API Ispat & Powertech Pvt. Ltd. -...

32
API Ispat & Powertech Pvt. Ltd. [Expansion of Steel plant] Village: Siltara, near Phase – II, Siltara Industrial Area, Tehsil and District: Raipur Chhattisgarh PRE-FEASIBILITY REPORT

Transcript of API Ispat & Powertech Pvt. Ltd. -...

Page 1: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

API Ispat & Powertech Pvt. Ltd. [Expansion of Steel plant]

Vil lage: Siltara, near Phase – II, Siltara Industrial Area,

Tehsil and District: Raipur

Chhattisgarh

PRE-FEASIBILITY REPORT

Page 2: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

- i -

Contents

Chapter – 1: Executive Summary ...................................................................... 1

1.1 About Project Proponent ................................................................. 1

1.2 About the Proposed Project .............................................................. 1

Chapter – 2: Introduction of the Project / Background Information ....................... 3

2.1 Identi fication OF Project and Project Proponent ................................... 3

2.2 Brief Description of Nature of Product ............................................... 3

2.3 Need for the Project and importance to the Region ............................... 3

2.4 Demand – Supply GAP ................................................................... 4

2.5 Employment Generation (direct & indirect) ......................................... 5

Chapter – 3: Project Description ........................................................................ 6

3.1 Type of the Project ......................................................................... 6

3.2 Location of the Project .................................................................... 7

3.3 Details of the Alternate Sites ............................................................ 8

3.4 Size OR Magnitude of Operation ...................................................... 8

3.5 Manufacturing Process: ................................................................... 9

3.5.1 Pelletization Unit: .......................................................................... 9

3.5.2 Induction Furnace: ........................................................................12

3.5.3 Rolling Mill Unit: .........................................................................15

3.5.4 Ferro Alloys Manufacturing Unit: ....................................................17

3.6 Raw Material Requirement .............................................................18

3.7 Water requirement and its Source .....................................................20

3.8 Solid Waste Generation and its Disposal:...........................................20

Chapter – 4: Site Analysis.................................................................................21

4.1 Connectivity ................................................................................21

4.2 Land use......................................................................................21

4.3 Topography .................................................................................22

4.4 Existing land use pattern.................................................................22

4.4 Existing infrastructure....................................................................22

4.5 Climatic data from secondary sources ...............................................22

Chapter – 5: Planning Brief ..............................................................................23

5.1 Planning Concept ..........................................................................23

5.2 Population Projection.....................................................................23

Page 3: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

ii

5.3 Land use Planning .........................................................................23

5.4 Amenities / Facilities .....................................................................23

Chapter – 6: Proposed Infrastructure ................................................................24

6.1 Industrial Area (processing Area) .....................................................24

6.2 Residential Area (non Processing Area) .............................................24

6.3 Green Belt ...................................................................................24

6.4 Social Infrastructure ......................................................................25

6.5 Connectivity:................................................................................25

6.6 Drinking Water Management ..........................................................25

6.7 Sewerage System ..........................................................................25

6.8 Industrial Waste Management .........................................................26

6.9 Solid waste Management & its Disposal ............................................26

6.10 Power Requirement & Its Source .....................................................26

Chapter – 7: Rehabilitation & Resettlement (R & R) Plan ....................................27

Chapter – 8: Project Schedule & Cost Estimates .................................................28

8.1 Project Schedule ...........................................................................28

8.1 Project Cost .................................................................................28

Chapter – 9: Analysis of Proposal......................................................................29

9.1 Financial and Social Benefits ..........................................................29

9.2 Socio-economic Developmental Activities .........................................29

Page 4: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 1

Chapter – 1: Executive Summary

1.1 About Project Proponent

API Ispat & Powertech Pvt. Ltd. [here in after referred as APIIPPL] company is in

steel business and having good reputation in the market, which was gained with

good business experience. Looking forward in prospects of Steel sector, APIIPPL

propose to go for expansion of steel plant in Raipur District of Chhattisgarh State.

1.2 About the Proposed Project

API Ispat & Powertech Pvt. Ltd. is existing steel plant at Siltara village, near Phase

– II, Siltara Industrial Area, Tehsil and District: Raipur, Chhattisgarh. Now as a part

of expansion, APIIPPL is planning to enhance the capacity of Induction Furnace,

Rolling Mill and establish new unit of Pellet plant, EAF and Ferro alloys. Following

is production capacity and plant configuration:

Table 1: Unit Configuration

Sr. No.

Unit Existing CFE awarded Proposed Expansion

After Expansion Implemented To be

commissioned

1. Iron Ore Beneficiation and Pelletization Plant

--- --- 1 x 2000 TPD or

2 x 1000 TPD

= (0.6 Million TPA)

1 x 2000 TPD or

2 x 1000 TPD

= (0.6 Million TPA)

2. DRI Kilns

(Sponge Iron )

1 x 350 TPD

= (105,000 TPA)

1 x 350 TPD

= (105,000 TPA)

---- 2 x 350 TPD

= (210,000 TPA)

3 Steel Melting Shop

a Induction Furnace with CCM (MS Ingots/ billets/ blooms)

2 x 12 Tons = (86400 TPA)

--- 3 x 15 Tons = (162000

TPA)

2 x 12 MT & 3 x 15 MT = (248400

TPA) b Electric Arc Furnace with

AOD/ VOD & Caster (MS

and SS Ingots/ billets/ blooms)

--- --- 2 x 20 MVA = (120000

TPA)

2 x 20 MVA = (120000

TPA)

