An Bord Pleanála · Web viewIt is the use of the word “should” and the line that is used in...
-
Upload
hoangkhanh -
Category
Documents
-
view
214 -
download
1
Transcript of An Bord Pleanála · Web viewIt is the use of the word “should” and the line that is used in...
+An Bord Pleanála
Inspector’s Report
PL27.EF2016PL27.CF2002
Wicklow County Council.
Nature of Application: Approval under Section 175 and
Compulsory Purchase Order.
Location of Development: Greystones Harbour and North Beach,
Rathdown Upper and Lower.
Nature of Development: New Harbour, Marina, Residential,
Commercial, club facilities, public open
space, access and off-street car parking.
Inspector: James Carroll
PL27.EF2016/CF2002 An Bord Pleanála Page 1 of 136
INTRODUCTION
An application for approval under Section 175 of the Planning and Development Act
2000 for a public/private partnership project, at Greystones Harbour and the North
Beach Area in Greystones was the subject of a decision to seek further information by
An Bord Pleanála. This resulted from the consideration, by An Bord Pleanála, of the
proposed development, including a Compulsory Purchase Order.
Consideration of the proposal had been made by An Bord Pleanála following the
submission of the application for approval, by the public/private partners, both
Wicklow County Council and Sispar. Following the submission of objections, an
Oral Hearing was held, by the instant inspector, in March and April of 2006.
Following full consideration of the proposal, a report and recommendation, dated 11th
July 2006, was submitted to An Bord Pleanála, by the instant inspector, for
consideration.
An Bord Pleanála by decision of the 14th August 2006, requested the applicants,
through Wicklow County Council, to furnish the following additional information as
per Section 175(5)(a) of the Planning and Development Act, 2000.
“1. The Board is not satisfied, on the basis of the submissions made, that the issue
of the precasting yard/batching plant in relation to its design, layout and
potential sourcing of material on site from a borrow pit should be dealt with at
detailed design stage of the project having regard to potential adverse
environmental impacts of such works. Having regard to the industrial type
nature and scale of this element, required to enable the construction of the
proposed development, it is considered that the precasting yard/batching plant
should be subject to examination of its detailed design and layout, together
with detailed assessment of any material to be extracted from the site, in order
to adequately assess the potential adverse environmental impacts of such
works. Such detailed design should show distances from nearest residential
properties and detailed mitigation measures in relation to potential impacts
regarding noise, dust, light and traffic disturbance.
PL27.EF2016/CF2002 An Bord Pleanála Page 2 of 136
2. The Board might not be satisfied that the overall approach to dealing with the
old dump by redeposition of approximately 90,000 square metres of material
from one end of the site to other parts of the landfill and overall capping
would result in a satisfactory solution having regard to potential adverse
environmental impacts of such works. In this regard, the developer is
requested to consider an alternative option showing the complete removal of
landfill material from the site (preferably by sea), to be dealt with in
accordance with best modern practice, to ensure that any long-term
environmental impact is avoided. The developers’ response should also
outline the position regarding any necessary waste licences required.
3. Noting the already restricted road access to the site, the Board is not satisfied
on the basis of the submissions made that the required beach nourishment_ of
approximately 6,000 tonnes per annum cannot be brought to site by sea in
order to mitigate any potential negative traffic impacts resulting from the
proposal to bring this material by road, and consequently through the future
completed development.
4. Having regard to the design, scale, location and quantum of development
generally located at Courtyard 1, and in particular Blocks B and C and
adjacent Terrace 13 in relation to the adjacent proposed hard/landscaped realm
(traversed by essential and important roadways/vehicle routes) it is considered
that the proposed development in this location would result in significant
traffic generation and a congested form of overdevelopment in this area the
site which would seriously impinge upon any meaningful use of the space as a
public square and result in a visually intrusive and dominant form of
development in relation to its harbourside setting and existing built fabric,
including residential properties.
5. It is considered that the proposed development generally located at Courtyard
1, and in particular Blocks B and C and adjacent Terrace 13 by reason of its
design, scale and bulk fails to create an acceptable form of urban/architectural
treatment of this transitional area located between the proposed new
PL27.EF2016/CF2002 An Bord Pleanála Page 3 of 136
development and its receiving environment of generally smaller scale
Victorian seafront buildings, which include residential properties.
6. It is considered that the proposed clubhouses by reason of their design, scale,
height and location in close proximity to the site boundary and existing
residential properties (notwithstanding the difference in level between the site
and adjoining public road) would result in the visually obtrusive form of
development at this location and a form of development which might seriously
injure the visual amenities of the area and residential amenities of property in
the vicinity.
In relation to the issues raised at 4 and 5 above it is considered that Blocks B and C
and adjacent Terrace 13 should be omitted from the proposed development and the
resultant free area should form a meaningful and open/aspect harbour side public
space. Block D should consequently be redesigned to address both the enlarged
public space and Basin 1, with commercial activity on the ground floor facing the
public space. Proposed underground car parking at this location may be retained.
The redesign of the scheme should also address the issues raised at 6 above, which
may require the relocation of the club houses and ancillary facilities to an alternative
location on the overall site.
The redesign undertaken in relation to the above shall result in a reduction in the
quantum of overall development and associated traffic generation and may require
some redesign of other elements within the overall proposed development whilst
maintaining the integrity of the overall proposal. Where necessary the EIS should be
amended to reflect the modifications proposed in response to this notice.”
Following the notification of requirement for further information the developers
submitted revised proposals.
The revised proposals were notified to the objectors who, in turn, submitted
comments.
PL27.EF2016/CF2002 An Bord Pleanála Page 4 of 136
Comments were also submitted by supporters of the proposal.
Objectors to the proposal requested An Bord Pleanála to reopen the oral hearing.
These requests were acceded to.
The oral hearing was reopened on 31st March 2007 and continued on the 2nd and 3rd
April 2007 concluding on the 3rd.
A transcript of the proceedings constitutes part of PL27.EF2016 and PL27.CF2002.
BACKGROUND TO PROPOSED DEVELOPMENT
The background to the proposal initially submitted to An Bord Pleanála is contained
in the Inspector’s report of 11th July 2006 (pages 5 and 6).
The legal procedures are referred to in Pages 6 and 7.
Site location and description are described in Pages 7 to 13. The overall development
is referred to in Pages 13 to 28.
The initial report refers briefly to the Environmental Impact Statement on Pages 28
and 29.
Pages 29 and 30 refer to the Compulsory Purchase Order.
Pages 31/33 refer to objections to the proposal.
The bulk of the report is taken up with the oral hearing constituting Pages 31 to 182.
Finally the assessment and recommendation cover Pages 182 to 239. A 21 page
appendix is also included, which outlines the planning context current at the time the
proposal was being considered by An Bord Pleanála.
PL27.EF2016/CF2002 An Bord Pleanála Page 5 of 136
REVISED PROPOSALS
Following the request for further information, amendments to the proposal were made
by the developers. These amendments are outlined in Volume 2 of the additional
information submitted by McCabe Durney to An Bord Pleanála on 25/10/2006. The
main outlines of the revisions are as follows:
Blocks B and C and the adjacent Terrace 13, included in the original development,
have been omitted. The resultant freed area has been incorporated into an enlarged
harbour side public open space.
Block D and Basin 1 are retained. Block D has been redesigned to address the
increased area of public open space to the south and the water and buildings
surrounding Basin No. 1. Underground car parking has been retained at the location.
The clubhouse facilities have been redesigned as a largely single-storey structure. The
sailing club however retains a two-storey element. The overall buildings have been
located to the most easterly location within the inner dock structure of the existing
harbour. This repositioning moves the structures away from the site boundary and the
residential properties on Cliff Road/Bayswater Terrace.
Minor amendments to the overall proposed development have been included however
the integrity of the design proposal is maintained as originally intended in the urban
masterplan for the development.
Details of the redesigned proposal are referred to below.
INCREASED AREA OF PUBLIC OPEN SPACE
The creation of a public open space framed by the old and new development was
considered by the developers to redefine and restructure the public realm. As a result
the public square is designed to accommodate day to day activities and also future
special events such as cultural and arts events.
PL27.EF2016/CF2002 An Bord Pleanála Page 6 of 136
A new masterplan for the public open space was therefore proposed.
The enlarged public square seeks to provide a strong link between Victoria Road and
the new harbour. It is the introduction gateway to the development as outlined by the
developers. It consists of mainly hard surfaces however there is an element, in the
northern sector, of soft landscaping. The hard landscaping consists of a combination
of granite flags and setts with street furniture.
The soft landscaped areas are located to the south west of proposed Block D. Also
included in the proposal is extensive tree planting intended to frame views of spaces
and provide vertical intervention.
Immediately to the south of Block D an open café square is proposed.
Block D.
This has been redesigned in response to the request for further information.
A three-storey building is proposed at the southern elevation with two floors of
residential above ground floor commercial. There is a considerable element, at the
upper levels of balconies, large windows, screens and terraces.
The developers consider that the smaller scale of Block D recognises the existing
smaller scale of the Victorian seafront buildings.
The Clubhouses.
While the clubhouses have been redesigned they have generally not been relocated
within the overall site. In this regard they are located in the south-eastern corner of
the overall site.
PL27.EF2016/CF2002 An Bord Pleanála Page 7 of 136
While the additional information indicates that alternative locations outside of the
harbour area were examined an overriding _ requirement of each of the clubs is to be
adjacent to facilities which allow for safe access to launch facilities and supervision of
Maritime activities.
