Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block
Transcript of Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block
![Page 1: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/1.jpg)
Page 1 of 21
Lr.No APTS/IIP/335/GHMC-HTRIMS/2011 Dated : 03.09.2011
To
The Prospective Bidders
Sir, Sub: APTS – HWP Division – HRIMS Project – GHMC-Traffic & Transportation – Hyderabad
Traffic Integrated Management System (HTRIMS ) – Request for Expression of Interest
(RFEI) and Request for Proposal (Pre-qualification) issued on 27-07-2011 under Open
Competitive Bidding Procedures –Pre-bid minutes communicated - Intimation – Reg.
Ref: 1. APTS RFEI Ref. No: APTS/IIP/335/GHMC-HTRIMS/2011, dt 27-07-201
2. Pre-bid conference held on 05-08-2011.
*****
APTS has invited Request for Expression of Interest and Request for Proposal (Pre-
qualification) on 27-07-2011 under Open Competitive Bidding Procedures for “Supply of
Traffic Signal Hardware, Networking, Installation, Commissioning and Maintenance & Operations of the H-TRIMS Project for Hyderabad Traffic Police” for a period of five
years on BOOT model under the Hyderabad Traffic Police and Greater Hyderabad Municipal
Corporation.. Pre-bid meeting for the same was held on 05-08-2011. The specifications,
terms and conditions of the bid document were discussed during Pre-bid meeting. Following
are the clarifications/amendments given to the RFEI & RFP(PQ) document after discussions.
No Page
No
Section &
clause
No.
As per document Amendment issued
1 5 Sec-A-
1.1.3
Submission of
Response to RFEI &
PQ (Receiving EoI)
19.08.2011 at
03:00 PM
Opening of the
Response to RFEI &
Prequalification bids
19.08.2011 at
03:30 PM
Submission of
Response to RFEI &
PQ (Receiving EoI)
13.09.2011 at
03:00 PM
Opening of the
Response to RFEI &
Prequalification bids
13.09.2011 at
03:30 PM
2 6 Format for submitting EMD/Bid
Security through Bank Guarantee is
enclosed as Annexure – I.
3 6 1.1.3 The Business model for the Project:
Build Own Operate & Transfer (BOOT)
on equated quarterly installment (EQI)
model.
75% of capital cost to be paid on
completion of Acceptance Test. The
balance capital cost and O&M cost to be
paid in equal quarterly installments.
The Business model for the Project:
Build Own Operate & Transfer (BOOT)
on equated quarterly installment (EQI)
model.
75% of capital cost ( Capital cost of
Central Control Room + 50% of Traffic
Junctions) to be paid on completion of
Acceptance Test of Central Control Room
& 50% of Traffic Junctions.
75% of Capital Cost of remaining
junctions will be paid after Acceptance
Test on prorata basis.
Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block, Tankbund Road
Hyderabad – 500063, Andhra Pradesh, India
Phone: (40) 2322 4289, 23221760; Fax: 23227458
Web site: http://www.apts.gov.in
![Page 2: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/2.jpg)
Page 2 of 21
The balance capital cost and O&M cost to
be paid in equal quarterly installments
from the date of successful completion of
respective Acceptance Tests.
4 7 Sec-A-
1.1.10
1.1.10 Evaluation of received proposals: To be read as
1.1.9 Evaluation of received proposals
5 9 Sec-B-1.1
Table
Row
S.No.5
The Prime bidder or any member of the
consortium should have executed
minimum one project consisting 15
signals with microprocessor based
controller, in any city of India, for
supply, installation, FM & Maintenance
in any one of the last five financial years
(2006-07, 2007-08, 2008-09, 2009-10
and 2010-11).
The Prime bidder or any member of the
consortium should have executed
minimum one project consisting 15 signals
with centrally controlled microprocessor
based controller, in any city of India, for
supply, installation, FM & Maintenance in
any one of the last five financial years
(2006-07, 2007-08, 2008-09, 2009-10 and
2010-11).
6 13 Sec-C-
1.6.1
Table
Row
S.No.3
Power backup - Yes/No Power backup - Yes/No
(With 4 hours battery backup)
7 13 Sec-C-
1.6.1
Table
Row
S.No.4
Countdown timers - Yes/No: To be
Yes (All junctions)
All junctions will have countdown timers
except ( 02 ) vehicle actuated (VA) system
signals, these timers will run through VA
system Software.
8 13
1.6.4
Existing Traffic Signals in Hyderabad Revised Junction list is enclosed as
Annexure – II.
