Angola - Fisheries Sector Support Project - Appraisal Report · Risks: Encroachment by industrial...
Transcript of Angola - Fisheries Sector Support Project - Appraisal Report · Risks: Encroachment by industrial...
AFRICAN DEVELOPMENT FUND
PROJECT : FISHERIES SECTOR SUPPORT PROJECT
COUNTRY : ANGOLA
APPRAISAL REPORT
OSAN DEPARTMENT
April 2013
Appraisal Team
Regional Director : Mr. C. OJUKWU, Director, ORSB
Sector Director : Mr. A. BEILEH, Acting Director, OSAN
Division Manager : Mr. K. JOHM , Division manager, OSAN.4
Team Leader : Mr. F. MARTTIN, Senior Fishery Officer, OSAN.4
TABLE OF CONTENTS
I STRATEGIC THRUST AND RATIONALE 1
1.1 Project linkages with country strategies and objectives 1
1.2 Rationale for Bank’s involvement 2
1.3 Donor coordination 2
II PROJECT DESCRIPTION 3
2.1 Project components 3
2.2 Technical solutions retained, other alternatives explored 5
2.3 Project Type 6
2.4 Project costs and financing arrangements 6
2.5 Project Target Areas and Beneficiary population 8
2.6 Participatory process for identification, design and implementation 9
2.7 Bank Group experience, lessons learnt in project design 9
2.8 Key Performance Indicators 10
III PROJECT FEASIBILITY 10
3.1 Economic and Financial Performance 10
3.2 Environmental and Social Impacts 11
IV IMPLEMENTATION 13
4.1 Implementation Arrangements 13
4.2 Monitoring & Evaluation 15
4.3 Governance 16
4.4 Sustainability 16
4.5 Risk Management 17
4.6 Knowledge Building 18
4.7 Bank’s Field Office 18
V LEGAL INSTRUMENTS AND AUTHORITY 18
5.1 Legal instrument 18
5.2 Conditions associated with Bank’s intervention 18
5.3 Compliance with Bank policies 19
VI RECOMMENDATION 19
Appendix I Country’s comparative socio-economic indicators
Appendix II Table of AfDB’s portfolio in the country
Appendix III Similar projects financed by the Bank and other development
partners in the Angola
Appendix IV Map of Angola showing project areas
Appendix V Project sites
i
Currency Equivalents
As of July 2012
UA=USD 1.55644 July 2012
Fiscal Year 01 January – 31 December
Weights and Measures
1 metric tonne = 2204 pounds (lbs)
1 kilogramme (kg) = 2.200 pounds (lbs)
1 metre (m) = 3.28 feet (ft)
1 millimetre (mm) = 0.03937 inch (“)
1 kilometre (km) = 0.62 mile
1 hectare (ha) = 2.471 acres
ii
ABBREVIATIONS AND ACRONYMS
AfDB : African Development Bank
ADF : African Development Fund
AFDEP : Artisanal Fisheries Development Project
AWPB : Annual Work Plan and Budget
CAS : Catch and Effort Assessment Survey
CDC : Community Development Committee
CEFOPESCAS : Fisheries Training School (Centro de Formação Profissional de Pescas)
CPA : Fish Landing Site (Centros de Pesca Artisanal)
CSP : Country Strategy Paper
EIA : Environmental Impact Assessment
EIRR : Economic Internal Rate of Return
ESMP : Environmental and Social Management Plan
EU : European Union
FAO : Food and Agriculture Organization of the United Nations
FIRR : Financial Internal Rate of Return
FSSP : Fisheries Sector Support Project
GDP : Gross Domestic Product
GoA : Government of Angola
GPN : General Procurement Notice
HACCP : Hazard Analysis and Critical Control Points
ICB : International Competitive Bidding
INAPIT : Instituto de Apoio as Indústrias de Pescas e Investigação Tecnológica
IPA : National Institute for Development of Artisanal Fisheries and
Aquaculture (Instituto da Pesca Artesanal e da Aquicultura)
LDF : Local Development Fund
MCS : Monitoring, Control and Surveillance
MoF : Ministry of Fisheries
MTR : Mid Term Review
M&E : Monitoring and Evaluation
MFI : Micro-Finance Institution
MPA : Marine Protected Area
NCB : National Competitive Bidding
NGO : Non-Government Organization
NPV : Net Present Value
O&M : Operation and Maintenance
PCR : Project Completion Report
PHL : Post-Harvest Losses
PIO : Project Implementation Office
PIP : Public Investment Programme
PRSP : Poverty Reduction Strategy Paper
PSC : Project Steering Committee
SBD : Standard Bidding Documents
UNDB : UN Development Business
USD : United States Dollar
VMS : Vessel Monitoring System
WFP : World Food Programme
iii
Loan Information
Client’s information
LOAN RECEPIENT : REPUBLIC OF ANGOLA
EXECUTING AGENCY : MINISTRY OF AGRICULTURE, RURAL
DEVELOPMENT AND FISHERIES
Financing plan
Source Amount (UA million) Instrument
ADF 20.00 Loan
Government Contribution 5.49
Other n/a
TOTAL COST 25.49
ADB’s key financing information
Loan / currency
(UA)
Interest type* n.a.
Interest rate spread* 1%
Commitment fee* 0.5% undisbursed balance
Other fees* 0.75% Service Charge per year on the disbursed
and outstanding amount
Tenor 30 Years
Grace period 8 years
FIRR, NPV (base case) (19.49%, NPV US$234.0 million)
EIRR (base case) (22.04%)
*if applicable
Timeframe - Main Milestones (expected)
Concept Note approval
01/11/2011
Project approval 03/07/2013
Effectiveness 01/09/2013
Mid Term Review 01/01/2016
Infrastructure construction completed 01/08/2016
Completion 01/01/2019
Last Disbursement 30/06/2019
iv
Project Summary
Section Description
Project
overview
The Fisheries Sector Support Project will increase incomes of small scale
fishers and traders (mostly women) through marked improvements in the
fish landing and handling facilities thereby reducing post-harvest losses
and improving quantity and quality of fish landed and traded. It will be
implemented in coastal communities of Gilco, Yembe, Egipto Praia,
Salinas Sumbe, Dambe Maria and Ambriz. Key expected outputs are: 4
landing sites constructed, 2 landing sites rehabilitated, 10 landing sites
with additional works completed. 20 % reduction of Post-Harvest Losses.
The project will cost UA 25.49 million and will be implemented over a 5
year period.
Beneficiaries The direct beneficiaries are the fishing population of over 10,000 at the
project sites including women who constitute 80% of small scale fish
processors and traders. The project will also be of benefit to ancillary
trades such as boat repair, net mending, transportation, petty trade and
overall economic activities in the project areas.
Needs
Assessment
Currently the estimated post-harvest losses at project sites are more than
7,000mt/yr valued at about US$ 7 Million. The coastal population is poor
and vulnerable, as alternatives to fishing are scarce. Monitoring, Control
and Surveillance capacity in the artisanal fisheries is weak, as is the
capacity to manage landing sites and their infrastructures, hampering the
sustainable management of Angola’s marine resources.
Bank’s
Added Value
The Bank’s added value is from the experience and knowledge generated
from the implementation of the AFDEP which was completed in 2011. In
addition, the Bank has accumulated experience through the successful
implementation of its fisheries portfolio in 23 African countries covering
capacity building, fisheries infrastructure development and management,
quality assurance and environmental safeguards. Lessons learned include:
management of fishery infrastructures should be addressed from the
beginning of the project, project implementation should be anchored in
government structures, credit for fishing and fish marketing has a weak
record in most Bank supported fishery projects, procurement and
disbursement arrangements need to be tailored to the special conditions of
Angola.