A further alternative examined by the developers was in relocating a number of the
clubhouses throughout the harbour side area in the public space. This enables the
clubs to stay within the harbour. The developers consider that there would be a
drawback as clubs would be located away from the launching beach and slipway. It
will also involve members crossing through the new public square and the pedestrian
promenade to access launching facilities. Supervision would also be compromised.
The overall impact of dispersal of the clubhouses throughout the public realm in the
harbour area would, in the opinion of the developers, interrupt and hinder the
potential of the use of the new enlarged harbour side public space. Private buildings
and ancillary areas would be located within a public area giving rise to conflicts of
privacy, security and supervision.
The proposal submitted is a redesign and relocation of the clubhouses into a largely
single-storey complex of buildings directly to the south of the new southern
breakwater.
The developers consider that the revised location moves the entire buildings out of
potential views to and from Cliff Road and Bayswater Terrace. It would also have the
effect of moving buildings away from existing residential accommodation on Cliff
Road. It takes advantage of the difference in levels between Cliff Road and the
harbour area. This difference in levels is approximately 4 metres.
The sailing club, which would be the only two-storey element, would be located at the
most eastward point. It would also be aligned with the two-storey coastguard
building. It would not impact on potential views northwards from Cliff Road towards
Bray Head.
The other clubhouses are organised in a single-storey structure around a shared central
courtyard.
PL27.EF2016/CF2002 An Bord Pleanála Page 8 of 136
There would be extensive areas of off-street car parking and for boat and equipment
storage. The storage areas would be located to the west of the clubhouses.
Plans, elevations, sections and perspectives and photomontages of the revised
arrangements constitute part of the submission.
Vehicular Access to the Site.
The access arrangements to the site from Beach Road/Victoria Road have been
amended. Two access points are proposed. The eastern access point is into the off-
street car parking area serving the proposed clubhouses.
The western access is to the main area of the site and is in the approximate position of
the original single access proposed to the site.
The developers consider that the revised access arrangements are provided to address
the concerns of An Bord Pleanála in relation to significant traffic generation and a
congested form of overdevelopment of the southern end of the site at the proposed
public square.
The proposal is to split the access configuration into the proposed development with
the harbour and club areas served by the eastern access and the remainder of the site
by the western access. There is a separation distance of the order of 70 metres
between both access points.
The developers consider that separating these functions removes the potential
conflicts in traffic terms. It also removes potential congestion when both functions are
in use.It separates the traffic movements from the overall site from the enlarged public
open space area and the harbour.
The developers consider the new arrangement as viable and meaningful use of the
public open space including the boardwalk.
PL27.EF2016/CF2002 An Bord Pleanála Page 9 of 136
Quantum of Development.
The revised proposals reduce the overall scale of the development.
In terms of residential provision a total of 34 residential units have been removed.
This consists of 12 one-bed apartments, 9 two-bed apartments, 7 three-bed apartments
6 three-bedroom houses.
It was originally proposed to provide 375 residential units.The total now proposed is
341, a reduction of 9%..
Commercial Development.
The revision proposed reduces the commercial floorspace by 800 square metres from
6,425 square metres approximately to 5,625 square metres approximately. This is a
reduction of approximately 12%.
The developers consider that the reduced floorspace proposed results in a reduction by
104, in the number of off-street car parking spaces required by the overall
development.
Revised Residential Accommodation.
Revisions are proposed to Block G, at the northern end of the residential
development. Similar revisions are proposed to Block J, on the southern side of Basin
2. As well as a reconfigured Block D, at the southern end of the overall
residential/commercial development, a small revision is proposed to Terrace No. 1.
Buildings G and J are provided with additional accommodation at the third floor.
Proposed Batching Plant and Precasting Yard.
PL27.EF2016/CF2002 An Bord Pleanála Page 10 of 136
This aspect of the proposal was the subject of Item No. 1 of additional information
sought by An Bord Pleanála. This resulted in the submission of considerable detail in
relation to this aspect of the proposal and in particular dealt with noise, dust, light and
traffic disturbance, as required by the additional information request. The main
emphasis of the submission is the detailed assessment, by the developers, that this
element of the overall proposal can be implemented in a manner consistent with best
environmental practice and without material impact upon the residential amenities of
the area.
Old Dump.
The estimated volume of material in the old dump is approximately 90,000 cubic
metres.
The original proposal was that the southern end of the dump, consisting of
approximately 9,000 cubic metres be relocated to the northern end, which is
immediately to the north of the existing landfill. It was also proposed that 20,000
cubic metres, at the eastern extremity be reworked to provide a stable cliff edge along
the beach line where it is proposed to provide a public park.
Four options were examined in relation to the dump. The first consisted of retention
of the landfilled material on the site. The second constituted disposal of excavated
landfill material off-site. The third consisted of the removal of all landfilled material
off-site. The fourth consists of leaving the entire dump area as it is.
In relation to the first retention of all material on site, the developers consider that
based on best practicable environmental option and the proximity principle, keeping
all of the material on site is the preferred option. There are a number of precedents at
the Dublin Port Tunnel, the N11 Interchange at Greystones/Delgany (Bromley) and in
the Deansgrange area of Dublin (Pfizer Factory Pottery Road).
This involves capping all of the landfill including the 9,000cubic metres which would
require relocation on site.
PL27.EF2016/CF2002 An Bord Pleanála Page 11 of 136
The second option is the same as the first apart from the 9,000 cubic metres would be
moved off-site to a suitable facility. This would result in considerable truck
movements with excavated material being removed off-site and the importation of
suitable fill materials. This could give rise to almost 6,000 truck movements.
Exporting and importing material by sea would require a temporary berthing facility
which would require the building of a significant structure extending into deep water
to provide for barges to collect and supply material from a vertical quay wall
structure. A piled steel jetty would not work due to exposed sea conditions.
The third option would be to remove all of the landfill material off-site. No landfill
material is replaced within the site with this option. All excavated material is removed
off-site to a suitable facility. 90,000 cubic metres of imported fill would be required
to construct the landscaped public park. This would require up to 18,000 truck
movements. The disadvantages in relation to Option No. 2 with the removal and the
importation of material by sea would also result. There could be additional
difficulties in finding a suitable receiving facility with capacity to handle all of the
excavated material. The proposal also contravenes the proximity principle which
states that if local facilities are suitable they should be utilised instead of exporting
material.
The final alternative would be to leave the landfill as existing. This however would
result in a number of houses being located on top of the southern end of the old
landfill. This is unacceptable. There would also be a visual impact in relation to
locating the houses on top of a landfill as the landfill currently stands proud of much
of the surrounding landscape. This would create potentially significant visual impact
and overlooking issues.
The developers’ preferred option is to retain materials on site, with localised
relocation of a section of the material being the preferred option.
In correspondence with the Environmental Protection Agency, the developers
consider that retaining all landfill on site and relocating some of it, as proposed, is the
preferred option.
PL27.EF2016/CF2002 An Bord Pleanála Page 12 of 136
Beach Nourishment.
Beach nourishment constituted Item 3 of the further information sought by An Bord
Pleanála.
The developers consider that beach nourishment is the most appropriate and
sustainable method by which future coastal erosion can be managed between the site
and Bray Head. Material is required to be placed above high tide level up to the cliff
toe. It is proposed that along a stretch of beach 600 metres in length, material would
be spread over the area using a land based bulldozer.
The sourcing of material for beach nourishment is examined in some detail. The
conclusion is that the preferred option is the provision of material from the Codling
Bank, a number of kilometres off-shore and its use in beach nourishment. The
material would be dredged from the Codling Bank, and brought by the dredger to an
off-shore position from where material would be pumped ashore. This would
minimise impact. It would also achieve the shortest possible transport distances.
The developers have met with the Department of Communications, Marine and
Natural Resources but it is not clear as to whether or not that department would issue
a licence for extracting material from the Codling Bank.
Other options include locally sourced quarry material, being transported by road to
the site. It would also include material being transported by sea and road. Initially
the material would be transported by sea to Arklow or Wicklow Port and then
overland to the site. Types of material available at various locations were also
examined however not in great detail.
The developers consider that if the preferred option i.e. the Codling Bank is not
available, then transport by road from a local quarry, Ballyhorsey, is the preferred
option.
Environmental Impact Statement.
PL27.EF2016/CF2002 An Bord Pleanála Page 13 of 136
The Environmental Impact Statement has been amended to provide for the changes
proposed to the overall development, in the developers’ additional information
submission.
Written Submissions.
Following the submission of additional information to An Bord Pleanála, over 130
submissions have been received by An Bord Pleanála. The majority of these object to
the development resulting from the amendments proposed by the developers.
A limited number of submissions support the proposal.
While many individual objections have been submitted to the proposal a number are
based on similar grounds and constitute a common objection approach.
A number of group submissions have been lodged objecting to the development.
Written objections refer to the excessive scale and size of the development,
notwithstanding the reductions and changes proposed. Objection is still taken in
relation to traffic generation.
Objection is taken to the proposal to use an extensive part of D’Arcy’s Field as a
borrow pit, particularly having regard to new archaeological data made available,
following research on the part of the developers.
In support of the proposal reference is made to its acceptability by reason of reduction
in scale, increased public space, provision of marine clubhouse facilities and the
general overall acceptability of the development resulting from changes required as a
result of the additional information sought by An Bord Pleanála.
