AND QUALIFICAT'QN OF WE'L' -SLUG · and qualificat'qn of we'l' -slug all-tantalum capacitors final...
Transcript of AND QUALIFICAT'QN OF WE'L' -SLUG · and qualificat'qn of we'l' -slug all-tantalum capacitors final...
DESIGN, DEVELOPME'IT, MANUFACTURE
AND QUALIFICAT'QN OF WE'L' -SLUG
ALL-TANTALUM CAPACITORS
FINAL F.FPORT
Period: July 2'7, 1973 - December 15, 1976
Prepared By
Robert H. Maher - Project Engineer Tantalum Capacitors
PreDared For
GEORGE C . MARSHALL SPACE FLIGHT CENTER Marshall Space Flight Center, Alabama 35812
Contract No. NAS8 -298 19
(NAS A - C F - 1 5 n 2 1 2 ) D E S I G N , DEVELOPHENT, 877- 20 3 35 MANUFACTURE AND Q V A L I P I C A T I O N OF WET-SLUG ALL-TANTALUH CAP?CITORS F i n a l Report, 27 J u l . l a ? ? - 15 3ec. 1976 (Sprague Electric Unclas C3.1 93 p HC \r>S/MP 301 CSCL r ) q A G3/33 21748
SPRAGUE ELECTRIC COMPANY North Adams, Massachusetts 01247 January 1 5 , 1977
https://ntrs.nasa.gov/search.jsp?R=19770013391 2018-07-14T22:48:33+00:00Z
Contract No. NAS8-29819 Sprague Reference: A119-59 Pro jec t Engineer: R. H. Maher
Surmlemental ReDort to the F ina l ReDort
Attached i s Table XXXVIII f r o m the final repor t , for the 250pF - 10volt r emake group of 20 units, which has been revised to include the e lec t r ica l pa rame te r resu l t s f r o m the 10, 000 hour m a r k achieved on Apr i l 1, 1977. pa rame te r s were acceptably s table throughout the tes t .
It will be noted that all e lec t r ica l
The capacitance stability data quite conclusively proves that the extended cathode capacitance has stabil ized the total capacitor capacitance throughout the tes t . comparison of this pa rame te r between the original group and the remake group with the extended cathode capacitance which makes this fac t very apparent.
Following is a
Capacitance Stability at 10, 000 Hours of 12.5"C Life T e s t
250vF - 10Volts Standard No. Units with
Acapacitance (YO) Deviation 70 ACap > 10% 0- -- Low Avg. High -
Original Units 4 4 . 9 t 2 6 . 2 +37.9 5 .8 18/18
Remake Units t 2 . 8 1 t 4 . 08 t 4 . 9 5 0.54 0 120 (Extended Cathode
Cap)
Al l requirements of this contract a r e complete.
N
0000
000
000
m
6"
0'0 0 0
000
00
0
Ns
O
...- 000000000
rn
oo
oa
oo
o
4- N' m
' *- a" w' 2- N
OO
OO
OO
O
U
a
-73
-
T A B L E O F C O N T E N T S
SECTION 1 - ABSTRhCT
SECTION 2 - SCOPE OF WORK
SECTION 3 - DISCUSSION A. Development Phase
( 1 ) Special Tooling and Equipment (2) Procurement of Parts (3) Cathode Studies (4) Capacitor Design
B. Enginee, *ng Evaluation Phase (1) Test Specification
C. Qualification Test Phase D. MSFC Pieeting
SECTION 4 -WORK TO Bd PERFQRMED DURING THE NEXT REFORT PERIOD
SECTION 5 - EXPENDITYRES AND FORECAST
Page
1
2
13 13 14 18 23 24 24 55 83
84
85
i
L I S T O F F I G U R E S A N D T A B L E S
Figure No. Title
1 Percent Cathodic Effic-sncy V s Cathoc3 Formation Voltages F o r Various Cathode Systems
Table No.
I
II
ILI
IV
V
V I
v I1
Tit le
Cathode Liner Durability Testing (560p.F - 6V)
Tempera ture Character is t ics Per S pe ci f i c a ti on hi I t - C - 3 9 0 0 6 250pF - 10VDC Rating
T e mp e r a tu r e C h a r act e r i s ti c s P e r Specification MIL-C -39006 60pF - 50VDC Rating
Vib;ation Tes t Results P e r MIL-STD-202 60p.F - 5CVDC Ratings
T emp e r atu r e Cycling P e r f or man c e (-55°C to t125"C) 250pF - 1 0 V D C Rating
Engineering Evaluation Testing Specification MIL-C -39006B Qualification Inspection - Group I T e s t
Engineering Evaluation Tes t Specification MIL-C -39006B Qualification Inspection - Group VI Tes t s 250pF - lOV, T3 Case (26 Units)
Page
19
Page
22
26
27
28
29
3 1
32
ii
L I S T O F F I G U R E S A N D T A B L E S (CONT'D)
Table No. Title
VIII
:X
x
XI
XI1
XIII
XIV
xv
Page
Engineering Evaluation T e s t Specification MIL-C -39006B Qualification Inspection - Group V I Tes ts 18OpF - 25V, T 3 Case (26 Units) 33
Engineering Evaluation Tes ts Specification MIL-C -39006B Qualification Inspection - Group V I Tes ts 60pF - 50V, T3 Case (26 Unit:) 34
Engineering Evaluation Tes t s specification MIL-C -39006B Qualification Inspection - Group V I Tes ts 30pF - lOOV, T 3 Case (26 Units) 35
Engineering Evaluation Tes ts Specification MIL-C -39006B Qualification In'spection - Group LLI Tes t 37
Engineering Evaluation Tes t s Specification MIL-C -39006B Qualification Inspection - Group IV Tes ts 38
Engineering Evaluation Tes t s Specification MIL-C -39006B Qualification Inspection - Group V Tes ts 250pF - 1 0 V / 7 V , T3 Case ( 3 Units) 39
Engineering Evaluation Tes ts Specification MIL-C -39006B Qualification Inspection - Group V Tests 180pF - 25V!15V, T3 Case ( 3 Units) 40
Engineering E.Jaluation Tes ts Specification MIL-C -3S006B Qualification Inspection - Group V Tests 6OpF - S O V / 3 0 V , T 3 Case ( 3 Units) 41
iii
L I S T O F F I G U R E S A N D T A B L E S (CONT'D)
Ti t le Page - Table No.