Knowledge
Management
The project will generate useful knowledge in community and private
sector management of fish landing sites. It will further provide useful pilot
experience in fish quality control and improvement, as well as on
monitoring, control and surveillance which can be replicated over the
entire coast. This knowledge will be captured and disseminated through
regular project implementation reports.
v
ANGOLA Fisheries Sector Support Project
Result-Based Program Matrix
Country and project name: Angola: Fisheries Sector Support Project
Purpose of the project: Increase income of fishing communities through investments in fishery infrastructure and their management (including marine resources
management and safety at sea)
RESULTS CHAIN PERFORMANCE INDICATORS
MEANS OF VERIFICATION
RISKS/MITIGATION MEASURES Indicator
(including CSI) Baseline Target
IMP
AC
T
Poverty reduced and food security increase
among the Angolan population
Proportion of coastal people
below the poverty line (sex disaggregated)
54.3% (to be
confirmed by the baseline
survey)
Proportion of coastal people
below poverty line reduced by 10%
Government ,MARDF
MFI reports, Baseline
survey
Risks: Due to the global economic crisis and the rising food prices poverty
reduction and food security increase is hampered Mitigation measures: Dependence on the global market for income of fishing
communities will not be increased by focusing on local (and regional) markets
development Percentage of Underweight Children (Children under
the age of 5 years)
15.6% (to be confirmed by
the baseline
survey)
Percentage of Underweight children reduced by 20% at
landing sites covered by the
project
OU
TC
OM
ES
Increase of fishers and fish processors income % Increase of income of
fishers (sex disaggregated)
% Increase of income of
fish processors (sex
disaggregated)
70
USD/month
55
USD/month
(both to be confirmed by
baseline
survey)
20 % increase of income of
fishers and fish processors at
landing sites covered by the
project Project, Government, MFI reports, Baseline survey
Risks: Encroachment by industrial fleet in the artisanal fishing zone, resulting
in destruction of gear of the artisanal fleet and depletion of fish stocks.
Mitigation measures: The project will ensure Monitoring, Control and
Surveillance will improve. Fishers at selected landing sites will be trained in
fisheries management, including the need for enforcement of management
measures. Communication channels with the Fisheries inspection units will be established, ensuring that sightings of illegal (industrial) vessels will be
reported by artisanal fishers and acted upon by the fisheries inspection service.
Increase safety at sea Reduction of lives lost 25 lives lost
per year
50% reduction Project, Government, MFI
reports
Improve sustainability of fishery management No. of incursions (illegal entries into the artisanal
fishery zone) per year Frequent
(daily)
50% reduction of incursions at
MCS-covered sites
Gvt reports, project
reports
Reduction of Post-Harvest Losses (value) % reduction of Post-Harvest Losses (value)
7 000 mt per year (to be
confirmed by
baseline survey)
20 % reduction of Post-Harvest Losses at landing sites covered
by the project
vi
1) Sustainable exploitation of marine fishery
resources through Monitoring, Control & Mgmt.
1.1) Monitoring, Control and Surveillance
infrastructure provided
Coverage of inshore area by
VHF MCS system, no. of
towers built 0
4 towers built and system in place
Project reports
No. of vessels equipped with
a vessel tracker unit
0 100 fishing vessels equipped
with vessel tracker units
Risk: Fishers unwilling to install vessel trackers as they are unclear about the
purpose of the tracker
Mitigation measure: Ensure that fishers are aware of the purposes of the vessel tracker through training and meetings at landing sites
Reduction of lives lost 25 lives lost
per year
50% reduction Project, Government, MFI
reports
No. of incursions (illegal
entries into the artisanal fishery zone) per year
Frequent
(daily)
50% reduction of incursions at
MCS-covered sites
Government reports,
project reports
No. of HACCP systems
implemented at landing sites 0 16 Project reports
OU
TP
UT
S
No. of fish quality samples
taken and tested 0 50 samples/week Fishery product quality
inspection reports
1.2) Marine fishery resource management improved
Number of functioning fishery resource
management committees at
project sites (with a minimum participation of
50% of women)
0 16
Project reports
Fishery Resource Management Plans (16)
Risk: Fishers do not participate, because not convinced about the benefits of management.
Mitigation measure: The project will educate fishers of the benefits of
sustainable fisheries management, ensuring fair representation of all stakeholders involved.
1.3) Fishery monitoring improved National frame survey,
Catch and effort assessment
survey established at sites
Socio-economic survey at
sites (sex-disaggregated)
1 (1995),
None
none
1 (2013)
4 sites
16 sites
FAO generated Project
reports
Risk: Fishers unwilling to cooperate with data collection, because of fear
(taxes for instance), Fishers not convinced of the benefits of data collection, Data collection activities not sustainable, because of unavailability of
sufficient resources after project closure allocated
Mitigation measure: Educate fishers on the benefits of data collection, assure that data collected will be used in fishery resources management, through
participation of communities in data collection systems cost of data collection
will be reduced
2) Fishery Infrastructure Development
2.1) Landing sites constructed at project sites Number of Landing sites
constructed
0 4 landing sites constructed and in
use by at least 40 vessels to land their catch at project end
Project reports
Fishery Infrastructure
Management Plans (16)
2.2) Existing landing sites enhanced with
infrastructure such as fuel pumps, community
meeting places, kindergarten
Number of landing sites
improved
0 12 landing sites enhanced and in
use by at least 40 vessels to land
their catch at project end
2.3) Sustainable management of landing sites
(infrastructure) established
Number of landing sites with
fishery infrastructure management established
(with a minimum
participation of 50% of women)
0 16 landing sites with sustainable
management established (including marine resources
management fishery information
system and safety at sea)
vii
3) Project Management
3.1) Timely and cost effective Project
Management
Quarterly progress reports
submitted timely
MTR ESMP
Supervision
Audit report Procurement plan
Annual work plan
Disbursement rate
1 each quarter; 4 per year
1 MTR report ESMP Clearance certificates
2 supervision missions per year
6 months after financial year 1 per year (valid for 18 months)
1 per year (valid for 18 months)
Average 20% per year (KPI)
Project reports
KE
Y A
CT
IVIT
IES
COMPONENTS INPUTS
Component 1: Sustainable exploitation of marine fishery resources through Monitoring, Control and Management
1.1 Monitoring, Control, and Surveillance
1.2 Fishery resource management improved
1.3 Fishery monitoring
Component 1: 5.81 Million UA
Component 2: Fishery Infrastructure Development
2.1 Construction of artisanal fish landing sites/centers (– CPA) 2.2 Expansion of infrastructure at existing CPAs
2.3 Establishment of landing site management
Component 2: 14.88 Million UA
Component 3 : Project Management
3 1 Timely and cost effective Project management Component 3: 4.80 Million UA
Total 25.49 Million UA
1
REPORT AND RECOMMENDATION OF THE MANAGEMENT TO THE BOARD
OF DIRECTORS ON A PROPOSED LOAN TO ANGOLA FOR THE FISHERIES
SECTOR SUPPORT PROJECT
Management submits the following Report and Recommendation on a proposed loan for UA
20.00 million to be repaid in 30 years, including a grace period of 8 years, with a
commitment fee of 0.5%, other fees of 0.75% and a fixed interest rate of 1.0% p.a.to finance
the Fisheries Sector Support Project in Angola.
I. STRATEGIC THRUST AND RATIONALE
1.1 Project linkages with country strategies and objectives 1.1.1 Angola has a long-term vision document entitled Angola Visão 2025, with four
overarching objectives, as follows: (i) promotion and acceleration of growth and
competitiveness through economic diversification; (ii) poverty reduction through human
capital development and targeted interventions, specifically through private sector job
creation; (iii) balanced growth and harmonized development alongside natural resource
protection; (iv) achievement of all of the above by an efficient and accountable government,
with emphasis on institutional strengthening and human capacity development.
1.1.2 The Angola Country Strategy Paper (CSP) aligns the Bank Group’s corporate
strategy with the Government’s strategy aiming to achieve economic diversification through
non-oil private sector led growth to create employment and promote poverty reduction. The
CSP articulates the Bank’s engagement across two pillars: (i) Stimulus to the
competitiveness of the economy; and, (ii) Support to Economic Infrastructure Development.
1.1.3 The project seeks to achieve a reduction of post-harvest losses, and an increase in
fishers’ income through: (i) construction of new fish landing sites, (ii) enhancement of
existing fish landing sites, (iii) sustainable management of the established fish landing sites
and provision of sustainable marketing strategies which are all embedded in Pillars 1 and 2
of the CSP. The project outcomes and outputs address the areas mentioned in the broad
economic and development strategy pursued by the Government, and address both pillars of
the Bank’s Agriculture Sector Strategy through the development of fisheries Monitoring,
Control and Surveillance (MCS) and landing site infrastructure, and through capacity
building with respect to sustainable use of marine resources. The project will create
employment with stable supplies of quality fishery products at the landing sites (through cold
storage and availability of ice). More people will be engaged in processing and
transformation of fishery products. Local trade will increase as a result of the aforementioned
reasons. In total, an increase of 2,000 additional jobs directly related to the landing sites
(management of the landing sites, increased trade, processing, marketing) are expected to be
created. The FSSP will therefore build economic infrastructures (cold storage, ice machines,
and processing areas), while sustainably managing this important natural resource.