ORAL HEARING
PL27.EF2016/CF2002 An Bord Pleanála Page 14 of 136
In opening the oral hearing the Inspector stated that the additional information sought
by An Bord Pleanála was replied to by the developers. There was also a significant
amount of detail submitted following the developers’ additional information
submission. It was the intention of the reopened hearing to take evidence from the
developers initially, objectors subsequently and finally from supporters of the
proposal. It was not the intention to look in any detail at the substantive issues as they
had largely been gone in to previously.
For the developers Mr. D. Flanagan stated that Section 175 of the 2000 Planning and
Development Act provides the right of An Bord Pleanála to seek additional
information in relation to any matters pertaining to a proposal where, in the opinion of
An Bord Pleanála, such additional information is required to enable them to
adjudicate on the proposal.
What now currently stands before the Board is the proposed development resulting
from the request for additional information.
Item No. 1 falls into a number of categories. There is very significant and detailed
information presented in written form. Supplemental to that is other direct and
indirect impacts which have been outlined in relation to archaeological issues.
The second point, Item No. 2 relates to the old dump and the implications that this
raises in particular the removal of landfill material. It is intended that expert evidence
will set out alternatives in relation to this. Also in relation to this Wicklow County
Council has been in discussion and liasing with the Environmental Protection Agency
which has the statutory remit in relation to landfill.
Item No. 3 relates to beach nourishment and this will be referred to in some detail.
Items 4, 5 and 6 of the additional information was an invitation, by An Bord Pleanála,
to the developers, to look at the proposal in relation to locational elements, scale, and
provision of a meaningful open aspect to the overall proposals and this is replied to in
some detail and would be further supplemented during the course of the hearing.
PL27.EF2016/CF2002 An Bord Pleanála Page 15 of 136
The presentations by the developers will look at the pros and cons in terms of impact.
The developers have attempted to address the requirements of the additional
information requested by An Bord Pleanála.
For the developers Dr. I. Shanahan stated that she would deal with the environmental
effects and impacts of the concrete batching plant, the casting yard and the borrow pit.
There are two distinct activities proposed. Both are unrelated to each other. In the
first instance a concrete batching plant and an associated casting yard are proposed.
The borrow pit is unrelated to the batching plant and the casting yard.
Both of the activities proposed are temporary. The batching plant will be on site for
approximately 21 months at the start of the development. The borrow pit would be in
place for about 45 weeks. It would not be in continuous operation.
The batching plant is required as there is a significant requirement for concrete to
allow the development to proceed. Concrete will be used to construct the marina wall
and the breakwater. The casting yard would be used in connection with this.
The borrow pit would provide granular fill material for the landside reclamation. This
will result in a net reduction in imports of material onto the site. It will also provide a
repository for suitable dredge material thereby reducing exports off the site. There are
significant environmental benefits to be gained from choosing this option.
It is not intended that material from the borrow pit would be used in the concrete
batching plant.
The borrow pit is outlined in Drg. G2002 Rev A dated 16/10/2006.
The materials constituting the concrete are transported to the site, sand, gravel and
cement.
PL27.EF2016/CF2002 An Bord Pleanála Page 16 of 136
The batching plant is a temporary facility. When the need for materials does not exist,
the batching plant will be dismantled and taken away.
The borrow pit is intended to recover material for a particular purpose. It is then
intended to restore the landforms using material recovered from another location on
site. The borrow pit will not be in continuous operation for the entire duration of the
particular activity. It would be used only occasionally during the 45 week time frame.
Material will be excavated from the borrow pit and taken to be used for reclamation
on the landward the side of the marina wall. In addition there would be material
dredged from behind the marina wall and harbour and material that cannot be used for
other purposes. That material would be taken and reposited in the borrow pit.
There is a significant environmental benefit associated with the borrow pit.
Some dredged material will be reused. Some will be unsuitable for use and exported
off-site. However materials suitable for repositing in the borrow pit will restore the
landform.
Anything between 2,000 and 8,000 truck movements will not be required off-site as a
result of having the borrow pit activity on site. There is _a large varation in truck
numbers__ because until the dredging is done, the suitability of the different materials
and the nature of the materials being dredged wont be finally established. If it is
2,000 trucks then it is 6,000 truck movements that could be saved as a result of this
activity.
The driving force for choosing the borrow pit option was the environmental benefits
that can be gained from it.
The hours of operation in the batching plant will be 7 a.m. to 7 p.m. Monday to
Friday. Saturday operations will be from 7 a.m. to 5 p.m. It is not envisaged that
there would be any activity outside of these hours.
PL27.EF2016/CF2002 An Bord Pleanála Page 17 of 136
There is potential that there might be a requirement for some work to be done under
particular tidal conditions like a spring tide. This might be required to be done on
Sunday or a bank holiday however this would be a very rare occurrence. It would be
signalled well in advance to local residents.
Use of the borrow pit would be non-continuous. Operation times would be 7 a.m. to 7
p.m. Monday to Friday and 7 a.m. to 5 p.m. on Saturday.
Bringing readymix concrete onto the site would have resulted in 50% more truck
movements per hour than the option chosen.
Pre-casting blocks on the site is a very substantial activity given the 38 tonne size
blocks. Articulated transporting of such material in such bulk would be more
disruptive than the smaller vehicles associated with delivering sand and aggregate.
The wet process in the provision of concrete minimises the potential for dust emission
associated with transferring materials. This is the method chosen.
In terms of air quality, dust or particulate matter would be the main emissions.
Assessment of dust deposition predications have shown that levels of all of the
substances that could be associated with the dust generated are much lower than the
relevant air quality standards.
An air quality standard defines the acceptable level of exposure. As the assessment
showed that all of the levels would be very much slower than the air quality
standards,. it is reasonable to conclude that there won’t be any harmful effects on
health, on visibility or on residential or other amenity.
Noise impact assessment measures each individual activity and combined the impacts.
The prediction is that over a period of an hour continuous noise levels wouldn’t be
above 55 decibels. The standard for construction phase activities is 70 decibels when
expressed as an Laeq over 1 hour. The use of the batching plant, even at the nearest
PL27.EF2016/CF2002 An Bord Pleanála Page 18 of 136
residence, will produce a maximum noise level that is considerably lower than the
level which would normally be associated with and permissible for construction
activities.
The borrow pit is a non continuous activity. When operating it would add a
maximum of 3 decibels to the noise levels at the nearest residence to the site. This
calculation was carried out with the assumption that the borrow pit would always be
active and took the nearest dwellinghouse, which was 35 metres from the pit. While
this was the assumption, it is not going to happen in reality as for considerable periods
of time areas will be excavated which are at distances further away from the nearest
residences. What is given is the maximum possible impact at the closest residence to
the borrow pit. When the combined impact is considered, if the borrow pit is operated
at the same time as the batching plant, a combined impact provides 59 decibels plus 3
decibels which provides 62. The information has been deliberately presented in that
way so the combined impact is a very substantially lower one than the standard that
would apply to this type of development.
Lighting is an issue which a number of observations have dealt with. The lighting
scheme used will be the minimum required for safety and security. Lights will be
directional meaning that they will point out to sea if that is possible and downwards
whenever that is possible.
The lowest possible intensity of light consistent with safety for operation will be used.
Sensors will be used so that when required for night-time use they will be sensor
activated and then switched off.
A significant feature of the proposal is the Environmental Management Plan for the
project. The emphasis is very much on the managing of impacts and the minimisation
of impacts associated with the construction phase. The Irish Concrete Federation
Code of Practice for environmental operations would be used. A copy of this has
been submitted as part of the detailed documentation.
Sispar and Sisk are part of a consortium that have developed environmental
management plans specifically for this particular project. For any major construction
works a major works environmental plan is prepared. Quality plans as well as health
PL27.EF2016/CF2002 An Bord Pleanála Page 19 of 136
and safety plans are also drawn up. The projects are approached from the point of
view of providing a scheme of monitoring and mitigation, controlling and managing
impacts associated with developments. This also includes the provision of a senior
manager appointed as an environmental co-ordinator.
A major works programme for the proposal has been devised which provides for all
environmental impacts.
There is daily inspection for dust management and suppression measures. There is
continuous monitoring.
There is a system of daily and weekly noise measurements associated with activities.
There is a monthly audit by an independent consultant. Dr. Shanahan stated that her
company, TMS, have been commissioned to submit proposals for continued
involvement with the site to ensure that the environment plan is inspected
independently on a monthly basis.
There are 55 separate mitigation measures in place to provide proper environmental
management.
A suggestion has been made that the batching plant and casting yard should be
housed. Some small permanent batching plants, might be housed however all casting
yards known to Dr. Shanahan are external. However the critical elements in the plant
are enclosed.
There are very significant benefits in terms of traffic, traffic movements and impacts
associated with the provision of an on-site batching plant and a borrow pit.
Mr. Flanagan stated that in Appendix 6 of the submission of additional information to
An Bord Pleanála a step by step basis outlines a code of practice in relation to the
operation of the batching plant and the on-site conditions generally. The
Environmental Management Plan which is Appendix 6 goes further in many instances
than the Code of Practice.
PL27.EF2016/CF2002 An Bord Pleanála Page 20 of 136
Presenting evidence on behalf of the developers Dr. N. Brady stated that an
archaeological monitor and geophysical survey was conducted to provide additional
information to An Bord Pleanála on the archaeological potential of the D’Arcy’s Field
location.
This is where it is proposed to locate a temporary concrete batching plant and to
excavate a borrow pit to facilitate construction of the development.
