Analyzing the Potential for Small Hydroelectric Power ... · PDF fileAnalyzing the Potential...
Transcript of Analyzing the Potential for Small Hydroelectric Power ... · PDF fileAnalyzing the Potential...
Analyzing the Potential for Small Hydroelectric Power
Installment in the Dominican Republic
Blake D. Buehler
A project submitted to the faculty of
Brigham Young University
in partial fulfillment of the requirements for the degree of
Master of Science
E. James Nelson, Chair
Rollin H. Hotchkiss
Gustavious P. Williams
Department of Civil and Environmental Engineering
Brigham Young University
December 2011
Copyright © 2011 Blake D. Buehler
All Rights Reserved
ABSTRACT
Analyzing the Potential for Small Hydroelectric Power
Installment in the Dominican Republic
Blake D. Buehler
Department of Civil and Environmental Engineering, BYU
Master of Science
The Dominican Republic (DR) is in need of reliable, cost-effective power generation. A
prolonged electricity crisis and increasing power demand have left over seven percent of citizens
without access to electricity, and much of the population suffers from sporadic outages. The
purpose of this project is to build a methodology to evaluate small hydropower potential, which
can be used to alleviate the DR‟s energy problem among rural communities. The work is being
done for the DR‟s national water resource institute—the Instituto Nacional de Recursos
Hidràulicos (INDRHI)—which is overseeing the design and construction of multiple small
hydroelectric power projects (SHEPs) within the country.
This project has three major tasks: the design of a simple SHEP for a single location
along a river in the DR; the development of water flow prediction equations through a linear
regression analysis; and the design of an ArcGIS toolset to estimate the flow duration curves
(FDCs) at locations where data do not exist. An explanation of the inputs to the tool, as well has
how it produces a suitable output for SHEP evaluation will be presented. The paper also gives an
explanation of hydroelectric power generation in the DR, SHEPs, and the technical and practical
aspects of hydroelectric power.
INDRHI provided the temporal and spatial hydrologic data—drainage areas, precipitation
values, curve numbers (CNs), and slopes—for 13 different sites within the DR. An ordinary least
squares (OLS) analysis and manual numerical search for least square error (MNS) were both
calculated while implementing the regression procedure. The flow prediction equations are based
on the more accurate MNS method. Equations for flows ranging from 99 percent to 20 percent
were developed, with the emphasis being placed on the top 30 percent of flows. The specific
percentages used are 99, 95, 90, 85, 80, 75, 70, 60, 50, 40, 30, 20, 10, and 1. The regression
analysis was unable to yield equations for the 10 and 1 percentages because of high variability
introduced for less frequent flows. Because the lower percentages are not critical for locating
SHEP sites, the missing equations do not prohibit the analysis of flow availability for SHEPs.
The flow prediction tool performs three main functions: the delineation of a watershed
using a pour point placed upon a digital elevation model (DEM); the extraction of temporal and
spatial hydrologic data from raster and polygon feature layers; and the calculation of a watershed
FDC using the flow prediction equation and extracted data. Using the statistical flow prediction
equations and ArcGIS toolset, INDRHI engineers can now determine which sites will make the
best use of the available SHEP financing. Future efforts to improve the accuracy of the equations
can be achieved by expanding the collection and implementation of additional hydrologic data.
Keywords: Blake D. Buehler, small hydropower, ArcGIS, regression analysis
ACKNOWLEDGMENTS
I would like to express appreciation for Dr. E. James Nelson, Dr. Rollin H. Hotchkiss,
and Dr. Gustavious P. Williams for their assistance in editing this paper, as well as their
suggestions and ideas on how to approach this project. I would also like to thank Steve Hall and
Tyson Beaman for their research on turbines and their contributions to the SHEP design.
Additionally, I would like to thank INDRHI, and Fidel Perez in particular, for presenting this
project to work on and providing me with the data to accomplish it. Most importantly, I would
like to express my gratitude to my wife for her patience and support during the many months it
took to complete this project.
v
TABLE OF CONTENTS
LIST OF TABLES ........................................................................................................................ vii
LIST OF FIGURES ....................................................................................................................... ix
1 INTRODUCTION ................................................................................................................... 1
2 HYDROELECTRIC POWER GENERATION IN THE DOMINICAN REPUBLIC ........... 3
2.1 Current Power Generation in the DR ............................................................................... 3
2.2 Access for the Poor .......................................................................................................... 3
3 SHEPs ...................................................................................................................................... 5
3.1 History .............................................................................................................................. 5
3.2 Unique Aspects ................................................................................................................ 6
3.3 The Types ......................................................................................................................... 7
3.4 Turbines .......................................................................................................................... 10
3.5 SHEP Design .................................................................................................................. 14
4 TECHNICAL ASPECTS OF HYDROELECTRIC POWER GENERATION .................... 17
4.1 The Theory ..................................................................................................................... 17
4.2 Performance ................................................................................................................... 22
5 PRACTICAL ASPECTS OF HYDROELECTRIC POWER GENERATION ..................... 25
5.1 Advantages ..................................................................................................................... 25
5.2 Disadvantages................................................................................................................. 26
5.3 Financing ........................................................................................................................ 27
6 CASE STUDIES.................................................................................................................... 29
6.1 China .............................................................................................................................. 29
6.2 India ................................................................................................................................ 30
6.3 Turkey ............................................................................................................................ 30
vi
7 ANALYSIS ........................................................................................................................... 33
7.1 Regression Analysis ....................................................................................................... 33
7.2 Flow Duration Curves .................................................................................................... 44
7.3 ArcGIS Toolset .............................................................................................................. 49
7.3.1 Preparation .............................................................................................................. 50
7.3.2 Rivers ...................................................................................................................... 54
7.3.3 Pour Point Placement .............................................................................................. 55
7.3.4 Delineate ................................................................................................................. 56
7.3.5 Area_Convert .......................................................................................................... 57
7.3.6 Extract_Precip ......................................................................................................... 58
7.3.7 Slope ....................................................................................................................... 60
7.3.8 Extract Values to Table ........................................................................................... 61
7.3.9 Extract_CN ............................................................................................................. 63
7.3.10 ParametersToWatershed ......................................................................................... 63
7.3.11 FDC_Generation ..................................................................................................... 68
7.4 Comments....................................................................................................................... 72
8 CONCLUSION ..................................................................................................................... 75
REFERENCES ............................................................................................................................. 77
vii
LIST OF TABLES
Table 3-1: Five SHEP Setups (10). ................................................................................................ 9
Table 7-1: Data Provided by INDRHI ......................................................................................... 34
Table 7-2: Correlation Analysis ................................................................................................... 36
Table 7-3: Average Percent Error for Various Flows .................................................................. 37
Table 7-4: Standard Deviation for Various Flows ....................................................................... 37
Table 7-5: Minimum Square Error for Various Flows ................................................................ 38
Table 7-6: R2 Value for Various Flows ....................................................................................... 38
Table 7-7: Calculated vs. Original Canastica (Rincon) Hydrologic Parameters ......................... 68
Table 7-8: Basin Characteristics Used by States to Predict Stream Low Flows (23) .................. 73
viii
ix
LIST OF FIGURES
Figure 3-1: A Typical SHEP (9) .................................................................................................... 7
Figure 3-2: Hydroelectric Power Station Types (10) ..................................................................... 8
Figure 3-3: Subdivision of SHEPs with a Powerhouse Located in the Riverbed (10) .................. 9
Figure 3-4: An Existing Diverted Pipe System Currently in Place Within the DR ..................... 10
Figure 3-5: A Pelton Turbine (14) ............................................................................................... 12
Figure 3-6: How Water Hits a Pelton Turbine (15) ..................................................................... 12
Figure 3-7: Michell-Banki Turbine (17) ...................................................................................... 13
Figure 3-8: SHEP Design—Bottom View (Google SketchUp) ................................................... 15
Figure 3-9: SHEP Design—Top View (Google SketchUp) ........................................................ 16
