“Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over...

45
“Pushing the Limits of Constructability Pushes the Limits of Project Planning” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina Presented By: Chip Smith, PE – Woolpert Kate Labadorf, PE – City of Charlotte Storm Water Services Southeast Stormwater Association 2015 Annual Conference

Transcript of “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over...

Page 1: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

“Pushing the Limits of Constructability Pushes the Limits of Project Planning”

Case Study: Myrtle-Morehead SDIPCity of Charlotte, North Carolina

Presented By:Chip Smith, PE – Woolpert

Kate Labadorf, PE – City of Charlotte Storm Water Services

Southeast Stormwater Association 2015 Annual Conference

Page 2: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Presentation Outline

• Overview of Charlotte’s Flood Control Program• Myrtle-Morehead Project History• Phase 1 Constructability Issues Realized• Phase 2 Constructability Issues Under Design• Lessons Learned• Questions and Answers

Page 3: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

City Flood Control Projects

• Drainage system improvements for watersheds up to one square mile

• Typical planning, design and construction duration – 5 to 7 years

• Typical costs range from $500,000 - $10 million

• Annual Funding of $17.3 million

Page 4: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Problems:• Roadway flooding• Structural flooding• Stream erosion• Deteriorating infrastructure

4

High Water Marks

11024 Blue Heron Drive

Flood Control Project Types

Kingfisher Drive

Page 5: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Problems: • Road Flooding - 6 Roads• Structure Flooding - 20

structures• Deteriorating Infrastructure

Myrtle/Morehead Project

Parking deck flooding

Metal pipe with holes in bottom

Page 6: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Project History/Existing System Problems

• Project initiated in 2000 due to chronic flooding of Myrtle Square Apartments, Euclid Avenue, Myrtle Avenue, and Lexington Avenue

• Dilworth area was developed around a creek that was piped with various undersized culverts

• Existing culvert is located underneath and behind numerous houses and apartments

• Dilworth area is a designated Historic Area with homes exceeding $1M in value

Page 7: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Project Study Area

Project Area

Myrtle Square Condos

Dilworth Historic Area

Drainage Area Outfall

Arlington CondosFlooded Parking Deck

Low Areas

Page 8: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Project Study Area – Urban & Residential

McDowell Avenue Oriole Avenue

Page 9: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Project Study Area - Residential

Myrtle Avenue

Lexington Avenue

• Narrow Tree Lined Streets

• OH Utilities• On-Street Parking

Page 10: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Project Study Area - Residential

Myrtle Square Condominiums

Low Area

Existing Culvert in Courtyard

Page 11: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Project Study Area - Residential

Euclid Avenue “Sump”

Page 12: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Alternatives Considered

• Rehabilitation of Existing System– Results in Less than 2 Year LOS

• Upstream Detention for 10 Year LOS– Required 37 Ac-Ft of Storage

• Numerous Alignments for New Culvert• Other Potential Solutions

– Linear Storage– Storm Water Pump Station

Page 13: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Alternatives Considered

Charlotte Housing Authority

Alternative AlignmentsCharlotte Housing

Authority

37 Ac-FtPond

Page 14: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Alternative Chosen

Charlotte Housing Authority

Final Alignment

Page 15: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Project Design & Constructability Challenges

• Routing a 78” to 90” by-pass culvert through the Dilworth neighborhood streets at depths between 20 and 30 feet

• Tunneling under Morehead Street and replacing 80’ of the 54” water main (NCDOT Encroachment)

• Installing 90” culvert by open cut in McDowell Street (NCDOT Encroachment)

• Installing box culvert by squeezing it between a Public Relations firm and a Duke Over Head Transmission Line

Results in a monumental challenge of project planning & stakeholder involvement !

Page 16: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Impact of Constructability Challenges on Construction Costs

• Only 2 Bidders: $12.15M & $13.04M

• 150 LF of Tunnel 30 feet deep : $3.15M

• Sheeting and Shoring for Deep Open Cut: $600K

• Contaminated Soils and Groundwater: $520K

• 80 LF 54-inch Water Main Replacement: $300K

• Slow construction – 18 months for 1,400 LF : $7.58M

Page 17: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Phase 1 – Under Construction

Wray WardWray Ward

Wray WardWray WardWray Ward

Wray Ward

Dialysis Center

Duke Endowment HQ

Arts BBQ

Townhouses

Page 18: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Stakeholders• Property Owner and

