Annex 1 to Initial Environmental Examination (IEE)€¦ · Accelerated Rural Electrification...
Transcript of Annex 1 to Initial Environmental Examination (IEE)€¦ · Accelerated Rural Electrification...
-
Accelerated Rural Electrification Project (RRP MYA 53223)
Annex 1 to Initial Environmental Examination (IEE)
Environmental Management Plan Document Stage: Draft August 2020
Republic of the Union of Myanmar: Accelerated Rural Electrification Project
Prepared by the Ministry of Electricity and Energy, Government of The Republic of the Union of Myanmar for the Asian Development Bank. This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
-
Accelerated Rural Electrification Project (RRP MYA 53223)
Contents
A. Introduction 1 B. Mitigation and Monitoring Plan 1 C. Institutional Arrangements and Implementation Responsibilities 1 D. Monitoring and Reporting Procedures 3 E. Training and Capacity Building 6 F. Information Disclosure, Consultation and Participation 8 G. Project GRM 9 H. Mechanisms for Feedback and Adjustment 11 I. Cost Estimates 12 PART I 15 Environmental Management Plan 22 Environmental Monitoring Plans (EMOP) 58 Part II 79 Part III 82
List of Tables
Table 1. Safeguards Implementation Responsibility Table 2.1. Design and Pre-Construction Table 2.2. Activities Prior to Mobilization On-Site Table 2.3. Construction and Operation – New Substations, Extension Works, Access Roads Table 2.4. Construction and Operation – New Distribution Lines, Temporary Access Tracks Table 3.1. Design and Pre-Construction Table 3.2. Activities Prior to Mobilization on Site Table 3.3. Construction and Operation – New Substations, Extension Works, Access Roads Table 3.4. Construction and Operation – New Distribution Lines, Temporary Access Tracks Table 4.1. Ambient Air Quality Standards of Myanmar Table 4.2. NEQEG Limits for Site Runoff and Wastewater Discharges (Construction Phase) Table 4.3. NEQEG Effluent Limits Applicable to Electric Power Transmission and Distribution (Operation Phase) Table 4.4. NEQEG Allowable Noise Levels Table 4.5. NEQEG Exposure Limits to Electric and Magnetic Fields
-
A. Introduction 1. This Environmental Management Plan (EMP) identifies the potential environmental impacts and defines mitigation measures and monitoring requirements for the design and pre-construction, construction, and operation stages of the project. It also defines the institutional arrangements, roles and responsibilities of institutions involved and cost estimates for implementation of the EMP. The EMP will ensure environmental protection activities during all stages of the project implementation to prevent, reduce or mitigate adverse environmental impacts and risks. The EMP draws on the findings of the project initial environmental examination (IEE) report and discussions and agreements with Electricity Supply Enterprise (ESE) and the Asian Development Bank (ADB). 2. This EMP is based on preliminary design as of April 2020. Detailed engineering designs are yet to be finalized and may require subsequent revisions to this EMP. The ESE will provide the detailed designs to ADB for review to determine if the EMP requires revision. The draft and final EMP will be disclosed on the ADB public website (https://www.adb.org/) and included in the project administration manual (PAM). The final EMP will be included as a separate annexure in all bidding, tender and contract documents. The contractors1 will be informed of their obligations to implement the EMP and to include EMP implementation costs in their bids for project works that will include new construction of substations, 66kV and 33 kV distribution lines and extension works on existing substations. 3. The project involves the procurement of four (4) plants – design, supply, and installation contract packages consisting of three (3) packages for substations and one (1) package for the distribution automation system (DAS); and two (2) goods contracts for conductors and hardware, which will be undertaken through OCB with international advertisement. One (1) goods contract with 3 lots for the supply of concrete poles and seven (7) line installation works contracts with 26 lots will be undertaken through OCB with national advertisement).2
B. Mitigation and Monitoring Plan
4. This EMP covers the project area of influence and consists of three components: (i) project readiness checks for effective environmental management during design and pre-construction stage and environmental mitigation measures during construction and operation stage; and (ii) environmental monitoring measures during all stages of project implementation. C. Institutional Arrangements and Implementation Responsibilities 5. Executing Agency. The Government Ministry of Electricity and Energy (MOEE) will be the executing agency (EA) responsible for overall supervision and monitoring of project implementation and compliance with loan and grant assurances and the ESE under MOEE will be the implementing agency (IA). 6. Project Management Unit. The ESE will establish the project management unit (PMU). The PMU will have the responsibility to supervise and oversee compliance with (i) environmental
1 Contractors imply = Engineering Procurement, Construction (EPC) contractors, any key sub-contractors, and facility operators (Note: EMP implementation during operation stage will continue through the Project Implementation Units (PIUs) and for extension works at existing 230kV substations through the Department of Power Transmission and Supply Control (DPTSC) that is the facility operator 230 kV substations in Myanmar). 2 Project Administration Manual (PAM) for AREP, June 2020
-
2
safeguards requirements, (ii) coordinate the project Grievance Redress Mechanism (GRM), (iii) coordinate with line ministries to ensure smooth implementation of the project3, (iv) engage the project implementation consultancy (PIC) services, (v) supervise the procurement process, and (vi) report to the ADB. In particular, the PMU will ensure consistency of safeguards documents with government policy, legal and administrative framework across all jurisdictions – national, state and local level. To ensure effective implementation of environmental safeguards procedures, the PMU will assign one staff person as an environment & social manager and two staff persons as environment and social officers, on full time basis. 7. Project Implementation Units. The PMU will set up four Project Implementation Units (PIUs) at each Region / State ESE office. The PMU will assign to each PIU at least one full time staff person to handle environment & social safeguards implementation and serve as focal point persons on the field (PIU E&S focal point person); the PIUs will be responsible for day to day activity and compliance with safeguards during project implementation in the field including engaging in project GRM, information disclosure and meaningful consultations. 8. Project Implementation Consultant Services. PIC services will be engaged to assist PMU and PIUs with the implementation of the project, EMP and oversight of the contractors. At the end of PIC services contract, PMU will be responsible for ensuring compliance with safeguards. 9. The PIC will: (a) update, as necessary, the IEE, EMP, Resettlement and Ethnic Group Development Plan (REGDP), and, after obtaining ADB’s approval, oversee their implementation; (b) work and coordinate with contractors to develop and finalize package-specific site EMPs (SEMPs), and after obtaining approval of PMU, oversee their implementation; (c) conduct Environmental, Health and Safety (EHS) audit of existing substation that will undergo extension works; (d) supervise the design, supply, installation, and commissioning of the electricity distribution infrastructure; and (e) assist PMU, PIUs and contractors with compliance to ADB SPS requirements including handling complaints and/or grievances filed through the project GRM, if any. 10. The PIC will also be responsible for building ESE’s capacity in financial management, contract administration, safeguards monitoring and reporting. 11. In addition, PIC will assist the PMU and PIUs in coordination activities with relevant government agencies and local authorities on permits and clearances and compliance with relevant national regulatory requirements. The PIC will also assist the PMU, PIUs and contractors in conducting project level COVID-19 risk assessment as well as conduct random checks / audits of contractor’s EHS performance. PIC will ensure that the contractor’s Occupational Health and Safety (OHS) plans integrate measures to mitigate COVID-19 health risks that are aligned with government guidelines and measures listed in Part III of this Annexure.4,5 12. The PIC will work with ESE to prepare and submit the domestic IEE or EMP to the Environmental Conservation Department (ECD) or the Ministry of Natural Resources and
3 The PMU will ensure that subproject activities are synchronized between the REGDP and EMP implementation. The PMU will also ensure that no physical or economic displacement of affected persons (APs) will occur until: (i) compensation at full replacement cost has been paid to each affected person for subproject or sections of subprojects that are ready to be constructed; and (ii) other entitlements listed in the REGDP are provided to the APs. . 4 National guidance on Covid-19 is issued by the Ministry of Health and Sports (MOHS); web-link: https://www.mohs.gov.mm/ 5 The contractor’s OHS plans will be reviewed by PIC in consultation with public health inspectors of the area, local medical officers and other relevant health specialists; with a recommendation forwarded to the EA and IA for clearance.
-
3
Environmental Conservation (MONREC) for clearance and approval, as required, prior to any civil works contract awards. 13. International and national environmental specialists will support PMU for a total of forty-eight (48) person-months over a 72-month project implementation period.