1.1.4 The strategies adopted by the Angolan Government for the development of the
fishery sector aim to: organize and modernize the semi-industrial and industrial fishing fleet
and fish processing industries; support sustainable exploitation of the continental and
maritime artisanal fishery; development of inland and marine and inland aquaculture; create
infrastructure for fish landings and conservation; improve the fish distribution chain for
frozen, salted and dried fish; and, improve the fish quality assurance and inspection system.
2
1.2 Rationale for Bank’s involvement
1.2.1 The objective of the project is to increase the income of artisanal fishery communities
through investments in fishery infrastructure and sustainable management of the resource.
The Bank has successfully implemented a similar project in Angola, with positive outcomes.
The project sites supported through the previous project are currently being used. Key
lessons learned were that the management of infrastructures should be addressed at project
inception, staff retention should be a priority, official documents should be translated into
Portuguese, and baseline surveys should be carried out to measure impacts.
1.2.2 The Bank is in a unique position to succeed with the project, as it has experience with
the implementation of similar fisheries projects in 23 countries in Africa covering capacity
building, fisheries infrastructure development and management, quality assurance and
environmental safeguards. Lessons learned from these projects, like management of fishery
infrastructures should be addressed from the beginning of the project, project implementation
should be anchored in government structures, credit for fishing and fish marketing has a weak
record in most Bank supported fishery projects, procurement and disbursement arrangements
need to be tailored to the special conditions of Angola, have been taken into account during
the design of the FSSP.
1.3 Donor coordination
1.3.1. Donor activity in Angola has shifted in the last two years to an increased presence in
cross-cutting areas such as environment, decentralization, private sector development, and
regional integration. The major donors in Angola are the European Union, USAID, World
Bank, Italy and Norway. These donors focus on Health, Agriculture/Rural development,
Water, Infrastructure, Civil Society, Fishery Research and Human Rights.
1.3.2 While there is no formal donor coordination mechanism, an informal donor network
exists, through a thematic working group that meets as and when needed to discuss different
sectors (such as Social, Energy, Transport). With the opening of its field office in Angola, the
Bank aims to play a significant role in this working group.
1.3.3 There is no other major donor involvement in the project locations, apart from the
Bank financed Sumbe Water Supply, Sanitation and Institutional Support Project
(SWSSISP). Through cooperation between SWSSISP and the FSSP, potable water will be
provided to the Sumbe-Salinas landing site.
3
Table 1.1: Overview of Major Donor assistance in Angola
Sector or subsector Size
GDP Exports Labour force
Agriculture and
Fisheries sector
21.1% 5% 50 000 people
Players public annual Expenditure (2008 – 2011) average
Donors USD %
EU 64.0 33.26
USAID 44.5 23.13
World Bank 35.8 18.61
Italy 26.2 13.62
Norway 21.9 11.38
Total 192.4 100
Level of Donor Coordination
Existence of thematic Working Group Y
Existence of SWAPs or Integrated Sector Approaches N
ADB’s Involvement in donor coordination *** M [L/M/none]****
*As most appropriate ** Years [yy1 to yy2] ***for this sector or sub-sector
****L: leader, M: member but not leader, none: no involvement.
II. PROJECT DESCRIPTION
2.0.1 The sector goal of the project is to support sustainable exploitation of maritime
artisanal fishery; to create infrastructure for fish landings and conservation; improve the fish
distribution chain for frozen, salted and dried fish; and, improve the fish quality assurance
and inspection system in line with the overall sector objectives formulated by the
Government of Angola. The purpose of the project is to increase the income of artisanal
fishing communities through investments in fishery infrastructure and its management
(including marine resources and safety at sea)
2.0.2 The specific objective of the project is the reduction of Post-Harvest Losses and the
increase of fishers’ income through (i) Construction of new fish landing sites, (ii) Increasing
the community support function of fish landing sites, (iii) Establishment of sustainable
management of the fish landing sites, (iv) Monitoring, Control, and Management of the
artisanal fishing fleet and associated marine resources at the fish landing sites, (v)
Improvement of the management and monitoring of fishery resources.
2.1 Project components
2.1.1 The project is structured into three components: (A) Fishery Monitoring, Control and
Management; (B) Fishery Infrastructure Development; and, (C) Project Management. The
project will build four new Artisanal Fish Landing sites and improve the feeder roads to two
of these sites. Facilities provided at the landing sites will include cold storage, ice making
machines, and fish processing facilities, which are currently not available at the selected sites.
With these facilities and their proper management, post-harvest losses (currently estimated at
30% or around 7,000 mt) will be reduced. These landing sites will be managed according to a
management plan to be developed during the first year of the project.
4
2.1.2 A Vessel Monitoring System (VMS) will be installed in at least two sites (Egipto
Praia, Yembe), to enable the GoA to review options to increase the safety at sea for artisanal
fishers, and to manage fishery resources in a more sustainable manner. Two sites will be
rehabilitated (Ambriz and Dambe Maria) including putting in place a management system.
2.1.3 The ten sites of the Artisanal Fisheries Development Project (AFDEP) will be
supported with the installation of a fuel pump to reduce the burden of fishers to collect fuel
from fuel points far away their landing sites, and to increase the feasibility for private
management of the fishery infrastructure. With the provided facilities at the project fish
landing sites, traders will be sure of availability of (high quality) product at the sites. This
will therefore solidify the access of the involved fishing communities to markets. The two
feeder roads to Yembe and Egipto Praia will ensure year round access of traders to the fish
landing sites (the other sites are already accessible throughout the year).
2.1.4 The project does not aim to increase the total volume of landed fish, but aims at
reducing the quality losses after capture. Angola knows three quality categories (I, II, III)
with different pricings. Category I fetches the highest price, these are high-priced species
with a high quality. If the quality of the fish degrades, it will be classified one or two classes
lower according to the level of deterioration. The price of Category II is approximately 25%
of the Category I price.
2.1.5 Much of the fish at the selected landing sites is distributed in fresh form to the
domestic market. Currently, there is a significant quality (and therefore price-) loss in the
value chain caused by a lack of knowledge and skills in this respect. The project will address
these losses in quality through different actions; infrastructures (cold-rooms and ice making
machines) at project sites will prevent quality loss, and fishers/processors will be trained in
quality preservation and Post-Harvest Loss reduction techniques. Processors will also be
trained in appropriate transformation techniques, like fish salting, smoking and drying, while
others will learn to process slaughter waste into valuable fish meal, which can be used as a
component in animal feed.
2.1.6 The increased quality of the product will result in increased nutritional value for
consumers. The total monetary value of landed products (fish) will increase by at least ten to
fifteen per cent (10 – 15%). This increase will benefit fishers, processors and traders.
2.1.7 The direct beneficiaries are the fishing population of over 10,000 at the project sites
including women who constitute 80% of small scale fish processors and traders. Fishers will
receive more income (around 20%) through reduced post-harvest losses. The project will also
be of benefit to ancillary trades such as boat repair, net mending, transportation, petty trade
and overall economic activities in the project areas.
