ANNUAL - GTAC · 2017-05-13 · ANNUAL REPORT 2014/15 Government Technical Advisory Centre &...
Transcript of ANNUAL - GTAC · 2017-05-13 · ANNUAL REPORT 2014/15 Government Technical Advisory Centre &...
P a g e | 1
ANNUAL REPORT 2014/15
Government Technical Advisory Centre
&
National Treasury Programme 8:
Technical Support and Development Finance
ANNUAL REPORT
2014/15
GTAC Private Bag X115 Pretoria, 0001, South Africa Tel: +27 12 315 5111 Fax: +27 12 315 5786 ISBN: 978-0-621-43852-9 RP: 245/2015 This report is also available on www.gtac.gov.za
P a g e | 2
ANNUAL REPORT 2014/15
Mr NM Nene Minister of Finance
I have the honour of submitting the Annual Report of the Government Technical Advisory Centre and the Technical Support and Development Finance Programme for the period 1 April 2014 to 31 March 2015.
Andrew Donaldson Acting Head: GTAC
P a g e | 3
ANNUAL REPORT 2014/15
CONTENTS
MINISTER’S FOREWORD ................................................................................................... 4
REPORT OF THE ACCOUNTING OFFICER........................................................................ 5
ACCOUNTING OFFICER’S STATEMENT OF RESPONSIBILITY ....................................... 7
PART A: GENERAL INFORMATION ................................................................................... 8
Legislative mandate ........................................................................................................... 9
Mission statement and values ........................................................................................... 9
Strategic overview ........................................................................................................... 10
Organisational structure .................................................................................................. 12
PART B: PROGRAMME INFORMATION ........................................................................... 13
Government Technical Advisory Centre .......................................................................... 14
Independent Power Producer Procurement Programme ................................................. 55
National Treasury Programme 8: Technical Support and Development Finance ............. 58
PART C: FINANCIAL INFORMATION ............................................................................... 83
Report of the Auditor-General to Parliament on the Government Technical Advisory Centre ............................................................................................................................. 84
Annual financial statements ............................................................................................. 90
PART D: HUMAN RESOURCES MANAGEMENT ........................................................... 119
Human resources oversight: statistical information ........................................................ 120
PART E: GOVERNANCE ................................................................................................. 143
Risk management ......................................................................................................... 144
Internal audit report ....................................................................................................... 144
ANNEXURES ................................................................................................................... 145
Annexure 1: Annual performance tables ........................................................................ 146
Annexure 2: Abbreviations ............................................................................................. 156
P a g e | 4
MINISTER’S FOREWORD
Minister Nene It gives me great pleasure to welcome the first annual report of the Government Technical Advisory Centre (GTAC).
The Public Finance Management Act (1999) requires the National Treasury to promote transparency and the effective management of revenue, expenditure, assets and liabilities of departments, public entities and constitutional institutions. It also enjoins the National Treasury to assist organs of state in building their capacity for efficient, effective and transparent financial management.
GTAC’s mandate gives effect to these obligations. Although recently constituted as a separate government component, GTAC’s programmes and activities have evolved over several years. In addition to its in-house advisory and technical support capabilities, it has extensive experience in hiring professional service providers with public-sector expertise.
Building state capacity requires partnerships with the private sector in infrastructure development, operational improvements, technology and management systems. It also requires collaboration with university research and advisory centres, civil society organisations and international partners.
GTAC’s scope of work is wide, from administering job-creation projects, to strengthening municipal finance management, to providing advice on specialised transactions. Prioritisation is that much more important when there are many areas of possible assistance and a wide range of skills are sought.
In introducing this first consolidated account of the National Treasury’s technical support activities, I look forward to vigorous engagement on the lessons of our experience and priorities for the period ahead.
Nhlanhla Musa Nene Minister of Finance
P a g e | 5
REPORT OF THE ACCOUNTING OFFICER
Andrew Donaldson Acting Head and Accounting Officer of GTAC This is the first annual report of GTAC, established in terms of a 2012 proclamation and the subsequent assignment of functions by the Minister of Finance. GTAC’s origins are rooted in two initiatives of the National Treasury undertaken about 15 years ago:
The establishment in 2000 of the Public-Private Partnership (PPP) Unit in the Budget Office to support the new regulatory framework for national and provincial PPP projects.
The formation of the Technical Assistance Unit in 2001 in the Public Finance Division, building on the project and programme management services previously housed in the Reconstruction and Development Programme Office.
In subsequent years, the mandate of the PPP Unit expanded to include municipal projects, and the Technical Assistance Unit broadened its project management focus to include organisational development and planning support, infrastructure development and public finance management. In addition, several specific programmes were initiated to support provincial and municipal infrastructure delivery, neighbourhood development and improved financial management. In 2011 the Jobs Fund was launched.
While grounded in the National Treasury’s oversight of the Public Finance Management Act and its capacity-building responsibilities, these programmes are largely externally focused. In other words, they came about from the identified needs, project proposals or requests emanating from other departments or organs of state. As demand for these services grew, the idea gained impetus that externally oriented advisory and support services should be accommodated in a separate entity with an arms-length relationship with the National Treasury.
P a g e | 6
In 2012, the Ministers of Finance and Public Service and Administration approved the establishment of GTAC as a government component, giving effect to the vision of a self-standing entity within the public service to provide advisory and professional support services.
In April 2014, the Minister of Finance signed off on the transfer to GTAC of the advisory functions of the former PPP Unit, the Technical Assistance Unit, the Jobs Fund Project Management Unit, the National Capital Projects Unit and the Performance and Expenditure Review Programme. Implementation of this transition has been supported through an administrative shared service agreement with the National Treasury.
GTAC’s first year has been one of consolidating existing programmes and activities, while consulting and reflecting on strategic priorities and possible organisational shifts or adjustments. Full responsibility for administration of the Jobs Fund has been transferred from the Development Bank of Southern Africa. New partnerships have been initiated with the Office of the Accountant-General and the National Treasury’s Intergovernmental Relations Division to implement a second Municipal Finance Improvement Programme (MFIP) and the new Cities Support Programme.
Progress has been made in policy advice, financial analysis and organisational support across a wide range of issues, including energy security, broadband investment and industry structure, border ports of entry management, school district administration and regional economic development. GTAC assisted in the first two Phakisa initiatives, focused on the oceans economy and health clinic management.
This report also includes information on the National Treasury’s Programme 8 activities. GTAC shares management responsibilities for this programme with the Intergovernmental Relations Division and the Office of the Accountant-General.
Leading GTAC’s management team in this first phase of developing a new agency and shaping its future programmes has been a special privilege. Constructive collaboration with senior managers and staff of the National Treasury, other national and provincial departments, and several partner organisations has played a vital role in our progress. The leadership of Minister Nene and Deputy Minister Jonas has been invaluable in guiding our focus on high-impact initiatives and priorities while supporting innovation and renewal.
Andrew Donaldson Acting Head and Accounting Officer: GTAC
P a g e | 7
ACCOUNTING OFFICER’S STATEMENT OF RESPONSIBILITY
Statement of responsibility and confirmation of accuracy for the annual report for the year ended 31 March 2015:
I confirm the following:
The information and amounts disclosed in this annual report are compiled from the records of GTAC and the National Treasury, and accurately reflect, subject to the limitations of these records, the activities of GTAC and the Technical Support and Development Finance Programme.
To the best of my knowledge and understanding, the annual report is complete, accurate and free from material misstatements.
The annual report has been prepared taking into account the relevant guidelines issued by the National Treasury.
Following a determination by the Minister of Finance and approval by the Accountant-General, the annual financial statements (Part C) have been prepared in accordance with Generally Recognised Accounting Practice standards and the National Treasury’s relevant frameworks and guidelines.
In its governance, human resource management, financial management and risk management arrangements for 2014/15, GTAC relied on a shared service agreement with the National Treasury, while developing internal capacity to provide these corporate support functions independently in future.
GTAC’s financial statements include the Independent Power Producer Procurement Programme (IPPPP) account, through which expenditure incurred by the Development Bank of Southern Africa on the IPPPP Office is reimbursed out of revenue derived from fees payable by bidders and investors. The accuracy of this account relies on information maintained and provided by the Development Bank of Southern Africa.
GTAC’s financial statements for the year ended 31 March 2015 have been audited by the Auditor-General, who is responsible for reporting on whether the financial statements are fairly presented. The report is found on page 84.
In my opinion, the annual report fairly reflects the operations, performance information, human resources information and financial affairs of GTAC and Programme 8 for the financial year ended 31 March 2015.
Andrew Donaldson Acting Head and Accounting Officer: GTAC 30 October 2015
P a g e | 8
ANNUAL REPORT 2014/15
PART A: GENERAL INFORMATION
P a g e | 9
LEGISLATIVE MANDATE GTAC was established on 30 March 2012 as a government component in terms of the Public Service Act (1994) through Government Notice 261, Gazette 35194.
GTAC, which forms part of National Treasury’s Programme 8: Technical Support and Development Finance, is mandated to provide advisory services, programme management and development finance support to improve public finance management, support high-impact government initiatives, facilitate job creation and strengthen infrastructure planning and delivery to the National Treasury, centre-of-government departments and other organs of state.
GTAC does this by:
Rendering technical consulting services within the public sector. Providing specialised procurement support for high-impact government initiatives. Advising on the feasibility of infrastructure projects. Providing knowledge management for projects undertaken.
GTAC provides advisory and project management support using core funding provided by the National Treasury and co-funding by international donor partners, while partially recovering professional service costs from client departments or entities.
MISSION STATEMENT AND VALUES GTAC helps organs of state build their capacity for efficient, effective and transparent financial management. Its work is based on the following values and principles:
Accountability. Integrity. Collaboration and partnership. Evidence-based learning. Public- and private-sector participation. Broad-based development.
P a g e | 10
STRATEGIC OVERVIEW GTAC supports policy development, programme implementation and public finance management through advisory and professional support services, drawing on internal resources and independent service providers. It also contributes to public service research and capacity building by partnering with academic and research centres and developing public finance management training programmes.
GTAC’s approach to professional support services is based on three broad principles:
Client-focused and demand-driven programmes: Advisory and technical support responds to client needs and respects the ownership and accountability for services of responsible organs of state.
Diagnostic and management tools adapted to public-sector needs: Advisors and support staff use management tools, methods and practices rooted in South Africa’s legal and institutional frameworks to undertake and support projects, while drawing on experts in public-sector practice.
Capacity building through partnerships and learning by doing: GTAC’s approach is underpinned by a pragmatic and problem-solving approach to project support. It builds capacity through learning by doing and transferring skills through partnerships with other centres of expertise.
Within the context of government’s National Development Plan and medium-term strategic framework, GTAC aims to contribute to building a capable and development-oriented state, while strengthening government’s capacity to work with the private sector to promote growth, employment, infrastructure investment and public service delivery.
GTAC’s advisory and support functions and activities were organised as follows in 2014/15:
Transaction Advisory Services: Support for major infrastructure procurement projects, PPPs and service-delivery improvement transactions, including project conception and registration, transaction process support, and legal and financial advice.
Infrastructure and Capital Projects Appraisal: Infrastructure planning support, capital projects appraisal, network industry analysis and regulatory advice (particularly in the energy, transport, water and sanitation, and communications sectors).
Technical Consulting Services: Organisational development, and advisory and project management support for a range of national, provincial and municipal organs of state, consisting of four portfolio clusters:
Economic development and international relations. Social services. Infrastructure and rural development. Governance and administration.
P a g e | 11
Public Economics and Expenditure Reviews: Evaluation of public expenditure and performance; environmental economics; planning, budgeting, reporting and monitoring of service delivery; and public finance capacity building.
GTAC also coordinates and provides management support for Programme 8, and operates a project development facility through which potential PPP projects, neighbourhood development partnership projects and employment facilitation projects are supported.
Two dedicated project management units have been incorporated into GTAC’s establishment and activities in 2014/15:
The MFIP: On behalf of the Office of the Accountant-General, GTAC has established a project management team to implement the MFIP II.
The Jobs Fund: During 2014/15, responsibility for planning, managing and implementing the National Treasury’s Employment Creation Facilitation Programme was shifted from the Development Bank of Southern Africa to GTAC.
The National Treasury established the Jobs Fund in June 2011 to support innovative initiatives and approaches to job creation. The Jobs Fund uses a “challenge fund” methodology, allocating grant funds to projects that have performed competitively against impact criteria. This competitive application process means that only the best ideas are funded.
The Jobs Fund aims to stimulate good ideas, risk-taking and investment to discover new ways of working, where the costs and risks may be unknown and where the pro-poor impact, principally in the form of sustainable job creation, may be significantly larger than that of conventional approaches.
P a g e | 12
ORGANISATIONAL STRUCTURE GTAC forms part of the National Treasury’s Programme 8: Technical Support and Development Finance. It provides management support to the programme and administers several subcomponents of the programme on behalf of the National Treasury.
Figure 1: Programme 8 organisational structure
Figure 2: GTAC organisational structure
In its first phase of establishment, GTAC consisted of the following business units and personnel seconded from the National Treasury: the former Technical Assistance Unit, the PPP Unit, the National Capital Projects Unit and the Jobs Fund Project Management Unit. GTAC was assigned the Performance and Expenditure Review Programme, established through a partnership with the Department of Planning, Monitoring and Evaluation, as well as an ongoing project on environmental economics and fiscal issues. During the course of 2014/15, GTAC established a project management unit for the MFIP II by agreement with the Office of the Accountant-General.
GTAC’s advisory and technical support projects are undertaken in response to requests for support from other departments or organs of state. Project teams include GTAC staff, long-term technical advisors and professional service providers hired for specific projects. During 2014/15, GTAC appointed technical advisors through 105 professional services contracts. Corporate support services are in part provided through a service level agreement with the National Treasury.
P a g e | 13
ANNUAL REPORT 2014/15
PART B: PROGRAMME INFORMATION
P a g e | 14
GOVERNMENT TECHNICAL ADVISORY CENTRE GTAC provided technical and advisory support to 93 projects during 2014/15, including support for the Department of Public Works, developing the Border Management Agency business case, providing advice on the Department of Telecommunications and Postal Services’ broadband implementation strategy and providing support for the Wild Coast economic development plan in the Eastern Cape.
The centre also provided transaction support to the Passenger Rail Agency of South Africa (PRASA) rolling stock renewal programme, the Free State Department of Health’s investment in independent power capacity and a range of PPP projects.
GTAC’s long-term strategy is to provide a centre of excellence in policy advice and public finance management in partnership with academic and research centres focused on public-sector management and training. Project and programme management capacity in the public sector is supported through an active “community of practice”, and innovative approaches to local economic development are supported through the Economies of Regions Learning Network.
GTAC supports a research programme on employment, income distribution and inclusive growth based at the Southern African Labour and Development Research Unit at the University of Cape Town. It also seeks to promote public discourse and understanding of public policy, social and economic development and public finance management through publications, consultative forums and dialogue.
The Performance and Expenditure Review Programme was initiated as a joint project of the Department of Planning, Monitoring and Evaluation and the National Treasury, and is managed by GTAC. Nine performance and expenditure reviews were completed during the year, including studies on artisan training and technical and vocational education, the National Skills Fund, land restitution and the partnering of science councils with the private sector. The reviews aim to identify options that offer greater value for money in public expenditure and improve alignment in the use of development and service-delivery indicators for government-wide performance monitoring, budget planning and reporting.
P a g e | 15
MANAGEMENT AND CORPORATE SUPPORT
Acting Head of GTAC: Andrew Donaldson
GTAC management, staff and professional advisory teams undertook several strategic planning reviews and consultations during 2014/15 to improve and strengthen existing activities and identify priorities.
Several key themes emerged from these discussions:
GTAC’s relationship with the National Treasury is central to its mandate and priority programmes. It will continue to focus on building capacity in public finance management.
GTAC’s diagnostic and problem-solving approach to organisational development and technical support remains an important foundation of its work, drawing on multidisciplinary expertise where necessary and engaging clients and stakeholders in the problem-solving process.
GTAC will continue to support government’s capacity for evidence-based programme and policy development, drawing on external centres of expertise and building a “knowledge hub” through learning networks and links with other organisations.
GTAC focuses on building public-sector client capacity by offering a combination of diagnostic services, organisational development, and programme and project implementation support. It provides support for PPPs and other major government transactions, and assists the National Treasury in appraising major capital projects and reviewing financing options.
During the past year, GTAC took over the administration of the Jobs Fund from the Development Bank of Southern Africa, enabling this critical intervention to be more closely aligned with other National Treasury and GTAC initiatives. Jobs Fund personnel were successfully seconded from the Development Bank of Southern Africa during the reporting period.
In 2014/15, GTAC started to develop its organisational structure, which included several drafts for consideration. GTAC’s human resource capacity is a combination of professional and administrative staff, long-term advisors and short-term consultants for specific projects.
GTAC’s corporate support services, financial management and specialised procurement support services are currently limited in capacity with a growing workload. The centre aims to expand its internal professional capacity while continuing to draw on consultant expertise where needed. It also receives reliable service and support from the National Treasury’s Corporate Services through a shared services agreement.
The financial management component is consolidating the former project development facility and technical assistance trading accounts into GTAC, and has continued to provide a professional accounting service to all projects and programmes, including management of a substantial portfolio of professional service contracts, cost recovery from client departments and agencies, and management of donor funds.
P a g e | 16
Building a learning organisation: publications and partnerships
During 2014/15, GTAC established a dedicated publication and communication function. It has introduced several communication products to support GTAC’s internal development and to promote broader awareness of the centre and its outputs, including bimonthly and biweekly newsletters.
Progress has been made in developing the GTAC website, which will serve as the primary communication platform, including research, case studies, news and information about events and activities. The website will also become the primary vehicle for professional service procurement. GTAC aims to become a recognised repository of public finance research material, policy analysis and information about events, publications and important announcements.
During the past financial year, GTAC published three newsletters:
August 2014: An overview of GTAC’s establishment, including an introduction by the Minister of Finance.
October 2014: Focusing on the PPP Unit. February 2015: Profiling the National Capital Projects Unit.
The publication team also produced a brochure profiling Programme 8 activities, which it shared with Parliament in March 2015.
GTAC published eight issues of the biweekly WhatsUp newsletter in 2014/15, featuring news from the Jobs Fund, the PPP Unit and other National Treasury divisions, and highlighting activities and publications of partner organisations and networks.
GTAC has taken over the Development Bank of Southern Africa’s responsibility for producing the Development Southern Africa journal, which continues to enjoy a growing readership and strong academic recognition. Six issues were published during the year, including three special themed editions. The January 2015 issue was dedicated to South Africa’s emerging middle class.
GTAC also supported the employment, income distribution and inclusive growth research project, which is managed by the University of Cape Town’s Southern African Labour and Development Research Unit. This project was created in response to a request from the Minister of Finance for evidence, analysis and advice on public policy and public finance reforms to support accelerated employment creation, a more equitable distribution of income and inclusive growth.
The project’s www.econ3x3 site published 15 articles in 2014/15 and has seen a steady rise in readership.
GTAC helps to build public finance capacity through partnerships with a number of national and international centres of excellence. These arrangements bring mutual benefits, including knowledge and learning initiatives and project implementation support.
GTAC enters into a memorandum of understanding (MoU) with each partner institution, which establishes the strategic intent, objectives and terms of the partnership. A cooperation agreement
P a g e | 17
gives effect to the partnership MoU and identifies specific activities or joint initiatives to be implemented through collaborative projects.
During the past year, GTAC has signed MoUs and cooperation agreements with the University of Cape Town’s Graduate School of Development Policy and Practice, the University of the Witwatersrand’s Public Affairs Research Unit and the National Education Collaboration Trust. GTAC has provided funding to the Graduate School of Development Policy and Practice to enable 14 government managers to enrol for an MPhil in Development Policy and Practice.
Table 1: Signed MoUs, 2014/15
Several presentations and seminar events were hosted during the year, including case studies of GTAC projects and broader reviews of development and public finance issues. Highlights included:
A presentation by Professor Brian Levy, academic director at the Graduate School of Development Policy and Practice, on Integrating Governance and Growth in Development Strategies.
A specialist two-day workshop to consolidate the Human Settlement and Public Transport expenditure reviews.
An interactive seminar on leadership and personal development by Dr Annie McKee from the University of Pennsylvania.
Partner Areas of collaboration University of Cape Town Graduate School of Development Policy and Practice
Executive short courses. Dialogue (seminars & workshops). Case studies. MPhil scholarship.
University of the Witwatersrand Public Affairs Research Unit & National Treasury’s Cities Support Programme
Longitudinal and comparative research on the drivers of institutional performance in the public sector.
Case studies that highlight a relevant institutional dynamic affecting performance.
Dialogues between relevant stakeholders appraising new research findings on governance challenges.
National Education Collaboration Trust & Department of Basic Education
Referral model and system for psychosocial support for learners and process case study.
Case studies on the district intervention programme and the management of the examination system in basic education.
P a g e | 18
TRANSACTION ADVISORY SERVICES AND PUBLIC-PRIVATE PARTNERSHIPS
Unit Head: Tumisang Moleke
Building on the work of the former PPP Unit, GTAC provides specialised support for transactions governed by the Treasury Regulations on PPPs and advice on major infrastructure procurement transactions. Support typically extends beyond procurement into project implementation and contract management. The unit also hosts a quarterly PPP training programme and, on request, provides PPP training for foreign governments.
The unit monitors the performance of PPPs and provides implementation support to 18 active PPPs. The team also prepares draft policy documents for PPPs, related procurement issues and GTAC operations.
PPP procurements completed in 2014/15
Statistics South Africa office accommodation
The Statistics South Africa office accommodation project, initially registered with the PPP Unit in 2012, was financially closed during 2014/15. The project entails the design, building, financing, operation and maintenance of centralised office accommodation for Statistics South Africa, replacing the four buildings that previously housed the organisation’s 2 462 staff members.
The main building has a “drum and fingers” design, consisting of work stations, offices, meeting spaces, storage areas, staff areas, circulation and general spaces, a statistical training institute and an auditorium. The net present value of the total project cost, at the time of Treasury Approval III, was R2.5 billion.
Tshwane House
Tshwane House is the first municipal government accommodation PPP under the Municipal Finance Management Act (2003) and Municipal PPP Regulations. Following council approval in February 2015, the project was financially completed in March 2015.
The project is a 17-year contract (design, build, finance, operate and maintain) to deliver headquarters for the City of Tshwane, housing 1 589 municipal staff at a total project cost of R1.2 billion. It includes a 250-seated standalone council chamber with meeting rooms and communication booths, as well as 1 300 parking bays. The project is an integral part of Vision 55 and the regeneration of the inner city for the City of Tshwane.
Projects under assessment
Nelson Mandela Bay Municipality waste management
The Nelson Mandela Bay Municipality and Eskom have investigated the feasibility of a waste beneficiation and diversion project. The initial defects in the feasibility study have been rectified and
P a g e | 19
the municipality’s project steering committee is determining the most appropriate technology for this project.
Northern Cape renal dialysis
The Northern Cape Department of Health registered its renal dialysis project in 2013. The only hospital in the province capable of providing renal dialysis is in Kimberley, which poses a serious problem for patients needing this service in other areas of the Northern Cape. The project seeks to provide renal dialysis facilities, either new or upgraded, in Kimberley, Upington, De Aar, Kuruman and either Springbok or Calvinia. A transaction advisory team has been appointed, the feasibility study has been completed and approved, and the department is waiting for the Provincial and National Treasury to approve the procurement documents. It is hoped that the procurement process will be completed by the end of 2016 or the beginning of 2017.
Gautrain extension
The success of the existing Gautrain rail network has prompted the initiation of a feasibility study to explore options for its extension. As with the initial PPP procurement, the Gautrain extension feasibility study will require extensive assessment of different routes, especially in light of recent population growth trends in the province.
Tshwane fleet services
The City of Tshwane is reviewing its fleet services provision to determine the most appropriate model for implementation. A transaction advisor conducted a feasibility study of the City of Tshwane’s fleet operations and recommended that the city adopt a centralised co-sourcing full maintenance lease model. Using this model, the city has undertaken a competitive tender process and submitted its final recommendations to the Tshwane Municipality, with input from the National Treasury, along with the proposed PPP agreement for consideration in terms of the Municipal PPP Regulations.
Gauteng Province: Kopanong Precinct
The Gauteng Department of Infrastructure Development registered the Kopanong project with the National Treasury in 2014 to procure suitable head office accommodation and consolidate the functions of the Gauteng Provincial Government within the Johannesburg central business district. The PPP project entails the refurbishment and upgrade of 19 buildings. There are two vacant stands where new construction may take place.
The project aims to improve service delivery through the consolidated structures, identify a mechanism for improving socioeconomic development, improve space functionality and the working environment to cater for growth in various provincial departments, and stimulate urban regeneration.
P a g e | 20
A transaction advisory team has been appointed and a feasibility study completed, which the National Treasury and Gauteng Provincial Treasury are reviewing. If approved, procurement documents will be issued for the selection of a private-sector service provider.
Contract management and challenges in PPP procurement
The PPP Unit continues to support PPP contracts that are stable, financially sound and exhibit value for money. Several contracts are approaching expiration, and the unit’s monitoring and evaluation team is working with the institutions involved to ensure a seamless handover. The team achieved a significant PPP contract variation approval in the Universitas and Pelonomi joint-use hospitals PPP in February 2015.
The unit’s main challenge is the time needed to complete all the necessary work for PPP procurement, which often involves urgent and politically sensitive undertakings. Major time-consuming activities include procuring the sponsoring entity’s project officer and transaction advisor; accessing and interpreting all of the required information to construct the public-sector comparator in the feasibility study; procuring the private-sector service provider who will finance, design, construct and operate the desired infrastructure, which often includes protracted negotiations with a preferred bidder; and obtaining the necessary approvals from the sponsoring institution’s internal structures.
The PPP Unit strives to mitigate delays and explore mechanisms that will speed up the processes involved in meeting requirements, while ensuring that the PPP is still affordable, provides value for money, and transfers substantial and appropriate risk to the private party.
P a g e | 21
Non-PPP transactions
PRASA rolling stock procurement
The PPP Unit continues to provide support to the PRASA rolling stock procurement programme. This involves:
Assisting with the tender processes to upgrade depots. Finalising the design of passenger carriages. Negotiating for leases of land. Reviewing the financial model for the industrial supplier park.
The National Solar Water Heater Programme and renewable energy projects
From 2009 to 2014, Eskom was the implementing agent of the National Solar Water Heater Programme. This responsibility has now been transferred to the Department of Energy, which is exploring options for a revised implementation model. GTAC will help the Department of Energy to:
Review the performance and status of Eskom deliverables, programme outputs and outcomes.
Finalise the relevant submissions to the National Treasury regarding budget rollovers and methodologies for applying the necessary rebates (capital or operational subsidies).
Develop and design the revised new framework and approach for rolling out the programme, which includes identifying relevant stakeholders and drafting and commenting on the agreements to be entered with such stakeholders.
Establish a management and support structure and process for the programme’s rollout. Finalise current private-sector requests for information. Manage funds (particularly donor funds) transferred to the Department of Energy and
disbursed to various service providers. Create monitoring and verification frameworks with clear audit trails. Create a reporting framework.
GTAC is also in consultation with the Department of Energy concerning off-grid energy possibilities. Interest in procuring projects for off-grid electricity generation has been expressed by Gauteng Province, uMhlathuze (Richards Bay), the East London Industrial Development Zone, Cacadu District Municipality and the Free State Department of Health.
P a g e | 22
One-stop border post
The head of GTAC’s PPP Unit is the signatory on an African Development Bank-funded consultant contract with an international consulting joint venture. The joint venture has developed a draft one-stop border post policy under Cabinet’s direction. The draft will soon be finalised and presented to Cabinet. PPP Unit staff members have participated on the project steering committee for this initiative.
Free State Department of Health trigeneration project
The Free State Department of Health registered a project for the provision of energy services to its public hospitals in 2014. The department had previously issued a tender for such services for five public hospitals. During that period, it received an unsolicited bid to provide such services using trigeneration technology (combined cooling, heating and power generation) for the remaining public hospitals in the province. The terms of reference to be submitted to the PPP Unit’s panel of consultants are being prepared.
Table 2: Transaction support and PPP projects, 2014/15
New projects Department of Health Nelson Mandela Children’s Hospital.
Department of Public Works Government accommodation.
Department of Science and Technology
Appointment of transaction advisor for feasibility study – accommodation.
Gauteng Province Infrastructure development – rooftop solar PV green programme.
Gauteng Province Cogeneration/trigeneration plant project.
Western Cape Top yard multiple use project – feasibility study submitted.
Northern Cape Department of Cooperative Governance, Human Settlements and Traditional Affairs office accommodation in Kimberley.
Capricorn District Municipality Office accommodation.
Nelson Mandela Bay Municipality
Waste beneficiation and waste-to-energy project.
Department of Transport Office accommodation – Aviation Authority.
Free State Department of Health trigeneration
Off-grid energy provision for provincial hospitals.
Policy development and training initiatives One-stop border post Support for the National Treasury/African Development Bank initiative,
mandated by Cabinet, to develop a draft one-stop border post policy for its consideration.
Special economic zone regulations
Participate as a member of the Department of Trade and Industry/National Treasury team that is finalising the pending special economic zone regulations.
PPP training Coordinate the provision of PPP training for visiting foreign delegations and provide PPP training in African countries. Training was provided to a visiting delegation from Zimbabwe in December 2014 in Windhoek, Namibia, and Abuja, Nigeria, in November/December 2014. On 30 April 2015, the unit provided PPP training to a visiting delegation from Cameroon.
P a g e | 23
INFRASTRUCTURE AND CAPITAL PROJECTS APPRAISAL
Unit Head: Nicky Prins
The National Capital Projects Unit was formed to provide specialised analytical support to the National Treasury. The unit assesses large infrastructure investments, including reviewing the plans and supporting documentation of megaprojects to advise on their likely economic and financial viability, particularly where financial support of one form or another is being requested of the National Treasury. The unit also analyses the impact of infrastructure investments on the financial sustainability of public utilities, financial cost comparisons of investment programme options and potential funding strategies for infrastructure projects and programmes.
Assessing E skom’s support options
During 2014/15, the National Capital Projects Unit helped develop a support package for Eskom in the wake of the funding challenges associated with its investment programme and efforts to meet electricity demand. This work comprised much of the unit’s economic and financial analysis undertaken during the year.
The National Capital Projects Unit worked closely with the National Treasury’s Assets and Liabilities Management Division to assess Eskom’s situation, explore different solutions and package a set of proposals on behalf of an interdepartmental task team. The unit assisted policy-makers in their review of the proposals and provided additional analysis at their request. The process culminated in the proposal of a particular solution, and Cabinet adopted this support package in September 2014.
Following the package’s adoption, the unit continued to support the Assets and Liabilities Management Division and the task team in overseeing the implementation of its various solutions and tracking developments in Eskom’s financial sustainability. The unit continued to provide analytical support to the task team as its focus shifted to longer-term issues in the energy sector.
When the Eskom War Room was established in late 2014, the National Capital Projects Unit, as part of the National Treasury, was again asked to provide assistance, using its extensive knowledge of the electricity industry and its economic and financial assessment skills. The focus expanded beyond Eskom’s medium-term financial sustainability to include short-term challenges, as well as immediate and medium-term electricity supply concerns.
South Africa’s energy security rests on resolving these issues and the unit is expected to continue providing support to the task team for the foreseeable future.
Other infrastructure analysis projects
During 2014/15, the National Capital Projects Unit reviewed the Grand Inga Hydroelectric Project to highlight the likely costs, benefits and risks for the National Treasury, which is a member of the South African government team engaging with the Democratic Republic of Congo.
The unit also continued its analysis of the potential for using gas-fired power stations on a large scale in South Africa, the case for rolling out photovoltaic (PV) solar energy on rooftops for commercial and residential use, and the competitiveness of independent power producers.
