitor MRTPI
Land at: Bhaktivedanta Manor, Dharam Marg, Hillfield Lane, Aldenham,
Watford, WD25 8EZ
Reference: APP/N1920/C/10/2136252