5
Table 2.1: Project Components
Component Costs
(UA mill)
Description
A
Fishery Monitoring,
Control and
Management 5.81
National Artisanal Fishing Vessel Frame Survey, including
socio-economic information done at the beginning of the project,
and at the end of the project, so that progress of Key
Performance Indicators can be followed
Artisanal Catch and Effort Assessment Survey System in place,
enabling IPA to make a reliable estimate of the production of the
artisanal fisheries sector
Institutional capacity building of IPA and the Ministry (fishery
management, data collection and management, infrastructure
management, languages) so that support with respect to the
landing sites is ensured after project completion
Awareness raising with respect to sustainable exploitation of
marine resources, through workshops/trainings at 16 sites
Management arrangements in place with respect to marine
resources attributed to 16 CPAs
VHF based Vessel Monitoring System established, through
placing at least two (2) VHF towers at Yembe and at Egipto
Praia, and providing all artisanal fishing vessels at those sites
with a vessel tracker
Implementation of the Environmental and Social Management
Plan
Support to the HACCP programme implemented by the Instituto
de Apoio as Indústrias de Pescas e Investigação Tecnológica
(INAPIT) and the National System of Inspection of Fishery
Products implemented by the National Direction of Fishery
Fish quality control, inspection, certification at Gilco landing
site, ensuring quality and safety of products entering the markets
HIV/AIDS awareness raising amongst fisher population
B Fishery Infrastructure
Development 14.88
Construction of four (4) artisanal fish landing sites/centers CPA
at Gilco, Yembe, Egipto Praia, and Salinas-Sumbe with ancillary
facilities and associated road works
Rehabilitation/improvement of two (2) landing sites at Ambriz
and Dambe Maria
Additional infrastructure at ten (10) CPAs supported during
AFDEP
Sustainable Management of the sixteen (16) CPAs, either
through private sector management, or other management
options
C Project Management 4.80
Planning, management, coordination and implementation of
project activities
Monitoring and evaluation
Provision of technical assistance
Procurement of relevant office equipment and vehicles
TOTAL 25.49
2.2 Technical solutions retained other alternatives explored
2.2.1 The design of the project follows the design of the AFDEP, with a shift in focus
towards greater private sector engagement. Alternative approaches could have been: support
to fishery research, or support of the industrial fisheries sector. These were not chosen, as
other donors are supporting fishery research.
6
Table 2.2: Project alternatives considered and reasons for rejection
Alternative Name Brief Description Reasons for Rejection
Fishery Research Through research providing
information for the sustainable
management of the marine
aquatic resource
Angola receives already support in this field, through
the SAP-Imp project and through the EAF-Nansen
project (supported by NORAD)
Industrial
Fisheries
Supporting the
construction/rehabilitation of a
fishing port
No direct impact for poverty alleviation
2.3 Project Type
This is a stand-alone project following up on an earlier intervention, the Artisanal Fisheries
Development Project, which was funded by the Bank in 2002. The AFDEP project was
successfully completed in 2011.
2.4 Project costs and financing arrangements
2.4.1 Project Costs: The total costs for the project, is estimated at UA 25.49 Million,
comprising 64% in foreign cost and 36% in local costs. Physical and price contingencies
were estimated at 7% and 10%, respectively based on actual and projected levels of local and
foreign inflation rates. Physical contingencies are low given the information available from
completed civil works and goods purchased in the former fisheries project. A summary of the
project cost estimates by components and expenditure accounts is shown in Tables 2.3 and
2.4 below, while details are captured in the annexes.
Table 2.3:
Fisheries Sector Support Project - Summary Costs by Components
COMPONENTS
US$ ‘000 UA ‘000 %
F.E
%
Base
Cost
Local
Currency
Foreign
Exchange Total
Local
Currency
Foreign
Exchange Total
Fishery Monitoring, Ctrl & Mgt 1 617,00 6 468,00 8 085,00 1 038,91 4 155,64 5 194,55 80 24
Fishery Infrastructure Dvpt 5 062,94 14 758,81 19 821,75 3 252,90 9 482,42 12 735,31 74 58
Project Management 4 329,09 1 704,71 6 033,81 2 781,41 1 095,27 3 876,67 28 18
Total BASELINE COSTS 11 009,03 22 931,53 33 940,56 7 073,21 14 733,32 21 806,53 68 100
Physical Contingencies 580,62 1 753,75 2 334,37 373,05 1 126,77 1 499,81 75 7
Price Contingencies 2 621,85 779,50 3 401,35 1 684,52 500,82 2 185,34 23 10
Total PROJECT COSTS 14 211,50 25 464,77 39 676,28 9 130,77 16 360,91 25 491,68 64 117
7
Table 2.4: Fisheries Sector Support Project - Summary Costs by Expenditure Accounts
EXPENDITURE
ACCOUNTS
US$ ‘000 UA ‘000
% F.E % Bc Local
Currency
Foreign
Exchange Total
Local
Currency
Foreign
Exchange Total
INVESTMENT COSTS 6 883,79 22 621,65 29 505,43 4 422,78 14 534,22 18 957,00 77 87
WORKS 3 982,44 11 947,31 15 929,75 2 558,68 7 676,05 10 234,73 75 47
Construction & Rehab. 1 048,13 3 144,38 4 192,50 673,41 2 020,24 2 693,65 75 12
Public Utilities 50,00 150,00 200,00 32,12 96,37 128,50 75 1
Roads 2 884,31 8 652,94 11 537,25 1 853,15 5 559,44 7 412,59 75 34 GOODS 793,35 1 888,65 2 682,00 509,72 1 213,44 1 723,16 70 8
Vehicles 56,25 168,75 225,00 36,14 108,42 144,56 75 1
Equipment 737,10 1 719,90 2 457,00 473,58 1 105,02 1 578,60 70 7 SERVICES 2 108,00 8 785,69 10 893,69 1 354,37 5 644,73 6 999,10 81 32
Training 765,00 765,00 1 530,00 491,51 491,51 983,01 50 5 Technical Assistance - 4 111,69 4 111,69 - 2 641,72 2 641,72 100 12
Contractual Services 1 263,00 3 789,00 5 052,00 811,47 2 434,40 3 245,87 75 15
Audit 80,00 120,00 200,00 51,40 77,10 128,50 60 1 RECURRENT COSTS 4 125,24 309,88 4 435,12 2 650,43 199,09 2 849,53 7 13 PERSONNEL 3 450,00 - 3 450,00 2 216,60 - 2 216,60 - 10 DSA 567,00 189,00 756,00 364,29 121,43 485,72 25 2 O&M 14,74 27,38 42,12 9,47 17,59 27,06 65 -
Equipment 4,69 8,71 13,40 3,01 5,60 8,61 65 - Vehicles 10,05 18,67 28,72 6,46 11,99 18,45 65 -
Infrastructures - - - - - - - - GOC 93,50 93,50 187,00 60,07 60,07 120,15 50 1
Total BASELINE COSTS 11 009,03 22 931,53 33 940,56 7 073,21 14 733,32 21 806,53 68 100
Physical Contingencies 580,62 1 753,75 2 334,37 373,05 1 126,77 1 499,81 75 7
Price Contingencies 2 621,85 779,50 3 401,35 1 684,52 500,82 2 185,34 23 10
Total PROJECT COSTS 14 211,50 25 464,77 39 676,28 9 130,77 16 360,91 25 491,68 64 117
Table 2.5:
Fisheries Sector Support Project - Summary Costs by Year (‘000 UA)
COMPONENTS 2013 2014 2015 2016 2017 TOTAL
Fishery Monitoring, Control & Mgt 2 413,07 1 171,95 1 133,38 570,62 520,17 5 809,18
Fishery Infrastructure Development 2 974,34 8 345,61 3 557,89 - - 14 877,84
Project Management 1 650,08 699,92 764,97 820,42 869,28 4 804,66 TOTAL 7 037,48 10 217,48 5 456,24 1 391,03 1 389,45 25 491,68
2.4.2 Project Financing: The Bank will provide a loan to the tune of UA 20.00 Million
from ADF XII resources, representing 78.50% of the project cost, excluding taxes and duties.