Figure 3-10: SHEP Design—Front View (Google SketchUp) .................................................... 16
Figure 4-1: Physical Layout of Typical Hydropower Station (10) .............................................. 19
Figure 4-2: Schematic of a Typical SHEP (11) ........................................................................... 21
Figure 4-3: System and Operating Performance (10) .................................................................. 23
Figure 4-4: Discharge, Head, and Power Duration Curves (10) .................................................. 24
Figure 7-1: Comparison of Mean Square Error for Different Regression Models ...................... 39
Figure 7-2: Relationship between Observed and Predicted Q99 Flow ......................................... 41
Figure 7-3: Relationship between Observed and Predicted Q95 Flow ......................................... 41
Figure 7-4: Relationship between Observed and Predicted Q90 Flow ......................................... 42
Figure 7-5: Relationship between Observed and Predicted Q85 Flow ......................................... 42
Figure 7-6: Relationship between Observed and Predicted Qmean Flow ...................................... 43
Figure 7-7: Relationship between Observed and Predicted Flow for All Recurrence Intervals .. 44
Figure 7-8: Predicted FDC for Boca de Lajas (Palomino) .......................................................... 45
Figure 7-9: Actual FDC for Boca de Lajas (Palomino) ............................................................... 46
Figure 7-10: Comparison FDCs for Boca De Lajas (Palomino) .................................................. 46
Figure 7-11: Predicted FDC for Carata (Joca El Corte) .............................................................. 47
Figure 7-12: Actual FDC for Carata (Joca El Corte) ................................................................... 48
Figure 7-13: Comparison FDCs for Carata .................................................................................. 49
Figure 7-14: Custom Flow Prediction ArcGIS Toolset ............................................................... 50
Figure 7-15: Mosaic DEM of the DR .......................................................................................... 51
Figure 7-16: Preparation Tool in Model Builder ........................................................................ 51
x
Figure 7-17: Flow Direction Output (Zoomed in to Show River Lines) ..................................... 52
Figure 7-18: Flow Accumulation Output ..................................................................................... 53
Figure 7-19: Rivers Tool in Model Builder ................................................................................. 54
Figure 7-20: Rivers Tool Output (Zoomed in to Show River Lines) ........................................... 54
Figure 7-21: Pour Point Placement .............................................................................................. 55
Figure 7-22: Delineate Tool in Model Builder ............................................................................ 56
Figure 7-23: Delineated Canastica (Rincon) Watershed ............................................................. 56
Figure 7-24: Two Delineated Watersheds ................................................................................... 57
Figure 7-25: Area_Convert Tool in Model Builder ..................................................................... 57
Figure 7-26: Canastica (Rincon) Watershed Polygon Attribute Table ........................................ 58
Figure 7-27: Extract_Precip Tool in Model Builder ................................................................... 58
Figure 7-28: Isohyetal Line Feature Class ................................................................................... 59
Figure 7-29: Canastica (Rincon) Extract_Prec_Table ................................................................. 59
Figure 7-30: Slope Tool in Model Builder ................................................................................... 60
Figure 7-31: Canastica (Rincon) Output Slope Raster ................................................................ 60
Figure 7-32: Environment Settings .............................................................................................. 61
Figure 7-33: Extract Values to Table Input for Slope .................................................................. 62
Figure 7-34: Canastica (Rincon) Extract_Slope_Table ............................................................... 62
Figure 7-35: Extract_CN Tool in Model Builder ........................................................................ 64
Figure 7-36: Canastica (Rincon) Combined Slope and Land Use Polygon Feature Class .......... 65
Figure 7-37: Canastica (Rincon) Average_CN Table .................................................................. 65
Figure 7-38: ParametersToWatershed Tool in Model Builder.................................................... 66
Figure 7-39: Canastica (Rincon) Watershed Complete Attribute Table ...................................... 67
Figure 7-40: FDC_Generation Tool in Model Builder ............................................................... 69
Figure 7-41: Blank FDC Table .................................................................................................... 70
Figure 7-42: Populated FDC Table .............................................................................................. 70
Figure 7-43: Visual Representation of Canastica (Rincon) FDC ................................................ 71
Figure 7-44: All Joins Must be Removed Before the Tool Can be Used Again ......................... 71
Figure 7-45: Statistical, Original, and ArcGIS FDCs .................................................................. 72
1
1 INTRODUCTION
Like many developing countries, the Dominican Republic (DR) is in need of reliable,
cost-effective, power generation. A prolonged electricity crisis has led to frequent power
outages, high operating costs for distribution companies, electricity theft through illegal
connections, and low collection rates. The DR has electricity transmission and distribution
losses of 40 percent, which are the highest among all Latin American countries. These
problems, as well as increasing power demand and over seven percent of citizens lacking access
to electricity within the DR, necessitate a solution (1). Consequently, small hydroelectric power
projects (SHEPs) can be an economical and effective means of alleviating the DR‟s energy
problem among rural areas.
The purpose of my master‟s project is to build a methodology to evaluate small
hydropower potential, which can be used to alleviate the DR‟s energy problem among rural
areas. The work is being done for the DR‟s national water resource institute—the Instituto
Nacional de Recursos Hidràulicos (INDRHI)—which is overseeing the design and construction
of multiple hydropower projects within the country.
This project has three major tasks: the design of a simple SHEP for a single location
along a river in the DR; the development of water flow prediction equations through a linear
regression analysis; and the design of an ArcGIS toolset to estimate the flow duration curves
(FDCs) at locations where data do not exist. An explanation of the inputs to the tool, as well has
how it produces a suitable output for SHEP evaluation will be presented. The paper also gives an
2
explanation of hydroelectric power generation in the DR, SHEPs, and the technical and practical
aspects of hydroelectric power.
This paper outlines the methods used to accomplish the three tasks outlined above. An
explanation of hydroelectric power generation in the DR, SHEPs, the technical and practical
aspects of hydroelectric power, the financing of hydroelectric power, and three case studies will
also be provided.
3
2 HYDROELECTRIC POWER GENERATION IN THE DOMINICAN REPUBLIC
Seven-and-one-half percent of the people in the Dominican Republic do not have access
to electricity. Compounding the problem is the reality that the DR lacks professionals with
electric energy systems expertise (2). Large investments in electric power, which can support
economic development and improve peoples‟ quality of life, are sorely needed (3).
2.1 Current Power Generation in the DR
As of July 2003, 16 percent of the DR‟s power generating capacity came from hydro-
electric power plants (4). SHEPs are becoming more popular in the country and many have been
installed in rural during the past few years. However, a comprehensive list of the SHEPs and
their power generation capacity has not been published at this time.
2.2 Access for the Poor
Poor urban households in developing countries spend 15-22 percent of their income on
energy. The poor usually pay higher prices for energy than the rich because the heat content of
the fuels used by the poor are lower and their appliances are inefficient (e.g., appliances fueled
by wood or charcoal are generally very inefficient compared to appliances fueled by electricity).
Some governments have attempted to target subsidies for certain fuels to make energy services
more accessible and affordable to the urban poor. These attempts have largely failed because the
subsidies have actually restricted access to the poor and have been diverted to other economic
groups. Ideally, energy would be neither heavily subsidized, heavily taxed, nor have import
4
restrictions. Such conditions would help all households because they would keep traditional
fuels, used by the poor, at affordable levels (5).
5
3 SHEPs
For over 70 years hydroelectric projects (HEPs) have been built for water storage and
hydroelectric power generation. More recently, SHEPs have become popular alternatives for
small, rural communities with limited financial resources. SHEPs are different than HEPs in
many ways and can be built in various setups.
3.1 History
During the 20th
century hundreds of massive barriers of concrete, rock, and earth were
placed across river valleys all over the world. These dams created huge artificial lakes and
provided many benefits: reliable power supplies, irrigation and flood control drinking water,
jobs, and recreational uses (6; 7). However, these dams did not come without a cost: thousands
of local inhabitants were displaced because of the flooding of nearby land as reservoirs filled.
Additionally, numerous environmental problems resulted from such major interference with river
flows: erosion, disruption of natural ecosystems, and possible impact on global climate change
(6).
Small and micro-hydro plants are more environmentally friendly power generation
options than larger projects and are now playing a key role in the rural electrification of many
countries. In fact, SHEPs are the main prospect for future hydroelectric developments in Europe
and other locations where large-scale dams have already been exploited or are now considered
environmentally unacceptable (6).
6
3.2 Unique Aspects
SHEPs are usually differentiated from larger HEPs by the amount of power they generate
(6). When referring to small hydropower in developing countries, and specifically in the DR, a
designation of 10 MW of hourly capacity will be used, as outlined by the Electrical Power
Resources Survey and Development Administration (EIE) (8). When referring to micro
hydropower, the European Union definition will be applied: plants having between 115kW and
1MW of hourly capacity (8).
SHEPs differ from HEPs in more than just size. SHEPs are generally used in smaller, less
developed communities where power generating equipment must be simple, reliable, and easily
maintained by non-specialists. They are best suited to generate power for dispersed rural
communities with limited needs and have five principal components: a suitable rainfall
catchment area, hydraulic head, a means of transporting water from intake to turbine, a turbine
house containing the power generation equipment and valve gear, and a tailrace to return water
to its natural course (3). Figure 3-1 depicts a typical SHEP.