XVI
XVII
xvm
XIX
xx
XXI
XXII
XXIII
XXIV
xxv
Engineering Evaluation Tes t s Specification MIL-C -39006B Qualification Inspection - Group V Tests 1OOyF - lOOV/65V, T 3 Case (3 Units) 42
Engineering Evaluation Tes t 2 Volt Reverse Bias at 85°C 7 Volt Cathode Formztion
Engineering Evaluation Tes t 2 Volt Reverse Bias a t 125°C 7 Volt Cathode Formation
Engineering Evaluation Tes t 2 Volt Reverse Bias at 25°C 3 Volt Cathode Formation
Engineering Evaluation Tes t 2 Volt Reverse Bias at 85°C 3 Volt Cathode Formation
Engineering Evaluation Tes t 2 Volt P-everse Bias at 25°C 5 Volt Cathode Formation
Engineering Evaluati?q Tes t 2 Volt Reverse Bias at 125°C 5 Volt Cathode Formation
Engineering Evaluation Tes t Test /Sample Plan (UnitsITest)
Ripple Current Tes t on Remake C'niys 60pF - 50V, ltT1' Case Size Extended Cathode Area
45
46
48
49
50
51
52
54
Specification MIL-C -3900oR Qualification Inspection - Group I Tes t 57
i v
LIST O F F I G U R E S A N D T A B L E S (CONT’D)
Table No. Tit le
XXVI
XXVII
xxvm
XXIX
xxx
XXXI
XXXII
XXXIII
XXXIV
xxxv
XXXVI
Page
Specification MIL-C - 39006B Qualification Inspection - Group 11 Examination 58
Specification MIL-C -39006B Qualification Inspection - Group 111 Tes t s 55
Specification MIL-C - 39006B Qualification Inspection - Groilp IV Tests 60
Speci fi cation MIL -C - 3 9 00 6 B Qualification Inspection - Group V Tests 250pF - 10V/7V, T 3 Case (6 Units) 61
Specification MIL-C -39006B Qualification Inspection - Group V Tests 180pF - 25V/15V, T 3 Case (6 Units) 62
specification MIL-C -39006B Qualificatim Inspection - Group V Tests 60pF - 50V!’OV, T3 Case (12 Units) 63
Specification MIL-C -39U06B Qualification Inspection - Group V Tests 30p.F - lOOV/65 V, T3 Case (12 Units) 64
Specificati 19 MIL-C -39006B Qualification Inspection - Sroup IX Tests 6 5
Specification MiL-C -390068 Qualification Inspection - Group VI1 Tests 67
Specification MIL-C -39006B Qualification Inspection - Group V I Tes ts 68
Specification MIL-C -39006B Qualification Inspection - Group VI11 Tests 69
V
L I S T O F F I G U R E S A N D T A B L E S (CONT'D)
Table No. Title Page
XXXVII Specification MIL-C -39006B Qualification Inspection - G=oup VUI Tests 72
XXXVIII Parameter Behavior on Extended 125°C Life Test , Rating 25OpF - 10V/7V, Test Temp. 125"C, Test Voltage 6 Volts ( 2 0 Units) (Remake Units with Extended Cathode Capacitance) 73
XXXIX
X L
XLI
XLII
XLIII
x LIV
Parameter Behavior on Extended 85°C Life Test, Rating 250pF - lOV, Test Temp. 85"C, Test Voltage 10 Volts (51 Units) 74
Parameter Behavior on Extended 8 5 " C Life Test, Rating 180yF - 25V, T e s t Ter-ip. 85"C, Tes t Voltage 25 Volts (5 1 Units) 75
Parameter Behavior on Extended 85°C Life Tes t , Rating 60yF - 5OV, Tea t Tamp. 85"C, Tes t Voltage 50 Volts (102 Units) 76
Parameter Behavior on Exteaded &5"C Life Test, Rating 30pF - 1OOV. T e s t Temp. 85"C, Test Voltage 100 Volts (102 Units) 77
Parameter Behavior on Extended 125 O C Life Tes t , Rating 250pF - 10V/7V, Tes t Temp. 125"C, T e s t Voltage 6 Volts (20 Units) 79
Parameter Behavior on Extended 125°C :-Le Test, Rating 180pF - 25V/15V, Test Temp. 125"C, T e s t Voltage 15 Volts (20 Units) 80
L I S T OF F I G U R E S A N D T A B L E S (CONT'D)
Table No. Title
XLV
XLVI
Page
Parameter Behavior on Extended 125 a C Life Test , Rating 60pF - 5 0 V / 3 0 V , Test Temp. 125"C, Test Voltage 3 0 Vol ts t40 Units) 81
Parameter Behavior on Extended 125 C Life Test, Rating 30yF - lOOV/65V, T e s t Temp. 125"C, Test Voltage 6 5 Vol ts (40 Units) 82
v i i
SECTION 1
ABSTRACT
Over eleven hundred T3 case s ize all-tantalum capacitors
encompassing four ratings were developed and tested in accordance
with the MIL-C -39006 specification. Approximately one-half of the
capacitors were tested as Engineering Evaluat-on units and one -half
tested after the development stage as qualification units.
ra te level IIPtl has been granted by DESC primarily on the basis of
test data generated f rom this contract.
Failur o
The finalized product has all the advantages of the s i lver
cased wet ar.d i c capable of withstanding some reverse potential and
AC ripple current.
-1 -
SECTION 2
SCOPE OF WORK
1 . 0 Purpose
The contractor shall design, develop, manufacture, and qualify
a ser ies of wet-slug all-tantalum capacitors capable of meeting the
performance requirements of MIL-C-39006 and having the same
characterist ics 2.s st,-le SLK65 of MIL-C -39C06 , except a s noted
below. These devices shall be constructed so as to:
a.
b.
Have a hermetic glass-to-metal seal.
Withstand nominal reverse voltages and ripple
currents and remain functional.
c. Prevent formation of internal conductive whiskers
or particles.
2.0 Technical Requirements
2. 1 General DescriDtion
The contractor shall design and deve,Jp a capacitor w :h -. -.
the following general features, 5 --/-a '
- 2 -
y. Detailed drawings of proposed capacitor
construction shall accompany the manufacturer's proposal.
2 . 1 . 1 Case - .
The capacitor case shall be MIL-C-39006 size T 3 .
The case mater ia l shall be tantalum of such structure and purity that
it is capable of being formed to withstand reverse bias of up to two
volts at 125°C.
and anode.
The re shall be no EMF (generated) between the case
2 . 1 . 2 Seal - The cz7acitors shall have a hermetic sea l
consisting of a glass -to-tantalum bond and a tantalum-to-tantalum
weld capable of maintaining a seal-leak rate of no more than
1 x cc/second, at 1 atmosphere pressure differential at 25°C.
2 . 1 . 3 Electrolyte
The capacitor electrolyte shall be such that the
capacitor characterist ics a r e not affected by placing the capacitor
for at least 1000 hours in any position under normal ear th gravity.
2 . 1 . 4 Reverse Bias
The capacitors shall be capable of withstanding
a continuous reverse bias of 2 volts up to 125°C with no pernanent
degradation of capacitance, r?, o r DCL.
- 3 -
2.1.5 Shape and Size
Capacitor s ize , shape and external dimensions
shall conform to the requirements of case s izes specified in MIL-C-
39006, Style CLR65.
2.1.6
The capacitors shal l be manufactured in 4 ra, .A-.Zs*
10, 25, 30 and 100 DC working volts respectively at 85°C.
2. i . 8 Capacitance
The capacitance shail be at l ea s t the lower values
listed in MIL-C-39006, Style CLR65 for 85°C rated voltages of 10, 2 5 ,
50 and 100 volts under Case T3.
acceptable.
than the values l is ted in MIL-C-39006.
Capacitance tolerance of *20'70 *
Capacitance of -55°C and 125°C shall not change more
2.1.9 - Surge Voltage
The capacitors shall be capable of withstanding
surge voltages as follows a t 85°C:
WVDC
10 25 50
100
Surge V o l t a E
11.5 28.8 57.5
115
2.1.10 DC Leak-.ge
The capacitors shall have DC leakage values
l e s s than those l is ted in MIL-C-39006 at 25" anL 125°C and their
respective ratings ,
-4 -
2 . 2 P r o g r a m Description
2 . 2 . 1 Engineering Evaluation
The contractor shal l submit tes t data and reporis
showing successful completion of all of the following tes ts . H e shall
construct sufficient capacitors in case s ize 7 '3 and perforin the tes t s
presented in MIL-C-39006 for Qualification Groups 1 thru V I and
additional tes t s as specified] using the sample speciffed belcv: for
10, 25, 50 and 100 volts capacitors. The contractor shall propose
the quafitity of each voltage needed. Af'ier complet im of each tes t the
contractor shall per form failure analysis and submit .report to MSFC.
2 . 2 . 1 . 1 Groun r and I1 Tests
Group I and Group LI t es t s prescr ibed
for Qualification i n M L - C -39006 wi l l be performed.
2. 2. A. 2 Group LII Tests
The contractor sha l . pzrform Group XI
tes ts ( thermal shock, vibration] tsrnperature cycling, but not salt spral-)
defined i n Table I of MIL-C-39006B for each voltage,
- Leak;ge of
electrolyte af ter each tes t shall be determined by litrllus paper
moistenec i n deionized water. The tes t data shall be recorded,
2 . 2 . 1. 3 Groap IV Tests
The contractor shall perform Group IV
tes ts specified LIL-C-39306 for each voltage rating. Results shall
be recorded.
- 5 -
2.2.1.4 Group V Tes t s
The contractor shall per form Group V
tests specified in MIL-C-39036 for each voltage.
recorded at the various temperatures .
Readings shall be
2.2.1.5 Group VI Tes t s
The cor t rac tor shal l per form life tests
on all capacitors that successfully pass the abote tests. The life tes t
shall be in accordance with Group V I requirements. The contractor
shall perform failure analysis, report t o MSFC, and shal l send all
good capacitors to MSFC. Capad to r s shal l be weighed each time
measurements a r e taken.
2.2.1.6 Ripple Current Matrix
The contractor shall per form a matrix
study or. effects of ripple current on ten properib- biased capacitors of
each of the four voltages specified above, 240 units total, as follows:
85°C 125 "C - 25°C
Condition 1 (120Wz Sinusoidal) 450 n 4 450 mA 450 mA
Condition 2 Sawtooth pulses of Pulse Pulse Pulse f r equencv and amplitude to be determined
The current level should not cause a r i s e of capacikor temperature more
than 5°C a t room ambient.
exceed this level of I R heating.
If cecessary , reduce the 450 mA so as not t o
2
-6-
During electrical tes ts the contractor
shall f i r s t measure Cap, D F , and DCL before any forward bias is applied.
He shall then apply forward rated voltage for some chosen period, sur::
as five minutes, and again measure Cap, DF, and DCL. I’,ots f o r Cap,
D F and DCL before and after forward bias ;Cd l be made at 0, 120,
500, 1000, 2000 and 4000 hours, and curves drawn.