The archaeological work was not required by the National Monuments Section of the
Department of the Environment, Heritage and Local Government but rather was
undertaken to ascertain the archaeological potential of D’Arcy’s Field by providing
further information to the existing desktop data from two sources.
Archaeological assessment comprising the monitoring of the site investigation of trial
pits, review of bore hole logs and the acquisition of geophysical data within D’Arcy’s
Field, was completed in September 2006. This has revealed geophysical anomalies at
the northern end of the field indicative of archaeological features and a small series of
lesser features in the central and southern parts of the field.
D’Arcy’s Field lies in Rathdown Lower, south of the known archaeological
monuments of Rathdown Castle and associated settlement and St. Crispin’s Cell.
Reference No. Wicklow 8GH Monuments 11 and 12 located in Rathdown Upper
townland.
The trial pit excavations and bore holes across D’Arcy’s Field did not reveal
archaeologically significant material. Geophysical survey comprising a resistance and
gradiometer survey conducted by Target Archaeological Geophysics identified a
series of features.
The former playing fields, on D’Arcy’s Field, were identified. A service pipeline
trench which serviced the former sewage treatment plant, at the northern end of the
field was identified. The former field boundaries, outlined in the 1840 and 1911
Ordnance Survey 6” maps were identified.
PL27.EF2016/CF2002 An Bord Pleanála Page 21 of 136
The geophysical survey highlighted three archaeological anomalies at the north end of
D’Arcy’s Field. These are gradiometery and are features A, B and C.
Feature A represents a small circular enclosure approximately 13 metres in diameter
which may have been a burial site or a house.
Feature B represents a larger enclosure ovoid in shape and truncated, measuring
approximately 50 metres by 40 metres in diameter. It may have served as a settlement
site.
Feature C lies south of Feature A and 10 metres in diameter perhaps representing a
house site.
To the south of Features A to C, a lesser series of anomalies were identified in the
middle and southern sections of D’Arcy’s Field. One of these represents a former
field boundary identified on the 1840 map while the others are less distinct and small
in scale. Their archaeological merit is unclear. They are recognised to retain a low
archaeological potential.
The archaeological mitigation arising from this work recommends that the north end
of the field be avoided by all construction works plans. A fence line will be erected
10 metres south of Feature C to ensure this.
A programme of archaeological investigation will be considered for the lesser
anomalies in the central and southern sections of the field in advance of construction
commencing. Such work would consist of machine assisted excavation of test
trenches under archaeological direction. This would be carried out under licence from
the Department of the Environment, Heritage and Local Government.
Archaeological monitoring is recommended of all ground disturbance works during
construction with the proviso to resolve fully any archaeological materials that may
be exposed at that point.
PL27.EF2016/CF2002 An Bord Pleanála Page 22 of 136
All recommendations are subject to the approval of the Department of the
Environment, Heritage and Local Government and the National Museum of Ireland
at the Department of Arts, Tourism and Transport.
Submissions made to An Bord Pleanála in relation to the archaeological aspects of the
additional information submitted to Wicklow County Council for the proposed
harbour development, were made by the Department of the Environment, Heritage
and Local Government and the Friends of Historic Rathdown.
The Department of the Environment (Development Applications Unit) reaffirmed its
overall requirements for the proper archaeological resolution of the marine aspects of
the scheme. The department also stated that it has no objection to the proposed
development for the works on D’Arcy’s Field for the batching plant/precasting yard.
This is as a result of the developer stating that the department’s previous
recommendations will be implemented. These recommendations are the fencing off
of the northern section of the field, undertaking a programme of archaeological
excavation, archaeological monitoring of all ground disturbances. The second set of
submissions was made by the Friends of Historic Rathdown stating that the
archaeological geophysical survey was conducted thoroughly and expertly and
welcomed the recommendation that the north end of D’Arcy’s Field be avoided by all
construction works. They however felt that further testing was required in the
southern part of the field to assess the lesser anomalies before a decision could be
made on the excavation of the borrow pit and the construction of the temporary
batching plant.
The intention to preserve the archaeological integrity of the Rathdown archaeological
complex is fully supported by Sispar and Wicklow County Council whose report
outlines a detailed mitigation strategy to ensure this.
Archaeological investigation will take place sufficiently in advance of the
construction programme of works to ensure that all due time is provided to resolve
potential archaeological matters before the main works programme in D’Arcy’s Field
gets underway. The developers are committed to ensuring that all archaeological
work is completed in consultation with the Department of the Environment, Heritage
and Local Government.
PL27.EF2016/CF2002 An Bord Pleanála Page 23 of 136
The proposed borrow pit will not impact upon known features of archaeological
importance in D’Arcy’s Field. The presence of archaeologically sensitive features in
the central and southern part of the field has yet to be clarified. A programme of
archaeological investigation has been recommended and will be implemented.
The Friends of Historic Rathdown submitted that the newly identified features at the
northern end of the field resulting from Sispar’s survey should be included into the
scheduled site at Rathdown. This recommendation has merit however it is a matter
for the Department of the Environment, Heritage and Local Government to decide on.
The Friends of Historic Rathdown have submitted that scheduled site protection in the
north end of D’Arcy’s Field should extend to the coastline. This recommendation has
merit but is a matter for the Department of the Environment, Heritage and Local
Government to decide upon. There is however no proposal for a haulage route or
other vehicular route along the existing cliff edge. What is proposed here is a safe
pedestrian path outside the development area along the cliff edge to maintain the
situation that exists for the general public at present.
The Friends of Historic Rathdown submitted that landscaping proposals at the north
end of D’Arcy’s Field should be avoided. This recommendation is made in the
archaeological report submitted by Dr. Brady.
The Friends of Historic Rathdown submitted that the numbers of anomalies in the
central and southern part of D’Arcy’s Field be assessed in their archaeological merit
before consideration is given to granting permission. However these anomalies have
come to light as a direct result of the initiative to conduct geophysical surveys at this
stage in the planning process. The report outlines clearly a detailed mitigation
strategy which seeks to clarify whether these features are archaeological or not and
that this process should be completed before construction works commence.
The Friends of Historic Rathdown submitted that topsoil stripping within the central
and southern sector of D’Arcy’s Field will be unacceptable. The Department of the
Environment, Heritage and Local Government is the body which decides on what
PL27.EF2016/CF2002 An Bord Pleanála Page 24 of 136
mitigation measures are undertaken. The department have already indicated that
monitoring of ground disturbance is acceptable. However that decision will be
subject to review in light of the results of the investigation phase which would clarify
whether the anomalies identified are archaeological or not.
The Friends of Historic Rathdown object to the use of D’Arcy’s Field as a public
park. The field has served as playing fields for many years.
The Friends of Historic Rathdown submitted that cliff grading works alongside
D’Arcy’s Field are inappropriate. Only works necessary for public safety are to be
carried out along the cliff edge and these works will be archaeologically monitored.
The Friends of Historic Rathdown submitted that the future of the Gap Bridge
remained unclear. Removal of the Gap Bridge is not required by the present project.
However in the interest of safety, Sispar and Wicklow County Council have offered to
take the bridge down. In the event that this work is carried out the bridge will be
archaeologically surveyed in detail before works begin and the removal works will be
archaeologically monitored. Recovered cut stone will be reused as part of the amenity
works for the proposed part.
Dr. M. Clinton the archaeological consultant of the Friends of Historic Rathdown
raised a number of additional points which Dr. Brady, commented upon as follows:
In addition to geophysical Features A, B and C in the northern end of D’Arcy’s Field
there is the possibility of a further circular anomaly located 5 metres south-east of
Feature A. This is designated A2 by Clinton who interprets it to be 6/7 metres in
diameter and may represent a burial or a hut site. Dr. Clinton proceeds to speculate
on the archaeological nature of the other anomalies located in the central and southern
sections of the field.
The feature labelled A2 by Dr. Clinton was identified in the geophysical survey as
were other features referred to by Dr. Clinton in his submission. His analysis is a
comment on what he has endorsed as a survey of the highest standard. The fact that
these anomalies were not given further status in the report is because they had not
PL27.EF2016/CF2002 An Bord Pleanála Page 25 of 136
represented more clearly defined signatures that would suggest they are
archaeologically significant.
In the case of Dr. Clinton’s Feature A2, it is a moot point since this part of D’Arcy’s
Field is to be protected against any impact from the development project. With
respect to the lesser anomalies, a programme of archaeological mitigation has been
recommended to ascertain whether or not they are of archaeological significance in
advance of construction works proceeding in this location.
Dr. Clinton’s Feature D which is not to be confused with Feature D in the geophysical
report, a field boundary, is suggested to be a souterrain or a corn/drying kiln. Either
possibility would highlight an earlier medieval period context. However as Dr.
Clinton, who is a renowned expert on souterrains in Ireland, comments “these
underground passages are markedly rare in the early historic kingdom of Leinster and
in particular of the form suggested here”.
Having regard to the fact that a service trench was located in this area and having
studied the gradiometery data, it is quite unlikely that this anomaly is archaeological
at all. It may best be determined as a localised irregularity in the backfill associated
with the 20th Century pipe trench. Nevertheless the site is to be investigated as part of
the investigation process to clarify its nature.
Dr. Clinton discussed the possibility of the ditch feature identified while monitoring
Trial Pit 5 as being a relict field boundary feature which warrants further attention.
