An overview of the salient features of ‘Value Management’ ADAM ROBERTS & JOHN HEATHCOTE – MAY 2014

Transcript of An introduction to value management: slides and recording

APM working with BT Complete

An overview of the salient features of Value ManagementADAM ROBERTS & JOHN HEATHCOTE MAY 2014

1

AGENDAIntroduction (5 min)What is Value Management? (45 min)Research experiment (20 min) Further discussion (40 min)Presentation of findings (10 min)

Introduction (Opening page)Agenda 2

INTRODUCTIONAdam Roberts -Project Manager London Underground(MAPM)Full member of the APMCommittee member of the APM VM SiGFinal year of MSc. Strategic Project Management

John Heathcote Senior Lecturer Leeds Metropolitan University(MBA / MAPM)Full member of the APMChairman of the APM VM SiG

Introduce presentersAdam Roberts - Project Manager London UndergroundFull member of the APMCommittee member of the APM VM SiGFinal year of MSc. Strategic Project Management (Leeds Met)John Heathcote (MBA) Senior Lecturer Leeds Metropolitan UniversityFull member of the APMChairman of the APM VM SiGThis presentation has been created with the purpose of stimulating some open discussion between attendees and the presenter. There are companies and government departments that sincerely believe that they are monitoring Value and continually following various Value Management processes, however if this was the case, then why are there still so many projects failing to deliver significant value.The first 40 minutes of this presentation we will discuss the history of Value Management, the various definitions of Value and what the APM say about Value Management. Then I am going to ask everyone to partake in a little experiment, which will take about 15 min; after that John Heathcote will continue with the discussion on Value Management, while I process the data from the experiment. The last 10 min; I will be sharing the findings from the experiment and I will discuss the results with you. This should bring us to around 20.30 3

THE ORIGINS OF VALUE MANAGEMENT

Value Analysis was developed for procurement by a General Electric Company employee, Lawrence D Miles, in 1947 The success throughout 92 GE departments resulted in the training of thousands of employees in the basics of Value EngineeringThe technique first came to the UK in 1957

Source: Institute of Value Management (IVM)

ORIGIN OF VM - Lawrence Miles 1947 (GE -Procurement)Value Management was developed by Lawrence Miles in the United States, while working for General Electric Company during the 1940s. This was out of the necessity to find replacement components and materials due to the shortage created by World War II. Value analysis as it was then known was recognized as a formal process in 1947 and arrived in the UK 10 years later in 1957. During the preparation of this section of the presentation I came across a video on You Tube, that had everything that I wanted to say and more; so I thought that I would play this short 10 minute clip today as it sums up both the history of Value Management and pays tribute to the father of Value Management Lawrence D Miles, who died in 1985 at the age of 81 Source: Institute for Value Management4

DEFINITION OF VALUE?

All cost is for function - Lawrence D Miles (1904 1985)

A measure of how well an organisation, project, product, or service, satisfies stakeholders objectives in relation to the resources consumed

- Source: EN1325 - 1

WHAT IS VALUE? The Value Management Vocabulary, Terms and definitions EN 1325-1 defines Value as a measure of how well an organization, project, product, or service, satisfies stakeholders objectives in relation to the resources consumedThe concept of Value is based on the relationship between satisfying needs and expectations and the resources required to achieve them, which may change both with context and time. Interpretation of value will therefore tend to vary from person to person and will be influenced by the situation and may change over time.- Source: EN-1325-1

5

WHAT IS VALUE?

V (Value) B (Benefits + Requirements) / (Cost) OGC (2010)

Value increases when the satisfaction of the customers needs augments and the expenditure of resource diminishes Source: Robert Tassinari (1995)

WHAT IS VALUE? Represented as the ratio of satisfaction of needs (OGC / EN12973)Both the OGC - 2010 publication of Management of Value and the European standard EN12 973, describes Value being represented as the ratio of satisfaction of needs, whereby: Value is proportional to Benefits over the Cost; thus if the cost is higher than the benefit then the ratio will be less than 1. - Source: OGC / EN 12 973

6

OBJECTIVE / SUBJECTIVE?