The ADF financing will be in the form of a loan. The remaining balance of the project costs
amounting to UA 5.49 Million or 21.50% of the total project cost will be covered by the
Government of Angola. The detailed breakdown of financing for the project has been
captured in Annex B2. A summary of the project costs financing estimates by source of
finance is shown in Tables 2.6, 2.7 and 2.8 below:
8
Table 2.6: Fisheries Sector Support Project - Financing Plan
Sources of Finance
FINANCING SOURCE (‘000 US$) (‘000 UA)
% Local Foreign Total Local Foreign Total
Government of Angola 6 690,69 1 856,79 8 547,48 4 298,71 1 192,97 5 491,68 21,5
ADF Loan 7 520,81 23 607,99 31 128,80 4 832,06 15 167,94 20 000,00 78,5
Total 14 211,50 25 464,77 39 676,28 9 130,77 16 360,91 25 491,68 100,0
Table 2.7:
Fisheries Sector Support Project - Financing Plan
Sources of Finance per component
COMPONENTS ADF Government Total
UA ‘000 % UA ‘000 % UA ‘000 %
Fishery Monitoring, Ctrl & Mgt 4 624,95 79,6 1 184,23 20,4 5 809,18 22,8
Fishery Infrastructure Development 14 460,85 97,2 416,98 2,8 14 877,84 58,4
Project Management 914,19 19,0 3 890,47 81,0 4 804,66 18,8 TOTAL 20 000,00 78,5 5 491,68 21,5 25 491,68 100,0
Table 2.8
Expenditure Accounts by Financiers (‘000 UA)
EXPENDITURE ACCOUNTS ADF % Government % Total %
INVESTMENT COSTS 20 000,00 91,7 1 813,31 8,3 21 813,31 85,6
WORKS 12 048,26 98,8 148,02 1,2 12 196,28 47,8
Construction & Rehab. 3 201,45 100,0 0,00 - 3 201,45 12,6
Public Utilities - - 148,02 100,0 148,02 0,6 Roads 8 846,81 100,0 0,00 - 8 846,81 34,7 GOODS 1 657,88 86,9 249,74 13,1 1 907,62 7,5
Vehicles 162,85 100,0 0,00 - 162,85 0,6 Equipment 1 495,02 85,7 249,74 14,3 1 744,76 6,8 SERVICES 6 293,87 81,6 1 415,55 18,4 7 709,42 30,2
Training 1 158,06 100,0 0,00 - 1 158,06 4,5
Technical Assistance 2 354,53 81,6 532,58 18,4 2 887,11 11,3 Contractual Services 2 626,11 74,8 882,97 25,2 3 509,08 13,8
Audit 155,17 100,0 0,00 - 155,17 0,6 RECURRENT COSTS - - 3 678,37 100,0 3 678,37 14,4
PERSONNEL - - 2 877,95 100,0 2 877,95 11,3 DSA - - 635,14 100,0 635,14 2,5 O&M - - 34,30 100,0 34,30 0,1
Equipment - - 11,03 100,0 11,03 -
Vehicles - - 23,27 100,0 23,27 0,1 Infrastructures GOC - - 130,98 100,0 130,98 0,5
TOTAL 20 000,00 78,5 5 491,68 21,5 25 491,68 100,0
2.5 Project Target Areas and Beneficiary population
2.5.1 The project target areas are the rural coastal communities of Gilco, Yembe, Egipto
Praia, Salinas-Sumbe, Ambriz, Dambe Maria (selected on the basis of daily fish catches,
fishing population and market coverage among others) and the ten (10) sites of the AFDEP.
The total number of the fishing population of these sites stands around 10,000. Currently,
about 80% of small scale fish processors and traders are women. The project outcomes for
this target group are the reduction of PHL and increased incomes. There will also be benefits
to ancillary trades such as boat repair, net mending and overall economic activities in the
project areas.
9
2.6 Participatory process for identification, design and implementation
2.6.1 Beneficiaries and other relevant stakeholders participated during the identification
(August 2010), preparation (September 2011) and appraisal (January 2012) of this operation.
At each potential project site, a meeting with local stakeholders was organized. During these
meetings an overview of the situation of the site was elaborated upon with the stakeholders
(number of people, number of vessels, species fished on, processing methods, etc). Based on
the overview, a fishery infrastructure needs assessment was conducted and an estimate of the
yearly production was made.
Landing site Processing
area
Ice
machine
Cold
storage
Quay Fuel
point
Road Management Yearly
production
(mt)
Gilco Y Y Y N Y N P 9460
Egipto Praia Y Y Y Y Y Y C 5924
Yembe Y Y Y N Y Y P/C 2974
Sumbe Y Y Y N Y N P 2750
Ambriz N R R N N N P 1342
Dambe Maria N R R N N N P 1162 Y = Yes, N = No, R = Rehabilitation, P =Private, C = Community
2.6.2 Communities expressed a strong desire for ice making machines, cold storage,
processing facilities, and improvement of the access road to allow communication in the
rainy season (Egipto Praia and Yembe). The communities were also assessed with respect to
their management capacities. The Angolan Institute for the Development of Artisanal
Fisheries (IPA) was part of the appraisal team and agreed with the sites proposed. All
stakeholders will be represented in the infrastructure management committees and the marine
natural resources management committees to ensure sustainability of project achievements.
2.7 Bank Group experience, lessons learnt in project design
2.7.1 Based on lessons learnt from the AFDEP, advance contracting will be used for the
procurement of services for the design and implementation of the baseline surveys (the frame
survey, including socio-economic indicators) and the design and supervision of the landing
sites. The artisanal fishery development project had problems in retaining staff, and therefore
not all positions required for project implementation were filled. With competitive
remuneration, staff will be retained and the Project Implementation Office (PIO) shall have
the full complement required to implement the project as detailed in paragraph 4.1.1.
2.7.2 Lessons learnt from the AFDEP in Angola and other AfDB fishery projects in Africa
include, but are not limited to (see also paragraph 1.2.25 of the technical annex): (i)
management of infrastructures should be addressed during the start of the project; (ii) staff
retention should be a priority; (iii) official documents should be translated into Portuguese;
(iv) baseline-surveys should be carried out at the beginning of the project; (v) project
implementation should be anchored in the government structures for sustainability purposes;
(vi) a comprehensive ESMP design and implementation is needed; and, (vii) credit for fishing
and fish marketing has a weak record in most Bank supported fishery projects, and was
therefore avoided. Procurement and disbursement arrangements need to be tailored to the
specific conditions of Angola with limited use of ICB/NCB for goods and services widely
available in the local market.
10
2.7.3 The Bank’s current portfolio performance has been weak. This was mainly due to
absence of local Bank representation, project units operating as almost autonomous units and
not being embedded in Government structures; weak internal controls with respect to
financial management; and weak capacity within the project implementation units with
respect to application of Bank’s procurement rules and procedures. In the design of the
proposed project, emphasis has been put on anchoring the project in the National Institute for
Artisanal Fisheries and Aquaculture (IPA). This will ensure a continuous exchange of
information on the project, and its implementation, and will ensure the sustainability of the
project. The FSSP will not have a Special Account for Bank resources, avoiding
disbursement issues in this respect. Once the project has started, its capacity with respect to
procurement and disbursement will be supported through dedicated training and support from
the Bank’s Field Offices in Angola and South Africa.
2.8 Key Performance Indicators
2.8.1 Progress towards achieving income increase in fishing communities will be measured
through a baseline, midterm and project-end socio-economic surveys. With respect to PHL
reduction, achievements will be measured through combining the Catch and Effort
Assessment Survey (CAS) and product marketing survey. The M&E Specialist of the PIO
will be responsible for this assignment in cooperation with IPA and FAO. An MoU will be
concluded between FAO and the project to cover technical assistance for the artisanal fishing
vessel frame survey (including socio-economic data), basic fisheries data collection set-up
(Catch and Effort records), post-harvest loss assessment, reduction of post-harvest losses,
marine fishery resources management, and fishery infrastructure management.
2.8.2 The key performance indicators to be monitored include: (i) reduction of lives lost,
(ii) No. of incursions per year (iii) percentage reduction of post-harvest losses (value), (iv)
Coverage of inshore area by VHF MCS system and no. of towers built, (v) No. of vessels
equipped with a vessel tracker unit, (vi) No. of fish quality samples taken and tested, (vii)
Number of functioning fishery resource and infrastructure management committees in project
sites, and (viii) Number of Landing sites constructed and improved.
2.8.3 In particular, the numbers of women serving on the committees for management of
fishery infrastructure and the committees for management of the marine natural resources and
also the number of women trained during project implementation will be closely monitored to
ensure the set targets are met.
III. PROJECT FEASIBILITY
3.1 Economic and Financial Performance
3.1.1 The financial and economic analyses were carried-out on the basis of the assumptions
that the successful implementation of the project would generate the following three (03)
types of benefits: (i) Increased quality, volume and value of marketed fish; (ii) Temporary
and permanent jobs creation; and (ii) improved population livelihood.
