“Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets,...
Transcript of “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets,...
![Page 1: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/1.jpg)
1June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
““Voltage Stability Problems in the Power System of Greece Voltage Stability Problems in the Power System of Greece and Measures taken at System Design Stage, Daily Operation and Measures taken at System Design Stage, Daily Operation
and Real Timeand Real Time””
Thanos Thanos KoronidesKoronidesHellenic Transmission System OperatorHellenic Transmission System Operator
![Page 2: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/2.jpg)
2June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Power System in Power System in HTSOHTSO’’ss ResponsibilityResponsibility
Electric Power Transmission System• 400 kV Bulk Transmission• 150 kV In parallel with 400kV• Interface 400kV/150kV 43 Autotransformers of 250 or 280
MVA
Load of the System• Summer Peak at 9500 MW, last year (estimated)• Load evolution rate about 4% average last 10 years
![Page 3: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/3.jpg)
3June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Μηνιαίες αιχµές για την περίοδο 1997-2010
5,05,56,06,57,07,58,08,59,09,5
10,010,511,011,512,0
Ιαν Φεβ Μαρ Απρ Μάϊος Ιουν Ιουλ Αυγ Σεπτ Οκτ Νοε ∆εκ
µήνας
GW
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
Monthly Peaks and projections 1997-2010
![Page 4: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/4.jpg)
4June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Monthly Peaks since 1997
1997 1998 1999 2000 2001 2002 2003 2004 2005Jan 5768 6202 6212 6874 7076 7537 7408 8075 8102Feb 5875 5967 6288 6661 7055 6820 7832 8012 8393Mar 5658 6007 6131 6507 6736 6996 7488 7639 8016Apr 5614 5550 5684 5984 6343 6703 7145 7160 7445
May 5627 5572 5789 6422 6730 6521 7059 6847
June 6527 6703 6896 7697 7664 8587 8595 8448July 6703 7370 7364 8529 8598 8922 9040 9500*
Aug 6108 6973 7108 7603 7841 7694 8552 8582Sept 5787 6126 6120 6860 7121 6990 8537 8288Oct 5847 5608 5951 6465 6572 6843 6919 7153Nov 5685 6076 6374 6566 7002 7064 7358 8221Dec 6261 6718 6671 7182 7788 7767 8186 8354
Year 6703 7370 7364 8529 8598 8922 9040 9500*
![Page 5: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/5.jpg)
5June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Μοντέλα φορτίου-καιρού ηµερησίων αιχµών για την περίοδο Μαρ 1997 - Φεβ 2005
0
1000
2000
3000
4000
5000
0 5 10 15 20 25 30 35 40 45οC
MW
97-98
98-99
99-00
00-01
01-02
02-03
03-04
04-05
Load Temperature Dependency since 1997
Βασικό φορτίο ηµερησίων αιχµών για την περίοδο Mαρ 1997 - Φεβ 2005
010002000300040005000600070008000
Ιαν Φεβ Μαρ Απρ Μαιος Ιουν Ιουλ Αυγ Σεπτ Οκτ Νοε ∆εκ
1997
1998
1999
2000
2001
2002
2003
2004
2005
Basic Load Since 1997
High load-temperature Dependency
Air Conditioning and Pumping for Irrigation
Lot of MVARs
![Page 6: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/6.jpg)
6June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Main Features of the Power SystemMain Features of the Power System
Existing Production• Most of the Production ( ~68%) in the North• Most of the Load (~45%) in the South• Several Old Units in the South• Lack of 400kV Network in the very South
New Production:• Official Opening of the Market, 2001Zonal UOC pricing System for Generators in 3 zones North-Capital-
South, Most expensive in the North –zero near the Capital• Only one unit (300 MW) built after the opening. This in the North
![Page 7: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/7.jpg)
7June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Transmission System Expansion, very difficult• Licensing very complex and time consuming• Reaction of local communities – even to GIS substations with
cable connections
Voltage Stability Problems
• First incident 1996, at about 6500MW load• Second Incident 2004, 12 July voltage collapse and partial
black out at about 9300 MW
![Page 8: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/8.jpg)
8June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Voltage Collapse as recorded in Generating Stations in the South __
The Center__ and the Capital Area -- --
![Page 9: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/9.jpg)
9June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
![Page 10: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/10.jpg)
10June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Measures Taken at the Planning StageMeasures Taken at the Planning Stage
For the Olympics the following was planned• About 500 MVAR of Capacitors mainly at 20 kV including 100
MVAR at 150 kV• Five ATRs (280 MVA each) in the South• New 400/150 kV S/S 10km from the center of Athens• 250 MVA new GTs near Athens
Was available before July 12• About 400 Mvars (capacitors) constructed but ~100Mvars
commissioned, total commissioned few days after• 3 out of 5 ATRs commissioned, 2 commissioned few days after• 100 MVA of new GTs available the rest finished later• 400/150 kV S/S never finished due to local community reaction
![Page 11: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/11.jpg)
11June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
During O.G. 2004During O.G. 2004
Before the Olympics the majority of planned enhancements completed, except the new 400/150 kV S/S because of local reaction.