Positions Number Person–Months International Environment Specialist 1 12 National Environment Specialist 2 36
Total 48
14. Contractors. All contractors will be responsible for implementing the mitigation measures during construction and operation under the direct supervision of the PIC and PIUs and overall supervision of the PMU. To ensure that the contractors comply with the EMP provisions, the PMU will ensure that the safeguards requirements are included in all bids, contracts and tender documents including the provision to apply penalties in case non-compliances to safeguards are encountered repeatedly. 15. Each contractor will be required to work with PIC to finalize package-specific site Environmental Management Plan (SEMP) during construction, appoint a C-EHS focal point person within its staff on full time basis and submit monthly progress reports on the implementation of the site SEMP/EMP. Contractors will integrate COVID-19 health risk mitigation in their OHS plans. Contractors will also engage in project GRM and appoint a C-GRM focal point person within its staff on full time basis and will be required to regularly co-ordinate with affected persons (APs), households, General Administration Department (GAD), and village leaders to provide up to date information on project activities and address any issues that arise during subproject implementation during construction stage. The PIC will assist contractors / facility operators / PIUs in developing and implementing the Standard Operation & Maintenance Plans (SOMPs) during operation stage. The PIUs / facility operators will be required to regularly co-ordinate with APs/ households, GAD, and village leaders to provide up to date information on project activities and address any issues that arise during subproject implementation during operation stage.
D. Monitoring and Reporting Procedures
16. The PMU will be responsible for safeguards reporting. The PIUs, assisted by the PIC, will conduct monitoring for each subproject and provide the environment input based on site visits, compliance checks and prepare the subproject Quarterly Progress Reports (QPRs) for submission to the PMU; the PMU will verify the information and submit the project QPRs to ADB.6 The PIC will support the PMU to use the information from the project QPRs and prepare a safeguards monitoring report (template enclosed as Appendix 7 of IEE) for submission to ADB semi-annually during construction stage and annually during operation stage. The safeguards monitoring reports will be publicly disclosed on the ADB website. Reporting to ADB will continue until project completion report is issued. 17. The PIUs will be responsible for safeguards monitoring. The PIUs, assisted by PIC, will coordinate and interact with the PMU on compliance to ADB safeguards requirements and with
6 Initially the safeguards reporting will be via the project QPRs.
-
4
relevant government agencies and local authorities on permits and clearances and national environmental requirements, update and finalize the IEE and EMP as needed. 18. The PIC will assist the PMU, PIUs and contractors 7 in handling complaints and/or grievances filed through the project GRM, if any. The PIC will oversee three types of project monitoring conducted under the EMP.
(i) Project readiness monitoring. To be conducted by the PMU with assistance of PIC
(see Project Readiness Checklist); (ii) Environmental monitoring. To be conducted by the PIUs and contractors, assisted
by PIC, across all stages of project implementation as described in the EMP and assessing compliance with applicable Myanmar environmental quality standards (This is provided in Part II of this EMP); and
(iii) Compliance monitoring. To be conducted by the PMU, assisted by PIC to verify
EMP mitigation and monitoring compliance during project implementation, including random checks / audits of contractor’s EHS performance.
19. During construction, the contractor(s) will submit monthly progress reports to the PIUs on site SEMP/ EMP implementation which will inform the project QPR and semi-annual safeguard monitoring reports. The contractor monthly progress reports will include compilation of daily monitoring sheets (that will be prepared for use by PIC) that is duly signed by the PIU E&S focal point person. 20. During operation, the facility operator/ contractor will also submit monthly progress reports to PIUs for the first year of operation and quarterly progress reports thereafter. These will inform the annual safeguard monitoring reports. 21. ADB will oversee subproject compliance based on the subproject QPRs and semi-annual and annual monitoring reports provided by the PMU and site visits (generally one to two times per year). For any non-compliance, ADB will make suitable recommendations for undertaking remedial measures for mid-term correction and improvement, if required. ADB’s monitoring and supervision activities are carried out on an on-going basis until a project completion report is completed.
Project Readiness Checklist
S. No Indicator8 Criteria Assessment
1
IEE and EMP update IEE and EMP updated after technical detail engineering
design and approved by ADB
Yes No
2 Compliance with loan covenants
The borrower complies with loan covenants related to project design and environmental management planning, including ensuring IEE and EMP is updated before award of contracts
Yes No
7 Contractors imply = Engineering Procurement, Construction (EPC) contractors, any key sub-contractors, and facility operators. Note: EMP implementation during operation stage will continue through the PIUs and for extension works at existing 230kV substations through Department of Power Transmission and Supply Control (DPTSC) that is the facility operator 230 kV substations in Myanmar. 8 REGDP = Resettlement and Ethic Group Development Plan; SEMP = Site Environmental Management Plan; SOMP = Standard Operation & Maintenance Plan; GRM = Grievance Redress Mechanism.
-
5
S. No Indicator8 Criteria Assessment
3 Domestic environmental assessment
Domestic IEE / EMP prepared and submitted to ECD / MONREC for review and approval
Yes No
4 Implementation Set up
PIC services hired, including International and National Environmental and Social Safeguards Specialists
Yes No
5 Training and Capacity Building
Training and capacity building conducted for PMU, PIUs and contractors
Yes No
6
Public involvement effectiveness
Meaningful consultations completed Yes No
GRM established with entry points Yes No
Staff environment focal point person appointed by PIUs (PIU E&S focal point person) on full time basis
Yes No
Environment focal point appointed by each Contractor (C-EHS)
Yes No
GRM focal point appointed by each Contractor (C-GRM) Yes No
7 REGDP Land acquisition completed and compensation paid
Yes No
8 SEMP / SOMP
Package-specific site SEMP / SOMP prepared containing site maps with receptor information
Yes No
9 EHS audit
EHS audit for existing substations undergoing extension works completed
Yes No
10 Climate risk measures Climate risks integrated into final detailed engineering design
Yes No
11 Design Features for Environmental Impact Mitigation
Features integrated into final detailed engineering design (all infrastructure including any corrective measures from the EHS audit findings in design for existing substations)
Yes No
12 COVID-19 risk measures
COVID-19 risk mitigation measures integrated into project planning
Yes No
13 Chance find procedures for PCRs
Identification of sensitive periods conducted Ocular inspection/ Transect survey Chance Find Procedures established for PCRs
Yes No
14 Environmental Baseline Surveys
TOR prepared for recruitment of third- party monitoring contractor
Monitoring conducted, findings and recommendations shared
Yes No Yes No
15 Bidding documents and contracts with environmental safeguards
Bidding documents and contracts incorporating the project EMP as loan assurance
Yes No
16 Permits, Clearances, Approvals
Permits, Clearances, Approvals obtained Yes No
17 EMP financial support
The required funds have been set aside for EMP implementation
Yes No
18 PIB prepared for dissemination
PIB in local language prepared with project information and key contact information including GRM focal point person contacts
Yes No
-
6
E. Training and Capacity Building 22. The capacity of PMU, PIUs and contractors’ staff responsible for EMP implementation, GRM and supervision, monitoring and reporting will be strengthened through appointment of dedicated and trained officers at the PMU and focal point persons at the PIUs as well as ensuring appointment of contractors C-EHS and C-GRM focal point persons; refer to discussion under Institutional and implementation responsibilities. 23. The PMU, PIUs and contractors will receive training in EMP and GRM implementation, site inspections, supervision, monitoring and reporting, conducting meaningful consultations, information disclosure, handling complaints / dispute resolution, as well as on the relevant environmental rules and regulations. Training will be facilitated by the PIC. In addition, orientation and briefing of project staff, all contractors / sub-contractors, hired workers will be conducted prior to mobilization on site during construction and operation stages.