--
At least one l i t rms check shall be
made during this testing, and final visual inspection shall be made.
Two capacitors f rom each rating shall
be opened and examined for internal deteriorktion (whiskers, leaks,
cracks, etc.).
Remaining capacitors shall be sent
to MSFC.
c 2 . 2 . I . 7 Reverse Bias
The contractor shall perform matrix
studies at a reverse voltage of -2 volts using 10 each of each voltage
rating made with at least three cathode formation voltages (such a s
3 V , 5 V and 7V) as indicated below.
-7-
Nominal Cathode Formation Temperature
25°C - 85°C lZ5OC 7
Voltage
3.0 10 each 10 each None voltage voltage rating rating
5.0 Same None 10 each voltage rating
7.0 None 5 ea@ 1OV 10 each 5 ea@ 100 V voltage
rating
This is a total of 210 capacitors.
These tests shall run for 2000 hours, with
electrical tests (Cap, DF, and DCL) taken at 0 , 250, 500, 1000 and 2000
hcurs. See Para. 2.2.1.6 for Electrical Test Method. r
2.2.2 Demonstration of Capability to Mass Produce and Qualify
When tes ts in 2 .2 .1 indicate to MSFC a capacitor
of stable design and of good workmanship and quality, the manufacturer
w i l l produce a minimum of 600 s ize T3 capacitors and subject them to
screening and qualification tes ts as specified in MIL-C-39006B for
Style CLR65. The subgroups should be divided using the full total
specified, however only the T3 case s ize will be used. That will be
a minimum of 594 devices for the voltage classes specified in
MIL-C-39006B. All limits and tes t conditions shall be those specified
in MIL-C -39006B.
-8-
After the successful completion of the above
tests and inspection, the all-tantdum capacitor in the T j case size
in the voltage ranges specified in MIL-C-39006B will be considered
qualified for MSFC use in Critical Space Hardware. These capacitors
wi l l be sent to MSFC after completion of tests.
2.3 Reports Requirements
2.3.1 Monthly Progress Reporat
The contractor shall have this report prepared
for distribution by not later than the 15th day of the month following
the reported period. Reports shall be in narrative form, brief and
informal in content, and w i l l include, but not be limited to the following:
a. A quantitative description of overall progreg . ;
b. An indication of any current probler- .vhich may impede performance, and prop, zd corrective actions , and:
C. A discussion of %e uork to be performed during the next mcmthly reporting period, including the approximate man hours and dollar expenditures.
d. Expenditures t o date and forecast of funds required for completion. a detailed discussion of funding deviations or problems.
This should include
2.3.2 Final Report
2.3 .2 .1 The final report shall be narrative i n
form and include, as applicable, the following:
-9-
a.
b.
C.
8.
e.
Initial program concepts;
Changes in program concepts and factors causing the changes;
Problem areas and necessary corrective actions;
An overall evaluation of the program and the program results, and;
Recommendations.
2.3.2.2 A rough draft of the final report shall be
submitted for approval to the Contracting Officer within twenty (20) days
after completion of the Scope of Work. Comments w i l l be furnished to the
contractor wit& fifteen (15) days of receipt of the draft copy of the
report. Upon receipt of the draft copy in its approved form, the
contractor shall reproduce and distribute it as directed-in Para. 2.3.5.
2.3.3 Report(s) Preparation Instructions
The above report(s) shall be submitted under a
title page showing the following information:
a. Contractor's name and address, including segment generating the report.
b. Title of report, including period covered, when applicable.
c. Author(s)
d. Type of report and contract number
e. Date of publication
- 10..
f. Prepared for George C. Marshall Space Flight Center, Marshall Space Flight Center, Alabama 358 12
g. fnclude an abstract
h. All technical reports. wblications, and wisuol presentations submitted to MSFC under this contract shall use the International System of Units as the preferred primary system. Ekpression in SI unite alone would obviously impair communications or reduce the usefulness of the report to the primary recipients. When both systems of units are used, SI units are to be stated first and customary units afterwards, in parentheses. In each such case, the publication shall state which system of units was used for the principal measurements znd calculations. SI units are specified in National Bureau of Standards Technical News Bulletin, Vol. 48, No. 4, page 61, April 1964; and defined in NASA SP-7012, The International System of Units , Physical Constants, and Conversion Factors, revised 1969. Both of these documents can be obtained from the Superintendent of Documents, U. S, Government Printing Office, Washington, D. C. 20402.
2.3.5 Reports Distribution
Copies of report(s) other than those intended for the
Defense Contract Administration Services District, shall be distributed
to National Aeronautics and Space Administration, George C. Marshall
Space Flight Center, Marshall Space Flight Center, Alabama 35812 to the
codes 2nd in the quantities indicated below. A copy of the transmittal
letter showing distribution of the reports shall be furnished to A&PS-PR-M.
-11-
Monthly Quarterly Final - C d e s
A&=-PR-RDMI 1 0 0
A&=-MS-D 5 AQPS-TU 0 SQE-QUAL-QT 3
S&E-QUAL-OC 1 S&E-ASTR-RNI 1 StE-QUAL-E (Davis) 1
1 Totals 13
W. R. Barlow
Applicable DCASO -
*Plus reproducible copy.
5 1 1W
1 1 1 1
20 -
5 1
10
1 1 1 1
20 -
- 12-
SECTION 3
DISCUSSION
A. Development Phase
(1) Special Tooling and Equipment
'It should be noted that a l l tooling and equipment a r e
funded solely by the Sprague Electr ic Company.
An indexing welding fixture was designed in the
ear ly par t of September, 1973 to be used in the
hermetic sealing operation of the can rim and outer
seal header. The welding method employed was that
of overlapping TIG welds.
Problems with cracked glass plagued this operation
and required severa l modifications in the mechanical
and electrical design of the indexing fixture.
fifth month evaluations revealed that the efficiency
By the
and reproducibility of the system was improved to the
point where a total of 218 capacitors were welded with
-13-
acceptable quality and were scheduled for use in the
evaluation of processes in the Engineering Evaluation
Phase of 5 . ~ contract.
Several refinements were subsequently made in the sys tem
t o facilitate the welding operation and this system was
not finalized until the eighth rr-onth of the contract.
(2) Procurement of P a r t s
a. Tantalum Cans
Several dozen prototype drawn tantalum cans were
obtained f rom a potential supplier.
evaluation of these tantalum cans indicated that the
supplier has the necessary technology t o produce
tantalum cans having the properties required in this
contract. Subsequent to finalization of the appropriate
par t specifications, procurement was initiated for a
sufficient quantity of tantalum cans needed to complete
this program.
Results of an
Two shipments of drawn tantalum cans were received
during January 1974.
was used for evaluation including welder set-up and
cathode studies.
The f i r s t of these shipments
The second shipment was used tc
- 14-
refine processing techniqzes and to construct par t s
fo r the Engineering Evaluation portion of the contract.
The remainder of the tantalum cans to fulfill the
requirements of this contract were received by
March 1974. However, due to the quantity of cans
used i n developing a solution to the hermetic seal
problem and to alleviate the possibility of a future
shortage, 200 additional cans were procured i n
December, 1974.
b. Tantalum Shells.
The tantalum shel l portion of the all tantalum
capacitor construction is a drawn metal par t used
in the construction of the tantalum-to-glass-to-
tantalum seal,
of the sea l and is welded to the capacitor case. The
tantalum can is distinguished f rom this par t in that
it comprises the cathode and contains the working
electrolyte for the system. Initial attempts to procure
the tantalum shell were successful. Subsequent
attempts, however, resulted i n cracks and excessive
metallurgical s t r e s ses . These properties precluded
It is that par t which forms the periphery
-15-
the use of these par ts in seal construction.
Attempts to alter metallurgical properties were
futile.
problem to the surface condition of the tantalum
Extensive evaluation finally traced the
stock. A cooperative program between the Sprague
Electric Company, the shell manufacturer and the
material supplier was initiated in an attempt to solve
the problem. Numerous t r ips by both Sprague
representatives and the mater ia l supplier were
made. A decision was then made to physically
t rea t the surface of the tantalum stcck by established
Sprague processes in order to improve drawing properties.
Several samples of specially prepared tantalum stock were
prepared and submitted to the shell manufacturer.
The treated tantalum was found to perform infinitely
better than the untreated stock.
scheduling was adhered to and sufficient par ts to
manufacture the remaining engineering evaluation
par t s were put through the first stage of shell manu-
facture.
examined by the metallurgy department of the Sprague
Electr ic Company and resubmitted to the shell manu-
facturer for finishing oper G t' ion.