P a g e | 24
Having built up considerable expertise in energy infrastructure analysis, the unit was able to respond to many smaller requests for insights and assistance from National Treasury units dealing with energy-related issues. This includes the liquid fuels sector, where analysis was provided on PetroSA’s proposed investment in the retail fuel sector, as well as an update of a previous report on the sector.
The unit also developed its capabilities to analyse rail transport infrastructure. With a number of passenger and freight rail projects at different stages under consideration, this will be an important focus area over the coming years. The unit contributed to the analysis of the Moloto Corridor rail feasibility study and gained early insights on the methodology for assessing the case for a Gautrain extension.
One of the unit’s main challenges has been managing the increased demand for infrastructure investment analysis as it has built its expertise and proficiency in this area, while still having a relatively small staff complement. Increasing the unit’s staff complement is under consideration to build the unit’s capacity to respond to requests for advice and expand analytical capacity in other infrastructure sectors.
Private-sector financing of infrastructure
The National Capital Projects Unit is responsible for convening a task team on private-sector infrastructure financing on behalf of the National Treasury, which involves various government departments and representatives from finance industry and labour organisations.
Following diagnostic research done in 2013/14 to understand possible constraints to the industry investing more in public infrastructure, in 2014/15 the unit produced a study on its findings, an action plan for government to address these issues and more in-depth work on selected areas. In addition, the unit conducted a series of interviews with industry representatives to assess progress made during the task team’s existence. The task team continued to facilitate engagements between the industry and government, focusing mainly on opportunities in the energy sector. Assistance with additional sectors, such as transport and water, is envisaged in future, although energy investment is likely to remain an important focus area.
P a g e | 25
Table 3: National Capital Projects Unit activities, 2014/15
TECHNICAL ADVISORY SERVICES
Acting Head: Emmanuelle Gille
Advisory and technical support: approach and priorities
GTAC’s advisory and technical support activities are organised into four project portfolios:
Social services Governance and administration Economic development Infrastructure and rural development.
These projects help build capacity in client departments, both through the support provided and direct capacity-building sessions.
New projects Assessment of Moloto feasibility study
Assess the feasibility study on the Moloto Corridor rail project.
Rooftop PV distributed generation
Assess the potential of residential and commercial rooftop solar PV panels to provide an economically viable energy-generation solution.
Ongoing projects Assistance to National Treasury on Eskom’s financial sustainability
Analytical support and additional capacity to National Treasury to analyse Eskom’s financial sustainability issues.
Feasibility of gas-fired power stations using imported gas
Assess the impact of pricing on the potential of gas-fired power stations to provide an economically viable electricity generation solution, using imported gas.
Financial cost modelling of large projects
Apply financial cost modelling techniques to understand the comparative total and unit costs of a range of large projects.
Task team on private-sector funding of infrastructure
Facilitate interactions between representatives of government, business and labour on aspects of the infrastructure financing environment to be addressed in order to attract greater private-sector investment in public infrastructure projects.
Liquid fuels industry study
Update an earlier assessment of the feasibility of large investments in the liquid fuels industry.
Completed projects Assessment of pre-feasibility study of Grand Inga Hydroelectrical Project.
Assessment of economic feasibility of gas-fired power stations using local gas.
Assessment of economic competitiveness of independent power producers.
Assistance to National Treasury in assessing the feasibility of PetroSA’s proposed investment in the retail fuel industry. Policy development and training initiatives Study on measuring rail transport externalities
Prepare the unit for likely future rail project feasibility studies that will need to be assessed on behalf of the National Treasury.
Study on passenger rail evaluation methodology
Prepare the unit to evaluate the expected Gautrain extension feasibility study that will be submitted to the National Treasury on completion.
P a g e | 26
Technical assistance and management support services are offered to departments and other organs of state across government. Support includes programme and project management, organisational development, strategic planning and performance management.
Programme and project management support is focused on three areas: people, processes, and tools and technology. The unit aims to facilitate the implementation of high-priority programmes and projects, and improve government’s capability to deliver. It provides guidance on project planning, helps set up project management offices, conducts project management health checks and expands government’s project management community of practice.
Organisational development support builds clients’ capacity to improve their effectiveness and performance. It takes into account the various key functional areas of strategic management, human resources management, financial management, supply chain management and operations management.
GTAC uses a results-based management approach to its strategic planning and performance budgeting support, which offers departments a valuable performance information management tool. Results-based management shifts the focus in planning, monitoring and reporting on activities and outputs to include expected outcomes or results. This is based on the understanding that it is not only government’s activities that should be monitored and measured, but also the results that it achieves. GTAC helps clients construct visual models to illustrate the links between their actions and the intended results.
Departments tend to focus on compliance in the strategic planning process rather than viewing the process, plans and in-year reporting as opportunities to improve programme performance. In addition, many departmental planning sections struggle to get operational units to meaningfully participate in planning and reporting processes.
GTAC offers not only a thorough understanding of government frameworks and the ability to draw on the experience of other government departments, but also an understanding of teams and the ability to encourage teams to work together.
Performance management support entails providing assistance for the development of performance management frameworks and various monitoring and reporting processes. This area of support to clients focuses on the value of the results-based management approach and thinking.
An important element of GTAC’s support is the diagnostic study, which is undertaken during the engagement phase of a project. It assesses the client’s practical needs and challenges, makes recommendations and informs the design of an appropriate support programme or intervention. These diagnostic studies are a joint effort between the client and GTAC, and provide an opportunity for mutual learning and capacity building. GTAC peer reviews its diagnostic studies to enhance learning and identify areas for improvement.
GTAC supported 80 projects during the year, which were at various stages of implementation at the end of 2014/15. A list of these projects is provided in the table at the end of this section. Some of the projects that GTAC supported during the year are highlighted below.
P a g e | 27
Eastern Cape Department of Education: improving supply chain management
GTAC provided support to the Eastern Cape Department of Education to improve its supply chain management performance, including human resources management. There are a number of factors that contribute to poor learning outcomes, including poor curriculum support and weak administrative and financial systems (human resources, supply chain management, financial management) across the education delivery system, from the head office to schools. This is often compounded by a problematic organisational culture that hinders effective service delivery.
This project has provided an opportunity for GTAC to develop and test an integrated and holistic conceptual model to build capacity. The model was developed through a number of engagements within GTAC, as well as with partners from the School of Governance at the University of Ottawa in Canada.
GTAC worked at all levels of the provincial education system and, as a result, the Eastern Cape Department of Education has refined its supply chain management policies, developed standard operating procedures and introduced improved supply chain management business processes. It has also developed policies, procedures and business processes for schools’ management of the National School Nutrition Programme.
Improvement is evident in eight schools in the Grahamstown district where, following GTAC’s assistance, learners are now benefiting from the nutrition programme during breaks without any disruption to the curriculum. The schools’ senior management teams are now fully functional and relations between supply chain management and the Grahamstown district offices have improved, as have the turnaround times for the procurement of goods and services.
Border Management Agency feasibility study
The success of interdepartmental programmes depends on joint prioritisation, planning, budgeting and implementation within a system of independently structured departmental mandates, accountabilities and funding. GTAC has assisted in a number of such areas, most notably in the border control environment, which requires a balance between the competing needs of trade facilitation and free travel on the one hand, and crime prevention, security, trade protection and sovereignty on the other. This is made all the more complex due to the number of government agencies involved: there are 21 departments and agencies responsible for setting policies, performing border controls or both.
During 2014/15, GTAC helped develop a status quo analysis on border functions, challenges and international comparisons, with a focus on ports of entry functions and operations. This analysis clarified the nature of a border management agency as an implementing agent for many parent departments that set policies relating to the cross-border movement of people and goods. South Africa does not have similar agencies or organs of state from which accountability and governance arrangements can be borrowed. Suitable enabling legislation is being drafted for the envisaged Border Management Agency to satisfy the constraints and principles identified in the institutional options analysis. Work is also continuing with a detailed status quo analysis of border line control and protection functions and operations.
P a g e | 28
Thusong service centres business case
GTAC also supported the development of a business case for the Thusong service centre programme. The one-stop service centres provide integrated information and services to communities, particularly in rural areas. The centres provide government social and administrative services, office services, education and skills development services, local economic development services, business services and community opportunities, and information and communication activities.
There have been varying degrees of success to date across the 183 centres. The business case used these successes to further clarify intergovernmental roles and responsibilities. One of the main challenges is the programme’s overall ownership. Many of the services delivered though the Thusong service centres are the responsibility of individual national departments, but most centres are owned and/or operated by municipalities. A follow-on project to recommend a formalised funding model for these centres is now being undertaken.
Broadband policy, planning and implementation
During the reporting period, GTAC helped the Department of Telecommunications and Postal Services implement its broadband policy, South Africa Connect. The centre focused on developing competence in programme and project management, and helping the department plan the first phase of the policy’s rollout, due to start in 2015/16.
A team has been put in place to support the implementation of this first phase while planning for subsequent phases continues. GTAC has already improved the department’s ability to manage planning. In 2015/16, the centre may also provide implementation support for digital development.
GTAC’s support included a review of the telecommunications sector’s market structure. Independent experts conducted a market structure study, which provided a detailed analysis of the current market. The study recommended interventions to improve the functioning of the market, efficiently leverage industry capabilities and ensure better returns on public-sector spending.
Oceans management and economic potential
GTAC provided technical support to the Department of Environmental Affairs for the development of a draft policy on the oceans economy, which aims to unlock the economic potential of neighbouring oceans.
While the Department of Environmental Affairs is the custodian of the management and conservation of the oceans, there are many stakeholders who have legislative jurisdiction over certain ocean activities. GTAC supported a detailed stakeholder analysis at the start of the project to identify the interests of the different stakeholders and understand the legislation that governs their actions. As a result, the policy was drafted taking due cognisance of all the existing legislative mandates.
Through the technical support provided, the Department of Environmental Affairs published the White Paper on National Environmental Management of the Ocean. Cabinet approved the white
P a g e | 29
paper, which draws on international best practice and a solid understanding of the domestic legislative environment, and sets out a coordinated sectoral management approach to ocean environmental management. This will allow South Africa to address the growing challenges posed by the effects that humans have on the ocean environment more effectively, while maximising the economic development potential that the ocean presents.
Economies of Regions Learning Network
The Economies of Regions Learning Network is an important GTAC initiative. This learning network brings together economic development practitioners across government to strengthen their agency as leaders in the regional economic development arena. It was established in 2012 to actively support innovation and the effective implementation of regional economic development programmes through institutional transformation. The Economies of Regions Learning Network aims to build organisations’ capacity to implement and support regional economic development initiatives by sharing ideas and approaches. The core members are public-sector policy-makers and practitioners from key provinces and cities in South Africa. Associate members include practitioners from academia, the private sector and non-profit organisations.
Diagnostic studies and reviews
The diagnostic study provides the foundation for successful engagement. It provides an accurate assessment of the real needs and/or challenges, as opposed to perceived needs, of the client. GTAC uses the diagnostic report to make recommendations and design the support required by the client in such a way that directly addresses the agreed needs of the client. These diagnostic studies are a joint effort between the client and GTAC, and are an opportunity for mutual learning and some form of capacity building for the client.
Department of Human Settlements
At the request of the Department of Human Settlements, GTAC reviewed the Technical Capacity Development Chief Directorate’s operations to identify ways to align it with the department’s mandate.
The review contextualised the work of the chief directorate within the human settlements policy and legislative environment, defined the human settlements delivery chain, identified emerging issues and made suggestions for the department’s consideration. Although all project outputs were delivered as planned, the envisaged outcome has not been achieved largely due to the client’s lack of follow-up on the issues identified.
P a g e | 30
Eastern Cape Department of Economic Development, Environmental Affairs and Tourism
As part of GTAC’s support for the Eastern Cape Provincial Department of Economic Development’s planning for the Strategic Integrated Project (SIP) 3 (South-eastern Node and Corridor Development), the centre undertook a diagnostic study to better understand the economic development challenges facing the Wild Coast and determine the support GTAC could offer.
As part of GTAC’s study, it focused on developing a strategy to help people in the field deal with issues in the Eastern Cape Wild Coast integrated development plan. The diagnostic report provides a detailed account of the Wild Coast’s regional development conditions and economic development prospects. Following the conclusion of the diagnostic study, GTAC is developing a programme map and monitoring framework for the department.
Department of Planning, Monitoring and Evaluation
GTAC conducted a detailed diagnostic study of mining communities and labour-sending areas to inform the planning, coordination and budgeting processes needed to revitalise distressed mining communities. The project aims to help government develop a clear, prioritised action plan and to effectively implement the revitalisation of distressed mining communities project.
Given the nature and scope of this project, the project team tested the diagnostic tool and analytical framework in Westonaria Local Municipality, a mining town selected due to its availability of data and the Gauteng Planning Commission’s extensive work conducted in this area. The draft diagnostics of the 26 mining towns and labour-sending areas have been completed, and the project team is engaged in regional workshops with municipal and provincial stakeholders to test the draft diagnostics, review data and fill information gaps.
An important component of the project has been the ongoing interaction with the Department of Planning, Monitoring and Evaluation. During these engagements, the project has helped develop project management capability, provided insight into the diagnostic process (especially regional economic analysis) and supported effective intergovernmental information sharing on specific regional interventions.
Western Cape Department of Economic Development and Tourism
The Transnet National Ports Authority gave the Royal Cape Yacht Club notice of the non-renewal of its lease, which expires in December 2023. The Western Cape Economic Development and Tourism Department requested support to conduct a comprehensive analysis of the current and future effect the Royal Cape Yacht Club has on the City of Cape Town.
This was a small, focused study conducted to inform the relocation of the yacht club, including an analysis of the related requirements, constraints, benefits and costs. The study identified a number of possible locations and an in-principle decision was made to relocate the yacht club to the V&A Marina. It is expected that the Royal Cape Yacht Club will be relocated in a timely manner with positive economic effects for the City of Cape Town and the Western Cape.
P a g e | 31
Western Cape Department of Economic Development and Tourism
This project aimed to develop high-level concept design options for the Gateway precinct in the Cape Town Port precinct. It included a status quo investigation with a baseline assessment of key infrastructure, a review of planning policy directives, a synthesis of constraints and opportunities, and the development of a conceptual framework.
The project’s collaborative approach to developing ideas and concepts enabled structured engagement and the co-design of options. GTAC’s role as a neutral but interested party played an important role in bringing together a variety of role-players to agree on a shared spatial vision for the foreshore area. The conceptual development framework presented a vision for the area with which all role-players felt comfortable.
Western Cape Department of Economic Development and Tourism
The Western Cape Government has linked its development and supply of skills to the anticipated demand for skills arising from the province’s economic priorities, infrastructure plans and ongoing investments. These planned infrastructure developments and the need for maintenance will affect the skills supply and demand in the Western Cape, and as a result, are quite significant for the Western Cape Government Provincial Skills Forum’s programmes and projects.
GTAC provided technical support to the Provincial Skills Forum to develop an objective and evidence-based assessment of the scope for the Western Cape Government’s interventions to match the demand for infrastructure maintenance skills with the supply of artisanal skills provided by public and private further education and training (FET) colleges, now known as technical vocational education and training colleges, in the Western Cape.
GTAC conducted a government infrastructure maintenance skills pilot study, which analysed challenges in government infrastructure maintenance and how these relate to the development and placement of qualified artisans in the broader public sector. The centre also reviewed the skills demand in the electricity, water and sanitation, solid waste, and roads departments of three municipalities (the City of Cape Town, Saldanha Bay Local Municipality and Theewaterskloof Local Municipality), two provincial departments (the Department of Transport and Public Works, and the Department of Health), and one state-owned company (Transnet).
This research provides a platform to discuss infrastructure and skills development. Insights can help develop a strategy with profound implications for economic development.
Eastern Cape Department of Provincial Planning and Treasury
GTAC is helping the Eastern Cape Provincial Treasury review the province’s public entities and their subsidiaries. This project is being executed in phases, with the first phase focusing on providing a holistic overview of all the public entities and their subsidiaries to identify their mandates, functions, key activities and funding streams. Once this is completed, GTAC will complete a more detailed review of the individual entities to identify possible overlaps, gaps and opportunities in the context of existing national and provincial strategic priorities.
P a g e | 32
Strategic planning and performance budgeting
GTAC provides strategic planning and performance budgeting support using a results-based management approach. It helps clients construct visual models to illustrate the links between their actions and their intended results.
Quality Council for Trades and Occupations
GTAC helped the Quality Council for Trades and Occupations revise and finalise its strategic plan for 2012/13 to 2016/17, and prepare its annual performance plan for 2014/15. The centre also helped the council’s staff prepare operational plans. GTAC held a series of planning workshops with council staff, as well as a strategic planning workshop.
During this process, the Quality Council for Trades and Occupations gained a better understanding of the strategic and annual performance planning framework, and the alignment of planning requirements. The council has since put a schedule and process in place to ensure that all the planning components meet its submission deadlines.
National Heritage Council
The National Heritage Council requested support for the review of its medium-term strategic framework and annual performance plans. GTAC analysed and discussed the strategic plans with the council before holding planning workshops. This helped the management teams develop outputs, targets and indicators to address the weaknesses identified in previous strategic plans.
Ditsong Museums
GTAC helped Ditsong Museums of South Africa develop its strategic and annual performance plans for 2015/16 to reflect its new vision of decentralising decision-making authority to various museums. GTAC assessed the previous strategic plan, developed a results matrix, held capacity-building sessions with management staff and facilitated strategic planning workshops.
Department of Planning, Monitoring and Evaluation
The Department of Planning, Monitoring and Evaluation is responsible for government’s strategic plans and annual performance plans. This function was previously managed by the National Treasury, which has agreed to work with the department on a more integrated planning system and framework. GTAC is helping the Department of Planning, Monitoring and Evaluation build its knowledge and capability to effectively manage this new function.
Facilitation
GTAC provides facilitation support for once-off, short interventions at the request of the client. The support typically entails engaging with the client to understand its needs and develop a workshop programme, providing advice on the strategic planning framework developed by the National Treasury, facilitating the workshop and drafting the workshop report.
P a g e | 33
This support was provided to the following clients:
KwaZulu-Natal Office of the Premier. East London Industrial Development Zone. National Treasury, Cooperative Banks Development Agency. National Treasury, Chief Directorate: Economic Services. National Treasury, Public Finance.
GTAC also provided team coaching and leadership development to units within and outside the National Treasury. Feedback from this support has been positive and there have been an increasing number of requests of this nature.
Department of Planning, Monitoring and Evaluation: Operation Phakisa Health Lab
Operation Phakisa, in its adapted form, is an initiative designed to fast-track the implementation of solutions for critical development issues highlighted in the National Development Plan.
The Department of Planning, Monitoring and Evaluation invited GTAC to participate in the Operation Phakisa Health Lab for Ideal Clinic Realisation and Maintenance. A team of five GTAC representatives attended the training course offered by McKinsey, a consulting firm, before the start of the lab. The lab was supported by a combined team from the Department of Health; the Department of Planning, Monitoring and Evaluation; the Malaysian Performance Management Delivery Unit; McKinsey and GTAC over a period of six weeks.
GTAC facilitated the deliverables of various work streams and provided coaching to help lab leaders present to the directors-general, Minister and President. Further discussions are being held with the Department of Planning, Monitoring and Evaluation to reflect on this experience and discuss GTAC’s support for forthcoming labs.
Organisational development
GTAC’s organisational development support focuses on building the capacity of client organisations in a holistic manner to improve performance.
GTAC has developed five specific areas of work to complement its organisational development: Gestalt organisational and systems development; meta-coaching (neurolinguistic programming and neurosemantics); change management; leadership development; and strategic management.
South African National Biodiversity Institute
GTAC has provided support to the South African National Biodiversity Institute (SANBI) since 2010. SANBI was established by combining two institutions under the National Biodiversity Institute to form a new public entity. This transition presented a number of organisational management problems. Some of the problems experienced included the lack of a common understanding of the goals of the transformation objectives within SANBI; management of the expectations of staff and stakeholders of the transition given the expansion of the mandate; diverse constituencies, cultures
P a g e | 34
and backgrounds, areas of work and skills levels; and aligning projects to the government mandate and strategic planning guidelines.
GTAC acted as an independent facilitator, guiding the transitional process and ensuring ownership of SANBI’s new integrated vision. It conducted a comprehensive diagnostic study of the organisation, which informed the individual and group coaching programme.
The SANBI chief executive officer reported that GTAC’s assistance was vital to the success of its transformation initiative, and that the leadership training and coaching was invaluable in fostering change in the organisation.
Eastern Cape Office of the Premier
The Eastern Cape Provincial Government, under the leadership of the Office of the Premier, initiated a system-wide culture change programme in 2011. GTAC and its predecessor, the Technical Assistance Unit, have been assisting the Eastern Cape Office of the Premier in designing and implementing its provincial culture change programme over the last three years.
The project focused on capacitating a group of change agents from the Eastern Cape through a series of workshops and action learning sessions, supported by an expert team consisting of local and international advisors. GTAC trained about 200 change agents, completed a diagnostic report and helped the different departments design and implement interventions focusing on the themes that emerged from the diagnostic report. GTAC also held sessions with the province’s political and administrative leaders focusing on their role in leading the culture change programme.
The provincial culture change programme has taken root in the province, with capacitated and energised officials in place and some encouraging results. In the process, GTAC learnt that culture change support could be more usefully integrated into its broader strategic and technical support.
Department of Higher Education and Training
GTAC provided assistance to the Department of Higher Education and Training to shift the administration of the functions for FET colleges and adult education and training from provincial education departments to the national Department of Higher Education and Training. GTAC’s support improved the capacity of the Department of Higher Education and Training to manage and implement the function shift.
When the project ended in June 2014, some progress had been made, but challenges hindered the function shift’s completion. GTAC’s technical assistant in the department was subsequently contracted directly by the Department of Higher Education and Training to continue with the support. Through this support, the function shift has progressed significantly. The budget has been shifted and 25 532 out of a possible 33 820 posts have been loaded onto the department’s system.
Transport Education and Training Authority
The Transport Education and Training Authority was established in terms of the Skills Development Act (1998) to facilitate the development, registration and implementation of learnerships, skills
P a g e | 35
programmes and strategic initiatives, and the approval of workplace skills plans. In 2010, the Transport Education and Training Authority initiated a process of organisational development that sought to align its structure and culture to the organisational strategy, and improve its human resources policies, procedures and systems.
GTAC reviewed and strengthened the organisation’s strategy and change management implementation. It developed an organisational structure aligned to the strategy and held coaching sessions for the Transport Education and Training Authority’s managers and their teams. The sessions provided an opportunity for teams to present and resolve their organisational development problems.
National Arts Council
The National Arts Council asked GTAC to help it conduct an organisational review to improve its performance and resources, and ensure efficient placement and prioritisation of work roles that link to the strategic plan.
The project entailed re-crafting the National Arts Council’s strategy, reviewing governance structures and providing general human resources and organisational development support to the chief executive officer. To improve the organisational processes, GTAC helped design and implement a new core business process, resulting in more efficient and effective ways of working.
The new organisational design was well received and provided important capabilities to support the council’s strategy. The strategy has also been well implemented and milestones have been consistently achieved.
Department of International Relations and Cooperation
The Department of International Relations and Cooperation asked GTAC to help it establish and operationalise the South African Development Partnership Agency.
Although GTAC established a project management office to support the department and South African Development Partnership Agency project counterparts, the agency did not become operational because GTAC’s support to the client was terminated before completion. This was due to the project being deprioritised within the Department of International Relations and Cooperation.
Department of Public Works
GTAC provided support for the national Department of Public Works’ turnaround initiative from November 2011 to December 2014. In the first phase of the project, GTAC reviewed the departmental situation and made recommendations to the Minister of Public Works on ways to help stabilise the department. The centre also helped the department identify, design and rationalise its turnaround projects; improve its supply chain management processes; and design and launch a model to improve service delivery.
P a g e | 36
Department of Planning, Monitoring and Evaluation
The Department of Planning, Monitoring and Evaluation aims to improve service delivery in government through an operations management and support programme.
During the first phase of the operations support programme, GTAC helped the department develop a conceptual understanding of operations management in the public service and explore possible approaches to providing support to departments.
During a more detailed analysis of the needs of potential pilot departments and sites, GTAC and the department developed case studies on the operations improvement experiences of the Department of Home Affairs (ID Turnaround Project), the Department of Justice and Constitutional Development (Maintenance Turnaround Lean Project) and the Gauteng Department of Roads and Transport (Best Practice Model for Vehicle Registration and Licensing).
GTAC also produced a study on lessons learnt from existing operational improvement initiatives and a needs analysis. The report sheds light on the characteristics of some well-known operations improvement models. During the next stage of support, GTAC will help the Department of Planning, Monitoring and Evaluation design the operations management support programme based on the study’s recommendations.
National Treasury, Public Finance
GTAC provided support to the National Treasury to develop an operational framework for the management of 12 proclaimed fishing harbours. The desired outcome of the project was an effective intergovernmental mechanism with an associated set of procedures and processes to enable the coordinated and cooperative management of the fishing harbours.
GTAC produced a report with a balanced view of the future management of the harbours and clearly articulated roles of the different spheres involved. GTAC presented this document at a workshop, which brought together all government role-players in a joint session. During the workshop, the officials from all spheres of government largely agreed on who should be responsible for the various functions.
Safety and Security Services Sector Education and Training Authority
The Safety and Security Services Sector Education and Training Authority is responsible for skills development and implementation within the safety and security sector. It has been beset by problems of poor management and controls, particularly in the areas of supply chain and financial management. The authority decided to institute a turnaround process and asked GTAC to help implement its turnaround strategy.
During 2014/15, GTAC helped the Safety and Security Services Sector Education and Training Authority improve its capabilities to manage the supply chain and discretionary grant projects. This included improving supply chain management, improving the management of performance information, supporting the implementation of an improved human resources performance
P a g e | 37
management system and implementing a culture-change programme through leadership and team coaching. This support is ongoing.
Eastern Cape Department of Sports, Recreation, Arts and Culture
The Eastern Cape Department of Sports, Recreation, Arts and Culture asked GTAC to help it address challenges related to its operations and service delivery. GTAC conducted an organisational review to improve the department’s delivery against its mandate.
GTAC produced an innovative service delivery model and structure, as well as a functional structure aligned to the department’s strategy and mandate. The main challenge now is to ensure that this structure receives the required financial support from the Provincial Treasury to enable implementation.
National Treasury, Office of the Chief Procurement Officer
The National Treasury established the Office of the Chief Procurement Officer to modernise and clean up supply chain management in government. The institutionalisation of this office is critical.
GTAC conducted a rapid review of the Office of the Chief Procurement Officer and recommended that support be provided to establish the office’s expanded function, clarify its vision and strategic agenda, and reaffirm the existing team.
GTAC helped the office develop its strategy and the organisation itself through team-building activities, functional analysis and human resources modelling.
Neighbourhood Development Programme
The Neighbourhood Development Programme’s Urban Network Strategy is an important focus area, providing direction for spatial targeting and large spatial interventions in South Africa’s cities. GTAC was asked to conduct research on the urban network strategy.
This support is ongoing. GTAC is conducting research to deepen the strategy, drawing on insights form stakeholders focused on the urban spatial and economic debate in South Africa. GTAC will produce high-quality toolkits and guidelines that will be made accessible to municipalities.
Office of Health Standards Compliance
GTAC has provided support to the Office of Health Standards Compliance since 2010, initially developing a business case and later establishing the office as a fully functional organisation. GTAC helped ensure that this new public entity was established and capacitated to implement robust policies, procedures and systems in pursuit of protecting and promoting the health and safety of South Africans.
This support included organisational development and human resources management support, financial management support, change management and coaching, and strategic planning support.
P a g e | 38
Given the limited capacity of the newly created public entity, GTAC’s technical and advisory support played a valuable role during the office’s establishment. The Office of Health Standards Compliance is starting to develop its own capacity and expertise with much less dependency on external support as GTAC’s support comes to an end.
Department of Science and Technology
GTAC provides technical support to the Department of Science and Technology to support the establishment of the Astronomy Management Authority and the National Indigenous Knowledge Systems Office as special service delivery units.
The department established the Astronomy Management Authority as an internal directorate to ensure that all the regulations of the Astronomy Geographic Advantage Act (2007) are adhered to. However, given the regulatory oversight responsibility of the Astronomy Management Authority, it should ideally be located at arm’s length from the department. GTAC is helping to develop a business case that will assess the authority’s appropriate institutional form.
GTAC is also helping the Department of Science and Technology develop a business case on the appropriate institutional form for the National Indigenous Knowledge Systems Office. The department intends to establish the office as a special service-delivery unit to separate its regulatory and implementation activities from the department’s strategic functions. The viability of such a unit will be tested against a range of other options during the feasibility study.
National Treasury, Intergovernmental Relations: Cities Support Programme
The National Treasury’s Intergovernmental Relations Division is responsible for coordinating the Cities Support Programme, which is designed to assist metropolitan municipalities. It operates across five component areas in eight metropolitan municipalities using a results-based approach.
The programme provides targeted technical assistance to cities, coordinating this with fiscal incentives and a complementary programme of regulatory reforms.
GTAC provides technical support to the Cities Support Programme in selected cities to strengthen their leadership capabilities and teams to enable them to more rapidly and effectively address their identified strategic development challenges.
During 2014/15, GTAC supported the Nelson Mandela Bay Metropolitan Municipality. It piloted a variety of approaches and tools, including scenario planning, and helped develop the municipality’s understanding of the broader historical, economic, political and social factors that have contributed to the city’s current dynamics.
Programme and project management support
Programme and project management support is focused on people, processes, tools and technology. GTAC facilitates the implementation of priority programmes and projects, and improves government’s capability to deliver. This support includes providing guidance and advice for project
P a g e | 39
planning, helping to set up project management offices, conducting project management health checks and expanding government’s project management community of practice.
National Treasury, Intergovernmental Relations: Cities Support Programme
In addition to the technical support to the Cities Support Programme discussed previously, GTAC also helped the programme with a subnational “doing business” study in South Africa’s nine largest cities (the eight metropolitan municipalities and the Msunduzi Municipality) during 2014/15. The study is a city-level variation of the World Bank’s annual Doing Business report.
The purpose of the study is to establish incentives to improve government performance. GTAC has provided technical management support to oversee and coordinate project activities and ensure that the findings of the study are institutionalised. It has also provided intergovernmental stakeholder support to the International Finance Corporation/World Bank team and facilitated peer-to-peer learning through the Economies of Regions Learning Network and related forums.
National Treasury, Intergovernmental Relations: Cities Support Programme
A review of the Cities Support Programme’s results framework and implementation readiness highlighted the need for additional specialist capacity to provide monitoring and evaluation support.
GTAC was asked to support the Cities Support Programme manager to develop and implement a monitoring, reporting and evaluation system. The support includes developing and defining the monitoring and reporting framework, developing a monitoring and reporting system, defining and developing the evaluation framework and system, and helping to prepare quarterly and annual evaluation reports. This support is ongoing.
National Treasury, Intergovernmental Relations: Provincial and Local Government Infrastructure Chief Directorate
GTAC and its predecessor the Technical Assistance Unit have supported the Infrastructure Delivery Improvement Programme since 2010. The project consisted of the following six outputs:
Supporting the programme management unit. Mobilising, procuring and demobilising technical assistants. Managing contracts (financial and administration). Managing regional (provincial/sector department) programmes. Providing technical advice to the programme management unit. Developing skills.
In 2014/15, GTAC focused on the technical closure of the programme’s last phase, including a careful handover of several important functions to the client. This brought to a close four years of intense support on this large project. GTAC and the client held a handover workshop to reflect on lessons learnt and what work could be done in partnership with GTAC in the future.
P a g e | 40
Department of Arts and Culture
The Department of Arts and Culture requested organisational development support to enable the Infrastructure Development directorate to improve its service delivery. This directorate is responsible for implementing capital projects.
GTAC produced a diagnostic report with high-level recommendations for improving the management of facilities and budgets. Technical advisors were appointed to finalise the directorate’s strategy and develop systems and policies for its effective management. GTAC also developed an organisational structure and job profiles for the relevant positions.
