APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

22
APC at NJT From Zero to 100% Dave Rynerson October 16, 2014

Transcript of APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Page 1: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

APC at NJTFrom Zero to 100%

Dave Rynerson

October 16, 2014

Page 2: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Smart Bus ProjectAVA on new buses since 2008

Page 3: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Bus Routes:204 NJT

46 subcontract

Peak:1,900 NJT

200 subcontract

Page 4: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Lincoln Tunnel Toll Plaza and Express Bus Lane

Page 5: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Departure Time and Gate

Page 6: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Smart Bus Project Calendar Requirements

Real-Time Customer Info (MyBus NOW) Computer Aided Dispatch Passenger Counting Single-Point Sign On

Page 7: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Calendar

Page 8: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Secrets to Success

The HASTUS calendar Integrated system maintenance Short lag time for data availability New data types

Running time Load factors On time performance

Page 9: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Running Time

Page 10: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Load Factors

Page 11: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Categorized for Title VI

Page 12: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

On Time Performance

Page 13: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Issues: Accuracy

First time point Large bus terminals High on/off counts Inclusion of driver, data collector, and non-riding

customers with questions

Page 14: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

APC Coverage

Page 15: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Issues: Coverage

Manual vs. Schedule logon Discards Unknown stops Lead time in data prep and deployment Missing deadhead run time

Page 16: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

PM Peak from the Port Authority Bus Terminal is particularly difficult

Page 17: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Issues: Data Maintenance

Scheduling, GIS, and bus stop data must be integrated

Page 18: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

CASSSchedules

DailyDispatch

CustomerInformation

GISRoutes

Systems in 2004

BSI Bus Stops

Page 19: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

HASTUSSchedules

DailyDispatch

BSI/GIS/Smart Bus

CustomerInformation

Internal (e.g.APC) Info

Systems in 2014

Page 20: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Stops & Time Points in GIS

Page 21: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Conclusions

Accuracy and coverage are still issues

APC has been transformational

The transformation is just getting started!

Page 22: APC at NJT From Zero to 100% Dave Rynerson October 16, 2014.

Questions?