3.1.2 Financial Analysis: The financial analysis was carried-out on the basis fishing
activity models for a 20-year period and about 980 fishing boats producing 35,000 mt tons
annually or 170 kg per unit in 210 rotations per year. Post-harvest losses is currently
estimated to be 7,000 mt (valued at about US$ 7 Million), which the project is expected to
11
reduce by 20%. In this context, only 70 % represent premium market fish valued at
US$ 3,500 per ton out of a total marketable production of 28,000 mt in the without project
situation. The remaining production corresponds to 20 % of medium quality value at
US$ 1,000.00 per ton, and 10 % for household for consumption. Current average incomes per
fisher are estimated at US$840 per annum. With the project support, incomes are expected to
rise to at least US$1,010 per annum per fisher.
3.1.3 The expected reduction of 20% in post-harvest losses sets marketable volume to
29,400 mt of which premium and medium quality represent 85 % and 5%, in the with- project
situation. In addition, the project is also expected to generate temporary and permanent
employments with an estimated financial benefit of US$ 7.69 Million p.a. On the basis of
these assumptions, the project worth came out with an IRR of 17.59% and net present value
of 83.99 Million. The IRR and NPV are greater than the opportunity cost of capital (OCC)
estimated at 12% and zero, respectively.
3.1.4 Economic Analysis: The economic analysis was carried-out on the basis of fishing
activity models and economic prices and cost. The economic cost was generated from
COSTAB, on the basis a standard conversion factor (SCF) of 0.95, which was also used for
the shadow pricing of benefits from tradable goods, corresponding to the volume of premium
quality fish, on the basis the following formula:
SER = OER*(1+FxP) or OER/SER=1/(1+FxP) = SCF or SER=OER/SCF ▪Where SER = shadow exchange rate; OER = Official exchange rate; FxP= Foreign exchange premium; and
SCF=Standard conversion factor
3.15 In addition, cost of labour was adjusted to a conversion factor of 0.65, as a non-
tradable and inelastic good, due to unemployment. Furthermore, fish consumption volumes
were included as substitutes for marketed protein. Finally tax, subsidies and interest payments
were also removed from financial values and prices, so as to reflect costs and benefits to
society, in the process of computing costs and benefits in situations with and without project.
As a result of the computation, the economic analysis yielded, based on the above
assumptions a combined net economic impact (NPV) of about US$ 97.58 million for a 20-
year operational period and ERR (economic rate of return) of 22.45%. This outcome means
that the economic feasibility of the project is even higher than the financial feasibility, or the
value to society for the establishment of fisheries infrastructures is even higher than the cash
value of its benefits. The detailed economic analysis of the program is captured in the
technical annexes of the current report.
3.2 Environmental and Social Impacts
3.2.1 The project has been classified as Environmental Category II according to the Bank’s
Environmental and Social Assessment Procedures (ESAP) (August 2011), as it is expected to
have site-specific and short-term negative impacts largely occurring during the construction
phase. Overall, the project is expected to generate positive social-economic and environment
benefits leading to improved environmental and socio-economic conditions of the fisher
communities at the project sites. Potential negative impacts will likely occur during the
construction of the fish landing sites, fish processing facilities, water supply and sanitation,
and waste management system. The envisaged impacts include noise and vibration, dust, soil
erosion and water pollution. An Environmental and Social Management Plan has been
prepared elaborating the mitigation and monitoring measures to be undertaken during project
implementation. They include sprinkling water at the construction sites to suppress dust,
12
providing erosion control measures to reduce soil and water pollution, proper selection of
borrow pits and rehabilitation with vegetation after decommissioning. To address the current
practice of discarding slaughter waste at sea and on land (approximately 20% of catch), the
project will support facilities for processing waste into animal feed. Both waste management
and potable water availability at all sites will improve sanitary conditions at landing sites and
reduce spread of infectious diseases such as cholera.
Climate change
3.2.2 Data on specific impacts of climate change on the Angola fisheries sector is not
comprehensive. The predicted variations in temperatures, precipitation, storm frequency and
intensity and the changes in the Benguela current are expected to have an impact on
productivity of ecosystems and hence the quantity and distribution of fish species. The
National Adaptation Plan of Action (NAPA) priorities published in December 2011 include
the need for a study on the exact impacts of climate change on the fisheries sector, given its
vulnerability. The vulnerability of the sector is due to the level of dependence on fisheries in
specific sites and the adaptive capacity in the sector. As such, the mitigation measures
included in the project are in capacity building to raise awareness on impacts of climate
change and the dissemination of knowledge on adaptation measures. The project will provide
information on fish landings to support the NAPA objectives. With respect to infrastructure,
sites have been selected at locations with some natural protection and the design of
infrastructure will take cognisance of the potential impact of climate change, while the VMS
will be able to issue storm warnings.
Gender
3.2.3 In Angola it is estimated that 80% of small scale fish traders and processors are
women1. The fish processing facilities at each of the landing sites will thus be mainly of
benefit to the women in the fishing communities. Much of the fish at the selected landing
sites is distributed in fresh form to the domestic market. Currently, there is a significant
quality (and therefore price-) loss in this value chain caused by a lack of knowledge and skills
with respect to quality preservation. At the project sites, infrastructures (cold-rooms and ice
making machines) will prevent quality loss, while processors will be trained in quality
preservation and Post-Harvest Loss reduction techniques. Processors will also be trained in
appropriate transformation techniques, like fish salting, smoking and drying, while others will
learn to process slaughter waste into valuable fish meal, which can be used as a component in
animal feed. Women and youth make up 60% of the population in the selected fishing
communities and the improved fish production is expected to result in increased incomes for
the fish traders and to provide employment for some of the youth during the project
implementation phase and the management of the sites.
3.2.4 The project implementation is expected to enhance the roles of women in the fishing
communities. Key Performance Indicators data to be collected in this respect are: Household
incomes of the coastal population, Distribution of male versus female in the Management
committees, Volume of trade per vendor at the project sites, Number of businesses at the
landing sites, number of processing facilities, including the gender of the management. All
data collected will be gender dis-aggregated.
1 FAO Fishery Sector Overview, ftp://ftp.fao.org/FI/DOCUMENT/fcp/en/FI_CP_AO.pdf
13
3.2.5 The baseline survey of family living conditions will show the proportion of female-
headed households which most likely will be high, after 30 years of internal conflict. Thus
the project, in addition to rehabilitating infrastructure to support the reduction of post-harvest
losses, will support women to better organise themselves in production and marketing, and
contribute to the development of women’s associations. The project will systematise the
representation of women and the youth in resource and infrastructure management decision-
making bodies to enable them to fully defend their interests and thus gradually improve their
status and empower themselves. In collaboration with NGO’s and the Gender Institutions, the
project will carry out training in gender equality for the various parties involved (project
staff, technical services, partner institutions, etc.).
Social Impacts
3.2.6 The project will improve the quality of fish being landed thus increasing the value and
reducing post-harvest losses, which are currently estimated at 30-35%. Through the reduction
of PHL fishers and processors will handle more, higher quality product and thus have a
higher income. The construction works will provide short term employment for some of the
community members while the operation of the landing sites will provide more long term
employment opportunities. The project infrastructure will improve the well-being and
hygiene of the communities through the provision of sanitary facilities and waste
management system. This will reduce the disease burden on the community and the time
spent in search of potable water. The HIV prevalence rate is higher in the fishing
communities compared to the national prevalence rates. Therefore the project has included
HIV/AIDS awareness and sensitisation activities for the communities. The project is not
expected to result in any major negative social impacts.
Involuntary resettlement
3.2.7 The project will not involve any involuntary resettlement
IV. IMPLEMENTATION
4.1 Implementation Arrangements
Executing Agency
4.1.1 The Ministry of Fisheries (MoF) is the executing agency and will be responsible for
overseeing the overall implementation of the project. A Project Implementation Office (PIO)
in the National Institute for Development of Artisanal Fisheries and Aquaculture (IPA) will
manage the day-to-day activities of the project. The PIO will be headed by a Project
Coordinator (PC). The Project Coordinator will be supported by staff seconded from IPA or
the MoF, especially the Fisheries Specialist, the Environmental Management Specialist, the
Community Development Specialist, and the Monitoring and Evaluation Specialist
knowledgeable in fisheries statistics. This will ensure ownership of the project in the MoF,
and IPA. If these four positions cannot be filled by staff from IPA or the Ministry they will be
recruited competitively. The Civil Engineer/Quantity Surveyor, Procurement Specialist,
Accountant, and Book Keeper will be recruited competitively. All proposals with respect to
project staff will be submitted to the Bank for review and No Objection. A Project Steering
Committee (PSC), chaired by the Director of IPA, will provide policy guidance and oversee
14
project implementation. The Project Coordinator will act as the PSC Secretary. The PSC will
meet at least twice a year. At the project sites the district officers of IPA will play a pivotal
role with respect to project activities. They will coordinate all activities at their site with the
support from the Implementation Office in Luanda. The road works will be under the general
oversight of the local governments (Benguela Provincial Government for Egipto Praia and
Bengo Government for Yembe) supported by the Consulting Engineer.