Recent developments in small hydro technology have led to extremely robust systems
that can last for 50 plus years with minimal maintenance. SHEPs can also make a more
immediate impact on the replacement of fossil fuels when adequate water flow is available: they
can produce electricity on demand more efficiently than alternate energy sources that require
costly storage or backup systems. Some studies indicate that SHEPs are cost competitive with
fossil fuel power stations in remote rural areas that would be uneconomical to serve from larger
power networks (6).
7
Figure 3-1: A Typical SHEP (9)
Recent developments in small hydro technology have led to extremely robust systems
that can last for 50 plus years with minimal maintenance. SHEPs can also make a more
immediate impact on the replacement of fossil fuels when adequate water flow is available: they
can produce electricity on demand more efficiently than alternate energy sources that require
costly storage or backup systems. Some studies indicate that SHEPs are cost competitive with
fossil fuel power stations in remote rural areas that would be uneconomical to serve from larger
power networks (6).
3.3 The Types
Hydroelectric power stations can be divided into three main categories: low, medium, and
high head. Stations can further be classified as run-of-river or hydroelectric stations with
reservoirs. In actuality, most stations are mixed types, but for discussion purposes it is best to
distinguish them. Figure 3-2 shows the various breakdowns (10).
8
Figure 3-2: Hydroelectric Power Station Types (10)
SHEPs can be designed with the power house and dam placed in various locations within
the riverbed or near the riverbank. Three different setups are commonly used for powerhouses
placed in the riverbank: connected, detached, and submerged. These three setups can be further
subdivided, as show in Figure 3-3, resulting in five unique setups. Table 3-1 contains
descriptions of each of the five design types (10). Canals, pipes, or tunnels can also be used to
transport water to a powerhouse, which is the more likely scenario in the DR. Figure 3-4 shows
an existing diverted pipe system currently in place within the DR.
9
Figure 3-3: Subdivision of SHEPs with a Powerhouse Located in the Riverbed (10)
Table 3-1: Five SHEP Setups (10)
Setup Description
Conventional block design
The longitudinal axis of the power house and the dam are perpendicular
to the course of the river
Can only be used in areas with low flood potential)
Indented power station
Powerhouse set up outside the riverbed in an artificial bay
Required in very narrow streams so dam can use entire width of the river
Twin block power station Powerhouses placed on both sides of river
Built on rivers boarding two countries/regions
Power station in pier
Powerhouse is identical to the piers that support the gates of the barrage
Space-saving design for rivers with favorable flow conveyance
Submersible power station
Power station and dam are built in one block
Blends well with surrounding landscape
Minimum space required
10
Figure 3-4: An Existing Diverted Pipe System Currently in Place Within the DR
3.4 Turbines
Energy can be extracted from water in different ways, but the basic principles are always
the same: there must be a water source with a relative steady flow and a turbine that can harness
the energy that is produced by this flow. Depending on the characteristics of the water source,
different turbines can be used. This section gives a brief explanation of two turbine types—
Pelton and Michell-Banki—that could be successfully used in SHEPs within the DR, as well as
the reasons for my design using a diverted pipe system.
The Pelton turbine comes from the family of impulse1 turbines. This turbine is ideal for
rivers with medium to high change in head because it requires high velocity, rather than a high
1 power is derived from the force of water at high pressure hitting the passing buckets
11
volume of water (11). According to Popular Science Magazine (12), Pelton turbines can be run
on as little as 1.5 cfm of water, making it extremely useful for low flow SHEPs.
Pelton turbines can accept multiple jet streams, which improve their efficiency and power
generation potential. According to Z.H. Zhang (13), engineering professor at Dalian University
of Technology in China, Pelton turbines can easily achieve hydraulic efficiencies greater than 90
percent. The number of nozzles is determined by the size of the Pelton turbine and the number of
bowls. Nozzles are aligned so that each stream will only come in contact with one bucket at a
time.
Pelton turbines use two interlocking bowls, depicted in Figure 3-5, to harness a velocity
jet stream of water, as shown in Figure 3-6. When the water hits the bowls, the water is split and
each half is deflected at nearly 180 degrees: water is constantly forcing the turbine forward (11).
The Michell-Banki cross-flow turbine, as shown in Figure 3-7, was first developed in
1903 by Australian engineer Anthony Michell. However, it did not generate much interest and
was never widely distributed. Later, a Hungarian professor named Donat Banki independently
invented a similar turbine in Germany. Through a series of publications from 1917 to 1919
awareness of this turbine increased, which led to its more common use (14).
Unlike the Pelton model, the Michell-Banki turbine uses a broad rectangular water jet
that generates only a small amount of back pressure. The turbine uses two velocity stages.
During the first stage water goes through the runner blade, which then goes inward to the center
where it meets the cross blade. Once at the center, the same process is continued to release the
water outward without producing any back pressure. The introduction of air into the draft tube2
has enhanced the turbine‟s performance because it helps regulate the water head (14)
2 the flared passage leading vertically from a water turbine to its tailrace.
12
Figure 3-5: A Pelton Turbine (15)
Figure 3-6: How Water Hits a Pelton Turbine (16)
13
Figure 3-7: Michell-Banki Turbine (17)
The Michell-Banki turbine is best implemented in rivers with low head and high water
volumes because it uses blades, which limit disruption to the flow of water, instead of bowls
(11). In fact, electric power can be generated in rivers with as little as three feet of head
difference (12). The hydraulic efficiencies of Michell-Banki turbines can be as high as 88
percent (18).
During my trip to the DR in March 2011, I visited four SHEPs currently in operation.
Each uses a diverted pipe system in place of a penstock and has a powerhouse placed near, but
not in, a stream. INDRHI wants to build SHEPs using diverted pipe systems because they are
less expensive than other alternatives and still achieve INDRHI‟s main goal: meeting the
electricity demands of small, rural locations throughout the country (19). As such, powerhouses
can be built alongside riverbanks, rather than within riverbeds. I recommend the use of the
14
Pelton turbine for SHEP designs in the DR because it can best make use of the large, drastic head
changes in fast moving rivers found throughout the country‟s rugged highlands and mountains.
3.5 SHEP Design
Using Google SketchUp, I designed a basic SHEP. I decided to use a small diversion
weir in the design of the SHEP because weirs are excellent at building up river elevation head
and providing a consistent flow to generate power. An inlet box, which will take in water and
filter obstructions such as sticks, rocks, and other debris that may damage the turbines, is located
in front the weir. A steady stream of water will travel through a 4-12 inch pipe and split into two
nozzles, from which the water will strike the Pelton turbine, thereby turning the motor and
creating power.
According to INDRHI, there should not be any boat travel along the rivers where SHEPs
will be placed, so a weir should not be a human hazard (20). Figure 3-8, Figure 3-9, and Figure
3-10 show various angles of the SHEP design that was created using Google SketchUp. The
figures are for visualization purposes only and were not built to scale.
15
Figure 3-8: SHEP Design—Bottom View (Google SketchUp)
16
Figure 3-9: SHEP Design—Top View (Google SketchUp)
Figure 3-10: SHEP Design—Front View (Google SketchUp)
17
4 TECHNICAL ASPECTS OF HYDROELECTRIC POWER GENERATION
In order to increase understanding, a brief explanation of hydroelectric power is provided.
The operating performance of SHEPs is explored as an introduction to the importance of being
able to predict river flow rates and calculate power generation over time.
4.1 The Theory
The potential energy found within falling water can be converted to electricity using
hydroelectric power plants. As defined by the authors of Renewable Energy: Technology,
Economics, and Environment (10), theoretical water power PWa,th between two points on a river
can be calculated using Equation 4-1:
( ) (4-1)
where, = water density
g = gravitational constant
= volumetric flow rate (through the hydroelectric power station)
= headwater elevation head
= tailwater elevation head
Transfer losses, often referred to as head loss, within a hydroelectric station cause a
portion of power calculated in Equation 4-1 to be lost. The Bernoulli equation, Equation 4-2, can
be written to represent these actual conditions (10).
18
(4-2)
where, z = potential energy (i.e., elevation head)
= pressure energy
= kinetic energy
= head loss
ξ = the loss coefficient
Hydro turbines convert water pressure into mechanical shaft power which, in turn, can be
used to drive an electricity generator or other machinery. The power available is proportional to
the product of pressure head and water discharge (6)
A hydroelectric power station is made up of many parts: a dam or weir, intake works, a
penstock3, a headrace
4, a powerhouse, and a tailrace
5. Figure 4-1 shows the physical layout of a
typical hydro station. The numbers in the figure indicate the path that water travels through the
hydropower plant in order to generate power. The energy line, energy loss, velocity head,
pressure head and the geodetic elevation6 of the streamline are also displayed (10).
