Analisis PU Resumen estimado REV2

22
(500-1200)UF TABIQUE VOLCOMETAL E = 6 cm VOLCANITA 10mm St 1.000 m2 VOLCANITA 10mm St 1.000 m2 Aislan Glass R-94 1.000 m2 TORNILLO AUTOPERFORANTE 25 19.000 uni MASILLA BASE JUNTA (30kg) 0.067 sac HUINCHA 2.000 ml CLAVO HILTI SDM27 1.500 uni FULMINANTE CALIBRE 27 ROJO 1.500 uni PINO BRUTO 0.003 pul CANAL 39x20x0,5mm 0.850 ml MONTANTE MET. 38x38x0,5mm 2.500 ml ESQUINERO METAL. P/VOLCAN. 0.300 ml PERDIDAS 5% CARPINTERO + 1 AYUD 0.100 dia LEYES SOCIALES (O.E.) 55.000 % TOTAL TABIQUE VOLCOMETAL E = 9 cm VOLCANITA 15mm St 1.000 m2 VOLCANITA 15mm St 1.000 m2 Aislan Glass R-94 1.000 m2 TORNILLO AUTOPERFORANTE 25 19.000 uni MASILLA BASE JUNTA (30kg) 0.067 sac HUINCHA 2.000 ml CLAVO HILTI SDM27 1.500 uni FULMINANTE CALIBRE 27 ROJO 1.500 uni PINO BRUTO 0.003 pul CANAL 61x20x0,5mm 0.850 ml MONTANTE MET. 60x38x0,5mm 2.430 ml ESQUINERO METAL. P/VOLCAN. 0.300 ml PERDIDAS 5% CARPINTERO + 1 AYUD 0.100 dia LEYES SOCIALES (O.E.) 55.000 % TOTAL TABIQUERIA MADERA PIE/DER A 0.60MT VOLCANITA 15mm St 1.000 m2 VOLCANITA 15mm St 1.000 m2 Aislan Glass R-94 1.000 m2 MASILLA BASE JUNTA (30kg) 0.067 sac HUINCHA 2.000 ml Pino 2X3 SECO IMPREGNADO 0.75 pul CLAVO CORRIENTE 4'' 0.05 kg PERNO COCHE 5x3/8 ACERO 0.65 uni PERDIDAS 10% CARPINTERO + 1 AYUD 0.12 dia