Trial Pit 5 is located in the south-western corner of D’Arcy’s Field. It is a location
that does not show field boundaries in the first edition of the Ordnance Survey map of
1840 as correctly observed by Dr. Clinton. Nor is it on the line of the later field
boundary which enclosed the field further and was plotted on the second edition
Ordnance Survey maps of the early 1900s. Overlying the 1995 Ordnance Survey of
Ireland vertical aerial photograph shows Trial Pit 5 located within the section of waste
ground adjacent to the railway line. This may be a modern feature associated with the
rerouted railway line.
PL27.EF2016/CF2002 An Bord Pleanála Page 26 of 136
Dr. Clinton has submitted an argument in favour of hand excavation over machine
associated topsoil stripping. The machine assisted clearance is a standard practice
across Ireland. In recommending monitoring of ground disturbance activities in
D’Arcy’s Field the Department of the Environment, Heritage and Local Government
has indicated that topsoil stripping is a reasonable mitigation in the present case.
While Dr. Clinton’s suggestion has merit it is a matter for the department to decide
the most appropriate course of action.
Dr. Clinton has proposed that the protected perimeter of 10 metres south of Feature C
is extended to 25 metres in the northern section of D’Arcy’s Field. The decision in
relation to this is one which rests with the department. The department has required
the fencing off of the northern section of the field. While not commenting in further
detail in this regard the indications are that the department is in agreement with the
proposals as submitted in the archaeological report by Sispar.
The submissions by the Department of the Environment, Heritage and Local
Government do not object to the proposed development proceeding with the work in
D’Arcy’s Field. It has reaffirmed its recommendation for the maritime aspects of the
proposal.
The submission by the Friends of Historic Rathdown commends the archaeological
work commissioned by Sispar and Wicklow County Council and recognises that the
geophysical survey was of the highest standard. Concern has however been raised by
them about the process of mitigation which should follow. Clear and comprehensive
mitigation strategy has been included in the archaeological report. This is aimed at
safeguarding the known archaeological features and assessing further anomalies
whose archaeological merit is unclear. Such work is regulated and policed by the
state authorities whose statutory responsibility it is to ensure that all archaeological
work is conducted to the highest standard.
In a reply to a question from Mr. Flanagan, Dr. Brady stated that it is often the case
that the amount of information currently available to the developers, in terms of
archaeologically, does not become available until after work has commenced. In this
PL27.EF2016/CF2002 An Bord Pleanála Page 27 of 136
instance there is a significant additional input at an early stage which has led to the
information being available as a result of the investigation of D’Arcy’s Field.
For the developers Dr. B. Madden stated that at the initial oral hearing a detailed
ecological assessment was presented by him based on field surveys and a desk review.
The revised scheme raises no significant ecological issues. The site for the batching
plant and the borrow pit had been included in the original baseline survey. It has no
archaeological interest as it is largely amenity grassland. In relation to sand martins
nesting in the clay cliffs, it was concluded that loss of a section of low cliffs for
potential and future nesting by sand martins is an impact of only slight significance
because it is a relatively short stretch of cliff at the extreme southern end of the
overall cliff system.
The presence of the batching plant is unlikely to have any additional impacts on the
sand martins. The impact by nearby working machinery is unlikely to affect the birds
who readily rest in active sand and gravel quarries.
Continuing his evidence Dr. Madden stated that the proposed borrow pit and batching
plant is not expected to have any significant impact on bats as the field is presently
open grassland which offers poor foraging habitat. Bats will still be able to forage
along the cliff face and along the railway corridor.
For the developers Mr. S. Mason stated that the proposal takes account of the
underlying rationale of the proximity principle under the EU Waste Directives which
seek to minimise the movement of waste and to promote near source solutions under
the principles of best available technology and best practicable environmental options.
The Environmental Protection Agency are the statutory authority with respect to
matters relating to waste related activities. Consultations were held with the EPA
which includes the provision of the reference site investigation and analytical data of
the material in question.
PL27.EF2016/CF2002 An Bord Pleanála Page 28 of 136
The most appropriate solution remains to remove and redeposit approximately 9,000
cubic metres of material from the southern extent of the old dump and 20,000 cubic
metres approximately across the dump for landscaping purposes.
The relocated material will be monitored by an experienced environmental engineer
or scientist while being excavated, for any contamination which may pose an
environmental risk and such materials will be sampled and analysed for disposal to a
suitable disposal facility as required.
The EPA has advised that once “negligible environment risk”, is associated with the
materials which are being used in the landscaping activities this represents the best
practicable environmental option (BPEO).
Investigation by the developers has established that the risk is negligible.
All material will be capped with a layer of natural soils.
The EPA recommend that the most appropriate course of action would be for the
contractor to obtain a permit under the Waste Management Regulations 1998.
Wicklow County Council are fully aware of their responsibilities in terms of the need
for a permit under the Waste Management Permit Regulations 1998 for the proposed
works. Such a permit would be procured prior to any excavation works on the landfill
taking place.
The proposed works will transform the old dump which is unsightly and of no benefit
to local amenities into a landscaped public park. Also proposed are coastal defences
which will ensure that future erosion will not expose the fill material which is left in
situ.
While there will be short-term environmental effects such as dust and noise
generation these are not significant and will be mitigated through the construction
management plan. The overall long-term environmental effect on the site will be
positive.
PL27.EF2016/CF2002 An Bord Pleanála Page 29 of 136
The dump closed in 1976.
Due to the varied nature of the fill in the dump and the uncontrolled nature of
dumping while landfill was in operation, any excavation works should be supervised
by an environmental engineer to observe for any unforeseen contaminants within the
landfill if such hotspots were encountered they would have to be segregated and
stockpiled separately. Analysis of the material stockpiled, depending on their
composition, would be required and depending on the results these materials may
have to be removed off-site for disposal with the landfill acceptance criteria
determining whether materials could be deposited.
It is not proposed to truck material off-site unless necessary in order to minimise
trucks movements.
Truck movements at the rate of one truck per 10 cubic metres of material is a
conservative figure used by the developers.
Only inert materials will be reused on site. All excavations works will be monitored
by an environmental engineer.
The reprofiling of the site using available material is in harmony with both the
rationale of the proximity principle and best practicable environmental options. The
do minimum option will not produce as beneficial an end product and will involve the
use of imported material to carry out any necessary reprofiling, further raising ground
levels.
The old dump predated the implementation of the European Landfill Directive. The
site has undergone normal biological maturation in the intervening years since closure
therefore the EPA advise that the material presents a negligible risk. The legislation
in relation to the Landfill Directive and subsequent Irish Regulations are not therefore
applicable. In relation to the EPA Code of Practice on environmental risk
assessments for unregulated waste disposal sites, the development does not fall under
the guidance timeline as the old dump closed in 1976.
PL27.EF2016/CF2002 An Bord Pleanála Page 30 of 136
In relation to building on or near a landfill and the protection of new buildings and
occupants from landfill gas the site investigation of the old dump included
monitoring. This monitoring demonstrated that the old dump is at the end of its
biological maturation phase in which methane is produced and the available organic
load has been essentially anaerobically and aerobically digested.
This would be expected from a dump which has been closed for over 20 years. This
greatly reduces the risk of gas generation, particularly anaerobically. Exposure of any
remaining organics will lead to accelerated aerobic decomposition rather than
anaerobic.
A number of apartment blocks are proposed to be situated on an area which would
previously have been part of the old dump. This area constitutes the 9,000 cubic
metres of material to be relocated to the northern end of the landfill. Ground floor
levels will be below the base of the fill material remaining within the old dump. No
private gardens will be situated near the remaining dump as the ground between the
last block of housing will be made up of car parking spaces and the roadway. The fill
remaining in situ will be capped so as to allow any future degassing as previously
occurred on the site, ameliorating any possible lateral migration of gases.
In relation to Dutch remediation guidelines for contaminate soil, the parameters and
levels encountered on the site pose no risk. Elevated metal concentrations were
detected in a number of samples tested. This is consistent with the descriptions of the
made ground presented within the logs for the investigation locations where metals
were noted. It is not a given that the source of these metals is from deposited
material. The EPA reached the conclusion that the risk posed was negligible.
The Dutch intervention values are described generic assessment criteria. In this regard
“if the intervention values are exceeded clean-up should be considered unless a
subsequent site specific risk assessment proves otherwise”.
Since the intervention values are generic a site specific qualitative risk assessment
was carried out on the site using the principles of source/pathway/receptor. In this
PL27.EF2016/CF2002 An Bord Pleanála Page 31 of 136
case the contaminated soils were considered the source with the receptors being the
future site users. Since the main pathways for the contaminants to reach the receptors
would be through the inhalation of soils as fugitive dust and the ingestion of soils by
severing these pathways, the risks will be mitigated. This will be achieved through
the installation of a cap over the affected soils. The cap will be thick enough to allow
vegetation to grow without encountering the main ground beneath. Vegetation will
help to increase the resistance of the cap to erosion. The risk to human health has
been minimised so as to be negligible.
In relation to the proximity principle, the underlying rationale for this is that all effort
should be made to ensure the minimisation of the transport of waste. As a logical
follow-on the EPA and the Department of the Environment, Heritage and Local
Government have consistently advised that construction and demolition activity
should seek to minimise the generation of waste for external disposal and should seek
to implement design options which maximise on-site reuse. According to the
proximity principle material from the old dump would not have to be accepted by any
facility located abroad. The use of local facilities would represent a more sustainable
option.
In relation to the removal of materials by sea this has been thoroughly investigated.
While there are examples of exporting material by ship from Ireland it requires access
to a suitable quay/dock with sufficient draught to accommodate ocean going vessels.