Preliminary program
The partially completed shells were then
Two s eparat e pre -drawing t r e atrnent s we r e
tr ied, and the resulting parts evaluated. Both
treatments resulted in the satisfactory drawing of
shells with one method preferred chemically. Seals
were manufactured f rom the shells using the
perferred treatment method and these were
used to finish additional capacitors.
supply was cri t ical , but the drawing problem was
solved.
The shell
During the December 1974 report period 1700 shells
were received which supplied an adequate number of
shells for the contract completion. However, the
delay incur red her e unavoidably delayed the
completion of the contract by a minimum of two
months.
c. Glass Insulator (Tantalum Shell)
The extruded glass for use in the glass-to-tantalum-
to-glass sea l was received in mid-December, 1973.
Glass preforms were prepared f o r use in seal
evaluations.
d. Chamber Top Retainer
Initial experiments with the prototype tantalum
-17-
e.
cans revealed that it was necessary to modify the
top retainer. Hence, redesigned top retainers w e r e
ordeydd and received during December, 1973, These
par ts , however, along with the bottom retainer required
slight modifications for the purpose of a better fi t . The
modified par ts were subsequently procured.
Construction of the Engineering Evaluation parts
utilized the original par t s which did not a l ter the
capacitor performance o r capabilities.
Specifications and Drawings
Specifications and drawings pertaining to the
component capacitor par ts were completed by
March, 1974.
Cathode Studies
LCeveral tantalum powders and processing cmditions
(identified i n Figure 1) were evaluated for producing a
suitable cathode system.
the percent cathodic efficiency, plotted against cathode
Figure 1 graphically represents
formation voltages for these cathode systems,
cathodic efficiency is defined as:
The percent
Percent Cathodic Efficiency VS
Cathode Formation Voltages For Various Cathode Syste
100
90
80
70 ?'o CatLodic Efficiency
60
50
40
30
20
10
Figure 1
-19.
Where CAE is the capacitance of a standard 10 volt
rated anode measured ia series with the experimental
cathode system; and CAS is the capaa tance of a standard
10 volt rated anode measured in se r i e s with a platimted
silver cathodz. The cathode sys tem F which utilized an
ultrahigh CV/gram powder identified in Figure 1 represented
.e best 'obtainaole cathode performance. Results of
these cathode stL*dies indicated that presently available
tantalum powders could provide monometallic cathode
systems which will permit the contract capacitance
objectives to be met at the specified cathode formation
voltages of 3, 5 and 7 volts.
Preparation and processing parameters fo r the mono-
metallic tantalum cathode were finalized and implemented
during Febrtlzry 1974.
cans were processed with good results using thr-se
techniques.
-9 significant number of tantalum
A patent application for th is processing technique was
' filed on August 22, 1974 under number SN 499750,
entitled "Method for Preparing the Container of an
Electrolytic Capacit , I
-20-
The above processing technique was obsoleted by a more
improved, pressed cathode l iner method. The l iners a r e
pressed and sintered in the car.. In this man2er the l iner
weight and density can be increased and controlled within
5-770 thereby yielding higher and more uniform capacitance
values between cans. I
Five capacitors rated at 560pF - 6 V which were made with
pressed cathode l iners were vibration tested up to the 80G
level, as a means of determining the durability of the
cathode system, with satisfactory results. These units were
vibrated at 20G1s, 40G's and 60G's in each of two directions
for 1 hour/direction ahd with the frequency modulated between
10 and 2000 hertz. At the 80G level the same procedure was
followed a s above but then the capacitors were given 3 hours
of additional vibration for a total time of 8 hours. At this
point testing of these units ceased.
Listed in Table I a r e the individual data fo r each capacitor
before test , after shock (100G's) and after vibration at 80G's.
The decrease i n the dissipation factor (DF) after the 80C
vibration tes t was looked at as a means for lowering the
equivalent se r ies resistance (ESR) however these results could
not be repeated with other units tested similarly.
-21-
TABLE I .
CATHODE LINER DURABILITY TESTING (560yF - 6V)
Before Tes t Post (IOOG) Shock Post Vibration (80G) DF DCL Cap DF DCL UnitNo. Cap. Dz DCL Cap -
1 574.1 23.4 .0055 560.1 26.8 .005 592.4 18.2 1.4
- -
2 563.0 23.8 -0075 549.5 26.2 .0130 582.6 16.5 1.4
3 569.6 26.6 .0090 556.7 25.1 .0135 592.6 16.4 1.5
4 571.5 22.4 .0062 557.6 25.6 .0075 593.5 17.3 1.0
5 567.8 24.4 .0048 561.0 28.2 .0084 599.9 18.3 1.3
Cap = Capacitance in yFd D F = D;-ssipation Factor in 70 DCL = Direct Current Leakage in PA.
-22 -
(4) Capacitor Design
During the first quarter sevaral prototype 250pF - 1OV rated
tantalum capacitors which were constructed (without the
hermetic seal) using cathode sys tem F were evalvated for
electrical characterist ics. After assembly the par t s were
processed according to standard Sprague Electr ic Company
processing techniques and measured. The typical electr ical
parameter values for these capacitors were as follows:
a. Capacitance = 263pF
b.
c.
d.
Leakage Current @ 1OV = 2. SPA
Equivalent Ser ies Resistarice = 1.3 ohms
Leakage Current @ -2 V = 0.39@.
Sever21 prototype capacitors were constructed during the second
quar te r period to evaluate cathode systems and the welding
fixture.
were necessary to ensure compatibility with processing
pa i -me te r s .
These evaluations indicated that 2 ?sign modifications
Difficulties encomtered i n containing the acid
electrolyte during welding necessitaLed modificat:ons to the
top retainer portion of the capacitor. Evaluation of the modified
design proved to be effective in containing electrolyte during the
welding operation and was incorporated into the finalized
capacitor design.
Evaluatim capacitors.
This design was used in the Engineering
-23-
Ten 60yF - 50V capacitors were consigned to Marshall Space
Flight Center (L. Hamiter) for evaluation.
B. Engineering Evaluation Phase
(1) Tes t Specification
Tes t specificatims outlining test procedures and sequences
to be used during the Engineering Evaluat iw an-! Qualific-t;m
Testing portions of this contract were prepared and issued
to appropriate personnel by the Sprague Quality As mrance
and Reliability Department during the first quar te r of t h i s
contract.
Work on the Engineering Evaluation Phase of the contract was
initiated i n mid-January, 1974.
Processing of par ts necessary for use i n the Engineering
Evaluation began, including the processing of the cathode
and anodization of tantalum pellets.
i n procuring tantalum sea l shelia resulted in a delay in the
execution of this portion of the contract. Several Engineering
Evaluation tes t sample capacitors were randomly selected
f rom parts being processed and evaluated.
evaluation was to characterize the parts for electrical , temper -
ature and environmental performance.
evaluated were the 250pF - 10VDC and the 60 pF - 5 0 V D C units.
The difficulty encountered
The purpose of this
The two ratings
-24-
Electrical and temperature characterist ics for the 250pF - lOVDC and 60pF - 50VDC ratings a r e shown in Tables LI
and ILT respectively. Al l parameters were within the Specifi-
cation MIL-C-39006 limits except for two par ts which slightly
exceeded the -55OC capacitance change requirement. Two
parts do not meet initial capacitance specification (i. e. *20%).
All other performance parameters for the 6OpF - 53VDC
rating were within specification limits.
Several units of the 60pF - SOVDC rating were vibration
tested per Specification MIL-STD-202 Tes t Condition ttDtt ,
wi*thout voltage. All par ts were fcund to meet the electrical
performance requirement after vibration testing. These
dpta a r e presented i n Table IV.
of this test demonstrates the capability of the cathade coating
to withstand severe vibration without adversely affecting
The successful completion
electrical performance.
Temperature cycling performance for the 250p.F - lOVDC$
rating ( -55'C to +125"C after 30 cycles) i s presented i n
Table V. Electrical performance was not affected adversely
by cycling tests.
of meeting Specification MIL-C -39006 requirements.
This performance indicates the capability I
Q
0
0
m
rr) I
. m
c w E
u 0 In
ru r(
u 7 * E
*
.,-I
3
mm
NN
NN
NN
d-
-,
0000000000
..........
.
-27-
TABLE IV
VIBRATION TEST RESULTS PER MIL-STD-202
60pF - 50VDC RATINGS
Reading Initial Reading After Vibration Test
5 OV 5 OV ESR DCL C a p - - ESR DCL - Unit # C a p - -
1 2 3 4 5 6 7 8 9 10
60.1 .93 b 06 55.3 1.2 . 06 61.9 -95 . O S
60.7 1.0 .05 55.2 1.2 . 05 54.6 1.2 .05 54.3 1.9 .09 63.0 .92 . 05
57. 1 091 1.5
59.9 1.0 b 2
60.2 .90 .I3 55.4 1,l . 13 57.3 .92 1.2 .
