AE94.2 UPGRADING PROJECT
Stefano Traverso Federico BonzaniProduct DevelopmentProduct Development
AE94.2 Project Manager Head of [email protected] [email protected]
19th AE94 2 Users Conference19 AE94.2 Users ConferenceKuala Lumpur, December 2nd 2010
Contents
New development for Ansaldo Energia AE94.2New development for Ansaldo Energia AE94.2
F D l t d P d t O iFrame Development and Product Overview
AE94.2-Evo1 details
AE94.2-Evo2 overview
Summary and Conclusiony
Pag. 1Ansaldo Enegia 2010. All rights reserved
Contents
New development for Ansaldo Energia AE94.2New development for Ansaldo Energia AE94.2
F D l t d P d t O iF D l t d P d t O iFrame Development and Product OverviewFrame Development and Product Overview
AE94.2-Evo1 details
AE94.2-Evo2 overview
Summary and Conclusiony
Pag. 2Ansaldo Enegia 2010. All rights reserved
Product Development Roadmap
1075°C 33MAC1090°C 33MAC
UP TO 1075°C 41MAC
Availability Optimized
AE94 2 Evo2
Future Upgrades
1060°C 41MACUP TO 1075 C 41MAC
AE94 2 6+
AE94.2-Evo1
AE94.2-Evo2
New Compressorolut
ion
94.2-3
94.2-6
AE94.2-6+
TT1+
HCO
Opt.Comp.
Opt. HGP components.
New Burner 15ppm (methane)
New 3D Turbine B&V
1090°CEvo
94.2 3 TT1
CMF+
1075°C
Basis
1060°C
p p
1075°C 1090°C
Pag. 3Ansaldo Enegia 2010. All rights reserved
2010 201320071999÷2004Year of introduction
Technical Features for new AE94.2 Evo1/Evo2
Evo1/2Burner (HW7 package)
15ppm@1090°CISO
Evo1/2Mixing chamber (HW3 package)
Evo2Turbine (HW4 package)
Evo1/2extensive TBC protecting layer
Evo2New AE3D Turbine (I-IV stages)
Evo1Turbine (HW2 package)
Optimized Turbine (I-II stages)
Evo2Compressor (HW5 package)
New AE3D Compressor (I-V stages)
p ( g )
Evo1/2Hot Gas Casing (HW3 package)
extensive TBC protecting layer Optimized cooling flowsOptimized cooling flows
Upgrades Packages Upgrades Packages AE94 2 itAE94 2 it
TT1 1090TT1 1090°°C C or or
Pag. 4Ansaldo Enegia 2010. All rights reserved
over AE94.2 unitsover AE94.2 units ooMAC41@up to 1075MAC41@up to 1075°°CC
AE94.2 : Development Packages Benefits
@
94.2-6 94.2-6+ 94.2-Evo1 94.2-Evo215°C 15°C 30°C 30°C
GT VersionΔTT1 Benefit expected over 94.2-3@1060°C
Single Cycle, ISO conditions, Natural gas firing
+15°C +15°C +30°C +30°C
+7.3MW +10.6MW +14.6MW +29MW
+0.2pt% +0.5pt% +0.6pt% +2.0pt%
ΔTT1
ΔPower(*)
ΔEfficiency(*)
2004 2008 2010 2013Availability- Upgrading Packages
TT1+ TT1+
CMF+ CMF+
HCO Hydraulic Clearence Optimisation
6+ IGV & CV16 Optimized
HW2 Enhanced Turbine B&V coatings
HW3Enhanced inner casing coatings
Enhanced mixing chamber coatings
HW7 New Burner 15ppm (methane)HW7 New Burner 15ppm (methane)
HW5 New 3D compressor
HW4 New 3D turbine Blades & Vanes
Pag. 5Ansaldo Enegia 2010. All rights reserved
All Upgrades Packages are Fully Retrofittable over 94.2-3 / 94.2-6
Contents
New development for Ansaldo Energia AE94.2New development for Ansaldo Energia AE94.2
F D l t d P d t O iFrame Development and Product Overview
AE94.2AE94.2--Evo1 detailsEvo1 details
AE94.2-Evo2 overview
Summary and Conclusiony
Pag. 6Ansaldo Enegia 2010. All rights reserved
HW2 : Vanes and Blades package
New coatings (BC and TBC)
Improve thermo-mechanical behavior
+15°C TT1 @ 33MAC
TARGETS
Vane #1 Vane #2
+15°C TT1 @ 33MAC
+5°C TT1 @ 41MAC
Potential life extension for Blade 1 and Blade 2.