Part of the remediation of the Sir John Rogerson's Quay gasworks site in Dublin
Docklands, used a conveyor belt system to transport soils directly from the site into
the awaiting ships. Only highly contaminated and hazardous materials were exported
in this way. This would have accounted for about 30% of all excavated soils on that
site.
Removal of soils by sea from Greystones would require transport by road to a suitable
quay/dock or alternatively construction of a substantial temporary berthing facility
with its own adverse environmental effects and potentially significant programme
effects.
PL27.EF2016/CF2002 An Bord Pleanála Page 32 of 136
In relation to protecting the dump on an eroding coastline, as indicated in the EIS and
subsequent reports, the proposed development works including the groyne to create a
sheltered beach area and the ongoing beach nourishment will lead to accretion which
is the accumulation of material along the southern section of the north beach. The
rock revetment proposed along the edge of the old dump is provided to protect the old
dump from erosion which is mainly a risk at the construction stage of the works.
In relation to beach nourishment the aim of the transport of the beach nourishment
material report was to reinvestigate different methods of transport for the beach
nourishment material including transporting by sea and by road.
The conclusion reached is that the original proposal of bringing in the material by
road is still the most viable and sustainable solution.
In relation to obtaining suitable material for beach nourishment the developers
investigated potential quarry sources including samples taken around Ireland and in
Wales. It is intended to use material which matches the current beach material as
closely as is practicable of the samples looked at. The Wicklow sample from
Ballyhorsey would be the better match.
Some replenishment work was done on Bray seafront a few years ago. The material
used there was dredged from the Codling Bank so it is pretty much the same material.
The Ballyhorsey material is suitable as beach nourishment material. There is
sufficient quantity available for the required 30 years of supply.
In relation to the availability of suitable ports for earth moving material the only
quarry on the east coast of Ireland with direct access to water is Arklow Quarry. This
is a hard rock quarry which does not contain the natural sand and gravel material
required for beach nourishment material.
Material would therefore have to be brought from an inland quarry to a loading quay
where a seagoing vessel could moor. For each quarry the most suitable loading quay
was established. This is indicated in the original submission following the request for
PL27.EF2016/CF2002 An Bord Pleanála Page 33 of 136
additional information. The road stone jetty in Arklow was considered most suitable
for the Ballyhorsey Quarry.
Placing beach nourishment material from the sea can be done with a split barge,
pontoon or a side tipping vessel. A pontoon would only be available to work in very
calm seas. This is non viable for Greystones. The other two options are viable
although the split barge may have difficulties coming close enough to the shore in
neap tides.
The side dumping vessel has been used along this coastline quite regularly. The ship
carrying beach nourishment material needs to come close enough to the shore to
ensure that the material can be retrieved by an excavator. This requires calm
conditions.
The new harbour has no quay wall long enough to take a barge. The marina is laid
out in such a way that larger boats are moored close to the entrance. Only the smaller
boats can manoeuvre into the north-west corner.
To bring a barge into the marina some of the fixed and swing moorings will have to
be removed. This will affect the capacity of the harbour and the marina. Bringing a
barge into the harbour would be physically very difficult.
The marina and harbour are public spaces which would be completely disrupted,
closed off and most likely damaged by the off-loading of beach nourishment material.
The small harbour and leisure marina are unsuitable locations for the operation of
barges, excavators and earth moving trucks. It is considered that this is not a suitable
place for such an activity.
Providing material for beach nourishment from the Codling Bank would need to be by
a suction dredger. Because the mobilisation costs of a suction dredger are very high,
it would only be viable to carry out the beach nourishment with these vessels in 5 to
10 year periods. In reply to questions from the Inspector Mr. Mason stated that this 5
to 10 year period was based on the availability of barges and on the economics of the
operation.
PL27.EF2016/CF2002 An Bord Pleanála Page 34 of 136
Mr. Mason stated that removing material from the Codling Bank was a statutory
process which would require license. It would not be practicable to do this on an
annual basis.
Suction dredgers cannot operate in shallow waters however they can spray material on
to shore from a distance.
The Bray beach nourishment was carried out with materials recovered from the
Codling Bank and pumped directly ashore by means of pipes from the suction
dredger. The suction dredger could be used for delivery of quarry material however it
is practically and economically unlikely.
In reply to a question from the Inspector, Mr. Mason stated that he had some general
details of the type of operation undertaken at Bray. It was administered by Bray
Urban District Council.
The most desirable form of transport for beach nourishment material would be
retrieval from the Codling Bank and pumping onto the beach at Greystones. This is
however completely dependent on obtaining a license from the Department of
Communications, Marine and Natural Resources. It therefore cannot be proposed or
imposed by condition in any planning permission.
In practical terms it would be most viable and sustainable to bring material in by road
from a local quarry such as Ballyhorsey. This operation would be carried out once a
year in Spring in a well organised and safe manner.
In relation to the old dump Mr. M. Boland from the Environmental Section of
Wicklow County Council stated that he had gone through the old files relating to the
Greystones dump. It has ceased operation in 1976.
Mr. Flanagan stated that while April 1976 was the official date of closure that is not to
say that there may have been unauthorised tipping on the site.
PL27.EF2016/CF2002 An Bord Pleanála Page 35 of 136
In relation to the removal of landfill material from one part of a site to another in the
case of the provision of the Port Tunnel at Fairview Park, the EPA considered that the
replacement of excavated old landfill material was the best practical environmental
option.
In reply to further questions from the Inspector, Mr. Mason stated that there was no
necessity to reimport material onto the site if the landfill was removed from the site,
unless it was the intention of the developer to replicate the existing contours on the
site resulting from the deposition of landfill material.
In reply to further questions from the Inspector in relation to the use of a new harbour
for importing beach nourishment material, Mr. Mason stated that the overall impact of
bringing material by sea for the replenishment would be a factor of the size of the
vessel. This would also dictate the number of visits. Smaller vessels than indicated by
Mr. Mason in his direct evidence could potentially be used. The developers have not
located anything, however smaller vessels might be available.
The size of vessels indicated by the developers would accommodate 500 tonnes which
would equate to approximately 250 cubic metres of material. This would result in 24
or 25 trips to provide the 6,000 tonnes required for beach nourishment.
Nourishment would be undertaken within a certain period of time in the Spring before
the beach is in use.
Mr. Mason stated that in relation to the Codling Bank there is a windfarm in the
vicinity as well as a proposal to further develop windfarms on the bank. There are
also fishing grounds.
For the developers Mr. D. McDaid stated that he presented the traffic and
transportation evidence on behalf of the developers in the oral hearing in 2006.
His evidence to the current hearing would present traffic impacts of the proposed
development modifications as well as responding to specific submissions relating to
transport.
PL27.EF2016/CF2002 An Bord Pleanála Page 36 of 136
There would be a reduction in the amount of traffic generated by the development
resulting from the reduction in the amount of developments. The number of
residential units has been reduced by 34 from 375 to 341.
There would be a reduction of between 9 and 13% in traffic generation. There would
be an associated reduction in traffic impact on the local road network. There would
be a decrease in the off-street car parking requirement of 104 spaces. The new
requirement would be 953 spaces.
The development proposes a modification to access the site off Beech Road. The
enlargement of the public square facilitates a redesign of the access into the
development. This is in response to Items 4 and 5 of the additional information
request. This relates to the elimination of any potential impact and improving the
environment for pedestrians. This is achieved by the introduction of a separate access
for the harbour, public parking and boat storage at the clubhouses. The revised layout
provides two access points, one to the main area of the site and the other to the
general harbour area.
The two accesses are approximately 70 metres apart. They would therefore operate
independently.
It is proposed to reduce the speed limit to 30 kph on Beach Road. It is also proposed
to include a change of road material treatment including raised speed tabling.
In relation to the submission on behalf of the Greystones Protection and Development
Association by Boreham Consulting Engineering Limited, queries were raised in
relation to results of the assessment of the proposed modified development and the
access arrangements.
There is no issue with reporting in the degree of saturation as opposed to the ratio of
flow to capacity arising from the use of the Pickady programme. This is the software
used in the junction assessment. There is no issue with reporting results as a degree
of saturation as they are effectively the same measurable quantity. The only real
difference is the degree of saturation is reported as a percentage while ratio flow
capacity is reported as a ratio for example 0.85 rather than 85%.
PL27.EF2016/CF2002 An Bord Pleanála Page 37 of 136
Degree of saturation is defined as the ratio flow demand to the maximum flow which
can be passed through the intersection from a particular approach.
Reference is also made to the revised harbour access junction layouts and the
proximity of the new harbour car park access to the modified Cliff Road junction with
Beach Road/Trafalgar Road. It is stated by the objectors that the proximity is
substandard with reference to the design manuals for roads and bridges (DMRB). It is
considered therefore that this will result in turning movements and traffic from both
junctions conflicting. There is also suggestion that the harbour development junction
should have right turning pockets for traffic exiting.
The design vision is to create a low speed urban pedestrian friendly environment
within and adjacent to the harbour area.
The design manual for roads and bridges (DMRB) primarily relates to the design
standards for trunk roads that is not fully or directly applicable in more urban, low
speed environments. For example the new access junctions to the proposed harbour
development have been purposely narrowed to facilitate short pedestrian crossings
rather than widened to two lanes on exit as suggested which would create an
imbalance of car dominated design.
The Traffic Management Guidelines note that “for priority junctions in an urban
context, side road junction mouths should be as compact as possible, this reduces
pedestrian crossing times, assists cyclists and discourages inappropriate vehicle
turning speeds.”
