ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to...
Transcript of ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to...
![Page 1: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/1.jpg)
MANAGING GLOBAL ADJUSTMENT, ONE PEAK AT A TIME Prepared By:
Matt Lensink, P. Eng., Chief Operating Officer
June 22, 2017
![Page 2: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/2.jpg)
Introduction/History
• Founded by Martin Lensink in early 2001
• Thermal power engineering consulting firm
• Core team of 45 people: • In 2013, core team of 12 people • In 2014, core team of 32 people
• Core value is serving customers, above all else
• Multi-Discipline Engineering Firm: • Mechanical; Electrical; Civil/Structural
![Page 3: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/3.jpg)
Core Competencies
• Cogeneration/CHP
• Energy Management
• District Energy
• Boilers
• Power Generation
• Biogas/Biomass
• Air Emissions Control
![Page 4: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/4.jpg)
GA-OEFC-NUG GA-OPG GA-IESO
Contracts administered by the Ontario Electricity Financial Corporation (OEFC) with existing generation facilities
Ontario Power Generation (OPG) nuclear and baseload hydroelectric generating stations
Contracts with the Independent Electricity System Operator (IESO) (and the former Ontario Power Authority) for new gas fired generation, renewable facilities, energy from waste and biomass, nuclear refurbishments, as well as conservation programs
What is GA? It is the difference between the Hourly Ontario Energy Price (HOEP) and..
Global Adjustment (GA) covers the cost of providing adequate generating capacity and conservation programs
![Page 5: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/5.jpg)
Energy vs. GA Breakdown
Credit: Ontario Energy Board, “Regulated Price Plan Price Report.” 2015.
![Page 6: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/6.jpg)
Is GA Consistent?
![Page 7: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/7.jpg)
Why is GA Important to You?
• CLASS “A” CUSTOMERS Pay global adjustment (GA) based on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a 12- month base period.
• In order to keep smaller businesses going in Ontario, the Ontario Government is expanding the Class A electrical consumer designation to include customers that have a peak demand of 1MW or greater during an annual base period that starts May 1st – April 30th.
• *NEW: On March 2, 2017, the Ontario government announced the threshold for North American Industry Classification System (NAICS) 31-33 customers would be further lowered to 500 kW
![Page 8: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/8.jpg)
When have GA Peaks Occurred? (2012-2016)
19,000
20,000
21,000
22,000
23,000
24,000
25,000
2012 2013 2014
Note: Years that do not contain 5 bars, indicate that the peak occurred more than once in the same month
![Page 9: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/9.jpg)
GA Curtailment Will Get Harder
Year Total # of
Participants
Introduced at 5 MWe 2010 250
Dropped to 3 MWe 2014 350-400
Dropped to 1 MWe January, 2017 1,300 – 1,400
Dropped to 0.5 MWe* April, 2017 2,000 – 2,300
* for selected NAICS Codes
![Page 10: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/10.jpg)
Who is Eligible?
• Your host Local Distribution Company (LDC) can help you: • Determines the hourly demand values for each month • Takes the highest hourly value (i.e. peak) from each month • Calculates the average of the 12 month values for the months of
May through to and including April
• 12-month average = 3.85 (3.6 + 2.8 + 2.1 + 3.2 + 4.8 + 4.6 + 4.9 + 3.8 + 4.1 + 5.1 + 3.7 + 3.5) / 12
• You also need to be classified under the North American
Industry Classification System (NAICS) as one of the following… • Mining, Quarrying, and Oil and Gas Extraction • Manufacturing • Greenhouse, Nursery, and Floriculture Production • Refrigerated Warehousing • Data Processing, Hosting and Related Services
![Page 11: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/11.jpg)
Who is Included Under NAICS 31-33 Customers?
![Page 12: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/12.jpg)
Opting into Class A
![Page 13: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/13.jpg)
How are Customers Assessed?
![Page 14: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/14.jpg)
How are Class A Customers Charged?