Value is Subjective OGC (MoV)Value is a Subjective term APM BoK 6th Edition

So: Is the Management of Value - Subjective or is it Objective?

WHAT IS VALUE? The EN 1325-1 defines Value as a measure of how well an organization, project, product, or service, satisfies stakeholders objectives in relation to the resources consumedThe concept of Value is based on the relationship between satisfying needs and expectations and the resources required to achieve them, which may change both with context and time. Interpretation of value will therefore tend to vary from person to person and will be influenced by the situation and may change over time.Source: EN-1325-1

Both the Office of Government Commerces 2010 publication of Management of Value and the European standard EN12 973, describes Value being represented as the ratio of satisfaction of needs, whereby: Value is proportional to Benefits over the Cost; thus if the cost is higher than the benefit then the ratio will be less than 1. Source: OGC / EN 12 973

Before I continue with this part of the presentation, I would like to ask just by way of a show of hands if you think of Value Management is a Subjective process or if you think it is an Objective Process?This question has caused for some real interesting debate in the SiG in recent months; so I was interested to see how divided this group may be?

In most cases when looking at value (and arguably all cases) we will express the value outcome in currency which would suggest that value can be measured in s and pence. (in the UK anyway) if value is measured in currency then we can expect that value can be identified and quantified with certainty; and to a certain extent accuracy. According to the OGC Value as in Portfolio, Programmes and Project Management is effectively Value for Money, which is usually reflected in measurable cost. Source: Office of Government Commerce (2010)Management of Value

The OGC, are very clear, whereby they state that Value is subjectiveThe APM BoK 6th Edition states that: Value is a subjective term and means different things to different people. However can we not specify the amount of Value (in currency) we wish to create by the implementation of a project and then objectively manage the performance of the project, resulting in managing the value outcome? (Discuss) - Then surely the management of the specified sum of money, can only be objective? (Discuss) - As it will be the projects objective to deliver the specification as set out in the requirements definition. It is the requirements that will need to specify the value outcome that the project team is required to deliver? (Discuss) - For those of you that believe that Value Management is subjective, is it possible that if you had the full set of requirements and if those requirements were extremely accurate, that you could objectively manage those requirements and in turn objectively manage the Value that the project has been commissioned to deliver? (Discuss) - Could this then raise the question between stakeholders as to how much the deliverable would be worth? (Discuss) - If all stakeholders were in agreement of the monitory value of the project deliverable then surely there is a clear quantifiable value as to the net worth of the project deliverable! Can this deliverable then be managed objectively? (Discuss)

Source:OGC (Value of Management)APM BoK 6th edition

In his book, Managing Projects for Value (2002), John Goodpasture talks about Value as being a balance of quality, resources and risk; this could be where the anomaly is introduced, as the value assigned to the quality and various risks can be subjective, which would support the consensus that value is subjective. I would say that there is a sliding scale the less the Project manager knows about the requirements that they are commissioned to deliver the more subjective the value management will be for that particular project and visa versa.It can therefore be expected that if a full set of requirements are locked down at the onset of the project, with complete approval and acceptance from all Stakeholders that the expected delivered value can by managed objectively and the more objectively that the value can be managed the higher the probability of achieving project success. (Which could open up the debate as to what is Project success?) Not NOW!Goodpasture states that Truly successful project managers understand that project exist only to promote and benefit the organisation at large Source: John C GoodpastureManaging Projects for Value

7

MANAGEMENT OF VALUE - OGC

Value = CurrencyValue as in Portfolio / Programme / Project = Value for moneyReflected in measurable cost

WHAT IS VALUE? In most cases when looking at value (and arguably all cases) we will express the value outcome in currency which would suggest that value may be measured in s and pence. (In the UK anyway) if value is measured in currency then can we not expect that value to be identified and quantified with certainty; and to extent, accuracy? According to the OGC Value as in Portfolio, Programmes and Project Management is effectively Value for Money, which is usually reflected in measurable cost. Source: Office of Government Commerce (2010)Management of Value 8

DISCUSSION

If Value is Subjective how can we make managing Value an Objective process?If the Value (in currency) is specified via a consensus of all Stakeholders, can the management of this Value be managed Objectively?Is there a risk when attempting to manage Value Subjectively?Can Value be managed both Subjectively and Objectively depending on the level of requirements definition?