The 50 metre junction spacing suggested is not relevant in this particular instance in
an urban situation where through careful design a low speed will be achieved.
Traffic calming for new residential roads, as contained in the Traffic Management
Guidelines (Chapter 7) states that:
PL27.EF2016/CF2002 An Bord Pleanála Page 38 of 136
Drivers slow down when turning or yielding at junctions. The careful
positioning of priority junctions can assist in restraining speed along a length
of road. An acceptable spacing between adjacent junctions in a low 30 kph
speed environment is in the order of 30 metres. This is approximately what is
proposed in this instance.
The adjoining Cliff Road is effectively a one-way street off Beach Road/Trafalgar
Road. It remains two-way only for a short distance to provide access to
approximately four residential dwellings. The level of traffic therefore exiting from
Cliff Road onto Beach Road/Trafalgar Road is extremely low. The 50 metre junction
spacing reference from the design manual for roads and bridges generally relates to
stopping sight distance criteria. In this instance, there are clear open views from each
junction and on the approach to each junction to ensure good forward visibility while
driving through a traffic calmed low speed environment.
The proposals represent acceptable safe and good practice urban design principles and
will provide an enhancement to the local area.
The issue of the location of the bus stop on the northern side of Beach Road was
raised in the context of visibility from the harbour junctions. There is excellent
visibility in all directions from both harbour access junctions given the open nature of
the area. This results typically in acceptable sight distances from at least 4.5 metres
back from the stop line on the minor arms of the access junctions in question.
When occasionally buses pull into the lay-by on the northern side of Beach Road
there will remain an appropriate level of acceptable visibility from a distance of 2.4
metres back from the junction. These are acceptable for a low speed environment.
The impact of the proposed beach nourishment campaign each year is considered, by
the developers, to be negligible in terms of available road capacity.
In reply to the number of questions from the Inspector Mr. McDaid stated that the
area was effectively very much a low speed environment in that the road crossed
sections are typically narrow. At the bend in the road coming around from Trafalgar
PL27.EF2016/CF2002 An Bord Pleanála Page 39 of 136
Road to Beach Road the geometry of the road is also conducive to a low speed
environment by physically changing the appearance of the area. It is the intention to
use block paviors typical to what is inside the harbour area. This would reinforce the
feeling that it is a low speed mixed environment. The 30 kph speed area would
commence to the west of the bridge.
In clarification Mr. R. O’Hanlon stated that he was the engineer operating with
Wicklow County Council in the Greystones area office. Discussions have taken place
between the developers and the area engineers in relation to the provision of a 30 kph
speed limit as well as the provision of other speed control measures. The 30 kph
speed limit will commence between the junction of Rathdown Road, Church Road
and the bridge at Beach Road.
Mr. Flanagan stated that there would be a statutory procedure under the traffic acts to
produce a 30 kph speed limit however it is one which is supported by the County
Council generally and by the Gardai.
For the developers Mr. M. Hussey stated that he was the project architect with
O’Mahony Pike Architects. The design and amendments to the development had
been prepared jointly by O’Mahony Pike Architects, Broadway Malyan and Mitchell
Associates in a collaboration on the design of the new enlarged harbour open space.
Changes were brought about to the proposal in response to Items 4, 5 and 6 of An
Bord Pleanála’s request for additional information.
The omission of Blocks B, C and adjacent Terrace 13 and the redesign of the area
located at the southern end of the new development described as Courtyard 1 within
the original proposal allows for the creation of an enlarged harbour public space. This
would be traffic free.
Block D has been redesigned. The clubhouse buildings have also been redesigned.
The new harbour will have a meaningful use as a new public square providing
numerous public facilities and amenities including landscaped gardens, seating areas,
walkways, sculpture, place for gathering, public functions and festivals.
PL27.EF2016/CF2002 An Bord Pleanála Page 40 of 136
The new space will be free of buildings and traffic stretching from the bottom of
Trafalgar Road to the redesigned Block D on the southern edge of the new
development a distance of some 160 metres.
It is designed as a public place, accessible and permeable with an open aspect located
between the existing houses and buildings of Cliff Road, North Beach and the new
development. It is proposed to integrate the new harbour front buildings, where these
now form two edges of the new harbour side space thereby maintaining and
complementing the harbour side setting.
New traffic arrangements are included. A separate access to serve North Beach is
intended. A new access is also proposed for the coastguard, clubs and harbour uses.
These proposals prevent traffic from crossing or interfering with the use of the new
harbour side public space while removing the potential for conflict or congestion in
this location.
The creation of the new harbour side space will provide for better relationship
between the new development and the existing Victorian seafront buildings.
Building D will have a different scale and character which responds to a greater
degree to the existing buildings both on North Beach and on the harbour front.
The overall height of Building D is three-storeys. This is an attempt to respond to
Bayswater Terrace which itself is a terrace of two-storey housing.
The clubhouse redesign has reduced both the scale and height of these buildings. The
clubhouses have been reorganised and laid out in a largely single-storey structure with
the sailing club having the only two-storey element. Individual clubs are gathered
into a single building about a shared central courtyard space. A compact building
form is created which will reduce both the visual impact and physical appearance of
the clubhouse facilities.
PL27.EF2016/CF2002 An Bord Pleanála Page 41 of 136
The clubhouse building has been relocated to the most eastward location immediately
inside the new southern breakwater. The relocation of the clubhouses will remove the
buildings from the southern site boundary along Cliff Road and away from the
residential buildings.
Continuing Mr. M. Hussey stated that the redesigned clubhouses will effectively
minimise any visual intrusion and impact on visual amenity.
Other minor amendments have been made to this scheme. Some two-storey houses
have been placed beside the existing North Beach houses. Buildings G and J have
been modified.
However the alignment of the boardwalk and the continuation of the Trafalgar Road
axis northwards is maintained. The clear and legible sequence of public spaces
through the scheme is maintained through Basins 1 and 2 and the north cove square
arriving at the new public park. This sequence of space is fundamental to the original
proposals and remains within the amended scheme.
The enlarged public square at the heart of the old harbour area will greatly benefit the
town. Over time as the town expands in size and function it could become the
primary civic space and the main focus of Greystones on the new harbour front.
The new square is framed by two modern canopy structures creating the visual
enclosure between them and the existing beach house building. This frame allows for
a strong link between the existing Victorian Road and the new harbour and is
essentially the framing of an existing view. It will act as a gateway to the
development about which the roadways are directed.
Canopies are rooted into the ground on bold concrete polished piers within a
lightweight roof structure suspended above these piers. Tensile wires connected to
steel columns are used to be reflective of the Maritime structures. At night, lighting of
the soffit will further enhance the idea that the roof floats above the ground..
Tall signage columns repeat the rhythm set by the piers, signage and decoration
creating a dramatic and colourful place.
PL27.EF2016/CF2002 An Bord Pleanála Page 42 of 136
The hard landscaping will be a combination of granite flags and sets to provide a
quality robust space. The street is purposely pushed to the edges of the square to
allow maximum flexibility and use.
In contrast to the hard nature of the public square and harbour the areas between the
public square and Block D have been designed as a series of smaller interlocking
landscape spaces which will attract different users. A dramatic grass pyramid is
created at the road entrance to the residential and public park areas. In a
predominantly flat environment it was considered important to create some vertical
element marking the new development. It serves as a counter point to the hard public
square but also a signpost that this route leads north towards the public park. The
grassed areas and meadows also act as soft areas in front of the existing houses.
In front of Block D the planting lifts out from the paving level and rises into a series
of planters to enclose the café square immediately to the south of Block D. The café
square is intended for the cafes and restaurants to extend out into the outdoors to
enjoy the setting and add considerable vitality to the public realm.
The clubhouse buildings and boat storage areas are located on the most eastward
position within the masterplan. The landscape is stark, simple and robust in response.
This area will facilitate boating activity, loading and launching of boats and dinghies
and consequently the entire edge onto the shingle beach is purposely kept open and
uncluttered. Broad concrete steps drop down from the quay edge towards the beach
with slipways located on either end as the beach profile moves in response to
conditions these steps will become either more or less exposed with sand and shingle.
The paving crescent directly adjacent to the harbours edge will be dressed with
granite flags and granite sets reflective of historic quay edges. The boatyard will be
constructed in in situ cast concrete to create large flexible working areas. Public
parking is provided at two locations adjacent to the boat storage area and near the café
square. The layout allows boat users to drive down to the harbour quay and offload
trailers and equipment and then park cars within easy walking distance of activities.
Visitors to the new development or harbour side space can access parking which
PL27.EF2016/CF2002 An Bord Pleanála Page 43 of 136
overlooks the grass meadow areas. The parking courts have been designed as
possible expansion spaces to the public square if required to accommodate festivals or
other events.
Structured tree planting has been introduced to frame views or spaces creating micro-
climate by deflecting and reducing the wind to bring a vertical green element into an
otherwise hard landscaped area. The monkey puzzle tree is proposed for its
commanding silhouette and its hardiness in exposed climatic conditions.
In relation to clubhouse buildings a number of alternative locations were investigated
to redesign and relocate the clubhouses outside the harbour area and also to redesign
and relocate within the harbour area.
A fundamental requirement of each of the clubs is to be adjacent to facilities which
allow for safe access to launch facilities and the supervision of Maritime activities.
