Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018 · Angeles...
Transcript of Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018 · Angeles...
Angeles Forest and Palmdale Roost 2018 Solar PV DisturbancesApril 20, 2018 and May 11, 2018 Disturbances
Ryan D. Quint, PhD, PESenior Manager, Advanced System Analytics and Modeling, NERC
RELIABILITY | ACCOUNTABILITY2
Published Disturbance Report
https://www.nerc.com/pa/rrm/ea/Pages/April-May-2018-Fault-Induced-Solar-PV-Resource-Interruption-Disturbances-Report.aspx
RELIABILITY | ACCOUNTABILITY3
Angeles Forest DisturbanceApril 20, 2018, 17:11:06 PDT
RELIABILITY | ACCOUNTABILITY4
• 17:11:06 PDT• 500 kV “bolted” line-line fault, normally cleared in 2.6 cycles• Faulted line is mixed 500 kV underground/overhead
configuration Relatively lopsided RLC line parameters, unbalanced line shunt reactors
to compensate for high capacitive charging from the underground portion of the line.
Angeles Forest Disturbance
RELIABILITY | ACCOUNTABILITY5
Angeles Forest DFR Records at Fault Location
DFR at Remote End
DFR at Local End
RELIABILITY | ACCOUNTABILITY6
CAISO BPS-Connected Solar and Net Load
RELIABILITY | ACCOUNTABILITY7
SCE BPS-Connected Solar
RELIABILITY | ACCOUNTABILITY8
PG&E BPS-Connected Solar
RELIABILITY | ACCOUNTABILITY9
LADWP BPS-Connected Solar
RELIABILITY | ACCOUNTABILITY10
Combined Cycle Unit Trip
• One natural gas turbine at a 2-on-1 combined-cycle power plant in PG&E footprint tripped off-line due to the fault event.
• Plant tripped on low fuel gas pressure, causing one natural gas turbine loaded at 125 MW to trip.
• Subsequently reduced steam turbine output from 150 MW to 75 MW over the course of 19 minutes.
RELIABILITY | ACCOUNTABILITY11
Affected Solar PV in SCE
RELIABILITY | ACCOUNTABILITY12
Palmdale Roost DisturbanceMay 11, 2018, 15:20:14 PDT
RELIABILITY | ACCOUNTABILITY13
• Fault on short 500 kV line, B-N, normally cleared in 3 cycles.
Palmdale Roost Disturbance
DFR at One End of Faulted Circuit
DFR at Other End of Faulted Circuit
RELIABILITY | ACCOUNTABILITY14
CAISO BPS-Connected Solar and Net Load
RELIABILITY | ACCOUNTABILITY15
SCE BPS-Connected Solar
RELIABILITY | ACCOUNTABILITY16
PG&E BPS-Connected Solar
RELIABILITY | ACCOUNTABILITY17
LADWP BPS-Connected Solar
RELIABILITY | ACCOUNTABILITY18
IID BPS-Connected Solar
RELIABILITY | ACCOUNTABILITY19
Affected Solar PV in SCE
RELIABILITY | ACCOUNTABILITY20
Additional Information Related to Disturbances
RELIABILITY | ACCOUNTABILITY21
Map of Fault Locations
RELIABILITY | ACCOUNTABILITY22
CAISO Solar Profiles on Days of Disturbances
RELIABILITY | ACCOUNTABILITY23
System Frequency during Disturbances
RELIABILITY | ACCOUNTABILITY24
CAISO ACE
RELIABILITY | ACCOUNTABILITY25
Findings from Disturbance Analyses
(Refer to the Disturbance Report for Associated Recommendation for Each Finding)
RELIABILITY | ACCOUNTABILITY26
• Many plants exhibited momentary cessation
• Issuance of NERC Alert for Canyon 2 Fire disturbance was around time of both disturbances Not likely any major updates
implemented by then
• Data gathered from NERC Alert shown in figure
• ERO expecting applicable GOs to implement recommendations to improve performance.
Finding 1: Continued Use of Momentary Cessation
RELIABILITY | ACCOUNTABILITY27
Finding 1a: Improved Recovery from Momentary Cessation
RELIABILITY | ACCOUNTABILITY28
Finding 2: Fault Ride-Through Performance
RELIABILITY | ACCOUNTABILITY29
Finding 3: Transient AC Overvoltage and DC Reverse Current Tripping
RELIABILITY | ACCOUNTABILITY30
Finding 4: Partial Tripping and Partial Momentary Cessation
RELIABILITY | ACCOUNTABILITY31
Finding 5: Difference between Inverter Terminal and POI Voltage
RELIABILITY | ACCOUNTABILITY32
Finding 6: Lack of High Resolution Data and Time Stamping
RELIABILITY | ACCOUNTABILITY33
Finding 7: Response of DER
RELIABILITY | ACCOUNTABILITY34
Finding 7: Response of DER
CAISO Net Load
SCE “Net Load”
RELIABILITY | ACCOUNTABILITY35
Finding 7: Response of DER
PG&E Load Buses
SCE Load Buses
RELIABILITY | ACCOUNTABILITY36
Finding 8: PDCI Performance and RAS Actions
RELIABILITY | ACCOUNTABILITY37
Finding 8: PDCI Performance and RAS Actions
RELIABILITY | ACCOUNTABILITY38
• Unit tripped due to low fuel gas pressure as the turbine control system attempted to readjust the number of burners used as the plant initiated a runback of active power output.
• One CT tripped, causing the steam turbine to also reduce output over many minutes.
Finding 9: Combustion Turbine Trip
RELIABILITY | ACCOUNTABILITY39
Disturbance Analysis Team
RELIABILITY | ACCOUNTABILITY40
Ryan Quint, PhD, PESenior ManagerAdvanced System Analytics and ModelingNorth American Electric Reliability CorporationOffice (202) 400-3015Cell (202) [email protected]