33MAC @ 1090°C
41MAC @ 1065°C
Pag. 7Ansaldo Enegia 2010. All rights reserved
Blade #1 Blade #2New HW2 vs previous design
HW3 : Improved combustion chamber
New coatings on IC and MC
Reduced thermal stresses
I d li bilitImproved reliability
Reduced damages
Red ced maintenance cost
Inner casing
Reduced maintenance cost
Pag. 8Ansaldo Enegia 2010. All rights reserved
Mixing chamber
HW7 : New Low NOx Burner
Benefit (natural gas firing)
Compared to HR3-Burner further NOx reduction
NOx emission below 15ppm
Enhanced combustion stability
F rther flashback resistanceFurther flashback resistance
Scope
New diagonal swirlerNew diagonal swirler
Enhanced pilot flame system
Enhanced ignition system
Pag. 9Ansaldo Enegia 2010. All rights reserved
AE94.2 Evo1 : Summary
Upgrade Scope (HW2 & HW3 upgrade packages)
Advanced coatings (BC & TBC) on turbine blades and vanes
Advanced coatings (BC & TBC) on mixing chamber and inner casing
New advanced low NOx burner for natural gas firingNew advanced low NOx burner for natural gas firing
Benefit
Turbine inlet temperature increase from 1075°C to 1090°CTurbine inlet temperature increase from 1075 C to 1090 C
Open/Combined cycle improvements:
Increase in GT power output
Increase in GT exhaust energy / Combined Cycle efficiency
NOx emission below 15ppm (natural gas firing)
Maintenance Interval Extension 41MAC @ 1065°C (for base load units):
Increased efficiency & power output (+5°C TT1 respect to MAC41@ 1060°C)
Pag. 10Ansaldo Enegia 2010. All rights reserved
Reduction of maintenance costs
Contents
New development for Ansaldo Energia AE94.2New development for Ansaldo Energia AE94.2
F D l t d P d t O iFrame Development and Product Overview
AE94.2-Evo1 details
AE94.2AE94.2--Evo2 overviewEvo2 overview
Summary and Conclusiony
Pag. 11Ansaldo Enegia 2010. All rights reserved
HW4 : New AE3D GT Blades & Vanes
New aerodynamic features
Reduced stage losses by fully 3D design
reduction of trailing edge thickness
y
Expansion line optimization
8 l t l 3D bl d & V8 completely new 3D blades & Vanes
New GT application on Evo2
Retrofit on AE94.2-3 and AE94.2-6 Increased power and efficiencyIncreased maintenance intervals @1075°C (41MAC@1075°C)
Pag. 12Ansaldo Enegia 2010. All rights reserved
HW4 : AE3D Performance Benefits
Fully Retrofittable over 94.2-3 / 94.2-6
Optimized 3D d i
y
Enhanced base
aerodynamic airfoil design
Reduced
AE3D
AE3DAE3D
P (*) GT
Enhanced base material and
coatings
Reduced cooling/leakage
air flows
AE3D
AE3D AE3D
AE3DPower(*) GT
+8 MWEfficiency(*) GT
AE3D
AE3DAE3D
Efficiency GT +1.2pt%AE3D
3
AE3D
Pag. 13Ansaldo Enegia 2010. All rights reserved
(*) expected values for 94.2-6 upgrade @1075°C ISO conditions, Single Cycle, Methane firing.
HW4 : Roadmap toward AE3D Turbine B&V
12/13 : Product Validation
04/13 : AE3D Turbine Blades & Vanes available
04/12 : Product commercialization04/12 : Product commercialization
09/10 : Concurrent Engineering with casting suppliers startg pp
01/10 : Product specification
03/09 : Project Start
Pag. 14Ansaldo Enegia 2010. All rights reserved
HW5 : Fully 3D Compressor Blades & Vanes
Five front stages fully 3D designg y g
Completely retrofitable on AE94.2 range gas turbine with same rotor di kdisks too
+4% inlet mass flow @same efficiencyefficiency
Low mass flow variations against ambient temperatureambient temperature
High turndown capabilities
W t i bilitiWet compression capabilities
A il 12 P d t i li ti
Pag. 15Ansaldo Enegia 2010. All rights reserved
April 12 : Product commercialization
AE94.2 Evo2 : Summary
Upgrade Scope (HW4, HW3 and HW5 upgrade packages)
New Ansaldo Energia 3D turbine blades and vanes,
New aerodynamic optimized 1-5 compressor stages,
Advanced coatings (BC & TBC) on mixing chamber and inner casing
Benefit
Evo2 Turbine inlet temperature fixed to 1090°CEvo2 Turbine inlet temperature fixed to 1090 C
+10.0% increased power output in Simple Cycle(*)
+8.0% increased power output in Combined cycle(**)8.0% increased power output in Combined cycle( )
more than +1.4pt% increased efficiency in Simple Cycle (Up to 4.0% higher exhaust mass flow provide more power output in case of existing combined cycle or combined cycle extension compared to HW4 package only)cycle or combined cycle extension compared to HW4 package only)
Maintenance Interval Extension @ 1075°C (41MAC for base load units)
Pag. 16Ansaldo Enegia 2010. All rights reserved
(**) w/o design limit in Combined plant parts(*) ISO conditions, methane firing
Contents
New development for Ansaldo Energia AE94.2New development for Ansaldo Energia AE94.2
F D l t d P d t O iFrame Development and Product Overview
AE94.2-Evo1 details
AE94.2-Evo2 overview
Summary and ConclusionSummary and Conclusionyy
Pag. 17Ansaldo Enegia 2010. All rights reserved
Summary & Conclusion
Ansaldo Energia Upgrade present and future packages for AE94 2Ansaldo Energia Upgrade present and future packages for AE94.2 have been presented.
All upgrade packages are modular, can be combined and are completely retrofitable.
Extended maintenance interval MAC41 up to 1075°C ISO (by HW2 HW4 d HW3 k )or HW4 and HW3 packages).
Decreasing combustion emissions by new VeLoNoxTM low NOx Burner (15ppm for methane firing units)Burner (15ppm for methane firing units).
Further development is ensured.
Pag. 18Ansaldo Enegia 2010. All rights reserved
AE94.2 UPGRADING PROJECT
MANY THANKS FOR YOUR ATTENTION