Table 4.1: Breakdown of project costs by procurement methods
ANGOLA
FISHERIES SECTOR SUPPORT PROJECT Procurement Arrangements - Non ICB/NCB/QCBS Aggregated as Other
(UC '000)
PROCUREMENT ACCOUNTS
Procurement Method
ICB LIB NCB QCBS Other N.B.F. Total
A. GOODS Vehicles - - - - 162,85 - 162,85
[162,85]
[162,85]
Equipment 935,28 437,04 - - 372,44 - 1 744,76
[935,28] [187,30]
[372,44]
[1 495,02]
B. WORKS Construction & Rehabilitation 2 678,06 - 523,39 - - - 3 201,45
[2 678,06]
[523,39]
[3 201,45]
Public Utilities - - - - - 148,02 148,02
Roads 8 846,81 - - - - - 8 846,81
[8 846,81]
[8 846,81]
C. SERVICES Training - - - 988,54 169,52 - 1 158,06
[988,54] [169,52]
[1 158,06]
Technical Assistance - - 638,25 2 248,86 - - 2 887,11
[638,25] [1 716,28]
[2 354,53]
Contractual Services - - - 1 542,07 1 967,01 - 3 509,08
[1 233,66] [1 392,45]
[2 626,11]
Audit - - - 155,17 - - 155,17
[155,17]
[155,17]
D. PERSONNEL - - - - - 2 877,95 2 877,95
E. OPERATING COSTS - - - - - 800,42 800,42
Total 12 460,14 437,04 1 161,64 4 934,64 2 671,82 3 826,39 25 491,68
[12 460,14] [187,30] [1 161,64] [4 093,65] [2 097,26] - [20 000,00]
Note: Figures in parenthesis are the respective amounts financed by ADF Loan
Procurement Arrangements
4.1.2 Following the assessment of the National Procedures and Regulations (NPP) and
bidding documents for procurement of Goods and Works under NCB done by the Bank in
October 2011, it was noted that the NPP are generally consistent with the Bank Rules and
Procedures. Principles under the new Law are in line with procurement best practices
regarding fairness, transparency, competitiveness and cost effectiveness. On the other hand
the assessment noted that the Regulations and Standard Bidding Documents (SBDs)
complementing the new law have not yet been developed to give effect to the implementation
of the law. The National Competitive Bidding Procedures (NCB) have been found to be
generally compliant with international acceptable practices, however, some deviations need
15
to be addressed in order to make NPP comply with Bank rules and procedures. Angola has
also not developed national SBDs for procurement of Goods and Small Works.
4.1.3 In view of the above, all procurement under the project done by NCB will be subject
to the Bank’s Rules and Procedures for the Procurement of Goods and Works, May 2008
edition and as amended from time to time using the relevant Bank’s SBDs. The various items
under different expenditure categories and related procurement arrangements are summarized
in Table 4.1 above. Each contract to be financed by the Loan, the different procurement
methods or consultant selection methods, the need for prequalification, estimated costs, prior-
review requirements, and time frame are agreed between the Borrower and the Bank project
team and are provided in the Procurement Plan in technical annex B5. Further details with
respect to Procurement arrangements can be found in Technical Annex B5 Procurement
Arrangements.
Disbursement Arrangements
4.1.4 The Direct Payment Method will be used for the disbursement of the loan resources
according to the Disbursement Handbook of the Bank. Where necessary, the reimbursement
method will be used for eligible expenses. The PIO will open an account into which the
Government will make its counterpart contribution.
Financial Management
4.1.5 The Project accountant will be responsible for ensuring the maintenance, at all times,
of satisfactory and professionally acceptable accounting records and asset registers in
accordance with Bank guidelines. In addition, The PIO will ensure that adequate internal
control systems are maintained. The project accounts will be audited annually by an
independent audit firm recruited through Least Cost Selection. Annual audit reports will be
submitted to the Bank not later than six (6) months after the end of each financial year. The
PIO will also submit regular quarterly and annual progress reports in accordance with the
Bank Group reporting guidelines. The PIO will use the administrative manuals which are
already in use by the other AfDB projects in the Agriculture and Environment Sectors as a
basis for the FSSP administrative manual.
4.2 Monitoring and Evaluation
4.2.1 For the monitoring and evaluation of the project, a number of milestones have been
established during the entire 5-year implementation period to ensure activities are effectively
implemented as planned. The M&E Specialist will be responsible for all M&E activities,
other duties will be assigned to specific staff of the PIO. All socio-economic surveys and,
where possible, other surveys, will collect gender disaggregated data. Some indicators to be
collected will be: income gender-disaggregated, percentage of female-headed households,
Number of people (gender disaggregated) sensitized in gender issues, number of participants
in trainings (gender disaggregated), and management committee members (gender-
disaggregated)
4.2.2 With respect to Monitoring and Evaluation the project will be supported by FAO, a
centre of excellence, which has experience with similar projects in the region. FAO will assist
with the implementation and analysis of the data of these surveys. The M&E framework will
require strong engagement of beneficiaries in order to better determine the impact of the
16
project on their welfare. The M&E system will demonstrate impacts on the local economy
through linkages with other sectors.
Timeframe Milestone Monitoring process feedback loop
Yr 0 Design of New infrastructure (4 sites) PC, Proc S, CE, & M&E, Consultant reports
Yr 0 Design of Rehabilitation structures (2 Sites) PC, Proc S, CE, & M&E, Consultant reports
Yr 0 Design of additional works (10 sites) PC, Proc S, CE, & M&E, Consultant reports
Yr 0 Baseline Survey (Socio-Eco, CAS, Marketing) FS, CDS, M&E reports
Yr 2 VMS in place PC, FS
Yr 3 4 sites ready PC, Proc S, CE, & M&E, Consultant reports
Yr 3 2 sites rehabilitated PC, Proc S, CE, & M&E, Consultant reports
Yr 3 10 sites with additional works ready PC, Proc S, CE, & M&E, Consultant reports
Yr 3 Mid-term Survey (Socio-Eco, CAS, Marketing) FS, CDS, M&E reports
Yr 4 Infrastructure management in place (16 sites) PC, FS, CDS reports
Yr 4 Resource management in place (16 sites) PC, FS, CDS reports
Yr 5 End Survey (Socio-Eco, CAS, Marketing) FS, CDS, M&E reports
4.3 Governance
4.3.1 The main governance issues relate to bidding and contracting procedures for the
various contracts under the project. To avert irregularities in the bidding processes the
standard Bank rules and procedures will be used. In addition, the Project Steering Committee
(PSC) will play an important over-sight role to ensure that procurement procedures are
transparent and competitive. The PSC will be constituted by members from key Ministries
and beneficiary representatives (see paragraph 2.3.2 of the technical annex). The PIO will
maintain up-to-date books of accounts and asset registers for the project. The books of
accounts and asset registers will be audited by an independent audit firm to ensure that
project resources are used efficiently and effectively for intended purposes.
4.3.2 Another governance issue relates to sustainable management of marine resources.
Currently there is a lack of sufficient information on artisanal fisheries to base sustainable
management on. Through the project an artisanal fishing vessel frame survey will be
conducted, which will serve as the basis for a catch and effort assessment survey system
(CAS). This CAS will provide additional information to base sustainable fisheries
management on. Through the VMS the enforcement of measures with respect to closed areas,
or seasons, will be facilitated, which is also improving governance.