60.0 1,O 1,3 60.8 .94 .13 55.3 1.2 0 1 1 54.4 1.2 011 54.7 1.8 . 12 63.0 092 0 1 1
62.0 b87 014
Cap = Capacitance in pFd. ESR = Equivalent Ser ies Resistance in ohms. DCL = Direct Current Leakage in FA.
TABLE V
TEMPERATURE CYCLING PERFORMANCE ( -55°C to +125'C) 250~1.F - 1OVDC RATING
Post 10 Post 20 Post 30 Temperature Cycles Temp. Temp. Tes t
Initial Cycles Cycles 1 ov 1 ov 1 ov
Cap ESR DCL CGL DCL Cap ESR - - - Unit #
291 . 76 . 56 . 68 -88 274 -63 302 -77 2.6 6.1 6.2 279 1.0 363 -86 .54 1.0 1.6 34 1 . 74 217 . 77 . 43 . 70 -54 212 . 80 334 -68 42 . 75 -58 313 -56 314 -76 2.8 . 69 -59 301 . 66 308 . 75 . 43 . 75 .55 298 .63 252 .61 * 9 2 3.1 .81 251 . 59
1 ov DCL
86
- 6.0 1.4 . 74 . 84 . 71
. 98 2.6
Reag e 1 ov DCL
. 52 . 71
.49 . 45 . 53
.43
.64
.47
-
Cap = Capacitance in pFd. ESR = Equivalent Ser ies Resistance in ohms. DCL = Direct Current Leakage in PA.
-29-
Work continued on this tes t phase units with the 7 volt
cathode groups completed during April 1974.
48 hour voltage conditioning, (Group I of the MIL-C-
39006 Specification) was performed during the May 1974
report period. These tes t data are reported in Table VI
under the 50 unit section.
The
All initial parameter< with the exception of two DCL
levels i:- the lOOV rating and one high capacitance
par t i n the 25V rating a r e within MIL-C-39006, style
CLR 65 limits.
Twenty-six units f rom each of the tes t ratings, 250pF - lOV, 180pF - 25V,- 60pF - 50V and 30pF - lOOV, were
placed on a Group VI, 2000 hour, 85°C life test.
capacitor weights were measured at each readout point.
This testing was completed by November 1974 and the
tes t data a r e reported i n Tables VI1 - X for the 1OV - lOOV groups resTectively.
Individual
Additionally capacitors f rom each of these ratings were
subjected to the Qualification Inspection testing for Group
III (Shock, Vibration, Salt Spray and temperature cycling),
Group I V (Terminal Strength, Moisture Resistance, Surge,
Sleeve Tes t and Cold Temperature Storage) and Group V
- 3 0-
*m
e--
Om
m
9-
n
idd
l I
r-
m
mm
-
l.iN.0
I I
m
7
**
N
3
1
4O
I
rh
u1
-J
414108
e c1 .
..
N-
-
0-
6Y
O 0
8
N ..
.
0-
- 0-
... a
m0
I I
In
E
a tc
c
.e
t 0 U
U L
5 C
C
C
n
b*
b9
N
N
..
om
ON
010
Nrn
..
WN
m -3
N *v
dd
NO
nl
m
04
Nc
u
..
mm
&
&
11
00
00
0
0
fu
zz
A
h I
Y
b
cg 0
+ Qo
9
+ - -4 4
4-
W
0
4- .. & 1
s C 0 0 ry
n
E 2 s a 0
(d U
.d
U
rb a
om
-m
a
m-
4
..
..
rn
rn
mm
L
LL
L
51
55
0
00
0
ZX
ZZ
0000
mo
o
nlo
o
-N
U
U
e: Q)
c Q)
&
&
u u
a (3
mc
or
nm
h
2h
4
05
00
Z
ZZ
Z
3
15
0000
mo
o
NO0
- .v
c
M
Y
c’ 3 bn
0
.d
-32-
< s c r D U a I
s C
C
C n
IC
In
0
t-
N
+
eo 00
0
+ t- 4
0
+ v1 &
1
;
0
0 0
N
c
E Q
) V
C (d
u (d a
(d
0
d c,
.r(
Ln
IC
NN
..
-N
Qr
C
..
4
-4
t-N
eo
..
4
0-
ba
.
.
urn
L
L
55
0
3
00
0 0
N
z3:
CL
E
2 L. 0
0
Y
c 3
rd a .r( c)
.#-I
w a
ij
9
*a+*
NN
OIA
.. 3000
AA
AA
0303
mo
o
NO
0
"N
-33-
a c -? c
c 0 U
Q L z s C
C
C
fi
c
.1
N
0
4
m
+ e
ln
0
+
N
4
0
+ m
&
3 3
0 0
C
N
z - 5 a.l u e (d
u a a (d
L)
U
.r(
a
-c
N
.. d
.4
VIO
I
lc
lc
.
.
9-
ii
ON
wm
..
mm
&
&
35
;; 00
0 0
N
n
Ts Y
b 0
u cd E 0
a a 0
m
c)
cr .rl Y
.d
ON
mm
M
-r
d.
4
... o
oo
d
0300
moo
NO
9
-n
l
0000
moo
YO
0
-N
-34-
4 L
c .. c 0
u U I
; C
C
C
h
6
* 0
QI
0
nl
4-
In
N
0
4-
M 0
0
+ m
& I
$ 0 0 0 nl n
E 0)
U
E
a Y
.d U
(d
P
(d
u a
9p
c
00
..
ma
ro
m
..
Qt
c
NN
..
do
.11 N
..
mm
53
&
&
G
00
0 0
fu
c
s
- &
0
c)
U
cd cr E C
(d a
rn
.r( c)
.s4 m
b"
d
mn
l 0
4
dd
ma
m
a
dd
4
rngo
do
00
..
N
-n
l 40
00
..
mm
&
&
35
G!
00
0
0
tu
dddd
dddd
dd
dr
l
nl
lc
mo
g
om
NO
eo00
a\O
'A
O
5113 521s
0000
00
00
0000
moo
mo
o
NO
0
NO
0
xz
xz
%
$$
c1
.c,
3 E
x u L3
n
M -
-35-
(Stability at Low and High Terr,peratures). The
summarized test data for these Groups a re reported
in Tables XI - XVI.
During the August 1974 report period a serious problem
relating to the capacitor hermeticity came to light.
Leak testing of random samples of capacitors per
MfL-STD-202E, Method 112B, Condition C, procedure IIIa
revealed fine leaks in 11 of 12 units tested.
leaks (Method A) or electrolyte leaks were detected.
No gross
This situation prompted an examination of the entire
seal situation. As a result all the completed units on
hand, with the exception of those at the control lab, were
tested for hermeticity.
gross leak test (MIL-STD-202E, Method 112B, Condition A)
failures were noted.
prior to Condition C to minimize contamination of the Mass
Spectrometer.
leaks after gross leak screening, and 111 good seals.
represents a 44.6% yield on seals out of the 249 units tested.
Seal problems were narrowed down to sensitivity to welding
heat, with the further observation that the condition of the
tantalum surface of the shell prior to fusing affected the
degree of sensitivity.
One new development was that
Condition A was used as a screen
The results were 114 gross leaks, 24 fine
This
-36 -
+ F
Y
>
d
>
0
ORIGINAL PAGB a OF POOR QU-
>
I
i 141
m
m
E E
>
>
0
w
m-9
..
.
ow
0 1
I 0
N
U
0
In cu c: 0
Il
n -
..
..
qooo
Nd
N
*m
*mmN
..
..
o
co
oo
0
I N
-39-
U
0
m
nt
ON
N
od
9
rn
mo
a-
I
..
.
4
mm
Q
llnm
nl
e
9
0
9m
O I
I a-
... 4
I- N
om
a@ ..
04
0 I
I
4
.... e
lno
-
004
I
... r-'p
co
o
9
ln
N0
9
QN
U'C
O
Qc
- +
.... 4
0 90\-
4-C
r)a
+
.... d
-40-
["
0
5;
... N
mO
1(
\1
9
+
uic*;d
IN'
In
+
m
0
-a0 e
.-
.
-*
* 'P
9
9
M
pr)
0
m
e
9
I I
FN
w
N
C' I
NO
%
I-
m
-*
or
I
9 ...