4. Rolling Mill --- 1 x 322.5 TPD +

1 x 161.7 TPD = (145250 TPA)

1 x 650 TPD

= (200000 TPA)

1 x 322.5 TPD,

1 x 161.7 TPD & 1 x 650 TPD & = (345250 TPA)

5. Ferro alloys [2 x 9 MVA] --- --- 2 x 9 MVA 2 x 9 MVA

i. Ferro – Silicon --- --- 12600 TPA 12600 TPA

Page 5: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

2

or or or ii. Silico–Manganese --- --- 28400 TPA 28400 TPA

or or or iii. Ferro–Manganese --- --- 37000 TPA 37000 TPA

6 Power Plant–WHRB based 8 MW 10 MW --- 18 MW

7 Power Plant–FBC based 7 MW --- --- 7 MW

97.75 acres of land is in possession of management and proposed expansion will

be taken up the existing plant premises.

Total project cost envisaged for the proposed expansion project is Rs.240 Crores.

*****

Page 6: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 3

Chapter – 2: Introduction of the Project / Background Information 2.1 Identification of Project and Project Proponent

API Ispat & Powertech Pvt. Ltd. [here in after referred as APIIPPL] company is

engaged in steel business and having good reputation in the market, which was

gained with good business experience. Looking forward in prospects of Steel

sector, APIIPPL propose to go for expansion of steel plant in Raipur District of

Chhattisgarh State.

2.2 Brief Description of Nature of Product

The company after assessing the market potential of the steel industry thoroughly

decided to go in for iron-ore pellets. The highly encouraging response received

on market survey also ruled favorably for the said project. Promoters are well

experienced entrepreneurs and are well supported by technical personnel

experience to run such unit.

Presently, most of the coal based sponge iron plants in India uses iron ore lumps.

The requirement is generally 1.8 t/ t of sponge iron. This high requirement is

mainly due to the fines generated in handling the purchased ore from the source

to the plant. This reduces the kiln campaign length and increases ore fines lost.

Use of pellets with better physical and metallurgical properties for sponge iron

production reduces the accretion formation in the kiln and the pellets

consumption is about1.6 t/t. Further, the production from the kiln is expected to

increase by 25% to 30%.

In view of the above, API Ispat & Powertech Pvt. Ltd. proposed to go for

expansion of steel plant at Siltara village, near Phase – II, Siltara Industrial Area,

Tehsil and District: Raipur, Chhattisgarh.

2.3 Need for the Project and importance to the Region

Utilization of low grade ore and fines has to play an important role. In India partly

due to the sponge iron sector; the overall percentage of lumps usage in steel

making (47%) is higher than most other countries. As hard ore reserves is

depleting day by day, lump generation suitable for blast furnace operation is

coming down resulting in production of large amount of surplus fines. Alternative

Page 7: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 4

iron making processes for production of steel may lead to changing pattern of use

material inputs and feed stock causing significant shift in respective share of

lumps and agglomerated iron ore (pellets) and will also enable the use of ores

which could not be utilized earlier. As fines forms considerable part of iron ore

resources, value addition to the iron ore fines through various activities such as

beneficiation, Pelletization is the need of the hour.

2.4 Demand – Supply GAP

With the rapid development of Infrastructure and manufacturing sector, the Iron

and steel industry is poised for an accelerated growth. Steel demand in the

country is increasing at an average rate of 10% and is likely to remain in 10-12%

range at least for the next decade. In order to meet the steadily growing steel

demand in the country, domestic steel producing capacity is required to be higher

than 110 mtpa within next three years and, 150 mtpa by the year 2016-17. Indian

economy is growing at more than 10% rate, steel demand and supply will grow in

the same way. As good quality iron ore deposits are depleting fast beneficiation

technologies will have to be adopted to meet iron ore demand. Therefore good

yield of beneficiation process generally around 70 % will make this technology

economically viable.

Agglomeration technologies such as Pelletization will have to be added to DRI

Plant / Steel Plant so that concentrates can be used as feed material. Recycling of cheaper raw material (fines) by beneficiation and pelletization process as feed material will result in better Return on Investment as

compared to using Iron ore as feed material.

With superior reducibility behavior of pellets compared to lump ore efficiency

of DRI production improves.

It can be concluded from results obtained by conducting various tests on

manufactured pavement blocks that substitution of iron ore tailings for sand or quarry dust shows better compressive strength without much change in water absorption.

In the Indian context, by the year 2020, India’s production of steel is expected to

touch110 Million Tonnes and it is imperative that the fines generated in the

mining of iron ore be utilized for the production of steel. The Indian steel industry

which predominantly uses expensive lump ore is gradually moving towards usage

of iron ore pellets.

Page 8: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 5

The present Indian raw material scenario offers an opportunistic disposition

towards pellet making owing to the availability of large quantities of sub grade

fines, slimes and blue dust etc. at different mine heads. These materials are not

suitable for sinter making. Pelletization is the only possible route for salvaging

these, otherwise waste but valuable materials. Recent techno-economic studies

indicated favorable indices for installation of pellet plants, both small and large

scale. The demand supply analysis also underlines the need for Pelletization.

2.5 Employment Generation (direct & indirect)

PHYSICAL INFRASTRUCTURE

Once the proposed activity is commissioned, the socio-economic status of the

local people will improve and there by infrastructure facilities like communication

systems will improve. Most of the villages at present do not have protected

water supply. After the implementation of the project, the affordability of the

public to spend on water treatment, supply & distribution will more along with

the aid from the state government.

