S.No Description Qty Unit Specification Remarks 1 Ventilation Air and Exhaust Flue Gas System Air Intake Filter Housing 3 Nos Paint Coated Supply & Installation Air Intake Filter sets 3 Nos Filtration Class G3 Supply & Installation Air Intake Ducting 3 Nos As Per GEJ Recommendation Supply & Installation Exhaust Silencer Structure 3 Lot MS Structure Supply & Installation Exhaust Silencer Condensate Piping 3 Lot Supply & Installation Engine Exhaust Piping 3 Lot Supply & Installation Exhaust piping insulation with GI cladding 3 Lot Supply & Installation 2 Cooling Water System Cooling tower 2 Nos 225 USRt Cooling water header 3 Lot Seamless ASTM A106, Sch 40 Supply & Installation Piping for genset's LT circuit 3 Lot Seamless ASTM A106, Sch 40 Supply & Installation Piping for genset's HT circuit 3 Lot Seamless ASTM A106, Sch 40 Supply & Installation Expansion tanks piping 3 Lot GI piping with fitting Supply & Installation Water charging pump 1 Nos Supply & Installation A-OES Scope of Supply Power generation system

Transcript of annex a

S.No Description Qty Unit Specification Remarks

1Ventilation Air and Exhaust

Flue Gas System

Air Intake Filter Housing 3 Nos Paint Coated Supply & Installation

Air Intake Filter sets 3 Nos Filtration Class G3 Supply & Installation

Air Intake Ducting 3 NosAs Per GEJ

Recommendation Supply & Installation

Exhaust Silencer Structure 3 Lot MS Structure Supply & Installation

Exhaust Silencer CondensatePiping 3 Lot Supply & Installation

Engine Exhaust Piping 3 Lot Supply & Installation

Exhaust piping insulation withGI cladding 3 Lot Supply & Installation

2 Cooling Water System

Cooling tower 2 Nos 225 USRt

Cooling water header 3 LotSeamless

ASTM A106, Sch 40 Supply & Installation

Piping for genset's LT circuit 3 LotSeamless

ASTM A106, Sch 40 Supply & Installation

Piping for genset's HT circuit 3 LotSeamless

ASTM A106, Sch 40 Supply & Installation

Expansion tanks piping 3 LotGI piping with

fitting Supply & Installation

Water charging pump 1 Nos Supply & Installation

A-OES Scope of Supply

Power generation system

S.No Description Qty Unit Specification Remarks

3 Lube Oil System Nos

Lube oil filling and overflowlines 3 Lot

Seamless Sch 40,A106 Supply & Installation

Dirty oil drain line 3 LotSeamless Sch 40,

A106 Supply & Installation

Lube oil filling line to genset 3 NoSeamless Sch 40,

A106 / A53 Supply & Installation

4 Fuel System

Gas supply line up to gasstreet 3 Lot

with in powerhouse Supply & Installation

Paint work on piping 3 Jobwith in power

house

Valves & Fittings 3 Lotwith in power

house Supply & Installation

Piping Supports 3 Lotwith in power

house Supply & Installation

5 Electrical

LV Incoming power panel 3 Nos Supply & Installation

MCC Panel 1 NoFor auxiliaries of

genset Supply & Installation

Body Earth, Auxiliary andControl cables 3 Lot

Within OES BatteryLimit

Earth point with Material &cable will be provided by SSD

Electrical installation material 3 Lot Cable trays Supply & Installation

S.No Description Qty Unit Specification Remarks

6 Documentation

General arrangement layout 1 Job As per scope

Cable trench and cablerouting drawings Job Nos As per scope

Operation Philosophy Job Nos As per scope

P &ID 1 Job As per scope

Complete Project Schedule 1 Job As per scope

Project Schedule Job Nos As per scope

Project Submittals 1 Job As per scope

Wiring diagrams Job Nos As per scope

7 Shipping and Transportation

Transportation of localauxiliary items to site withtransportation insurance

1 Job As per scope

Lifting, unloading, rigging andplacement at designated

place1 Job As per scope

Flushing, Hydrotesting andRecharging 1 Job

With in 01 meter ofOES battery limits As per scope

NOTE:1. Protection setting & other signals will be identified by OES