WHAT IS VALUE? APM Value is a subjective term / OGC Value is subjectiveSo if Value is subjective, does it not follow that the management of value would also be subjective? (DISCUSS)However can we not specify the amount of Value (in currency) we wish to create by the implementation of a project and then manage the performance of the project objectively? Resulting in managing the value outcome? (Discuss)Then surely the management of the specified sum of money, is objective? (Discuss) It will be the projects objective to deliver the specification as set out in the requirements definition. It is the requirements that will need to specify the value outcome that the project team is required to deliver? (Discuss)For those of you that believe that Value Management is subjective, is it possible that if you had the full set of requirements and if those requirements were extremely accurate, that you could objectively manage those requirements and in turn objectively manage the Value that the project has been commissioned to deliver? (Discuss)Could this then raise the question between stakeholders as to how much the deliverable would be worth? (Discuss)If all stakeholders were in agreement of the monitory value of the project deliverable then surely there is a clear quantifiable value as to the net worth of the project deliverable! Can this deliverable then be managed objectively? (Discuss)

9

BALANCE

Value is a balance of:RiskResourcesQualityDetailed requirements Objective / Subjective process

Truly successful Project Managers understand that Projects exist only to promote and Benefit the organisation at large

- Source: John C Goodpasture (Managing projects for Value)

WHAT IS VALUE? In his book, Managing Projects for Value, John Goodpasture talks about Value as being a balance of quality, resources and risk; this could be where the anomaly is introduced, as the value assigned to risk can be subjective, which would support the consensus that value is subjective. Could this mean that there is a sliding scale the less the Project Manager knows about the requirements that they are commissioned to deliver the more subjective the Value Management will be for that particular project and visa versa.It can therefore be expected that if a full set of requirements are locked down at the onset of the project delivery, with the approval and acceptance from all Stakeholders that the expected delivered value could by managed objectively and the more objectively that the value is managed the higher the probability of achieving project success. (Which could open up the debate as to what is Project success?) Not NOW!Goodpasture states that Truly successful Project Managers understand that project exist only to promote and benefit the organisation at large Source: John C GoodpastureManaging Projects for Value 10

APM BOK 6TH EDITION

Value Management is an established, structured approach to both requirements management and solutions development. This is a consultative approach that focuses on the Value that can be generated by Stakeholder Requirements

Source: APM BoK 6th Edition

APM BoK 6th edition

Unfortunately the 6th edition of the APMs Body of Knowledge does not have a specific section for Value Management, however it is quite interweaved with the section on requirements; whereby the APM define requirements as: the process of capturing, assessing and justifying stakeholders wants and needsSource: APM BOK 6th edition

Incidentally, Jeremy Warhurst will be delivering a presentation on The Fundamentals of Requirements in London on the 10th July this year; as it can be expected that if the requirements are not correct then it will be near impossible to determine the expected outcome value.

The APM state that both requirements and Value Management is about capturing, assessing and justifying stakeholders wants and needs but is value management also about managing the Value that can be achieved from the wants and needs of the stakeholders? (Discuss)Source: APM BoK 6th edition

The APM refer to the process having four steps: Framing, Gathering, Analysing and processing.Framing the work involves establishing the high-level principles within which requirements will be managed. It will establish how functions such as stakeholder management, risk management and resource management will be integrated with requirements management to maximise value. This step also involves an early assessment of the high-level requirements by developing a Value profile that estimates the relative contribution to the Value of each requirement. Source: APM BoK 6th edition

The gathering of requirements can be done in any number of ways. It ranges from personal interviews, surveys and workshops, to focus groups, modelling and simulation. Some methodologies, including Agile approaches, are designed to enable the continuous gathering and refinement of requirements on the assumption that the stakeholders may not be sure of their needs. One of the advantages of a formal method, such as Value Management, is that it provides lessons learned that could be used to review how similar requirements may have been managed previously. Source: APM BoK 6th edition

Analysing requirements combines information from functions such as schedule management and investment appraisal with specific Value-based techniques such as function analysis and function cost analysis. The result is a thorough understanding of requirements and the Value they contribute to the overall objective. Source: APM BoK 6th edition