9 20 1.6.6 Hyderabad – New locations where new
signals to be installed
Revised Junction list is enclosed as
Annexure – III.
10 19 1.6.5 Existing Traffic Signals in Cyberabad Revised Junction list is enclosed as
Annexure – IV.
11 22 1.6.7 Cyberabad –New locations where new
singles to be installed
Revised Junction list is enclosed as
Annexure – V.
12 23 1.6.8 Installation of New Signals –
ABSTRACT
Revised ABSTRACT enclosed as
Annexure - VI
![Page 3: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/3.jpg)
Page 3 of 21
Clarifications given to the RFEI & RFP (PQ) Ref. No. APTS/IIP/335/GHMC-HTRIMS/2011, dt. 27-07-2011
No Page
No
Section &
clause
No.
As per document Clarification sought Clarified as
1 6 Sec-A-
1.1.3
Build Own Operate & Transfer (BOOT) on
equated quarterly installment (EQI) model.
75% of capital cost to be paid on completion of
Acceptance Test. The balance capital cost and
O&M cost to be paid in equal quarterly
installments.
1. As the payment term is 75% against
Acceptance Test and balance 25% & O&M
cost on EQI, we would like to understand
the relevance of BOOT Model.
2. Authority for Acceptance Test and
Acceptance Test parameters to be made
clear in RFQ.
3. BEL Recommendation: payment terms –
capital cost 80% advance, 10% after
acceptance test and balance 10% on EQI on
Prorata basis. O&M also on EQI from the
date of completion and on pro-rata basis.
4. What are the stages in the project, this
acceptance test will be conducted
1. The solution required from the bidder
contains Operations and Maintenance
service component also in addition to
supply and installation of traffic signal
monitoring system for a period of 5 years.
Hence BOOT is the suitable model for this
requirement.
2. Details regarding Acceptance Test will
be provided in the Request for Proposal
(technical & financial).
3. Payment terms in detail will be issued in
the Request for Proposal (technical &
financial).
4. Please refer to Section-A, Clause 1.1.8
& 1.1.10. In the first stage pre-qualification
bids will be evaluated. The bidders
complied with Pre-qualification criteria
will be shortlisted and are eligible for
receiving the Request for Proposal
(Technical & Financial). The short listed
bidders should give a presentation on their
proposed solution to the Technical
Evaluation Committee on the specified
date/time. Presentations are one at a time
and while a bidder is presenting his
solution other bidders will not be allowed.
The received proposals/solutions will be
examined and evaluated for its operational
& technical feasibility. No bidder will be
disqualified based on his solution.
The RFP (Technical & Financial) will be
prepared based on examination of all the
![Page 4: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/4.jpg)
Page 4 of 21
proposed solutions and will be issued to
the pre-qualified bidders. The RFP
(Technical & Financial) will be a complete
document covering all the technical and
financial details.
2 9 Sec B-1.1 Payments will be released to Prime bidder by
GHMC as per the certification of
Hyderabad Traffic Police Department, Government of Andhra Pradesh.
Certifying Authority to be mentioned:
BEL Recommendation: Completion
certificate to be obtained from the concerned
Traffic Police In-charge and same will be
submitted to GHMC for payment.
Payment terms in detail will be issued in
the Request for Proposal (technical &
financial).
3 12 Sec C- 1.2 Objective of the Project:
Operate the signaling parameters manually
from the central control room based on the
existing traffic information from the online
real-time cameras installed in the traffic
junctions. The surveillance cameras are not
part of this project.
1. O&M of existing third party camera is not
considered in BEL scope.
2. Please clarify the number of locations we
want to operate manually from the control
room based on the existing traffic
information from the online real-time
cameras
3. We understand that signaling parameters
such as sequencing of operation, time slots,
directions etc. that are to be modified
centrally. Further to this conditions like
a) Issuing of Group Command to set a Route
for a group of junctions .
b) Setting of blinkers for a single or a group
of junctions.
c) Altering Signalling parameters for an
individual junction from Central Control
Roometc.
If not pl. clarify.
1. O&M of existing third party cameras are
part of this project.
2. All the 221(Included 15(SCB) signals
are to be operated manually and through
automated software from the central
control room, it is based on the existing
live traffic information from the online
and real-time cameras
3. Bidder is free to propose his solution on
these issues keeping in view of the
objectives of this project. The Committee
will examine all the solutions and arrive at
a conclusion.
4 12 Sec C –
1.4 • It is proposed to install new signals in all
locations.
• Traffic department identified
location/signals will have Countdown
timers other than the (20) vehicle Actuated
traffic signals.