Transcript of Analisis PU Resumen estimado REV2

Page 1: Analisis PU Resumen estimado REV2

(500-1200)UF

TABIQUE VOLCOMETAL E = 6 cmVOLCANITA 10mm St 1.000 m2 $ 1,735

VOLCANITA 10mm St 1.000 m2 $ 1,735

Aislan Glass R-94 1.000 m2 $ 1,108

TORNILLO AUTOPERFORANTE 25 19.000 uni $ 5

MASILLA BASE JUNTA (30kg) 0.067 sac $ 3,060

HUINCHA 2.000 ml $ 13

CLAVO HILTI SDM27 1.500 uni $ 39

FULMINANTE CALIBRE 27 ROJO 1.500 uni $ 36

PINO BRUTO 0.003 pul $ 2,000

CANAL 39x20x0,5mm 0.850 ml $ 211

MONTANTE MET. 38x38x0,5mm 2.500 ml $ 326

ESQUINERO METAL. P/VOLCAN. 0.300 ml $ 120

PERDIDAS 5%

CARPINTERO + 1 AYUD 0.100 dia $ 17,000

LEYES SOCIALES (O.E.) 55.000 %

TOTAL

TABIQUE VOLCOMETAL E = 9 cmVOLCANITA 15mm St 1.000 m2 $ 2,360

VOLCANITA 15mm St 1.000 m2 $ 2,360

Aislan Glass R-94 1.000 m2 $ 1,108

TORNILLO AUTOPERFORANTE 25 19.000 uni $ 5

MASILLA BASE JUNTA (30kg) 0.067 sac $ 3,060

HUINCHA 2.000 ml $ 13

CLAVO HILTI SDM27 1.500 uni $ 39

FULMINANTE CALIBRE 27 ROJO 1.500 uni $ 36

PINO BRUTO 0.003 pul $ 2,000

CANAL 61x20x0,5mm 0.850 ml $ 265

MONTANTE MET. 60x38x0,5mm 2.430 ml $ 381

ESQUINERO METAL. P/VOLCAN. 0.300 ml $ 144

PERDIDAS 5%

CARPINTERO + 1 AYUD 0.100 dia $ 17,000

LEYES SOCIALES (O.E.) 55.000 %

TOTAL

TABIQUERIA MADERA PIE/DER A 0.60MT

VOLCANITA 15mm St 1.000 m2 $ 2,360

VOLCANITA 15mm St 1.000 m2 $ 2,360

Aislan Glass R-94 1.000 m2 $ 1,108

MASILLA BASE JUNTA (30kg) 0.067 sac $ 3,060

HUINCHA 2.000 ml $ 13

Pino 2X3 SECO IMPREGNADO 0.75 pul 2,400

CLAVO CORRIENTE 4'' 0.05 kg 400

PERNO COCHE 5x3/8 ACERO 0.65 uni 62

PERDIDAS 10%

CARPINTERO + 1 AYUD 0.12 dia 17,000

Page 2: Analisis PU Resumen estimado REV2

LEYES SOCIALES (O.E.) 55% %

TOTAL

TABIQUERIA ISOMURVOLCANITA 10mm St 1.000 m2 $ 1,735

VOLCANITA 10mm St 1.000 m2 $ 1,735

PASTA PLANCHA POLIGYP (saco 30 kg) 0.08 sac 3,800

BLOQUE DE YESO ISOMUR 1.02 m2 3,420

PASTA ISOMUR (saco 30 kg) 0.08 sac 4,325

YESO CALCINADO (saco 30 Kg) 0.07 sac 1,657

ERACLIT 25mm 2x0.5 mt 0.03 m2 1,606

AISLAPOL 25 mm. STD. 0.03 m2 485

PERDIDAS 10%

CARPINTERO TERMINACION+AYUD 0.07 dia 21,000

LEYES SOCIALES (O.E.) 55% %

TOTAL

TABIQUERIA HORMIGON CELULARPASTA PLANCHA POLIGYP (saco 30 kg) 0.08 sac 3,800

BLOQUE HORMIGON CELULAR 8.00 m2 1,387

PASTA PEGAR (saco 30 kg) 0.08 sac 4,325

YESO CALCINADO (saco 30 Kg) 0.07 sac 1,657

PERDIDAS 10%

CARPINTERO TERMINACION+AYUD 0.07 dia 21,000

LEYES SOCIALES (O.E.) 55% %

TOTAL

Page 3: Analisis PU Resumen estimado REV2

$ 1,735

$ 1,735

$ 1,108

$ 95

$ 205

$ 26 $ 4,904 56%$ 59

$ 54

$ 6 $ 119 1%$ 179

$ 816

$ 36 $ 1,031 12%$ 303

$ 1,700

$ 736 $ 2,436 28%$ 8,792

$ 2,360

$ 2,360

$ 1,108

$ 95

$ 205

$ 26

$ 59

$ 54

$ 6 $ 6,273 71%$ 225

$ 925

$ 43 $ 1,194 14%$ 373

$ 1,700

$ 736 $ 2,436 28%$ 10,276

$ 2,360

$ 2,360

$ 1,108

$ 205

$ 26 $ 6,059 51%1,800

20

40 1,860 16%$ 792

2,040

Page 4: Analisis PU Resumen estimado REV2

1,122 3,162 27%11,873

$ 1,735

$ 1,735

315

3,488

359

111

53

16

$ 781

1,470

809

10,873

315

11,096

359

111

$ 1,188

1,470

809

15,348

Page 5: Analisis PU Resumen estimado REV2

(500-1200)UF

ENVIGADO PISO 2" x 6" PINO BRUTO (3.6 mt) 0.85 pul 2,800CLAVO CORRIENTE 3'' 0.1 kg 310PLACA TERCIADO ESTRUCTURAL 18 MM uni 1.1 3,938PERDIDAS 10%CARPINTERO + 1 AYUD 0.06 dia 13,383LEYES SOCIALES (O.E.) 0.55 %