The process step is primarily about providing feedback to stakeholders, building consensus, and generating ideas. The results of the analysis are communicated through individual consultation or group workshops. This leads to a debate about functionality and alternative ideas. The result is a baseline set of options for functional requirements.Source: APM BoK 6th edition

11

FRAMING

Establishing high level principles Establishes function integration to maximise ValueDevelop Value profileRelative contribution to the Value of each requirement

Source: APM BoK 6th Edition

Framing the work involves establishing the high-level principles within which requirements will be managed. It will establish how functions such as stakeholder management, risk management and resource management will be integrated with requirements management to maximise value. This step also involves an early assessment of the high-level requirements by developing a Value profile that estimates the relative contribution to the Value of each requirement. - Source: APM BoK 6th edition

12

GATHERING

Focus groups, personal interviews, surveys, etc.Agile methodology continuous gathering Value Management includes Lessons Learned

Source: APM BoK 6th Edition

The gathering of requirements can be done in any number of ways. It ranges from personal interviews, surveys and workshops, to focus groups, modelling and simulation. Some methodologies, including Agile approaches, are designed to enable the continuous gathering and refinement of requirements on the assumption that the stakeholders may not be sure of their needs. One of the advantages of a formal method, such as Value Management, is that it provides lessons learned that could be used to review how similar requirements may have been managed previously. - Source: APM BoK 6th edition 13

ANALYSING

Combines functions with Value based techniquesFunction AnalysisFunction Cost Analysis Understanding of RequirementsSource: APM BoK 6th Edition

Analysing requirements combines information from functions such as schedule management and investment appraisal with specific Value-based techniques such as function analysis and function cost analysis. The result is a thorough understanding of requirements and the Value they contribute to the overall objective. - Source: APM BoK 6th edition 14

PROCESSING

Provides feedback to StakeholdersBuilds consensusGenerates ideas Communicated through various methodsIndividual consultation / group workshops, etc.Leads to debateSource: APM BoK 6th Edition

The process step is primarily about providing feedback to stakeholders, building consensus, and generating ideas. The results of the analysis are communicated through individual consultation or group workshops. This leads to a debate about functionality and alternative ideas. The result is a baseline set of options for functional requirements.- Source: APM BoK 6th edition 15

WHAT IS VALUE MANAGEMENT?

Value Management is the name given to a process in which the functional benefits of a project are made explicit and appraised consistent with a Value system determined by the client

Value Management is a process and links the functional benefit with the clients expectation

Source: Kelly. J et al (2004)Value Management of Construction Projects

What is Value Management?

In the book Value Management of Construction Projects the authors define Value Management as a process and links the functional benefit with the clients expectation. This may suggest that value is subjective, but once the value criteria has been agreed and established i.e. the stakeholder requirement is clearly outlined. Could the management of that expectation possibly be objective? (DISCUSS)In this respect it can be suggested that it is imperative to have a clearly defined definition of the expected Value outcome for the project before attempting to manage the stakeholders expectations. Source: John Kelly, Steven Male & Drummond GrahamValue Management of Construction Projects

Value Management is a process and links the functional benefit with the clients expectation

16

DEFINITION OF VM- (EN 12 973)Value Management is a style of Management, particularly dedicated to motivate people, develop skills and promote synergies and innovation, with the aim of maximising the overall performance of an organisation

- Source: (EN12973)

What is Value Management?

The European Standard defines Value Management as a style of management, particularly dedicated to motivate people, develop skills and promote synergies and innovation, with the aim of maximizing the overall performance of an organization - Source: (EN12973)17

DEFINITION OF VM - IVMValue Management is a structured team based approach to identify functional requirements of Projects and / or contracts to achieve Optimum Function for Minimum Cost

Source: Institute for Value Management website

The Institute of Value Management define Value Management as a structured team based approach to identify functional requirements of projects and / or contracts to achieve Optimum Function for Minimum Cost- Source: Institute for Value Management website18