1. All 233 (188 existing + 45 new) junctions
will have new signal system.
2. All 233 junctions will have count down
timers except 2 vehicle actuated junctions.
The vehicle actuated technology to be
mentioned in the RFQ. BEL doesn’t
recommend inductive loop vehicle actuation
technology.
1.Total 221(180 existing + 41 new) will have
New Signal system. (15) Secunderabad
Cantonment Board area are also included under
the scope of this project.
2. All junctions will have countdown timers
except ( 02 ) vehicle actuated (VA) system
signals, these timers will run through VA
system Software.
![Page 5: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/5.jpg)
Page 5 of 21
3.
a) It is been asked to replace all the
countdowns in all the junctions except at 9
SCB junctions. 20 Vehicle actuated traffic
signals are not defined in the scope. Please
clarify.
b) Please specify interfacing details of the
vehicle actuated sensors.
c) Please specify no. of countdowns per
junction/ per one approach road at a
junction.
3. Refer to Annexure VII.
5 12 Sec C- 1.2 Objective of the Project:
Monitor health of every signal point from the
Central control room to attend the failure/
breakdowns.
The parameters to be monitored are to be
indicated.
The bidder has to propose the parameters
in his solution.
6 12 Sec C- 1.2 Objective of the Project:
Create a centralized Management Information
System (MIS) for Faster decision making in
traffic emergency
1.MIS report format to be provided by the
customer. BEL will implement as per the
format.
2. What is traffic emergency? What is
required as MIS during Traffic Emergency
1.The bidder has to propose his MIS in his
solution.
2. Traffic emergency is that, heavy Rain
fall, accidents, Terrorist attack, VVIP
Movements etc.
7 12 Sec C- 1.3 Key Performance Indicators: The system is to be made available round the
clock
1.How the down time is
considered/measured during Force Majure
and System Failures.
2. Force Majure (Like Thunders,
Accidents,Processions, damage due to
riots/disturbances, AP Transco Power
Supply breakdowns etc.) can not be taken in
to system downtime. Also for this,
rectification time depends on the severity of
failure.
3. System failures like controlling system,
lamps, control unit failure, communication
failure.
4. Restoration during partial failure of
system like lamps on the cantilever etc. may
These issues are part of and will be
covered in Request for Proposal (Technical
& financial)
![Page 6: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/6.jpg)
Page 6 of 21
not be possible to attend immediately due to
traffic conditions on site.
5. Minimum downtime allowed for
periodical maintenance of the system.
7 12 Sec C- 1.3 Key Performance Indicators:
Central command to eliminate the traffic jams
1.Clarification required on the technical
aspect of eliminating traffic jam from
Central command.
2. To be elaborated further.
This is part of bidders proposed solution.
8 12 Sec C-1.3 Key Performance Indicators: Availability of the traffic information online
in the portal
1. Technical clarification required. Portal
format to be provided.
2. Please clarify, is there any separate
website required for availing the traffic
information online.
3. If the traffic information means the
density at particular junction – This is not
possible as the present scope does not cover
the measurement of traffic density. If not
please clarify. Establishment and
Maintaining the portal is not in the present
scope.
1. This is part of bidders proposed solution.
2. In the existing traffic website and it
should be web based technology.
3. Traffic information means live status
and health of the signals and daily abstract
of signal functioning is to be developed in
3D Microsoft / Silver Lite software.
9 12 Sec C-1.3 Key Performance Indicators:
Remote management for fast decisions for
diversion of the traffic in emergency
1.Technical clarification with example
required.
2. Group command for a series of junctions
in a route or to a particular junction from
central place can be given. Please clarify if
there is any further scope to be covered.
1. This is part of bidders proposed solution.
2. Corridor-wise stretches will be given.
Group Command signal for the Corridor or
stretches, should work in the traffic
emergency.
10 12 Sec C –
1.4
Create a Backup Server for the central control
room server at the Cyberabad Traffic control
room which will store entire data. Two
workstations for controlling the Cyberabad
signals to be installed at Cyberabad Traffic
control room
1.Equipment to be placed at the Cyberabad
Traffic Control to be defined. Equipments,
Servers, and number of work stations
required at central Control room are not
defined in the Scope.
2. Distance/Place and connectivity details
between Main Server at Central Control
Room to the Backup Server to be defined in
the scope.
1. Bidder has to propose the Bill of
Material & Bill of quantity as part of his
solution keeping in view of the scope of
work and objectives of the project.
2. We have mentioned two main central
control rooms. One at Hyderabad City
Police, second is at Cyberabad Police.
Remaining all destinations points
mentioned in the location list.