EMPLOYMENT POTENTIAL

The proposed project creates employment to 100 people during construction and

50 people during operation of the proposed expansion.

Sr. No. Category Nos. of employment 1. Skilled 15

2. Semi skilled 15

3. Un-skilled 25

*****

Page 9: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 6

Chapter – 3: Project Description 3.1 Type of the Project

API Ispat & Powertech Pvt. Ltd. is existing steel plant at Siltara village, near Phase

– II, Siltara Industrial Area, Tehsil and District: Raipur, Chhattisgarh. Now as a part

of expansion, APIIPPL is planning to enhance the capacity of Induction Furnace,

Rolling Mill and establish new unit of Pellet plant, EAF and Ferro alloys. Following

is production capacity and plant configuration:

Sr. No.

Unit Existing CFE awarded Proposed Expansion

After Expansion Implemented To be

commissioned 1. Iron Ore Beneficiation and

Pelletization Plant --- --- 1 x 2000 TPD

or 2 x 1000 TPD

= (0.6 Million TPA)

1 x 2000 TPD or

2 x 1000 TPD

= (0.6 Million TPA)

2. DRI Kilns

(Sponge Iron )

1 x 350 TPD

= (105,000 TPA)

1 x 350 TPD

= (105,000 TPA)

---- 2 x 350 TPD

= (210,000 TPA)

3 Steel Melting Shop

a Induction Furnace with CCM (MS Ingots/ billets/ blooms)

2 x 12 Tons = (86400 TPA)

--- 3 x 15 Tons = (162000

TPA)

2 x 12 MT & 3 x 15 MT = (248400

TPA) b Electric Arc Furnace with

AOD/ VOD & Caster (MS

and SS Ingots/ billets/ blooms)

--- --- 2 x 20 MVA = (120000

TPA)

2 x 20 MVA = (120000

TPA)

4. Rolling Mill --- 1 x 322.5 TPD +

1 x 161.7 TPD = (145250 TPA)

1 x 650 TPD

= (200000 TPA)

1 x 322.5 TPD,

1 x 161.7 TPD & 1 x 650 TPD & = (345250 TPA)

5. Ferro alloys [2 x 9 MVA] --- --- 2 x 9 MVA 2 x 9 MVA

i. Ferro – Silicon --- --- 12600 TPA 12600 TPA or or or

ii. Silico–Manganese --- --- 28400 TPA 28400 TPA or or or

iii. Ferro–Manganese --- --- 37000 TPA 37000 TPA

6 Power Plant–WHRB based 8 MW 10 MW --- 18 MW 7 Power Plant–FBC based 7 MW --- --- 7 MW

Page 10: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 7

3.2 Location of the Project

Proposed Project is located at Siltara village, near Phase – II, Siltara Industrial

Area, Tehsil and District: Raipur, Chhattisgarh. 97.75 acres of land is in possession

of management and proposed expansion will be taken up the existing plant

premises.

Topographical location of project site is shown below:

Page 11: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 8

3.3 Details of the Alternate Sites

No alternative sites have been considered as proposed expansion will be taken up

in the existing plant premises.

3.4 Size OR Magnitude of Operation

As a part of expansion, APIIPPL is planning to enhance the capacity of Induction

Furnace, Rolling Mill and establish new unit of Pellet plant, EAF and Ferro alloys.

Following is production capacity and plant configuration:

Sr. No.

Unit Existing CFE awarded Proposed Expansion

After Expansion Implemented To be

commissioned 1. Iron Ore Beneficiation and

Pelletization Plant

--- --- 1 x 2000 TPD

or 2 x 1000 TPD = (0.6 Million

TPA)

1 x 2000 TPD

or 2 x 1000 TPD = (0.6 Million

TPA)

2. DRI Kilns (Sponge Iron )

1 x 350 TPD = (105,000

TPA)

1 x 350 TPD = (105,000 TPA)

---- 2 x 350 TPD = (210,000

TPA)

3 Steel Melting Shop

a Induction Furnace with

CCM (MS Ingots/ billets/ blooms)

2 x 12 Tons

= (86400 TPA)

--- 3 x 15 Tons

= (162000 TPA)

2 x 12 MT &

3 x 15 MT = (248400

TPA)

b Electric Arc Furnace with AOD/ VOD & Caster (MS and SS Ingots/ billets/ blooms)

--- --- 2 x 20 MVA = (120000

TPA)

2 x 20 MVA = (120000

TPA)

4. Rolling Mill --- 1 x 322.5 TPD + 1 x 161.7 TPD = (145250 TPA)

1 x 650 TPD = (200000 TPA)

1 x 322.5 TPD, 1 x 161.7 TPD & 1 x 650 TPD & = (345250

TPA) 5. Ferro alloys [2 x 9 MVA] --- --- 2 x 9 MVA 2 x 9 MVA

i. Ferro – Silicon --- --- 12600 TPA 12600 TPA or or or

ii. Silico–Manganese --- --- 28400 TPA 28400 TPA

or or or iii. Ferro–Manganese --- --- 37000 TPA 37000 TPA

6 Power Plant–WHRB based 8 MW 10 MW --- 18 MW 7 Power Plant–FBC based 7 MW --- --- 7 MW

Page 12: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 9

3.5 Manufacturing Process: 3.5.1 Pelletization Unit:

The iron ore Pelletization unit comprises of following sections:

a. Drying & Prepn. of Iron Ore Fines b. Grinding c. Mixing and Blending

d. Pelletization e. Screening f. Travel Grate Furnace g. Rotary Kiln h. Cooler

i. Stacking j. Recovery of Dust and Spillage

a. Drying & Preparation of Iron ore Fines:

