ANALYSIS OF STRESS CORROSION CRACKING OF X65 OIL PIPELINE€¦ · design, materials and ......
Transcript of ANALYSIS OF STRESS CORROSION CRACKING OF X65 OIL PIPELINE€¦ · design, materials and ......
http://www.iaeme.com/IJMET/index.asp 212 [email protected]
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 4, April 2017, pp. 212–222 Article ID: IJMET_08_04_025
Available online at http://www.iaeme.com/IJMET/issues.asp?JType=IJMET&VType=8&IType=4
ISSN Print: 0976-6340 and ISSN Online: 0976-6359
© IAEME Publication Scopus Indexed
ANALYSIS OF STRESS CORROSION CRACKING
OF X65 OIL PIPELINE
Elwaleed Awad Khidir
Department of Mechanical Engineering, Jubail University College,
Jubail Industrial City 31961, Kingdom of Saudi Arabia &
Department of Mechanical Engineering, Faculty of Engineering
University of Khartoum, Khartoum, Sudan
Syed Ameer Basha
Department of Mechanical Engineering, Jubail University College,
Jubail Industrial City 31961, Kingdom of Saudi Arabia
Hayder M. A. A. Al-Assadi
Faculty of Mechanical Engineering
Universiti Teknologi MARA
Shah Alam, Selangor, 40450, MALAYSIA
ABSTRACT
This paper presents the investigations that have been carried out by the University of
Khartoum to identify the root causes of the pipeline failure and to avoid the reoccurrence
of the failure. The transmission pipeline belongs to Greater Nile Petroleum Operating
Company (GNPOC) and has been commissioned in1999. The investigations showed that
the pipeline corrosion started after the disbondment of the Heat Shrinkable Sleeve (HSS)
coating around the girth weld. The study indicated that the material properties comply with
the requirements of the American Petroleum Institute (API) standards. It was observed that
the external surface of the pipeline lost its ductility due to the hydrogen embrittlement,
which contributed to crack growth beside the soil nature, the soil compaction and the
location of the concrete anchor. The failure was classified as Circumferential stress
corrosion cracking (C-SCC) of neutral-pH form and transgranular cracks morphology.
Key words: Pipeline Failure; Stress Corrosion Cracking; Hydrogen Embrittlement.
Elwaleed Awad Khidir, Syed Ameer Basha and Hayder M. A. A. Al-Assadi
http://www.iaeme.com/IJMET/index.asp 213 [email protected]
Cite this Article: Elwaleed Awad Khidir, Syed Ameer Basha and Hayder M. A. A. Al-
Assadi, Analysis of Stress Corrosion Cracking of X65 Oil Pipeline. International Journal
of Mechanical Engineering and Technology, 8(4), 2017, pp. 212–222.
http://www.iaeme.com/IJMET/issues.asp?JType=IJMET&VType=8&IType=4
1. INTRODUCTION
Oil and gas transmission pipelines have a good safety record due to the combination of good
design, materials and operating practices. However, like any engineering structure, pipelines do
occasionally fail. The most common causes of damage and failures in onshore and offshore, oil
and gas transmission pipelines are external interface and corrosion [1]. Corrosion usually appears
as either general corrosion or locallised (pitting) corrosion. Corrosion causes metal loss. It can
occur on the internal or external surfaces of the pipe, in the base material, the seam weld, the girth
weld, and/or the associated heat affected zone (HAZ).
Most buried pipelines that have been in service for five or more years experience numerous
corrosion and metallurgical defects, in particular cracks. The sources of these cracks can be due to
randomly distributed defects induced by the manufacturing process or the degradation of carbon
steel components of pipelines. The combined action of stress (e.g., hoop and/or residual) and
natural soil environment containing varying amounts of moisture and oxygen further facilitates the
initiation of the crack(s) and accelerates their propagation through the pipe thickness by a factor
that may range up to many times. In general the heat affected zone (HAZ) of a weld (especially at
the region adjacent to the fusion line) is hardened after welding. The hardened microstructures are
usually sensitive to hydrogen embrittlement (HE) and stress corrosion cracking [2].
In particular, weldments of thermomechanical-control processed (TMCP) steels such as the
API X65 steel show a greater difference between weld metal and HAZ properties than other
structural steel welds because of the HAZ softening effect, due to the thermal cycle experienced
in the welding process. This leads to further tempering of the already quenched and tempered
region. Therefore the difference in material properties between the different weld regions
influences how plasticity develops at flaws and hence the relationship between the crack driving
force and applied loading [3].