$/M^2

ENVIGADO PISO METALCON 150CA085@040Actividad Unidad Cantidad PrecioPERFILES METALCON ESTRUCTURAL kg 3.69 720TORNILLO AUTOP 10X3/4" uni 28 7DISCO CORTE 7" PARA METAL uni 11 670PLACA TERCIADO ESTRUCTURAL 18 MM uni 1.1 3,938PERDIDAS 5%Carpintero metalico + ayudante día 0.1 17,000LS % 0.55

Losa de Hormigon e=11 cm P.U CANT. UNIDADCOLOCACION HORMIGON 18,500 1 GLCOLOCACION ENFIERR. 22,356 1 GLCOLOCACION MOLDAJE 35,000 1 GLENLUCIDO LOSA 14,630 1 GLFIERRO CONSTRUCCIÓN 900 220 KGHORMIGON H20 40,000 2.7 M3ARRIENDO MOLDAJE 13,602 1 GLCONSTRUCCION MOLDAJE 1,366 1 GLPLACAS REBALCE 11,500 0.33 PLPLACA FENÓLICA LOSA 16,500 1.25 PLTOTAL/M2

(Más de 1200)UF

ENVIGADO PISO METALCON 150CA160@040Actividad Unidad Cantidad PrecioPERFILES METALCON ESTRUCTURAL kg 6.88 720TORNILLO AUTOP 10X3/4" uni 28 7DISCO CORTE 7" PARA METAL uni 11 670PLACA ESTRUCTURAL OSB 15 MM uni 0.34 5,690HORMIGON LIVIANO m3 0.05 38,000Malla electro soldada un 0.1 22,470Conectores un 1.8 549PERDIDAS 5%Carpintero metalico + ayudante día 0.1 17,000

Page 6: Analisis PU Resumen estimado REV2

Albañil + ayudante día 0.09 25,000LS % 0.55

ENVIGADO PISO 2" x 10" PINO BRUTO (3.6 mt) 1.4 pul 2,800CLAVO CORRIENTE 3'' 0.1 kg 310PLACA ESTRUCTURAL OSB 15 MM uni 20 5,690HORMIGON LIVIANO m3 2.7 57,839PERDIDAS 10%Albañil + ayudante día 0.09 25,000CARPINTERO + 1 AYUD 0.06 dia 13,383LEYES SOCIALES (O.E.) 0.55 %

$/M^2

Losa de Hormigon e=15 cm P.U CANT. UNIDADCOLOCACION HORMIGON 18,500 1 GLCOLOCACION ENFIERR. 22,356 1 GLCOLOCACION MOLDAJE 35,000 1 GLENLUCIDO LOSA 14,630 1 GLFIERRO CONSTRUCCIÓN 930 220 KGHORMIGON H20 50,000 3.69 M3ARRIENDO MOLDAJE 13,602 1 GLCONSTRUCCION MOLDAJE 1,366 1 GLPLACAS REBALCE 11,500 0.33 PLPLACA FENÓLICA LOSA 16,500 1.25 PLTOTAL/M2