Financial Intelligence Centre
GTAC and its predecessor the Technical Assistance Unit have provided support to the Financial Intelligence Centre since 2005 at various stages of its communications and information technology system’s development. This included establishing a programme management office and defining, planning and supporting the management of the Sekunjalo modernisation programme.
GTAC has helped the Financial Intelligence Centre plan and implement its modernisation programme through programme management support, technical support and advisory services. This assistance has provided the client with much needed capacity to execute this important and complex project.
Performance management
The performance management area of support entails providing assistance for the development of performance management frameworks and various monitoring and reporting processes.
Safety and Security Sector Education and Training Authority
In addition to the support discussed previously, GTAC provided technical assistance to the Safety and Security Sector Education and Training Authority to improve its capacity to monitor and evaluate projects funded by discretionary grants.
GTAC developed a monitoring and evaluation framework for the grant management system. In the first phase of this work, the centre conducted a diagnostic study of the existing monitoring and reporting systems and selected projects funded through the discretionary grant. This was followed by the development of a framework and evaluation system. GTAC held a capacity-building workshop with the project management office to implement the approved framework. GTAC has recommended that the Safety and Security Sector Education and Training Authority continue to focus on developing its capacity.
P a g e | 41
Department of Planning, Monitoring and Evaluation
In response to service-delivery challenges in departments with concurrent functions, the Forum of South African Directors-General management committee asked the Director-General of the Department of Planning, Monitoring and Evaluation to convene the relevant national departments to ensure that minimum norms and standards for service delivery are in place, and monitored and reported on adequately.
The following departments were identified to participate in the project: Agriculture, Forestry and Fisheries (agriculture, animal control and diseases); Cooperative Governance (disaster management, building regulations, firefighting services, storm-water management systems); Basic Education (education); Environmental Affairs (environment, nature conservation, pollution control, soil conservation, air pollution); Health (health service, municipal health services); Human Settlements (housing); Social Development (welfare services, childcare facilities); Energy (electricity and gas reticulation); and Water Affairs (water and sanitation services limited to potable water supply systems and domestic waste-water and sewage disposal systems).
GTAC provided technical advice and support to the Department of Planning, Monitoring and Evaluation, and assisted with the overall management of the norms and standards project. The project was conducted in stages, the first of which entailed an audit of the current minimum national norms and standards in the selected departments. GTAC produced a status quo report based on this audit.
In the next stage, a set of minimum norms and standards for the departments was developed with an emphasis on roles, functions and concurrent responsibilities. GTAC’s role included reviewing international experience in setting norms and standards, and developing an approach to setting norms and standards.
The project concluded that it is important to determine the exact purpose of minimum norms and standards and how these affect concurrent functions. Norms and standards set for functions in local government must ensure which functions are being devolved or assigned to local government. Costing of norms and standards is also critical. The National Treasury and the Fiscal and Finance Commission will play a bigger role in this work once each department adopts and implements their norms and standards.
KwaZulu-Natal Department of Cooperative Governance and Traditional Affairs
GTAC provided support to the KwaZulu-Natal Department of Cooperative Governance and Traditional Affairs by developing a departmental guideline on monitoring and evaluation. It was anticipated that this support would lead to the institutionalisation of performance management, with consequences for non-adherence to the policy and framework, to ensure transparency and accountability.
Department of Planning, Monitoring and Evaluation
Government is committed to improving the quality and pace of service delivery, and recognises that this requires a significant improvement in the public service’s management practices. The former
P a g e | 42
Technical Assistance Unit helped the Department of Planning, Monitoring and Evaluation develop the management performance assessment tool to assess the quality of management practices in national and provincial departments. The department also developed a municipal version of the tool called the municipal assessment tool. GTAC was asked to help pilot the application of the assessment tool in municipalities and develop criteria for wider application, particularly in municipalities with reduced capacity. Workshops with municipalities and a detailed study of the tool revealed that the municipal assessment tool had to be adapted to suit the specific needs and conditions of municipalities.
The refined assessment tool was renamed the local government municipal improvement model. This improved model is now used to measure the institutional performance of municipalities across key performance areas. In each area, performance is assessed against standards established by the relevant department. The local government municipal improvement model adopts a holistic approach to analysing institutional performance in municipalities.
Manufacturing, Engineering and Related Services Sector Education and Training Authority
GTAC is helping the Manufacturing, Engineering and Related Services Sector Education and Training Authority develop a monitoring and evaluation framework that will enable the authority to track the results of its skills development work, including its contribution to South Africa’s growth and development objectives. The framework will focus on impact and facilitate the effective use of information for management decisions and improvements in the authority’s skills development work. The project is ongoing.
Table 4: Technical Advisory Services project list Project
Nature of support Status
Department of Human Settlements: High-level diagnostic of the Technical Capacity Development Chief Directorate
Diagnostic Completed
Department of Planning, Monitoring And Evaluation: Support to distressed mining communities
Diagnostic Ongoing
Department of Economic Development, Environmental Affairs and Tourism: Eastern Cape Wild Coast integrated development programme (SIP 3)
Diagnostic Ongoing
Department of Rural Development and Land Reform: Cadastre modernisation programme
Diagnostic Pipeline
Limpopo Province Provincial Treasury: Infrastructure delivery support Diagnostic Pipeline Council for the Built Environment: Strategic support on the application of infrastructure delivery management system for built environment specialists
Diagnostic Pipeline
Western Cape Department of Economic Development and Tourism: Royal Cape Yacht Club
Review Completed
Western Cape Department of Economic Development and Tourism: Foreshore precinct development
Review Completed
Western Cape Department of Economic Development and Tourism: Government infrastructure maintenance skills pilot study
Review Completed
Department of Telecommunications and Postal Services: Wholesale open access network study
Review Ongoing
Eastern Cape Provincial Treasury: Review of the mandates of Eastern Cape public entities and their subsidiaries
Review Ongoing
National Treasury Asset and Liability Management: Review of provincial Review Pipeline
P a g e | 43
Project
Nature of support Status
development finance institutions KwaZulu-Natal Department of Cooperative Governance and Traditional Affairs: End-term review of the strategic plan 2010–2015
Review Pipeline
Department of Environmental Affairs: National Framework on Marine Spatial Planning for South Africa
Review Pipeline
Quality Council for Trades and Occupations: Revision of strategic plan 2012/13 to 2016/17 and annual performance plan for 2014/15
Planning and budgeting
Completed
National Heritage Council: Support for medium-term strategic framework and annual performance plan
Planning and budgeting
Completed
National Economic Development and Labour Council: Development of strategic plan and annual performance plan
Planning and budgeting
Completed
Financial Intelligence Centre: Strategic support for Egmont Group Planning and budgeting
Completed
Ditsong Museums: Strategic plan facilitation Planning and budgeting
Ongoing
Department of Planning, Monitoring and Evaluation: Building capacity for the strategic and annual planning function
Planning and budgeting
Ongoing
Public Service Sector Education and Training Authority: Development of 2015/16 annual performance plan
Planning and budgeting
Ongoing
Tax Ombud: Strategic and annual performance plan 2015 Planning and budgeting
Pipeline
KwaZulu-Natal Office of the Premier: Facilitation of strategic planning and annual performance plan
Facilitation Completed
National Treasury, Public Finance: Leadership transition support Facilitation Completed Cooperative Banks Development Agency: Facilitation of strategic planning sessions
Facilitation Completed
East London Industrial Development Zone: Strategic planning support Facilitation Completed Department of Planning, Monitoring and Evaluation: Operation Phakisa: Health Lab
Facilitation Ongoing
National Treasury, Public Finance: Strategic planning for Economic Services Chief Directorate
Facilitation Ongoing
South African National Biodiversity Institute: Sustainable transformation process – phase 3
Change management
Completed
Eastern Cape Office of the Premier: Implementation of the provincial culture change programme
Change management
Ongoing
Department of Environmental Affairs: State of management of the oceans in South Africa
Organisational development
Completed
Department of Higher Education and Training: FET functions transfer Organisational development
Completed
Department of Higher Education and Training: Functions transfer Organisational development
Completed
Transport Education Training Authority: Organisational development review
Organisational development
Completed
National Arts Council: Organisational review Organisational development
Completed
Department of International Relations and Cooperation: Operationalisation of the South African Development Partnership Agency
Organisational development
Completed
Department of Planning, Monitoring and Evaluation: Operations management support programme
Organisational development
Completed
National Treasury, Public Finance: Development of a model for the management and operation of fishing harbours
Organisational development
Completed
Department of Public Service and Administration: Development of business case to define institutional arrangements
Organisational development
Completed
Eastern Cape Department of Education: Supply chain management improvement to contribute to the turnaround framework
Organisational development
Ongoing
Department of Public Works: Operational support to the department’s business improvement unit
Organisational development
Ongoing
Safety and Security Sector Education and Training Authority: Support for systems improvement and culture change
Organisational development
Ongoing
Eastern Cape Department of Sport, Recreation, Arts and Culture: Conducting an organisational review of the department
Organisational development
Ongoing
National Treasury: Technical support to the Office of the Chief Organisational Ongoing
P a g e | 44
Project
Nature of support Status
Procurement Officer development Department of Planning, Monitoring and Evaluation: Monitoring programme
Organisational development
Ongoing
Neighbourhood Development Programme: Guidelines to develop the Urban Network Strategy support guide
Organisational development
Ongoing
Department of Planning, Monitoring and Evaluation: Opsup – phase 2 Organisational development
Ongoing
National Treasury, Intergovernmental Relations: Cities Support Programme: Nelson Mandela Bay organisational development support
Organisational development
Ongoing
Department of Home Affairs: Feasibility study for Border Management Agency
Organisational development
Ongoing
Department of Science and Technology: Feasibility study for Astronomy Management Authority
Organisational development
Ongoing
National Department of Health: Health Standards Compliance Office Organisational development
Completed
Office of Health Standards Compliance: Technical assistance to develop systems and build capacity
Organisational development
Ongoing
Department of Science and Technology: Feasibility study for the National Indigenous Knowledge Systems Office
Organisational development
Ongoing
National Treasury, Intergovernmental Relations: Cities Support Programme – leadership development support
Organisational development
Ongoing
Department of Telecommunications and Postal Services: Development of policy directions on rapid deployment
Organisational development
Pipeline
Eastern Cape Education: Integrated School Improvement Programme Organisational development
Pipeline
North West Department of Health: Implementation of operations management framework
Organisational development
Pipeline
Department of Mineral Resources: Review and re-engineering of business processes
Organisational development
Pipeline
National Treasury, Public Finance: Development of a funding model for Thusong service centres
Organisational development
Pipeline
Eastern Cape Office of the Premier: Support to the Office of the Premier technical support unit
Organisational development
Pipeline
Department of Cooperative Governance and Traditional Affairs: Shared services model for corporate and financial services for the Department of Cooperative Governance and Traditional Affairs and the Municipal Infrastructure Support Agent
Organisational development
Pipeline
National Treasury: Infrastructure Delivery Improvement Programme – phase 3
Programme management
Completed
Department of Arts and Culture: Support to implement capital works projects
Programme management
Completed
Financial Intelligence Centre: Implementation of United Nations Office on Drugs and Crime support system
Programme management
Completed
Department of Telecommunications and Postal Services: Broadband implementation plan
Programme management
Ongoing
National Treasury, Intergovernmental Relations: Cities Support Programme: Technical management support for subnational doing business report
Programme management
Ongoing
Financial Intelligence Centre: Business support system implementation Programme management
Ongoing
National Treasury, Office of the Accountant-General: Support for the municipal financial planning and budgeting reform programme
Programme management
Ongoing
National Treasury, Intergovernmental Relations: Cities Support Programme: Monitoring and evaluation support
Programme management
Ongoing
City of Johannesburg Department of Economic Development: Institutional and programme development support
Programme management
Pipeline
Department of Communications: Establishment of a project management unit
Programme management
Pipeline
Limpopo Department of Sport, Arts and Culture: Spending of the community library conditional grant
Programme management
Pipeline
National Treasury, Intergovernmental Relations: Infrastructure delivery improvement support initiatives
Programme management
Pipeline
P a g e | 45
Project
Nature of support Status
Safety and Security Sector Education and Training Authority: Diagnostic and monitoring and evaluation framework for projects
Performance management
Completed
Department of Planning, Monitoring and Evaluation: Development of norms and standards for concurrent functions
Performance management
Completed
KwaZulu-Natal Department of Cooperative Governance and Traditional Affairs: Development of departmental monitoring and evaluation policy
Performance management
Completed
Department of Planning, Monitoring and Evaluation: Municipal performance assessments
Performance management
Completed
Manufacturing, Engineering and Related Services Sector Education and Training Authority: Assistance with monitoring and evaluation policy and framework
Performance management
Ongoing
National Treasury, Budget Office: Improved expenditure monitoring and data reporting systems
Performance management
Ongoing
Department of Planning, Monitoring and Evaluation: Phakisa operations manual
Methodology development
Pipeline
P a g e | 46
ENVIRONMENTAL ECONOMICS AND FINANCE
Unit Head: Sharlin Hemraj
During the reporting period, GTAC conducted a review of environmental public finance issues. The centre also supported several climate-change policy initiatives and provided economic analysis to the Department of Environmental Affairs.
Biofuels incentive mechanism
South Africa’s Biofuels Industrial Strategy, adopted in 2007, recommends the development of a financial incentive mechanism to support a 2 per cent penetration of biofuels into the national road transport fuel pool. A position paper drafted by the Department of Energy in 2013 proposed a production incentive for biofuels based on a return on assets of 15 per cent. It set out details on the licencing criteria for manufacturers; biofuels pricing and reference crops; qualifying criteria for the biofuels subsidy scheme; and proposed administration of the biofuels levy and disbursement of funds. For the pricing framework, the position paper expanded on the financial model to be used to determine the levels of the incentive required to support the production of bioethanol and biodiesel.
The National Treasury has undertaken further work on risks to the fiscus associated with the proposed incentive, including the open-ended nature of the liability. To support this work, GTAC provided the National Treasury with an assessment of the biofuels incentive mechanism. The National Treasury and the Department of Energy compiled a joint briefing note outlining the alternative approach of a competitive bidding process for the biofuels incentive mechanism for their respective ministers.
Waste tyre management
South Africa generates a significant amount of tyre waste. The inappropriate disposal of existing and legacy waste tyres – either into landfills or dumped illegally – has negative environmental consequences. In response, the Minister of Water and Environmental Affairs has approved the Recycling and Economic Development Initiative of South Africa.
GTAC has supported the National Treasury in clarifying the nature of proposed fees as “taxes” under this initiative, the flow of collected revenues to the Department of Environmental Affairs, and associated governance and institutional arrangements. This process resulted in the announcement of the tyre levy in the 2015 Budget. GTAC also provided support on the implementation process for the tyre levy, and the need for further consultation on the establishment of the Waste Bureau to manage and oversee industry waste management plans.
Biodiversity finance initiative
The United Nations Development Programme has initiated a process to quantify the level of spending on biodiversity management. South Africa has been selected as a recipient of funding for a pilot project. This work will entail a policy, institutional and expenditure review. The Department of
P a g e | 47
Environmental Affairs appointed a national project lead in March 2015 and GTAC has been asked to provide economic analysis support for this initiative.
Climate finance
The National Climate Change Response Policy requires South Africa to develop a monitoring and evaluation system to measure progress against targets. In 2014, the Department of Environmental Affairs began a process to develop the monitoring and evaluation system, including setting up a greenhouse gas emissions inventory and recording climate finance flows.
During the reporting period GTAC coordinated National Treasury inputs on climate finance data and the design of the monitoring and evaluation system. The centre also facilitated discussions with interested parties such as the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP), the South African National Energy Development Institute and the National Business Initiative.
Discussion paper: public environmental expenditure
Government is working to encourage the shift towards a low-carbon, green economy. As part of a longer-term project, GTAC has prepared a discussion paper on environmental expenditure programmes, which will be published in 2015/16. It reviews South Africa’s public programmes, resources and instruments to support the transition to a green economy, informed by methodologies developed by the World Bank and the Organisation for Economic Cooperation and Development.
PUBLIC FINANCE AND EXPENDITURE REVIEWS
Unit Head: Ronette Engela
Purpose
Government’s performance and expenditure reviews are a joint project initiated by the Department of Planning, Monitoring and Evaluation and the National Treasury. The project will cover between 20 and 30 leading policy initiatives. It is designed to identify options to obtain greater value for money and improve alignment in the use of development and service-delivery indicators. The latter objective will strengthen performance monitoring, and budget planning and reporting, across government.
Review topics are identified during discussions of the Ministers’ Committee on the Budget and include priority areas identified in the National Development Plan.
Each public expenditure review has a steering committee composed of officials from the National Treasury, the Department of Planning, Monitoring and Evaluation and the relevant national department. Technical analysis is done by consultants appointed through a tender process. Progress is tightly monitored through a formal system that requires joint evaluation and sign-off. Projects typically take place over four to five months. A completed review includes programme analysis and performance measures, expenditure analysis, and costing models with forward projections, proposed scenarios and rollout plans.
P a g e | 48
Highlights, achievements and challenges
The first phase of reviews has been well received, contributing knowledge about key programmes and options to improve budgeting and value for money.
Following the completion of analytical work, the Department of Planning, Monitoring and Evaluation, the National Treasury and affected departments discuss reform options. To date these fall into three categories:
Improvements to government’s Basic Accounting System and other state information systems.
Use of technical information to improve programme planning and implementation. Institutional and policy options for additional consideration.
The extensive modelling provided by the reviews allows officials to understand the impact of policy parameters on budget requests and to make proposals for possible savings. The methodology can be expanded to estimate the costs of new policy proposals. A process is under way to develop guidelines and tools to broaden practical access to this methodology.
In some cases, the studies identify policy and programme design challenges that may prompt more in-depth reviews. For example:
Following completion of a review of language services policy and activities of related entities, the Department of Arts and Culture is undertaking reforms in these areas.
Reform of business processes of the artisan training division in the Department of Higher Education and Training, and the National Skills Fund has been initiated.
Following a scarce skills study in the Department of Home Affairs, a broader review of issues associated with the Basic Accounting System is under way.
Reviews of public transport and housing have generated considerable interest. Further work on the links between urban housing and public transport is in progress. A focus group has been formed to create a better understanding of the interdependencies and dynamics linking human settlement, transport and urban spatial forms, and to identify ways to strengthen programmes.
In taking the public expenditure review project forward, problems in obtaining data in appropriate formats will need to be addressed, particularly in complex areas of work. Cooperation of line departments and officials, and action on review implications are important determinants of success.
P a g e | 49
Highlights of completed and current studies
Given that this is GTAC’s first annual report, it is reporting on both current and completed studies – including those that were concluded before the current reporting period.
Micro Agriculture Finance Institutions of South Africa (completed April 2014)
The Micro Agriculture Finance Institutions of South Africa (MAFISA) was designed to provide loan financing to small and very small agricultural producers and processors. Government allocated R1 billion to MAFISA in 2005. Micro-loans are made through a system of financial intermediaries appointed by the Department of Agriculture, Forestry and Fisheries. Beneficiaries pay 8 per cent interest on the loans, and the intermediaries carry the risk of default.
The study shows that MAFISA is only viable if a default rate of less than 5 per cent can be maintained. This does not appear to be realistic in the agricultural environment. If government decides to continue with MAFISA or similar programmes, a workable risk-sharing structure should be designed. In addition, there is a policy coordination problem given the number of grant instruments in agriculture. Action has been taken to withdraw MAFISA funds and address the outstanding loan book. It seems likely that a high proportion of loans will be not be recovered.
Pan South African Language Board, Commission for the Promotion and Protection of the Rights of Cultural, Religious and Linguistic Communities, and Department of Arts and Culture Language Services (completed April 2014)
Unclear and open-ended mandates appear to have contributed to poor operational focus and overlaps in activities related to the “promotion and development of languages”. Three entities work in this area, but there is limited consultation among them when planning activities and outputs. This review raised concerns about the cost implications of the Use of Official Languages Act (2012), which requires all national departments, national public entities and enterprises to have a language unit.
Artisan development programme (completed July 2014)
Artisan training has been revived from a low point in 2005, when only 4 500 artisans qualified, to nearly 15 000 in 2013. Artisan development currently costs government just over R4 billion per year. The National Development Plan sets a target of 30 000 artisans a year by 2030, and expenditure is set to expand to nearly R6 billion by 2018. Although significant investment in artisan training is required, the study shows that better value can be obtained from allocated funds. The quality of programmes offered by technical vocational education and training colleges, and their throughput rates, need to be improved if employer confidence in these programmes is to be increased.
National Skills Fund (completed July 2014)
The National Skills Fund receives about one-fifth of the skills development levy of 1 per cent on all payrolls. The fund is meant to play a catalytic role in post-school education and training. However, the various national skills development strategies do not give clear direction on how this role is to be fulfilled. In recent years, substantial National Skills Fund funding has gone towards financing
P a g e | 50
budgetary shortfalls in FET colleges and the National Student Financial Aid Scheme. These stop-gap measures are not consistent with the National Skills Fund’s intended role.
Moreover, funding the budgetary shortfalls of colleges and the National Student Financial Aid Scheme out of its reserves will deplete the National Skills Fund’s reserves over the next three years. It is unclear how further budgetary shortfalls will be financed, placing the fiscus under additional pressure.
The expenditure review suggests that refocusing National Skills Fund funding on bridging programmes to enable the young and unemployed to obtain post-school education and training, and on industry-relevant technical and vocational programmes, could benefit about 170 000 learners a year.
Small Enterprise Development Agency technology incubators (completed July 2014)
The study of the technology incubation programme of the Small Enterprise Development Agency shows that it is well-conceived and consistent with global best practice for small business development, technology adoption and long-term sustainability. In recent years, the focus on technology has been diluted from a performance targeting and monitoring perspective. The review recommends that this should be given renewed focus in the expected realignment of enterprise support agencies associated with the establishment of the Department of Small Business Development.
Land restitution (completed August 2014)
To date, the Land Restitution Programme has settled 85 per cent of about 60 000 claims lodged since its inception in May 1995. Most of the settled claims were urban (87 per cent) and were relatively straightforward. Most initial claims (92 per cent) were finalised through financial compensation. Since the inception of the Commission on Restitution of Land Rights, R29.3 billion has been spent on land restitution. The number of claims settled per year has been declining since 2002, and in the last five years only 2 808 claims were settled. As at March 2013, there were 8 733 outstanding claims.
According to a regulatory impact assessment done by the Department of Rural Development and Land Reform, the reopening of the claims process could result in the registration of an estimated 397 000 new claims. Based on current trends, the cost of land claims over the next two decades could be between R230 billion and R265 billion.
The process that underpins the restitution programme is inherently complicated and highly structured. However, its efficiency is compromised by weak business processes, human resource constraints, and overlapping roles and responsibilities between the Department of Rural Development and Land Reform and the Commission on Restitution of Land Rights.
P a g e | 51
Effective partnering of science councils with the private sector (completed September 2014)
As a group, South Africa’s science councils generate about R0.62 in private income for every R1 invested by government. This is low by international comparison. The exceptions are Mintek and, to a lesser degree, the Council for Scientific and Industrial Research. (Private income in the study includes contracts with state-owned companies, which account for a small proportion of councils’ income.) It is apparent from the study that partnerships with the private sector have not been given sufficient priority as a policy objective. While not necessarily appropriate for science councils, important links with trade and industry policy, and technology development, should be pursued.
Public transport systems in five metro areas (completed November 2014)
Public transport services are characterised by long travel distances, high peak demand, minimal off-peak use and unidirectional travel patterns strongly influenced by the spatial structure of South African cities. Government subsidies for rail and bus public transport are high, equivalent to about 60 per cent of the cost of rendering the services. Yet it is estimated that 18 per cent of households spend more than a fifth of their income on transport.
Suboptimal and fragmented management of public transport services contributes to high costs. The wide range of institutional arrangements, combined with fragmented control over transport budgets, means that large shares of public resources are allocated to services carrying relatively fewer passengers, while high-volume services provided by minibus taxis receive much less support.
Over the short term, these deficiencies can be addressed by improving institutional alignment between public transport departments at provincial and local level, and PRASA. Metropolitan government should become the key site of decision-making. This would facilitate better planning and integration. In addition, a pragmatic approach to the articulation between formal transport and the minibus taxi sector is needed. Current plans to formalise the taxi industry, or replace it with more formal services, are unlikely to be affordable in the short term.
Over the longer term, government needs to integrate public transport and land-use planning to change the urban spatial form. This includes shortening travel distances, creating bidirectional passenger flows throughout the day, and reducing the high differential between peak and off-peak demand. Short-term strategies to support the densification of cities in specific nodal areas and along identified corridors will help to reduce the costs of public transport.
P a g e | 52
Scarce skills immigration policy (completed November 2014)
Skilled immigrants contribute to economic growth and create jobs. Many countries seek to obtain scarce skills through preferential immigration criteria, sometimes combined with active recruitment programmes. South Africa’s formal immigration policy is still based on a labour protection paradigm, though government has signalled the intention to change this approach. The National Development Plan sets a target of 50 000 scarce skills visas to be issued a year by 2030.
The study assisted the Department of Home Affairs in developing a proactive skilled immigration policy and implementation plan based on a well-researched scarce skills list and taking into consideration the costs of mission consular services and permitting procedures.
Funding model for social housing (initiated October 2014)
In social housing projects, government capital and institutional subsidies account for about 70 per cent of expenditure. The balance is raised through debt and private-sector equity funding. Private-sector investment in social housing, which is determined by projections of future rental income and operating costs, has been stagnant. The study seeks to identify factors that could contribute to greater private investment in social housing, and options for more efficient and effective use of available funds and institutional capacity.
Water and sanitation value chain (initiated October 2014)
Providing water to households involves various stages, from collection and storage of raw water, to supply of bulk water, to provision of potable water and subsequent recovery through treatment plants. Management of water flows and associated expenditure is negotiated through a complicated institutional landscape that includes a Department of Water Affairs trading account, 15 water boards, and district and local municipalities. The review seeks to better understand this process, and identify and assess alternative arrangements for cost recovery rather than ongoing fiscal transfers. There is a concern that some of the present infrastructure subsidies in the municipal infrastructure grant and the funding for water boards involve overlapping funding for the same services.
Provincial road expenditure (initiated October 2014)
A comparative cost study of provincial road expenditure is working to understand trends and cost drivers. While unit costs between provinces differ because of differences in geography and soil conditions, it is not clear that the range of unit costs per kilometre for similar roads can be ascribed to these differences. This study should contribute to better road rehabilitation, maintenance planning and budgeting.
Nutrition and food security for children (initiated October 2014)
There are 18 nutrition intervention programmes undertaken by national and provincial departments of Health, Agriculture and Social Development. Expenditure trends for these various interventions are not readily available. This study aims to assist in this regard.
P a g e | 53
School infrastructure delivery (initiated October 2014)
There is a large difference in the costs of school infrastructure between provinces – even where buildings and circumstances are similar. A detailed understanding of unit costs for school infrastructure delivery is required, along with models predicting future costs and possible savings. The Department of Basic Education gazetted a set of norms and standards for school infrastructure in November 2013. The cost implications of these norms, most of which are to be phased in over 10 years, are not yet clear.
Further education and training funding (initiated October 2014)
FET colleges can provide unemployed young people with skills, and contribute to productivity and growth. The full cost implications of the proposal to double the number of people presently trained need to be understood. In the earlier National Skills Fund study, it became apparent that FET colleges were charging different fees for similar courses and raising income through diverse services to business clients. To help assess budget proposals for increased capacity, the National Treasury seeks a clear picture of the value of current expenditure. The National Skills Fund study has provided some insight into FET costs and has identified possible concerns about the relevant funding norms.
Government accommodation – leases (initiated October 2014)
Government leases a significant portion of its office accommodation from private landlords. The cost of leasing those premises is about R3 billion per year and is a significant area of government expenditure. Perceptions of state departments overpaying for office accommodation and/or not deriving value for money have fuelled concern of the additional burden on the fiscus. The study aims to review the rental costs for leased-in office accommodation.
Personnel expenditure trends (initiated March 2015)
The growth of the personnel expenditure component of the national budget needs to be better understood. Initiatives such as the occupation-specific dispensation for scarce personnel appear to have had a far larger impact on departmental budgets than was envisaged. In addition, the National Treasury would like to support discussions in the Public Service Coordinating Bargaining Chamber through detailed projections and modelling of the fiscal consequences of various proposals, including those involving housing benefits and possible medical scheme benefit amendments.
A series of detailed sectoral reviews of personnel expenditure (beginning with education, health, defence and the South African Police Service) will be undertaken. These will enable scenarios for remuneration and employee benefits to be quantified. An overarching model to assess headline and general trends in personnel will be developed on the basis of data extracted. This is a large project that will be undertaken in phases over two years.
JOBS FUND PROJECT MANAGEMENT UNIT
Unit Head: Najwah Allie-Edries
P a g e | 54
The Jobs Fund supports initiatives that generate employment in innovative ways. The fund offers once-off grants in the areas of enterprise development, infrastructure, support for work seekers and institutional capacity building.
The fund awards grants through a competitive project application process that rewards the best ideas. Funding allocations are transparent, open and competitive, and are made by an independent investment committee. Project partners are required to share risks and costs by matching the grant fund allocation.
Since its inception in July 2011, the Jobs Fund has concluded four calls for proposals, allocating R4.7 billion in grants to 90 approved projects. At end-March 2015, R2.5 billion had been disbursed to active portfolio projects that had created 47 967 new permanent jobs and placed 21 100 beneficiaries in previously vacant permanent positions. The fourth-round projects, approved in January 2015, involved existing partners scaling up projects already under way. The fifth call for proposals targets the agricultural sector. The application stage for this round closed in February 2015. The fund’s technical evaluation committee has recommended 30 partners to submit a full business case.
MUNICIPAL FINANCE IMPROVEMENT PROGRAMME
Unit Head: Danie Beukes
The MFIP, now in its second phase, is an initiative of the Office of the Accountant-General. It is financed through Programme 8 of the National Treasury vote. The MFIP is designed to support municipalities in meeting the requirements of the Municipal Finance Management Act and addressing associated capacity constraints.
The MFIP’s programme management unit operates within GTAC. It is responsible for planning and preparing the MFIP’s work programme, managing its budget, formulating its scope of work and specific project objectives, managing its projects and evaluating resource performance.
The MFIP II includes support for the municipal finance reform activities of the Intergovernmental Relations Division of the National Treasury, including improved financial monitoring and reporting and implementation of the municipal chart of accounts.
P a g e | 55
INDEPENDENT POWER PRODUCER PROCUREMENT PROGRAMME OVERVIEW
The Department of Energy, the National Treasury and the Development Bank of Southern Africa established the IPPPP at the end of 2010. This urgent intervention sought to increase power generation capacity, subject to relevant provisions of the Electricity Regulation Act and under the authority of the Minister of Energy.
The programme’s overall mandate is to secure electrical energy generated from renewable and non-renewable sources from the private sector. Private-sector participation diversifies the supply and nature of energy production, improves energy security, introduces new skills and investment into the energy technology industry, and enables the benchmarking of performance and pricing. The renewables component of the programme, described below, makes an important contribution to reducing South Africa’s reliance on fossil fuels.
The IPPPP is designed to be self-funding through revenue derived from development fees paid by IPP bidders and investors, which cover the programme’s additional operational, procurement and contract management expenses. The office’s operational expenditure is recovered from IPP development fees in a programme account maintained by GTAC on behalf of the National Treasury and the Department of Energy. The IPPPP Office is administratively supported by the Development Bank of Southern Africa.
RENEWABLE PORTFOLIO
The REIPPPP is the most advanced component in the IPPPP portfolio. It is seen globally as a success story, with lessons for both developed and developing countries. The programme currently considers projects based on onshore wind, concentrated solar power (CSP), solar PV, small hydro, biomass, biogas, landfill gas and cogeneration technologies. It aims to:
Procure 13 225 MW of renewable energy by 2020 from various sources, including onshore wind, CSP, solar PV, small hydro, biomass, biogas and landfill gas.