Stress corrosion cracking can be defined as the interaction of a tensile stress and an aqueous
environment acting on a susceptible metallic surface to initiate and propagate cracks. Since the
first discovery of Stress Corrosion Cracking (SCC) on the exterior surface of a buried high-
pressure natural gas transmission pipeline in 1965, SCC has continued to make a significant
contribution to the number of leaks and ruptures experienced by several countries throughout the
world (Argentina, Australia, Iran, Iraq, Italy, USA, Canada, the former Soviet Union, Pakistan,
Saudi Arabia and The Netherland) [4-6].
Two forms of SCC in the external surface of buried pipelines have been identified: high-pH or
“classical SCC” and low-pH or “near neutral SCC”. Both types of SCC have only been observed
under disbonding coatings [7]. High-pH SCC is by far the most reported form of SCC and is
characterized by the presence of numerous fine longitudinal intergranular. Cracking is associated
with relatively concentrated carbonate (CO3-) -bicarbonate (HCO3
- ) solution having pH in the
range 9 to 12.5. Low-pH SCC (or near neutral pH) on the outer surface of pipelines is associated
with specific soil conditions at free corrosion potential, where cathodic protection is ineffective.
Low-pH SCC occurs in the presence of dilute ground waters containing free carbon dioxide (CO2)
having a pH of around 6-8 [4, 8]. Pipeline steels becomes susceptible to near-neutral pH stress
Analysis of Stress Corrosion Cracking of X65 Oil Pipeline
http://www.iaeme.com/IJMET/index.asp 214 [email protected]
corrosion cracking only when coatings on pipeline steels are damaged. This usually happens after
5 – 10 years of operation. During this 5-10 years period, the pipeline steels have been mechanically
conditioned by stress variations in the pipe that could be a key factor to the cracking after the
coating is damaged [9]. Marr et al. [10] wrote ‘‘the failure of a coating system is a primary factor
in the initiation and propagation of SCC.’’
Different types of coatings have been used to protect oil and gas pipelines over the past 50
years, such as coal tar or asphalt enamels, polyolefin tapes, two layer extruded polyethylene
coatings, single or dual layer fusion bonded epoxy coatings, heavy three or multi-layer polyolefin
coatings [11].
2. EXPERIMENTAL
3.1. Visual Inspection
The Greater Nile Petroleum Operating Company (GNPOC) 28” crude oil transmission pipeline
has been commissioned in1999. The design temperature and pressure are 55oC – 75oC and 97.24
bar, respectively.
On the 15th March, leakage of oil was observed on the 28” (API-5L WT 10.72/16.36mm)
buried pipeline. The location of the leakage is approximately 45.17 meters at the discharge side of
pump station 1. It was reported that the cracked zone was between 11:00 to 12:00 o’clock positions.
A mechanical leak repair clamp was installed as a temporary repair but the pipe was still leaking.
A permanent repair has been carried out by welding the same clamp and the leak was still there.
Then the defected spool pipe was replaced by a 4m new spool pipe and the pipeline was back to
normal operation.
The pipeline corrosion started after the disbondment of the Heat Shrinkable Sleeve (HSS)
coating around the girth weld. Figures 1 shows the corroded area around the girth weld. The
fractured side represents the pipe of 10.72 mm thickness (Figure 1 a). This side contained small to
large wide shallow pits, while the side of the 16.36mm thickness spool contained relatively small
pits (Figure 1 b). The crack lies in the Heat Affected Zone (HAZ) around 10 to 15 mm from the
girth weld. The crack is in the circumferential direction that initiated from external surface of the
pipe toward the internal surface. The length of the crack is about 16 cm.
(a)
Elwaleed Awad Khidir, Syed Ameer Basha and Hayder M. A. A. Al-Assadi
http://www.iaeme.com/IJMET/index.asp 215 [email protected]
(b)
Figure 1 Corrosion on the (a) 10.72 mm thickness side (b) the 16.36 mm side (the coin in the picture is of
20 mm diameter)
2.2. Chemical Composition of X65 Steel
The chemical composition of the steel by weight is shown in Table 1 (wt%). The microstructure
is composed of polygon ferrites and a few pearlites as shown in Figure 2. The X65 steel was
characterized as being susceptible to near-neutral pH stress corrosion cracking [9].