44
61
l
m
u 0
m
N
u m
N
&
$4
46
m
-41
-
v1 k
U
0
Ul
N
... ON0 I
d'
m
+
OI
m
me
00
Q
J
NN
N I
O
m
I
... m
cc
mN
4
Ln 4
N"
I
O
... . m
I
9
* c-
o\
I l
cc
9
N
cr
)I
cc
N
e""
@N
O I
I N
...
cc
o
No
m;
WN
Od
cr)
I
....
-42
-
Changes in the sea l fusing and welding processes, in order
to minimize the heat sens,tivity, resulted in a decrease
in units failing the s e d tes t s f rom 54% to only 7%. Since
shells were in shor t supply only 130 seals were available
for welding with the new processing methods. These
130 seals resulted in 121 units successfully completing
the seal tests. The 770 loss represents nearly an eight
fold decrease in the loss ra te f r o m faulty seals.
However, due to further problems in the welding of the
hermetic seal a comprehensive program, including the
investigation of l a se r welding, was started.
there were sufficient shells and cans on hand at this t ime’
Fortunately
to allow a thorough and methodical investigation of the
problem. Significant progress on this problem was made
during the seventeenth report period and by the eighteenth
report period it w a s concluded that l a se r welding was the
solutior, to the hermeticity problem.
l a se r welded with a greater than 9770 hermetic yield.
Over 500 units were
Due to losses encountered during the welding and hermetic
sea l difficulties i t was necessary that a few additional units
be assembled to complete the ripple matrix units. These
units along with the units for completion of the reverse
voltage tes t matrix were completed by May, 1975. The
-43-
voltage conditioning data for there groups a r e reported
in Table VI under the two 20 unit headings. The ripple
tes t units were sent to NASA on May 13, 1975 for testing.
The 7 volt cathode formation group began the 2 volt
reverse testing at 85°C and 125°C during October.1974.
Ten capacitors f rom each of the four ratings were sub-
jected to the 125°C temperature and 5 units f rom the
1OV and lOOV groups were placed on the 85°C test.
This testing was completed by Janaary, 1975. The
summarized tes t data a r e reported in Tables XVII
and XVIII for the 85°C and 125°C temperature testing
respectively. These data indicate that a 7 volt formed
cathode i s capable of withstanding intermittent voltage
reversals in the order of 2 volts.
that a stability reage at the 85°C rated voltage and
It should be noted
temperature fcr 16 hours was performed at the end of
each readout interval.
The 3 volt and 5 volt cathode formation groups were
completed by May, 1975 and commenced the 2 volt
reverse bias matrix testing,
by August 1975 and the summarized test data a r e reported
This testing was completed
-44-
>
w
.
-4s-
?
I Ib
l e
e I
-
9 e
e e
ea
+ 4
* I
e e
o'
I-N
-*
I
l0
OO
O
99
99
I b'
__
-N
N~
-O
-
ln(
.tm
ddddd
*(. ?
?".?
?
oo
oo
a
ON
(.*
*
NN
NN
W
NN
NN
N
do
'n'o
'n'
b
I- -
i n Tables XIX - XXII. In general the 5 volt cathode
formations proved to be saiisfactory and the 3 volt cathbde
formations to be marginal for the required 2 volt reverse
capability.
A summary of all the Engineering Evaluation Testing i s
given in TaLle XXIII.
Dcring August 1975 reports were received f rom NASA that
several capacitors were showing excessive Capacitance loss
duricg ripple voltage testing. Evaluation of the data indicated
that this bahavior was probably dependent upon initial cathode
capacitance. A higher cathode capacitance appears to be
required than i s necessary on1.y to support the anode
capacitance to obtain the desired total initial capacitdnce.
Hence, 6OpF - 50volt capacitors with extended cathode
capacitances adequate to cope with the ripple. current
encountered in the testing were constructed for retestin;
t o confirm that low cathode capacitaRce was the problem.
Ten of these 60pF - 50 volt units to replace the ten units
showing excessive capacitor -5ange on ripple test were
shipped to NASA for the retest during November 19’15.
Analysis of t -vo capacitors of each rating (250pF - lOV,
180pF - 25V, 60yF - 50V and 30yF - lOOV) failing the
-47-
90
Na
N
~L
-
OQ
OO
.dddd
* Odd0
m~
co
-
N-
O
c.-_-
.
: Y
-1
Q
<
e
20=3%Z
Od
d0
6
00
00
0
n
~n
a-
o
00
0-
-
dddid
Om
nO
a
----e
OO
QO
O
m
mn
-n
o
ddddd
dd
dd
d
or
01
1
oa
om
o
ddddd
oo-o-
bl
1-i *,-I n
-r-4
-
nr
40
Q
PO
nn
-1i=
00
00
0
127 -. -. -.
*1 *I
r; ; ff f --. 0
00
00
-. 19.9.
N
?--N
-
nt
mn
n
ddddd
.no
rn
o-
ddddd
NIY
NC
IN
(. - 1-i i/ 4.3
wc
n-
c
-0
00
0
<id
<<
N
NN
NN
Ca
.O.n
-4
-43-
x X
m
0
ON
-0
N
OO
-
dddd
oco-
0';;; ---- *e-... C
CP
S
NN
NN
.&;o
s
ON
IN
n
cr
-
00
0
-n
Nn
ce
-+
nr
-
00
-
.o'd
dd
a
-*o
I
U-
0
00
00
.dddd
P >
*
+,
-
i-
>
0
e
-
-0
-
- .: ':5
9 :* C
W>
b
U3
a
.ne- b-0
g;z .
-49-
om
04
*a
me
N
Q-C
IO
0
00
00
..... *a*--
cc
c.Q
c
NN
NN
N
mc
om
r
idn
'dd
*
*e
n*
N
YN
NN
a
-*.tu
-
OOOdd
00
01
5
NQ
OC
o
m-
0.
.-
0-
0
9-9
4
....
.;<i; m
mn
m
*m
-n
~
OO
N-
N
Odddd
Odd&d
ma
n
o
-~
m-
m
ta-,, O
-N
nY
ddddd
-N
-
*o
eo
ul
0-
0-
0
ddddd
~n
n~
n
ddddd
io';;;
e m
e. o
o'o
'on
'o
-e-- 0
*-n
-u
c
)n
nn
n
..... O
O-
Yn
NN
NN
N
9.9.99.3 **-e*
a****
..... m
mm
mr
n
on
aa
m
> c
- 0 e
-
, .:
.
TABLE XXLII
ENGINEERING EVALUATION TEST TEST /SAMPLE PLAN
(UNITS/TEST)
25OpF - 1OV 18OpF - 25V 60pF - 50V 30pF - IOOV Test Report Test Report Test Report Tes t Report
Test Routine N ~ . ( ~ 8 0 4 ) N ~ . ( ~ 8 0 5 ) NO. ( ~ 8 0 3 ) pro. ( ~ 8 0 2 )
1. Group1 Voltage Conditioning DC Ledcage Capacitance Dissipation Factor
2. GroupII - Visqial & Mech. (Internal) Vis.ial & Mech. (External)
3. GroupIII Shock Vibration Temperature Cycle
4. Group IV So Id e r abili ty Terminal Strength Surge Moisture Dielectric Sleeve Test Insulption Sleeve Test Low Temp. Storage Seal
5. GroupV Stab. Low & High Temp.
6. GroupVI Life Test
7. 2 Volt Reverse Bias Matrix
Voltage Cathode Formation
3.0 Volts ( 2 5 ° C ) 3.0 Volts (85°C) 5 . 0 Volts (25°C 5.0 Volts (125'C)
7.0 Volts (125°C) 7.0 Volts (8:,"C)
90 90 90 90
2 75
3 3 3
3 3 3 3 3 3 3 3
3
26
10 10 10 10
5 10
85 85 85 85
2 . 77
3 3 3
3 3 3 3 3 3 3 3
3
26
10 10 10 10
10
85 85 85 85
2 75
3 3 3
3 3 3 3 3 3 3 3
3
26
10 10 10 10
10 -
YO 90 90 90
2 75
3 3 3
3 3 3 3 3 3 3 3
3
26
10 10 10 10
5 10
NASA ripple current tes t f o r capacitance loss was
undertaken and completed in December, 1975. In
general it was shown that the capacitance loss was
due to an increased thickness in the cathode dielectric
oxide layer as is evident by a color change in the
cathode lining. A detailed report including colored
photographs showing the cathode colors were sent to
NASA.
The ten 60yF - 50V remake capacitors completed
2000 hours of ripple current testing at NASA by
April 1976.
for the electrical parameters of capacitance, dissipation
factorand room temperature DC leakage as we11 as
capacitance stability.
in the parameter data summary table.