Contribute to socioeconomic development and environmentally sustainable growth. Stimulate the domestic renewable energy industry.
Under the REIPPPP, tenders are structured in a rolling bid-window programme that facilitates sustained market interest and increases competitive pressure among bidders to reduce pricing.
As at 31 March 2015, there were four approved REIPPPP bid windows, as shown below.
P a g e | 56
Table 5: REIPPPP bid window summary, end-March 2015
The table below summarises the total capacity and number of projects procured as at end-March 2015. In total, 4 122 MW of electricity has been procured from 66 projects, of which 1 709 MW has been connected to the national grid.
Table 6: REIPPPP projects by technology and capacity, end-March 2015
Notable achievements of the REIPPPP include the following:
Average tariffs have declined as a result of the competitive procurement approach, with the average tariff (in 2013 terms) for onshore wind declining by 43 per cent to an average of R0.74 per kWh, and for solar PV by 68 per cent to R0.99 per kWh between bid window 1 and 3.
IPPs have committed a total R145 billion in investment. Some 49 per cent of IPP construction spend has been procured from local suppliers. South Africans own 50 per cent of REIPPPP projects. As at end-March 2015, black South Africans
owned 28 per cent of total projects that have reached financial closure. Relative to comparable coal- and diesel-generated Eskom power, 3.3 million tonnes of carbon
dioxide equivalent reduction has been achieved. The majority of IPP projects have reached commercial operation earlier than initially envisioned.
Bid window 1 Bid window 2 Bid window 3 Bid window 3.5
Submission date: 4 November 2011
28 preferred bidders 1 425 MW of
contracted capacity Financial close:
5 November 2012
Submission date: 4 March 2012
19 preferred bidders 1 040 MW of
contracted capacity Financial close: 9 May
2013
Submission date: 19 August 2013
17 preferred bidders 1 456 MW of
contracted capacity Financial close: 16 of
17 projects have reached financial close, one remaining project expected to reach financial close in Q3 2015/16
Submission date: 31 March 2014
Two preferred bidders 200 MW of contracted
capacity Financial close:
Expected in Q3 2015/16
Technology Bid window 1 Bid window 2 Bid window 3 Bid window 3.5 Total MW Nr MW Nr MW Nr MW Nr MW Nr
Onshore wind 649 8 559 7 787 7 - - 1 995 22 Solar PV 627 18 417 9 435 6 - - 1 479 33 Solar CSP 150 2 50 1 200 2 200 2 600 7 Landfill gas - - - - 18 1 - - 18 1 Biomass - - - - 17 1 - - 17 1 Small hydro - - 14 2 - - - - 14 2 Total 1 425 28 1040 19 1457 17 200 2 4 122 66
P a g e | 57
The REIPPPP has led to South Africa’s inclusion as one of the world’s top 10 markets for utility-scale solar power capacity (solar installations of 5 MW and above) and the top 10 renewable energy investing countries in 2014.1
PROGRAMME EXPANSION
The IPPPP Office has announced an expansion of the programme under bid window 4. The programme is also broadening its invitations to independent small-scale renewable energy producers. At the same time, the Department of Energy has expanded the mandate of the IPPPP Office to include the procurement of electrical energy from coal, natural gas, cogeneration and imported hydro in line with 2010 Integrated Resource Plan requirements.
1 Sources: http://www.southafrica.info/business/success/energy-080714.htm#.VVGyMfmqozt and Frankfurt School and United Nations Environment Programme Collaborating Centre for Climate & Sustainable Energy Finance. 2015. Global Trends in Renewable Energy Investment 2015. Frankfurt School: Frankfurt.
P a g e | 58
NATIONAL TREASURY PROGRAMME 8: TECHNICAL SUPPORT AND DEVELOPMENT FINANCE OVERVIEW OF THE TECHNICAL SUPPORT AND DEVELOPMENT FINANCE PROGRAMME
The National Treasury’s Programme 8: Technical Support and Development Finance aims to build public-sector capacity by offering a range of diagnostic services, organisational development, and programme and project implementation support; to improve capacity in PPPs and capital projects’ planning and oversight; to strengthen public-sector financial management and infrastructure delivery; and to facilitate job creation.
GTAC provides coordination and management support to the Technical Support and Development Finance Programme. The Programme 8 subprogrammes aim to:
Strengthen public finance management capacity in municipalities and support provincial treasury oversight of local government financial management.
Support infrastructure planning and implementation in provinces and infrastructure skills development in municipalities.
Promote public and private investment in city development, integrated urban networks and neighbourhood development initiatives.
Promote innovative and partnership-based approaches to job creation, jobseeker support and enterprise development.
LOCAL GOVERNMENT FINANCIAL MANAGEMENT SUPPORT
Financial management grant to municipalities
Background and purpose
The Municipal Finance Management Act Implementation Unit in the Office of the Accountant-General administers the financial management grant, which is available to all 278 municipalities. To receive the grant, municipalities must submit support plans that identify weaknesses in financial management to be addressed through the grant allocations. Financial management grant funds can be used to establish municipal budget and treasury offices; improve supply chain and audit outcomes; appoint financial management interns; invest in financial management systems, training and implementing reforms; and implement any financial discipline. Progress is monitored through regular reports to the National Treasury.
P a g e | 59
Transfer of funds
In 2014/15, R449.1 million was disbursed in terms of the Division of Revenue Act (2014) in two payments. In July 2014, R442.3 million was transferred to 274 municipalities. Payment was delayed to four municipalities who either did not comply with the Division of Revenue Act requirements or did not provide their updated cash flows and reasons for spending prior funds slowly. The outstanding documents were subsequently submitted to the National Treasury after correspondence with these municipalities and R6.8 million was transferred to the remaining four municipalities in August 2014.
Financial management grant support plans
An analysis of the 2014/15 financial management grant support plans submitted by municipalities showed that municipalities on average planned to spend the grant as follows:
Figure 3: 2014/15 financial management grant planned spending
In 2014/15, funds were allocated to build capacity and skills development in finance and supply chain management disciplines within the minimum competency framework.
Reporting and outputs achieved
Municipalities have to submit financial management grant spending reports aligned to their support plans to the National Treasury on a monthly basis. Due to staffing constraints, it is impossible to undertake site visits or perform physical verifications at municipalities.
P a g e | 60
The actual performance of the grant is best measured at the municipal level and can be audited as part of the regularity audit performed by the Auditor-General.
Total spending levels at the end of March 2015 were on average 67 per cent. The municipal financial year differs from the provincial financial year. The 2014/15 municipal financial year end was June 2015. In the past, spending has been close to 100 per cent at municipal year end.
The financial management grant contributed to the following outputs:
All 278 municipalities submitted their 2014/15 financial management grant support plans. 128 municipal managers and 140 chief financial officers completed municipal finance
management programme training as at 31 March 2015, and 8 946 municipal officials completed financial management and supply chain management training.
As at 31 March 2015, 1 302 interns were appointed in municipalities across all nine provinces.
Figure 4: Financial management grant interns
Municipalities reported the establishment of:
Internal audit units at 278 municipalities. Audit committees at 277 municipalities. Supply chain management units at 278 municipalities.
A total of 233 municipalities developed audit action plans to address 2013/14 audit findings.
Improvements in audit outcomes over the past five years are illustrated below.
2618 9 42 20
7
19 1515
196 3
18 9
14
12 714
1 1 1 1 1
EC FS GP KZN LP MP NC NW WC
Municipalities with at least 5 interns Municipalities with less than 5 interns
Municipalities with no interns
P a g e | 61
Figure 5: Audit outcome – five-year trend
Since 2010/11, the number of municipalities that submit their annual financial statements to the Auditor-General on time has improved. Auditor-General reports also indicate a steady improvement in positive audit outcomes. In 2013/14, 266 municipalities submitted their annual financial statements to the Auditor-General by 31 August 2014. (Since then, all 278 municipalities have submitted their 2013/14 annual financial statements for audit.)
Figure 6: Submission of annual financial statements to Auditor-General by 31 August
Municipal Finance Improvement Programme II
Highlights and achievements of MFIP II
The MFIP II was based on other successful capacity-building programmes implemented by the National Treasury over the last 15 years. The programme took into consideration the
013263952657891
104117130143156169182195208221234247260273
2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14
Disclaimer
Adverse
Qualified
Unqualified
Clean
Outstanding
238
247
263266
218
228
238
248
258
268
278
2010/11 2011/12 2012/13 2013/14
P a g e | 62
recommendations outlined in the independent evaluation reports of the Siyenza Manje Programme and the MFIP I, including balancing strategy and operations with fresh approaches to capacity building; changing design elements; applying strict entry criteria; undertaking initial diagnostics and more focused reporting; and placing greater emphasis on institutional issues.
Because an unqualified audit opinion is not an indicator of improved service delivery, it is not the sole focus of the MFIP II. The MFIP II’s objectives incorporate all aspects of the municipal accountability cycle, including strategic planning, budgeting, in-year implementation and compilation, annual financial statements, annual reports, asset management and supply chain management.
To improve programme governance, communication and stakeholder relations, a programme steering committee comprising representatives of the chief directorates within the National Treasury mandated and responsible for local government, representatives from the provincial treasuries and GTAC was established. The programme steering committee aims to give effect to the guiding principles informing the MFIP II support modalities by implementing a participatory and consultative engagement process; adapting to the sometimes volatile local government environment; improving efficiency and effectiveness through a dedicated centralised programme management unit; and improving accountability and ownership by establishing MFIP steering committees.
The programme is conservative, using a three-year programme as a basis for future trends (year one is used as a baseline with just two comparative years). The programme management unit will use emerging defined trends to test whether a positive correlation exists between the number of successfully completed outputs within the institution itself and (generally at an increasing rate in year two) in technical compliance. Although raw data from the MFIP I pointed towards a possible correlation, no clear conclusion could be made at that time. The MFIP II will examine this further to inform future support modalities.
Institutional and technical impact
The impact of the MFIP II’s institutional reforms is already evident in its first financial cycle. A detailed breakdown showing the extent of compliance with individual institutional outputs is available, including progress across individual municipalities.
The programme has supported 11 municipalities since January 2015. As at 31 March 2015, 180 out of 275 (65 per cent) activities were complete. Depending on the extent of support provided, municipalities are required to complete up to 25 activities, although this figure differs in the data provided as certain activity deadlines had not yet occurred.
The ongoing sustainable achievement of these institutional activities, which is seen as a precursor to becoming technically competent, should over time result in greater compliance with the Municipal Finance Management Act – enhancing municipal financial management by using financial resources efficiently and placing those resources against service delivery priorities more effectively.
Because advisors were only effectively placed in municipalities from 12 January 2015, only a small percentage of the overall technical outputs were completed by 31 March 2015. About 25 (or
P a g e | 63
4 per cent) of a total of 572 activities were completed. This will change during the first quarter of 2015/16 as the advisors’ focus will move from the institutional activities, which have specific target dates due to their conditions, to technical implementation.
The reforms must be fully institutionalised to ensure sustainability. It is therefore extremely important to maintain a strong focus on capacity building within the budget and treasury offices and internal audit units of municipalities – and continue to scrutinise these units, specifically in terms of all institutional reforms associated with the MFIP II support plan such as ensuring the appointment of senior finance officials, regular reviews of organograms, staff development and the adoption of finance delegations as required.
Training and development initiatives
Capacity-building programmes often initially achieve targets at a slower pace as work culture and job design must evolve. Sustainable change is only possible in the medium to longer term, providing for more robust and systemic change in which a stronger and more independent institution will emerge. Central to this tenet is the need to continue to up-skill, train and develop provincial and municipal officials to meet their legislative obligations.
The programme provided support in all Municipal Finance Management Act functional areas in municipalities being supported. In the programme’s first year, municipalities received a total of 229 separate training sessions from advisors located in municipalities, with a combined coverage of 128 officials and 12 councillors since the programme started. Although this does not guarantee the enhancement of officials’ skills, it does contribute to their ongoing development.
Improved diagnostics and methodologies
Specialist consultants support municipalities experiencing particular financial management challenges in areas such as asset management, revenue management, financial planning and budgeting, costing and tariff setting, financial systems and processes and supply chain. These interventions provide the National Treasury with opportunities to explore improvements in its own assessments of these issues.
Organisational needs will continue to be framed by requests that are substantiated by objective evidence found in audit reports, management letters, the Local Government Database; and the Financial Management Capability Maturity Model (FMCMM) and performance reviews undertaken by the provincial treasuries, among others.
Expanded monitoring and reporting
The MFIP II improved its monitoring and reporting systems, taking into account the lessons learned from the first phase, and through that has been able to provide information to support other financial management reform programmes. Expansive dashboard reports that can be used to determine baseline achievements for other support interventions are prepared, as well as reports correlating municipalities’ institutional and technical achievements.
P a g e | 64
The National Treasury uses weekly timesheets to calculate the time needed to implement and institutionalise some of the financial management reforms at the respective municipalities. Using these statistics, future support programmes can be efficiently and cost-effectively managed as the time to complete work can be set up front, thereby improving the National Treasury’s ability to negotiate rates payable.
These systems and information will be passed on to other stakeholders through this and other National Treasury reports.
Lessons learnt
The MFIP II is based on the MFIP I’s review, which was conducted in October 2013. This review attributed the failure of previous capacity-building initiatives to factors such as:
Uncertainty surrounding the roles and responsibilities of municipalities, as well as national, provincial and other stakeholders.
Assumption that a lack of capacity is the root cause of all municipal performance failures. Lack of prioritising municipal needs. Lack of performance monitoring. Absence of a mechanism to manage the transition of support.
Lessons learned during the MFIP II’s first year will be incorporated into future operations and other National Treasury capacity-building initiatives.
The Auditor-General’s management reports, among other sources, are used to assess municipalities seeking programme support, ensuring that support is given to critical areas not always clearly identified by the municipality or high-level audit reports. For example, the Auditor-General identified human resource management deficiencies that directly affect irregular and unauthorised expenditure, leading to qualified audit opinions.
The results of the FMCMM and 32 norms and ratios will also be used to inform future support requests, allowing advisors to prepare more focused support plans.
The MFIP II also maximises the involvement of stakeholders and key individuals in implementing reforms to minimise potential resistance to change and encourage organisations and individuals to champion change management strategies. The programme steering committee has been critical to the programme’s success, as decisions regarding support strategies are taken collectively, thereby strengthening the collaboration between the National Treasury and provincial treasuries.
Municipal progress is monitored and evaluated through quarterly site visits and weekly timesheets, both of which identify issues and potential problems much earlier, allowing more time for remedial actions to be taken.
Recruiting adequately skilled and experienced individuals to be placed as advisors at municipalities has been problematic. Of the 66 potential service providers identified from the MFIP II database and Technical Assistance Unit panel that were invited to submit proposals, 37 (56 per cent) responded,
P a g e | 65
all of which were formally interviewed. Of these, 20 (30 per cent) were offered consultancy agreements and 16 (24 per cent) accepted.
To address the shortage of skilled advisors, the programme steering committee approved a proposal requesting permission to recruit 10 technical assistants to be paired with current advisors for six to nine months to improve their advisory skills before placement at municipalities. The assistants must still be recruited.
The MFIP’s main aim is to build financial management capacity in municipalities. To ensure that the services delivered by the programme and advisors serving on the programme are continuously addressing the actual needs of the municipality and are able to adapt to changes, the core of the signed support plan remains constant for the support period while biannual reviews inform areas of weakness and gaps.
A clear support plan, a steering committee that meets on a regular basis, strong political leadership and senior finance officials to champion the reforms are needed to successfully strengthen the organisations being supported, leading to improvements in technical competence and ultimately compliance with the Municipal Finance Management Act.
URBAN DEVELOPMENT AND SUPPORT
The neighbourhood development partnership grant, which supports municipal planning and investment in targeted locations, aims to attract and sustain third-party capital investment and business development to improve the quality of life and access to opportunity in underserved townships or settlements.
Introduced in 2013/14, the integrated city development grant supports metropolitan municipalities to improve spatial targeting and sequencing of infrastructure investments, particularly identified integration zones. The grant is administered by the Cities Support Programme.
These two complementary programmes support local government to use resources efficiently to achieve its economic growth potential and create vibrant, sustainable places for citizens. The neighbourhood development partnership grant is administered by the Neighbourhood Development Programme and the Cities Support Programme is administered by the Local Government Infrastructure Unit – both of which are located within the National Treasury’s Intergovernmental Relations Division.
Neighbourhood Development Partnership Grant Programme
Established in 2006, the Neighbourhood Development Programme Unit is responsible for managing the neighbourhood development partnership grant. This grant aims to fund, support and facilitate the planning and development of neighbourhood development programmes and projects that provide catalytic infrastructure to attract third-party public- and private-sector investment to unlock the social and economic potential in targeted underserved neighbourhoods, improving residents’ quality of life and contributing to South Africa’s economic performance.
The National Development Plan’s human settlement chapter highlights the importance of transforming towns and cities spatially to improve access to economic opportunities as well as the
P a g e | 66
quality of life of citizens, especially residents in townships or those living on the periphery. The Neighbourhood Development Programme Unit’s strategic planning and investment framework, the urban network strategy, supports this transformation together with broader economic developmental outcomes.
Using the urban network strategy as a guide to changing the spatial form of South Africa’s larger urban centres, the Neighbourhood Development Programme aims to:
Support municipalities in city-wide strategic planning to ensure more integrated, equitable, efficient and effective cities focused on improving the lives of the urban poor.
Optimise public infrastructure investment, fiscal and regulatory development incentives and the coordinated urban management of targeted strategic nodes and urban hubs in townships.
Attract, coordinate and leverage private-sector investment into the targeted transit-oriented mixed-use precincts.
Provide the spatial-targeting component of the Cities Support Programme as reflected in the built environment performance plans (for metros). The programme is governed by conditions set out in the Division of Revenue Act.
P a g e | 67
Figure 7: Urban network topology
Based on the urban network methodology, 26 strategic township urban hubs (transit-oriented nodes) across South Africa’s eight metros and 10 secondary cities have been identified. Precinct design, urban hub development and project identification are under way. The neighbourhood development partnership grant also supports the sustainable development of each urban hub through targeted catalytic project funding for municipalities and a multi-stakeholder precinct management approach. The Neighbourhood Development Programme further supports municipalities through an Intersite/PRASA partnership, which provides municipalities with intermodal transit-oriented development procurement and planning expertise, and a capital project packaging facility (project preparation facility) available through the Development Bank of Southern Africa.
P a g e | 68
Highlights, achievements and challenges
The neighbourhood development partnership grant comprises a technical assistance component and a capital grant component. The technical assistance component, which is managed through the GTAC project development facility account, is intended for network, precinct and project planning; project packaging and urban management coordination. The 2014/15 project expenses budget was R30 million. Of this, R17.3 million was spent on 26 technical assistance projects. The capital grant component provides catalytic investment into targeted township precincts. R590.4 million has been transferred to municipalities for capital projects in 2014/15.
Figure 8: Waaihoek urban hub phasing plan
The neighbourhood development partnership grant is also responsible for knowledge sharing and capacity building. The Neighbourhood Development Programme has developed a precinct management guideline, which has been advertised to key stakeholders such as the South African Local Government Association, property developers, PRASA and local government.
Since its inception in 2006/07 the neighbourhood development partnership grant has registered 317 projects across more than 65 municipalities. In total, 241 township projects have been completed to the value of over R2.5 billion and 42 township projects in urban areas and five in rural areas are still under construction. Neighbourhood development partnership grant projects in rural municipalities are supported in collaboration with the Department of Rural Development and Land Reform’s 27 priority district and small town regeneration programmes to explore the feasibility of a similar grant for rural areas.
P a g e | 69
Figure 9: Waaihoek urban unification node
In 2014/15, all neighbourhood development partnership grant projects across 16 rural municipalities were completed. Preparations for the second handover stage are under way, with eight rural municipalities, including two new municipalities (Mbizana Local Municipality and Ingquza Hill Local Municipality), allocated technical assistance to support planning together with the Department of Rural Development and Land Reform.
Table 7: Neighbourhood Development Programme – strategic nodes and urban hubs
Municipality Township Hub name City of Johannesburg Soweto Jabulani Mall Area Diepsloot Diepsloot Ekurhuleni Tembisa Tembisa Station (Intersection 2nd October/Andrew
Mapheto Drive) Daveryton Daveryton/Etwatwa Vosloorus Katlehong/Thokoza/Vosloorus Kwa-Thema Kwa-Thema/Tsakane/Duduza City of Tshwane Mamelodi Denneboom Station Hammanskraal Hammanskraal Station Mabopane Mabopane/Soshanguve Station Atteridgeville Saulsville Station Ga-Rankuwa Ga-Rankuwa Hospital Mangaung Bloemfontein CBD Bloemfontein CBD Cape Town Philippi Philippi Nelson Mandela Ibhayi Ibhayi Cluster Emfuleni Evaton Sebokeng (Intersection of K53/Moshoeshoe and K178
(Boy Louw) Mbombela Tekwane South Tekwane South
P a g e | 70
Municipality Township Hub name Matlosana Jouberton N12 separating Jouberton and Alabama (New Tower
Mall) eThekwini Umlazi W Node Mpumalanga Mpumalanga Town Centre KwaMashu KwaMashu Town Centre and Bridge City Buffalo City Mdantsane Mdantsane Town Centre (Highway Node) Rustenburg Phokeng Rustenburg CBD Msunduzi Edendale Edendale, along Sinathiingi Road Emalahleni Kwa-Guqa/Hlalanikahle Witbank CBD Newcastle Madadeni Madadeni/JBC/Osizweni Polokwane Seshego Seshego Sol Plaatje Galeshewe Kimberley CBD/Indian Centre Mogale City Kagiso/Sinqobile Cluster Leratong Node
Table 8: Neighbourhood Development Programme – flagship projects
Municipality Township name
Hub name Projects Capital grant
Tshwane Ga-Rankuwa Ga-Rankuwa Hospital
Ga-Rankuwa walkways R26 633 125
Hammanskraal
Hammanskraal CBD Pedestrian bridge and traders’ stall over R101
R42 935 380
Saulsville Saulsville CBD Pedestrian bridge over the railway lines
R32 723 718
Cape Town Philippi Philippi East Mitchells Plain link road R31 926 432 Lentegeur PTI: Western forecourt
R17 459 171
Stock Road: Rehabilitation and NMT
R52 048 633
Mbombela Tekwane South Tekwane South (FH) Kanyamazane road link R69 979 066 Matlosana Jouberton N12 separating
Jouberton and Alabama
Jabulani/Buitekant Street R28 224 879
Pedestrian bridge R21 625 000 eThekwini Umlazi W Node KwaMnyandu activity bridge R31 891 255
Shezi Road public realm elements
R30 599 375
Msunduzi Edendale Edendale, along Sinathiingi Road
Thwala Road upgrade R20 892 712
Newcastle Madadeni Madadeni/JBC/Osizweni
Osizweni secondary node walkways
R32 527 227
JBC urban hub traffic lights and walkways
R20 096 104
Polokwane Seshego Seshego Seshego roads upgrade R28 097 350
Mogale City Kagiso/Sinqobile Cluster
Leratong Node Upgrading walkways along Kagiso Drive to Kagiso Mall
R35 829 507
Leratong pedestrian walkways
R10 650 589
Munsieville pedestrian walkways
R20 627 548
Upgrading intersection of Jacobs and Geba streets in Kagiso
R5 107 889
P a g e | 71
Cities Support Programme and integrated city development grant
Background and purpose of the Cities Support Programme
Reversing the exclusionary nature of the urban spatial economy is embedded in the Constitution. The National Development Plan recognises that the sprawling, low-density and segregated land-use patterns in South African cities are economically inefficient, highly inequitable and prevent higher rates of national economic growth.
South Africa’s largest cities need to be managed in a way that captures the benefits of their growing economic significance.
Although cities are growing, urbanisation has not resulted in higher economic growth, faster reductions in poverty levels or increased employment, as has occurred elsewhere in the world. For South Africa’s cities to become engines of growth, government needs to focus on making cities more productive, inclusive and sustainable.
The Cities Support Programme within the Intergovernmental Relations Division of the National Treasury was established in 2012. It is a demand-driven programme that supports metropolitan municipalities and the broader intergovernmental environment to achieve higher economic growth and reduce poverty levels. It works closely with the Intergovernmental Relations Division to foreground a cities-explicit agenda with a clear mandate to review the way cities are treated.
Implementation progress
Service providers have been hired to help implement the Cities Support Programme activities, focusing on support in the built environment, governance support, access to global technical experts (through the World Bank) and support to improve the infrastructure delivery management systems in cities.
In response to the changing way in which South African cities are being planned and built, in July 2014 the South African Cities Network and the Cities Support Programme jointly commissioned a study to develop a tool to inform spatial planning decisions in metros. The report and tool were completed in January 2015.
In 2014/15, the built environment performance plan review process was improved by aligning the reviews with the mid-year budget review process. Although the performance plans’ quality and content have improved, many cities did not supply sufficient information on catalytic urban development projects. To address this weakness, a supplementary note to the guidelines for the 2015/16 – 2017/18 built environment performance plan has been developed and issued to cities.
Following the success of a three-day workshop that was held in November 2014 to help municipal officials conceptualise and practically apply lessons learnt to their own catalytic projects, a series of expert panel reviews on identified catalytic projects in cities took place. To date the Urban Land Institute expert panels have reviewed existing project concepts for the Voortrekker Road Corridor (Cape Town), Sleeper site (Buffalo City Municipality) and Warwick Junction (eThekwini).
P a g e | 72
During 2014/15, the programme engaged with the World Bank to define its support on urban transport mobility and access, resulting in another World Bank mission, which occurred in February 2015. As part of the mission, technical support meetings were held with the City of Johannesburg, eThekwini, Nelson Mandela Bay and Ekurhuleni. The work programme focused on the review of the integrated public transport networks in the various cities, including the fare policy and technology support in Johannesburg and fiscal and funding issues in eThekwini.
In 2014/15, the programme started a number of public transport projects. It also continued to redesign the fiscal architecture in the urban transport sector, with a particular focus on the possibilities for formula/results-based financing approaches for both capital and operating grants, and to undertake city-specific capacity-building activities that link city-level identified priorities with capacity constraints identified by national government.
The programme’s economic development component, which got under way in 2014/15, provided technical support on specific aspects of city economic strategies, including to Johannesburg, Cape Town and Nelson Mandela Bay. Support for Mangaung’s investment promotion programme was planned for August 2015.
The subnational “cost of doing business” report was finalised and will be launched in June 2015. The report measures the cost of doing business in cities against one another, and benchmarks their performance at an international level as well. The Cities Support Programme will provide support to weak areas and another assessment will be conducted in 2017 to review whether or not improvements have been made.
In addition, considerable effort was put into designing an executive leadership programme in city economic development, which is planned for November 2015. The programme will make focused, specific requests for economic development support from city governments.
In 2014/15, the Cities Support Programme began to reform municipalities’ reporting indicators by developing a set of indicators to measure the success of investments in the built environment to makes cities well governed, productive, inclusive and sustainable, and by reducing the number of indicators against which municipalities need to report. The eight metropolitan municipalities were consulted during this process. A workshop was held with all the cities on 30 March 2015 to discuss the indicators and another session to further refine the indicators will be held in May 2015.
INFRASTRUCTURE DEVELOPMENT SUPPORT
The infrastructure skills development grant
The infrastructure skills development grant is managed by the Chief Directorate: Provincial and Local Government Infrastructure within the Intergovernmental Relations Division of the National Treasury. This grant is a direct conditional grant to municipalities and a schedule 5B grant in terms of the Division of Revenue Act. The infrastructure skills development grant aims to support municipalities to build long-term sustainable capacity by training young professionals in technical skills needed in built environment professions.
P a g e | 73
Unemployed graduates in possession of an appropriate tertiary qualification (a national diploma and/or a degree from an accredited university of technology or a university) are recruited for training and registration as professionals with the built environment statutory councils. Graduates are assigned to mentors, who ensure that graduates receive relevant training and complete the work required by the statutory councils. A total of 17 municipalities are participating in the programme.
Highlights and achievements
During 2013/14, the programme established a steering committee, comprising statutory councils and sector departments, which is responsible for providing strategic guidance and support, and advises on the training duration needed per skill category. In 2014/15 the programme:
Finalised the infrastructure skills development grant guidelines and policy documents. The municipalities are implementing the programme as per the guidelines and there is clear direction.
Recruited 424 graduates (2014/15 target: 350) for training in all 17 participating municipalities and the partnering water boards. A higher than expected number of graduates are registered as candidates with the relevant statutory councils.
Transferred the 2014/15 budget of R104.4 million to the 17 participating municipalities. Due to budget limitations, no new municipalities were allocated funding in 2014/15.
Compiled a database of all graduates and mentors.
Challenges and remedial measures
A number of graduates resigned from the programme due to attractive stipends from other organisations. To address this, the infrastructure skills development grant guidelines contain recommended salary scales for graduates. In addition, contracts now stipulate that graduates who resign before qualifying will be penalised.
Graduates are uncertain about employment in municipalities after completing the training programme, exacerbating graduate resignations in search of secure employment. To manage this, some municipalities have begun to approach district municipalities to establish possible placements for graduates after completing training.
Flagship projects
Workshops are held at the end of every quarter where municipalities present on their achievements, challenges and future actions, affording municipalities the opportunity to learn from one another, share lessons learnt and determine the best practice. In addition, the municipalities have formed a task team that is responsible for identifying challenges that may affect training, as well as developing solutions through case studies.
The geographic information system and property valuation graduates will be the first group to complete the training programme. The other skills categories will begin to exit the training
P a g e | 74
programme from December 2015, while engineering graduates will complete their training from 2016 onwards due to the Engineering Council of South Africa’s complex requirements.
Infrastructure Delivery Improvement Programme
The fourth phase of the Infrastructure Delivery Improvement Programme focuses on implementing and sustaining the work done in the programme’s previous phases. As part of the fourth phase, the National Treasury is providing technical assistance to the national departments of Health and Basic Education as well as the provincial treasuries to help them implement and sustain the infrastructure delivery management system (IDMS) beyond March 2018.
Over the next three years, the Infrastructure Delivery Improvement Programme IV will focus on achieving the following outputs:
Output 1: The IDMS is internalised and embedded in a sustainable intergovernmental institutional system.
Output 2: The IDMS processes and systems are implemented by participating national and provincial departments.
Output 3: Appropriate capacity within the participating national and provincial departments to implement and maintain the IDMS.
Output 4: IDMS evaluation, monitoring and reporting systems are implemented and functional.
To realise these outputs by March 2018, the Infrastructure Delivery Improvement Programme aims to:
Improve infrastructure monitoring and reporting systems. Enhance the infrastructure delivery management toolkit. Institutionalise the IDMS’s human resources capacity. Reform legislation and infrastructure grant frameworks to support the IDMS. Embed the construction procurement strategy in the IDMS. Increase the focus on and budget for maintaining infrastructure. Design and implement a comprehensive training programme for officials interacting with the
IDMS. Ensure that knowledge and lessons learnt are shared across national and provincial
departments. The programme will also identify good practices within provinces and share them accordingly.
Highlights and achievements
In 2014/15, the programme established a programme support office at the Development Bank of Southern Africa, as well as a panel of service providers that will be used to procure technical assistants that will be deployed to support provincial and national departments that are implementing the Infrastructure Delivery Improvement Programme. The programme’s planning phase was reviewed.
P a g e | 75
After consulting with national and provincial departments, 12 logical frameworks were developed. To date, a National Treasury logical framework has been approved by the Intergovernmental Relations Division and six Provincial Treasury logical frameworks have been approved by the respective department heads.
Eleven technical assistants have been appointed to help with the programme’s implementation. Six of them will form part of the National Treasury’s panel of experts and the remaining five have been assigned to various projects within the National Treasury.
The Office of the Chief Procurement Officer has developed procurement standards to guide procurement in the public sector. Employees responsible for human resources capacitation continue to assist national and provincial departments to build infrastructure units.
Challenges
There were delays in establishing a functional programme support office, procuring provincial technical assistants, and approving the infrastructure procurement standards developed by the Office of the Chief Procurement Officer.