![Page 7: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/7.jpg)
Page 7 of 21
11 13 Sec C –
1.6.1 Power backup 1. For how many Hours power backup need
to be mentioned.
2. Source of Power to be mentioned-
conventional or solar.
3. Under whose scope provision of power
supply point from APSEB along with
energy meter and the monthly power bill
payment need to be considered.
4. 24V DC overhead power cable for control
unit to the poles can be allowed or not.
1. 4 Hours.
2. conventional power
3. GHMC provides the power connection
and pays the power bills.
4. Over head cable is not allowed
12 18 Sec C –
1.6.4 New Signals only the required connectivity
components shall be added to the controller.
Each controller operates on its own protocol.
Incompatibility of controller protocol will
not allow the existing controller to integrate
with the new system.
Bidder may propose replacement of
controllers in his solution.
13 18 Sec C –
1.6.4
Only 126 Junctions out of total existing 137
junctions names is given
1. 11 Junction names to be provided.
2. If 9 SCB signals are not part of the scope
then the signals under the scope will be 137-
9=128. Please clarify
3. Please specify the junctions with island
which result in more number of poles and
lamp aspects.
1.Revised list of names is provided as
Annexure - II
2. SCB Locations also included in the
scope of work.
3. Details are provided at Annexure – VII.
14 20 Sec C –
1.6.5
Only 49 junctions out of total existing 51
junctions names is given
2 Junction names to be provided. Revised Junction list is enclosed as
Annexure – IV.
15 Project Duration Realistic project duration should be
mentioned in the RFQ
Project duration will be given in RFP
(technical & financial). However, bidder
can propose his project plan in his solution.
16 Connectivity 1. Connectivity to the junction and control
room through leased line to be provided by
GHMC/Hyderabad Traffic Police
2. Dedicated leased line required for each
junction or not.
1. Connectivity wired/wireless has to be
arranged by the bidder
2. Bidder can propose wired/wireless
connectivity in his solution.
3. Connectivity Charges (both initial and
![Page 8: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/8.jpg)
Page 8 of 21
3. For wired/wireless communication,
monthly charges to the service provider
come under whose scope
recurring) are to be borne by the bidder
which will be reimbursed in Equated
Quarterly Installments.
17 Road cutting permission Road cutting permission to be provided by
GHMC/Hyderabad Traffic Police
Getting Road cutting Permission is the
bidder’s responsibility. However
GHMC/Hyderabad traffic police will
provide necessary assistance in getting the
required permissions.
18 Downtime Accident and theft cases will not come
under downtime. Damages caused by third
party during road widening, flyover works,
underpass works, drainage works etc. also
will not come under downtime.
These instances will be covered under
force majure in RFP (technical and
financial)
19 Complaint monitoring software and Facility
Management Services (FMS)
To be clearly defined in the RFQ. This is part of bidders proposed solution.
20 Blinker 1.Locations where the Blinkers to be
installed to be provided.
2. BEL provides single head and double
head solar blinker
3. BEL recommends SMS interface for
monitoring blinker status.
4. The number of poles and lamp aspects to
be placed at junction.
1. Location list for Blinkers will be
provided in the RFP (Technical &
Financial).
2. Give the specific proposal in the EOI
documents.
3. This is part of bidder’s solution.
4. Details enclosed as Annexure – VII
21 Junction signalization layout drawing and
configuration approval
Who will provide and approve the junction
layouts drawing and configurations
GHMC will provide the junction layout
drawing and configuration.
22 Single Point of contact/nodal agency A single nodal agency with officials drawn
from traffic police, Cyberabad Police, Law
and Order Police is required to co-ordinate
the project. Information to be provided.
This subject will be taken care during the
implementation phase of the project.
![Page 9: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/9.jpg)
Page 9 of 21
23 Does it required to give free left signal
lamp?Does it require LEFT & RIGHT
directions controlling independently
Yes. Details enclosed as Annexure V.
Whether the existing poles to be used or not Total new poles should be erected and old
poles may be taken back in the buyback
mode.
Specifications of Cantilever Pole and
standard Pole (Height, Horizontal length of
the cantilever, foundation depth etc.)
Specifications for Standard Poles &
Cantilever Poles (Height, Horizontal length
of the cantilever, foundation depth etc.) are
provided as Annexure VIII
Should we provide primary and secondary
signals to be provided wherever it is
possible?
Junction by junction details will be issued
in the RFP (Technical & Financial)
Roles, Responsibilities of GHMC, Traffic
Police Department, Hyderabad and APTS
and also the methodology for accepting,
monitoring, testing, & certifying and passing
the bills for payments etc.