-
T
rain
ing
an
d C
apac
ity
Bu
ildin
g P
lan
an
d C
ost
Est
imat
e
P
MU
= p
roje
ct m
anag
emen
t uni
t; P
IU =
pro
ject
impl
emen
tatio
n un
it; C
ontr
acto
rs =
EP
C c
ontr
acto
rs;
RE
DG
P =
Res
ettle
men
t and
Eth
ic D
evel
opm
ent P
lan;
IFC
(W
BG
) E
HS
=
Inte
rnat
iona
l Fin
ance
Cor
pora
tion
(Wor
ld B
ank
Gro
up)
Env
ironm
enta
l, H
ealth
and
Saf
ety
Fre
quen
cy:
PM
U, P
IUs,
Pro
ject
Sta
ff -
once
a y
ear
for
tota
l of 6
yea
rs
Pro
ject
Con
trac
tors
- 3
tim
es o
ver
tota
l 8
mon
ths
(6 m
onth
per
iod
of c
ivil
wor
ks a
nd 1
-2
mon
ths
of in
stal
latio
n of
equ
ipm
ent,
strin
ging
of c
ondu
ctor
s et
c)
Fac
ility
Ope
rato
rs -
2 ti
mes
per
yea
r fo
r to
tal o
f 3 y
ears
Tra
inin
gA
ttend
ees
Con
tent
Sch
edul
eP
erio
d (d
ay)
Fre
quen
cyN
o of
per
sons
Cos
t (U
SD
/per
son/
day)
Tot
al C
ost (
US
D)
AD
B S
PS
(20
09)
Mya
nmar
's r
elev
ant e
nviro
nmen
t,
heal
th a
nd s
afet
y la
ws,
reg
ulat
ions
and
polic
ies
WB
G E
HS
Gui
delin
es
Env
ironm
enta
l mon
itorin
g an
d
repo
rtin
g
Req
uire
men
ts fo
r in
form
atio
n
disc
losu
re, p
ublic
con
sulta
tion,
com
mun
ity a
war
enes
s pr
ogra
m
Soc
ial s
afeg
uard
req
uire
men
ts
(RE
GD
P)
Rol
es a
nd r
espo
nsib
ilitie
s an
d
Pro
cedu
res
Pro
ject
GR
M
Fac
ility
Ope
rato
rs
Ope
ratio
n S
tage
: Onc
e
prio
r to
sta
rt o
f
oper
atio
n
0.5
620
80
4,8
00
16,6
50
6
6,6
00
Tot
al
Tot
al a
cros
s ea
ch R
egio
n
Pro
ject
Con
trac
tors
-
Con
trac
tor
EH
S /
GR
M
Fie
ld S
taff)
Con
stru
ctio
n S
tage
:
Onc
e pr
ior
to s
tart
of
civi
l wor
ks
13
1050
1
,500
0.5
310
50
7
50
80
9,6
00
Sam
e as
abo
veE
nviro
nmen
tal
Aw
aren
ess,
Orie
ntat
ion
and
Brie
fing
on
Saf
egua
rds
Pro
ject
Con
trac
tors
-
Con
trac
tor
EH
S /
GR
M
Fie
ld S
taff)
Con
stru
ctio
n S
tage
:
Onc
e pr
ior
to
mob
ilizat
ion
on s
ite
durin
g co
nstr
uctio
n
EM
P
impl
emen
tatio
n
PM
U, P
IUs,
Pro
ject
Sta
ff
Des
ign
and
pre-
cons
truc
tion
stag
e:
once
dur
ing
desi
gn
and
pre-
cons
truc
tion
stag
e
16
20
-
F. Information Disclosure, Consultation and Participation
24. Consultation during design and pre-construction. Section 7 of the IEE describes the public consultations, information disclosure and participation activities carried out during project preparation. 25. Future Consultations. A detailed Consultation and Participation Plan will be prepared for the affected persons (APs) in the project area and other relevant stakeholders with schedule, location, invited participants, information to be disseminated and methods of consultation; this will be based on the project Stakeholder Communication Plan. An overview activity outline for a Consultation and Participation Plan is enclosed. Consultations with the APs will include dissemination of project information booklet (PIB) in Burmese. The PIB will include project information such as on project environmental impacts (positive and negative), safeguards measures including community health and safety, health & safety risks due to transmittable diseases (HIV/AIDs, COVID-19), training in emergency response (ERPs), project implementation schedule, results from environmental baseline surveys, land acquisition and compensation process as per REGDP), APs right to complain and the project GRM. The PID will also include the contact information including ESE website address, PMU, PIUs, PIC and contractors address and telephone number for focal point persons / local entry points e.g. C-EHS and G-GRM, GAD and village leaders. 26. Consultations with the APs will provide a two-way information-sharing channel, ensuring that the concerns, questions and ideas of the APs will be discussed and responded to in an appropriate and gender inclusive way. The PIUs, PIC and contractors will record all information dissemination and consultation activities and the results from consultations with the APs. The PIUs and PIC will also record how concerns raised and recommendations made are addressed in the updated IEE and EMP. Consultations will be supported and supervised by PMU. Consultations with APs, concerned stakeholders especially the affected communities, and households will continue throughout project implementation and will be open and gender inclusive. The updated IEE and EMP will be disclosed on ADB website as required by the ADB SPS 2009 and Access to Information Policy (September, 2018)9.
Activity Outline for Consultation and Participation Plan and Information Disclosure
Project Implementation Schedule
Activity Stakeholders
Detail design phase: Detailed Walkover Survey and once prior to construction
Public information meetings Informal meetings on subproject design for aligning people’s responses in detailed design Dissemination of PIB Community Awareness Program one month prior to civil works, including informal meetings for information updates on project schedule and activities through village leaders and GAD
Affected Persons (APs) Affected Households Villages, Village leaders, GAD
Civil works construction
Informal meetings for information updates on project schedule and activities through village leaders and GAD Public information meetings as needed Community Awareness Program once during civil works PIB made available at consultations, project field offices and GAD
9 https://www.adb.org/documents/access-information-policy
-
9
Project Implementation Schedule
Activity Stakeholders
Operation and Maintenance
PIB distributed to communities Informal meetings for information updates and concerns
G. Project GRM 27. A project specific GRM will be established as part of this EMP to receive and manage any public concerns, issues or grievances that may arise due to the project. The GRM comprises: (i) a set of clear procedures developed by the PMU to receive, record and address any concerns which are raised by affected stakeholders; and (ii) specific contact details for individuals at the PMU, PIUs and contractor level that serve as focal point persons for access to the GRM. 28. Composition and Area of Jurisdiction. The PMU will set up a Grievance Redress Committee (GRC) as soon as the project commences. GRC will function from construction to operation stage. The GRC will be established at two levels across the project area of influence where the subprojects will be implemented. 29. GRC at PIU level (ESE PIU Office at Region/State). As practiced, the GRC at PIU level will include local two representatives of affected person (AP), including a woman representative, one GAD person from the concerned township, contractor EHS and GRM focal point persons (C-EHS and C-GRM), one representative from concerned government line agencies (e.g. Revenue, Forest, etc.), PIU E&S focal point person PIC national environment and social specialists, project manager and project director PIU region office. 30. GRC at PMU Level (ESE PMU Office at Naypyitaw). GRC at PMU level will include one representative of PMU (E&S manager, officers), director, project implementation (ESE), director, civil (ESE), director, planning (ESE). 31. Responsibilities. The GRC is expected to: (i) resolve issues on dust, noise, vibration, construction related nuisances to APs, households or public; (ii) resolve issues on land acquisition (if any), compensation to temporary damages to crops, orchards, trees and other use of land such as temporary / permanent areas for distribution towers / poles and ROW; (iii) convene once a month to review complaints lodged (if any); (iv) record the grievances and resolve the issues within the stipulated time from the date the grievance was filed; and (v) report to the APs, households and public upon the status of grievance resolution and the decisions made or action taken. All contractors including contractor appointed GRM focal point persons ( C-EHS / C-GRM) and work staff will be briefed by the PIC on project GRM. 32. Procedures. The key contacts for the GRC will be included in the PIB for dissemination in the project area of influence and also posted at project field construction sites, field offices, construction (workers) camps and public notice boards in affected villages and townships in Burmese language. There are multiple entry points to the project GRM, including face-to-face meetings, written complaints, contractor information, anonymous drop-boxes for written comments, and/or e-mail. All concerns received will be treated confidentially and professionally. The identity of individuals will not be circulated among project agencies or staff and will only be shared with senior staff and then only when there is clear justification. The GRM will consist of the following steps of conflict resolution:
-
10
Step 1
33. At field level, the contractor can act as an entry point, where an AP / complainant can be presented to the contractor either verbally in person or in writing.10 The AP can also approach the contractor through the local GAD office or the village leader. The contractor will be obliged to provide immediate written receipt of the complaint and take it forward in a written format and share with the GRC at PIU level for record. The contractor assisted by PIC will resolve the issue with the AP / complainant within seven (7) days through direct negotiation, maintain the record of grievances received and redressed.