Flagship projects
The programme helped the Directorate of Provincial Government Infrastructure to develop a web-based infrastructure reporting model.
Human resources oversight committees for each sector have been formed to assist the National Treasury, the national sector departments (Health, Basic Education, Public Works and Transport) and the provincial departments (Treasury, Health, Education, Public Works and Roads) to become sustainable by implementing the IDMS human resources capacitation framework.
The programme plans to enhance and refine the IDMS and infrastructure delivery management toolkit by incorporating the lessons learnt and developments that evolved during the programme’s third phase.
Facilitated through the University of Pretoria, the programme offers a two-day introductory training course on the IDMS. In 2014/15, 340 officials attended the two-day IDMS training session.
The programme is undertaking infrastructure procurement reforms by aligning infrastructure delivery-related legislation and developing procurement standards, instructions and guidelines within the context of the IDMS.
P a g e | 76
EMPLOYMENT FACILITATION
The Jobs Fund
Establishment of the Jobs Fund
The Jobs Fund, established in 2011, supports initiatives that create employment in an innovative manner. The fund offers once-off grants in the areas of enterprise development, infrastructure, support for work seekers and institutional capacity building.
Progress with implementation, highlights, achievements and challenges
Of the 90 projects that have been approved, 86 have been contracted and 81 are being implemented. The table below depicts the cumulative implementation progress to date.
Table 9: Jobs Fund Implementation Programme (progress to date)
Indicators Target Actual % target reached
Projects contracted as at 31 March 2015 90 86 96
Projects reporting as at 31 March 2015 90 81 90
Jobs Fund grant disbursed as at 31 March 2015 R2.868 billion R2.514 billion 88
Grantee contributions leveraged R2.924 billion R3.003 billion 103
Total value of implementing projects R5.792 billion R5.517 billion 95
Permanent jobs created 43 746 47 967 110
Short-term jobs created 17 648 13 648 77
Placements 27 693 21 100 76
Beneficiaries completing internships 9 883 10 443 106
Beneficiaries completing training 88 365 98 859 112
The Jobs Fund has made good progress against its targets, with all targets at 76 per cent and above. The Jobs Fund exceeded a number of targets, including the new permanent job creation indicator by 10 per cent, the time-bound internship indicator by 6 per cent, and the training indicator by 12 per cent.
A number of the Jobs Fund projects have finished, providing an opportunity to identify lessons learned to improve future projects.
This information will be used to evaluate the interventions’ impact on job creation and to assess the success of the different projects’ implementation models. These assessments will help to identify:
Overall portfolio impact. Which models have worked best and why. Which models can be efficiently scaled. Which projects can be replicated in other areas. The factors that affect the success of a project/type of project.
P a g e | 77
Ultimately, the results of these evaluations will produce sound best practice models and recommendations for job creation policy in South Africa.
Project implementation issues and delays
The following project implementation challenges have been noted:
Poor planning and underestimating the time needed to set up key project components results in delays in project implementation.
The seasonality of agricultural projects requires every project phase to be properly planned. A season lost in the agricultural sector negatively affects a project’s deliverables. Labour disputes in the metal and mining industries, for example, have a major impact on the implementation progress of some projects.
Projects underestimate the importance of securing partners. The limited institutional capacity of some Jobs Fund partners to implement their projects
effectively and provide the Jobs Fund with information on their progress has, in some cases, led to late disbursement, resulting in implementation delays and termination. Management team disruptions can also negatively impact on compliance and overall progress.
Unfavourable global economic conditions, such as exchange rate fluctuations, have delayed some projects.
Changing dynamics in the labour market have been a challenge. Projects in the work seekers funding window are struggling to find permanent positions for their beneficiaries. Due to slow economic growth, the labour market is depressed and a number of prospective employers are offering fixed-term contracts instead of permanent contracts to manage this risk. Projects in the agricultural sector have also reduced the anticipated number of jobs to be created, citing the change in employment policy as a key reason.
Projects that do not report (or report late) on their progress negatively affect the fund’s ability to meet its disbursement targets. The fund’s achievements are also underreported.
Financial management challenges
Various Jobs Fund projects encountered delays due to the following financial management challenges in 2014/15:
Lack of financial and management capacity within projects resulted in reporting delays and governance challenges.
Internal organisational procedural delays in cases where the project is housed within a large organisation or provincial government department.
An inability to secure matched funding by projects affected implementation plans and overall budget targets.
Delays in receiving the first advance disbursement due to contracting delays and other pre- implementation delays affected projects’ overall implementation schedule, especially in cases where the Jobs Fund’s disbursement represented a greater portion of the project budget.
P a g e | 78
Highlighted Jobs Fund projects
Harambee Youth Employment Accelerator
Experience is the determining factor in how likely a person is to gain formal employment, locking out millions of youth caught in the vicious cycle of not having experience and not being able to access it. The Harambee Youth Employment Accelerator helps young South Africans to get and keep their first job through a bridging programme that directly addresses the needs of employers.
Harambee recruits South African jobseekers between the ages of 18 and 28 from marginalised communities who have not had permanent employment for 12 months and have been searching for work for at least six months.
Selected candidates are placed in the bridging programme, where they gain the basic skills, behaviours, mindset and profile required to integrate into the workplace. Successfully bridged prospects are placed in full-time employment with project partners and receive continued support from Harambee during their induction and transition into the workplace.
“The Harambee Youth Employment Accelerator is one of the Jobs Fund’s flagship projects. The fund’s objectives are well aligned with the work that the programme is doing – that is to focus on the upliftment of youth and women,” explained Najwah Allie-Edries, Head of the Jobs Fund.
Harambee’s first project, which concluded in January 2015, managed to exceed both of its performance indicator targets. The project received a Jobs Fund grant of R120 million and matched funding of R120 million.
Table 10: Harambee Youth Employment Accelerator (progress to date) Year 1 Year 2 Year 3 Contract total Demographics
Target Actual Target Actual Target Actual Target Actual % <36
% female
% male
% PDI
Permanent positions with project partners
1 495 1 566 4 330 4 490 4 175 4 060 10 000 10 116 97 63 37 100
Beneficiaries trained 1 640 1 780 4 928 4 495 2 767 3 293 9 335 9 568 100 56 44 100
As a result of its past success, Harambee was accepted into the scale-up round, which began in January 2015. The project received a Jobs Fund grant of R132 million and matched funding of R353 million.
The project’s targets are:
18 000 short-term jobs. 42 700 beneficiaries trained. 22 000 permanent placements with project partners. 8 000 permanent placements beyond project partners.
P a g e | 79
Shanduka Black Umbrellas
Shanduka Black Umbrellas collaborates with partners in the private sector, government and civil society to address the low levels of entrepreneurship and high failure rate of 100 per cent black-owned emerging businesses in South Africa using an incubator model.
Over a three-year period, beneficiaries follow a structured programme that provides professional services including skills development, mentoring, access to markets and office infrastructure at a subsidised rate. These interventions help the entrepreneurs to build a solid foundation for establishing and maintaining sustainable businesses.
Shanduka Black Umbrellas received a R10.5 million grant from the Jobs Fund, which is matched with R8.2 million from the project itself. To date, the project has created 207 permanent positions, thus exceeding its projected figures. In addition, Shanduka Black Umbrellas ensures that at least 50 per cent of all businesses selected for the programme survive beyond the first three years of their existence (national average: 10 to 20 per cent).
The Jobs Fund is funding the Shanduka Black Umbrellas Durban and Pretoria incubator; however, only the Durban incubator’s results are included in this report. The project is still under way, yet the Durban incubator has already exceeded its contracted targets.
Table 11: Shanduka Black Umbrellas (progress to date)
Current quarter Inception to date Contract total Demographics
Target Actual Target Actual Actual Target % <36 % female
% male % PDI
Permanent positions with project partners
14 66 197 294 206 294 68 36 64 100
Cape Craft and Design Institute
The Cape Craft and Design Institute, a sector development agency in the Western Cape, supports the development and sustainability of the crafts sector in the province through:
Strengthening businesses by, for example, training on pricing, financial management and sales techniques.
Facilitating market access by, for example, match-making with buyers and publishing catalogues.
Product support, which involves testing different production processes with support from trainers and mentors.
The Cape Craft and Design Institute intends to use the Jobs Fund funding to provide financial support to relatively healthy small businesses to help them expand. For the Jobs Fund-funded project, the Cape Craft and Design Institute approached 28 companies already receiving support and analysed five to six areas where finance was needed to fund a specific intervention and the number of jobs expected to be created as a result of this support.
P a g e | 80
The beneficiary companies also pledged their own matched funding contribution towards the cost of support. The project’s budget comprises the Jobs Fund grant of R11.6 million and matched funding of R2.9 million.
The project is still under way, yet it has already exceeded its “inception to date” target by 24 per cent.
Table 12: Cape Craft and Design Institute (progress to date)
Table 13: Jobs Fund projects
Project Status
The Knead Bakery Training and Enterprise Initiative Approved
Department of Local Government: Community Works: Schools Support Programme Approved
Trust for Urban Housing Finance Jobs Fund Leveraging Approved
Lima Rural Development Foundation: Smallholder Farmer Support Programme Completed
Southern African Wildlife College: Training and Development of Unemployed Youth Completed
Harambee: Yellowwoods Ventures Investments Completed
Guarantee Trust Corporate Support Services: Work-readiness Programme for Unemployed Graduates Completed
Mercedes-Benz South Africa Completed
Medipost Pharmacy Completed
South African National Parks Completed
AngloGold Ashanti Contracted
ECDC (Trading Up) AsgiSA Rural Agro Initiative Implementing
AsgiSA EC: Eastern Cape Community Forestry Implementing
Shanduka Black Umbrellas Implementing
Awethu Entrepreneurship Foundation Implementing
Project Preparation Trust KZN: eThekwini Development of Emerging Enterprises Implementing
TechnoServe South Africa: Job Creation through Small Farmer Commercialisation Implementing
Premier’s Advancement of Youth: Economic Development in a Learning Province Implementing
RedCap Foundation: Jumpstart Jobs Fund Expansion Project Implementing
Fetola Foundation: Graduate Intern Programme Implementing
Child Welfare South Africa Implementing
Buhle Farmers Academy Implementing
USE-IT: Compressed Earth Blocks Implementing
KwaZulu-Natal Progressive Primary Health Care Implementing
Cape Craft and Design Institute Implementing
Current quarter Inception to date Contract total
Target Actual Target Actual Target Actual
New permanent jobs 50 85 307 381 451 381
P a g e | 81
Project Status
National Council for Persons with Physical Disabilities: Job Placement Agency Implementing
The Small Enterprise Foundation Implementing
Careers for Youth with Disabilities in South Africa Implementing
Hand in Hand: Job Creation through Enterprise Development Implementing
Lima: Manzengwenya-Mbazwana Forestry Development Programme Implementing
Resource Africa: Rural-based Enterprise Empowerment and Employment Implementing
Heifer: Blouberg Agricultural Development Project Implementing
Newlands Mashu: Edamame Soybean Industry Establishment Implementing
Ubuntu Institute for Young Social Entrepreneurs Implementing
Swellendam Tourism Rural Empowerment Partnership Implementing
Siyazisiza Craft Development Programme Implementing
Phakamani: Creating Micro Jobs for Rural Women Implementing
Clothing Bank National Expansion Implementing
Shanduka Black Umbrellas Pretoria Incubator Implementing
Sabi Sand: Rural SMMEs’ Development and Employment Creation Implementing
Africa Ignite: Tourist Markets Ignite Rural Enterprise Implementing
Timbali: 300 SMMEs in Commercial Agri-parks Implementing
Awethu Project Incubator Implementing
Anglo American Implementing
Mondi Zimele Implementing
Akwandze Agricultural Finance: Small-scale Sugarcane Irrigation Infrastructure Capitalisation Project Implementing
SAWC: Unlocking Community Benefits through Conservation Implementing
Curafin: Owner Driver Programme Implementing
Microsoft Student-to-Business Programme Implementing
Microsoft BizSpark Programme Implementing
Building a Learning Academy Implementing
Claremont Farming: AgriBEE Agro-processing Linkage Project Implementing
Hot Dog Café Cadet Programme Implementing
The Cape Flats Business Hub Implementing
South African Franchising Warehouse: Business Partners Implementing
A2Pay: Community Access to Wireless Retail Technologies Implementing
Eksteenskuil Raisin Incubator Implementing
Milk SA: Sustainable Commercialisation Smallholder Dairy Implementing
Programme for Industrial and Manufacturing Excellence Implementing
Diepsloot Industrial Development Zone Implementing
Just Veggies: VegFresh and Frozen Vegetable Supply Chain Implementing
Atlantic: Guarantee Mechanism to Crowd In Investors Implementing
Tongaat Hulett Sugarcane Development Initiative Implementing
P a g e | 82
Project Status
Vumela Enterprise Development Fund Implementing
Orange Grove UHT and Recapitalisation Programme Implementing
Department of Trade and Industry: Monyetla Work-readiness Programme Implementing
South African National Biodiversity Institute Implementing
Amatola Water Learning Academy Implementing
Bioprocess and Product Development Centre Implementing
CoachLab Leadership Skills Development Programme Implementing
Coega Strategic Skills Development Programme Implementing
Nissan Investment Support Programme Implementing
Development of Cashmere Fibre Industry Implementing
Sisonke: Post-settlement Support Land Reform Projects Implementing
Metal Surface Treatment Plant Implementing
Department of Economic Development and Tourism: WSP Implementing
Department of Economic Development and Tourism: TDM Implementing
Department of Economic Development and Tourism: CapaCITi 1000 Implementing
Royal Fields Implementing
Department of Environmental Affairs: Natural Resources Management Programme: Eco-factories Project Implementing
Harambee: Youth Employment Accelerator Implementing
Heifer International South Africa: Thusanang Dairy Project Terminated
WDB Trust: Non-private Sector Enterprise Development Terminated
Enablis Entrepreneurial Network South Africa Terminated
Triple Trust: Manufacture/Distribution of Efficient Cookstoves Terminated
TEBA Limited: Mineworker and Ancillary Job Facilitation from TEBA Labour Pools Terminated
College of Sustainable Agriculture: Karoo Incubator Terminated
Detailed descriptions of the Jobs Fund’s projects are available online (https://www.gtac.gov.za/programmes-and-services/the-jobs-fund).
P a g e | 83
ANNUAL REPORT 2014/15
PART C: FINANCIAL INFORMATION
P a g e | 84
REPORT OF THE AUDITOR-GENERAL TO PARLIAMENT ON THE GOVERNMENT TECHNICAL ADVISORY CENTRE REPORT ON THE FINANCIAL STATEMENTS
Introduction
1. I have audited the financial statements of the Government Technical Advisory Centre set out on pages 90 to 111, which comprise the statement of financial position as at 31 March 2015, the statement of financial performance, statement of changes in net assets, cash flow statement and statement of comparison of budget and actual amounts for the year then ended, as well as the notes, comprising a summary of significant accounting policies and other explanatory information.
Accounting officer’s responsibility for the financial statements
2. The accounting officer is responsible for the preparation and fair presentation of these financial statements in accordance with South African Standards of Generally Recognised Accounting Practice (SA Standards of GRAP) and the requirements of the Public Finance Management Act of South Africa, 1999 (Act No.1 of 1999) (PFMA), and for such internal control as the accounting officer determines is necessary to enable the preparation of financial statements that are free from material misstatement, whether due to fraud or error.
Auditor-General’s responsibility
3. My responsibility is to express an opinion on these financial statements based on my audit. I conducted my audit in accordance with International Standards on Auditing. Those standards require that I comply with ethical requirements, and plan and perform the audit to obtain reasonable assurance about whether the financial statements are free from material misstatement.
4. An audit involves performing procedures to obtain audit evidence about the amounts and disclosures in the financial statements. The procedures selected depend on the auditor’s judgement, including the assessment of the risks of material misstatement of the financial statements, whether due to fraud or error. In making those risk assessments, the auditor considers internal control relevant to the entity’s preparation and fair presentation of the financial statements in order to design audit procedures that are appropriate in the circumstances, but not for the purpose of expressing an opinion on the effectiveness of the entity’s internal control. An audit also includes evaluating the appropriateness of accounting policies used and the reasonableness of accounting estimates made by management, as well as evaluating the overall presentation of the financial statements.
5. I believe that the audit evidence I have obtained is sufficient and appropriate to provide a basis for my audit opinion.
P a g e | 85
Opinion
6. In my opinion, the financial statements present fairly, in all material respects, the financial position of the Government Technical Advisory Centre as at 31 March 2015 and its financial performance and cash flows for the year then ended, in accordance with the SA Standards of GRAP and the requirements of the PFMA.
Emphasis of matter
7. I draw attention to the matter below. My opinion is not modified in respect of this matter.
Financial reporting framework
8. As disclosed in note 1.1 to the financial statements, the government component was granted a departure in terms of section 79 of the PFMA. In this regard, the government component was allowed to depart from the requirements of the Treasury Regulations in respect of its preparation of the financial statements by preparing it in accordance with the SA Standards of GRAP as opposed to the Modified Cash Standard.
REPORT ON OTHER LEGAL AND REGULATORY REQUIREMENTS
9. In accordance with the Public Audit Act of South Africa, 2004 (Act No. 25 of 2004) and the general notice issued in terms thereof, I have a responsibility to report findings on the reported performance information against predetermined objectives for selected subprogrammes presented in the annual performance report, non-compliance with legislation and internal control. The objective of my tests was to identify reportable findings as described under each subheading but not to gather evidence to express assurance on these matters. Accordingly, I do not express an opinion or conclusion on these matters.
Predetermined objectives
10. I performed procedures to obtain evidence about the usefulness and reliability of the reported performance information for the following selected subprogrammes presented in the annual performance report of the government component for the year ended 31 March 2015:
Subprogramme 1: Technical Support and Development Finance Programme Management on pages 146 to 147.
Subprogramme 2: Government Technical Advisory Centre on pages 147 to 149.
Subprogramme 3: Local Government Financial Management Support on pages 149 to 150.
Subprogramme 4: Urban Development Support on pages 151 to 152.
Subprogramme 5: Employment Creation Facilitation on pages 152 to 154.
Subprogramme 6: Infrastructure Development Support on page 155.
P a g e | 86
11. I evaluated the reported performance information against the overall criteria of usefulness and reliability.
12. I evaluated the usefulness of the reported performance information to determine whether it was presented in accordance with the National Treasury’s annual reporting principles and whether the reported performance was consistent with the planned subprogrammes. I further performed tests to determine whether indicators and targets were well defined, verifiable, specific, measurable, time bound and relevant, as required by the National Treasury’s Framework for managing programme performance information (FMPPI).
13. I assessed the reliability of the reported performance information to determine whether it was valid, accurate and complete.
14. The material findings in respect of the selected subprogrammes are as follows:
Subprogramme 1: Technical Support and Development Finance Programme Management
Usefulness of reported performance information
15. Performance targets were not specific in clearly identifying the nature and required level of performance, and were not measurable, as required by the FMPPI.
16. Performance indicators were not clearly defined so that data can be collected consistently and is easy to understand and use. Performance indicators were also not verifiable.
17. The measurability of planned targets and indicators could not be assessed due to the indicator definitions not addressing the nature and required level of performance clearly.
Reliability of reported performance information
18. The FMPPI requires auditees to have appropriate systems to collect, collate, verify and store performance information to ensure valid, accurate and complete reporting of actual achievements against planned objectives, indicators and targets. Significantly important targets were not reliable when compared to the source information or evidence provided. This was due to the fact that proper indicator definitions were not used to predetermine the evidence and method of calculation for actual achievements.
Subprogramme 2: Government Technical Advisory Centre
Usefulness of reported performance information
19. Performance targets should be specific in clearly identifying the nature and required level of performance as required by the FMPPI. A total of 25% (>20%) of the targets were not specific.
20. This was because management did not adhere to the requirements of the FMPPI.
P a g e | 87
Reliability of reported performance information
21. The FMPPI requires auditees to have appropriate systems to collect, collate, verify and store performance information to ensure valid, accurate and complete reporting of actual achievements against planned objectives, indicators and targets. Significantly important targets were not reliable when compared to the source information or evidence provided. This is due to the fact that proper indicator definitions were not used to predetermine the evidence and method of calculation for actual achievements.
Subprogramme 3: Local Government Financial Management Support
Usefulness of reported performance information
22. Performance targets should be specific in clearly identifying the nature and required level of performance as required by the FMPPI. A total of 25 per cent (>20 per cent) of the targets were not specific.
23. This was because management did not adhere to the requirements of the FMPPI.
Reliability of reported performance information
24. The FMPPI requires auditees to have appropriate systems to collect, collate, verify and store performance information to ensure valid, accurate and complete reporting of actual achievements against planned objectives, indicators and targets. Significantly important targets were not reliable when compared to the source information or evidence provided. This is due to the fact that proper indicator definitions were not used to predetermine the evidence and method of calculation for actual achievements.
25. I did not identify any material findings on the usefulness and reliability of the reported performance information for the following programme:
Subprogramme 4: Urban Development Support
Subprogramme 5: Employment Creation Facilitation
Subprogramme 6: Infrastructure Development Support.
ADDITIONAL MATTERS
26. Although I identified no material findings on the usefulness and reliability of the reported performance information for the selected subprogrammes, I draw attention to the following matters:
P a g e | 88
ACHIEVEMENT OF PLANNED TARGETS
27. Refer to the annual performance report on pages 139 to 148 for information on the achievement of planned targets for the year.
ADJUSTMENT OF MATERIAL MISSTATEMENTS
28. I identified material misstatements in the annual performance report submitted for auditing on the reported performance information for subprogramme 1: Technical Support and Development Finance Programme Management; subprogramme 2: Government Technical Advisory Centre; subprogramme 3: Local Government Financial Management Support; subprogramme 4: Urban Development Support; subprogramme 5: Employment Creation Facilitation; and subprogramme 6: Infrastructure Development Support. As management subsequently corrected only some of the misstatements I identified material findings on the usefulness and reliability of the reported performance information.
UNAUDITED SUPPLEMENTARY INFORMATION
29. The supplementary information set out on page 145 (Gautrain Loan) does not form part of the annual performance report and is presented as additional information. I have not audited this information and, accordingly, I do not report thereon.
COMPLIANCE WITH LEGISLATION
30. I performed procedures to obtain evidence that the government component had complied with applicable legislation regarding financial matters, financial management and other related matters. My findings on material non-compliance with specific matters in key legislation, as set out in the general notice issued in terms of the PAA, are as follows:
STRATEGIC PLANNING AND PERFORMANCE MANAGEMENT
31. A strategic plan for 2014–2016 was not prepared by the Minister of Finance as required by Treasury Regulation 5.1.1.
32. The strategic plan and annual performance plan were not provided to Parliament to facilitate the annual discussion as required by Treasury Regulation 5.2.1.
ANNUAL FINANCIAL STATEMENTS, PERFORMANCE AND ANNUAL REPORTS
33. The financial statements submitted for auditing were not prepared in all material respects in accordance with the requirements of section 40(1) of the PFMA. The auditors identified material misstatements in the submitted financial statements in respect of various disclosure notes, which management subsequently corrected resulting in the financial statements receiving an unqualified audit opinion.
P a g e | 89
INTERNAL CONTROL
34. I considered internal control relevant to my audit of the financial statements, annual performance report and compliance with legislation. The matters reported below are limited to the significant internal control deficiencies that resulted in the findings on non-compliance with legislation included in this report.
LEADERSHIP
35. The oversight processes implemented by management in respect of financial and performance information were inadequate, resulting in non-compliance.
FINANCIAL AND PERFORMANCE MANAGEMENT
36. Management did not prepare performance information that could be assessed for usefulness and reliability.
Pretoria
31 July 2015
P a g e | 90
ANNUAL FINANCIAL STATEMENTS
P a g e | 91
Government Technical Advisory Centre (GTAC) Financial Statements for the year ended 31 March 2015 Index
The reports and statements set out below comprise the financial statements: Index Statement of Financial Position Statement of Financial Performance Statement of Changes in Net Assets Cash Flow Statement Statement of Comparison of Budget and Actual Amounts Accounting Policies Notes to the Financial Statements The financial statements set out on pages 3 to 22, which have been prepared on the going concern basis, were approved by the accounting authority on 29 May 2015 and were signed on its behalf by:
Andrew Donaldson Accounting Officer
P a g e | 92
Statement of Financial Position as at 31 March 2015
Notes 2015
Assets Non-Current Assets Property, plant and equipment 4 305 636
305 636 Current Assets Receivables from exchange transactions 5 13 567 135 Cash and cash equivalents 6 1 151 872 975
1 165 440 110
Total Assets 1 165 745 746
Liabilities Current Liabilities Trade and other payables under exchange transactions 7 120 463 584 Payables under non-exchange transactions 8 227 120 996 Provisions 9 1 292 334 Total Liabilities 348 876 914 Net Assets 816 868 832
Accumulated surplus 816 868 832 Net Assets 816 868 832
P a g e | 93
Statement of Financial Performance Notes 2015 Revenue Revenue from exchange transactions Cost Recovery Revenue 10 51 945 675 IPPPP RFP access fee Revenue 11 5 890 200 Investment revenue 12 37 948 817 Total revenue from exchange transactions 95 784 692 Revenue from non-exchange transactions Appropriated Funding 13 105 054 613 Donor Funding 14 34 443 889 IPPPP Project Development Fee Revenue 11 550 940 780 Total revenue from non-exchange transactions 690 439 282 Total revenue 786 223 974
Expenditure Goods and Services 15 530 440 584 Compensation of Employees 16 35 059 992 Depreciation/amortisation and impairment 4 24 968 Total expenditure 565 525 544
Surplus for the year 220 698 430
P a g e | 94
Statement of Changes in Net Assets Note Reserves
Balance at 1 April 2014 - Net Assets transferred on 1 April 2014 28 596 170 402 Net Surplus for the year ended 31 March 2015 220 698 430
Balance at 31 March 2015 816 868 832
P a g e | 95
Cash Flow Statement Note 2015 Cash flows from operating activities Receipts Government funding and other sources 1 056 657 331 Interest income 17 33 606 970
1 090 264 301 Payments Grants and project payments 603 788 266 Compensation to employees 33 767 658 637 555 924 Net cash flows from operating activities 18 452 708 377 Purchase of property, plant and equipment 4 (330 603) Net cash flows from investing activities (330 603)
Net increase in cash and cash equivalents 452 377 774 Cash and cash equivalents at the beginning of the year - Cash and cash equivalents - Transfer of functions 28 699 495 201 Cash and cash equivalents at the end of the year 6 1 151 872 975
P a g e | 96
Statement of Comparison of Budget and Actual Amounts
Approved budget Actual Variance
Over / (Under) Notes
Statement of Financial Performance
Revenue Revenue from exchange transactions Cost Recovery Revenue 35 582 257 51 945 675 16 363 418 23 IPP RFP access fee Revenue - 5 890 200 5 890 200 23 Investment revenue 1 920 000 37 948 817 36 028 817 23 Total revenue from exchange transactions 37 502 257 95 784 692 58 282 435
Revenue from non-exchange transactions Appropriated Funding 242 417 127 105 054 613 (137 362 514) 23 Donor Funding 65 219 218 34 443 889 (30 775 329) 23 IPP Project Development Fee Revenue 216 000 000 550 940 780 334 940 780 Total revenue from non-exchange transactions 523 636 345 690 439 282 166 802 937 Total revenue 561 138 602 786 223 974 225 085 372
Expenditure Goods and Services 506 295 106 530 440 584 24 145 478 23 Compensation of employees 52 472 170 35 059 992 (17 412 177) 23 Depreciation/amortisation and impairment 2 371 000 24 968 (2 346 032) 23 Total expenditure 561 138 276 565 525 544 4 387 268 Surplus for the year 326 220 698 430 220 698 104
P a g e | 97
Accounting Policies
1. Significant Accounting Policies 1.1 Presentation of Financial Statements GTAC is established as a Government Component in terms of the Public Services Act and as such is required to prepare the financial statements in accordance with Modified Cash Basis. GTAC has obtained a departure from the Accountant General from Modified Cash and hence the financial statements have been prepared in accordance with the Standards of Generally Recognised Accounting Practice (GRAP), issued by the Accounting Standards Board in accordance with Section 91(1) of the Public Finance Management Act (Act 1 of 1999). These financial statements have been prepared on an accrual basis of accounting and are in accordance with historical cost convention as the basis of measurement, unless specified otherwise. A summary of the accounting policies, which have been applied in the preparation of these financial statements are disclosed below. 1.2 Presentation Currency These financial statements are presented in South African Rand, which is GTAC's functional currency. Amounts are rounded to the nearest Rand. 1.3 Going Concern These financial statements have been prepared based on the expectation that GTAC will continue to operate as a going concern for at least the next 12 months. 1.4 Property, plant and equipment Property, plant, and equipment are carried at cost less accumulated depreciation and any impairment losses. Property, plant and equipment are depreciated on the straight line basis over their expected useful lives to their estimated residual value. The useful lives of items of property, plant and equipment have been assessed as follows: Item Average useful life Office equipment 5 years Computer equipment 3 years The residual value, the useful life and depreciation method of each asset are reviewed at least at each reporting date. If the expectations differ from previous estimates, the change is accounted for as a change in accounting estimate. Reviewing the useful life of an asset on an annual basis does not require the entity to amend the previous estimate unless expectations differ from the previous estimate. The gain or loss arising from the derecognition of an item of property, plant and equipment is included in surplus or deficit when the item is derecognised. The gain or loss arising from the derecognition of an item of property, plant and equipment is the difference between the net disposal proceeds, if any, and the carrying amount of the item. Where the carrying amount of an item of property, plant and equipment is greater than its estimated recoverable service amount, it is written down immediately to its recoverable amount (i.e. impairment losses are recognised).
P a g e | 98
1.5 Financial Instruments Initial recognition GTAC recognises a financial asset or a financial liability in its statement of financial position when it becomes a party to the contractual provisions of the instrument. Financial assets All financial assets are categorised as loans and receivables. The classification depends on the nature and purpose of the financial assets and is determined at the time of initial recognition. Cash and cash equivalents Cash and cash equivalents are stated at amortised cost, which, due to their short-term nature, closely approximate their fair value. Financial assets at amortised cost Trade receivables, loans, and other receivables that have fixed or determinable payments that are not quoted in an active market are classified as 'financial assets at amortised cost'. These financial assets are measured at amortised cost using the effective interest method less any impairment. Interest income is recognised by applying the effective interest rate. Effective interest method The effective interest method is a method of calculating the amortised cost of a financial asset and of allocating interest income over the relevant period. The effective interest rate is the rate that exactly discounts estimated future cash receipts through the expected life of the financial asset, or, where appropriate, a shorter period. Impairment of financial assets Financial assets are assessed for indicators of impairment at each year-end. Financial assets are impaired where there is objective evidence that, as a result of one or more events that occurred after the initial recognition of the financial asset, the estimated future cash flows of the investment have been impacted. For financial assets carried at amortised cost, the amount of the impairment is the difference between the asset's carrying amount and the present value of estimated future cash flows, discounted at the original effective interest rate. The carrying amount of the financial asset is reduced by the impairment loss directly for all financial assets with the exception of trade receivables where the carrying amount is reduced through the use of an allowance account. When a trade receivable is uncollectible, it is written off against the allowance account. Subsequent recoveries of amounts previously written off are credited against the allowance account. Changes in the carrying amount of the allowance account are recognised in the surplus or deficit. Financial liabilities All financial liabilities of GTAC are recognised at amortised cost. The classification of financial liabilities depends on their nature and purpose and is determined at the time of initial recognition. Other financial liabilities Other financial liabilities are initially measured at fair value, net of transaction costs. Other financial liabilities are subsequently measured at amortised cost using the effective interest method, with interest expense recognised on an effective yield basis. The effective interest method is a method of calculating the amortised cost of a financial liability and of allocating interest expense over the relevant period. The effective interest rate is the rate that exactly discounts estimated future cash payments through the expected life of the financial liability, or, where appropriate, a shorter period.