These will be provided in the RFP
(technical & financial) Document
How the security for the installation ensured Installation security is the responsibility of
Bidders only Department will be Co-
ordinate with them.
Will the user is providing any infrastructure
like mobile ladder, vehicles for monitoring
etc. during installation and maintenance of
the system.
The Bidder has to provide all arrangements
work his own.
We request you to give at least 4 weeks time
from the date of clarifying the issues as we
need to do the site inspection for further
process
Enough time was provided, hence further
extension is not possible.
![Page 10: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/10.jpg)
Page 10 of 21
All other terms and conditions of the RFEI & RFP (PQ) remain un-altered.
Yours sincerely,
Sd/-
Manager (HWP-SS)
Suggestions 1. We propose to allow quoting Schedule of
Items separately i.e. Supply of Items,
software, Installation and commissioning
costs separately. Supply of Items inclusive
of taxes like Central excise and other duties
+ VAT.
2. Installation and commission charges +
Service tax – for better comparison and
finalization.
Bidder can propose their recommendations
in detail in their proposal.
![Page 11: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/11.jpg)
Page 11 of 21
Annexure - I
APTS Ref. No.....
Bid Security (EMD) Form
(To be issued by a bank scheduled in India and having at least one branch in Hyderabad)
Whereas...................................... (Here in after called "the Bidder") has submitted its bid
Dated ……........ (Date) for the execution of........................ (Here in after called "the Bid")
KNOW ALL MEN by these presents that WE ................... of ........................ having our
registered office at........................ (hereinafter called the "Bank") are bound unto the Andhra
Pradesh Technology Service Ltd. (hereinafter called "The APTS") in the sum of ................
for which payment well and truly to be made to the said APTS itself, its successors and
assignees by these presents.
The conditions of this obligation are:
1. If the bidder withdraws its bid during the period of bid validity or
2. If the bidder, having been notified of the acceptance of its bid by the APTS during the
period of bid validity:
a. fails or refuses to execute the contract form if required; or
b. fails or refuses to furnish the performance security, in accordance with the bid
requirement;
We undertake to pay the APTS up to the above amount upon receipt of its first written
demand, without the APTS having to substantiate its demand, provided that in its demand the
APTS will note that the amount claimed by it is due to it, owing to the occurrence of one or
both of the two conditions, specifying the occurred condition or conditions.
This guarantee will remain in force up to and including 45 days after the period of the bid
validity, and any demand in respect thereof should reach the Bank not later than the above
date.
Place:
Date:
Signature of the Bank
and seal.
![Page 12: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/12.jpg)
Page 12 of 21
Annexure – II
LIST OF EXISTING LOCATIONS FOR INSTALLATION OF TRAFFIC SIGNALS
Sl.No. Police Station Signal Name Type of Jn Remarks
1. Mahankali Ghosmandi X Roads 4 Way
2. Mahankali Patny X Roads 4 Way
3. Mahankali SBH X Roads 4 Way
4. Mahankali Delight X Roads 3 Way
5. Gopalapuram YMCA X Roads 4 Way
6. Gopalapuram St.John’s rotary 4 Way
7. Gopalapuram Sangeeth X Roads 4 Way
8. Gopalapuram Alugaddabavi T-jn. 3 Way
9. Gopalapuram Mettuguda X Roads 4 Way
10. Gopalapuram Padmaraonagar T junction 3 Way
11. Thirumalgherry Sweekar upakar X Rd 4 way
12. Thirumalgherry MCEME x Rd 4 way
13. Thirumalgherry Tadban X Rd 4 way
14. Thirumalgherry Y Junction at Mess pump House 3 way
15. Thirumalgherry Bowenpally X Rd 4 way
16. Thirumalgherry Tivoli 4 way
17. Thirumalgherry Sec’bad Club 4 way
18. Thirumalgherry Ratnaih Petrolpump 4 way
19. Thirumalgherry Picket 3 way
20. Begumpet Bible House 4 Way
21. Begumpet Karbala Maidan 4 Way
22. Begumpet Ranigunj 4 Way
23. Begumpet Nallagutta 3 Way
24. Begumpet Paradise 4 Way