Step 2
34. If or when the AP / complainant is not satisfied with the action or decision of the contractor, the AP / complainant will take the issue to GRC at PIU level. In all cases, the grievances will be recorded in writing. The GRC at PIU level will have two (2) weeks to resolve the complaint through a hearing and negotiation and will be assisted by the PIC. If the issue is not handled within two (2) weeks, or if the complainant is not satisfied with the result, he/she can bring the issue to the GRC at PMU level. Note: the GRC at PIU level may forward or accelerate the case to GRC at PMU level if it cannot be redressed at GRC PIU level. The grievance redress process at GRC at PIU level is as follows:
o GRC at PIU level will review the filed complaint and prepare a Case File for GRC hearing and negotiation
o A formal GRC hearing will be held at a mutually agreeable date between GRC members and AP / complainant or representative
o On the date of the hearing, the AP / complainant or representative will appear to air the issue/ grievance / complainant
o All proceedings shall be recorded and documented o Final resolution issued by GRC at PIU level will be communicated to the AP /
complainant / representative Step 3 35. If the issue/complaint cannot be resolved in a way that is satisfactory to all parties, the GRC at PIU level will bring the issue to the GRC a PMU level. The GRC at PMU level will meet the AP / complainant / representative of AP and try to resolve the issue/ grievance. Within four (4) weeks of the submission of the complaint to the GRC, it has to take a decision and inform in written to the AP / complainant / representative of AP, GRC at PIU level of the decision. Step 4 36. If efforts to resolve disputes using the grievance procedures remain unresolved or unsatisfactory, AP / complainant have the right to directly discuss their concerns or problems with the ADB’s Environment, Natural Resources and Agriculture Division, Southeast Asia Department through the ADB Myanmar Resident Mission. If AP / complainant is still not satisfied with the responses of the Resident Mission, they can directly contact the ADB Office of the Special Project Facilitator. The Office of the Special Project Facilitator procedure can proceed based on the accountability mechanism11 in parallel with the project implementation.
10 If APs do not have sufficient writing skills or are unable to express their grievances verbally, it is a common practice that they are allowed to seek assistance from any recognized local NGO or other family members, village heads or community chiefs to have their complaints or grievances written for them. APs will be allowed to have access to the detail measurement survey or contract document to ensure that all the details have been recorded accurately enabling all parties to be treated fairly. Throughout the grievance redress process, the responsible GRC will ensure that the concerned APs are provided with copies of complaints and decisions or resolutions reached. 11 Weblink: https://www.adb.org/site/accountability-mechanism/main
-
11
37. Access to Country Legal System: The AP / complainant will avail the right to approach the judiciary or Courts directly if they like, without approaching the GRC.
38. GRC Recordkeeping and Reporting. The GRC at PMU level and PIU level will keep a record of all the grievances received including contact details of complainant, date the complaint was received, nature of grievance, agreed corrective actions, the date these were affected and the final outcome. Documentation of the grievances filed and resolved will be summarized, submitted to the PMU and reported in the project Quarterly Progress Reports (QPRs) and semi-annual safeguard reports during construction stage.
39. Disclosure of Information. Under the direction of the PMU, the PIUs with assistance from PIC will disseminate PIBs and also inform APs / complainants / representative of APs on grievance redress procedure, who to contact and when, where and how to file a grievance, time likely to be taken for redressal of minor and major grievances, etc. It will be made known that AP/ complainants are not charged any fee under project GRM. It is a good practice to provide the APs / complainants / representative of AP with transport facilities to the GRC hearings. Grievances received and responses provided will be documented and provided to APs / complainants / representative of APs during the process. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the project construction field offices, GAD, township offices (if required).
40. Review of the Process. The PMU will periodically review the implementation of the project GRM and record information on the effectiveness of the mechanism, especially on the project‘s ability to prevent and address grievances. 41. Moreover, ADB safeguards indicators include assessment of whether the project GRM is functioning effectively, indicators of a functioning GRM, include:
PMU provided a formal letter that confirms that the GRM has been established and is operational with a list of GRC committee members at each level including PMU and PIU focal point persons for GRM
The PIB has the GRM steps explained and GRM focal point person contact information and has been handed out to all APs, households and available at local GAD offices
Evidence of consultation/verbal dissemination of the project GRM to APs, households and public consultation (This could be shown through presentation materials, minutes of meetings, photos and attendance sheet)
Evidence of project signage within the community and at construction sites / camps with GRM focal point person contact information
GRM focal point persons mobilized and functioning in their role GRM record-keeping system is established and functioning Complaints and resolutions included in project QPR and semi-annual safeguards
monitoring reports. H. Mechanisms for Feedback and Adjustment 42. The EMP is a living document. The need to update and adjust the EMP will be reviewed during final project detailed engineering design or when there are design changes, changes in construction methods and program, unfavorable safeguards /environmental monitoring results or
-
12
inappropriate monitoring locations and ineffective or inadequate mitigation measures. Based on safeguards /environmental monitoring and reporting systems in place, the PMU (with the support of the PIUs and PIC) shall assess whether further mitigation measures are required as corrective action or improvement in environmental management practices are required. The PMU will inform ADB promptly on any changes to the project and needed adjustments to the EMP. The updated EMP will be submitted to ADB for review and approval and will be disclosed on the ADB project website. I. Cost Estimates 43. There are three types of mitigation measures and corresponding costs:
i. Measures that will permanently become part of the infrastructure such as permanent sanitary facilities, permanent (‘bunded’) impermeable surfaces, septic tanks, features for adverse environmental impact mitigation, climate risks, landscaping, hedge planting, permanent access roads to substation plots, road signage, perimeter fencing, detailed engineering measures for preventing soil erosion and/or localized flooding/ wildfires will be included in the main civil work contract costs and not double counted as part of EMP costs, estimated as USD$ 27.6 million or 16.8% of the total base cost.12
ii. Measures such as conducting environmental baseline surveys for surface water quality air quality and noise, developing SEMPs/SOMPs, training, EHS audit can be counted as part of the environmental (and social) impact mitigation; the total estimate is US$1.00 million or 1% of total project base cost. The indicative cost estimates are provided below.
iii. Measures during the construction stage (e.g., periodic watering for dust suppression, use of hand held portable air and noise monitoring devices, EMF measuring devices, quiet / low noise machinery and equipment, PPE, etc.) as well as measures to mitigate unforeseen impacts due to construction activities will need to be included in the tender documents to ensure that all contractors budget these items in their bids. Contractors will also bear all environmental monitoring costs during the operational stage.
iv. Information disclosure, developing PIB, project GRM related costs involved in resolving the complaints (meetings, consultations, communication and reporting/information dissemination) will be borne by the ESE.
v. Human resources for EMP support are part of the Project Implementation Consultation Services (PIC); the total estimate is US$6.99 million or 5% of total project base cost.
12 Source: Project Administration Manual, June 2020. The total project base cost is US $ 165.29 million; subject to change.