P a g e | 99
1.6 Tax No provision has been made for taxation, as GTAC is exempt from income tax in terms of Section 10 of the Income Tax Act, 1962 (Act 58 of 1962). 1.7 Employee benefits The cost of employee benefits is recognised during the period in which the employee renders the related service. Employee entitlements are recognised when they accrue to employees. A provision is made for the estimated liability as a result of services rendered by employees up to the reporting date. Termination benefits are recognised and expensed only when the payment is made. Liabilities for annual service bonus and long service bonus are recognised as they accrue to employees. The entity recognises these bonus obligation during the vesting period based on the best available estimate of these bonuses expected to vest. 1.8 Revenue from Exchange Transactions Revenue from exchange transactions is recognised when it is probable that future economic benefits or service potential will flow to the entity and these benefits can be measured reliably. Revenue is measured at the fair value of the consideration received or receivable. 1.8.1 Cost Recovery Revenue Revenue for services rendered is recognised as cost recovery revenue when it is associated with identified services provided to a client or counterparty, the costs incurred in providing these services can be reliably measured, the stage of completion of the services at the end of the reporting period can be determined and the costs and revenue can be appropriately apportioned between completed and to-be-completed services. 1.8.2 IPP RFP access fee Revenue Receipts received by the Independent Power Producer (IPP) programme from private parties are accounted for as exchange revenue when the receipts are measured reliably and identified economic benefits associated with the receipts flow to the private party. 1.8.3 Investment Revenue Investment Revenue is Interest income that accrues on a time-proportionated basis, taking into account the principal amount outstanding and the effective interest rate over the period to maturity. 1.9 Revenue from Non-Exchange Transactions
Non-exchange revenue transactions result in resources being received by GTAC, usually in accordance with a binding arrangement. When GTAC receives resources as a result of a non-exchange transaction, it recognises an asset and revenue in the period that the arrangement becomes binding and when it is probable that the entity will receive economic benefits or service potential and it can make a reliable measure of the resources transferred. Where the resources transferred to the entity are subject to the fulfilment of specific conditions, it recognises an asset and a corresponding liability. As and when the conditions are fulfilled, the liability is reduced and revenue is recognised. The asset and the corresponding revenue are measured on the basis of the fair value of the asset on initial recognition.
P a g e | 100
1.9.1 Appropriated Funding This is revenue received as a transfer through national budget allocation. It is utlised for the operations of the GTAC. GTAC is required to return the funds to National Treasury at the end of the financial year, but requests to retain the funds annually to support future commitments. The amount allocated is measured reliably and it is probable that the economic benefits associated with the funds will flow to the entity. It is recognised immediately on receipt. 1.9.2 Donor Funding Donor funds are recognised when the funds can be measured reliably on the date the draw-down requisition becomes effective and the cost associated with the revenue has been incurred. The funds transferred are subject to the fulfilment of specific conditions, an asset and a corresponding liability is recognised. As and when the conditions are fulfilled, the liability is reduced and revenue is recognised. 1.9.3 IPP Project Development Fee Revenue IPP Project Development Fees is calculated as 1% of the project value for the bidder to go to the next phase. This amount is is non-refundable, there are no conditions attached and therefore recognised on receipt. 1.10 Comparative Figures There are no comparatives for the financial year as GTAC became operational on 1 April 2014. 1.11 Fruitless and Wasteful Expenditure
Fruitless expenditure means expenditure which was made in vain and would have been avoided had reasonable care been exercised. All expenditure relating to fruitless and wasteful expenditure is recognised as an expense in the statement of financial performance in the year that the expenditure was incurred. The expenditure is classified in accordance with the nature of the expense, and where recovered, it is subsequently accounted for as revenue in the statement of financial performance. 1.12 Irregular Expenditure Irregular expenditure as defined in section 1 of the PFMA is expenditure other than unauthorised expenditure, incurred in contravention of or that is not in accordance with a requirement of any applicable legislation, including - (a) this Act; or (b) the State Tender Board Act, 1968 (Act No. 86 of 1968), or any regulations made in terms of the Act; or (c) any legislation providing for procurement procedures. 1.13 Related Parties
The entity is related to other entities and departments in all spheres of government. The transactions are consistent with normal operating relationships between the entities, and are undertaken on terms and conditions that are normal for such transactions.
P a g e | 101
1.14 Significant Judgments, Estimates and Assumptions
The preparation of annual financial statements requires management to make judgments, estimates and assumptions that affect the application of policies and the reported amounts of assets and liabilities, revenue and expenses. Estimates are made based on the best available information at the time of preparation of the Annual Financial Statements. The estimates and underlying assumptions are reviewed on an on-going basis. Revisions to accounting estimates are recognised in the period in which the estimate is revised if the revision affects only that period or in the period of the revision on future periods if the revision affects current and future periods.
1.15 Public Sector Practices and Policies Inter-relationship with other government entities
GTAC has been establised as a government component, with National Treasury as its Principal.
Public Finance Management Act reporting requirements
Section 55(2)(b) No material losses occurred during the current financial year due to criminal conduct nor any unauthorised expenditure or irregular expenditure.
1.16 Events after Reporting Date
Events after the reporting date are those events, both favourable and unfavourable, that occur between the reporting date and the date when the financial statements are authorised for issue. Two types of events can be identified: (a) Those that provide evidence of conditions that existed at the reporting date (adjusting events after the reporting date); and (b) Those that are indicative of conditions that arose after the reporting date (non-adjusting events after the reporting date)
1.17 Budgets
A comparison of the budget estimates for GTAC's programmes and activities and the realised outcome (actual) amounts is included in the financial statements.
The comparison of budget and actual amounts shows: (a) Approved and final budget amounts; (b) Actual amounts on a comparable basis; and (c) By way of note disclosure, an explanation of material differences between budget estimates and actual amounts.
1.18 Transfers under Common Control
Several functions were transferred to GTAC on the 1 April 2014 by National Treasury, which is GTAC's principal department. With effect on this date the National Treasury: (a) Derecognised in its financial statements, all the assets transferred and liabilities relinquished at their carrying amounts. (b) Recognised the difference between the carrying amounts of the assets transferred and the liabilities relinquished in its accumulated surplus or deficit.
P a g e | 102
1.19 Contingent Liabilities and Provisions
A contingent liability is: (a) A possible obligation arising from past events, to be confirmed by the occurrence or non-occurrence of one or more uncertain future events not wholly within the control of the entity; or (b) A present obligation that arises from past events but is not recognised because: i. It is not probable that an outflow of resources embodying economic benefits or service potential will be required to settle the obligation; or ii. The amount of the obligation can not be measured with sufficient reliability.
Contingent liabilities are not recognised in the financial statements, but are disclosed in the notes.
Provisions are recognised when: (a) GTAC has a present obligation as a result of past events (b) it is probable that an outflow of economic benefits will be required to settle the obligation © a reliable estimate can be made of the obligation.
1.20 Commitments
A commitment is a future expense for which GTAC is contractually liable, but in respect of which a payment obligation has not yet been incurred at the reporting date.
Commitments are not recognised in the financial statements, but are disclosed in the notes.
1.21 Segment Reporting
GTAC's financial statements are set out in segments: - (1) in view of the separate nature and financial effects of its main activities and their associated economic environments (2) in order to disclose the separate resource allocations and associated governance arrangements for these activities; and (3) to support transparency of financial reporting and discharge of GTAC's accountability obligations.
A segment is an activity of an entity: (a) that generates economic benefits or service potential (including economic benefits or service potential relating to transactions between activities of the same entity); (b) whose results are regularly reviewed by management to make decisions about resources to be allocated to that activity and in assessing its performance; and (c) for which separate financial information is available. (c) for which separate financial information is available.
P a g e | 103
Notes to the Financial Statements 2015
2. General Information The Government Technical Advisory Centre (GTAC) has been established as a government component in terms of the Public Services Act ,by Proclamation promulgated by the President of South Africa.
The object of the GTAC is to assist Organs of State in building their capacity for efficient, effective and transparent financial
management. The functions of GTAC are: (a) to render technical consulting services to Centre of Government Departments and Organs of State;
(b) to provide specialised procurement support for high-impact government initiatives; (c) to render advice on the feasibility of infrastructure projects; (d) to provide knowledge management for projects undertaken; and (e) anything ancillary to the functions 3. New Standards and Interpretations 3.1 Standards Issued, but not yet effective At the date of authorisation of these financial statements, there are standards and interpretations in issue but not yet effective.
These include the following standards and interpretations that are applicable to the entity and may have an impact on future
financial statements: Standard/ Interpretation:
Effective date: Expected impact: Years beginning on or after
• GRAP 105: Transfers of functions between entities under common control
Not yet effective This standard establishes the accounting principles for the acquirer and transferor in a transfer of functions between entities under common control.
A transfer of functions is the reorganisation and/or the re-allocation of functions between entities by transferring functions between entities or into another entity.
Entities have transferred from their original being to GTAC. It is expected that this standard will impact the disclosures of these
financial statements.
• GRAP 20: Related Not yet effective This standard prescribes the disclosure of information relevant to draw attention to the possibility that the entity's financial position and surplus / deficit may have been affected by the existence of related parties. It is not expected that this standard will significantly impact future disclosures.
parties
P a g e | 104
• GRAP 18: Segment Reporting
Not yet effective This standard enable users of the financial statements to better understand the GTAC’s past performance, to evaluate the nature and financial effects of the activities in which it engages and the economic environments in which it operates
It is not expected that this standard will significantly impact
future disclosures.
3.2 Standards not yet effective or relevant The following standards and interpretations that have been issued but are not yet effective are not applicable to the entity and will not have an impact on future financial statements: Standard/ Interpretation: Effective
date: Expected impact:
Years beginning on or after
No significant impact on future disclosures
• GRAP 32: Service Concession Arrangements: Grantor Not yet effective
No significant impact on future disclosures
• GRAP 106: Transfers of functions between entities not Not yet
effective No significant impact
on future disclosures under common control • GRAP 107: Mergers Not yet
effective No significant impact
on future disclosures • GRAP 108: Statutory Receivables Not yet
effective No significant impact
on future disclosures
P a g e | 105
4. Property, plant and equipment
2015 Cost Accumulated Carrying
value depreciation
Office furniture and fittings
- - -
Office equipment 51 091 6 206 44 886 Computer equipment
279 512 18 762 260 750
Leasehold improvements
- - -
Total 330 603 24 968 305 636
Reconciliation of property, plant and equipment - 2015
Opening
balance Additions Disposals Depreciation Total
Office furniture and fittings - - - - - Office equipment - 51 091 - 6 206 44 886 Computer equipment - 279 512 - 18 762 260 750 Leasehold improvements - - - - - - 330 603 - 24 968 305 636 5. Receivables from Exchange Transactions
Trade Receivables 5 719 507 VAT receivable 1 285 455 Interest receivable 6 562 173 13 567 135
P a g e | 106
6. Cash and Cash Equivalents Cash and cash equivalents consist of:
Bank Accounts: - Government Technical Advisory Centre (GTAC)
206 998
- Building a Capable State (BCS)
1 433
- Project Development Facility (PDF) 1 433 - Neighbourhood Development Programme (NDP) 1 500 - Independent Power Producers Procurement Programme (IPPPP) 1 433 212 797 Call Accounts: - GTAC 221 744 289
- BCS 11 281 745 - PDF 136 260 176 - NDP 69 707 395
- IPPPP 712 666 573 1 151 660 178 Total Cash and cash equivalents 1 151 872 975 Cash and cash equivalents comprise cash held by GTAC and short-term bank deposits on call. The carrying amount of these assets approximates their fair values.
During 2014/15 funds were invested in call accounts with Nedbank to maximise the interest earned.
P a g e | 107
7. Trade and other Payables under Exchange Transactions
Trade payables 35 906 586 Income received in advance - Cost Recovery GTAC
-GTAC 7 556 998
-PDF 77 000 000 120 463 584 The carrying amount of trade and other payables approximate their fair value due to the relatively short-term maturity of these financial liabilities.
8. Payables under Non-Exchange Transactions Income received in advance - GTAC 81 159 447 - Municipal Financial Improvement Programme
II (MFIP) 87 831 432
- NDP 58 014 113 Interest received on Donor funds 116 004 227 120 996 9.Provisions Provisions for Leave 701 089 Provisions for Bonuses 591 245 1 292 334 Reconciliation of employee provisions - 2015 Opening
balance Provided Utilised Total
Leave provision - 701 089 701 089 Bonus provision - 591 245 591 245 - 1 292 334 - 1 292 334 10. Cost Recovery Revenue Technical assistance Various 46 159 341 Infrastructure Delivery Improvement Programme (IDIP) 5 786 334 51 945 675 11. Independent Power Producers (IPP) Revenue IPPPP RFP access fee Revenue Large Renewable Energy RFP (Request for Proposals) 405 500 Small Renewable Energy 85 000 Coal 5 399 700 5 890 200
P a g e | 108
IPPPP Project Development Fee Revenue
Large Renewable Energy projects 476 705 555 Peaking Power Plants 74 235 225 550 940 780 Total IPPPP Revenue 556 830 980 12. Investment Revenue Interest 37 948 817 37 948 817
P a g e | 109
13 Appropriated Funding (National Treasury vote) Government Technical Advisory Centre (GTAC) 79 752 000 Project allocations: Municipal Finance Improvement Programme II (MFIP) 10 956 569 Neighbourhood Development Programme
(NDP) 14 346 044
105 054 613 14. Donor Funding General Budget Support (GBS) 19 642 539 - funding from the European Union through National Treasury for institutional transformation "Building a Capable State" (BCS) 14 801 350 - funding from the Canadian department of Foreign Affairs ,Trade and development 34 443 889 15. Goods and Services Accounting fees 184 634 Administrative fees 94 474 Advertising 169 062 Assets less than capitalisation threshold and maintenance
37 483
Audit fees 713 176 Bank Charges 20 723 Bursaries 98 541 Catering 72 721 Communications 126 216 Computer services 1 820 Consumables and maintenance 260 570 Entertainment 6 999 Licence Fees 18 785 Losses and Damages 48 114 Operating payments 21 098 Project expenditure - BCS 14 801 350 Project expenditure - GTAC 78 086 377 Project expenditure - IDIP 5 786 334 Project expenditure - MFIP(ii) 10 956 569 Project expenditure - NDP 14 346 045 Project expenditure - NDP internal 456 164 Project expenditure - PDF 3 877 531 Subscriptions 245 910 Training 141 497 Travel and subsistence 1 528 226 Venues and facilities 37 174 132 137 593 Project expenditure - IPP 398 302 991 530 440 584
P a g e | 110
16. Compensation of Employees Salaries and Wages 19 677 728 UIF, Pensions and Medical Aid 2 729 048 Performance and other bonuses 2 935 865 Other employee related costs 830 347 Non pensionable and housing allowances 8 887 004 35 059 992
17. Investment Income
Interest income at the beginning of the year
2 220 326
Net investment income received per the Statement of Financial Performance
37 948 817
Accrued net interest income at the end of the year (6 562 173)
33 606 970
18. Net cash flows from operating activities Surplus for the year 220 698
430 Adjustments for: Depreciation 24 968 Increase in Salary provisions 1 292 334 Increase in accruals
24 932 222
Increase in Income received in advance
311 561 990
-under Exchange transactions 84 556 998
-under Non-Exchange transactions 227 004 992
Changes in working capital (Increase) in receivables from exchange transactions
(13 567 135)
Increase in payables under exchange transactions
10 974 363
Increase in payables under non-exchange transactions
116 004
Transfer of functions - Net assets and liabilities (103 324 799)
452 708 377
19. Commitments Project Commitments
Accumulated surplus
816 868 832
P a g e | 111
Current commitments will be funded from the accumulated surplus as well as from future government grants, cost recovery and donor funds.
Operating Commitments
Payable within the next 12 months - Contractual commitments 127 625 209
Payable after 12 months but before 60 months - Contractual commitments 33 889 797
Payable after 60 months -
20. Related Parties During the financial year, GTAC entered into various transactions with related parties. Relationship National Treasury is the Principal entity to GTAC.
Related party balances Receivables Department of Public Works 4 152 592 Department of Communications 649 520 Department of Science and Technology 277 288 National Treasury 640 107
5 719 507
P a g e | 112
Payables Development Bank of South Africa 25 538 757 National Treasury 145 762
25 684 519 Other payables
National Treasury -GTAC 7 556 998
-Employment Creation Facilitation Programme
50 098 983
-Municipal Finance Improvement Programme II
87 831 432
-Neighbourhood Development Programme 58 014 113 Department of Public Works 77 000 000
280 501 526
These funds have been committed against projects
Related party transactions Funding provided by relating parties National Treasury -GTAC 79 752 000 -Employment Creation Facilitation
Programme 28 300 000
-Municipal Finance Improvement Programme II
98 788 000
-Neighbourhood Development Programme 30 000 000 Department of Public Works 77 000 000 313 840
000 Revenue received for services provided
Department of Communications 7 471 711 Department of Co-operative Governance & Traditional Affairs
44 770
Department of Home Affairs 3 949 672 Department of Human settlements 60 000 Department International Relations and Co-operation (DIRCO) 662 607 Department of Provincial Planning and Treasury EC 857 892 Department of Public Service Administration
1 171 056
Department of Public Works 4 152 592 Department of Science and Technology 277 288 Ditsong Museums SA 204 457 Eastern Cape Department of Sport , Recreation, Art and culture 1 317 237 Manufacturing and engineering related Services Sector Education and Training Authority (MERSETA) 139 576 National Treasury 20 747 156 Office of the Health Standards compliance 2 795 327 Office of the Premier - Eastern Cape 433 090 Office of the Premier - Kwazulu Natal 113 686 Public Service Education and Training Authority (PSETA) 256 873 Quality Council for Trade and Occupation 20 870
P a g e | 113
Safety and Security Sector Education and Training Authority (SASSETA) 554 187 South African National Bio diversity institution 2 184 177 The Presidency 4 531 451
51 945 675
Expenses paid Development Bank of South Africa 398 909 526 398 909 526 Services rendered at no cost Financial Intelligence Centre 1 683 705 1 683 705 Services received at no cost Financial Intelligence Centre 90 728 National Treasury 2 109 360 2 200 088 These costs at fair value relates to office space occupied by GTAC. Key Management personnel No of Individuals Political office bearers 0 - Officials: Levels 15 to 16 0 - Levels 14 8 9 419 352 9 419 352
P a g e | 114
21. Risk Management The focus of risk management in GTAC is on identifying, assessing, managing and monitoring all known forms of risk across the entity. While operating risk cannot be fully eliminated, management endeavours to minimise it by ensuring that the appropriate infrastructure, controls, systems and ethics are applied throughout the entity and managed within predetermined procedures and constraints. As GTAC acquires finance from the National Treasury Finance Department and does not have borrowed funds, it does not have major exposure to credit, liquidity, interest and market risk. Credit risk Credit risk is the risk that one party to a financial instrument will cause a financial loss for the other party by failing to meet an obligation. Credit risk arises from cash and cash equivalents, and deposits with banks and financial institutions, as well as outstanding receivables and committed transactions. For banks and financial institutions, only highly reputable financial institutions are used. Liquidity risk Liquidity risk is the risk that the entity will not be able to meet its financial obligations as they fall due. Ultimate responsibility for liquidity risk management rests with the National Treasury finance department, which has built an appropriate liquidity risk management framework for the management of the National Treasury's short, medium and long term funding and liquidity management requirements.
Interest rate risk GTAC has limited exposure to interest rate risk. GTAC's cash and cash equivalents are subject to interest rate risk for the portion of interest received. The interest rate risk is limited as funds are invested with one of the four major banks and this is assessed annually.
Market risk No significant market events occurred during the year that materially affected GTAC. GTAC's activities of mainly of an administrative or support service nature, with limited exposure to market movements.
P a g e | 115
22. Events after the Reporting Date No material events after the reporting date. 23. Budget Differences Notes to Statement of Comparison of Budget and Actual amounts
Cost Recovery Revenue Over budget The number of consulting projects were under budgeted for as the consulting services is a demand driven industry. IPP RFP access fee Revenue Over budget The RFP fees were not budgeted for in this financial year. Investment revenue Over budget Higher inflows of revenue due to the receipt of IPP development fees being higher than budget. Appropriated Funding Under budget Administrative expenditure on the Jobs Fund Project Management Unit was initially mainly accounted for by National Treasury as a transfer to the DBSA. The Unit was transferred to GTAC during 2014/15 together with the associated expenditure. Donor Funding Under budget During the financial year, there were less projects funded from donor funds than budgeted for. IPP Project Development Fee Revenue Over budget Whereas the bid window for peaking power plants closed in prior period, the development fee revenue flowed in the current period. Goods and Services Over budget Increased transactional advisory expenditure for evaluations of proposals in the IPP as well as office overheads under budgeted in IPP. This overspend was funded by internal funds generated by the IPPP programme through project development funds received from successful bidders and was not an overspend on Voted funds. This is not a contravention of section 39(2)(a) of the PFMA. Compensation of employees Under budget Staff structure yet to be finalised before any new positions are created and recruited for. Depreciation/amortisation and impairment Under budget There has been less procurement of equipment assets than budgeted for during this financial year.
P a g e | 116
24. Financial Instruments Categories of financial instruments 2015 Financial assets
At amortised Total cost
Receivables from exchange transactions 13 567 135 13 567 135 Cash and cash equivalents 1 151 872 975 1 151 872 975 1 165 440 110 1 165 440 110 Financial liabilities At amortised Total
cost Payables from exchange transactions 120 463 584 120 463 584 Trade and other payables from non-exchange transactions 227 120 996 227 120 996 347 584 580 347 584 580
25. Contingencies Accumulated surplus 816 868 832
In terms of the PFMA, all surplus funds as at the reporting date may be forfeited to the National Treasury. A request for the retention
26. Fruitless and Wasteful Expenditure
To the best of our knowledge no fruitless and wasteful expenditure have been incurred during the current year. 27. Irregular Expenditure To the best of our knowledge no irregular expenditure was incurred in the current year.
P a g e | 117
28. Transfer of Functions between Entities under Common Control The following units functions were transferred to GTAC: 1. Technical Assistance Unit (TAU) 2. Private and Public Partnerships Unit (PDF) 3. National Capital Projects Unit 4. Jobs fund 5. Expenditure Performance Review The net assets transferred to GTAC was R596 170 403. TAU PDF Total Assets Current Assets Receivables from Exchange transactions 2 236 425 1 777 037 4 013 462 Receivables from Non-Exchange transactions 630 551 - 630 551 Cash and Cash Equivalents 80 398 229 619 096 972 699 495 201 83 265 205 620 874 009 704 139 214 Liabilities Current liabilities Payables under exchange transactions 29 441 941 3 569 110 33 011 051 Unspend government fund - 42 360 159 42 360 159 Other payables under non-exchange 32 597 602 - 32 597 602 62 039 543 45 929 269 107 968 812 Net assets 21 225 662 574 944 740 596 170 402
No consideration was paid by GTAC to National Treasury for these transfers of assets and relinquishment of liabilities.
P a g e | 118
29. Segment Reporting GTAC's accounts are reported in two segments, in view of the separate management, resource allocation, and accountability arrangements for these two sets of activities. The first comprises GTAC's advisory and programme management activities, including the organisational units and functions transferred from the National Treasury. The second segment comprises the accounts of the Independent Power Producers Procurement Programme, which are administered by GTAC on behalf of the Department of Energy, National Treasury, and the IPPPP Office which is based at the Development Bank of Southern Africa. The IPPP Programme's revenue derives from fees raised through IPPP transactions, which are ring-fenced for meeting the administrative costs of the procurement programme and future contract management. The IPPPP revenue, expenditure, and accumulated funds are therefore reported and accounted for separately from GTAC's advisory and programme management services.
2015
GTAC Advisory and Programme
Management Services
Independent Power Producers
Procurement Programme
Total
Revenue Revenue from exchange transactions 51 945 675 5 890 200 57 835 875 Revenue from non-exchange transactions 139 498 502 550 940 780 690 439 282 Total segment revenue 191 444 177 556 830 980 748 275 157 Expenditure Goods and Services 132 137 593 398 302 991 530 440 584 Compensation of Employees 35 059 992 - 35 059 992 Depreciation/amortisation and impairment 24 968 - 24 968 Total segment expenditure 167 222 553 398 302 992 565 525 544 Total segmental surplus before interest 24 221 624 158 527 988 182 749 613 Interest revenue 12 868 080 25 080 737 37 948 817 Surplus for the period 37 089 704 183 608 725 220 698 430 Assets Segment Assets 448 408 014 717 032 096 1 165 440 110 Total Assets 448 408 014 717 032 096 1 165 440 110 Liabilities Segment Liabilities 322 652 358 24 932 222 347 584 580 Total Liabilities 322 652 358 24 932 222 347 584 580 Other Information Capital Expenditure* 305 636 Non cash items excluding depreciation - Accrued expenses - Deferred revenue - * Excluding additions to financial instruments and post-employment benefit assets
P a g e | 119
ANNUAL REPORT 2014/15
PART D: HUMAN RESOURCES MANAGEMENT
P a g e | 120
HUMAN RESOURCES OVERSIGHT: STATISTICAL INFORMATION EXPENDITURE
In 2014/15, GTAC’s activities were organised into five subprogrammes. The following tables summarise expenditure on personnel by programme (Table 14) and by salary band (Table 15), and also show expenditure on training and professional and special services.
Table 14: Personnel costs by programme, 2014/15
Percentage of average personnel cost per employee calculated based on the number of employees in Table 18, which excludes Jobs Fund employees (14).
Table 15: Personnel costs by salary band, 2014/15
Percentage of average personnel cost per employee calculated based on the number of employees in Table 25.
Programme
Total expenditure
Personnel expenditure
Training expenditure
Professional and special
services
Average personnel cost per employee
(R 000) (R 000) % of total (R 000) (R 000) (R)
Programme 8 Technical Support and Development Finance
41 778 33 707 0 0
80.6
674
Total 41 778 33 707 0 0
Salary band Personnel expenditure (R 000)
% of total personnel cost
Average personnel cost per employee
(R 000)
Lower skilled (levels 1–2) - - -
Skilled (levels 3–5) 209 0.6 209
Highly skilled production (levels 6–8) 3 228 9.6 269
Highly skilled supervision (levels 9–12) 12 223 36.3 582
Senior management (levels 13–16) 18 047 53.5 1128
Total 33 707 100.0 674
P a g e | 121
The following tables provide a summary, per programme (Table 16) and salary band (Table 17), of expenditure incurred on salaries, overtime, home owners’ allowance and medical assistance. The tables also indicate the percentage breakdown of personnel expenditure.
Table 16: Salaries, overtime, home owners’ allowance and medical assistance by programme, 2014/15
Percentage of personnel cost of salaries, overtime, home owners’ allowance and medical assistance is calculated using the total personnel expenditure per programme in Table 18.
Table 17: Salaries, overtime, home owners’ allowance and medical assistance by salary band, 2014/15
Percentage of personnel cost of salaries, overtime, home owners’ allowance and medical assistance is calculated using the total personnel expenditure per programme in Table 18.
Programme Salaries Overtime Home owners’ allowance
Medical assistance
(R 000) % of total (R 000) % of
total (R 000) % of total (R 000) % of
total
Programme 8 19 678 58.38 0.00 0.00 164 0.49 391 1.16
Total 19 678 58.4 0 0.0 164 0.5 391 1.2
Salary band Salaries Overtime Home owners’ allowance Medical assistance
(R 000) % of total (R 000) % of
total (R 000) % of total (R 000) % of
total
Lower skilled (levels 1–2)
0 0 0 0 0 0 0 0
Skilled (levels 3–5) 146 69.6 0 0 11 5.2 9 4.1
Highly skilled production (levels 6–8)
2 276 70.5 0 0 54 1.7 170 5.3
Highly skilled supervision (levels 9–12)
7 082 57.9 0 0 17 0.1 90 0.7
Senior management (levels 13–16) 10 174 56.4 0 0 82 0.5 122 0.7
Total 19 678 58.4 0 0 164 0.5 391 1.2
P a g e | 122
EMPLOYMENT AND VACANCIES
The following tables summarise the number of GTAC posts, the number of employees, the vacancy rate and staff that are additional to the establishment. This information is presented by subprogramme (Table 18) and by salary band (Table 19). The vacancy rate reflects the percentage of posts that are not filled.
Table 18: Employment and vacancies by programme, 31 March 2015
Table 19: Employment and vacancies by salary band, 31 March 2015
Filling of senior management service posts
The tables in this section provide information on employment and vacancies for members of the senior management service by salary level. They also provide information on advertising and filling of senior management service posts, reasons for not complying with prescribed timeframes and disciplinary steps taken.
Programme Number of funded posts Headcount Vacancy rate %
Number of posts filled additional to the establishment
Programme 8 50 50 0 9
Total 50 50 0 9
Salary band Number of posts Headcount Vacancy rate %
Number of posts filled additional to the establishment
Lower skilled (levels 1–2)
0 0 0 0
Skilled (levels 3–5)
1 1 0 0
Highly skilled production (levels 6–8)
12 12 0 3
Highly skilled supervision (levels 9–12) 21 21 0 5
Senior management (levels 13–16) 16 16 0 1
Total 50 50 0 9
P a g e | 123
Table 20: Senior management service post information, 31 March 2015
Table 21: Senior management service post information, 30 September 2014
Senior management service level
Total number of funded
senior management
service posts
Total number of senior
management service posts
filled
% of senior management
service posts filled
Total number of senior
management service
posts vacant
% of senior management service posts
vacant
Director-General/ Head of Department
0 0 0 0 0
Salary level 16 0 0 0 0 0
Salary level 15 0 0 0 0 0
Salary level 14 5 5 100 0 0
Salary level 13 11 11 100 0 0
Total 16 16 100 0 0
Senior management service level
Total number of funded
senior management
service posts
Total number of senior
management service posts
filled
% of senior management
service posts filled
Total number of senior
management service
posts vacant
% of senior management service posts
vacant
Director-General/ Head of Department
0 0 0 0 0
Salary level 16 0 0 0 0 0
Salary level 15 0 1 0 0 0
Salary level 14 8 8 100 0 0
Salary level 13 13 13 100 0 0
Total 21 22 100 0 0
P a g e | 124
Table 22: Advertising and filling of senior management service posts, 1 April 2014 to 31 March 2015
Note: Positions were reported on in the National Treasury 2014/15 Annual Report.
Table 23: Reasons for not having complied with the filling of funded vacant senior management service posts advertised within six months and filled within 12 months of becoming vacant, for the period 1 April 2014 to 31 March 2015
Reasons for vacancies not advertised within six months
N/A
Reasons for vacancies not filled within 12 months
N/A
JOB EVALUATION
The Public Service Regulations (1999) introduced job evaluation to ensure that work of equal value is remunerated equally. Within a nationally determined framework, executing authorities may evaluate or re-evaluate any job in their organisations. In terms of the regulations, all vacancies on salary levels 9 and higher must be evaluated before they are filled.
Senior management service level
Advertising Filling of posts
Number of vacancies advertised within six months of becoming
vacant
Number of vacancies filled within six months
of becoming vacant
Number of vacancies not filled within six months
but filled within 12 months
Director-General/ Head of Department
Salary level 16
Salary level 15
Salary level 14
Salary level 13
Total
P a g e | 125
Table 24 gives the number of jobs evaluated during the year under review. It also provides statistics on the number of posts upgraded or downgraded.
Table 24: Job evaluation, 1 April 2014 to 31 March 2015
Total 50 3 6 1 2 0 0
The following table gives the number of employees whose salary positions were upgraded when their posts were upgraded. The number of employees differs from the number of posts upgraded because not all employees are automatically absorbed into the new posts and some upgraded posts remained vacant.