The test data a r e reported in Table XXIV
The tes t conditions a r e stated
It will be noted that all capacitors experiecced some
capacitance loss over the tes t interval, however, wi th
the maximum loss being -6 .670.
the maximum capacitance loss was -42%. The failure
mode he re was apparently eliminated via the extended
cathode surface area.
With the original units
-53-
m
Q)
In
In
* I
n)
*
F-
i
In
&
vi I
m
vi
00
0
v1 2 z 3.
w
4 Y z 0
Tr I
E 0 &
trl
0
ln I
0
m
3
al N
Q; m
I c (6
.C(
a" 0
m
pr) I
0
U
m
c.)
0
C
N
I
A
m -
N
d) 9
0
N
c)
5
0
W
CJ Q
)
I
m
4
9
r
4
0
4
00
00
00
*"a
-4
2," co 9
ui
N
0
A
2.
F-
0
Q 1
(d 4
I .. 0
E
0
.C(
Y
.CI
W
E
0 u
h
e a
(d
u Q
u n n
rrl. Y
(d
0
-54-
The initial D F values reported at NASA s e e m to be
out-of-line with the values measured at Sprague pr ior
to shipping the units.
more reasonable when one compares them with the Sprague
init ial values.
The 2000 hour D F values a r e much
C. Qualification Tes t Phase
Initial processing of the Qualification Tes t Phase capacitor
parts began in June 1974. During the next 3 - 4 months the
development of the hermeticity problem and the unavailability
of materials resulted in a prolonged period of inactivity in this
phase.
By December 1974 approximately 7570 of the qualification
tes t units had been processed to the point preceding the hermetic
s e d closure. Once again the hermeticity problem delayed
further progress on these units for a couple of months.
HJwever, by April 1975, 594 tes t capacitors had been
delivered to the Sprague tes t facility for commencement of
this tes t phase.
During May 1975 the qualification testing had proceeded as
follows :
Group i testing was complete. One unit (60~F - 5 0 V )
w a s replaced as a result of high DC leakage. 1-
- 5 5 -
remained within the required 2.0p.A range but
deviated greatly f r o m the remainder of the
units (see Table XXV).
Group II and Grcup 111 tests were completed
without fa i lure (see Tables XXVI and XXVII
respectively).
Group N had been completed without fa i lure (see
Table XXVIII),
Group V had been completed without failure ( see
Tables XXIX - XXXII for the lOV, 25V, 50V
and lOOV groups, respectively).
Group VI was scheduled for the 1000 hour readout
on 9 June 1975.
successfully passed.
The 250 hour readout was
Group VI1 was scheduled for completion about
4 June 1975.
Group VI11 was scheduled for the 1000 hour readol;t
on 9 June 1975. The 250 hour readout was
s u cc e s s f ully pas s e d . Group IX had been completed without failure ( see
T able XXXIII).
The Group VI1 testing was completed during the first week of
June 1975. The tes ts were completed successfully, and in
- 5 6 -
I I
I I
am
E
E
aa
&
&
100
00
uu
I I
I I
1
cr) O
Nc
r)
co
rn
01
I
N .
..
cr) N
cv
940
9
4c
;d
I
N
mN
e
P-0
d4
dl I
rr)
>
-57
-
TABLE XXVI
Rat ing
SPECIFICATION MIL-C -39006B QUALIFICATION INSPECTION - GROUP II EXAMINATION
A r e a Visual and Mechanical Examination
250pF - 1OV T 3 Case
180pF - 25V T 3 Case
60pF - 50V T 3 Case
30pF - lOOV T 3 Case
of Exam
Internal D eg rad ati on Dimension; Workmanship Markings
Internal Degradation Dim ens ions W orkmanship Markings
In t e rna l D e g r ad ati on Dimens ions W orkmanship Mar king s
Internal Degradation D i m ens ions W orkmans hip Markings
Int e r nal (1 Unit)
Conforms - -
Conforms - - -
(2 Units)
Conforms - - -
Conforms -
External (98 Units)
- Conforms Conforms C onf o r ms
- Conforms Conforms Conforms
(196 Units)
- C onf o r m s C onf o r ms C o d c r m s
- C onf o r m s Conforms Conforms
- 5 8 -
-0
9
NQ
'O
io
m'o
*
I
N
I2
... c 0 u
uu
u
ul
-
*O
mN
91
o
ol
no
4
90 u
uu
IC
9
-o
f-
0
9
o0
n;o
d
m
OI'U
m
a0
m
m-
Gl
Ao
l I
I
I
I 9
d
a
m m
N
O
0
rr) 0
*N
0
4
lG
0 I
I I
I I
0
N
I1
rn -
m
16
0 I
I
N
N
mN
c- .r
cp *
-
m
0.
IN'&
I
, I
I I
cp .
..
cp
1-
0
I
I
I
I I
9
cp Eo
9
0
mo
9 0 In
;dl
I I
I I
I
Il
l 1
01
Ol
22
0
0
uu
IO
I
I I
>
>
> b
0
4
In
E c 2
Y-
-4
a-a
a 446
-60-
u 0
m
m I
9
09
m
I-
0
+ rr)
d&-* I4
e
Ne
d
-IoIC
( I
m
9
+ N
...
dcd
d I
d
rA
1 N
'-l -
om
-4
m
N
tu
N'G
d Id
o\
e-
4.
I 1
s'
;
o\
tu d
I
0
dp
c
9
N
.. &
I
Il
nt
u
4
I
0
m
9m
N
..
.
Nu
l0
1
I m N
u 0 m N
.... ln
l'-N
Q\
cc +
cr)
m
m-4
*tu
rc -+
N .
..
-
o r ._ X
I
-61
-
u 0
m
Qo
W 0
ln
N
.. . ~
QL
.,
I
N
00 +
d
ml
n
C0
t-
d
QJ
at-0
I
O
cc I
..
.
4
9
mIn
-4
..
.
OF
0 I
1
m
u 0
m
N
u 0 -7 N
d
In
0
In Q
IN m
eln
o0
9
I
..
..
C
I
-62 -
-63-
u 0
In
In I
c) 0
In
N
d
04
4
mm
9
m
N
+ ...
QIN
O
I-;
eo
*
QC
O-;
v)
dN
-d Id
m
N
rr
)C
Qo
m
mo
N
... .
CO
N 0
I
O
N
I
0
00
-
PC
-0
0040
I I
N ...
u 0
In
N
u 0
m
N
4
9
QI*
md
Nm
N
NO
4
m
I
....
0
QN
In
44
0
ON
O-
;
m
I
..
..
00 N
4
mc
'-.co
00-00
N
I
....
00 0
Sm
dm
ee
4-P
m
+
..
..
0
m
-9-9
.... Q
lm-;m
N
+
-64-
,1
11
,
30
9
mm
-
0
+
-A cc
'dd
d,
I
I
-0
m
In
n2
9
m'o
;oj
I In
hl
Q
QDO
&id
D
N
z
-3-
0
-4
GQ
6
ou
-7 a-
-r
ue
-
..
rcI
Yo
mu
-ma
046
6 IC
7
uu
ip
uo
U
*.I--
-33
I I
I IC
..
.
- .
..
Y
co
I
3
..
.
-33 I
I t
m
- J a
>
>
> 3
J~i~rrJAG
PAGE IS
OF POOR QU
m
,-
-0
3 -
addition all 18 Group VI1 units successfully passed the "for
information only" fine leak tests requested by Dr . Holladay
of NASA (see Table XXXIV) .
By the end of July 1975 +he Group VI and Group VLII 2000 hour
l i fe tests at 85°C and 125"$, respectively, had completed
testing with the final readcuts made during August.
The Group V I life tests were completed without fa i lure ( see
Table XXXV).
125°C seve ra l capacitance change (increase) failures were
encountered in the lower voltage grcups (10 and 2 5 volt units).
The 50 and 100 volt units passed satisfactorily (see Table
XXXVI).
problems encountered in the ripple test portion of the
Engineering Evaluation Phase, the problem appeared to be
due to insufficient initial cathode capacitance. A sufficient
number of 250pF - 10V ra ted capacitors with extended
cathode capacitance adequate enough to eliminate the
capacitance drift failure mode Segan construction.
In the Group VI11 life tes ts conducted at
As in the case of the capacitance change
Meanwhile, the l ife tes t units \vhich completed the 2000 hour
life tes ts were returned to the Sprague Control Laboratory
.iere the 8 5 ° C and 125°C life tes ts n-ere car r ied on urdtil
a total of 10, 000 hours had been reached.