-
13
Saf
egu
ard
s Im
ple
men
tati
on
- C
ost
Est
imat
es
Item
Nu
mb
er
To
tal C
ost
(US
D)
So
urc
es o
f F
un
d
AH
um
an
Reso
urc
es f
or
EM
P S
up
po
rt
Inte
rnatio
nal E
nvironm
ent S
pecia
list, N
o. pers
so
n -
112 p
ers
on-m
onth
s (
spre
ad o
ver
entir
e p
roje
ct
imple
meta
tion
period o
f to
tal 7
2 m
onth
s)
2,1
6,0
00
Inte
rnatio
nal E
nvironm
ent S
pecia
list -
Tra
vel
Assum
es 6
vis
its, 14 d
ays p
er
vis
it (inclu
din
g
travel t
ime);
6 R
T @
1,5
00/R
T; 84 d
ays d
ays p
er
die
m@
$110 /day
18,2
40
Site
Vis
its / T
ransport
atio
n C
osts
for
Inte
rnatio
nal S
pecia
list
Assum
es 6
site
vis
its2,4
00
Natio
nal E
nvironm
ent S
pecia
list , N
o. pers
ons 2
18 p
ers
on m
onth
s e
ach o
r 36 p
ers
on m
onth
s tota
l
(spre
ad o
ver
entir
e p
roje
ct im
ple
menta
tion p
eriod
of 72 m
onth
s)
1,0
8,0
00
Site
Vis
its / T
ransport
atio
n C
osts
for
Natio
nal E
nvironm
ent
Specia
lists
Assum
es 2
0 s
ite v
isits
8,0
00
Sub-t
ota
l 3,5
2,6
40
Contin
gencie
s (
3%
)10,5
79
A. T
OT
AL
3,6
3,2
19
EM
P C
osts
B.1
Environm
enta
l monito
ring s
urv
ey to e
sta
blis
h b
aselin
e (
air,
nois
e, surf
ace w
ate
r)
All
subpro
jects
1,0
0,0
00
c/o
PIC
B.2
Tra
inin
g a
nd C
apacity
build
ing P
MU
, P
IUs a
nd P
roje
ct
Contr
acto
rs; O
rienta
tion o
f P
roje
ct S
taff a
nd C
ontr
acto
rs
All
subpro
jects
66,6
00
c/o
PIC
B.3
Pre
para
tion o
f S
ite s
pecifi
c E
MP
- S
EM
Ps / S
OM
P; E
HS
audit
All
subpro
jects
2,0
0,0
00
c/o
PIC
Sub-t
ota
l 3,6
6,6
00
Contin
gencie
s (
10%
)36,6
60
B. T
OT
AL
4,0
3,2
60
Part
of P
roje
ct
Imple
menta
tion
Cosulta
nt S
erv
ices
(PIC
)
3.0
%
see tab 2
lum
psum
S.N
oC
ost
per
Un
it
(US
D)
A.1
18,0
00 p
er
month
A.2
18,2
40
A.3
lum
psum
A.4
3,0
00 p
er
month
A.5
lum
psum
B.
lum
psum
10.0
%
-
14
Ite
mN
um
be
rT
ota
l C
os
t
(US
D)
So
urc
es
of
Fu
nd
Ad
min
str
ati
ve
Co
sts
, G
RM
, C
on
su
lta
tio
ns,
Su
rve
y
Pe
rmits
and A
ppro
va
lsA
ll s
ubp
roje
cts
19
,000
C.2
Pu
blic
co
ns
ulta
tion
s a
nd
Info
rmatio
n D
isclo
sure
All
subp
roje
cts
40
,000
C.3
GR
M im
ple
men
tatio
nA
ll s
ubp
roje
cts
40
,000
C.4
EM
F m
onito
ring
de
vic
eA
ll s
ubp
roje
cts
1,0
00
C.5
Su
rve
y o
f a
ffec
ted
tre
es
no
t co
ve
red
un
der
Entil
em
ent M
atr
ix
of R
EG
DP
e.g
. alo
ng
roa
d e
as
em
ents
All
subp
roje
cts
50
,000
Bo
rne
by
ES
E in
coo
rdin
atio
n w
ith th
e
Loc
al F
ore
st
De
part
me
nt
Sub-t
ota
l 1,5
0,0
00
Con
ting
en
cie
s (
5%
)7,5
00
C.
TO
TA
L1,5
7,5
00
DC
on
str
ucti
on
an
d O
pera
tio
n M
an
ag
em
en
t
D.1
En
vir
onm
en
tal m
onito
rin
g d
uring
civ
il w
ork
s a
nd o
nce
aft
er
com
ple
tion o
f c
ivil
wo
rks (
inclu
din
g e
qu
ipm
ent
suc
h a
s h
an
d-
held
nois
e m
ete
rs, air
qu
alit
y m
ea
suri
ng
de
vic
es
, E
MF
me
asu
rem
en
t d
evic
es)
and
PP
E
All
subp
roje
cts
1,0
0,0
00
Bo
rne
by
Co
ntr
acto
r
(inc
lud
ed
in c
on
tra
cto
r
cos
ts)
D.2
Imp
lem
enta
tion
of
SE
MP
/ S
OM
P s
uc
h a
s S
ite R
esto
ratio
n
Pla
n, S
pill
s R
ep
on
se P
lan, O
HS
Pla
n, E
RP
, C
om
mun
ity
He
alth
an
d S
afe
ty P
lan
, T
raffic
Co
ntr
ol P
lan,
etc
All
subp
roje
cts
2,5
0,0
00
Bo
rne
by
Co
ntr
acto
r
(inc
lud
ed
in c
on
tra
cto
r
cos
ts)
Subto
tal
3,5
0,0
00
Con
ting
en
cie
s (
5%
)17,5
00
D.
TO
TA
L3,6
7,5
00
GR
AN
D T
OT
AL
(A
+B
+C
+D
)12
,91,4
79
lum
psu
m
5.0
%
Bo
rne
by
ES
Elu
mp
su
m
lum
psu
m
lum
psu
m
lum
psu
m
5.0
%
lum
psu
m
C.1
Lum
psu
m
CS.N
oC
os
t p
er
Un
it
(US
D)
-
15
PA
RT
I
T
able
1.
Saf
egu
ard
s Im
ple
men
tati
on
Res
po
nsi
bili
ty
Res
po
nsi
ble
E
nti
ty
Pro
ject
Sta
ge
and
En
viro
nm
enta
l Res
po
nsi
bili
ty
Pro
ject
Pre
para
tion
Eng
inee
ring
Det
aile
d D
esig
n T
ende
ring
& P
re-c
onst
ruct
ion
Con
stru
ctio
n
Ope
ratio
n
MO
EE
T
he E
A fo
r th
e pr
ojec
t will
be
resp
onsi
ble
for
the
over
all s
uper
visi
on a
nd m
onito
ring
of th
e pr
ojec
t im
plem
enta
tion
and
has
suffi
cien
t and
qua
lifie
d st
aff.
The
EA
will
ens
ure
impl
emen
tatio
n is
in li
ne w
ith s
afeg
uard
s do
cum
ents
and
loan
and
gra
nt c
oven
ants
.
ES
E
The
IA w
ill s
et u
p a
PM
U s
uppo
rted
by
dedi
cate
d an
d tr
aine
d on
e (1
) E
&S
man
ager
and
two
(2)
E&
S o
ffice
rs o
n st
aff o
n fu
ll tim
e ba
sis
PM
U
The
PM
U w
ill b
e re
spon
sibl
e fo
r ov
eral
l sup
ervi
sion
and
coo
rdin
atio
n du
ring
proj
ect i
mpl
emen
tatio
n an
d en
sure
con
sist
ency
of a
ll sa
fegu
ards
do
cum
ents
with
gov
ernm
ent p
olic
y, le
gal a
nd a
dmin
istr
ativ
e fr
amew
ork
acro
ss a
ll ju
risdi
ctio
n an
d w
ill a
ssis
t with
pro
ject
GR
M, f
inal
izat
ion
of R
EG
DP
an
d in
con
duct
ing
info
rmat
ion
disc
losu
re, m
eani
ngfu
l con
sulta
tion
and
part
icip
atio
n. T
he P
MU
will
als
o be
res
pons
ible
for
proc
urem
ent o
f goo
ds,
wor
ks a
nd s
ervi
ces,
sub
mis
sion
of r
epor
ts to
AD
B a
nd c
oord
inat
ion
with
line
min
istr
ies
to e
nsur
e sm
ooth
and
effi
cien
t im
plem
enta
tion
of th
e pr
ojec
t.
