Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles...

40
Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April 20, 2018 and May 11, 2018 Disturbances Ryan D. Quint, PhD, PE Senior Manager, Advanced System Analytics and Modeling, NERC

Transcript of Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles...

Page 1: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

Angeles Forest and Palmdale Roost 2018 Solar PV DisturbancesApril 20, 2018 and May 11, 2018 Disturbances

Ryan D. Quint, PhD, PESenior Manager, Advanced System Analytics and Modeling, NERC

Page 2: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY2

Published Disturbance Report

https://www.nerc.com/pa/rrm/ea/Pages/April-May-2018-Fault-Induced-Solar-PV-Resource-Interruption-Disturbances-Report.aspx

Page 3: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY3

Angeles Forest DisturbanceApril 20, 2018, 17:11:06 PDT

Page 4: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY4

• 17:11:06 PDT• 500 kV “bolted” line-line fault, normally cleared in 2.6 cycles• Faulted line is mixed 500 kV underground/overhead

configuration Relatively lopsided RLC line parameters, unbalanced line shunt reactors

to compensate for high capacitive charging from the underground portion of the line.

Angeles Forest Disturbance

Page 5: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY5

Angeles Forest DFR Records at Fault Location

DFR at Remote End

DFR at Local End

Page 6: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY6

CAISO BPS-Connected Solar and Net Load

Page 7: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY7

SCE BPS-Connected Solar

Page 8: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY8

PG&E BPS-Connected Solar

Page 9: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY9

LADWP BPS-Connected Solar

Page 10: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY10

Combined Cycle Unit Trip

• One natural gas turbine at a 2-on-1 combined-cycle power plant in PG&E footprint tripped off-line due to the fault event.

• Plant tripped on low fuel gas pressure, causing one natural gas turbine loaded at 125 MW to trip.

• Subsequently reduced steam turbine output from 150 MW to 75 MW over the course of 19 minutes.

Page 11: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY11

Affected Solar PV in SCE

Page 12: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY12

Palmdale Roost DisturbanceMay 11, 2018, 15:20:14 PDT

Page 13: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY13

• Fault on short 500 kV line, B-N, normally cleared in 3 cycles.

Palmdale Roost Disturbance

DFR at One End of Faulted Circuit

DFR at Other End of Faulted Circuit

Page 14: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY14

CAISO BPS-Connected Solar and Net Load

Page 15: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY15

SCE BPS-Connected Solar

Page 16: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY16

PG&E BPS-Connected Solar

Page 17: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY17

LADWP BPS-Connected Solar

Page 18: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY18

IID BPS-Connected Solar

Page 19: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY19

Affected Solar PV in SCE

Page 20: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY20

Additional Information Related to Disturbances

Page 21: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY21

Map of Fault Locations

Page 22: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY22

CAISO Solar Profiles on Days of Disturbances

Page 23: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY23

System Frequency during Disturbances

Page 24: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY24

CAISO ACE

Page 25: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY25

Findings from Disturbance Analyses

(Refer to the Disturbance Report for Associated Recommendation for Each Finding)

Page 26: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY26

• Many plants exhibited momentary cessation

• Issuance of NERC Alert for Canyon 2 Fire disturbance was around time of both disturbances Not likely any major updates

implemented by then

• Data gathered from NERC Alert shown in figure

• ERO expecting applicable GOs to implement recommendations to improve performance.

Finding 1: Continued Use of Momentary Cessation

Page 27: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY27

Finding 1a: Improved Recovery from Momentary Cessation

Page 28: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY28

Finding 2: Fault Ride-Through Performance

Page 29: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY29

Finding 3: Transient AC Overvoltage and DC Reverse Current Tripping

Page 30: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY30

Finding 4: Partial Tripping and Partial Momentary Cessation

Page 31: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY31

Finding 5: Difference between Inverter Terminal and POI Voltage

Page 32: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY32

Finding 6: Lack of High Resolution Data and Time Stamping

Page 33: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY33

Finding 7: Response of DER

Page 34: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY34

Finding 7: Response of DER

CAISO Net Load

SCE “Net Load”

Page 35: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY35

Finding 7: Response of DER

PG&E Load Buses

SCE Load Buses

Page 36: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY36

Finding 8: PDCI Performance and RAS Actions

Page 37: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY37

Finding 8: PDCI Performance and RAS Actions

Page 38: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY38

• Unit tripped due to low fuel gas pressure as the turbine control system attempted to readjust the number of burners used as the plant initiated a runback of active power output.

• One CT tripped, causing the steam turbine to also reduce output over many minutes.

Finding 9: Combustion Turbine Trip

Page 39: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY39

Disturbance Analysis Team

Page 40: Angeles Forest and Palmdale Roost 2018 Solar PV Disturbances April and... · 4/20/2018  · Angeles Forest and Palmdale Roost . 2018 Solar PV Disturbances. April 20, 2018 and May

RELIABILITY | ACCOUNTABILITY40

Ryan Quint, PhD, PESenior ManagerAdvanced System Analytics and ModelingNorth American Electric Reliability CorporationOffice (202) 400-3015Cell (202) [email protected]