-66 -
> 0
4
> In
hl
9
-67-
mo
m
uuu
d
d
t I
10
1 I
I
I
'I
7
m 0
- 0
4
I1
10
11
11
I
11
01
11
>
>
ORIGIN& PAGE IS
- OF POOR QUALITyI -08 -
N
I,
#-
I I
I,
mu
lu
a
~~
e-
n
7-10-
a-
* .
..
..
N
> s
- . 0
ON
N
-N
fi'a
F
--
rb
-f
i
r- +
.
..
..
- 7 3
L
"- 1
, I
-,
I
I,
I
I,
.,
,
I I
I
.-'I-
By November 1975 the 250p.F - ! O V / 7 V , remake units with
the extended cathode capacitance were completed and had
begun 125°C life testing.
achieved during April 1976. A comparison of the tes t data
between this group and the original tes t group of this rating
is given in Table XXXVII.
the extended cathode capacitance had stabilized the capacitance
parameter during this tes t .
to continue to 10, 000 hours.
contract these xnits had achieved 6000 hours of tes t and
exhibited excellent parameter stability.
electrical parameter readout was taken at this point and
i s repcrted i n Table XXXVIII.
The 2000 hour tes t m a r k was
It is unequivocally clear that
These units were placed back on t e s t
By the completion date of this
A complete
A follow-up report t o this contract with the summarized
1 0 , 0 0 0 hour data wi l l be made around March 1977.
The 10, 000 hour, 85°C extended life tes t mark was achieved
during September 1970.
capacitance, dissipation factor, 2 5 ° C DC leakage and 85’C
DC leakage were obtained on each unit.
reported in summarized form i n Tables XXXIX - XLII along
with the calculated values for capacitance change ana the standarc!
de v i ation.
Complete parameter readouts of
These data a r e
- 7 1 -
N
I
I
I-
I
I
I.
I I
I)
*
EE
-- rc' 0 d
T
+ N
5
-Y
m
.ro
-4
o
r-'o
o I
,,
, .F Y
0
N,
..
.
..
iG
ni
NH,
CQCFQ'
Odd
q m
ma
+
+
c .U
NN
0000
00
0
00
00
0
'0
00
0
00
00
00
00
L
no
oo
3o
oc
0
00
0
00
0
00
N
00
03
00
C
nl- \d d
Y
QO
000 000
000
--
.I
d
d
-4
d
CI
E P
) U
C
a
c,
.r(
U
;d a
m u a
n
E L 0
U (d
Y
.4
E 3
ro 3. m rn E
.r(
Y
.r(
.r(
Y>
e
o
Q)
"
L
U
s
U
C
Q)
0
C
-73 -
h
m E-c
3
z
00
00
0
00
c
!o
oo
0
00
0
00
00
00
00
0
00
0
00
0
u? 0 0
0 0 0 0 3
000
00
0
003
00
0
N0
30
00
00
c4 1 Y
ll % u Q
h
E L
U
0
V
m La C
0
rd a m v)
.d
@
...1
.d
C
u C
u CC
-74-
d
13
53
53
5
53
5
35
35
2
3~
5S
35
~5
0
00
3
22
; 0
03
0
00
00
c
0v
oc
oD
"c
Eb
00
00
0
00
oooc 0003
,"
=.o
oo
oo
oo
m;I
ZZ
ZZ
Z
ZZ
Z
ZZ
Z
zz
zz
Z
ZZ
~Z
ZZ
Z~
kZ
/
000
00
0
000
.@
00
0
00
0
OOt
00
0
ulc
oc
oc
oc
c.! c 0 c 0
0
'-1 c
00
0
.I
b
a a 4
u a
CI
k? Y
L 0
r, u 6 E 0
a a m
'A
b.4 .d
Y
.@
b"
Y
c u L
-75 -
m
9
3
m
4
e
ul aY
IC
e
0
0
<- 0
0
0
3
; .i/
d
a ;I z.2
Il
l.
I
I.
I
ll
.
Il
l.
l
tl
ll
ll
l.
z CI
n L 5
0
rc
Y
3
0
c! 0, 30353003
- m
^o
c3
oo
o
0
~~
00
00
0
3
3
3
9 C
-
&
C
Q) L
a
E
Q) L.
L
C Y
u 13 Ir, C
c rz n. n n
.d
d
..4 ..* r\ -
-76-
A
VI
E-( c(
z 3 tu 0
d -
uc3
O
<
m
3030 030 3000
oc
a0
o
=.
o3
oc
oo
o
00
0 coo
530
300
LP
30
30
03
0
$0
030 303
3c=
300
N0
30
C3
00
0
P) u C ld Y
.d 'j
i5 a
m 0
a
c.
Y
L
i 0 'i
i5 E " .d
Y m a n a n
.. , .e
- W
W c,
n
All capacitors successfully completed this test. However,
one unit in the '00 volt grocp exhibited a hot DC leakage
value an order of magnitude higher than the maximum
8,000 hour value. This value was still within the MIL-C-
>9O(ib /22 specification allowed maximum vahe .
The 10,000 hour readout for all four ratings on the 125°C
extended l i fe test occurred during October 1976. The low,
average and high data for the electrical parameters of
capacitance, dissipation factor, 25°C DC leak3ge and 125'C
DC leakage for each grou2 has been reported in Tables
XLUI - XLVI. Additionally the standard deviation statistic
for each parameter 'has been included.
The three lower v o l t q e groups exhibited failures for
excessive capacitance increase at the end of 6,000 hours
of test an?. that every group had a failure for excessi--?
capacitance increase at the end of 10.000 hours of test.
The nctrrher of capacitors failing decreased nith increasing
2ated potential as indicated Lelow:
Number of Cnits with
Rating r o AC > 1c-7
10, uC)O Hours - 6, O O C Hours
25Q 10 v 181 18 180yr - 25v 17/2@ 9 J y F - S @ V 1 / i o 30+F - lOOV O i 4 0
18/ 18 ?0/20
2 / 4 0 1 ;40
-78 -
5.
0
LC
9
e s
z 3 N, 0
"d
0.
->
&G
I o
m0
3
01
0 oooc so00
03
3c
oe
=o
c
GC
I
CO
D
0,S
o
CO
C
303
N3
03
C3
OC
0
00
L
r3
C3
03
30
coo
00
0
030
.a 3-
L -
8 .d
Y
m
c a .* a .r(
2
cl 2
-80-
A
VI
e z 3
m
0
d.
VI - f9 I
0 9
N
Il
l.
N
d
-P I
t.
N
In
Il
l 0
11
11
1l
11
0
W
d
CI
.= 3
U
C
a Li m R
d
03
3
.C(
c) a
m a .d
3
u c u n I
CL
m
z 3
z 5 0
m
4
r- I
ll
.
0
4
4
11
.
N
m
Il
l.
0
30
Il
l.
0
4
11
11
11
11
In
c(
0
4 eLn
bN
CS
0
00
0
4-eo
NQ
'
X*
S3
00
N
ca
03
)N
-ln*
OC
Pr'r
-
30
0-
-
-L
n4
--
-+
--
N'--
oc3c 00-000300
..
..
.
..
.
..
..
..
..
.
tJ
0
00
03
300 3300
03
00
0003
300 000
coo
933
Lr
30
.r
(
.a
000 030
003
330
-.le
3
A
3
0
C
(d
Y
.r(
2 1. rj L'
v
>
YO
G
O
a-
L
c3
oc
3
3C
C
390c
-82 -
However, i t was pointed out ea r l i e r in this report that
this failure mode was eliminated v i a the extended cathode
surface area as evinced by the remake groups performance
through 6 , 000 hours as outlined in Table XXXVIII.
MSFC Meeting
A meeting was held on Wednesday, March 1 3 , 1974 at the
Marshall Space Flight Center between representatives of
the Sprague Electr ic Company and NASA. Persons who
attended included the follouing:
Sprague Electr ic Company NASA
John L. Moresi Dr. A . M. Halladay
John P. Moynihan M. Nowakowski
Franc is J. Garnari F r e d Laracuente
The purpose of this meeting was to discuss the progress of
this contract and consign seve ra l prototype capacitors to
NASA for testing.
design and monometallic cathode assemblies Lvere d i scusse i
and examined.
were measured by NASA during the meeting.
agreed closely with readings taken by thz S7rague Electr ic
Constructional aspects of the capacitor
2ctricA parameters of the prototype capacitors
The readings
Company.
could meet initial hii l i tary Specification l imits as well as
withstanding - 2 V reverse voltage.
These prel iminary tes ts indicated t52t the par ts
- 8 3 -
SECTION 4
WORK TO BE PERFORMED DURING THE NEXT REPORT PERIOD
Contract completed.
4 -
SECTION 5
EXPENDITGRES AND FORECAST
Total contract funds were utilized i n performing this
contract effort.
-85-