Everything went smooth during the games, it is characteristic that the auxiliary gen sets in Olympic Installations were never used not even for a minute during the games.
![Page 12: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/12.jpg)
12June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Other Measures for the FutureOther Measures for the Future
• Further Compensation of the reactive Load(about 200 MVAR per year)
• Load Management incentives and Load Reduction AutomationFirst Measures Taken Summer 2005
• Provision for Market Splitting into two areas in the new Grid Code (signed in April) in conjunction with a 2 zones UOC pricing for Generators
![Page 13: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/13.jpg)
13June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Measures Taken in Daily OperationMeasures Taken in Daily Operation
Use of OPF
• OPF program available, integrated in the EMS platform• Typically used day ahead for the next day operation and on the
spot with real time data• Use of OPF for tuning taps of 400/150 kV Autotransformers
![Page 14: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/14.jpg)
14June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
OPF in the Day Ahead Operation
• Read unconstrained generationschedule from Market Database
• Read from Market Database thesystem load forecast.
• Use expected topology, accordingto the maintenance plan, solve aPower Flow and check for possibleviolations on network branches.
• In case of violations, solve an OPF for generation rescheduling thatcorrects these violations.
![Page 15: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/15.jpg)
15June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
OPF and Network Programs in Real Time Operation
![Page 16: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/16.jpg)
16June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Voltages in the south before and after OPF in critical winter day 2003
![Page 17: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/17.jpg)
17June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Change of tap settings
![Page 18: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/18.jpg)
18June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Unit MVar controls
![Page 19: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/19.jpg)
19June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Increase of System Loadability Limits before and after OPF
86008600 9200
![Page 20: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/20.jpg)
20June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Athens area loadability limits before and after OPF
![Page 21: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/21.jpg)
21June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
OnOn--Line Voltage Security Assessment in the Line Voltage Security Assessment in the HTSO Control CenterHTSO Control Center
![Page 22: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/22.jpg)
22June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
VSA in the NCCVSA in the NCC
VSA implementation in the Control Center of HTSO was developed in the frame of a research project named OMASES partially funded by EU funds.
OMASES-VSA integrates two VSA software packages,Secure Operation Limits (SOL) and contingency filtering which rely on the ASTRE software developed at the University ofLiège.
Computation of Post Contingency Loadability Limits and theproduction of PVcurves rely on the WPSTAB softwaredeveloped at the National Technical University of Athens.
![Page 23: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/23.jpg)
23June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
VSA MAIN FUNCTIONSVSA MAIN FUNCTIONS
System Stress: Security margins computed for a pattern of system stress, i.e. a change in load and generation which makes the system weaker by increasing power transfer over long distances.