• Monthly GA Costs (Province Wide) x Peak Demand Factor
• $706.8M X 0.00018368= $129,825.02 (customers GA charge for March 2015)
![Page 15: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/15.jpg)
If I curb my electricity usage or eliminate these peaks entirely, what is the impact on my business? Minor Shift
![Page 16: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/16.jpg)
If I curb my electricity usage or eliminate these peaks entirely, what is the impact on my business?
Significant Shift
![Page 17: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/17.jpg)
Overall Cost Savings
Cost PDF Scenario Cost Savings
706.8 M
(March 2015)
0.00018368 No Shifting $129,825 N/A
0.00017997 Minor $127,203 $2,622
0.00015585 Significant $110,155 $19,670
0.00000000 Complete Load
Displacement $0 $129,825
![Page 18: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/18.jpg)
WHAT CAN I DO ABOUT IT?
![Page 19: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/19.jpg)
• Steel making facility in southern Ontario
• Only runs production at night
• Taking advantage of off-peak electricity rates
• Avoids Global Adjustment charges
A SOLUTION:
TIME SHIFTING
![Page 20: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/20.jpg)
• Kimberly-Clark tissue mill in Huntsville • 24/7 operation
• Curtails mill 13 times per year • Shifts preventative maintenance to ‘GA Days’
• Mill curtails 5.4 MWe of total 7.5 MWe load
• 41% reduction in annual GA Spend
A SOLUTION:
CURTAIL PRODUCTION
![Page 21: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/21.jpg)
• Campbell’s Soup plant in Etobicoke, ON • 24/7 operation
• Installed 4.5 MWe cogeneration plant • Generates electricity and heat 24/7
• Benefit from electricity savings and natural gas savings. • Over $1.8 million in annual savings
• Benefited from SaveOnEnergy incentive grant
• Hedge against policy changes
A SOLUTION:
COGENERATION
![Page 22: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/22.jpg)
• Simple cycle generation using either:
• Natural Gas
• Diesel
• Emissions control required
• Design for conversion to cogeneration in the future.
A SOLUTION:
PEAK SHAVING
![Page 23: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/23.jpg)
• Utilize energy storage for peak shaving
• Lithium ion batteries
• Compressed air
• No incremental GHGs
• Limited storage capacity for dynamic GA market
A SOLUTION:
PEAK SHAVING
![Page 24: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/24.jpg)
• Demand response & Global Adjustment
• 4 x 2800 kW Generators
• Synchronized with grid.
• Project installed by Wajax
A CASE STUDY:
PEAK SHAVING
![Page 25: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/25.jpg)
Customizing the Solution
• Grid Parallel • Synchronize with utility grid • Stable voltage and frequency
• Partitioned Connection • Separate a portion of the facility to generation
for peak hours
• Islanded Connection • Take the whole facility off of the grid for peak
hours
![Page 26: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/26.jpg)
WHAT ABOUT INCREMENTAL GHG?
![Page 27: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/27.jpg)
Biodiesel Cycle
• The carbon that is emitted by combustion of biodiesel is
recovered by plants which can be followed through the
cycle to create biodiesel again
![Page 28: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/28.jpg)
RENEWABLE NATURAL GAS
![Page 29: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/29.jpg)
WHAT NOW?
![Page 30: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/30.jpg)
GA Prediction
• Self-monitor – monitor weather, IESO data, and other metrics to self-monitor and predict peaks
• Third-party Notification Services – a third party provider can notify or dispatch for curtailment or peak shaving assets Can provide week ahead, day ahead, or
real time notification
29
![Page 31: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/31.jpg)
How Do You Opt-In?
![Page 32: ANAGING GLOBAL ADJUSTMENT NE PEAK AT A TIME · 2017. 7. 7. · on their percentage contribution to the top five peak Ontario demand hours (i.e. peak demand factor) over a ... 2014](https://reader034.fdocuments.us/reader034/viewer/2022051912/6002ab976c852d494c5914dd/html5/thumbnails/32.jpg)
QUESTIONS?? Matt Lensink, P. Eng., Chief Operating Officer
CEM Engineering, 905-935-5815, [email protected]