Generally Iron Ore Fines, Lime Stone and Dolomite fines available, contain

more than 6-7% moisture and require drying before grinding. The drying is

carried out in Rotary Drum Dryer. The moisture content in the dry material

is controlled. The low grade Iron Ore Fines is feed in a screen for

separation. Oversize/ under size moves to the primary grinding circuit.

b. Grinding

Iron Ore Fines, Dolomite and Lime Stone are mixed in required proportion

and fed into a Ball Mill. The fineness of the product is controlled as may be

necessary for particular ore and Pellet quality.

c. Mixing and Blending

Iron Ore powder blended with Bentonite and other binding materials in

desired proportion. Small quantity of water is added during blending

operation. This raw mix is ready for Pellet making and store in feed

hopper.

d. Pelletization

Controlled quantity of raw mix is fed on disc Pelletizer. Some amount of

water is sprinkled for producing Pellets. These Pellets are passed through

Page 13: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 10

oversize and undersize screens. Sized Pellets are then sent to sintering

section.

e. Screening

Pellets produce in Pelletization sections are passed through oversize and

undersize screens. Rejects Pellets are sent back to raw mix silos sized

Pellets are fed in to Indurations Furnace.

f. Travel Grate Furnace

A Travel Grate Furnace is used for indurations of Pellets. This is divided

into 3 sections (Drying–Preheating–Heating). Hot Pellets at around 950ºC

to 1000ºC from this Travel Grate are dropped into the Kiln for further

strengthening.

g. Rotary Kiln

Rotary Kiln receives Pellets from the Indurations Furnace where Pellets

have to withstand at high temperature approx. 1050ºC – 1200ºC. Here the

Pellets gain more hardness due to high temperature. Furnace Oil /

Producer Gas will be used as a fuel inside the Kiln. After the Kiln the Pellets

are passed to the Grate Cooler.

h. Cooler

Grate Cooler receives hot Pellet with temperature up to 1200ºC coming

from Rotary Kiln. Cooler has its own blowers to blast the air from bottom.

The hot air from the first zone is used as a combustion air in kiln. The hot

blast of the second zone is used in the pre-heating zone-1 of travel grate

and the air from the 3rd zone is discharged to the atmosphere through

chimney as its dust concentration is well within the permissible limits of

pollution norms. Volume of cooling air in all the three zones is regulated

automatically through the temperature control loops as per the

requirement. Cold Pellets at about 100ºC are discharged on conveyors and

they are quenched by the cold water for further cooling and then

conveyed to the stock pile/ loading hoppers.

i. Stacking

Page 14: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 11

The screened Pellets of required size duly cooled at air cooler and

subsequently natural cooling are transported to Bunkers

j. Recovery of Dust and Spillage

Spillage from drying zone and preheating zone of traveling grate, dust

from the wind box of traveling grate and dust collected through de-duster

of technological process shall meet and will be sent to dust bin via belt

conveyor, after they are ground together with iron ore concentrate at

grinding mill. Spillage (dry Pellets) produced at the discharge end of

traveling grate will be fed into the kiln from the feed chute of the kiln feed

end by bucket elevation. Almost all the dust and spillage are re-circulated

and recovered.

Process flow diagram

Page 15: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 12

3.5.2 Steel Melting Shop

Semi-finished steel in the form of Steel Ingots & Billets is manufactures through

Induction Furnace with Concast that works on the principle of induction melting

of scrap/ Pig Iron with the help of electric power. An alternating electromagnetic

field induces eddy current in the metal so that the electrical energy converts into

heat whose quantity depends on the resistively of the charge. If the charge

consists of the metal scrap, chips other metal rejections then the eddy currents

arise between separate pieces of charge because high contact resistance. So small

charge pieces required increase frequency of current that feeds the induction

heater in order to speed up melting of the charge. Induction furnaces operate on

current of commercial frequencies (50 HZ) or on current of higher frequencies

from 500 to 2000 Hz. Induction furnaces are beneficial in steel making for low

melting loss.

An Induction furnace constitutes a single larger primary coil made of water-

cooled copper tube. The working voltage impressed across the terminals of the

coil. These furnaces have a great much application for melting of iron, Steel and

Nonferrous. This type of furnace has a rammed lining. The ramming mantel silica

mass contains should more than 96% silica and minimum of Al2O3 & Fe2O3. Before

ramming the material a steel template kept inside the furnace and rammed the

material between the template and the insulated coil of the induction heater. To

minimize the consumption of electric power and cut down the melting period the

crucible wall must be as thin as possible. During running the furnace one must

keep watch on the state of lining because it operates under most unfavorable

condition. The inside of crucible lining is in contact with liquid metal while its

outside surface contacts the water-cooled induction.

Charging: -

The pieces of scrap should be kept on the bottom gently to avoiding impacts into

a compact heap. The scrap pieces / Pig Iron should be in small size that provide

good compacting of the batch without leaving spacing between the charge and

crucible wall. This offer an advantage of quick melting of the charge with a

minimum power spent in the stage for the heat.

Page 16: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 13

The zone of a highest temperature during the meet lies in the power part of the

crucible therefore it is practical to place first high melting scrap on the crucible

bottom. Large and high melting pieces should stand parallel and close to the

crucible was while low melting components should be in the middle of the large

crucible. Small capacity furnaces are loaded manually and the large capacity

furnaces with the aid of buckets.