25. Begumpet CTO 4 Way
26. Begumpet Rasoolpura 4 Way
27. Panjagutta NFCL 3 Way
28. Panjagutta Punjagutta junction 4 Way
29. Panjagutta Shalimar junction 3 Way
30. Panjagutta Maitrivanam 4 Way
31. Panjagutta S.R. Nagar 4 Way
32. Panjagutta Kalyan Nagar 4 Way
33. Panjagutta Balkampet T junction 3 Way
34. Panjagutta Yellamma Temple 3 Way
35. Panjagutta Dharam Karam Road 3 Way
36. Panjagutta Greenland junction 3 Way
37. Panjagutta Rajiv Gandhi Statue 3 Way
38. Panjagutta VV Statue junction 5 Way
39. Panjagutta KCP junction 3 Way
40. Panjagutta Taj Krishna 3 Way
41. Panjagutta Road.No.1/10 B/Hills 3 Way
42. Panjagutta Road.No. 1/12 3 Way
43. Banjara Hills Rd.No.36/10 junction J/Hills 3 Way
44. Banjara Hills Peddamma Temple junction 3 Way
45. Banjara Hills Jubilee Hills Check post junction 4 Way
46. Banjara Hills KBR Park junction 4 Way
47. Banjara Hills Sagar Society 3 Way
48. Banjara Hills Srinagar “T” junction 3 Way
49. Banjara Hills Yousuf guda Checkpost junction 3 Way
50. Chikkadpally Kattamaisamma 3 Way
51. Chikkadpally Indira Park 4 Way
52. Chikkadpally Ashoknagar 4 Way
![Page 13: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/13.jpg)
Page 13 of 21
53. Chikkadpally RTC X Roads 4 Way
54. Chikkadpally VST X Roads 4 Way
55. Chikkadpally Azamabad X Roads 4 Way
56. Chikkadpally Musheerabad Roads 4 Way
57. Chikkadpally Kawadiguda Roads 4 Way
58. Chikkadpally Children’s Park 3 Way
59. Saifabad Liberty 4 Way
60. Saifabad Amberdkar Statue 4 Way
61. Saifabad Telugutalli 4 Way
62. Saifabad Ravindra Bharathi 3 Way
63. Saifabad Old PS Saifabad 4 Way
64. Abids GPO 4 Way
65. Abids Bata “T” junction 3 Way
66. Abids Tajmahal junction 3 Way
67. Abids SBH Gunfoundry signal 3 Way
68. Abids BJR Statue 3 Way
69. Abids Basheer Bagh junction 5 Way
70. Abids Old MLA Qrts., junction 3 Way
71. Abids Himayathnagar Y junction 3 Way
72. Abids Narayanguda X Roads 4 Way
73. Abids King Koti X Roads 4 Way
74. Goshamahal Taj Island 4 Way
75. Goshamahal M.J.Market 4 Way
76. Nampally PCR junction 5 Way
77. Nampally Chapel Road 3 Way
78. Nampally A1 Nampally 4 Way
79. Asifnagar Khaja Mansion 3 Way
80. Asifnagar Masab Tank 4 Way
81. Asifnagar Meraj Café 4 Way
82. Asifnagar Nanal Nagar 3 Way
83. Asifnagar Toli Chowki 4 Way
84. Asifnagar Mogal-Ka-Nala 4 Way
85. Asifnagar Laxmi Nagar 4 Way
86. Asifnagar Rethibowli 3 Way
87. Charminar Madina X Roads 3 Way
88. Charminar City college X Roads 4 Way
89. Charminar Bahadurpura X Roads 4 Way
90. Falaknuma DMRL X Roads 4 Way
91. Falaknuma Old Chandrayangutta 4 Way
92. Falaknuma MBNR X Roads 4 Way
93. Falaknuma Nagulchinta 3 Way
94. Falaknuma Himmathpura 4 Way
95. Mirchowk Etebar Chowk X Roads 4 Way
96. Mirchowk Bibi Bazar X Roads 4 Way
97. Kachiguda Amberpet T junction 3 Way
98. Kachiguda Road.No.6, Amberpet 4 Way
99. Kachiguda Tilaknagar X Road 4 Way
100. Kachiguda Nimboliadda Y junction 4 Way
101. Kachiguda Chaderghat X Road 3 Way
102. Kachiguda Chaderghat cause way 4 Way
103. Kachiguda Tourist Hotel 3 Way
104. Kachiguda Lingampally X Road 4 Way
105. Kachiguda Kachiguda X Road 4 Way
106. Kachiguda Barkathpura Post Office 4 Way
107. Kachiguda Crown Café X Road 4 Way
108. Kachiguda A.Y. Mandali (Barkathpura) 4 Way
109. Kachiguda Fever Hospital 4 Way
110. Kachiguda Hindi Mahavidyalay 3 Way
![Page 14: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/14.jpg)
Page 14 of 21
111. Kachiguda N.C.C. junction 3 Way
112. Kachiguda Tarnaka X Road 4 Way
113. Kachiguda Habsiguda X Road 4 Way
114. Sulthanbazar Andhra Bank 4 Way
115. Sulthanbazar DM & HS 4 Way
116. Sulthanbazar P/Bowli X Roads 4 Way
117. Sulthanbazar Rangmahal Y junction 3 Way
118. Sulthanbazar S.J. Bridge 4 Way
119. Malakpet Gaddiannaram X Roads 4 Way
120. Malakpet Moosaram Bagh X Roads 4 Way
121. Malakpet Saleem Nagar X Roads 4 Way
122. Malakpet Chenchalguda Rotary 3 Way
123. Malakpet Saidabad “T” junction 3 Way
124. Malakpet Dhobighat X Roads 4 Way
125. Malakpet I.S. Sadan X Roads 4 Way
126. Malakpet Chempapet X Roads 4 Way
![Page 15: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/15.jpg)
Page 15 of 21
Annexure – III
STATEMENT OF TRAFFIC SIGNALS PROPOSED FOR NEW LOCATIONS IN HYDERABAD.