4.4 Sustainability
Sustainable Resource Use
4.4.1 The implementing agency (IPA) has the mandate to ensure sustainable use of Marine
Fishery Resources. With the support from FAO, information with respect to targeted fish
stocks attributed to the project landing sites will be improved, allowing better informed
management decisions on the exploitation of the fish stocks. Also, with FAO support, the
IPA will work with the communities to draw up a fishery resource management plan which
will be adopted at each landing site. The management plans will have as objective to
maximise the yield of the marine fishery resources in a sustainable way, to support the
incomes of the fishing communities involved.
17
Infrastructure Management
4.4.2 All stakeholders will be involved in the implementation of the management structure
of the landing sites, ensuring ownership of the management process. These management
structures will deal with the daily running of the sites, and will be guided by an infrastructure
management committee at each site. The management committee will ensure that the landing
site will be run in an economically viable manner, ensuring the sustainability of the structures
(covering not only maintenance costs, but also depreciation) and the provision of services for
an acceptable cost to the communities involved. Boat landing fees will contribute to cost
recovery towards maintenance of the infrastructure while the ice making and cold storage
facilities will be run on commercial terms by private sector entities.
IPA Support
4.4.3 The project provides for strengthening of human and institutional capacity of IPA at
headquarters and provincial offices, including infrastructure management capacities. After
the end of the project, IPA/GoA will be able to continue supporting the fishing communities
with respect to sustainable management of fishery resources and fishery infrastructures.
4.5 Risks Management
4.5.1 Based on experiences of the Artisanal Fisheries Development Project and other
fisheries projects in the region five risks to the FSSP implementation have been identified.
4.5.2 The global economic crisis and rising food prices on the world market might have a
negative impact with respect to reducing poverty and increasing food security. By focusing
on local market development, the project will not increase the dependence of participating
communities on the global market forces and minimize the impact of these risks on the target
population.
4.5.3 The project will ensure that Monitoring, Control and Surveillance of the Artisanal
Fisheries Zone attributed to the project fish landing sites will be improved. Fishers and other
stakeholders at the landing sites will be trained in fisheries management, including ways of
enforcement of management decisions. Communication channels with the fishery inspection
service will be established, ensuring that sightings of illegal (industrial) vessels will be
reported and acted upon. The encroachment by the industrial fleet of the artisanal fisheries
zone will be prevented, preventing destruction of gear of artisanal fishers, and the depletion
of fish stocks in the artisanal fisheries zone by the industrial fleet.
4.5.4 Through training and awareness campaigns at the project fish landing sites, fishers
will be made aware of the advantages of vessel tracker units on fishing vessels with respect to
safety at sea (in an emergency a distress signal indicates which position the vessel in distress
has). This will reduce the reluctance of fishers to install vessel trackers on their vessels
4.5.5 Stakeholders at the project fish landing sites will be trained in the benefits of
sustainable fishery management, including ways to participate in making fishery management
decisions in the fishery management committees to be established at the project fish landing
sites. Through this training participation by all stakeholders in fishery management
committees will be ensured.
18
4.5.6 Fishery data collection needs to be done routinely to establish the status and trends of
the fishery, needed to make informed fishery management decisions. However, data
collection schemes implemented by the Government only would be too costly to be
sustainable. Through participation of the stakeholders at the landing sites, including the
fishers, the cost of this data collection can be reduced, ensuring sustainability.
4.6 Knowledge Building
4.6.1 The project is expected to generate considerable knowledge, lessons and experiences
that will add value and build up a knowledge-base to inform the design and management of
similar projects in other RMCs. The effectiveness of various fishery infrastructure
management options will be evaluated. An assessment of PHL will be made and poverty
levels of population at the project sites will be monitored.
4.6.2 A report on the fishery infrastructure management will be produced. A frame survey
will form the basis for the basic fisheries data collection through the CAS. This will provide
information on the use of the marine fishery resources. PHL will be assessed by comparing
landed against marketed production. Through three socio-economic surveys, information will
be available to track incomes of fishers and processors over the project life and beyond.
4.7 Bank’s Field Office
4.7.1 The African Development Bank Field Office (AOFO) in Luanda will support the
project through assisting with the preparation of documents, monitoring of progress, and
interface between different Bank projects for periodic meetings, where exchanges of
experiences and lessons will take place. To this end a project monitoring and tracking tool
has been finalised by AOFO. Furthermore the Bank’s Field office will liaise between the
Project and responsible officers in the Bank.
V. LEGAL INSTRUMENTS AND AUTHORITY
5.1 Legal instrument
The project will be financed pursuant to an ADF loan agreement between the
Borrower and the ADF
5.2 Conditions associated with Bank’s intervention
Conditions for Bank’s first disbursement/effectiveness
5.2.1 Conditions for effectiveness: The Loan Agreement will enter into force upon
fulfillment by the Borrower of the provisions of Section 12.01 of the General Conditions.
5.2.2. Conditions Precedent to First Disbursement of the Loan: The obligations of the Fund to
make the first disbursement of the Loan shall be conditional upon the entry into force of the
Loan Agreement and the fulfillment by the Borrower, in form and substance satisfactory to the
Fund, of the following condition:
(i) Provide evidence of the recruitment of a Project Coordinator whose qualifications and
experience shall be acceptable to the Fund.
19
5.2.3. Other Conditions: The Borrower shall, in form and substance satisfactory to the Fund,
fulfill the following conditions:
(i) Provide, within six (6) months after the first disbursement, evidence of the recruitment
of: (a) a fisheries specialist; (b) an environmental management specialist; (c) a
community development specialist; (d) a monitoring and evaluation specialist
knowledgeable in fisheries statistics; (e) a civil engineer/quantity surveyor; (f) a
procurement specialist; (g) an accountant; and (h) a book keeper; whose qualifications
and experience shall be acceptable to the Fund;
(ii) Provide, within six (6) months after the first disbursement, evidence of the
establishment of a Project Steering Committee (PSC) consisting of the following
members/representatives of: Minister of Fisheries (Chairperson), Ministry of Finance,
Ministry of Planning, Ministry of Environment, Ministry of Public Works and Roads,
Women Promotion Ministry, Representatives of the community development
committee; and
(iii) Provide, within twelve (12) months after the first disbursement, evidence of the
completion of: (a) the FAO supported artisanal fishing vessel frame survey; and (b)
the socio-economic survey.
5.2.4 Undertaking: The Borrower undertakes, in form and substance satisfactory to the Fund,
to:
i) carry out, and require its contractors to carry out, the Project in accordance with the
recommendations, standards and procedures set forth in the ESMP; and
ii) deliver to the Fund project quarterly reports, describing the Borrower’s
implementation of the ESMP (including any implementation failures and related
remedies, if any).
5.3 Compliance with Bank Policies
This project complies with all applicable Bank policies.
VI. RECOMMENDATION
6.0.1 Management recommends that the Board of Directors approves a loan not exceeding
an amount of UA 20 million to the Republic of Angola for the purposes and subject to the
conditions and modalities stipulated in this report.
II
Appendix II: Table of AfDB’s portfolio in Angola
On-Going Portfolio In Angola (UA millions)
PROJECT SECTOR APPROVAL
DATE
EFFECTIVE
DATE
CLOSING
DATE
TOTAL
COST
TOTAL
DISBURSED
%
DISBURSE
MENT
Bom Jesus Calenga
Rural Development
Project
P-AO-A00-001
Agriculture
and Rural
Development
24/11/2005 14/09/2006 31/12/2012 17.20 6.91 40.20%
Environmental
Sector Support
Project
P-AO-CZO-001
Environment 11/03/2009 17/12/2009 31/12/2015 12.00 1.3 10.70%
Financial Support
Management
Project
P-AO-KFO-002
Finance 14/11/2007 04/09/2008 31/12/2012 5.90 0.4 7.81%
Sumbe Water
Supply, Sanitation
and Institutional
Support Project
P-AO-E00-003
Water and
Sanitation 28/11/2007 04/04/2009 30/06/2013 12.00 0.1 1.58%
Institutional
Capacity Building
Poverty Reduction
Project
Governance 23/02/2011 May 2011 30/07/2013 5.17 0 0%
GRAND TOTAL COMMITMENT 52.27 8.71 16.66%
III
Appendix III: Similar projects financed by the Bank and other development
partners in Angola
The EU is undertaking a survey with respect to projects per donor in Angola for 2010/2011, the
information will be shared from the EU representation as soon as the report is finalized. Once this
information is available it will be included in this appendix