Melting: -

At the beginning of the melting the furnace works for 5 to 10 minutes on low

power until the surge of current fed from the generator disappear. The furnace

power is then brought up to a maximum. The charge melts with the crucible held

closed. When the charge approaches the fluid stages then the solid pieces are

pressed backed with a crow bar. The furnaces is then loaded to its capacity by

adding small size of scrap as soon as the charge melted, the stag is formed to

protect the metal from oxidation and to avoid reduce the melting loss. If the slag

generate in excess it should be skimmed off periodically, at the last to deoxidized

the metal with Ferromanganese, Silico-manganese and Ferro-silicon. Now the

metal is ready tap for either in ingot or billet casting.

Casting in Ingot mould: -

For casting ingot the metal temperature should be around 1560ºC/ 1570 ºC in

ladle. Liquid metal tap from furnace to ladle by the help of crane then the ladle in

the centered on the trumpet metal flows from the ladle bottom and filled the

ingot mould. Thus the ingot is ready.

Casting in B.C.M: -

Steel for making billet, the temperature of liquid metal from furnace to ladle, the

final metal temperature in ladle should be 80ºC. superheat from liquidious. Liquid

metal is storage in tundish through ladle then the tundish metal passes from the

various section of mould jacket that is as per requirement (100 X 100 mm, 125 X

125 mm, 160 X 160 mm, 200 X 200 mm) this is a continuous process, length of

billet of is cut as par requirement. Process flow chart is enclosed.

Plant facilities for Continuous Casting Machine

Billet caster:

Page 17: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 14

The billet caster shall be complete with ladle stand, mould assembly, strand guide

segments and supports withdrawal and straightening system, mould cooling

system, Cut off equipment including length measuring device, Marking machine

etc. Requisite dummy bar and facilities for Dummy bar disconnecting and a

dummy bar receiver will be included.

Auxiliary equipment :

The auxiliary facilities required for the Billet caster will be included. This will

include operating platform, cooling bed, ventilation system for spray chambers,

equipment for collection and disposal of crop-ends, Repair and assembly facilities

for moulds, and segments, Tundishes, Tundish preparation facilities including

tundish drying station, Hydraulic system and Centralized lubrication system, scale

handling system.

Electrical Equipment:

The electrical equipment for the caster will include the drives, HT switchgear, LT

switchgear, control desks, cabling and accessories.

Instrumental and automation:

A modern DCS process automation system shall be provided for control of process

function, sequencing and interlocking and to execute safely controls. Specific

features shall include mould level control, computer aided quality control, and

process field instruments comprising measuring units, transmitters, load cells,

actuators, Programmable controllers and PCs and communication system.

Plant facilities for Ladle Furnace

The LF installation will be single station system with provision for arc heating,

inert gas stirring, and addition of ferroalloys and additives. The LF will be

complete with transformer, Ladle stirring system Aluminum wire feeder, Carbon

injecting device, additives storage and addition system, Sampling and

temperature measuring device. A fume extraction and cleaning system consisting

of bag filters, ID fan and chimney with the related ductwork will be provided.

Auxiliary equipment:

Page 18: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 15

The auxiliary facilities required for the LF will be included the transfer cars, slag

handling facility, hydraulic and lubrication systems, Electro nipping station.

Argon oxygen decarburisation unit (AOD) / Vacuum degassing/ Vacuum oxygen

decarburisation (VD/VOD)

One AOD/VOD converter of replaceable shell design will be installed for

production of different grades of stainless steels. Treatment of the liquid stainless

steel at AOD/VOD, stainless steel requiring vacuum treatment will be brought to

vacuum degassing unit. After tapping heat from AOD/VOD, alloy steel requiring

vacuum treatment will be brought to vacuum degassing unit.

Ladle will be placed inside the vacuum tank after which tank will be sealed with

tank cover. Vacuum pump will be switched on and argon gas will be

simultaneously purged in the liquid steel during entire vacuum treatment. Sample

will be taken and, if necessary, alloying elements will be added through vacuum

lock hopper to get the desired chemical composition. Vacuum degassed steel will

be shifted to ladle turret for casting into billets.

3.5.3 Rolling Mill Unit:

Rolling mill unit comprise of Re-heating furnace, Roughing Mill, Intermediate Mill,

Finishing Mill, Finishing Section and Auxiliary Equipments.

Reheating furnace

A pusher type furnace has been envisaged for the heating of billets. The furnace

will be end charging and side discharging. It will have single row as well as double

row charging facility. In priority rolling mill will be operated on hot charging basis

i.e. ingots/ billets will be directly rolled in rolling mill without heating. In case

Page 19: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 16

heating will be required then the Producer gas will be utilized as primary fuel and

Furnace oil will be utilized as secondary as well as auxiliary fuel in pusher type of

re-heating furnace of rolling mill. The furnace combustion system will comprise of

air blowers, coal/ FO storage, supply and preheating system and other associated

facilities. The product of combustion will leave the furnace at charging end and

exhausted through underground flue tunnel and passed through a metallic

tubular recuperator before finally let off to a self-supporting steel chimney of

sufficient height. A set of instrument will be used for smooth operation of the

furnace.

Bar and round mill

A cross country type mill has been envisaged for the plant. The stands have been

grouped into roughing, intermediate and finishing groups. Roughing group will

have 4 (four) stands, intermediate group will have 8 (eight) stands and finishing

mill will have 8 (eight) stands. Roughing group of stands will be driven by one

motor. 4 nos. of intermediate stands will be driven by two motors and balance 4

nos. will be driven by a separate motor. Each stand of finishing group will be

driven by single motor. Necessary guides and troughs will be provided at entry

and exit of mill stands.