Eng
age
with
C
onsu
ltant
s on
IEE
, E
MP
, RE
GD
P
Eng
age
with
in
tern
atio
nal a
nd
natio
nal
envi
ronm
enta
l and
so
cial
spe
cial
ists
as
part
of t
he P
IC
serv
ices
App
ly a
nd o
btai
n pe
rmits
, cle
aran
ces,
ap
prov
als
from
re
leva
nt g
over
nmen
t ag
enci
es
Pro
vide
s a
form
al
lette
r to
AD
B th
at
conf
irms
that
the
GR
M h
as b
een
esta
blis
hed
and
is
oper
atio
nal w
ith a
list
of
GR
C c
omm
ittee
Rev
iew
and
app
rove
up
date
d IE
E /
EM
P /
RE
GD
P
Con
firm
clim
ate
chan
ge
adap
tatio
n m
easu
res
have
bee
n in
clud
ed in
th
e fin
al e
ngin
eerin
g de
sign
Con
firm
that
key
des
ign
feat
ures
for
effe
ctiv
e en
viro
nmen
tal
man
agem
ent a
nd
miti
gatio
n m
easu
res
have
bee
n in
clud
ed in
fin
al e
ngin
eerin
g de
tail
desi
gn
Rev
iew
bid
ding
do
cum
ents
to e
nsur
e th
at
the
IEE
/EM
P c
laus
es a
re
inco
rpor
ated
Man
age
the
proc
urem
ent
proc
ess
Sup
ervi
se E
MP
im
plem
enta
tion
to e
nsur
e ef
fect
iven
ess
Ope
rate
and
coo
rdin
ate
the
proj
ect G
RM
rec
ords
and
re
port
ing
Pre
pare
pro
ject
QP
Rs
and
sem
i-ann
ual s
afeg
uard
s /
envi
ronm
ent m
onito
ring
repo
rts
and
subm
it th
ese
to
AD
B
Insp
ect i
mpl
emen
tatio
n of
m
itiga
tion
mea
sure
s
Pre
pare
ann
ual
safe
guar
ds /
envi
ronm
enta
l m
onito
ring
repo
rts
until
a P
roje
ct
Com
plet
ion
Rep
ort
is is
sued
-
16
Res
po
nsi
ble
E
nti
ty
Pro
ject
Sta
ge
and
En
viro
nm
enta
l Res
po
nsi
bili
ty
Pro
ject
Pre
para
tion
Eng
inee
ring
Det
aile
d D
esig
n T
ende
ring
& P
re-c
onst
ruct
ion
Con
stru
ctio
n
Ope
ratio
n
mem
bers
at e
ach
leve
l inc
ludi
ng P
MU
an
d P
IU fo
cal p
oint
pe
rson
s fo
r G
RM
PIU
The
re w
ill b
e a
tota
l of f
our
PIU
s pe
r R
egio
n / S
tate
. The
PIU
s w
ill b
e re
spon
sibl
e fo
r da
y-to
-day
pro
ject
impl
emen
tatio
n an
d en
surin
g co
mpl
ianc
e w
ith
safe
guar
ds a
nd o
vers
ight
of c
ontr
acto
rs.
The
PM
U w
ill a
ssig
n a
dedi
cate
d an
d tr
aine
d fo
cal p
oint
per
son
at e
ach
PIU
in c
harg
e of
env
ironm
enta
l sa
fegu
ards
and
the
proj
ect G
RM
App
oint
at l
east
one
(1
) en
viro
nmen
t &
soci
al fo
cal p
oint
pe
rson
on
staf
f at
each
PIU
(fu
ll tim
e)
Man
age
EM
P im
plem
enta
tion
on th
e gr
ound
to e
nsur
e ef
fect
iven
ess
Ove
rsig
ht o
f Con
trac
tors
Eng
age
in r
esol
ving
gr
ieva
nces
or
com
plai
nts
as
per
proj
ect G
RM
Eng
age
in in
form
atio
n di
sclo
sure
, con
sulta
tion
and
part
icip
atio
n ac
tiviti
es
Man
age
EM
P
impl
emen
tatio
n on
th
e gr
ound
to e
nsur
e ef
fect
iven
ess
Ove
rsig
ht o
f C
ontr
acto
rs
Eng
age
in r
esol
ving
gr
ieva
nces
or
com
plai
nts
as p
er
proj
ect G
RM
Eng
age
in
info
rmat
ion
disc
losu
re,
cons
ulta
tion
and
part
icip
atio
n ac
tiviti
es
PIC
P
IC f
or p
roje
ct w
ill b
e re
spon
sibl
e fo
r co
mpl
ianc
e as
sura
nce
with
saf
egua
rds
thro
ugh
supe
rvis
ion
and
mon
itorin
g of
EM
P,
site
SE
MP
/SO
MP
s an
d al
l co
ntra
ctor
s ac
ross
all
stag
es o
f pro
ject
impl
emen
tatio
n in
clud
ing
final
test
ing
and
com
mis
sion
ing.
PIC
will
als
o be
res
pons
ible
for
proc
urem
ent p
roce
ss
/ im
plem
enta
tion
and
cont
ract
man
agem
ent a
nd p
repa
ratio
n of
saf
egua
rds
docu
men
ts, p
rogr
ess
repo
rts
and
mon
itorin
g re
port
s.
Ass
ist P
MU
in
prep
arat
ion
of P
IB fo
r di
ssem
inat
ion
Con
duct
info
rmat
ion
disc
losu
re,
Ass
ist i
n up
datin
g IE
E
/EM
P /
RE
GD
P a
s ne
eded
Eng
age
with
EC
D
appr
oved
loca
l thi
rd-
part
y m
onito
ring
Inco
rpor
ate
proj
ect E
MP
in
tend
er d
ocum
ents
, bid
s an
d co
ntra
cts
Eng
age
with
con
trac
tors
to
dev
elop
pac
kage
- sp
ecifi
c si
te E
MP
(S
EM
P)/
Con
duct
orie
ntat
ion
and
brie
fing
of p
roje
ct s
taff,
w
orke
rs, c
ontr
acto
rs o
n sa
fegu
ard
requ
irem
ents
for
civi
l wor
ks
Con
duct
orie
ntat
ion
/ br
iefin
g of
pro
ject
st
aff,
wor
kers
, co
ntra
ctor
s, f
acili
ty
oper
ator
s on
sa
fegu
ard
-
17
Res
po
nsi
ble
E
nti
ty
Pro
ject
Sta
ge
and
En
viro
nm
enta
l Res
po
nsi
bili
ty
Pro
ject
Pre
para
tion
Eng
inee
ring
Det
aile
d D
esig
n T
ende
ring
& P
re-c
onst
ruct
ion
Con
stru
ctio
n
Ope
ratio
n
cons
ulta
tion
and
part
icip
atio
n ac
tiviti
es
Con
duct
trai
ning
and
ca
paci
ty b
uild
ing
for
PM
U, P
IUs
and
cont
ract
ors
Ass
ist P
MU
in
obta
inin
g pe
rmits
and
cl
eara
nces
/ ap
prov
als
Pre
pare
TO
R fo
r re
crui
tmen
t of t
hird
- pa
rty
mon
itorin
g co
ntra
ctor
Eng
age
with
PM
U,
PIU
s to
inte
grat
e pr
ojec
t-le
vel C
OV
ID-
19 r
isk
mea
sure
s in
pr
ojec
t pla
nnin
g
Con
duct
EH
S a
udit
for
exis
ting
subs
tatio
ns fo
r m
arke
d fo
r ex
tens
ion
wor
ks
cont
ract
or a
nd
coor
dina
te
envi
ronm
enta
l bas
elin
e su
rvey
s as
per
the
mon
itorin
g pl
an in
the
appr
oved
EM
P
Con
firm
that
miti
gatio
n m
easu
res
have
bee
n in
clud
ed in
fina
l en
gine
erin
g de
tail
desi
gn in
clud
ing
clim
ate
risks
ada
ptat
ion
mea
sure
s, r
esul
ts o
f the
ba
selin
e su
rvey
s, k
ey
desi
gn fe
atur
es fo
r en
viro
nmen
tal
man
agem
ent
Ass
ist P
MU
in
prep
arat
ion
and
subm
issi
on o
f dom
estic
IE
E to
MO
NR
EC
/ E
CD
SO
MP
s w
ith s
ite m
aps
and
rece
ptor
info
rmat
ion;
in
tegr
ate
CO
VID
-19
risk
miti
gatio
n m
easu
res
in
cont
ract
or O
HS
pla
ns
App
rove
con
trac
tor
appo
inte
d en
viro
nmen
t an
d G
RM
foca
l poi
nt
pers
ons
with
in c
ontr
acto
r st
aff (
C-E
HS
and
G-G
RM
)
Ass
ist P
MU
, PIU
s an
d co
ntra
ctor
s in