Loadability Limits: how much the system can be stressed before reaching instability. Pre-contingency loadability limits and Post-contingency Loadability limits (PCLLs) (apply contingency, then stress)
Secure Operation Limits For a given direction of stress, the SOL corresponds to the most stressed operating point such that the system can withstand any contingency of a specified list (stress first, then apply contingencies)
Diagnostic Tools in Expert Mode In case of voltage instability ranking of bus active and reactive power injections, thereby pointing out where generation should be rescheduled, or load shed.
![Page 24: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/24.jpg)
24June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, SwitzerlandPackage to be archived
FRONTEND DATABASE
ASTRE
Data Loader Program
WPSTAB
Data Loader
Program
HTTP server
Data files
Results
Log files
![Page 25: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/25.jpg)
25June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
One Critical CaseOne Critical Case Summer 2002
no.contingency
namemargin(MW)
329 LINE_CON_ΤΜΟΥ∆ΑΝ-ΜΟΥ∆.1 0296 LINE_CON_ΜΟΥΡΤ-ΜΕΣΟΓ.1 0228 LINE_CON_ΚΘΕΣ-ΣΧΟΛΑΡ.1 0312 LINE_CON_ΜΕΣΟΓΓ-ΚΕΡΚ2.1 0109 LINE_CON_ΑΡΓ2-ΑΡΓ1.1 73347 LINE_CON_ΣΧΗΜ-ΘΗΒΑ.1 9469 GEN_CON_Κ_ΛΑΥΡΙΟ.GFIC.UN 14658 GEN_CON_ΛΑΥΡΙΟ.GFIC.GEN2.UN 16790 LINE_CON_ΑΓΡΑΣ-ΣΚΥ∆ΡΑ.1 292388 LINE_CON_ΦΙΛΙΠ-ΑΜΦΙΠΟ.1 32422 GEN_CON_ΑΓ.ΓΕΩΡΓ.GEN9.UN 470
all other contingencies > 668
![Page 26: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/26.jpg)
26June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
National PV curve without Contingency National PV curve without Contingency (500 MW margin)(500 MW margin)
Summer 2002
![Page 27: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/27.jpg)
27June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
National PV curve for Contingency 69National PV curve for Contingency 69Summer 2002
![Page 28: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/28.jpg)
28June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
LoadabilityLoadability ––Athens Area Load after Contingency 69Athens Area Load after Contingency 69Summer 2002
![Page 29: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/29.jpg)
29June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
LoadabilityLoadability ––Central Area Load after Contingency 69Central Area Load after Contingency 69Summer 2002
![Page 30: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/30.jpg)
30June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
The PV curve pre BThe PV curve pre B--O Conditions (2004). O Conditions (2004). LoadabilityLoadability limit is 9390 limit is 9390 ΜΜW (400 MW in the South out W (400 MW in the South out
the previous day) and the margin is only 40 MW.the previous day) and the margin is only 40 MW.
0.72
0.74
0.76
0.78
0.8
0.82
0.84
0.86
0.88
0.9
9050 9100 9150 9200 9250 9300 9350 9400
Vol
tage
s (p
.u.)
Area Load (MW)
LONG-TERM SIMULATION
710
2 ATRs and 400 MVARs not commissioned
2 Units went off
Several Lines in maintenance
![Page 31: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/31.jpg)
31June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
LoadabilityLoadability after loss of Aliveriafter loss of Aliveri--3 unit. System 3 unit. System collapse due to voltage instability.collapse due to voltage instability.
0.7
0.72
0.74
0.76
0.78
0.8
0.82
0.84
0.86
0.88
0.9
8850 8900 8950 9000 9050 9100 9150 9200 9250 9300 9350 9400
Vol
tage
s (p
.u.)
Area Load (MW)
LONG-TERM SIMULATION
710
![Page 32: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/32.jpg)
32June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Loss of AliveriLoss of Aliveri--3 unit, but 132 3 unit, but 132 MvarMvar of capacitor banks of capacitor banks available (were commissioned 10 days after). The system available (were commissioned 10 days after). The system could withstand the loss of the unit with a margin of 70 could withstand the loss of the unit with a margin of 70
MW.MW.