Table 1 Chemical Composition
Element Average (wt%)
Magnitude API 5L X65
C 0.077 0.28 max
Mn 1.58 1.40 max
P 0.014 0.03 max
S 0.0026 0.03 max
Si 0.355 -
Nb 0.036 -
Cr 0.021 -
Ti <0.001 -
Mo <0.002 -
V 0.0016 -
Ni 0.019 -
Al 0.032 -
Cu 0.0092 -
Analysis of Stress Corrosion Cracking of X65 Oil Pipeline
http://www.iaeme.com/IJMET/index.asp 216 [email protected]
Figure 2 Microstructure of X65 Steel
2.3. Mechanical Properties of X65 Steel
Three samples were prepared from both pipes of different thickness to check their mechanical
properties. The mechanical properties of the material under investigation are shown in Table 2.
The pipe material complies with the requirements of the API 5L X65 [12].
Table 2 Chemical Composition
Property Average API 5L X65 range
Tensile strength (MPa) 649.0 531-758
Yield strength (MPa) 555.8 448-600
2.4. Soil Analysis
The soil at Heglig is black cotton soil, which is characterized by high swelling on wetting and
excessive shrinkage on drying due to the high content of montmorillonitic (beidellite) groups of
clay minerals. Although the soil is very hard in the dry state, nearly all its strength is lost when
saturated. This behavior is attributed generally to the presence of a high percentage of colloidal
material [13]. pH values of the soils range between 7 and 9. Figure 3 shows the areas of black soil
deposits in warm climates [14].
Elwaleed Awad Khidir, Syed Ameer Basha and Hayder M. A. A. Al-Assadi
http://www.iaeme.com/IJMET/index.asp 217 [email protected]
Figure 3 Areas of black soil deposits in warm climates shown in black [14]
A sample was taken from the soil surrounding the buried pipeline at Heglig. The soil was
analyzed at the Faculty of Engineering, University of Khartoum. The laboratory results are shown
in Table 3. The results show that the soil pH is 7.8. The soil resistivity is 3.1 Ohm-m, which
indicates the highest corrosion environment along the pipeline [15].
Table 2 Soil properties
Property Average
pH 7.8000
Chloride (%) 0.0020
Sulphate (%) 0.0031
Carbonate (%) 0.0420
Organic Matter (%) 4.0480
3. DISCUSSION
It is very clear that the pipeline corrosion started after the disbondment of the HSS coating around
the girth weld and in the HAZ. The fractured side represents the pipe of 10.72 mm thickness, which
contained small to large wide shallow pits, while the side of the 16.36mm thickness spool
contained relatively small pits. The length of the crack is about 16 cm (Figure 4). The crack
initiated and propagated in the circumferential direction from external surface of the pipe toward
the internal surface.
Analysis of Stress Corrosion Cracking of X65 Oil Pipeline
http://www.iaeme.com/IJMET/index.asp 218 [email protected]
Figure 4 Sketch for the corroded area welding joint and the crack position
The crack feature from outside is very clear. The internal surface of the spool showed that the
crack started with a neck-like shape before opening (Figure 5). This could be attributed to that the
ductility of the inside surface of the spool was not affected by the embrittlement occurred at the
outside surface.
It was proved that the application of Cathodic Protection (CP), when pipeline failure is
imminent, is not always advisable because CP results in the steel becoming charged with hydrogen.
When sufficient hydrogen concentrates in pipeline steel, the metal loses its ductility – a
phenomenon known as hydrogen embrittlement. In reported cases, after one to two years of
service, more than a sixfold increase of hydrogen content occurred in the external surface of pipes
and, after 15 years, there was approximately a tenfold increase of hydrogen content [16]. As such,
it is hardly a coincidence that almost all failures in cathodically protected pipelines were
encountered in pipes installed for more than 10 years [17].
Previous studies of SCC of X-52 and X-80 pipeline steels in near-neutral pH solution showed
that SCC accelerated as the applied cathodic potential became more negative; and that hydrogen
diffused into the steel during SCC and concentrated around the crack tip, proving that crack growth
at cathodic potentials was due to the presence of occluded hydrogen in steels. On February 20,
2002, during a panel discussion on Cathodic Protection Myth-Conceptions held during the NACE
International Northern Area Western Conference in Edmonton, the subject ‘‘Cathodic Protection
Causes Hydrogen Embrittlement of Steel Pipelines’’ was voted as one of the 12 most important
subjects to be considered by the Canadian pipeline industry. It was a defining moment in the public
acknowledgement of the need to address the problem of cathodically induced hydrogen
embrittlement of pipeline steels [5].