Table 25: Profile of employees whose salary positions were upgraded due to their posts being upgraded, 1 April 2014 to 31 March 2015 Beneficiaries African Asian Coloured White Total
Female 1 0 0 0 1
Male 0 0 0 0 0
Employees with a disability 0 0 0 0 0
Total 1 0 0 0 1
Salary band Number
of posts
Number of jobs
evaluated
% of posts evaluated by salary
bands
Posts upgraded Posts downgraded
Number % of posts evaluated Number % of posts
evaluated
Lower skilled (levels 1–2) 0 0 0 0 0 0 0
Skilled (levels 3–5) 1 0 0 0 0 0 0
Highly skilled production (levels 6–8)
12 3 25 1 33 0 0
Highly skilled supervision (levels 9–12)
21 0 0 0 0 0 0
Senior management service band A 11 0 0 0 0 0 0
Senior management service band B 5 0 0 0 0 0 0
Senior management service band C 0 0 0 0 0 0 0
Senior management service band D 0 0 0 0 0 0 0
P a g e | 126
The following table shows the number of cases where remuneration levels exceeded the grade determined by job evaluation. The reasons for the deviation are provided in each case.
Table 26: Employees whose salary level exceeded the grade determined by job evaluation, 1 April 2014 to 31 March 2015 (in terms of PSR 1.V.C.3)
The table below describes the beneficiaries in terms of race, gender, and disability.
Table 27: Profile of employees whose salary level exceeded the grade determined by job evaluation, 1 April 2014 to 31 March 2015 (in terms of PSR 1.V.C.3)
Beneficiaries African Asian Coloured White Total
Female 5 0 2 1 8
Male 2 0 0 2 4
Total 7 0 2 3 12
Occupation Number of employees
Job evaluation level
Remuneration level Reason for deviation
Deputy Director-General 0 0 0 N/A
Chief Director 3 14 15 N/A
Director 3 1
13 13
14 15
N/A
Deputy Director 1 1
12 11
13 12
N/A
Assistant Director 0 0 0 N/A
Administrative level 2 1
7 7
8 9
N/A
Total number of employees whose salaries exceeded the level determined by job evaluation in 2014/15
12
Percentage of total employment 24%
P a g e | 127
EMPLOYMENT CHANGES
Changes in employment during 2014/15 are summarised below. Turnover rates provide an indication of trends in GTAC’s employment profile. The following table gives the turnover rates by salary band.
Table 28: Annual turnover rates by salary band, 1 April 2014 to 31 March 2015
Table 29: Reasons for staff leaving the department
Salary band
Number of employees per band as
on 31 March
2014
Appointments and transfers
into the department
Terminations and transfers
out of the department
Turnover rate %
Lower skilled (levels 1–2) 0 0 0 0
Skilled (levels 3–5) 0 1 0 0
Highly skilled production (levels 6–8)
0 14 1 0
Highly skilled supervision (levels 9–12)
0 23 3 0
Senior management service band A 0 10 0 0
Senior management service band B 0 6 0 0
Senior management service band C 0 0 0 0
Senior management service band D 0 0 0 0
Total 0 54 4 0
Termination type Number % of total
Death 0 0
Resignation 4 100
Expiry of contract 0 0
Dismissal – operational changes 0 0
Dismissal – misconduct 0 0
Dismissal – inefficiency 0 0
Discharged due to ill-health 0 0
Retirement 0 0
Severance package 0 0
Transfers to other public service departments 0 0
Total 4 100
Number of employees who left as a percentage of total employment (as at 31 March 2015) 8
P a g e | 128
Table 30: Promotions by salary band
EMPLOYMENT EQUITY
The tables in this section are based on the formats prescribed by the Employment Equity Act (1998).
Table 31: Total number of employees (including employees with disabilities) in each of the following occupational categories, 31 March 2015
Minister and Deputy Minister included in totals (legislators, senior officials and managers).
Salary band Employees
31 March 2014
Promotions to another salary level
Salary band promotions as a % of employees by
salary level
Lower skilled (levels 1–2)
0 0 0
Skilled (levels 3–5)
0 0 0
Highly skilled production (levels 6–8)
0 1 0
Highly skilled supervision (levels 9–12)
0 0 0
Senior management (levels13–16)
0 1 0
Total 0 2 0
Occupational categories (SASCO)
Male Female
African Coloured Indian White African Coloured Indian White Total
Legislators, senior officials and managers 7 0 1 1 1 2 1 4 17
Professionals 1 0 0 2 10 0 0 5 18
Technicians and associate professionals 1 0 0 0 9 1 1 3 15
Clerks 0 0 0 0 0 0 0 0
Service and sales workers 0 0 0 0 0 0 0 0 0
Plant and machine operators and assemblers 0 0 0 0 0 0 0 0 0
Elementary occupations 0 0 0 0 0 0 0 0 0
Total 9 0 1 3 20 3 2 12 50
P a g e | 129
Table 32: Total number of employees (including employees with disabilities) in each of the following occupational bands, 31 March 2015
Table 33: Recruitment, 1 April 2014 to 31 March 2015
Occupational bands Male Female
African Coloured Indian White African Coloured Indian White Total
Top management 0 0 0 0 0 0 0 0 0
Senior management 6 0 1 2 1 2 0 4 16
Professionally qualified and experienced specialists and mid-management
2 0 0 1 9 0 1 8 21
Skilled technical and academically qualified workers, junior management, supervisors, foremen and superintendents
1 0 0 0 9 1 1 0 12
Semi-skilled and discretionary-decision making
0 0 0 0 1 0 0 0 1
Unskilled and defined decision-making 0 0 0 0 0 0 0 0 0
Total 9 0 1 3 20 3 2 12 50
Occupational bands Male Female
African Coloured Indian White African Coloured Indian White Total
Top management (15–16)
0 0 0 0 0 0 0 0 0
Senior management (13–14)
0 0 0 0 0 0 0 0 0
Professionally qualified and experienced specialists and mid-management (9–12)
2 0 0 0 0 0 0 0 2
Skilled technical and academically qualified workers, junior management, supervisors, foremen and superintendents (6–8)
1 0 0 0 1 0 0 0 2
Semi-skilled and discretionary decision making (3–5)
0 0 0 0 0 0 0 0 0
Unskilled and defined decision making (1–2) 0 0 0 0 0 0 0 0 0
Total 3 0 0 0 1 0 0 0 4
Employees with disabilities 0 0 0 0 0 0 0 0 0
P a g e | 130
Table 34: Promotions, 1 April 2014 to 31 March 2015
Table 35: Terminations, 1 April 2014 to 31 March 2015
Minister and Deputy Minister not included in totals.
Occupational bands Male Female
African Coloured Indian White African Coloured Indian White Total
Top management (15–16)
0 0 0 0 0 0 0 0 0
Senior management (13–14)
0 0 0 0 0 0 0 0 0
Professionally qualified and experienced specialists and mid-management (9–12)
0 0 0 0 1 0 0 0 1
Skilled technical and academically qualified workers, junior management, supervisors, foremen and superintendents (6–8)
0 0 0 0 1 0 0 0 1
Semi-skilled and discretionary decision making (3–5) 0 0 0 0 0 0 0 0 0
Unskilled and defined decision-making (1–2) 0 0 0 0 0 0 0 0 0
Employees with disabilities 0 0 0 0 0 0 0 0 0
Total 0 0 0 0 2 0 0 0 2
Occupational bands Male Female
African Coloured Indian White African Coloured Indian White Total
Top management (15–16)
0 0 0 0 0 0 0 0 0
Senior management (13–14)
0 0 0 0 0 0 0 0 0
Professionally qualified and experienced specialists and mid-management (9–12)
2 0 0 0 1 0 0 0 3
Skilled technical and academically qualified workers, junior management, supervisors, foremen and superintendents (6–8)
0 0 0 0 1 0 0 0 1
Semi-skilled and discretionary decision making (3–5) 0 0 0 0 0 0 0 0 0
Unskilled and defined decision-making (1–2) 0 0 0 0 0 0 0 0 0
Total 2 0 0 0 2 0 0 0 4
P a g e | 131
Table 36: Disciplinary action, 1 April 2014 to 31 March 2015
Table 37: Skills development, 1 April 2014 to 31 March 2015
Male Female
African Coloured Indian White African Coloured Indian White Total
Disciplinary action 0 0 0 0 0 0 0 0 0
Occupational categories Male Female
Total African Coloured Indian White African Coloured Indian White
Legislators, senior officials and managers 4 0 1 1 0 1 0 1 8
Professionals 2 0 0 0 4 0 0 1 7
Technicians and associate professionals 0 0 0 0 4 0 0 2 6
Clerks 0 0 0 0 0 0 0 0 0
Service and sales workers 0 0 0 0 0 0 0 0 0
Skilled agriculture and fishery workers 0 0 0 0 0 0 0 0 0
Craft and related trades workers 0 0 0 0 0 0 0 0 0
Plant and machine operators and assemblers 0 0 0 0 0 0 0 0 0
Elementary occupations 0 0 0 0 0 0 0 0 0
Total 6 0 1 1 8 1 0 4 21
Employees with disabilities 0 0 0 0 0 0 0 0 0
P a g e | 132
PERFORMANCE REWARDS
To encourage good performance, GTAC granted the following performance rewards during the year under review. The information is presented in terms of race, gender and disability (Table 38), salary bands (Table 39) and critical occupations (Table 40).
Table 38: Performance rewards by race, gender and disability, 1 April 2014 to 31 March 2015
Beneficiary profile Cost
Number of beneficiaries
Total number of employees in
group % of total
within group Cost (R 000) Average cost per
employee
African
Male 7 9 78 360 51
Female 18 20 78 480 27
Asian
Male 1 1 100 38 38
Female 2 2 100 70 35
Coloured
Male 0 0 0 0 0
Female 3 3 100 184 61
White
Male 3 3 100 173 58
Female 11 12 92 495 45
Total 45 50 85 1 800 40
P a g e | 133
Table 39: Performance rewards by salary band for personnel below senior management service level, 1 April 2014 to 31 March 2015
Table 40: Performance-related rewards (cash bonus) by salary band for senior management service
Salary band Beneficiary profile Cost
Number of
beneficiaries Number of employees
% of total within salary band
Total cost
(R 000)
Average cost per
employee (R 000)
Total cost as a % of total personnel
expenditure
Lower skilled (levels 1–2) 0 0 0 0 0 0
Skilled (levels 3–5) 1 1 100 13 13 0.01
Highly skilled production (levels 6–8)
10 10 100 199 19 0.03
Highly skilled supervision (levels 9–12)
16 23 69.5 627 33 0.09
Total 27 34 79.4 839 33 0.12
Salary band Beneficiary profile Total cost
(R 000)
Average cost per
employee
Total cost as a % of
total personnel
expenditure
Number of beneficiaries
Number of employees
% of total within band
Band A 12 13 92 611 47 0.09
Band B 5 5 100 350 66 0.05
Band C 0 0 0 0 0 0
Band D 0 0 0 0 0 0
Total 17 18 94.7 961 54 0.14
P a g e | 134
FOREIGN WORKERS
Table 41: Foreign workers by salary band, 1 April 2014 to 31 March 2015
Table 42: Foreign workers by major occupation, 1 April 2014 to 31 March 2015
LEAVE UTILISATION, 1 JANUARY 2014 TO 31 DECEMBER 2014
The Public Service Commission has identified the need for careful monitoring of sick leave in the public service. The following tables indicate the use of sick leave (Table 43) and disability leave (Table 44). In both cases, the estimated cost of the leave is also provided.
Salary band March 2014 March 2015 Change
Number % of total Number % of total Number % change
Lower skilled (levels 1–2) 0 0 0 0 0 0
Skilled (levels 3–5) 0 0 0 0 0 0
Highly skilled production (levels 6–8) 0 0 0 0 0 0
Highly skilled supervision (levels 9–12) 0 0 3 100 3 100
Senior management (levels 13–16) 0 0 0 0 0 0
Total 0 0 3 100 3 100
Salary band March 2014 March 2015 Change
Number % of total Number % of total Number % change
Senior management 0 0 0 0 0 0
Professional qualified 0 0 0 0 0 0
Skilled technical 0 0 3 100 3 100
Semi-skilled 0 0 0 0 0 0
Unskilled 0 0 0 0 0 0
Total 0 0 3 100 3 100
P a g e | 135
Table 43: Sick leave, 1 January 2014 to 31 December 2014
Table 44: Disability leave (temporary and permanent), 1 January 2014 to 31 December 2014
Table 45 summarises the annual leave used during 2014/15. The wage agreement concluded with trade unions in the Public Service Coordinating Bargaining Council in 2000 requires management of annual leave to prevent high levels of accrued leave being paid at the time of termination of service.
Salary band Total days
% days with medical
certification
Number of employees using sick
leave
% of total employees using sick
leave
Average days per employee
Estimated cost
(R 000)
Lower skilled (levels 1–2) 0 0 0 0 0 0
Skilled (levels 3–5) 4 100 1 2.6 4 5
Highly skilled production (levels 6–8) 74 81 9 23.1 8 76
Highly skilled supervision (levels 9–12)
111 86 13 33.3 9 181
Senior management (levels 13–16) 97 71 16 41.0 6 312
Total 286 80 39 100 7 330
Salary band
Total days taken
% days with medical
certification
Number of employees
using disability
leave
% of total employees
using disability
leave
Average days per employee
Estimated cost
(R 000)
Lower skilled (levels 1–2) 0 0 0 0 0 0
Skilled (levels 3–5) 0 0 0 0 0 0
Highly skilled production (levels 6–8)
0 0 0 0 0 0
Highly skilled supervision (levels 9–12)
0 0 0 0 0 0
Senior management (levels 13–16) 0 0 0 0 0 0
Total 0 0 0 0 0 0
P a g e | 136
Table 45: Annual leave, 1 January 2014 to 31 December 2014
Table 46: Capped leave, 1 January 2014 to 31 December 2014
The following table summarises payments made to employees as a result of leave not taken.
Table 47: Leave payouts for the period 1 April 2014 to 31 March 2015
Salary bands Total days taken Average per employee
Lower skilled (levels 1–2) 0 0
Skilled (levels 3–5) 26 26
Highly skilled production (levels 6–8) 194 18
Highly skilled supervision (levels 9–12) 394 23
Senior management (levels 13–16) 442 23
Total 1 056 22
Salary bands Total days of capped leave
taken
Average number of days taken per
employee
Average capped leave per
employee as at 31 December 2014
Lower skilled (levels 1–2) 0 0 0
Skilled (levels 3–5) 0 0 0
Highly skilled production (levels 6–8) 0 0 0
Highly skilled supervision(levels 9–12) 0 0 0
Senior management (levels 13–16) 0 0 0
Total 0 0 0
Reason Total amount
(R 000) (a)
Number of employees
(b)
Average payment per employee
(R 000)
Leave payout for 2014/15 due to non-utilisation of leave for the previous cycle 0 0 0
Capped leave payouts on termination of service for 2014/15 0 0 0
Current leave payout on termination of service for 2014/15 56 4 14
Total 56 4 14
P a g e | 137
HIV/AIDS AND HEALTH PROMOTION PROGRAMMES
Table 48: Steps taken to reduce the risk of occupational exposure
The information in the following table is based on GTAC’s shared service agreement with the National Treasury.
Table 49: Details of health promotion and HIV/AIDS programmes
Units/categories of employees identified to be at high risk of contracting HIV and related diseases (if any)
Key steps taken to reduce the risk
N/A N/A
Question Yes No Details, if yes
1. Has the department designated a member of the SMS to implement the provisions contained in Part VI E of Chapter 1 of the Public Service Regulations (2001)? If so, provide her/his name and position.
X
2. Does the department have a dedicated unit or has it designated specific staff members to promote the health and well-being of your employees? If so, indicate the number of employees who are involved in this task and the annual budget that is available for this purpose.
X
The Employee Wellness Unit is a subdirectorate of the Organisational Development directorate within the Human Resources Management Chief Directorate. The Employee Wellness Unit is run by a wellness specialist (Assistant Director) and one intern, recruited through the National Treasury Graduate Development Programme on a fixed-term contract for a period of two years. The unit has a budget of R3.5 million to use over a period of three years.
3. Has the department introduced an employee assistance or health promotion programme for employees? If so, indicate the key elements/services of this programme.
X
The National Treasury provides employee assistance programmes under its programme brand of Siyaphila. Siyaphila is a confidential, free, 24-hour, 365-day personal support line for National Treasury employees and their immediate family members. These services include counselling services, wellness management, HIV/AIDS management, primary healthcare services and productivity management.
P a g e | 138
4. Has the department established (a) committee(s) as contemplated in Part VI E.5 (e) of Chapter 1 of the Public Service Regulations? If so, please provide the names of the members of the committee and the stakeholder(s) that they represent.
X
The committee consists of employees across the department in various divisions. These include: Sheridan Pillay Johnny October Margaret Serumula Innocentia Machaba Jolanda Watton Octavia Maphila Nomlotha Mazibuko Betty Malope Judith Rudolph Ezre Stokes Tebogo Lekote This committee has not been active in 2014/15 and is to be revived in 2015/16. It has, however, been involved in events planning, identifying health inhibitors and providing solutions to enhance the quality of service rendered to the department. A review of the terms of reference and contracting of committee members will occur in 2015/16.
5. Has the department reviewed its employment policies and practices to ensure that these do not unfairly discriminate against employees on the basis of their HIV status? If so, list the employment policies/practices reviewed. X
The HIV/AIDS and TB management policy has been reviewed and tabled at the Governance Review and Departmental Bargaining Chambers for consultation and endorsement. A task team for Employee Wellness Programme policies and frameworks has been established and is represented by stakeholders including organised labour, employee relations, occupational health and safety, the chief risk officer, divisional support of Corporate Services and Human Resources Management.
6. Has the department introduced measures to protect HIV-positive employees or those perceived to be HIV-positive from discrimination? If so, list the key elements of these measures.
X
Confidentiality clauses are in place and still enforced. New infections are managed by the primary healthcare personnel.
7. Does the department encourage its employees to undergo voluntary counselling and testing? If so, list the results achieved.
X
In 2014/15, 194 employees voluntarily tested for HIV/AIDS. The department has a clinic on-site providing primary healthcare services. The clinic is occupied by a nurse twice a week for four hours each day, and a doctor one day a week for an hour. The services are free and provide employees with an opportunity to do voluntary testing. The Siyaphila programme hosts six departmental events per year, where employees also have the opportunity to do voluntary testing. Nurses are present at each of the events to render this service.
P a g e | 139
LABOUR RELATIONS
GTAC did not enter into collective agreements with trade unions during 2014/15.
Table 50: Collective agreements, 1 April 2014 to 31 March 2015
Table 51: Misconduct and disciplinary hearings finalised, 1 April 2014 to 31 March 2015
Table 52: Types of misconduct addressed at disciplinary hearings
8. Has the department developed measures/indicators to monitor and evaluate the effect of its health promotion programme? If so, list these measures/indicators.
X
Rate of absenteeism. Number of health-related complaints. Voluntary HIV/AIDS reports (that do not
compromise confidentiality). Employee Wellness Programme satisfaction
surveys. Wellness cards to continuously monitor and
improve on health risk assessments. Quarterly and annual usage statistics of
services.
Subject matter Date
N/A N/A
Outcomes of disciplinary hearings Number % of total
Correctional counselling 0 0
Verbal warning 0 0
Written warning 0 0
Final written warning 0 0
Suspended without pay 0 0
Fine 0 0
Demotion 0 0
Dismissal 0 0
Not guilty 0 0
Case withdrawn 0 0
Total 0 0
Type of misconduct Number % of total
Disruptive behaviour, gross negligence, insubordination, dishonesty
0 0
Total 0 0
P a g e | 140
Table 53: Grievances lodged, 1 April 2014 to 31 March 2015
Table 54: Disputes lodged with councils, 1 April 2014 to 31 March 2015
Table 55: Strike actions, 1 April 2014 to 31 March 2015
Table 56: Precautionary suspensions, 1 April 2014 to 31 March 2015
Number % of total
Number of grievances resolved 0 0
Number of grievances not resolved 0 0
Total number of grievances lodged 0 0
Number % of total
Number of disputes upheld 0 0
Number of disputes dismissed 0 0
Total number of disputes lodged 0 0
Total number of person working days lost 0
Total cost (R 000) of working days lost 0
Amount (R 000) recovered as a result of no work no pay 0
Number of people suspended 0
Number of people whose suspension exceeded 30 days 0
Average number of days suspended 0
Cost of suspensions 0
P a g e | 141
SKILLS DEVELOPMENT
This section summarises GTAC’s skills development work.
Table 57: Training needs identified, 1 April 2014 to 31 March 2015
Minister and Deputy Minister not included in total.
Occupational categories Gender
Number of employees
as at 1 April 2014
Training needs identified at start of reporting period
Learnerships Skills
programmes and other
short courses
Other forms of training
Total
Legislators, senior officials and managers
Female 6 0 2 0 2
Male 9 0 5 1 6
Professionals Female 18 0 5 0 5
Male 5 0 2 0 2
Technicians and associated professionals
Female 12 0 5 1 6
Male 0 0 0 0 0
Clerks Female 0 0 0 0 0
Male 0 0 0 0 0
Service and sales workers
Female 0 0 0 0 0
Male 0 0 0 0 0
Skilled agriculture and fishery workers
Female 0 0 0 0 0
Male 0 0 0 0 0
Craft and related trades workers
Female 0 0 0 0 0
Male 0 0 0 0 0
Plant and machine operators and assemblers
Female 0 0 0 0 0
Male 0 0 0 0 0
Elementary occupations
Female 0 0 0 0 0
Male 0 0 0 0 0
Subtotal Female 36 0 12 1 13
Male 14 0 7 1 8
Total 50 0 19 2 21
P a g e | 142
Table 58: Training provided, 1 April 2014 to 31 March 2015
Minister and Deputy Minister not included in total.
INJURIES ON DUTY
Table 59: Injuries on duty, 1 April 2014 to 31 March 2015
Occupational categories Gender
Number of employees
as at 1 April 2014
Training provided within the reporting period
Learnerships
Skills programmes
and other short
courses
Other forms of training
Total
Legislators, senior officials and managers
Female 6 0 2 0 2
Male 9 0 5 1 6
Professionals Female 18 0 5 0 5
Male 5 0 2 0 2
Technicians and associated professionals
Female 12 0 5 1 6
Male 0 0 0 0 0
Clerks Female 0 0 0 0 0
Male 0 0 0 0 0
Service and sales workers
Female 0 0 0 0 0
Male 0 0 0 0 0
Skilled agriculture and fishery workers
Female 0 0 0 0 0
Male 0 0 0 0 0
Craft and related trades workers
Female 0 0 0 0 0
Male 0 0 0 0 0
Plant and machine operators and assemblers
Female 0 0 0 0 0
Male 0 0 0 0 0
Elementary occupations
Female 0 0 0 0 0
Male 0 0 0 0 0
Subtotal Female 36 0 12 1 13
Male 14 0 7 1 8
Total 50 0 19 2 21
Nature of injury on duty Number % of total
Required basic medical attention only 0 0
Temporary total disablement 0 0
Permanent disablement 0 0
Fatal 0 0
Total 0 0
P a g e | 143
ANNUAL REPORT 2014/15
PART E: GOVERNANCE
P a g e | 144
GOVERNANCE GTAC is a government component established in terms of Legal Notice 261, issued in terms of the Public Service Act and gazetted on 30 March 2012.
The Minister of Finance assigned several functions and organisational units from the National Treasury to GTAC in April 2014. Personnel were initially seconded from the National Treasury to GTAC.
For purposes of planning and reporting in terms of the Public Finance Management Act and in compliance with the Treasury Regulations, for the period under review GTAC was a component of Programme 8 of the National Treasury vote – Technical Support and Development Finance – and is accordingly included in the 2014/15 strategic and annual performance plans and the annual report of the National Treasury.
RISK MANAGEMENT Through a shared service agreement with the Corporate Services Division of the National Treasury, GTAC has used the National Treasury Enterprise Risk Management services during 2014/15.
INTERNAL AUDIT REPORT During 2014/15, GTAC continued to use the National Treasury’s internal audit function through a shared services agreement.
P a g e | 145
ANNUAL REPORT 2014/15
ANNEXURES
Pa
ge
| 1
46
AN
NEX
UR
E 1:
AN
NU
AL
PER
FOR
MA
NC
E TA
BLE
S Pr
ogra
mm
e 8:
Tec
hnic
al a
nd M
anag
emen
t Sup
port
and
Dev
elop
men
t Fin
ance
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
Subp
rogr
amm
e: T
echn
ical S
uppo
rt an
d De
velo
pmen
t Fin
ance
Pro
gram
me M
anag
emen
t
1 Pr
ogra
mme o
ffice d
evelo
pmen
t: stre
ngthe
n pro
gram
me of
fice a
nd co
ordin
ate bu
dget
and d
onor
fund
ing, a
nd go
vern
ance
and p
rogr
amme
repo
rts
Stre
ngthe
n pr
ogra
mme o
ffice
and c
oord
inate
budg
et an
d don
or
fundin
g C
omply
with
go
vern
ance
and
repo
rting
requ
ireme
nts
Targ
et:
Comp
lete
prog
ramm
e offic
e pr
opos
al Qu
arter
ly re
portin
g on
prog
ramm
e 8
Quar
terly
repo
rting
on pr
ogra
mme 8
Qu
arter
ly re
portin
g on
prog
ramm
e 8
Prog
ramm
e 8 an
d GT
AC Q
uarte
rly
Repo
rts to
Mini
ster o
f Fin
ance
; NT
Stra
tegic
Plan
and A
PP
Prog
ramm
e 8 an
d GTA
C 01
-Q4 r
epor
t and
stra
tegic
plan
for 20
15 M
TEF
comp
iled.
Narra
tive r
epor
t com
piled
will
be av
ailab
le in
1st Q
uarte
r of
2015
/16.
Annu
al ou
tput a
nd va
rianc
e: Pr
ogra
mme 8
offic
e co
ordin
ation
func
tion c
ontin
ues t
o be p
erfor
med b
y GTA
C.
The P
rogr
amme
Offic
e was
stre
ngthe
ned t
hrou
gh qu
arter
ly ma
nage
ment
comm
ittees
held
to co
ordin
ate bu
dget
and
dono
r fun
ding.
This
was b
y com
plying
with
the g
over
nanc
e an
d rep
ortin
g req
uirem
ents
throu
gh q
uarte
rly na
rrativ
e re
ports
that
indica
te fin
ancia
l and
gove
rnan
ce co
mplia
nce.
A pu
blish
able
2014
/15 an
nual
repo
rt wi
ll be a
vaila
ble by
the
end s
econ
d qua
rter o
f the 2
015/1
6 fina
ncial
year
.
Achie
ved:
Prog
ramm
e 8
Mana
geme
nt Co
mmitte
e es
tablis
hed
Prog
ramm
e 8 an
d GT
AC Q
1 rep
ort
comp
iled
Prog
ramm
e 8 an
d GT
AC Q
2 rep
ort
comp
iled
Prog
ramm
e 8 an
d GT
AC Q
3 rep
ort a
nd
strate
gic pl
an fo
r 20
15 M
TEF
comp
iled
2 G
TAC
estab
lishe
d
Fu
rther
deve
lop
GTAC
’s ca
pacit
y and
ad
visor
y ser
vice
prod
ucts
Targ
et:
Estab
lish i
nitial
or
ganis
ation
al de
sign
Comp
lete f
inanc
ial
mana
geme
nt an
d HR
tran
sition
Qu
arter
ly re
portin
g on
GTA
C Qu
arter
ly re
portin
g on
GTA
C
Prog
ramm
e 8 an
d GT
AC Q
uarte
rly
Repo
rts to
Mini
ster o
f Fin
ance
Annu
al ou
tput a
nd va
rianc
e: Co
mplet
ion of
GTA
C fin
ancia
l ma
nage
ment
and H
R tra
nsitio
n defe
rred t
o 201
5/16.
Seco
nd ph
ase o
f org
aniza
tiona
l HR
trans
fer im
pleme
nted w
ef 1 A
pril 2
015.
Appr
oval
rece
ived t
o tra
nsfer
emplo
yees
after
the s
econ
dmen
t per
iod to
GTA
C.
Finan
cial re
portin
g for
GTA
C pr
ovide
d on a
quar
terly
basis
as
part
of the
narra
tive r
epor
ts. F
inanc
ial S
tatem
ents
will b
e pr
ovide
d und
er th
e Ann
ual R
epor
t for G
TAC
and
Prog
ramm
e 8.
The d
eferra
l of H
R an
d fina
ncial
arra
ngem
ents
will b
e
Achie
ved:
Inter
im G
TAC
Mana
geme
nt Co
mmitte
e es
tablis
hed
Finan
cial
mana
geme
nt an
d HR
proc
esse
s un
der w
ay
Supp
ort fo
r Pha
kisa
labs p
rovid
ed (s
ee
quar
terly
repo
rt)
Quar
terly
repo
rting
Pa
ge
| 1
47
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
addr
esse
d for
finali
zatio
n dur
ing th
e 201
5/16 f
inanc
ial ye
ar,
to be
comp
leted
by 31
Mar
ch.
3 Pr
oject
appr
aisals
and e
cono
mic a
sses
smen
t of p
olicy
and p
rogr
amme
s
Per
form
3–5 p
rojec
t ap
prais
als
Stre
ngthe
n majo
r ca
pital
proje
ct ap
prais
al ca
pacit
y D
evelo
p fra
mewo
rk for
priva
te fin
ance
in
supp
ort o
f inf
rastr
uctur
e inv
estm
ent
Targ
et:
3–5 c
apita
l pro
ject a
ppra
isals;
repo
rt on
infra
struc
ture f
inanc
e tas
k tea
m
NCP
Unit:
Prog
ramm
e 8 an
d GT
AC Q
uarte
rly
Repo
rt, G
TAC
repo
rts 13
proje
ct as
sess
ment
repo
rts
Rese
arch
on tr
ansp
ort a
ppra
isal m
ethod
ologie
s
Repo
rt on
deve
lopme
nt of
inves
tmen
t fram
ewor
k
Perfo
rmed
four
proje
ct ap
prais
als
Stre
ngthe
ned m
ajor c
apita
l pro
ject a
ppra
isal c
apac
ity.
Deve
loped
a fra
mewo
rk for
priva
te fin
ance
in su
ppor
t of
infra
struc
ture i
nves
tmen
t
Comp
leted
nine
perfo
rman
ce an
d exp
endit
ure r
eview
s
Devia
tion
More
proje
ct as
sess
ments
done
, but
a num
ber o
f thes
e we
re sm
aller
and r
elated
to E
skom
and e
nerg
y sec
tor,
which
is at
ypica
l.
Metho
dolog
y ado
pted t
akes
4-6
mon
ths to
comp
lete o
ne
revie
w, 8-
10 re
views
are d
one s
imult
aneo
usly.
Achie
ved:
Prog
ramm
e 8 re
port
5 rep
orts
on ca
pital
proje
cts
Prog
ramm
e 8
quar
terly
repo
rt 2 r
epor
ts on
capit
al pr
ojects
Re
port
on
deve
lopme
nt of
inves
tmen
t fra
mewo
rk
Prog
ramm
e 8
quar
terly
repo
rt 2 r
epor
ts on
capit
al pr
ojects
4 rep
orts
on ca
pital
proje
cts
Unde
rtake
5–10
ex
pend
iture
and
perfo
rman
ce re
views
Ta
rget:
Ini
tiate
5–10
EPR
s Su
ppor
t per
sonn
el re
view
proc
ess
3-5 r
eview
repo
rts
3–
5 rev
iew re
ports
3–5 r
eview
repo
rts
GT
AC E
PR re
ports
an
d rec
ords
Ac
hieve
d: 2 r
eview
s com
pleted
3 r
eview
s co
mplet
ed
3 rev
iews
comp
leted
Ini
tiated
10 re
views
, co
mplet
ed
Subp
rogr
amm
e: G
over
nmen
t Tec
hnica
l Adv
isory
Cen
tre
4 Nu
mber
of te
chnic
al as
sistan
ce pr
ojects
supp
orted
10
0
Targ
et:
50
65
85
100
GTAC
Bus
iness
Ma
nage
ment
Infor
matio
n Sys
tem
93 p
rojec
ts su
ppor
ted.