3 a sluice or gate that controls water flow or an enclosed pipe that delivers water to the turbine
4 a channel that delivers flowing water to the turbine), a powerhouse, and a tailrace
5 a channel that delivers flowing water from the turbine
6 elevation head
19
Figure 4-1: Physical Layout of Typical Hydropower Station (10)
The intake structure (i.e., the “screen” from Figure 4-1), which keeps floating debris out
of a plant, connects the headwater to the penstock or turbine. Stoplogs, contained within the
structure, enable the hydroelectric power station to be drained during maintenance work.
Similarly, quick-action stop valves, located nearby, stop the water flow into the station if an
accident were to occur. Local energy losses ( ) in the intake structure and flow resistance at the
screen prevent some energy from being generated by the turbine. Losses can be calculated using
Equation 4-3 (10).
( )
(4-3)
The penstock, the structure extending from point 2 to point 3 in Figure 4-1, bridges the
distance between the intake structure and the turbine. Potential energy is converted into pressure
20
energy in the penstock, with some friction losses in the pipes. Equation 4-4 shows the Bernoulli
Equation for the penstock (10).
( )
(4-4)
The loss coefficient of the penstock (ξPS) is a product of a friction factor and the diameter
of the penstock. One way to increase turbine power within a station is to increase the diameter of
the penstock, which reduces the friction encountered by flowing water. Station operators must
weigh the benefit of this added power generation to the increase in plant costs, due to the more
expensive penstock (10).
Run-of-river power stations7 transfer water flows from the intake structure into the
turbine via an upstream canal, pipe, or tunnel as show in Figure 4-2 (10). These SHEPs produce
power in the same way as HEPs only they require little, if any, damming and turbines are located
off the river banks or within the riverbed.
The turbine converts pressure energy into mechanical energy. Equation 4-5 describes
how much of the water power can be transformed into mechanical energy at the turbine shaft
(10).
7 power stations that use the natural flow of rivers and turbine generators to capture the kinetic energy carried by
water
21
Figure 4-2: Schematic of a Typical SHEP (10)
(4-5)
where, = power generated by the turbine
= turbine efficiency
= density of water
= gravitational constant
= volumetric flowrate
= usable head at the turbine
Some turbines, especially reaction types, generate more power when using a draft tube.
The cross-section of the flow at the end of the draft tube is larger diameter where the water exits
the generator. The gradual change in diameter causes a reduction of flow velocity before it enters
the tailwater. The fact that the tailwater energy line is much lower than the initial energy line is
22
evidence that the generator has successfully extracted the energy from the falling water.
Additional kinetic energy is lost due to turbulence in the tailwater. The Bernoulli equation
between the turbine outflow and draft tube outlet is written in Equation 4-6 (10).
(4-6)
The main hydraulic losses in a hydroelectric power station occur in the intake structure,
the penstock, and the outflow. The actual water power generated is calculated by subtracting
these losses from the theoretical water power, as shown in Equation 4-7 (10).
( )
(4-7)
An optimized plant design and layout can minimize losses that are dependent on the flow
velocity, and consequently improve turbine efficiency. Optimization is important because the
power from the shaft is determined my multiplying the actual available water power by the
turbine efficiency (10).
4.2 Performance
The operating performance for a SHEP, with respect to electrical energy output, depends
heavily on the available flow and current head. Figure 4-3 shows an example of the interaction
of these elements, as well as turbine flow, over the course of a single year (10).
23
Figure 4-3: System and Operating Performance (10)
Turbine flow is directly linked to the discharge of the river. Consequently, turbines can
only generate power for the maximum/design flow, and additional discharge goes unutilized. The
power generated by the hydroelectric power station is nearly identical to the flow through the
turbine, as found in Equation 4-5. Available head also affects power output, but it is usually less
significant than flow because it is more consistent (10).
Knowing the design flow and head allows operators to calculate the power generated
over time. The power forecast can be adjusted according to increasing and decreasing flows at
any given time of year. Decreasing flows result in decreased power generation and, at low
enough flows, a hydroelectric plant must be turned off to prevent the turbines from being
damaged. Such flows should be rare if the plant is designed properly and positioned correctly.
Conversely, increasing flows above the design capacity results in decreased power generation
24
because the turbine cannot process the discharge (i.e., increased flows cause the difference
between the head and the tail water heights to become insignificant) (10).
The ability to predict flow rates is necessary to properly operate a hydroelectric plant.
Water flow varies during different daily hours and seasons of the year and therefore must be
studied and evaluated before installing SHEPs. Calculating the optimal installation capacity8 at
any site involves determining, at minimum, the downstream river flow, environmental needs and
rights, and a FDC (10). Figure 4-4 shows how the discharge, head, and power duration curves
for a hydroelectric plant relate to plant design (10). One of the main purposes of my project is to
generate FDCs that can be used to predict flows, which should prevent plants from unnecessarily
being turned off.
Figure 4-4: Discharge, Head, and Power Duration Curves (10)
8 optimal designed flow
25
5 PRACTICAL ASPECTS OF HYDROELECTRIC POWER GENERATION
Implementing hydroelectric power projects is not limited to having a firm grasp of their
technical aspects. Practical aspects—economic, social, and environmental—must also be
considered. This section is dedicated to a discussion of the advantages and disadvantages of
HEPs and SHEPs, as well as the financing of such products.
5.1 Advantages
SHEPs have three distinct advantages over HEPs. First, SHEPs have lower operating
costs and longer life cycles than other large-scale generating options. Second, the water that
drives the generation is not affected by market fluctuations because it can still be used for
consumption downstream (3).Third, small hydro projects are becoming increasingly popular in
exploiting energy potential because they are a much less risky investment, via reduced economic
costs, than large dams (6).
Hydropower in developing countries, collectively, had more than double the hydropower
potential of industrialized countries as of 1999. Only about 20 percent of that potential had been
tapped in developing countries, whereas nearly 70 percent of the potential had been tapped in
developed countries (5). The DR is estimated to have nine TWh per year of economically
feasible untapped hydropower potential (13). If accessed, the hydropower could increase the
2007 production level by 64 percent (15).
26
Recently, SHEPs have been used to generate power in many rural areas that might not
have otherwise had power accessible to them. Previously, only HEPs, associated with high
investment costs, had been available options (8). The construction of large dams and reservoirs is
unnecessary when implementing SHEPs because small scale hydropower is produced mainly by
run-of-river systems: SHEPs require little or no reservoir storage and can be designed for various
river types because they use river stages within their natural ranges. Consequently, the
environmental impact of SHEPs is usually negligible compared to that of HEPs attached to large
dams. Depending on the desired environmental impact, all or some of the river flow can be used
for power generation. In addition, SHEPs create job opportunities in rural areas, provide
significant forward and backward linkages9, and increase demand for power-generating turbines
and other equipment that will benefit the industrial sectors of economies that produce them (6).
5.2 Disadvantages
SHEPs do have some disadvantages that offset their hydropower potential. Although
SHEPs require little water, in comparison to HEPs, the management of competing water uses and
the creation of barriers for fish migration must still be considered. Droughts could eliminate
most, if not all, power generation potential from SHEPs because minimum flows would likely
not occur without water storage10
. Additionally, when SHEPs are built directly into the riverbed
three considerations must be taken into account: flood management, shiplock operation, and
groundwater stabilization. In particular, if ships must navigate the river, power generation
revenues may not negate the cost of shiplock operation (10).
9 the benefits of economic investment tends to stay within a local economy and enhance other domestic industries
10 this disadvantage is not as critical in the DR where average rainfall varies between 50 and 60 inches (21)
27
5.3 Financing
SHEPs are desired in the DR because they are more economical for the needs of the rural
populations than HEPs, do not require storage, and have less of an environmental impact.
Generally, the main economic advantage comes in the form of smaller capital and maintenance
costs (10).
During my March 2011 visit to the DR I discovered that the European Union, as well as
the DR Government and various Latin American agencies, will be providing the financing for
the SHEPs being designed by INDRHI. This is a huge advantage for the DR because of the
challenges associated with finding investors and capital.
28
29
6 CASE STUDIES
Developing countries have been investing in SHEPs for over 110 years. However, in
recent years the level of investment has increased dramatically. Dr. IbrahimYüksel (8), professor
of construction at Sakarya University in Turkey, recently performed case studies of SHEP
development in three such countries: China, India, and Turkey. Summaries of his research
follow.
6.1 China
China has abundant SHEP resources, scattered throughout the country, with development
potential around 100 GW. From 1993-2005 the country invested $1.6 billion in small
hydropower to increase rural capacity by 1000MW yearly. By the end of 2002 the country had
42,221 SHEPs with installed capacity of 28,489 MW (approximately one quarter of the country‟s
total development potential). In the same year, the ratio of SHEPs to HEPs was projected to be
33.7%. Additional installed capacity via SHEPs is projected to increase at 2,000 MW annually
(8).