0.74
0.76
0.78
0.8
0.82
0.84
0.86
0.88
0.9
0.92
9100 9150 9200 9250 9300 9350 9400 9450
Vol
tage
s (p
.u.)
Area Load (MW)
LONG-TERM SIMULATION
710
![Page 33: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/33.jpg)
33June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
0.74
0.76
0.78
0.8
0.82
0.84
0.86
0.88
0.9
0.92
9150 9200 9250 9300 9350 9400 9450 9500
Vol
tage
s (p
.u.)
Area Load (MW)
LONG-TERM SIMULATION
710
Capacitors as previous slide and 2 ATRs available, with unit Aliveri-3 out, the system could go up to
9460 ΜW(100 MW of margin), with this unit in up to 9650
(300MW margin)
![Page 34: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/34.jpg)
34June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
ConclusionConclusion 1/21/2
• Load Generation inbalance exposes the System in Voltage problems and instability
• Attracting new generation near the load is difficult in the open market environment , unless special measures and market rules are taken. In new grid code in Greece provision exists for market splitting (north-south). Also Generators are charged in two zones for UOC. HTSO is also allowed to procure units under special contracts
• System expansion is becoming more and more difficult. Some communities even react to GIS substations with cable connections.
![Page 35: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/35.jpg)
35June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
ConclusionConclusion 2/22/2
• Enhancements within existing substations , more ATRs linking 400kV/150 kV is improving the situation
• Better compensation, capacitors at 20kV, 150 kV and SVCs are effective solutions with no environmental impact
• Tools in the control room are very important for the operator :Provide advice for new tap settings and reactive generation Improve the loadability limits of the systemPin point critical contingenciesPin point areas with most effective load rejectionGive confidence to the operator and Justify operators action
![Page 36: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/36.jpg)
36June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
AcknowledgementAcknowledgement
VSA implementation in the NCC of HTSO was developed in the frameof the EU sponsored project named OMASES (Open Market Access and Security Assessment System) with the contribution of the following companiesHTSO,ALSTOM, CESI,TRACTEBELand the UniversitiesNational Technical University of AthensUniversity of LiegeUniversity of GenovaStrathclyde
![Page 37: “Voltage Stability Problems in the Power System of Greece ... · June 5-8, 2005 Les Diablerets, Switzerland 3 Μηνιαίες αιχµές για την περίοδο 1997- 2010](https://reader034.fdocuments.us/reader034/viewer/2022050513/5f9d1650094d1205d944bc2d/html5/thumbnails/37.jpg)
37June 5June 5--8, 2005 Les 8, 2005 Les DiableretsDiablerets, Switzerland, Switzerland
Main ReferencesMain References
• G.P. Christoforidis D.G. Michos “Operational Experience With Optimal Power Flow At The Hellenic Transmission System Operator” Medpower2004, Cyprus
• C. D. Vournas, G. A. Manos, J. Kabouris, G. Christoforidis, G. Hasse, T. Van Cutsem “On-Line Voltage Security Assessment of the Hellenic Interconnected System”,2003 Bologna Power Tech IEEE
• A. Bihain, G. Burt, F. Casamata, T. Koronides, R. Lopez, S. Massucco, D. Ruiz-Vega, C. Vournas, “Advance Perspectives and Implementation of Dynamic Security Assessment in the Open Market Environment”,paper 39-101, CIGRE 2002.
• Christoforidis G., Kabouris J., Vournas C., and Van Cutsem T., “Investigation of Parameters Affecting Voltage Security of the HellenicInterconnected System”, 15th PSCC, Liege, Belgium, Aug. 2005.
• T. Van Cutsem, J. Kabouris, G. Christoforidis, C. D. Vournas : “Applicationof real-time voltage security assessment to the HellenicInterconnected system”, IEE Proceedings - Generation, Transmission andDistribution,Vol.152, No.1, pp. 123-131, Jan. 2005.