VM SIG WHITE PAPER

Value Management greatly Enhances Value for MoneyBenefits should not be accepted at any priceThere is not always a link between TCQ and benefits Value Management / Engineering techniques creates Value early in the life of a project

Source: APM VM SiG (Peter Langley)

A White Paper was produced last year by the Value Management Specific interest Group and it describes Value Management as a technique, that if used correctly and at the right time in the life of a project, it can greatly enhance the Value for money that a project can deliver. It also suggests that we should not be willing to accept benefits at any price but only benefits at a cost that makes them worthwhile, thus creating Value. (Discuss)It is suggested that there is often no linkage between the successful delivery of a product to the project managers triple constraint (Time, Cost, Quality) and the achievement of benefits. The example of Wembley Stadium is referred to regarding the fact that it was late and over budget but there is still every chance that the benefits as the national football arena will be felt for many years to come. (Discuss)The paper then suggests that Value Management and Value Engineering are techniques that can help to create value early in the life of a project? (Discuss)Source: Peter Langley & The VM SiGWhite paper (2013)

We are coming up to the end of the first part of tonights presentation; but before I finish I would like to quote a passage from the European Standard for Value Management: The EN 12 973 represents a consensus of views and provides a benchmark of good practice. It is designed to provide flexibility and can be applied in a very wide range of circumstances. It captures the essence of Value Management and provides a framework for its application. It describes a range of useful tools and encourages the selection of the most appropriate methods to achieve the desired outcome- Source: EN 12 973

19

European Standard The EN 12 973 represents a consensus of views and provides a benchmark of good practice. It is designed to provide flexibility and can be applied in a very wide range of circumstances. It captures the essence of Value Management and provides a framework for its application. It describes a range of useful tools and encourages the selection of the most appropriate methods to achieve the desired outcome

- Source: EN 12 973

A White Paper was produced last year by the Value Management Specific interest Group and it describes Value Management as a technique, that if used correctly and at the right time in the life of a project, it can greatly enhance the Value for money that a project can deliver. It also suggests that we should not be willing to accept benefits at any price but only benefits at a cost that makes them worthwhile, thus creating Value. (Discuss)It is suggested that there is often no linkage between the successful delivery of a product to the project managers triple constraint (Time, Cost, Quality) and the achievement of benefits. The example of Wembley Stadium is referred to regarding the fact that it was late and over budget but there is still every chance that the benefits as the national football arena will be felt for many years to come. (Discuss)The paper then suggests that Value Management and Value Engineering are techniques that can help to create value early in the life of a project? (Discuss)Source: Peter Langley & The VM SiGWhite paper (2013)

We are coming up to the end of the first part of tonights presentation; but before I finish I would like to quote a passage from the European Standard for Value Management: The EN 12 973 represents a consensus of views and provides a benchmark of good practice. It is designed to provide flexibility and can be applied in a very wide range of circumstances. It captures the essence of Value Management and provides a framework for its application. It describes a range of useful tools and encourages the selection of the most appropriate methods to achieve the desired outcome- Source: EN 12 973

20

WHAT VALUE MANAGEMENT IS NOT

Value Management / Engineering / Analysis is definitely NOT a cheapening process!

Reliability and performance should never be sacrificed just for the sake of cutting costs

What is Value Management?

And finally I would like to reiterate what Value analysis is NOT. Value Management / Analysis is definitely NOT a cheapening process. Reliability and performance should never be sacrificed just for the sake of cutting costs. (Discuss) 21

FINDINGSTotal No of participants:

Total Number 131: Total Number 134:

Completed 131Completed 134:

% Complete 131% Complete 134

Average time 131Average time 134

% time difference 44

2222

1315

59%68%

496 s323 s

53.6%

Findings An attempt has been made to illustrate the effect of not giving a complete set of requirements. The hand outs contained two different sets of requirements. Although very similar, half of the pages that were handed out for the purpose of this experiment contained an additional 3 words. Each page contained 100 words of instructions, informing you of the requirement, however 50% of the pages included an additional 3 words (103 words) effectively resulting in 3% additional information. The three words were read diagonally upwardsThe purpose of the experiment is to determine the percentage time difference that has resulted, in this case, by giving an additional 3% of information. The result has been To be added on completion of the presentation

22