One wire rod out let has been provided in the mill. The wire rod line will have 4

stand block driven by a single motor through gear box. Coil forming and handling

of coil is provided.

Automated tilting, drop type tilter and feeding arrangement will be provided in

roughing group of stands. Repeaters have been provided in roughing /

intermediate stands as necessary.

Design provision has been made for introduction of slit rolling facility in future to

roll 8 mm, 10 mm & 12 mm rebars in two strands. The rebars discharged from the

mill will pass through a water cooling system comprising cooling pipes with high

pressure water nozzles for rapid water quenching. At the cooling pipes the bar

skin temperature will be reduced to about 600ºC. The core of the bar still

remains hot. This entrapped heat tempers the bar. This thermo-mechanical

Page 20: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 17

treatment of the bars increases tensile strength without adversely effecting

weldability and elongation properties. This process eliminates requirement of

cold twisting of bars for production of rebars.

A dividing shear, to cut the products to cooling bed length, will be located

immediately after the water cooling system. This shear will divide all products to

cooling bed lengths. Rake type cooling beds have been envisaged to receive the

rolled product. Cooling bed will be provided with incoming and outgoing roller

tables. One cold shear has been provided to cut the bars coming out of cooling

bed into commercial length of 6 to 12 m. The bar products will be formed into

bundles and will be strapped by strapping machine manually.

The finished products will be removed by overhead EOT crane and stored in the

storage area or dispatched through road vehicles.

3.5.4 Ferro Alloys Manufacturing Unit:

In Ferro alloy plant, Silico Manganese (Si-Mn), Ferro Manganese (Fe-Mn) and

Ferro Silicon (Fe-Si) is produced by smelting of Manganese ore with coke, coal,

quartz and dolomite. The smelting is a continuous process which will be done in

submerged arc furnace with a line voltage of 70-170V. The raw material premix

will be charged into the furnace near the electrodes through chutes. The

electrodes used are of self-baking type in which a series of cylindrical steel casings

Page 21: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 18

welded on the top of each other forms the electrode column in which solid green

carbon ‘paste’ blocks are added periodically from the top of the column. This

system takes advantage of the electric power used for the process to bake the

electrodes in place. The smelting process thus in submerged arc furnace produces

the ferro alloys.

Manufacturing Process Flow Chart is as below:

3.6 Raw Material Requirement

Raw material required for the proposed expansion is as followed:

a. For Iron Ore Pellet Plant (0.6 million Tons/ year):

Sr. No.

Raw Material Quantity (TPA)

Source Mode of Transport

1. Iron ore fines 663060 Local / Orissa

Sector

By Rail & Road through

covered trucks 2. Coke 21450 Indonesia / South

Africa / Australia Through sea route / rail

route / by road

3. Limestone 9020 Chhattisgarh / Madhya Pradesh

By Rail & Road through covered trucks

4. Bentonite 6800 Gujarat By Rail & Road through covered trucks

Submerge Electric

Arc Furnace

Feeders (for proper proportion)

Quartz

Manganese Ore Coke

Ferro Alloys

Slag

Page 22: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 19

b. For Induction Furnace unit (3 x 10 MT = 90000 TPA)

Sr.

No.

Raw Material Quantity

(TPA)

Source Mode of

Transport 1. Sponge Iron 13500 In house generation ----

2. Scrap 19125 Chhattisgarh By road through covered road

3. Ferro Alloys 2025 In house generation ----

cc.. FFoorr RRoolllliinngg MMiillll ((11 xx 665500MMTT == 220000000000 TTPPAA))

Sr. No.

Raw Material Quantity (TPA)

Source Mode of Transport

1. Billets / Ingots 216600 In house generation ----

dd.. FFoorr FFeerrrroo SSiilliiccoonn uunniitt ((22 xx 99 mmVVAA))::

Sr. No.

Raw Material Quantity (TPA)

Source Mode of Transport

1. Quartz 16890 Chhattisgarh / Andhra Pradesh

By Rail & Road through covered

trucks

2. Pet coke 5600 Chhattisgarh / Bihar By Rail & Road through covered

trucks

3. MS Scrap 350 Chhattisgarh By Road through covered trucks

4. Electrode paste

840 Andhra Pradesh (Vizag)

By Rail & Road through covered

trucks

ee.. FFoorr SSiilliiccoo MMaannggaanneessee uunniitt ((22 xx 99 mmVVAA))::

Sr. No.

Raw Material Quantity (TPA)

Source Mode of Transport

1. Manganese Ore 31780 MOIL / OMC By Rail & Road through covered

trucks

2. Mn. Slag 18000 In house generation ----

3. Quartz 7800 Chhattisgarh / Andhra Pradesh

By Rail & Road through covered

trucks

4. Pet coke 3160 Chhattisgarh / Bihar By Rail & Road through covered

trucks

ff.. FFoorr FFeerrrroo MMaannggaanneessee uunniitt ((22 xx 99 mmVVAA))::

Sr. No.

Raw Material Quantity (TPA)

Source Mode of Transport

1. Manganese Ore 53400 MOIL / OMC By Rail & Road through covered

trucks

Page 23: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 20

Sr. No.