pro
ject
re
adin
ess
with
res
pect
to
EM
P im
plem
enta
tion
Ass
ist c
ontr
acto
rs in
in
form
atio
n di
sclo
sure
, co
nsul
tatio
n an
d pa
rtic
ipat
ion
activ
ities
Pro
vide
tech
nica
l sup
port
to
PM
U, P
IUs
and
cont
ract
ors
o
Adv
ise
on m
itiga
tion
mea
sure
s
o
Pre
para
tion
of S
EM
P
o
Com
plia
nce
mon
itorin
g in
lin
e w
ith E
MP
Coo
rdin
ate
cons
truc
tion
supe
rvis
ion,
inst
alla
tion
and
com
mis
sion
ing
and
qual
ity
cont
rol
Ass
ist P
IUs
in c
ondu
ctin
g ra
ndom
che
cks
/ aud
its o
f co
ntra
ctor
’s E
HS
per
form
ance
Eng
age
with
con
trac
tors
and
co
ordi
nate
env
ironm
enta
l su
rvey
s as
per
the
envi
ronm
enta
l mon
itorin
g pl
an
in th
e ap
prov
ed E
MP
Ass
ist w
ith p
roje
ct G
RM
Pre
pare
pro
ject
QP
R a
nd
subm
it th
em to
PM
U fo
r ve
rific
atio
n an
d us
e
Sup
port
PM
U in
pre
parin
g se
mi-a
nnua
l mon
itorin
g re
port
Rev
iew
mon
thly
pro
gres
s re
port
s on
SE
MP
im
plem
enta
tion
by c
ontr
acto
rs
requ
irem
ents
for
O&
M
Ass
ist c
ontr
acto
rs in
in
form
atio
n di
sclo
sure
, co
nsul
tatio
n an
d pa
rtic
ipat
ion
activ
ities
Pro
vide
tech
nica
l su
ppor
t to
cont
ract
ors
in
prep
arin
g an
d im
plem
entin
g S
OM
Ps
Coo
rdin
ate
envi
ronm
enta
l m
onito
ring
acco
rdin
g to
the
appr
oved
E
MP
unt
il a
Pro
ject
C
ompl
etio
n R
epor
t is
issu
ed
Ove
rsee
O&
M
Pre
pare
pro
ject
Q
PR
s an
d su
bmit
them
to P
MU
for
verif
icat
ion
and
use
until
a P
roje
ct
Com
plet
ion
Rep
ort
is is
sued
Sup
port
PM
U in
pr
epar
ing
annu
al
mon
itorin
g re
port
ing
-
18
Res
po
nsi
ble
E
nti
ty
Pro
ject
Sta
ge
and
En
viro
nm
enta
l Res
po
nsi
bili
ty
Pro
ject
Pre
para
tion
Eng
inee
ring
Det
aile
d D
esig
n T
ende
ring
& P
re-c
onst
ruct
ion
Con
stru
ctio
n
Ope
ratio
n
Thi
rd-P
arty
M
onito
ring
Con
trac
tor
Con
duct
bas
elin
e su
rvey
s as
per
app
rove
d E
MP
Pre
pare
rep
ort o
f fin
ding
s an
d su
bmit
to
PM
U a
nd P
IC
DP
TS
C
Con
duct
info
rmat
ion
disc
losu
re, m
eani
ngfu
l co
nsul
tatio
n an
d pa
rtic
ipat
ion
activ
ities
incl
udin
g in
form
atio
n on
ER
P, c
omm
unity
hea
lth &
sa
fety
Und
erta
ke o
pera
tion
as p
er E
MP
Con
duct
info
rmat
ion
disc
losu
re,
cons
ulta
tion
and
part
icip
atio
n ac
tiviti
es
Und
erta
ke
envi
ronm
enta
l
mon
itorin
g ac
cord
ing
to th
e en
viro
nmen
tal
mon
itorin
g pl
an u
ntil
a P
roje
ct C
ompl
etio
n R
epor
t is
issu
ed
Ens
ure
prop
er
oper
atio
n an
d m
aint
enan
ce o
f su
bsta
tions
EC
D /
MO
NR
EC
Rev
iew
and
app
rove
the
dom
estic
IEE
/ E
MP
Rev
iew
env
ironm
enta
l ba
selin
e m
onito
ring
resu
lts
-
19
Res
po
nsi
ble
E
nti
ty
Pro
ject
Sta
ge
and
En
viro
nm
enta
l Res
po
nsi
bili
ty
Pro
ject
Pre
para
tion
Eng
inee
ring
Det
aile
d D
esig
n T
ende
ring
& P
re-c
onst
ruct
ion
Con
stru
ctio
n
Ope
ratio
n
Con
duct
insp
ectio
n an
d m
onito
ring
as p
er th
eir
man
date
Con
trac
tors
13
Coo
rdin
ate
with
PIC
to
final
ize
pack
age-
spec
ific
site
SE
MP
s / S
OM
Ps
cont
aini
ng s
ite m
aps
with
re
cept
or in
form
atio
n
Ens
ure
suffi
cien
t fun
ding
an
d hu
man
res
ourc
es fo
r pr
oper
and
tim
ely
impl
emen
tatio
n of
re
quire
d m
itiga
tion
and
mon
itorin
g m
easu
res
as
per
the
appr
oved
the
EM
P
thro
ugho
ut th
e co
nstru
ctio
n ph
ase
App
oint
at l
east
one
en
viro
nmen
t foc
al p
oint
per
son
with
in s
taff
(C-E
HS
)
App
oint
at l
east
one
GR
M fo
cal
poin
t per
son
with
in s
taff
(C-
GR
M)
Con
duct
env
ironm
enta
l m
onito
ring
as p
er th
e en
viro
nmen
tal m
onito
ring
plan
in
the
appr
oved
EM
P
Rep
ort r
esul
ts o
f the
m
onito
ring
data
to P
IU a
nd
PIC
Con
duct
orie
ntat
ion
and
brie
fing
of h
ired
wor
kers
Con
duct
info
rmat
ion
disc
losu
re, c
onsu
ltatio
n an
d pa
rtic
ipat
ion
activ
ities
Pre
pare
and
sub
mit
mon
thly
pr
ogre
ss r
epor
ts o
n si
te
SE
MP
impl
emen
tatio
n to
PIU
Con
duct
orie
ntat
ion
and
brie
fing
of h
ired
wor
kers
Con
duct
info
rmat
ion
disc
losu
re,
cons
ulta
tion
and
part
icip
atio
n ac
tiviti
es
Und
erta
ke
envi
ronm
enta
l m
onito
ring
as p
er
the
envi
ronm
enta
l m
onito
ring
plan
in
the
appr
oved
EM
P
until
a P
roje
ct
Com
plet
ion
Rep
ort
is is
sued
13
Co
ntr
acto
rs im
ply
= E
ng
inee
rin
g P
rocu
rem
en
t, C
onstr
uction
(E
PC
) co
ntr
acto
rs, a
ny
key s
ub
-co
ntr
act
ors
, a
nd
facili
ty o
pe
rato
rs (
No
te:
EM
P im
ple
me
nta
tion
du
ring
op
era
tion s
tag
e w
ill c
on
tinue
th
rou
gh t
he
Pro
ject
Imple
me
nta
tio
n U
nits
(P
IUs)
an
d f
or
exte
nsio
n w
ork
s a
t exis
ting
23
0kV
sub
sta
tion
s th
rou
gh t
he
Dep
art
me
nt
of
Po
we
r T
ransm
issio
n a
nd
Su
pply
Co
ntr
ol (D
PT
SC
) th
at is
th
e fa
cili
ty o
pe
rato
r 2
30 k
V s
ubsta
tio
ns in M
ya
nm
ar)
.
-
20
Res
po
nsi
ble
E
nti
ty
Pro
ject
Sta
ge
and
En
viro
nm
enta
l Res
po
nsi
bili
ty
Pro
ject
Pre
para
tion
Eng
inee
ring
Det
aile
d D
esig
n T
ende
ring
& P
re-c
onst
ruct
ion
Con
stru
ctio
n
Ope
ratio
n
AD
B
Rev
iew
and
app
rove
th
e IE
E a
nd E
MP
and
di
sclo
se o
n A
DB
w
ebsi
te
App
rove
upd
ated
IE
E/E
MP
if a
ppro
pria
te
and
disc
lose
on
AD
B
web
site
Rev
iew
bid
ding
do
cum
ents
Con
firm
pro
ject
’s
read
ines
s
Rev
iew
pro
ject
QP
Rs,
sem
i-an
nual
env
ironm
enta
l m
onito
ring
repo
rts
Und
erta
ke r
evie
w m
issi
ons
Adv
ise
on c
ompl
ianc
e is
sues
, as
req
uire
d
Rev
iew
and
dis
clos
e se
mi-
annu
al e
nviro
nmen
tal
mon
itorin
g re
port
s on
AD
B
web
site
.