Elwaleed Awad Khidir, Syed Ameer Basha and Hayder M. A. A. Al-Assadi
http://www.iaeme.com/IJMET/index.asp 219 [email protected]
Figure 5 The neck-like shape at internal surface of the spool before opening the crack started
As long as crack grows circumferentially at the corroded area, it can be classified as
circumferential stress corrosion cracking (C-SCC). This interpretation is supported by the
Canadian Energy Pipeline Association (CEPA) report [18], in which it was mentioned that most
cases the SCC appears to have been of the neutral-pH form (6-8 pH). The laboratory results showed
that the soil pH at the surroundings of the buried pipe is 7.8. Figure 6 shows how the crack
propagates circumferentially.
Figure 6 The crack propagation
The GNPOC Intelligent Pigging report in 2007 revealed that there is a metal loss at many
points along the pipeline. At the position of rupture the thickness of the pipe was reduced by 15%.
After the rupture the spool was replaced with a new one and the thickness at the same position was
measured and the reduction in thickness was estimated as 77%. Figure 7 shows the percentage
reduction of thickness from the year of commission in 1999 to the year of rupture 2007. It could
Analysis of Stress Corrosion Cracking of X65 Oil Pipeline
http://www.iaeme.com/IJMET/index.asp 220 [email protected]
be observed from the figure that the rate of corrosion is high between 2007 and 2010 compared
with the rate of corrosion from 1999 to 2007.
Figure 7 Variation of thickness reduction with time
The corrosion of the pipe was at the HAZ on the spool of 10.72mm thickness. Due to the
thickness reduction this part became a stress concentration zone (Figure 8). The stress on the pipe
around this area was bending stress because of the black cotton soil nature (soil movement), as
mentioned in section 2.7. This stress was enhanced by the heavy compaction that the soil, above
the pipe, was exposed to. The anchor block supporting the pipeline was just 25m from the defected
part. As a result the pipe became like a cantilever along which the weakest part was the area of
high stress concentration. The defected spool pipe was replaced with a 4m spool. The old spool
was separated using a torch. According to witnesses the separation created a loud noise and the
new spool was aligned, for welding, with difficulty. This indicated that the pipe was under bending
stress.
It was reported that C-SCC initiated and grew under conditions of high axial stress generated
by slow, continuous soil movement and/or localized pipe bending in the vicinity of rocks and dents
on slopes. The soil movements associated with these cases of C-SCC can be termed as creep
movements, as opposed to catastrophic landslides. These slow and continuous movements can be
difficult to recognize in the field but, as evidenced by strain measurements, can with time generate
stresses in excess of Specified Minimum Yield Strength (SMYS) on the pipe. Clay soils and
moisture on and in slopes can be risk factors for soil creep. Periodic increases in axial tension on
the pipe may be a result of seasonal rain. Besides contributing to axial loading of the pipeline, soil
creep would also contribute to coating disbondment [19-21]. Construction practices can also
induce axial stress in the pipe. This may occur where pipe was forced into alignment for welding
at tie-in locations, for example at stream crossings, or at locations of field bends. Bending stress
can occur at road crossings where the loads are too great for the cover and strength of the pipe.
Elwaleed Awad Khidir, Syed Ameer Basha and Hayder M. A. A. Al-Assadi
http://www.iaeme.com/IJMET/index.asp 221 [email protected]
Figure 8 Sketch for the pipe and surrounding conditions enhancing the crack propagation
4. CONCLUSION
• The study showed that the material properties comply with the requirements of the API standards.
• The HSS coating defect, the hydrogen embrittlement, the soil nature and the soil compaction are
the main reasons for the rupture.
• The results show that the soil pH is 7.8. Therefore, the failure was classified as circumferential
stress corrosion cracking (C-SCC) of neutral-pH form and transgranular cracks morphology.
• In the future the IP report must be taken into consideration, especially in areas of the same
conditions such as different thickness joints (different internal diameters), at positions not far from
the anchor blocks and where the soil of similar properties.
REFERENCES
[1] Cosham, A., Hopkins, P. and Macdonald, K. A. Best practice for the assessment of defects in
pipelines – Corrosion. Engineering Failure Analysis, 14, 2007, pp. 1245-1265.