Raw Material Quantity (TPA)

Source Mode of Transport

2. Pet coke 30780 Chhattisgarh / Bihar By Rail & Road through covered

trucks

3. MS Scrap 2060 Chhattisgarh By Road through covered trucks

4. Electrode Paste 6160 Andhra Pradesh (Vizag)

By Rail & Road through covered

trucks

3.7 Water requirement and its Source

Water required for the proposed expansion project will be 1400 KLD. Water

required will be supplied by Chhattisgarh Ispat Bhumi Ltd.

3.8 Solid Waste Generation and its Disposal:

Sr. No.

Type of Solid waste Quantity (in TPD)

Disposal Proposed

1. Ash / Dust generated from Pellet plant

= 27 Will be recycled in pellet making process.

2. Tar generated from Producer gas plant

= 2 Will be given to coal tar distillation units

3. Slag from SMS = 90 Slag generated from SMS will be given to slag crushing units.

4. Mill scales from Rolling mill

= 50 Reused in SMS

5. Slag from Fe-Mn = 100 To be reused in manufacture of Silico

Manganese as it contains high MnO2 and Silicon

6. Slag from Fe-Si = 13 To be used in cast iron foundries.

7. Slag from Si-Mn = 103 To be used for road construction / slag cement manufacture

*****

Page 24: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 21

Chapter – 4: Site Analysis

4.1 Connectiv ity

The proposed site is well connected with Road – Rail network. The following

table gives brief regarding connectivity of the proposed site:

Component Description

Road = NH – 200 = 2.4 km Rail = Nearest station – 7.3 km (Mandhar RS) Mumbai-Howrah mail line

Air = Raipur Air Port – 23 Kms.

Sea Port = Vishakapatanam – 505 Kms.

The location has a big advantage in its closed proximate to its market.

Traditionally, iron manufacturing units have tendered to cluster in the eastern

zone of India namely in the state of Jharkhand, Orissa and Chhattisgarh because

of easy availability of major raw input iron-ore and coal. Infrastructural and

other utility services are easily available. Skilled and un-skilled laborers are also

available easily.

Below mentioned table gives brief regarding environmental setting of the project

site

Sr. No. Particulars Distance from the site

1. National Park = No national Park is situated within the 15 km radial distance periphery

2. Wild life sanctuaries = Nil 3. Eco Sensitive Areas = Nil

4. Forests = Nil

5. Surface water bodies = Kharun River – 1.8 Kms. Kulhan nala – 7.8 Kms.

6. Costal Regulation Zone [CRZ] = Nil

7. Industrial Area = The unit is located adjacent to Phase – 2 of Siltara Industrial Area, Raipur

4.2 Land use

Existing plant is located adjacent to Phase # 2, Siltara Industrial Growth Centre.

The terrain of the land is almost plain.

Page 25: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 22

4.3 Topography

The topography of the land is flat without undulations.

4.4 Existing land use pattern

APIIPPL is an existing plant, partly located in Siltara Village, adjacent to Phase # 2,

SIltara Industrial Area, and its adjacent Village Sondra, Raipur Tehsil & District,

Chhattisgarh. Private owned land is diverted for Industrial purpose. 97.75 acres of

land is in possession of management and proposed expansion will be taken up in

the existing plant premises.

There are no ecologically sensitive places like national park, sanctuary,

biosphere reserve, reserve forest etc. around 10 Kms. radius of the site. There

is no route of migratory animals within the project site. The site satisfies the

criteria stipulated by the Ministry of Environment & Forest, Government of India

for setting up of industries.

4.4 Existing infrastructure

Water supply in most of the villages is available. Inter-village transport facility is

available only for the selected villages. While educational facilities & health

facilities are not encouraging in most of the villages. There is well established

road connection.

4.5 Climatic data from secondary sources

Raipur has a tropical wet and dry climate, temperatures remain moderate

throughout the year, except from March to June, which can be extremely hot. The

temperature in April–May sometimes rises above 48 °C (118 °F).These summer

months also have dry and hot winds. In summers, the temperature can also go up

to 50 °C. The city receives about 1,300 millimetres (51 in) of rain, mostly in the

monsoon season from late June to early October. Winters last from November to

January and are mild, although lows can fall to 5 °C (41 °F).

*****

Page 26: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 23

Chapter – 5: Planning Brief

5.1 Planning Concept

API Ispat & Powertech Pvt. Ltd. is existing steel plant at Siltara village, near Phase

– II, Siltara Industrial Area, Tehsil and District: Raipur, Chhattisgarh. Now as a part

of expansion, APIIPPL is planning to enhance the capacity of Induction Furnace,

Rolling Mill and establish new unit of Pellet plant, EAF and Ferro alloys

5.2 Population Projection

The project will be providing direct employment to nearly 100 workers. The local

persons will be given preference in employment as per the qualification and

technical competencies. Necessary training will be given to train the unemployed

youths of the nearby villages as per the qualification and technical competencies.

Indirect employment opportunities will be created in the periphery of the project

automatically as the project started operation in the region. In order to

operate and maintain the plant facilities, including its technical general

administration needs, the manpower for the proposed expansion will be 100.

The above manpower covers the top management, middle and junior level

executives and other supporting staff including workforce.

5.3 Land use Planning

APPIIPL is an existing plant. Land is converted for Industrial purpose. 97.75 acres

of land is in possession of management and proposed expansion will be taken up

in the existing plant premises.

5.4 Amenities / Facilities

Facilities like canteen, rest room and indoor games facilities has already been

provided in the existing plant as basic facilities to workers. No other additional

facilities are proposed.