Page 7: Analisis PU Resumen estimado REV2

2,38031

4,332674803442

8,662

Total2,657

196139

4,332366

1,700935

10,325

SUBTOTAL 18,500 22,356 35,000 14,630 198,000 108,000 13,602 1,366 3,833 20,625

$ 17,720

Total4,954

196139

1,9351,9002,247

988618

1,700

Page 8: Analisis PU Resumen estimado REV2

2,2502,173

19,099

3,92031

2,1472,947

9042,250

8031,679

14,681

SUBTOTAL 18,500 22,356 35,000 14,630 204,600 184,500 13,602 1,366 3,833 20,625

$ 21,098

Page 9: Analisis PU Resumen estimado REV2

(500-1200)UF

METALCON CUBIERTA PLANCHA ONDULADA (ZINC # 26)CLAVO TECH C/GOL.2''1/2x8 0.04 kg 1,125 45

PL ZINCALUM #26 LISA 0,5mm 0.06 m2 1,547 99

TOR.GAL. 2 1/2''x12mm P/TECH 0.64 uni 38 24

TOR.1x12 P/MAD C/PLAN ACERO 0.64 uni 5 3

PL ZINCALUM #26 ACAN. 0,5mm 1.06 m2 1,678 1,779

Metalcon 7.65 kg 720 5,508

PERDIDAS 5% 373

Metalconero + 1 AYUD 0.10 dia ### 1,700

CARPINTERO + 1 AYUD 0.02 dia ### 268

HOJALATERO + AYUD 0.03 dia ### 402

LEYES SOCIALES (O.E.) 55% % 1,304

TOTAL/M2 $ 11,505

MADERA CUBIERTA PLANCHA ONDULADA (ZINC # 26)PINO BRUTO 0.21 pul 1,600 336

CLAVO CORRIENTE 4'' 0.02 kg 300 6

CLAVO TECH C/GOL.2''1/2x8 0.04 kg 1,125 45

PL ZINCALUM #26 LISA 0,5mm 0.06 m2 1,547 99

TOR.GAL. 2 1/2''x12mm P/TECH 0.64 uni 38 24

TOR.1x12 P/MAD C/PLAN ACERO 0.64 uni 5 3

PL ZINCALUM #26 ACAN. 0,5mm 1.06 m2 1,678 1,779

PINO BRUTO 2.00 pul 1,800 3,600

CLAVO CORRIENTE 3'' 0.10 kg 310 31

PERDIDAS 10% 592

CARPINTERO + 1 AYUD 0.02 dia ### 340

HOJALATERO + AYUD 0.03 dia ### 402

CARPINTERO + 1 AYUD 0.05 dia ### 669

LEYES SOCIALES (O.E.) 55% % 776

TOTAL/M2 $ 8,703

(Más de 1200)UF METALCON CUBIERTA TEJA COLONIAL CHILENAALAMB.NEG#18 104mt/kg R/50K 0.06 kg 350 21

TEJA COLONIAL BIO BIO 24.00 uni 205 4,920

CABALLETE 0.50 uni 400 200

ARENA ESTUCO C/FLETE 15 KMS 4.00 lit 6 24

CEMENTO POLPAICO ESPEC PUBL 0.03 sac 2,607 73

Metalcon 9.70 kg 720 6,984

PERDIDAS 5% 611

Metalconero + 1 AYUD 0.10 dia ### 1,700

TEJERO + AYUD 0.15 dia ### 2,124

LEYES SOCIALES (O.E.) 55% % 2,103

TOTAL/M2 $ 18,760

MADERA CUBIERTA TEJA COLONIAL CHILENA

Page 10: Analisis PU Resumen estimado REV2

ALAMO BRUTO 0.60 pul 2,800 1,680

CLAVO CORRIENTE 3'' 0.03 kg 300 9

ALAMB.NEG#18 104mt/kg R/50K 0.06 kg 350 21

TEJA COLONIAL BIO BIO 24.00 uni 205 4,920

CABALLETE 0.50 uni 400 200

ARENA ESTUCO C/FLETE 15 KMS 4.00 lit 6 24

CEMENTO POLPAICO ESPEC PUBL 0.03 sac 2,607 73

PINO SECO IMPREGNADO 2.90 pul 2,400 6,960

CLAVO CORRIENTE 3'' 0.10 kg 310 31

PERDIDAS 10% 1,392

CARPINTERO + 1 AYUD 0.10 dia ### 1,340

TEJERO + AYUD 0.15 dia ### 2,124

LEYES SOCIALES (O.E.) 55% % 1,905

TOTAL/M2 $ 20,679

Page 11: Analisis PU Resumen estimado REV2

(500-1200)UF

DESCRIPCION UNID. CANT.