This
numb
er i
s de
termi
ned
by
dema
nd, a
nd al
so ap
prov
al wa
s give
n for
a lar
ger n
umbe
r of
proje
cts th
an c
ould
be a
chiev
ed.
Thou
gh th
e nu
mber
of
proje
cts s
uppo
rted
is low
er th
an a
nticip
ated
this
has
much
to
do w
ith th
e sc
alabil
ity o
f pro
jects.
This
impa
cts o
n the
nu
mber
of pr
ojects
supp
orted
.
Achie
ved:
80 su
ppor
ted
77 su
ppor
ted
84 su
ppor
ted
93 pr
ojects
su
ppor
ted
Pa
ge
| 1
48
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
5 Pe
rcenta
ge of
clien
ts wh
o hav
e obs
erve
d cap
acity
impr
ovem
ent
85
%
Targ
et:
85%
85
%
85%
85
%
Clien
t sati
sfacti
on
surve
y; fee
dbac
k and
ev
aluati
ons
The a
nnua
l av
erag
e for
this
ind
icator
was
90.6
25%
for
inter
nal a
s we
ll as
exte
rnal
clien
ts. In
Q4
96%
of e
xtern
al cli
ents
and
87.2
% o
f inte
rnal
clien
ts, a
n av
erag
e of
92%
, ob
serve
d cap
acity
impr
ovem
ent. T
his da
ta wa
s der
ived f
rom
clien
t sa
tisfac
tion
surve
ys,
feedb
ack
and
evalu
ation
s co
mplet
ed.
Achie
ved:
88.5%
93
%
89%
96
% ex
terna
l and
87
.2% in
terna
l =
92%
6 Nu
mber
of kn
owled
ge pr
oduc
ts re
lated
to ca
pacit
y buil
ding (
learn
ing ne
twor
ks, c
ommu
nities
of pr
actic
e, ca
se st
udies
, lear
ning
sess
ions a
nd kn
owled
ge ex
chan
ge)
10
Targ
et:
2 2
3 3
GTAC
reco
rds,
prog
ress
repo
rts
Seve
n ses
sions
and t
wo pr
oduc
ts we
re co
nduc
ted/pr
oduc
ed
in Q4
. For
201
4/15
a tot
al of
31 pr
oduc
ts an
d se
ssion
s wer
e co
nduc
ted an
d dev
elope
d.
Devia
tion
The
know
ledge
pro
ducts
and
ses
sions
are
nee
ds a
nd
oppo
rtunit
y driv
en w
hich
resu
lted i
n mo
re s
essio
ns t
han
plann
ed.
Achie
ved:
13
5 4
7 ses
sions
and 2
pr
oduc
ts
7
PPP
and c
apita
l pro
jects
supp
orted
PRAS
A ro
lling s
tock
Re
newa
ble en
ergy
IPP
prog
ramm
e
Hosp
ital re
vitali
satio
n
Othe
r pro
jects
Ongo
ing m
onito
ring
and s
uppo
rt for
im
pleme
ntatio
n of
PRAS
A ro
lling s
tock
prog
ramm
e
Targ
et:
Perfo
rman
ce of
the R
olling
Stoc
k pro
gram
me ag
ainst
targe
ts.
Quar
terly
repo
rts of
the
PRA
SA ro
lling
stock
prog
ramm
e
Quar
terly
repo
rts in
dicati
ng th
at PR
ASA
rollin
g stoc
k pr
ogra
mme i
s on t
rack
to m
eet q
uarte
rly ta
rgets
. No
varia
nce.
Ac
hieve
d: Qu
arter
ly re
ports
: PR
ASA
rollin
g stoc
k pro
gram
me is
on tr
ack t
o mee
t qua
rterly
targ
ets
REIP
PPP
3rd r
ound
an
d pre
para
tion f
or
furthe
r sup
port
to Do
E lar
ge po
wer p
rodu
cer
proje
cts
Targ
et:
Prog
ress
linke
d to
proje
ct life
-cycle
.
Prog
ress
linke
d to
proje
ct life
-cycle
.
Prog
ress
linke
d to
proje
ct life
-cycle
.
Prog
ress
linke
d to
proje
ct life
-cycle
Qu
arter
ly re
ports
of
the R
EIPP
PP O
ffice
Quar
terly
repo
rts on
prog
ress
linke
d to p
rojec
t life-
cycle
.
Achie
ved:
Ongo
ing su
ppor
t to
DoE
Prep
arati
on of
RE
IPPP
P 3r
d ro
und o
n tra
ck
REIP
PPP
3rd r
ound
ten
der c
omple
ted
Quar
terly
repo
rts on
pr
ogre
ss lin
ked t
o pr
oject
life-cy
cle
Phas
ed
imple
menta
tion o
f ho
spita
l rene
wal a
nd
PPP
supp
ort
Targ
et:
Prog
ress
base
d on
proje
ct life
cycle
Pr
ogre
ss ba
sed o
n pr
oject
life cy
cle
Prog
ress
base
d on
proje
ct life
cycle
Pr
ogre
ss ba
sed o
n pr
oject
life cy
cle
GTAC
Qua
rterly
re
ports
, PPP
Unit
re
cord
s
Feas
ibility
stud
ies co
mplet
ed as
part
of the
first
phas
e, wa
iting t
o pro
ceed
to im
pleme
ntatio
n.
This
proje
ct is
off th
e list
pend
ing th
e fina
l dec
ision
by D
oH.
Achie
ved:
Feas
ibility
stud
ies
comp
leted
Fir
st ph
ase c
omple
ted, w
aiting
to pr
ocee
d to i
mplem
entat
ion
Pa
ge
| 1
49
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
prog
ramm
e
Othe
r tra
nsac
tion
advis
ory p
rojec
ts:
appr
oxim
ately
10 pe
r ye
ar
Targ
et:
Quar
terly
repo
rt on
new
proje
cts re
gister
ed an
d pro
gres
s on o
ngoin
g pro
jects
GTAC
Qua
rterly
re
ports
, PPP
Unit
re
cord
s
Othe
r tra
nsac
tion a
dviso
ry pr
ojects
supp
orted
; qua
rterly
re
port
on ne
w pr
ojects
regis
tered
; pro
gres
s on o
ngoin
g pr
ojects
.
Achie
ved:
6 new
proje
cts
regis
tered
Ne
w pr
ojects
regis
tered
and r
egist
ratio
n let
ters i
ssue
d
Quar
terly
repo
rt on
ne
w pr
ojects
re
gister
ed an
d pr
ogre
ss on
ongo
ing
proje
cts
Subp
rogr
amm
e: L
ocal
Gove
rnm
ent F
inan
cial M
anag
emen
t Sup
port
8 Nu
mber
of fin
ancia
l man
agem
ent in
terns
appo
inted
to m
unici
paliti
es
1 3
90
Targ
et:
400
400
190
400
CD: M
FMA
Imple
menta
tion
Munic
ipaliti
es’
month
ly re
ports
1286
Inter
ns ap
point
ed
Varia
nce d
ue to
abso
rptio
n of in
terns
into
perm
anen
t po
sition
s at m
unici
paliti
es an
d inte
rns l
eavin
g for
othe
r op
portu
nities
. Ac
hieve
d: 1 3
09
1 278
1 2
84
1 286
9 Nu
mber
of m
unici
paliti
es as
sisted
thro
ugh M
FIP
Ini
tiatio
n of M
FIP
II and
es
tablis
hmen
t of P
MU
office
Targ
et:
Phas
e 1 of
the M
FIP
ende
d 31 M
arch
2014
. Wind
-dow
n of p
hase
1 an
d plan
ning f
or
MFIP
II. In
itial ro
und o
f plac
emen
ts in
munic
ipaliti
es in
Q3 a
nd Q
4
CD: C
apac
ity
Build
ing, O
AG.
MFIP
PMU
reco
rds
and m
unici
pal a
dviso
r re
ports
The F
MCMM
asse
ssme
nt wa
s und
ertak
en in
73%
of 27
8 mu
nicipa
lities
.
Seco
nd ro
und o
f mun
icipa
lities
iden
tified
for s
uppo
rt. 33
po
tentia
l ser
vice p
rovid
ers i
nvite
d to s
ubmi
t pro
posa
ls.
Inter
views
cond
ucted
23 –
27 F
ebru
ary 2
015 a
nd fu
rther
se
ven a
dviso
rs ap
point
ed co
mmen
cing M
arch
2015
. In to
tal
16 m
unici
pal a
dviso
rs ap
point
ed an
d two
Stan
dard
Cha
rt of
Acco
unts
(SCO
A) a
dviso
rs ap
point
ed.
Phas
e 1 of
the M
FIP
ende
d 31 M
arch
2014
. Wind
-dow
n of
phas
e 1 an
d plan
ning f
or M
FIP
II. Ini
tial ro
und o
f pla
ceme
nts in
mun
icipa
lities
in Q
3 and
Q4.
Achie
ved:
No m
unici
paliti
es
supp
orted
with
TA
assis
tance
in th
is qu
arter
TA
s app
ointed
to
IGR
to su
ppor
t mu
nicipa
l fina
nce
refor
m
MFIP
II de
signe
d an
d stee
ring
comm
ittee
estab
lishe
d Te
nder
issu
ed fo
r pr
ospe
ctive
servi
ce
prov
iders
MFIP
II ini
tial
datab
ase o
f ser
vice
prov
iders
appo
inted
on
11 N
ovem
ber
2014
11
mun
icipa
lities
ide
ntifie
d for
first
roun
d of s
uppo
rt 9 a
dviso
rs ap
point
ed fo
r co
mmen
ceme
nt of
dutie
s on 5
Janu
ary
2015
Seco
nd ro
und o
f mu
nicipa
lities
ide
ntifie
d for
supp
ort
33 po
tentia
l ser
vice
prov
iders
invite
d to
subm
it pro
posa
ls Int
ervie
ws
cond
ucted
23–2
7 Fe
brua
ry 20
15 an
d fur
ther 7
advis
ors
appo
inted
co
mmen
cing M
arch
20
15
In tot
al 16
Mun
icipa
l Ad
visor
s app
ointed
an
d 2 S
tanda
rd
Char
t of A
ccou
nts
Pa
ge
| 1
50
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
(SCO
A) A
dviso
rs ap
point
ed
10
Audit
actio
n plan
s dev
elope
d and
imple
mente
d
Al
l mun
icipa
lities
Targ
et:
60
120
180
278
CD: M
FMA
Imple
menta
tion
Month
ly re
ports
of
munic
ipaliti
es
Ther
e wer
e 203
mun
icipa
l aud
it acti
on pl
ans d
evelo
ped t
o ad
dres
s 201
3/14 a
udit f
inding
s as a
t 28 F
ebru
ary 2
015.
The
rema
ining
actio
n plan
s are
in th
e pro
cess
of be
ing
deve
loped
. De
viatio
n Th
e rem
aining
75 m
unici
pal a
udit a
ction
plan
s are
in th
e pr
oces
s of b
eing d
evelo
ped w
hich i
s dep
ende
nt on
issu
ance
of
audit
opini
on by
the A
udito
r-Gen
eral.
Achie
ved:
243
274
275
Ther
e wer
e 203
mu
nicipa
l aud
it ac
tion p
lans
deve
loped
to
addr
ess 2
013/1
4 au
dit fin
dings
as at
28
Feb
ruar
y 201
5 Th
e rem
aining
ac
tion p
lans a
re in
the
proc
ess o
f bein
g de
velop
ed
11
Mu
nicipa
l com
plian
ce w
ith B
udge
t and
Tre
asur
y Offic
e, su
pply
chain
man
agem
ent, i
ntern
al au
dit an
d aud
it com
mitte
e req
uirem
ents
Im
pleme
nt mu
nicipa
l fin
ancia
l man
agem
ent
capa
bility
asse
ssme
nt
Targ
et:
Phas
e 1 ro
llout
Phas
e 2 ro
llout
Asse
ssme
nts in
50
% of
mu
nicipa
lities
Asse
ssme
nts in
10
0% of
mu
nicipa
lities
CD: M
FMA
Imple
menta
tion U
nit
FMG
month
ly re
ports
fro
m mu
nicipa
lities
The
FMCM
M for
mun
icipa
lities
was
und
ertak
en in
73
per
cent
of mu
nicipa
lities
at
the e
nd o
f Ma
rch 2
015,
other
as
sess
ments
conti
nuing
in A
pril 2
015.
Delay
exp
erien
ced
in the
com
pletio
n of
asse
ssme
nt an
d ro
llout
by
munic
ipaliti
es
due
to oth
er
comm
itmen
ts ex
pres
sed
by m
unici
pal o
fficial
s. Ou
tstan
ding
asse
ssme
nts
will b
e foll
owed
up du
ring A
pril a
nd M
ay 20
15.
Due
to cir
cums
tance
s ou
tside
of t
he s
et tar
get a
var
iance
oc
curre
d and
shou
ld be
noted
.
Achie
ved:
FMCM
M too
l de
velop
ed an
d re
ady f
or co
untry
wi
de ro
ll out
Await
ing in
terna
l ap
prov
al pr
oces
s to
proc
eed w
ith
exter
nal te
nder
s
Deve
lopme
nt of
asse
ssme
nt too
l co
mplet
ed
Deve
lopme
nt of
FMCM
M as
sess
ment
tool
comp
leted
. Ten
der
evalu
ation
proc
ess
also c
omple
ted in
De
cemb
er 20
14.
Rollo
ut of
asse
ssme
nts at
mu
nicipa
lities
pla
nned
from
Ja
nuar
y to M
arch
20
15
The F
MCMM
for
munic
ipaliti
es w
as
unde
rtake
n in 7
3%
of mu
nicipa
lities
at
the en
d of M
arch
20
15, o
ther
asse
ssme
nts
conti
nuing
in A
pril
2015
Pa
ge
| 1
51
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
Subp
rogr
amm
e: U
rban
Dev
elopm
ent S
uppo
rt
12
Long
-term
urba
n reg
ener
ation
prog
ramm
es re
gister
ed (c
umula
tive)
13
Ta
rget:
CD: N
DP U
nit
Munic
ipal p
lans
subm
itted t
o NT
The P
rogr
amme
regis
tered
13 lo
ng-te
rm ur
ban r
egen
erati
on
prog
ramm
es du
ring 2
014/1
5.
Achie
ved:
2 3
8 13
13
Total
numb
er of
catal
ytic N
eighb
ourh
ood D
evelo
pmen
t Pro
gram
me pr
ojects
appr
oved
(cum
ulativ
e)
32
0
Targ
et:
300
310
315
320
CD: N
DP U
nit
Munic
ipal p
lans
subm
itted t
o NT
Cumu
lative
numb
er of
catal
ytic p
rojec
ts ap
prov
ed is
317.
Due t
o exte
nded
timefr
ames
to fin
alise
prec
inct p
lans (
urba
n hu
bs) t
o a su
fficien
t leve
l of d
etail t
o ide
ntify
catal
ytic
proje
cts, th
ere h
as be
en a
delay
in id
entify
ing th
e tar
geted
nu
mber
. De
viatio
n 3 c
atalyt
ic pr
ojects
unde
r way
. Due
to th
e rev
ised N
DPG
appr
oach
– i.e
. the U
rban
Netw
ork S
trateg
y, the
NDP
is
worki
ng w
ith a
redu
ced 1
8 mun
icipa
lities
. The
se
munic
ipaliti
es ar
e not
just d
oing p
rojec
ts, bu
t plan
ning a
t a
city-w
ide an
d pre
cinct
level.
Due
to lo
nger
timefr
ames
to
finali
se pr
ecinc
t plan
s (ur
ban h
ubs)
to a s
uffici
ent le
vel o
f de
tail w
here
by ca
talyti
c pro
jects
are i
denti
fied,
there
has
been
a de
lay in
iden
tifying
the t
arge
ted n
umbe
r of p
rojec
ts.
Achie
ved:
293
307
311
317
14
Numb
er of
Neig
hbou
rhoo
d Dev
elopm
ent P
artne
rship
Gran
t pro
jects
unde
r con
struc
tion
40
Targ
et:
10
20
30
40
CD: N
DP U
nit
Munic
ipal re
ports
su
bmitte
d to N
T
42 D
evelo
pmen
t Par
tnersh
ip Gr
ant p
rojec
ts un
der
cons
tructi
on ac
hieve
d. De
viatio
n 2 N
DPG
proje
cts un
der c
onstr
uctio
n. Du
e to t
he na
ture a
nd
scale
of pr
ojects
in th
e 18 u
rban
mun
icipa
lities
, ther
e are
mu
ltiple
multi-
year
capit
al pr
ojects
. In ad
dition
new
catal
ytic
proje
cts in
prec
incts
have
been
appr
oved
to pr
ocee
d to
cons
tructi
on. H
ence
, ther
e are
both
new
proje
cts an
d pr
ojects
on th
e gro
und.
In the
curre
nt fin
ancia
l yea
r, the
re
are a
n add
itiona
l two p
rojec
ts.
Achie
ved:
83
11
21
21
Pa
ge
| 1
52
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
15
Estim
ated N
eighb
ourh
ood D
evelo
pmen
t Pro
gram
me th
ird-p
arty
inves
tmen
t leve
rage
d (cu
mulat
ive)
R2
500 m
illion
Targ
et:
R2 50
0 milli
on
CD: N
DP U
nit
Munic
ipal re
ports
su
bmitte
d to N
T
R2 49
4 milli
on th
ird-p
arty
inves
tmen
t leve
rage
d. R
6 milli
on. L
ever
age i
s esti
mated
. It is
only
track
ed an
d re
porte
d by m
unici
paliti
es th
roug
h the
Unit
’s Ma
nage
ment
Infor
matio
n Sys
tem. T
his is
a be
st eff
ort e
stima
te.
Achie
ved:
No ch
ange
in
lever
age
R2 12
8 milli
on
R2 20
3 milli
on
R2 49
4 milli
on
16
Numb
er of
spati
al tra
nsfor
matio
n zon
es id
entifi
ed in
partic
ipatin
g mun
icipa
lities
(per
year
)
12
Targ
et:
2 5
- 5
CD: P
LGI
Munic
ipal B
uilt
Envir
onme
nt Pl
ans
Metro
polita
n mun
icipa
lities
have
subm
itted t
heir c
ounc
il ap
prov
ed bu
ilt en
viron
ment
perfo
rman
ce pl
ans f
or th
e 20
14/15
year
. Acro
ss th
e 8 B
uilt E
nviro
nmen
t Per
forma
nce
Plan
s, 14
integ
ratio
n zon
es w
ere
identi
fied a
s prio
ritise
d ar
eas f
or sp
atiall
y tar
getin
g both
publi
c and
priva
te se
ctor
inves
tmen
t.
Achie
ved:
None
: ann
ual ta
rget
14
17
Numb
er of
proje
cts w
ithin
identi
fied i
ntegr
ation
zone
s ide
ntifie
d for
plan
ning (
per y
ear)
8
Targ
et:
2 2
4 -
CD: P
LGI
Munic
ipal B
uilt
Envir
onme
nt Pl
ans
12 pr
ojects
wer
e ide
ntifie
d in Q
uarte
r 2 fo
r plan
ning a
nd ar
e cu
rrentl
y in d
iffere
nt sta
ges o
f plan
ning.
Achie
ved:
None
12
18
Numb
er of
integ
rated
city
deve
lopme
nt pr
ojects
unde
r imple
menta
tion
2
Targ
et:
2 CD
: PLG
I Mu
nicipa
l Buil
t En
viron
ment
Plan
s 3 i
ntegr
ated c
atalyt
ic pr
ojects
are c
urre
ntly u
nder
im
pleme
ntatio
n in t
he in
tegra
tion z
ones
. Ac
hieve
d: -
3
Subp
rogr
amm
e: G
autra
in L
oan
19
Lo
an re
paid
Re
paym
ents
made
as
due
Targ
et:
Repa
ymen
ts ma
de as
due
ALM
Divis
ion re
cord
s Pa
ymen
t don
e acc
ordin
g to t
arge
t R1
551 m
, mad
e up o
f R84
0 m ca
pital
and R
711 m
inter
est
was p
aid in
Apr
il. Ac
hieve
d: Ins
talme
nt of
R1 55
1 milli
on, m
ade u
p of R
840 m
illion
capit
al an
d R71
1 milli
on in
teres
t wa
s paid
in A
pril
Subp
rogr
amm
e: E
mpl
oym
ent C
reat
ion
Facil
itatio
n
20
Numb
er of
proje
cts ap
prov
ed
20
new
proje
cts
appr
oved
Targ
et:
20 ne
w pr
ojects
JF
Inve
stmen
t Co
mmitte
e minu
tes
The d
elay e
xper
ience
d by D
BSA
in co
ntrac
ting t
he 3
rd C
FP
proje
cts im
plied
that
there
was
no ca
pacit
y to o
pen a
new
gene
ral fu
nding
roun
d, the
refor
e the
antic
ipated
addit
ional
20 ne
w pr
ojects
, did
not m
ateria
lise.
A sc
ale-u
p fun
ding
roun
d for
exist
ing Jo
bs F
und P
artne
rs wa
s ope
ned i
n Ac
hieve
d: 2
Pa
ge
| 1
53
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
Octob
er 20
14 an
d this
yield
ed 2
new
proje
cts. C
umula
tive
(ince
ption
to da
te) nu
mber
of pr
ojects
appr
oved
is 89
21
Va
lue of
gran
t fund
ing ap
prov
ed (c
umula
tive)
R1
155 m
illion
Targ
et:
R1 15
5 milli
on
JF In
vestm
ent
Comm
ittee m
inutes
R1 5
71 m
illion
fund
ing w
as a
ppro
ved
in the
cur
rent
year
. Th
e gra
nt fun
ding t
arge
t was
infor
med
by th
e an
ticipa
ted 20
ad
dition
al pr
ojects
that
a ne
w fun
ding
roun
d wo
uld y
ield,
thus
the a
chiev
ed a
moun
t for
the
app
rove
d tw
o ne
w pr
ojects
is m
uch
less.
Cumu
lative
(inc
eptio
n to
date)
gra
nt fun
ds ap
prov
ed: R
4 661
bn.
Achie
ved:
R1
57 18
1 milli
on
21a
Valu
e of m
atche
d fun
ding
R1
000 m
illion
Targ
et:
R1 00
0 milli
on
JF In
vestm
ent
Comm
ittee m
inutes
The
curre
nt ye
ar v
alue
of fun
ding
match
ed a
moun
ted to
R3
587
milli
on. T
he p
otenti
al ma
tched
fund
ing le
vera
ged
from
the 2
new
app
rove
d pr
ojects
is le
ss th
an a
nticip
ated
if the
Job
s Fu
nd P
MU h
ad b
een
able
to ap
prov
e 20
new
pr
ojects
. Cu
mulat
ive
(ince
ption
to
date)
pla
nned
co
ntribu
tions
to
be l
ever
aged
fro
m the
por
tfolio
of
89
proje
cts is
R6,
823b
n.
Achie
ved:
R358
.795 m
illion
22
Numb
er of
new
jobs c
ontra
cted
30
000
Targ
et:
5 000
5 0
00
10 00
0 10
000
JF P
MU M
onito
ring
reco
rds
The
chan
ge in
the
forma
t of r
epor
ting
(i.e. r
ecor
ding
only
annu
al, n
ot cu
mulat
ive, p
erfor
manc
e) h
as le
d to
reco
rding
ou
r per
forma
nce
differ
ently
. The
two
new
appr
oved
proje
cts
will
not y
ield
new
jobs,
i.e. j
obs
that d
id no
t exis
t befo
re.
Howe
ver
cumu
lative
ly (in
cepti
on t
o da
te) t
he F
und
has
contr
acted
for 1
32 72
5 new
perm
anen
t jobs
again
st a t
arge
t of
150 0
00.
Achie
ved:
0 0
0 0
22a
Numb
er of
new
place
ments
contr
acted
7 0
00
Targ
et:
1 000
1 0
00
2 000
3 0
00
JF P
MU M
onito
ring
reco
rds
Numb
er of
NEW
Plac
emen
ts is
30 35
7 plac
emen
t con
tracts
Th
e tw
o ne
w ap
prov
ed p
rojec
ts ha
ve b
een
contr
acted
to
deliv
er 3
0 357
plac
emen
ts. T
his w
as m
ore
than
antic
ipated
. Cu
mulat
ively
(ince
ption
to da
te) th
e Fun
d has
contr
acted
for
84 51
3 plac
emen
ts.
Achie
ved:
None
1 0
00
2 386
30
357
22b
Num
ber o
f train
ing pl
acem
ents
contr
acted
11
915
Targ
et:
3 000
4 0
00
3 000
1 9
15
JF P
MU M
onito
ring
reco
rds
42 95
7 NEW
train
ing pl
acem
ents:
Th
e two
new
proje
cts ha
ve a
cont
racte
d tar
get o
f 42 9
57,
more
than
origi
nally
antic
ipated
. This
is be
caus
e it c
anno
t Ac
hieve
d: No
ne
4 000
5 3
26
42 95
7
Pa
ge
| 1
54
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
be kn
own u
pfron
t wha
t type
of pr
oject
appli
catio
ns w
ill be
re
ceive
d, or
whic
h app
licati
ons w
ill be
appr
oved
by th
e Inv
estm
ent C
ommi
ttee.
Cumu
lative
ly (in
cepti
on to
date)
the
Fund
has c
ontra
cted f
or 20
4 566
train
ing op
portu
nities
. 23
Va
lue of
gran
t fund
ing di
sbur
sed (
in-ye
ar)
R1
300 m
illion
Ta
rget:
R2
00 m
illion
R2
00 m
illion
R3
00 m
illion
R6
00 m
illion
JF
PMU
reco
rds
Total
gran
t fund
s disb
urse
d for
the y
ear a
moun
ted to
R1
.504 b
illion
The
varia
nce i
s due
to sp
ecial
initia
tives
un
derta
ken t
o red
uce t
he di
sbur
seme
nt ba
cklog
Ac
hieve
d: R2
98.15
4 milli
on
R216
.005 m
illion
R3
21.57
6 milli
on
R668
662 m
illion
24
Jobs
Fun
d eva
luatio
n rep
orts
docu
mente
d and
lear
ning o
n effe
ctive
appr
oach
es to
job c
reati
on di
ssem
inated
Two c
ompa
rativ
e an
alysis
stud
ies
One l
earn
ing fo
rum
Ta
rget:
Co
mpar
ative
An
alysis
on w
ork-
seek
ers p
rojec
ts
Comp
arati
ve
analy
sis on
En
terpr
ise
Deve
lopme
nt pr
ojects
One l
earn
ing fo
rum
Ne
wslet
ter
publi
shed
JF P
MU re
cord
s Se
cond
news
letter
to be
publi
shed
durin
g Apr
il 201
5. Jo
bs
Fund
artic
les pu
blish
ed in
Pro
gram
me 8
News
letter
pr
esen
ted to
Par
liame
nt in
March
2015
.
Ac
hieve
d: Re
view
has b
een
comp
leted
Re
view
has b
een
comp
leted
Le
arnin
g for
um he
ld on
1 Se
pt 20
14
2nd n
ewsle
tter t
o be
publi
shed
durin
g Ap
ril 20
15
Jobs
Fun
d new
s as
part
of Pr
ogra
mme
8 pam
phlet
and
GTAC
news
letter
pu
blish
ed
25
Emplo
ymen
t, inc
ome d
istrib
ution
and i
nclus
ive gr
owth
rese
arch
proje
ct (R
EDI3x
3)
10–1
5 res
earch
pa
pers
contr
acted
; 4
works
hops
and 1
po
licy c
onfer
ence
Targ
et:
1 wor
ksho
p 1 w
orks
hop
1 poli
cy co
nfere
nce
1 wor
ksho
p 1 w
orks
hop
SALD
RU pr
oject
reco
rds a
nd m
inutes
of
REDI
3x3 s
teerin
g co
mmitte
e
Wor
ksho
ps w
ere h
eld on
the i
nform
al se
ctor a
nd in
clusiv
e gr
owth.
Achie
ved:
A wo
rksho
p on t
he
infor
mal s
ector
was
ho
sted i
n Jun
e at
UCT
Polic
y con
feren
ce
postp
oned
Inc
lusive
grow
th wo
rksho
p held
in
Nove
mber
2014
2nd w
orks
hop o
n the
infor
mal s
ector
he
ld in
March
2015
Pa
ge
| 1
55
Perfo
rman
ce in
dica
tor
Qu
arte
rly ta
rget
s and
out
puts
achi
eved
Re
fere
nce/s
ourc
e Ex
plan
atio
n no
te
and
varia
nce
An
nual
targ
et
Q1
Q2
Q3
Q4
Subp
rogr
amm
e: In
frast
ruct
ure D
evelo
pmen
t Sup
port
26
Numb
er of
tech
nical
assis
tants
deplo
yed i
n par
ticipa
ting d
epar
tmen
ts to
supp
ort th
e dev
elopm
ent o
f cap
acity
in lin
e with
the
IDMS
31
tech
nical
assis
tants
in pr
ovinc
ial
depa
rtmen
ts
Targ
et:
10
21 (n
ew)
Ongo
ing m
onito
ring
and r
epor
ting
Ongo
ing m
onito
ring
and r
epor
ting
CD: P
LGI
TA co
ntrac
ts an
d re
ports
Out o
f the a
nnua
l targ
et of
31 te
chnic
al as
sistan
ts de
ploye
d a to
tal of
14 w
ere p
rocu
red.
Th
e rem
ainde
r wer
e not
proc
ured
and d
eploy
ed du
e to
the fin
aliza
tion o
f the p
lannin
g and
desig
n for
IDIP
Ph
ase I
V.
Ac
hieve
d: No
ne
9 2
3
27
Numb
er of
offic
ials t
raine
d on t
he In
frastr
uctur
e Deli
very
Mana
geme
nt (ID
M) T
oolki
t to su
ppor
t impr
oved
infra
struc
ture d
elive
ry in
prov
inces
15
0 gov
ernm
ent
offici
als tr
ained
on th
e ID
M too
lkit
Targ
et:
150
CD: P
LGI
Train
ing re
ports
and
atten
danc
e reg
ister
s
340 o
fficial
s tra
ined.
This
traini
ng is
dema
nd dr
iven a
nd
prov
incial
dema
nd ex
ceed
ed th
e tar
get w
ith a
posit
ive
varia
nce o
f 190
. Ac
hieve
d: 34
0
28
Numb
er of
grad
uates
train
ed (in
train
ing) in
line w
ith th
e rele
vant
statut
ory b
ody r
equir
emen
ts in
engin
eerin
g, tow
n plan
ning,
geog
raph
ic inf
orma
tion s
ystem
s and
proje
ct ma
nage
ment
35
0 gra
duate
s tra
ined
(in tr
aining
)
Targ
et:
350
CD: P
LGI
Munic
ipal re
ports
to
NT
The a
nnua
l targ
et is
350,
howe
ver;
munic
ipaliti
es re
cruite
d a t
otal o
f 424
grad
uates
. Th
e num
ber o
f gra
duate
s dec
reas
ed fr
om 43
6 to 4
24 as
so
me w
ere i
napp
ropr
iately
plac
ed on
the p
rogr
amme
and
some
resig
ned,
thus l
eadin
g to a
posit
ive va
rianc
e of 7
4.
Achie
ved:
424
P a g e | 156
ANNEXURE 2: ABBREVIATIONS CSP Concentrated solar power FET Further education and training FMCMM Financial Management Capability Maturity Model FMPPI Framework for managing programme performance information GTAC Government Technical Advisory Centre IDMS Infrastructure delivery management system IPP Independent power producer IPPPP Independent Power Producer Procurement Programme MAFISA Micro Agriculture Finance Institutions of South Africa MFIP Municipal Finance Improvement Programme MoU Memorandum of understanding PPP Public-private partnership PRASA Passenger Rail Agency of South Africa PV Photovoltaic REIPPPP Renewable Energy Independent Power Producer Procurement Programme SANBI South African National Biodiversity Institute SIP Strategic Integrated Project
P a g e | 157