By 2010, small hydropower in China was projected to provide electricity to 1,400 rural
provinces—an increase of 800 provinces from 2001. Additionally, the country was expected to
have had a nonconventional renewable energy increase of 14.3 GW from 2001 to 2010 (8). I
have been unable to locate a published paper indicating whether or not hydropower growth in
China has met these predictions.
30
6.2 India
India began using micro hydropower in 1897. Since then, many SHEPs have been set up
in the country‟s hilly regions and at canal drops. However, huge electricity demands have led the
country to shift its focus to HEPs. The need for SHEPs still exists in some rural areas, so India
has maintained mature and reliable technology to implement them when necessary. Efforts
during the past decades have focused on four improvements: efficiency of the equipment; design
and use of silt resistive material/coatings; reliable auto controls; and remote operation of units
(8).
In 2002 India had an estimated 15,000 MW of SHEP potential at 4,096 sites. By 2006 the
country had 420 plants with capacity up to 25 MW, and combined capacity of 1,423 MW. 187
projects, combining for 521 MW of installed capacity, were under construction at the time of this
article (8).
6.3 Turkey
Turkey began developing small hydropower in 1902. Since then, SHEPs have been
installed in many parts of the country. As with India, large, domestic energy demand has led the
government to focus on the development of HEPs. However, from the early 1970s to 2002,
SHEP capacity in Turkey still increased from 5-10 percent each year (8).
As of 2004, Turkey had an estimated installed capacity of 175 MW—or one-and-one-half
percent of total hydropower potential in country—within its SHEP network. The 70 in-operation
SHEPs were generating roughly 650 GW of energy, annually. Six more SHEPs were under
construction when the article was published (8).
31
In 2004, SHEPs constituted four percent of total exploited hydropower generation
potential, with HEPS exploiting the remaining 96 percent. In addition, 35 percent of Turkey‟s
total electricity production that year was generated from hydropower, with the remaining 65
percent coming from thermal plants (8).
32
33
7 ANALYSIS
Following a statistical procedure used by GLM Engineering (22), I performed a
regression analysis on 13 sites within the DR where drainage areas, precipitation values, curve
numbers, slopes, and FDCs were available. An ordinary least squares (OLS) and manual
numerical search for least square error (MNS) were both calculated while implementing the
procedure; the flow prediction equations are based on the more accurate MNS method. Using
these equations, as well as watershed hydrologic parameters from known datasets extracted with
tools from ArcMap®, predicted FDCs can be generated in Microsoft Excel for any site within
the DR.
7.1 Regression Analysis
INDRHI provided me with the hydrologic information in Table 7-1 and Table 7-2.
Temporal and spatial data—drainage areas, precipitation values, curve numbers, and slopes, and
FDCs—were collected from 13 different sites within the DR. Each of the four variables used in
the flow prediction equations can come from a GIS dataset and can be measured directly, except
for the CN. However, because the CNs is an indication of storage I determined to use it. The
duration and time frame of data collection varied at the 13 reference sites, although the raw data
was not available for the study. Hence, the regression analysis and subsequent water flow
equations are only as accurate as the given data.
34
Table 7-1: Data Provided by INDRHI
Station Name Drainage Area
(km2)
Rainfall
(mm/yr) CN Slope
Aguacate (Cerro El Medio) 77.48 1470.57 70.79 0.3897
Boca de Lajas (Palomino) 64.88 1293.96 76.39 3.3869
Boca de Lajas (Bohechio) 598.21 841.01 61.07 0.0273
Cabirma (Bulla) 653.49 1872.34 71.98 0.3114
Canastica (Inage) 111.91 1759.21 82.29 0.1981
Canastica (Rincon) 416.83 1508.76 82.03 0.3689
Carata (Arbonito El Corte) 466.50 1798.47 82.25 0.2508
Carata (Joca El Corte) 451.43 1798.47 82.25 0.2592
Majagual (El Millo) 34.13 1784.24 73.32 0.4484
Ingenito (Jaquime) 73.62 1327.04 82.29 0.4583
Vallesito (Palomino) 64.88 1293.96 76.39 3.3869
Vallesito (Bohechio) 598.21 841.01 61.07 0.0273
Montazo (Palomino) 64.88 1293.96 76.39 3.3869
Montazo (Bohechio) 598.21 841.01 61.07 0.0273
Higuera (Los Valencio) 196.20 1706.48 76.30 0.3605
Higuera (Jaquime) 218.82 1327.04 76.42 0.3663
Rancho el Pino (Arroyo el Limon) 405.83 1106.84 78.9 0.3789
Q99
(cms)
Q95
(cms)
Q90
(cms)
Q85
(cms)
Q80
(cms)
Q75
(cms)
Q70
(cms)
Q60
(cms)
Q50
(cms)
Q40
(cms)
Q30
(cms)
Q20
(cms)
0.26 0.28 0.32 0.35 0.38 0.41 0.45 0.51 0.58 0.64 0.71 0.93
0.89 2.29 2.84 3.22 3.60 3.94 4.27 5.15 6.15 7.26 8.82 11.46
1.34 2.11 2.60 2.97 3.29 3.65 3.98 4.71 5.62 6.91 8.62 11.25
4.39 5.64 6.58 7.49 8.40 9.34 10.38 12.91 15.79 19.21 23.30 30.28
0.30 0.51 0.75 0.83 0.90 0.97 1.05 1.19 1.53 2.41 3.01 3.50
1.97 2.76 3.22 3.64 4.00 4.36 4.77 5.68 6.66 8.50 10.07 13.55
1.70 2.20 2.83 3.34 3.91 4.50 5.09 6.80 8.33 10.12 12.41 15.52
0.94 1.64 1.89 2.14 2.40 2.69 3.01 3.75 4.86 6.04 7.31 9.15
0.52 0.59 0.68 0.77 0.86 0.94 1.03 1.21 1.39 3.63 2.14 2.69
0.27 0.36 0.47 0.57 0.68 0.78 0.86 1.01 1.17 1.39 1.70 2.21
0.89 2.29 2.84 3.22 3.60 3.94 4.27 5.15 6.15 7.26 8.82 11.46
1.34 2.11 2.60 2.97 3.29 3.65 3.98 4.71 5.62 6.91 8.62 11.25
0.89 2.29 2.84 3.22 3.60 3.94 4.27 5.15 6.15 7.26 8.82 11.46
1.34 2.11 2.60 2.97 3.29 3.65 3.98 4.71 5.62 6.91 8.62 11.25
1.60 1.99 2.48 2.68 2.88 3.07 3.27 3.72 4.28 4.94 5.72 6.82
4.20 6.65 9.68 11.38 12.21 12.23 12.65 13.48 14.71 16.38 18.43 21.69
0.83 1.52 1.83 1.99 2.15 2.30 2.45 2.73 3.00 3.26 3.61 4.21
35
Following the recommendation of INDRHI, flows at specific percentages were
interpolated from FDCs created for the 13 sites. I attempted to develop equations for flows
ranging from 99 percent to 1 percent, with the emphasis being placed on the top 30 percent of
flows. The specific percentages used are 99, 95, 90, 85, 80, 75, 70, 60, 50, 40, 30, 20, 10, and 1.
The regression analysis was unable to yield equations for the 10 and 1 percentages because of
high variability introduced at such low values. Because the lower percentages are not critical for
locating SHEP sites, the missing equations do not prohibit the analysis of flow availability for
SHEPs.
Following methods used by GLM Engineering in a minimum instream flow estimation
study at ungaged sites in Puerto Rico, I analyzed two regression models. First, the ordinary least
squares (OLS) model was used to estimate the regression coefficient vector of the linear model
for regression analyses. Second, the manual numerical search for least square error (MNS) was
used (22).
OLS minimizes the sum of squared residuals to estimate the following parameters:
drainage areas, precipitation values, curve numbers, and slopes. The OLS regression coefficient
vector ( ) was determined using matrix analysis and Equation 7-1 (22).
( ) (7-1)
Where, = Matrix of the watershed parameters
= Observed discharge vector
= Transform of Matrix X
36
The MNS method involves a numerical search of the least square error (MNS) using an
iterative Excel spreadsheet solver. I used the results from the OLS model as initial values and
with the „Solver‟ tool in Excel varied the parameters until the regression coefficients created the
minimum square error, relative to the original data.
I performed an analysis of variance (ANOVA) with a 0.05 significance level to determine
if any of the independent variables11
were significantly related to the dependent variable12
. The
results, found in Table 7-2, show that none of the variables were meaningful and that differences
are probably a product of chance.