S.No. Name of the Tr.
Police Stations
Name of the Junction Type of Jn Remarks
1. Flim Nagar 3 Way
2. BVB Junction 3 Way
3. Road No.45 J/Hills 3 Way
4. Journalist Colony 3 Way
5. Madapur Kaman 4 Way
6.
Jubilee Hills
Rd No 36/31 3 Way
7. Begumpet HPS Out Gate 3 Way
8. Mahankali Bata X Road Secunderabad 4 Way
9. Charminar Tadban 4 Way
10. Asif Nagar Humayunnagar 4 Way
11. Chikkadpally Praga Tools 3 Way
12. DSNR X Road 4 Way
13. Chaderghat Rotary 3 Way
14.
Malakpet
Nalagonda X Road 4 Way
15. Mothi Nagar 4 Way
16. S R Nagar
Rajiv Nagar 4 Way
17. Ajantha Gate 4 Way
18. Bazar Ghatt 4 Way
19.
Nampally
Eake Minar X Roads 4 Way
20. Thirumalgherry NCC 4 Way
21. Thirumalgherry Sec-bad club Gate No.2 (Airtel
office)
4 Way
22. Thirumalgherry Rythubazar 4 Way
23. Thirumalgherry Lothu kunta 3 Way
24. Thirumalgherry Diamond Point 5 Way
25. Thirumalgherry Priyadarshini Hotel 3 Way
26. Gopalapuram Chilakalguda X Roads 5 Way
27. Gopalapuram Keyes High School 3 Way
28. Panjagutta S.R.Nagar Community Hall 4 Way
29. Kachiguda Ali Café 4 Way
30. Sulthanbazar Ramkoti X Roads 4 Way
31. Goshamahal Malakunta 3 Way
![Page 16: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/16.jpg)
Page 16 of 21
Annexure – IV
Existing Traffic Signals in Cyberabad
Sl.No. Junction Name Type of Junction
1 Radhika X Road 4-Way
2 Sainikpuri XRoad 3-Way
3 Neredmet X Road 3-Way
4 Anand Bagh 4-Way
5 ECIL X Road 3-Way
6 ZTC 3-Way
7 Vinayak Nagar 3-Way
8 LFJ Uppal 3-Way
9 Nacharam 4-Way
10 Uppal X Road 4-Way
11 Ramanthapur X Road 3-Way
12 Chaitanyapuri X Road 3-Way
13 Fruit Market 4-Way
14 HUDA Complex 3-Way
15 Nagole X Road 4-Way
16 Bairamalguda 4-Way
17 Kharmanghat 4-Way
18 Hastinapuram 3-Way
19 L.B.Nagar Ring Road 4-Way
20 Kamineni Hospital 4-Way
21 Astalaxmi Temple 3-Way
22 Manda Malamma Temple 3-Way
23 Alkapuri Junction 3-Way
24 Auto Nagar 4-Way
25 Panama Jn. 3-Way
26 Sushma 3-Way
![Page 17: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/17.jpg)
Page 17 of 21
27 Madhapur PS Building 3-Way
28 Botanical garden 3-Way
29 Khajaguda 4-Way
30 Kothaguda 3-Way
31 Gachibowli 4-Way
32 ISB Junction 4-Way
33 Vittal Rao Nagar Junction 3-Way
34 Kondapur 3-Way
35 Raidurgam Junction 3-Way
36 Erragadda Junction 4-Way
37 Bharath Nagar Junction 3-Way
38 Moosapet 3-Way
39 Mothi Nagar Junction 4-Way
40 Narsapur Junction 4-Way
41 Balanagar Junction 3-Way
42 Godrej Junction 4-Way
43 V.V.Nagar 3-Way
44 G.T.Bank 3-Way
45 JNTU Junction 3-Way
46 Nizampet 3-Way
47 Miyapur Junction 3-Way
48 Hafeezpet Junction 3-Way
49 Malaysian Town Ship 3-Way
50 Gudenmet 3-Way
51 Gajularamaram 3-Way
52 Aramghar 4-Way
53 PDPC 3-Way
54 Hyder guda 4-Way
3 Way -->34, 4 Way --> 20
![Page 18: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/18.jpg)
Page 18 of 21
Annexure – V
Cyberabad – Proposed New Signals
Sl.No. Junction Name Type of Junction
1 Gachi Bowli (HKC) 3-Way