CIELO VOLCANITA 10MM C/JUNT/INVIS M2Pino bruto pul 1.96Volcanita 10 mm m2 1.05Clavo p/volcanita 670 u. kg 0.03Clavo 2 1/2"x1 (236u) kg 0.06Clavo Terrano 1" (500u) kg 0.03Huincha junta invisible 75 ml rollo 0.02Masilla Base junta (30 kg) sac 0.01PERDIDAS 10%Volcanitero + 1 ayudante día 0.1L.S. % 55%

Cielo MetalconTabla Consumo Cielo Metalcon Unidad Consumo Consumo /mt2Conector TI (bolsa de 10 u) Unitario 0.8Portante (Omega) 40-R Metro Lineal 1.007Canal Perímetro Perfil AT Metro Lineal 0.15Canal Horizontal Perfil AT Metro Lineal 0.225Tornillo Unión Conector-conector Unitario 0.8Tornillo Fijación Canal a Conector Unitario 0.8Tornillo Fijación 40-R a Canal Unitario 4.6Tornillo Fijación Placa a 40-R Unitario 22Volcanita 10 mm m2 1.05Huincha junta invisible 75 ml rollo 0.02Masilla Base junta (30 kg) sac 0.01PERDIDAS 5%Volcanitero + 1 ayudante día 0.1L.S. % 55%

(Mas de 1200)UF

DESCRIPCION UNID. CANT.

CIELO DE YESO 10 MM M2Pino bruto Cepillado pul 1.96Clavo 2 1/2"x1 (236 u) kg 0.08Yeso 10 mm 1x1,50 m s/inst. m2 1.05Clavo 2 1/2"x1 (236u) kg 0.06Clavo Terrano 1" (500u) kg 0.03Huincha junta invisible 75 ml rollo 0.02Masilla Base junta (30 kg) sac 0.01PERDIDAS 10%Yesero + ayudante día 0.1L.S. % 55%

Page 12: Analisis PU Resumen estimado REV2

Cielo MetalconTabla Consumo Cielo Metalcon Unidad Consumo Consumo /mt2Conector TI (bolsa de 10 u) Unitario 0.8Portante (Omega) 40-R Metro Lineal 1.007Canal Perímetro Perfil AT Metro Lineal 0.15Canal Horizontal Perfil AT Metro Lineal 0.225Tornillo Unión Conector-conector Unitario 0.8Tornillo Fijación Canal a Conector Unitario 0.8Tornillo Fijación 40-R a Canal Unitario 4.6Tornillo Fijación Placa a 40-R Unitario 22Volcanita 10 mm m2 1.05Huincha junta invisible 75 ml rollo 0.02Masilla Base junta (30 kg) sac 0.01PERDIDAS 5%Volcanitero + 1 ayudante día 0.1L.S. % 55%