A correlation analysis was also performed on the independent variables and the results
are shown in Table 7-3. Precipitation values and curve numbers had a 0.67 correlation, which
was not high enough to eliminate either. None of the other variables showed any significant
correlations, which were defined to be values greater or equal to 0.90.
Table 7-2: Correlation Analysis
Area Precipitation CN Slope
Area 1.00
Precipitation -0.26 1.00
CN -0.46 0.67 1.00
Slope -0.55 -0.08 0.18 1.00
Since none of the independent variables could be eliminated based on ANOVA or
correlation analyses, I used four standards to determine which variable combination13
should be
used to create flow prediction equations: the average percent error14
, standard deviation15
,
11
drainage areas, precipitation values, curve numbers, and slopes 12
flow 13
two or more independent variables used to collectively predict flow (the dependent variable) 14
the difference between predicted flow and actual observed flow at specific locations in the DR 15
based on a sample (ignores logical values and text in sample)
37
minimum square error16
and coefficient of determination17
(R2). These four standards are applied
at five of the most important percentage flow rates: 99, 95, 90, 85, and 50. Table 7-3, Table 7-4,
Table 7-5, and Table 7-6 show a breakdown of the four standards applied to each variable
combination.
Table 7-3: Average Percent Error for Various Flows
Variable Combination Flows
99 95 90 85 50
Area & Precipitation 42 68 76 77 62
Area & CN 49 71 78 79 68
Area & Slope 33 51 60 61 49
Precipitation & CN 50 -73 -73 -73 119
Precipitation & Slope 88 -9 -25 59 -34
CN & Slope 88 -5 66 -82 66
Area, Precipitation, and CN 40 66 76 77 63
Area, Precipitation, and Slope 31 75 -29 60 -4
Area, CN, Slope 21 35 46 48 36
Precipitation, CN, and Slope 50 6 -52 -57 155
Area, Precipitation, CN and Slope 33 43 51 53 46
Table 7-4: Standard Deviation for Various Flows
Variable Combination Flows
99 95 90 85 50
Area & Precipitation 0.93 1.39 1.55 1.57 1.42
Area & CN 0.94 1.43 1.57 1.58 1.47
Area & Slope 0.69 1.04 1.20 1.22 1.49
Precipitation & CN 1.63 0.61 0.49 0.48 2.72
Precipitation & Slope 1.76 1.36 0.70 1.76 1.24
CN & Slope 1.62 1.32 1.88 0.39 2.14
Area, Precipitation, and CN 0.96 1.45 1.62 1.65 1.62
Area, Precipitation, and Slope 1.74 1.28 0.58 1.19 0.57
Area, CN, Slope 0.55 0.84 1.05 1.09 1.04
Precipitation, CN, and Slope 1.69 1.50 0.63 0.52 3.60
Area, Precipitation, CN and Slope 0.65 0.98 1.17 1.21 1.29
16
a minimized version of the least square error 17
the square of the sample correlation coefficient between the outcomes and their predicted values
38
Table 7-5: Minimum Square Error for Various Flows
Variable Combination Flows
99 95 90 85 50
Area & Precipitation 15.01 36.66 72.84 100.45 200.01
Area & CN 17.40 38.32 74.51 102.62 223.75
Area & Slope 14.21 30.76 64.12 89.27 167.02
Precipitation & CN 21.77 112.37 191.39 254.17 409.40
Precipitation & Slope 21.98 77.52 135.88 124.43 607.52
CN & Slope 22.90 86.19 88.04 253.89 580.13
Area, Precipitation, and CN 13.24 35.50 72.01 99.45 186.47
Area, Precipitation, and Slope 45.62 37.00 105.57 89.08 528.01
Area, CN, Slope 12.11 25.61 57.84 81.37 130.08
Precipitation, CN, and Slope 31.29 70.57 142.72 201.64 340.33
Area, Precipitation, CN and Slope 10.87 25.08 57.28 80.61 121.38
Table 7-6: R2 Value for Various Flows
Variable Combination Flows
99 95 90 85 50
Area & Precipitation 0.351 0.192 0.133 0.127 0.299
Area & CN 0.248 0.155 0.113 0.109 0.213
Area & Slope 0.386 0.322 0.238 0.226 0.413
Precipitation & CN 0.119 0.003 0.004 0.005 0.001
Precipitation & Slope 0.049 0.013 0.000 0.001 0.000
CN & Slope 0.012 0.011 0.007 0.000 0.002
Area, Precipitation, and CN 0.429 0.219 0.144 0.137 0.349
Area, Precipitation, and Slope 0.098 0.210 0.137 0.228 0.063
Area, CN, Slope 0.477 0.435 0.312 0.294 0.542
Precipitation, CN, and Slope 0.028 0.020 0.213 0.033 0.016
Area, Precipitation, CN and Slope 0.530 0.447 0.319 0.300 0.574
The variable combination of area, CN, and slope had the lowest overall percent error—
21, 35, 46, 48, 36—for the five flow rates. The area, precipitation, CN, and slope combination—
33, 43, 51, 53, 46—followed closely behind with percentages ranging from five to 12 percent
higher. The same pattern held true for standard deviations: area, CN, and slope were the
lowest—0.55, 0.84, 1.05, 1.09, 1.04—with the four-variable combination having just slightly
higher values—0.65, 0.98, 1.17, 1.21, 1.29. However, the four-variable combination had the
lowest minimum square error values—10.87, 25.08, 57.28, 80.61, 121.38—which were
39
determined via linear regression analysis. Area, CN, and slope had the second lowest set of
values—12.11, 25.61, 57.84, 81.37, 130.08. The four-variable combination also had the highest
R-squared values—0.530, 0.447, 0.319, 0.300, and 0.574.
While the area, CN, and slope combination had lowest overall percent errors and standard
deviations, the four-variable combination had the lowest minimum square errors, the highest R-
squared values, and only slightly higher overall percent errors and standard deviations (than the
area, CN, and slope combination). Therefore, I decided to use the four-variable combination for
calculating my flow prediction equations. The OLS and MNS methods were both used during the
regression analysis of the four-variable combination. Figure 7-1 shows a comparison of the mean
square error for the two different regression models (22).
Figure 7-1: Comparison of Mean Square Error for Different Regression Models
1
10
100
1000
10000
Q99 Q95 Q90 Q85 Q80 Q75 Q70 Q60 Q50 Q40 Q30 Q20
Mea
n S
qu
are
Err
or
Regression Methods
MNS
OLS
40
The MNS method produced significantly lower mean square errors than the OLS method
and was the basis of the flow prediction equations below:
(7-2)
(7-3)
(7-4)
(7-5)
(7-6)
(7-7)
(7-8)
(7-9)
(7-10)
(7-11)
(7-12)
(7-13)
Figure 7-2, Figure 7-3, Figure 7-4, Figure 7-5, and Figure 7-6 compare actual stream
flows at the 13 DR reference sites with the values estimated by the flow prediction equations.
The equations appear to be reliable for all estimated values, as can be seen in Figure 7-7.
41
Figure 7-2: Relationship Between Observed and Predicted Q99 Flow
Figure 7-3: Relationship Between Observed and Predicted Q95 Flow
0.1
1.0
10.0
0.1 1.0 10.0
Pre
dic
ted
Q99 (
cms)
Observed Q99 (cms)
𝑄99 =7.683 102 𝐴0.729 𝑃0.916 𝐶𝑁3.826 𝑆0.380
0.1
1.0
10.0
0.1 1.0 10.0
Pre
dic
ted
Q95 (
cms)
Observed Q95 (cms)
95 =2.785 104 0.695 0.362 3.553 0.473
42
Figure 7-4: Relationship Between Observed and Predicted Q90 Flow
Figure 7-5: Relationship Between Observed and Predicted Q85 Flow
0.1
1.0
10.0
0.1 1.0 10.0
Pre
dic
ted
Q90 (
cms)
Observed Q90 (cms)
0.1
1.0
10.0
100.0
0.1 1.0 10.0 100.0
Pre
dic
ted
Q85 (
cms)
Observed Q85 (cms)
90 =1.168 104 0.640 0.292 3.118 0.435
85 =1.088 104 0.636 0.295 3.071 0.430
43
Figure 7-6: Relationship Between Observed and Predicted Qmean Flow
0.1
1.0
10.0
100.0
0.1 1.0 10.0 100.0
Pred
icte
d Q
mea
n (cm
s)
Observed Qmean (cms)
mean = 4.070 104 0.713 0.551 3.758 0.472
44
Figure 7-7: Relationship Between Observed and Predicted Flow for All Recurrence
Intervals Compared to Line of Perfect Correlation to Gage Station Data
7.2 Flow Duration Curves
I have chosen two of the project sites to demonstrate the predictive ability of the custom
flow duration curve prediction ArcGIS toolset. The predicted FDC for Boca de Lajas (Palomino)
generated using the above equations is shown in Figure 7-8. The actual FDC for Boca de Lajas
(Palomino), which was provided by INDRHI, is displayed in Figure 7-9. A comparison of the
two FDCs can also be found in Figure 7-10.