Businesses• Charlotte Water – 54-

inch WM Replacement and sewer relocation

• CDOT - Multiphase Traffic Control Plans

• Department of Water Quality

• Duke Energy – OH & Duct Banks

• AT&T – Duct Bank Crossing

• Piedmont Natural Gas –Existing & Abandoned Gas Mains

• NCDOT – Encroachment Permit & Design Approval

Page 19: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Wray Ward

Existing 9’x6’ RCBC

New 10’x6’ RCBC Adjacent to Existing 9’x6’ RCBC

Existing 9’x6’ RCBC removed to install 2-9’x6’ RCBCs

Existing 9’x6’ RCBC

Duke Energy OH Transmission Line

Duke & AT&T Duct Banks

Page 20: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder
Page 21: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

New 10’x6’ RCBC Connection @ Sta. 0+00

Page 22: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Duke Energy OH Transmission Line Tower

Page 23: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Required Nighttime/Weekend Work

Page 24: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Wray Ward

Existing 9’x6’ RCBC

New 10’x6’ RCBC Adjacent to Existing 9’x6’ RCBC

Existing 9’x6’ RCBC removed to install 2-9’x6’ RCBCs

Existing 9’x6’ RCBC

Duke Energy OH Transmission Line

Duke & AT&T Duct Banks

Page 25: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Duke Energy Duct Bank Crossing

Page 26: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

McDowell Street Junction Box

New Culvert C/L

New 12 FT x 12 FT Junction Box

Page 27: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

12’ x 12’ Junction Box

9’x6’ Downstream

90” Upstream

Page 28: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

McDowell Street

New Culvert C/L

Page 29: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Oh No ! Another Utility Coordination

New Fiber Optic Line

New Culvert C/L

Page 30: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

McDowell Street – Parking Garage Entrance

Page 31: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

McDowell Street – Parking Garage Entrance - October 2015

Page 32: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Tunneling & Water Main Replacement

No Blasting within 10 feet of Water MainTunneling Stopped for W.M Replacement

WM Replacement Between Dec. and March

NCDOT Encroachment

Tunnel Location

Page 33: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

12’ SEM Tunnel

Page 34: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

54-Inch Water Main Replacement

Page 35: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

54-Inch Water Main Replacement

Page 36: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Duke Endowment, Arts BBQ, H&R Block

Arts BBQ

Duke Endowment HQ & Parking Garage

Tunnel Shaft ~ 33 Feet Deep

Only Access

H&R Block

Page 37: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Duke Endowment; Arts BBQ; & H&R Block

Page 38: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Duke Endowment; Arts BBQ; & H&R Block

Page 39: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Oriole Avenue Townhouses

Page 40: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Phase 2 – Final Design

Myrtle Square Apts

New Apts

CHA Redevelopment

90-Inch Pipe ~ 30 Feet Deep

78-Inch Pipe ~ 25 Feet Deep

InterconnectionsMain Driveway

Location Based on Preliminary Re-Development Plans

Page 41: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Phase 2 –Sequence of Construction Prior to 90” & 78” Pipe Installation

1. Relocate Existing Private Utilities to New Location

2. Remove and Replace Existing Sanitary Sewer Mains in conflict with 90” & 78” Pipe

3. Re-instate Sewer Service Laterals to maintain sewer service during construction

4. Install temporary water main to remove existing water main in conflict with 90” & 78” Pipe

Page 42: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Stakeholders

• Property Owners and Businesses• Duke Energy – Overhead Power Service• Cable TV & Telephone – Overhead Serve• Piedmont Natural Gas – Existing & Abandoned

Gas Mains• Charlotte Water – Water and Sewer Service to

Customers• CDOT - Traffic Control Plans

Page 43: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Phase 2 –Sequence of Construction For 90” & 78” Pipe Installation

1. Setup 200’ max road closure2. Trim tree branches to prevent damage3. Install “active” shoring for open cut installation4. Install 90” & 78” Pipe, MH’s, and Street Drainage5. Install Temporary Pavement Restoration6. At Completion of City Block – Install New Water

System and Final Pavement Restoration

Page 44: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Lessons Learned1. Improve Bid Advertising for Phase 2

– Increase Number of Bidders2. Additional Construction Location Restrictions

– Oriole Street Started Earlier Than Expected– Construction Vehicle Parking, Material Deliveries

3. Stakeholder Involvement Increases During Construction– Significant Utility Coordination During Design – “Tip of Iceberg”– Property Owner Coordination - Unrealistic Requests– Day-to –Day Activities – Garbage Collection; Mail Delivery

4. Costs of “Handcuffing” Contractor– Unrealistic weekend closures

All These Lessons Learned Will Be Applied to Phase 2 !We Are Confident There Will Be Others to Overcome !

Page 45: “Pushing the Limits of Constructability Pushes the Limits of ......Relations firm and a Duke Over Head Transmission Line Results in a monumental challenge of project planning & stakeholder

Questions ??