Page 13: Analisis PU Resumen estimado REV2

P.UNIT TOTAL

450 8821,650 1,733

468 14375 23591 18

1,018 203,210 32

27217,000 1,700

935Total Neto 5,628

precio TOTAL286 229680 685680 102680 153

6 56 56 286 132

1,003 1,0531,018 203,210 32

12217,000 1,700

935Total Neto $ 5,201

P.UNIT TOTAL

600 1,176375 30

1650 1,733375 23591 18

1,018 203,210 32

30317,000 1,700

935

Page 14: Analisis PU Resumen estimado REV2

Total Neto 5,969

precio TOTAL286 229680 685680 102680 153

6 56 56 286 132

1,003 1,0531,018 203,210 32

12217,000 1,700

935Total Neto $ 5,201

Page 15: Analisis PU Resumen estimado REV2

(500-1200)UF

ALBAÑILERIA PRINCESA REJILLA STANDARD, ESTUCO UNA SOLA CARA Ladrillo Hecho a Máquina Rejilla Standard 50 153 Mortero Predosificado Pega Albañilería 58 48 Reglas de Aluminio 0.002 12,800 Bateas 0.002 3,500 Fierro estríado A-63-42 H 1.05 725 Alambre Negro #18 0.011 699 Separadores Plásticos p/fierro 0.4 2 Mortero Predosificado Estuco Interior 30 41Reglas de Aluminio 0.002 14,600Bateas 0.002 3,500PERDIDAS 15% Sub Total Materiales 75%Jornal Terminaciones 0.02 14,000MO Albañilería Princesa 1 2,200 MO Fierro 1 130 MO Estuco Muro 1 2,200 Sub Total MANO DE OBRA 25%Total

Metalcon con recubrimiento de OSB Smart side Material unidad Cant/m2 Placa de yeso cartón 10mm m2 1.10 Aislación LM de 40 kg/m^3 m2 1.00 OSB Smart side 11,1mm ((1,22 X 2,44) mt) m2 1.10 Fieltro 15 Lbs m2 2.10 Esquineros un 1.10 Tornillo pta broca c/alas y autoav. kg 25.00

5 MASILLA BASE JUNTA (30kg) sac 0.07 HUINCHA ml 2.00 PERDIDAS 5% Sub Total Materiales

Estructura Montante 60CA085 Kg 3.20 Canal 62C085 Kg 0.60 PERDIDAS 5% Sub Total Materiales

Mano de obra (Carpintero + Ayudante) estructura de acero dia 0.11 Maestro + 1 AYUD revestimiento dia 0.12 LEYES SOCIALES (O.E.) % 0.55 Sub Total Mano de obra

Total

Page 16: Analisis PU Resumen estimado REV2

DESCRIPCION UNID. CANT.ESTRUCTURA DE TABIQUE 2"x 3" MADERA Placa de yeso cartón 10mm m2 1.10 Aislación LM de 40 kg/m^3 m2 1.00 OSB Smart side 11,1mm ((1,22 X 2,44) mt) m2 1.10 Fieltro 15 Lbs m2 2.10 Esquineros un 1.10 Tornillo pta broca c/alas y autoav. kg 25.00 MASILLA BASE JUNTA (30kg) sac 0.07 HUINCHA ml 2.00 PERDIDAS 10% Sub Total Materiales

Estructura Clavos 2" Kg. 0.03Clavos de 3" Kg 0.05Pino bruto de 2"x3" Plg 1.3Fisher para anclaje Uni 0.65Perdida de material % 5 PERDIDAS 10% Sub Total Estructura

Mano de obra Maestro y Ayudante Dia 0.15 Maestro + 1 AYUD revestimiento dia 0.12 LEYES SOCIALES (O.E.) % 0.55 Sub Total Mano de obra

Total

(Más de 1200)UF

ALBAÑILERIA PRINCESA REJILLA STANDARD, AMBAS CARAS Ladrillo Hecho a Máquina Rejilla Standard 50 153 Mortero Predosificado Pega Albañilería 58 48 Reglas de Aluminio 0.002 12,800 Bateas 0.002 3,500 MO Albañilería Princesa 1 2,200 Fierro estríado A-63-42 H 1.05 725 Alambre Negro #18 0.011 699 Separadores Plásticos p/fierro 0.4 2 MO Fierro 1 130 PERDIDAS 15%Mortero Predosificado Estuco Interior 60 41Reglas de Aluminio 0.004 14,600Bateas 0.004 3,500Jornal Terminaciones 0.04 14,000MO Estuco Muro 2 2,200Total

Page 17: Analisis PU Resumen estimado REV2

DESCRIPCION UNID. CANT.ESTRUCTURA DE TABIQUE 2"x4" EN PINO IMPREGNADO Placa de yeso cartón 10mm m2 1.10 Aislación LM de 40 kg/m^3 m2 1.00 OSB Smart side 11,1mm ((1,22 X 2,44) mt) m2 1.10 Fieltro 15 Lbs m2 2.10 Esquineros un 1.10 Tornillo pta broca c/alas y autoav. kg 25.00 MASILLA BASE JUNTA (30kg) sac 0.07 HUINCHA ml 2.00 PERDIDAS 10% Sub Total Materiales