Rev
iew
and
app
rove
an
nual
en
viro
nmen
tal
mon
itorin
g re
port
s an
d di
sclo
se o
n A
DB
w
ebsi
te
Und
erta
ke p
roje
ct
com
plet
ion
revi
ew
mis
sion
and
pre
pare
P
roje
ct C
ompl
etio
n R
epor
t for
app
rova
l by
Boa
rd a
nd
disc
losu
re o
n A
DB
w
ebsi
te.
AD
B =
Asi
an D
evel
opm
ent B
ank;
C-E
HS
= C
ontr
acto
r E
nviro
nmen
tal,
heal
th &
saf
ety
foca
l poi
nt p
erso
n; D
PT
SC
= D
epar
tmen
t of P
ower
Tra
nsm
issi
on a
nd S
uppl
y C
ontr
ol; E
A =
Exe
cutin
g ag
ency
; EC
D =
Env
ironm
enta
l Con
serv
atio
n D
epar
tmen
t; E
MP
= E
nviro
nmen
tal m
anag
emen
t pla
n; E
SE
= E
lect
ricity
Sup
ply
Ent
erpr
ise;
G
RM
= G
rieva
nce
redr
ess
mec
hani
sm; I
A =
Impl
emen
ting
agen
cy; I
EE
= In
itial
env
ironm
enta
l exa
min
atio
n; R
EG
DP
= R
eset
tlem
ent a
nd E
thic
Gro
up D
evel
opm
ent
Pla
n; M
ON
RE
C =
Min
istr
y of
Nat
ural
Res
ourc
es a
nd E
nviro
nmen
tal C
onse
rvat
ion;
OH
S =
Occ
upat
iona
l Hea
lth &
Saf
ety;
PIC
= P
roje
ct im
plem
enta
tion
cons
ulta
nt
serv
ices
; PM
U =
Pro
ject
man
agem
ent u
nit;
PIU
= P
roje
ct im
plem
enta
tion
unit;
QP
R =
Qua
rter
ly p
rogr
ess
repo
rt; O
&M
= o
pera
tion
and
mai
nten
ance
; SE
MP
= S
ite
envi
ronm
enta
l man
agem
ent p
lan;
SO
MP
= S
tand
ard
oper
atio
n an
d m
aint
enan
ce p
lan
-
21
-
22
En
vir
on
men
tal M
an
ag
em
en
t P
lan
Tab
le 2
.1. E
MP
– D
esig
n a
nd
Pre
-Co
nstr
ucti
on
Pro
ject
Activ
ity
Po
ten
tial Im
pa
cts
/ Issu
es
Mitig
atio
n M
easu
res a
nd
Sa
feg
ua
rds
Re
sp
onsib
ility
14
So
urc
e o
f F
un
ds
Imp
lem
en
tatio
n
Su
pe
rvis
ion
DE
SIG
N A
ND
PR
E-C
ON
ST
RU
CT
ION
ST
AG
E
PR
OJ
EC
T R
EA
DIN
ES
S C
HE
CK
S F
OR
EF
FE
CT
IVE
EN
VIR
ON
ME
NT
AL
MA
NA
GE
ME
NT
Pro
ject
Im
ple
men
tatio
n
Se
t u
p
No
n-c
om
plia
nce
with
AD
B
SP
S 2
00
91
5 a
nd
th
e
Na
tio
nal re
gu
lato
ry
fra
me
wo
rk o
f M
ya
nm
ar
Ap
po
intm
en
t o
f a
Pro
ject
Im
ple
me
nta
tion
Co
nsulta
nt (P
IC)
Se
rvic
es1
6
Co
ntr
act
ing o
f In
tern
ation
al a
nd
Na
tion
al E
nvi
ronm
en
t C
on
sulta
nts
17
PM
U a
nd P
IUs s
et u
p w
ith d
edic
ate
d E
&S
sta
ff
ES
E
AD
B
Inclu
de
d in
th
e P
roje
ct
Co
sts
Pro
ject
Site
Se
lect
ion,
Ro
ute
Sele
ctio
n
(1)
Re
ce
pto
rs, p
art
icula
rly a
) h
ou
seh
old
are
as
/ str
uct
ure
s,
b)
su
rfa
ce w
ate
r so
urc
es,
c)
gro
un
dw
ate
r w
ells
, d
) ro
ad
an
d r
ailw
ay
cro
ssin
gs, e
) p
rote
cte
d
are
as,
fo
rests
, critic
al
ha
bita
ts a
nd
we
tlan
ds,
if
an
y, sp
ecie
s o
f co
nse
rva
tion
va
lue
, f)
p
hys
ica
l cu
ltura
l re
sou
rce
s
(PC
Rs).
18
Site
se
lecte
d f
or
the
su
bsta
tion
avo
ids s
en
sitiv
e n
atu
ral an
d
hu
man
rece
pto
rs s
uch
as p
rote
cte
d a
rea
s, h
abita
ts a
nd
sp
ecie
s o
f con
se
rva
tion
va
lue
, w
ate
r so
urc
es a
nd
h
ou
seh
old
s / s
tru
ctu
res,
PC
Rs
(e.g
. a
t n
ew
Ka
nla
lay
su
bsta
tion
site
in
Kyau
ngko
ne T
ow
nship
, A
yeya
rwa
dy
Re
gio
n 1
9
Ro
ute
se
lectio
n o
f d
istr
ibu
tion
lin
e a
vo
ids s
ensiti
ve n
atu
ral
an
d h
um
an
rece
pto
rs such
as
pro
tecte
d a
reas, h
ab
itats
a
nd
sp
ecie
s o
f con
ve
rsa
tion
va
lue
, w
ate
r so
urc
es)
De
taile
d w
alk
ove
r su
rve
y to
be
con
ducte
d to
info
rm
de
taile
d e
ngin
ee
rin
g d
esig
n t
o a
vo
id s
en
sitiv
e n
atu
ral an
d
hu
man
rece
pto
rs (
ho
use
ho
lds/ str
uctu
res/ scho
ols
) an
d
PM
U
PIC
AD
B
ES
E
bu
dg
et
14
PIC
– P
roje
ct Im
plem
enta
tion
Con
sulta
nts;
PM
U –
Pro
ject
Man
agem
ent
Uni
t of E
SE
; PIU
– P
roje
ct Im
plem
enta
tion
Uni
t of
ES
E; P
IU E
&S
– P
roje
ct I
mpl
emen
tatio
n U
nit E
nviro
nmen
t & S
ocia
l foc
al
poin
t pe
rson
; A
DB
– A
sian
Dev
elop
men
t B
ank;
Con
trac
tors
im
ply
- E
ngin
eerin
g, P
rocu
rem
ent,
Con
stru
ctio
n (E
PC
) co
ntra
ctor
s, k
ey s
ub-c
ontr
acto
rs a
nd f
acili
ty o
pera
tors
; C
-EH
S –
Con
trac
tor
Env
ironm
enta
l, H
ealth
and
Saf
ety
foca
l poi
nt p
erso
n; C
-GR
M –
Con
trac
tor
Grie
vanc
e R
edre
ss M
echa
nism
foca
l poi
nt p
erso
n 15
AD
B S
PS
200
9 –
Asi
an D
evel
opm
ent B
ank
Saf
egua
rd P
olic
y S
tate
men
t 200
9 16
For
det
ails
ref
er to
Tab
le 1
. Saf
egua
rds
Impl
emen
tatio
n R
espo
nsib
ility
. 17
PIC
will
be
supp
orte
d by
one
(1)
Inte
rnat
iona
l Env
ironm
ent S
peci
alis
t (12
per
son-
mon
ths
over
72
mon
ths)
and
two
(2)
Nat
iona