2 Cyber Gate way 3-Way
3 Wipro Nanakramguda 4-Way
4 Gandi Maisamma 4-Way
5 Suchitra Junction 4-Way
6 Chanda Nagar 3-Way
7 Hyder Nagar 3-Way
8 Cyber Towers 4-Way
9 NAC Junction (near Shilparamam 3-Way
10 Silicon Towers, Madhapur 4-Way
3 Way -->05
4 Way --> 05
![Page 19: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/19.jpg)
Page 19 of 21
Annexure – VI
ABSTRACT
S.No. Particulars Total Remarks
1. Hyderabad list of existing and proposed
location for installation of traffic signals
126
2. List of traffic signals proposed for new
locations in Hyderabad.
31
3. Cyberabad list of existing and proposed
location for installation of traffic signals
54
4. List of traffic signals proposed for new
locations in Cyberabad.
10
TOTAL:
221
SIGNAL TYPES
3 Way 4 Way 5 Way Total
Hyderabad 57 95 5 157
Cyberabad 37 24 0 64
Grand Total 221
![Page 20: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/20.jpg)
Page 20 of 21
Annexure – VII
Traffic Signaling System Configuration for 3-Way / 4-Way/5-Way Roads for
installation of new signals
SNo Item Description Quantity
3-Way 4-Way 5-Way
1 Controller 32 bit Microcontroller GPS enabled with
Remote monitoring and control features. 1 1 1
2 Cantilever Pole For all Roads 3 4 5
3 Standard Pole For all Roads 4 4 5
4 Signal Aspects -
a Red 12/15* 16/20* 20/25*
b Amber 12/15* 16/20* 20/25*
c Green 36/45* 48/60* 60/75*
5 Pedestrian Aspects One set of Pedestrian Signals per road.
a Pedestrian Red 8 8 10
b Pedestrian Green 8 8 10
6 UPS Battery 4 Hours Backup 1No. 1No. 1No.
7 Underground Cabling ISI Approved Cable. ** ** **
8 Count Down Timer One Count Down timer per road.
Applicable wherever timer is required 3 4 5
9 Alarms Audible Alarm System for Pedestrian
crossings 3 4 5
* ���� In case of Cantilever used as Left Primary.
** ���� As per the site requirement
![Page 21: Andhra Pradesh Technology Services Ltd. BRKR Bhavan, B-Block](https://reader031.fdocuments.us/reader031/viewer/2022020704/61fb4e4e2e268c58cd5c9a63/html5/thumbnails/21.jpg)
Page 21 of 21
Annexure – VIII
SPECIFICATION FOR STANDARD POLE
A. DIMENSION
Length - 5000 MM / 6000 MM
Diameter - 115 MM
Wall thickness - 4.5 MM
B. MATERIAL
Mild Steel (M.S) Tubular Pipe ( B-Class) as per IS-1239 (Part-1)-193
C. BASE PLATE
Size 200 MM x 200 MM x 12 MM thick welded to the bottom of the signal pole.
D. PAINT
Pole painted with two coats of primer and in addition bituminous painting for the bottom 1.5
M portion of pole.
SPECIFICATIONS FOR CANTILEVER POLES
DIMENSION
Length - 9000 MM
Wall thickness - 4.5 MM
Over hang - 3 M
MATERIAL
Mild Steel (M.S) Tubular Pipe ( B-Class) as per IS-1239 (Part-1)-193
BASE PLATE
Size 400 MM x 400 MM x 16 MM thick welded to the bottom of the signal pole.
PAINT
Pole painted with two coats of primer and in addition bituminous painting for other bottom
1.5 M portion of pole.