Estructura Clavos 2" Kg. 0.03Clavos de 4" Kg 0.05Pino bruto de 3"x4" Plg 1.3Fisher para anclaje Uni 0.65Perdida de material % 5 PERDIDAS 10% Sub Total Estructura

Mano de obra Maestro y Ayudante Dia 0.3 Maestro + 1 AYUD revestimiento dia 0.12 LEYES SOCIALES (O.E.) % 0.55 Sub Total Mano de obra

Total

Metalcon con recubrimiento de OSB Smart side Material unidad Cant/m2 Placa de yeso cartón 10mm m2 1.10 Aislación LM de 40 kg/m^3 m2 1.00 OSB Smart side 11,1mm ((1,22 X 2,44) mt) m2 1.10 Fieltro 15 Lbs m2 2.10 Esquineros un 1.10 Tornillo pta broca c/alas y autoav. kg 25.00 MASILLA BASE JUNTA (30kg) sac 0.07 HUINCHA ml 2.00 PERDIDAS 5% Sub Total Materiales

5 Estructura Montante 90CA085 Kg 4.09 Canal 92C085 Kg 0.83 PERDIDAS 5% Sub Total Materiales

Mano de obra (Carpintero + Ayudante) estructura de acero dia 0.15 Maestro + 1 AYUD revestimiento dia 0.12

Page 18: Analisis PU Resumen estimado REV2

LEYES SOCIALES (O.E.) % 0.55 Sub Total Mano de obra

Total

MURO HORMIGON CELULARPASTA PLANCHA POLIGYP (saco 30 kg) sac 0.083BLOQUE HORMIGON CELULAR m2 8PASTA PEGAR (saco 30 kg) sac 0.083Mortero Predosificado Estuco Interior 60Reglas de Aluminio 0.002Bateas 0.002 PERDIDAS 15% Sub Total Materiales

ALBAÑIL + AYUD dia 0.1MO Estuco Muro dia 0.07LEYES SOCIALES (O.E.) % 0.55 Sub Total Mano de obra

TOTAL

Page 19: Analisis PU Resumen estimado REV2

7,650 2,774 26 7 761 8 1

1,23029

71,874

14,366.3 280

2,200 130

2,200 4,810.0 19,176

P.UNIT Precio Costo/m2 1,234.4 1,357.8 1,194 1,194 1,454 1,599 156 327 800 880 8 200 3,060 205 13 26

289 6,079

720 2,304 720 432

137 2,873

20,000 2,200 17,000 2,040

2,332 6,572

15,524

Page 20: Analisis PU Resumen estimado REV2

P.UNIT TOTAL

1,234.4 1,357.8 1,194 1,194 1,454 1,599 156 327 800 880 8 200 3,060 205 13 26

579 6,368

250 8250 13

1,080 1,40470 46

73 154 1,697

15,000 2,250 17,000 2,040

2,360 6,650

14,715

7,650 2,774 26 7 2,200 761 8 1 130

2,0332,460

5814

5604,400

23,082

Page 21: Analisis PU Resumen estimado REV2

P.UNIT TOTAL

1,234.4 1,357.8 1,194 1,194 1,454 1,599 156 327 800 880 8 200 3,060 205 13 26

579 6,368

350 11350 18

1,920 2,49670 46

128 270 2,968

15,000 4,500 17,000 2,040

3,597 10,137

19,473

P.UNIT Precio Costo/m2 1,234.4 1,357.8 1,194 1,194 1,454 1,599 156 327 800 880 8 200 3,060 205 13 26

289 6,079

720 2,945 720 598

177 3,720

20,000 3,000 17,000 2,040

Page 22: Analisis PU Resumen estimado REV2

2,772 7,812

17,610

3800 3151387 11,0964325 359

82 4,92014600 293500 7

2,509 85% 19,236

21000 2,1002200 154

1,24015% 3,494

22,729