0.1
1.0
10.0
100.0
0.1 1.0 10.0 100.0
Pre
dic
ted
Flo
w (
cms)
Observed Flow (cms)
45
Figure 7-8: Predicted FDC for Boca de Lajas (Palomino)
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60 70 80 90 100
Q (
cms)
% Excedence
75%=4.20
80%=3.92
85%=3.55
90%=3.12
95%=2.46
46
Figure 7-9: Actual FDC for Boca de Lajas (Palomino)
Figure 7-10: Comparison FDCs for Boca De Lajas (Palomino)
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60 70 80 90 100
Q (
cms)
% Excedence
75%=3.93
80%=3.60
85%=3.22
90%= 2.83
95%=2.28
0
2
4
6
8
10
12
14
16
18
20
0 20 40 60 80 100
Q (
cms)
% Excedence
Developed Curve
Original Curve
47
The FDCs are very similar, but the statistical methods used to generate the equations are
not designed to predict extreme values located near the asymptote of the curve (i.e., the area
inside the red oval in Figure 7-8). However, for the purposes of determining where to place
SHEPs, the equations should be more than sufficient.
An additional predicted FDC for Carata (Joca El Corte) generated using the flow
prediction equations is shown in Figure 7-11. The actual FDC for Carata (Joca El Corte) is
displayed in Figure 7-12. A comparison of the two FDCs can also be found in Figure 7-13.
Figure 7-11: Predicted FDC for Carata (Joca El Corte)
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60 70 80 90 100
Q (
cms)
% Excedence
75%=4.25
80%=3.92
85%=3.54
90%=3.09
95%=2.44
48
Figure 7-12: Actual FDC for Carata (Joca El Corte)
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60 70 80 90 100
Q (
cms)
% Excedence
75%=4.49
80%=3.39
85%=3.34
90%=2.82
95%=2.19
49
Figure 7-13: Comparison FDCs for Carata (Joca El Corte)
7.3 ArcGIS Toolset
I have created a custom flow duration curve prediction ArcGIS toolset (Figure 7-14) that
performs three main functions: the delineation of a watershed using a pour point placed upon a
digital elevation model (DEM); the extraction of temporal and spatial hydrologic data from raster
and polygon feature layers; and the calculation of a watershed FDC using the flow prediction
equations and calculated regression parameters for the ungaged watershed. Each of the custom
tools has been created using parameters. This allows the user to change the tool input and run
various models. As mentioned previously, the extracted hydrologic parameters include drainage
area, CN, average yearly precipitation, and average watershed slope. Each can come from a GIS
dataset, and in this case data from
0
2
4
6
8
10
12
14
16
18
20
0 20 40 60 80 100
Q (
cms)
% Excedence
Developed Curve
Original Curve
50
Table 7-1were used. This section outlines the order and details the execution of each tool
in the main toolset 10_Steps for the Canastica (Rincon) watershed.
Figure 7-14: Custom Flow Prediction ArcGIS Toolset
INDRHI provided me with eight DEMs which they obtained online. Using the Mosaic
tool within ArcGIS I combined the DEMs into one larger DEM (Figure 7-15). The grid cell area
for each DEM is approximately 30 meters by 30 meters and the projected coordinate system is
NAD_1983_UTM_Zone_19N.
7.3.1 Preparation
The Preparation tool (Figure 7-16) creates flow direction (Figure 7-17) and flow
accumulation (Figure 7-18) hydrology layers from the DEM. These layers are used to determine
the boundary conditions of selected river watersheds.
51
Figure 7-15: Mosaic DEM of the DR
Figure 7-16: Preparation Tool in Model Builder
52
Figure 7-17: Flow Direction Output (Zoomed in to Show River Lines)
53
Figure 7-18: Flow Accumulation Output
54
7.3.2 Rivers
The Rivers tool (Figure 7-19) allows the user to set the minimum flow capacity of the
rivers using the raster calculator. The output (Figure 7-20) is a vector layer that allows the user to
visually locate where to place the pour point for watershed delineation.
Figure 7-19: Rivers Tool in Model Builder
Figure 7-20: Rivers Tool Output (Zoomed in to Show River Lines)
55
7.3.3 Pour Point Placement
Once the river vectors have been created the pour point can be placed (Figure 7-21) using
the ArcGIS Editor command. The user must be careful to place the pour point within an existing
flow accumulation grid cell, or the next tool (Delineate) will not work properly. Multiple pour
points may be placed if the user desires to analyze more than one watershed.
Figure 7-21: Pour Point Placement
56
7.3.4 Delineate
The Delineate tool (Figure 7-22) creates a watershed polygon outlining the drainage area
corresponding to the pour point (Figure 7-23). When delineating multiple watersheds the tool
must be run for each pour point individually (Figure 7-24).
Figure 7-22: Delineate Tool in Model Builder
Figure 7-23: Delineated Canastica (Rincon) Watershed
57
Figure 7-24: Two Delineated Watersheds
7.3.5 Area_Convert
The Area_Convert tool (Figure 7-25) first creates a new field (Shape_Area_km2) within
the watershed polygon. Then, the watershed area is converted from square meters to square
kilometers using the Calculate field tool. The polygon values can be viewed within its attribute
table (Figure 7-26).
Figure 7-25: Area_Convert Tool in Model Builder
58
Figure 7-26: Canastica (Rincon) Watershed Polygon Attribute Table
7.3.6 Extract_Precip
The Extract_Precip tool (Figure 7-27) extracts the annual yearly precipitation value of
each cell within a watershed polygon from a raster (precipitation values interpolated from an
isohyetal line feature class as shown in Figure 7-28) and places them in a table (Figure 7-29).
Later, another tool (ParametersToWatershed) will be used to sum the hundreds or thousands of
cell values and compute one average precipitation value to be used in the flow prediction
equations.
Figure 7-27: Extract_Precip Tool in Model Builder
59
Figure 7-28: Isohyetal Line Feature Class
Figure 7-29: Canastica (Rincon) Extract_Prec_Table
60
7.3.7 Slope
The Slope tool (Figure 7-30), which is identical to the one ArcGIS defines in ArcMap,
calculates the slope for each cell on a specified raster surface and generates an output slope raster
(Figure 7-31). The output is defined in percent rise. The use must be careful to specify an
appropriate watershed mask in the Raster Analysis section of the Environment Settings (Figure
7-32).
Figure 7-30: Slope Tool in Model Builder
Figure 7-31: Canastica (Rincon) Output Slope Raster
61
Figure 7-32: Environment Settings
7.3.8 Extract Values to Table
The Extract Values to Table tool is a tool already defined in ArcMap. I was unable to
duplicate the functionality of the Extract Values to Table tool in Model Builder or Python, so the
predefined tool was used. The tool is used to extract slope values from an output slope raster and
place them in a table—serving nearly the same purpose as the Extract_Precip tool within a slope
context (Figure 7-33). The output is a Table containing hundreds or thousands of individual
slope values (Figure 7-34)
62
Figure 7-33: Extract Values to Table Input for Slope
Figure 7-34: Canastica (Rincon) Extract_Slope_Table
63
7.3.9 Extract_CN
The Extract_CN tool (Figure 7-35) extracts CN values from a clipped portion of a soil
and land use polygon feature class (Figure 7-36) and generates a composite CN. First, the tool
clips the soil and land use polygon to conform to the shape of the watershed polygon. Then, it
creates three new fields within the clipped polygon and populates them. The First field contains
the product of CNs and areas for each distinct polygon within the watershed. The Computed_CN
field divides each value in the First field by the sum of the entire watershed area. The output
table, Average_CN (Figure 7-37), is the sum of all values in the Computed_CN field and is the
composite CN value for the entire watershed.
7.3.10 ParametersToWatershed
The ParametersToWatershed tool (Figure 7-38) is the most complex of the custom
ArcGIS tools created for this project. First, the tool calculates the average yearly precipitation, as
well as the average slope, of a specified watershed and generates two output tables. Two fields
are then created within each table: an average slope/precipitation and Precip_ID. Next, both
tables are populated with their corresponding average slope/precipitation value and each
Precip_ID is assigned a value of “1”. Finally, the specified watershed polygon is also given a
Precip_ID of “1” and linked to the two output tables. The watershed polygon attribute table now
contains all the hydrologic data needed to generate FDCs (Figure 7-39).