*****

Page 27: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 24

Chapter – 6: Proposed Infrastructure

6.1 Industrial Area (processing Area)

The main plant area comprises of iron ore handling area, storage area, crushing

sizing area, iron ore beneficiation unit etc.

The major equipment and facilities envisaged for the pelletizing plant are

described below

The pelletizing plant will mainly consist of the following sections:

Storage and handling of iron ore fines

Storage, handling and preparation of binder and additive

Iron ore improvement

Proportioning and mixing

Balling, in duration and cooling

Finished product storage

6.2 Residential Area (non Processing Area)

No colonization is proposed; however facilities like canteen, rest room and indoor

games facilities will be provided in the proposed plant and one Admin building is

also proposed.

6.3 Green Belt

More than 1/3rd

of total land available is reserved for plantation i.e. greenery.

Greenbelt development plan

Local DFO will be consulted in developing the green belt.

Greenbelt of 33% of the area will be developed in the plant premises as

per CPCB guidelines.

15 m wide greenbelt is being maintained all around the plant.

The tree species to be selected for the plantation are pollutant tolerant,

fast growing, wind firm, deep rooted. A three tier plantation is proposed

Page 28: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 25

comprising of an outer most belt of taller trees which will act as barrier,

middle core acting as air cleaner and the innermost core which may be

termed as absorptive layer consisting of trees which are known to be

particularly tolerant to pollutants.

6.4 Social Infrastructure

Social infrastructure will be developed as per need based in the Villages of the

close vicinity of the project.

6.5 Connectiv ity:

The proposed site is well connected with Road – Rail network. The following

table gives brief regarding connectivity of the proposed site:

Component Description

Road = NH – 200 = 2.4 km Rail = Nearest station – 7.3 km (Mandhar RS) Mumbai-Howrah mail line

Air = Raipur Air Port – 23 Kms.

Sea Port = Vishakapatanam – 505 Kms.

The location has a big advantage in its closed proximate to its market.

Traditionally, iron manufacturing units have tendered to cluster in the eastern

zone of India namely in the state of Jharkhand, Orissa and Chhattisgarh because

of easy availability of major raw input iron-ore and coal. Infrastructural and

other utility services are easily available.

Skilled and un-skilled laborers are also available easily.

6.6 Drinking Water Management

It is estimated that 20 KLD of water will be required for domestic purpose during

operation of expansion project.

6.7 Sewerage System

Domestic effluent collected through toilet blocks and other areas will be collected

through well designed sewer network and send to Septic tanks followed by soak

pits. No effluent will be left-out after Soak pits.

Page 29: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 26

6.8 Industrial Waste Management

Closed circuit system will be adopted in the proposed expansion project. Hence

zero effluent discharge will be maintained. Only waste water generated will be

sanitary waste water, which will be treated in septic tank followed by soak pit.

6.9 Solid waste Management & its Disposal Sr.

No.

Type of Solid waste Quantity

(in TPD)

Disposal Proposed

1. Ash / Dust generated

from Pellet plant

= 27 Will be recycled in pellet making

process. 2. Tar generated from

Producer gas plant = 2 Will be given to coal tar distillation

units

3. Slag from SMS = 90 Slag generated from SMS will be given to slag crushing units.

4. Mill scales from Rolling mill

= 50 Reused in SMS

5. Slag from Fe-Mn = 100 To be reused in manufacture of Silico Manganese as it contains high MnO2 and Silicon

6. Slag from Fe-Si = 13 To be used in cast iron foundries.

7. Slag from Si-Mn = 103 To be used for road construction / slag cement manufacture

6.10 Power Requirement & Its Source

Power required for the proposed project will be sourced from captive and nearby

grid.

*****

Page 30: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 27

Chapter – 7: Rehabilitation & Resettlement (R & R) Plan

No rehabilitation and resettlement is required as there are no habitations in the

existing plant site.

*****

Page 31: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

Page No.: 28

Chapter – 8: Project Schedule & Cost Estimates

8.1 Project Schedule

The plant will be implemented in 18 months from the date of receipt of

Environmental Clearance from the Hon’ble MoEF & NOC from CECB.

8.1 Project Cost

The estimated cost for the proposed expansion project will be Rs.240 crores.

*****

Page 32: API Ispat & Powertech Pvt. Ltd. - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_29_Nov_… · API Ispat & Powertech Pvt. Ltd. is existing steel

AAPPII IIssppaatt && PPoowweerrtteecchh PPvvtt.. LLttdd..

Expansion of Steel Plant Pre-feasibility Report

29

Chapter – 9: Analysis of Proposal

9.1 Financial and Social Benefits

With the implementation of the proposed project, the socio-economic status of

the local people will improve substantially. The land rates in the area will improve

in the nearby areas due to the proposed activity. This will help in upliftment of

the social status of the people in the area. Educational institutions will also come-

up and will lead to improvement of educational status of the people in the area.

Primary health centre will also be developed by us and the medical facilities will

certainly improve due to the proposed project.

9.2 Socio-economic Dev elopmental Activ ities

The management is committed to uplift the standards of living of the villagers by

undertaking following activities / responsibilities as the part of Corporate Social

Responsibility.

Health & hygiene

Drinking water Education for poor Village roads Lighting

Health & Hygine

Personal and domestic hygiene, Maintaining clean neighborhood, Weekly health camps offering free-check up & medicines Ambulance services

Education & drug de-addiction, aids.

Drinking Water

Making drinking water available at centralized locations in the village,

Supporting Education

Providing books to all poor children, Conducting annual sports festival in the village schools, Providing amenities like fans, lavatories, Maintain play ground etc.

*****