[2] Tsay, L. W., Chen, Y. C. and Chan, S. L. I. Sulfide stress corrosion cracking and fatigue crack
growth of welded TMCP API 5L X65 pipe-line steel. International Journal of Fatigue, 23,
2001, pp. 103-113.
[3] Lee, J. S., Ju, J. B., Jang, J., Kim, W. S. and Kwon, D. Weld crack assessments in API X65
pipeline, failure assessment diagrams with variations in representative mechanical properties.
Materials Science and Engineering A., 373, 2004, pp. 122-130.
[4] Manfredi, C. and Otegui, J. L. Failures by SCC in buried pipelines. Engineering Failure
Analysis, 9, 2002, pp. 495-509.
[5] Shipilov, S. A. and May, I. L. Structural Integrity of Aging Buried Pipelines Having Cathodic
Protection. Engineering Failure Analysis, 13, 2006, pp. 1159-1176.
[6] Van Boven, G. Chen, W. and Rogge, R. The role of residual stress in neutral pH stress corrosion
cracking of pipeline steels. Part I: Pitting and cracking occurrence. Acta Materialia. 55, 2007,
pp. 29-42.
[7] Fazzini, P. G. and Otegui, J. L. Experimental determination of stress corrosion crack rates and
service lives in a buried ERW pipeline. International Journal of Pressure Vessels and Piping,
84, 2007, pp. 739-748.
Analysis of Stress Corrosion Cracking of X65 Oil Pipeline
http://www.iaeme.com/IJMET/index.asp 222 [email protected]
[8] Pan, B. W., Peng, X., Chu, W. Y., Su, Y. J. and Qiao L. J. Stress corrosion cracking of API X-
60 pipeline in a soil containing water. Materials Science and Engineering A, 434, 2006, pp. 76-
81.
[9] Eslami, A. Fang, B., Kania, R., Worthingham, B., Been, J., Eadie, R. and Chen, W. Stress
corrosion cracking initiation under the disbonded coating of pipeline steel in near-neutral pH
environment.. Corrosion Science, 52, 2010, pp. 3750-3756.
[10] Marr, J. E. Hardy, S. B. and Huuskonen, E. SCC integrity management - liquid and gas pipeline
Systems. Calgary, Marr Associates, 2003.
[11] Fairhurst, D. Shreir's Corrosion. 2010, pp. 2702-2719.
[12] API 5L Specifications for Line Pipe. 42nd ed. American Petroleum Institute, 2000.
[13] Uppal, H. and Chadda, L. R. Engineering Geology. 1967, pp. 179.
[14] Dudal. R. Soil Science. 1963, pp. 95: 264.
[15] GNPOC. Root Causes Analysis Report for 28” Pipeline Leakage at Kp0.045 at Ps#1. Muglad
Basin, 2010.
[16] Mazel, A. G. On stress corrosion cracking of gas pipelines, Reliability and safety of gas
pipelines subject to stress corrosion cracking. STP 2–4, Moscow, RAO Gazprom, 1993, pp. 11.
[17] R. N. Parkins. Conceptual understanding and life prediction for SCC of pipelines, In:
Proceedings of the CORROSION/96: Research topical symposia. pp. 1-49. Houston, NACE
International.
[18] The CEPA Report on Circumferential Stress Corrosion Cracking. 1997. Canadian Energy
Pipeline Association (CEPA). Calgary, CEPA, 1996.
[19] Kane, R. D. Environmentally Assisted Cracking: Predictive Methods for Risk Assessment and
Evaluation of Materials, Equipment, and Structures. Philadelphia, PA. 2000.
[20] Abedi, S. Sh., Abdolmaleki, A. and Adibi, N. Failure analysis of SCC and SRB induced
cracking of a transmission oil products pipeline. Engineering Failure Analysis, 14, 2007, pp.
250-261.
[21] V. Amirthavalli, M. Juliyas Augustine Prince and B. Antony Fayaz. Petroleum Engineering
Learning Provocation, International Journal of Production Technology and Management, 6(2),
2015, pp. 16-20.
[22] Sherif A. Moustafa, Mohamed H. Al Awady and M.A.Ashmawy. Naphtha Removal from
Petroleum Industrial Effluent. International Journal of Civil Engineering and Technology, 6(9),
2015, pp. 139-146.
[23] CEPA. Stress Corrosion Cracking, Recommended Practices. 2nd ed., Calgary, Alberta,
Canada. 2007.