64
Fig
ure
7-3
5:
Extr
act
_C
N T
ool
in M
od
el B
uil
der
65
Figure 7-36: Canastica (Rincon) Combined Slope and Land Use Polygon Feature Class
Figure 7-37: Canastica (Rincon) Average_CN Table
66
Fig
ure
7-3
8:
Para
met
ersT
oW
ate
rsh
ed T
ool
in M
od
el B
uil
der
67
Fig
ure
7-3
9:
Can
ast
ica (
Rin
con
) W
ate
rsh
ed C
om
ple
te A
ttri
bu
te T
ab
le
68
7.3.11 FDC_Generation
The FDC_Generation tool (Figure 7-40) is the final custom ArcGIS tools created for this
project. The watershed polygon is linked to the FDC Table (Figure 7-41)—a template for
calculating the flows for the FDCs. The hydrologic variables are then entered into the flow
prediction equations, which generate the minimum flows for the watershed (Figure 7-42). The
final output is an FDC for the input watershed (Figure 7-43). The user must unjoin the Final
PopulatedTable from the FDC Table to rerun the tool (Figure 7-44)
Table 7-7 contains the final output values generated by the custom flow duration curve
prediction ArcGIS toolset, as well as the original hydrologic values provided by INDRHI. The
statistically developed, original, raw ArcGIS, and ArcGIS (with predefined polygon shape)
curves have also been plotted in Excel for comparison purposes (Figure 7-45).
Table 7-7: Calculated vs. Original Canastica (Rincon) Hydrologic Parameters
Raw ArcGIS ArcGIS (Predefined Polygon) Original
Area 533 km2 417 km
2 417 km
2
Precipitation 1600 mm/year 1552 mm/year 1509 mm/year
CN 82.78 82.31 82.03
Slope 0.14 0.13 0.37
69
Fig
ure
7-4
0:
FD
C_G
ener
ati
on
Tool
in M
od
el B
uil
der
70
Figure 7-41: Blank FDC Table
Figure 7-42: Populated FDC Table
71
Figure 7-43: Visual Representation of Canastica (Rincon) FDC
Figure 7-44: All Joins Must be Removed Before the Tool Can be Used Again
72
Figure 7-45: Statistical, Original, and ArcGIS FDCs
7.4 Comments
The custom flow duration curve prediction ArcGIS toolset does not generally predict
FDCs as accurately as the statistical equations. Drainage areas, especially, tend to be farther off
than the other basin characteristics. Therefore, the user should pay particular attention when
delineated watersheds to make sure they correspond to actual watershed boundaries. When
possible, use a predefined polygon shape file when defining watershed boundaries.
0
2
4
6
8
10
12
14
0 20 40 60 80 100
Q (
cms)
% Excedence
Statistical FDC
Original FDC
Raw ArcGIS FDC
ArcGIS FDC (Predefined Polygon)
73
The four variables—drainage areas, precipitation values, curve numbers, and slopes—
used to develop the flow prediction equations were provided by INDRHI. These and other basin
characteristics can be used when developing equations to predict FDCs. Table 7-8 shows the
types of basin characteristics, and their frequencies, used by the 22 states (within the United
States) with low-flow prediction equations. Drainage area, precipitation, and elevation are the
three most commonly used variables with in the United States.
Table 7-8: Basin Characteristics Used by States to Predict Stream Low Flows (23)
Basin Characteristic Frequency
Drainage Area 11
Drainage Area with Qualifier 9
Mean Annual Precipitation 11
Mean Monthly/Seasonal Precipitation 4
Mean Basin Elevation 9
Mean Watershed Slope 5
Mean Channel Slope 2
Basin Relief 2
Other 9
74
75
8 CONCLUSION
The purpose of this project was to build a methodology to evaluate small hydropower
potential, which can be used to alleviate the DR‟s energy problem among rural communities.
This was accomplished through the development of water flow prediction equations through a
linear regression analysis, as well as the design of a custom flow duration curve prediction
ArcGIS toolset that estimates FDCs at locations were data do not exist. The flow prediction tool
performs three main functions: the delineation of a watershed using a pour point placed upon a
digital elevation model (DEM); the extraction of temporal and spatial hydrologic data from raster
and polygon feature layers; and the calculation of a watershed FDC using the flow prediction
equation and extracted data. An explanation of the inputs to the tool, as well has how it produces
a suitable output for SHEP evaluation was presented. A short discussion of hydroelectric power
generation in the DR, SHEPs, and the technical and practical aspects of hydroelectric power
were also found in the paper.
The four-variable combination—area, precipitation, CN, and slope—produced the best fit
for the data and was used in developing the regression equations for custom flow duration curve
prediction ArcGIS toolset. Using the statistical flow prediction equations and ArcGIS toolset,
INDRHI engineers can now determine which sites will make the best use of available SHEP
financing. Future efforts to improve the accuracy of the equations can be achieved by expanding
the collection and implementation of additional hydrologic data.
76
77
REFERENCES
1. Yepez-Garcia R, Johnson T, & Andres, L. Meeting the Electricity Supply/Demand Balance
in Latin America & the Caribbean. The World Bank, 2010.
2. EarthTrends. Energy and Resources-Electricity-Access to Electricity, 2005.
http://earthtrends.wri.org/text/energy-resources/variable-1379.html. Accessed Mar 10,
2011.
3. Yüksel, I. Hydropower in Turkey for a Clean and Sustainable Energy Future. Renewable and
Sustainable Energy Reviews, 2008; 12: 1622-1640.
4. Organization of American States. LAC Policy Descriptions: Dominican Republic, 2003;
www.oas.org/dsd/reeep/formularios/dominican_republic_pb_reeep.doc. Accessed Nov
26, 2011.
5. Briscoe J. The Financing of Hydropower, Irrigation and Water Supply Infrastructure in
Developing Countries. Water Resources Development, Vol. 15, No. 4, 1999, pp. 459-491.
6. Dursun B & Gokcol C. The Role of Hydroelectric Power and Contribution of Small
Hydropower Plants for Sustainable Development in Turkey. Renewable Energy, 2010.
7. PSOMAS. Deer Creek Reservoir Drainage, TMDL Study, 2002.
http://www.waterquality.utah.gov/TMDL/Deer_Creek_Reservoir_TMDL.pdf. Accessed
Feb 10, 2011.
8. Yüksel I. Development of Hydropower: A Case Study in Developing Countries. Energy
Sources, 2007; 2:113-121.
9. Our Energy. Small Hydro (Small Hydroelectric), 2010.
http://www.our-energy.com/small_hydro.html. Accessed Mar 13, 2011.
10. Kaltschmitt M, Streicher W, & Wiese A. Hydroelectric Power Generation. Renewable
Energy: Technology, Economics, Environment, 2007.
11. Paish O. Small Hydro Power: Technology and Current Status. Renewable and Sustainable
Energy Reviews, Vol. 6, No. 6, 2002, pp. 537-556.
12. Popular Science Magazine. May 1977, Vol. 210, No. 5, 1997, pp. 87-93.
78
13. Zhang Z. Inlet Flow Conditions and Jet Impact Work in a Pelton Turbine. Proceedings of the
Institution of Mechanical Engineers, Part A: Journal of Power and Energy, Vol. 223, No.
5, 2009, pp. 589-596.
14. Adeyanju A. Technical Feasibility of a Micro Hydro Installation. Journal of Engineering and
Applied Sciences, Vol. 4, No. 5, 2009, pp. 324-334.
15. UCM Resita. Micro Hydro-Unit With Pelton Turbine of 40 kW, 2011.
http://www.ucmr.com/galerie-produse.php. Accessed July 27, 2011.
16. HK RE Net. Hydroelectric, 2007.
http://re.emsd.gov.hk/english/other/hydroelectric/hyd_tech.html. Accessed July 27,
2011.
17. Tripod. Hydraulic Water Turbines, 2011.
http://members.tripod.com/hydrodocs_1/turbines.html. Accessed July 22, 2011.
18. Desai V & Aziz N. Parametric Evaluation of Cross-Flow Turbine Performance. Journal of
Engineering, Vol. 120, No. 1, 1994, pp. 17-34.
19. Perez F. Personal Communication. January 19, 2011.
20. Perez F. Personal Communication. March 3, 2011.
21. Altapedia Online. Dominican Republic, 2011.
http://www.altapedia.com/online/countries/dominrep.htm. Accessed July 27, 2011.
22. GLM Engineering. Minimum Instream Flow Estimation at Ungaged Stream Sites in Puerto
Rico, 2009.
23. United States Geological Survey (USGS). National Streamflow Statistics Program, 2010.
http://water.usgs.gov/osw/programs/nss/pubs.html#al. Accessed November 28, 2011.