Ancillary facilities for secure training, maintenance and storage must be of a standard
to ensure viable and working community club use. Consultation with the clubs
clarified many of the requirements with specific emphasis on location and the need
for proximity to the harbour and its associated facilities.
The preferred and proposed location is the redesign and relocation of the clubhouses
into a largely single-storey complex.
The buildings are set back approximately 5 metres inside the southern breakwater,
aligned with the protective wave wall to the north of the coastguard building to
provide a degree of overtopping protection and also facilitating the provision of a
pedestrian way from Cliff Road down in to the harbour area.
Amendments to Buildings G and J include accommodation for part of the third floor.
The additions to these buildings completes the enclosure of the adjoining public space
creating a strong parapet level about the southern and northern edges and giving a
balance and symmetry to the framing of the views both out of these spaces over the
marina and seaward and also inward.
PL27.EF2016/CF2002 An Bord Pleanála Page 44 of 136
The western edge of the main access spine has been modified to provide some two-
storey houses adjacent to the existing houses along North Beach while at the same
time moving Building L so that it would still form the western edge of the retained
public space at Basin 1. These amendments retain the profile roof line along the
western side of the main access street where the three-storey buildings are located to
define public spaces or denote gateway points.
Two separate access points are proposed.
The overall development has been reduced by 34 residential units of which 12 are
one-bed apartments, 9 two-bed apartments and 7 three-bed apartments. 6 three-bed
houses have been removed also. The commercial floor areas have been reduced by
approximately 800 square metres.
Overtopping has been referred to by the Greystones Sailing Club. This does occur in
extreme conditions. It will occur along the southern breakwater. The club buildings
will also be subject to overtopping at these times however they are designed and
engineered to withstand the impacts of potential overtopping with particular attention
to the outer wall elements and roof areas of the single-storey buildings while the
upper floor structure of the sailing club along the exposed north, south and west
facades is designed against potential overtopping. It will include other protective
measures such as raised cills, reinforced glazing and protective shutters.
The view north over the harbour from the clubhouses will be somewhat restricted as a
result of the coastguard building but balcony areas at first floor level will allow for
greater oversight. The open boat storage areas are provided with a three metre fence
and controlled access.
The existing sailing club building contains approximately 190 square metres of floor
space. The proposed building is approximately 455 square metres.
The existing storage area to the sailing club is 825 square metres while the proposed
storage area extends to 1,540 square metres. Overall this constitutes in effect a
doubling of current facilities.
PL27.EF2016/CF2002 An Bord Pleanála Page 45 of 136
The redesigned scheme provides for the maintenance of views to the north and west
of the harbour and ensures that the impressive views of Bray Head to the north from
the harbour are uninterrupted. The creation of the enlarged harbourside space and the
pushing back of the building line to Block D means that views to the west and to the
Sugar Loaf are retained.
For the developers Mr. T. Durney stated that casting yards and batching plants are
normally acceptable subject to suitable precautions. They are an essential use as part
of the construction industry and An Bord Pleanála has granted permission with
conditions for many all over the country.
Greystones currently lacks a civic space of stature. The provision of the new public
square will provide this. The expansion of the population to circa 25,000 people
would bring demands for notable spaces of this nature. The town needs major
infrastructure in terms of public space. The new square would form the core setting
for what is sometimes called a social, cultural public realm which in plain English
means spaces for formal and informal public enjoyment, contact and civic
engagement.
The proposed development will increase the number of people using the space not
only because of the additional working and residential population but also because of
the harbourside commercial element, the restaurants, the shop etc., which will be
attractive for visitors.
The space in itself is unique in its character. There are no directly comparable public
spaces of this scale in Ireland leading out to a beach/harbour. It will therefore have a
strong sense of place. I think in urban design terms you are always of conscious of
trying to create that unique sense of place and undoubtedly I think this proposal
achieves that. It will represent Greystones in the public imagination by retaining the
picturesque in terms of the existing Victorian buildings, which define much of the
space, but also by demonstrating the town’s dynamism in creating new
complementary urban forms to the north. It will strongly signal both the beginning
and the end of the Greystones to Bray coastal walk.
PL27.EF2016/CF2002 An Bord Pleanála Page 46 of 136
The public square is designed for everybody. It is intended to attract the general
public including elderly, children, shoppers, café visitors and tourists as well as club
users and boating enthusiasts. It is this multiplicity of attractions drawing a wide
range of users together with the high design qualities of the space that will make it
successful.
The construction period will be reduced by 4 months as a result of the reduction in the
overall development. There will also be a reduction in the retail element, the waste
generated and the landscape impacts.
The proposed development is specifically limited in commercial floorspace to meet
neighbourhood as well as specialist visitor needs given the unique harbour side
setting. It was not intended that the proposal will compete in scale or uses with the
nearby town centre retail area or with other retail developments. The proposed
development will assist in the consolidation of the existing retailing core of
Greystones.
Any retail development in Charlesland has to justify its need in a Retail Impact
Statement. However the county manager and the planning staff of Wicklow County
Council were opposed to the rezoning of the Charlesland lands for reasons of adverse
impact.
There are no firm plans to relocate schools from the area to the east of the railway
line.
The proposal fully accords with the National Spatial Strategy and the National
Development Plan both in population and preferred residential location. The
Regional Planning Guidelines for the Greater Dublin Area envisage large growth
towns such as Greystones and Delgany as being commercial self sustaining with a
population of up to 25,000 persons. The recently adopted Local Area Plan would
allow for a population of 23,175 by 2012 assuming all zoned lands were developed
and occupied. This is highly unlikely to occur.
PL27.EF2016/CF2002 An Bord Pleanála Page 47 of 136
The Local Area Plan also allows for the development of the subject residential
element of the proposal as part of that growth.
The 2006 census of population shows that there has been a drop in the population of
Greystones from 7,315 to 7,016, or 2.9%. This is the first time that such a fall has
occurred in living memory as Greystones has been characterised by constant
population growth. It therefore reinforces the argument of the subject development as
all public planning policy documents advocate the consolidation of existing town
areas particularly those close to public transport nodes.
The proposed development will interact in a meaningful way with the Victorian town.
There will be a distinct contrast between the new development and the Victorian
character of the existing harbour development. Rather than merging the two
architectural forms there will be a distinct contrast.
The existing protected structures in the area were never directly impacted upon by the
proposed development given their separation from the development. However
separation has now increased in distance. In the case of houses along Cliff Road the
clubhouses are now 24 metres away from the nearest protected structure. The
previous figure was several metres. They also may be single-storey at a lower ground
level. The impact as previously occurred with two-storeys is in no way similar.
The protected houses on Victoria Road are now 112 metres at the nearest point from
the proposed development. They were formerly quite close at 14 metres. These
houses do not have a direct visual relationship with the proposed development given
the intervening structures.
There is no direct impact on the protected structures. In townscape terms both sets of
buildings can be seen in contrasting separate and complementary juxtaposition.
In relation to views into and out of the development, Views 1 and 2 originally
submitted were long distance views as seen from the cliff walk. The proposed
redesign does not have any impact on these views.
PL27.EF2016/CF2002 An Bord Pleanála Page 48 of 136
View 3 is an accurate description. View 4 is also a proper assessment and accurate
description.
View 6, northwards from the public coast road is an accurate representation of what is
proposed.
For the Planning Authority Ms. S. Walsh stated that the Local Area Plan was not in
place at the time of the last oral hearing. It has been referred to in a number of
submissions. While it is not strictly relevant to the issues raised in the further
information request it has been raised in submissions.
The Local Area Plan was adopted in December 2006.
The revised submission by the developers to An Bord Pleanála fully accords with the
provisions of the Local Area Plan and indeed the Action Plan for the area.
One significant change made to the Local Area Plan related to land in Charlesland
owned by a company called Zapi Developments. These lands were changed in the
Local Area Plan from employment use zoning to residential, and a mix of
employment and office use with a significant element of retail use. This was in spite
of the fact that the proposal was opposed by the Executive of Wicklow County
Council.
Although the site is 2.5 kilometres from the core retail area of Greystones it has the
potential to impact negatively on the vitality and vibrancy of the town centre.
The provision of retail accommodation at the harbour could also be impacted.
What is proposed in commercial floorspace at the harbour is intended to complement
the town centre.
The local area plan does not promote the relocation of the two existing schools from
east of the railway line to another location.
PL27.EF2016/CF2002 An Bord Pleanála Page 49 of 136
Mr. C. Hayden stated that he was President of the Greystones and District Chamber.
The Chamber supported the proposed development in particular the creation of a new
public square provided in the current proposals. This would be a major benefit to the
community and the business community alike. It has the potential to host exhibitions,
concerts and art festivals, street theatre and even possibly the National Boat Show.
The economic benefits of a facility like this are endless. Commerce will thrive in this
area of Greystones once these facilities are in place.
The proposal will also have a major benefit to tourism.
The proposal is also fully supported by the County Wicklow Chamber.
Mr. J. White stated that his submission was presented on behalf of the Greystones
Rowing Club, the Greystones Motor Yacht Club, the First Wicklow Sea Scouts
Greystones, the Greystones Ridge Angling Club, the Greystones Fishermen and the
Wicklow Aquanauts, who are based in Greystones.
This is a joint submission by regular users of the harbour and surrounding area. It is
in support of the proposed relocation and new design of the clubhouse section of the
development.
The rowing club will benefit greatly as the new facilities will mean space to store
boats indoors and the use of toilets and showers which are not available at present.
There will also be proper launching facilities.
The recently formed Greystones Motor Yacht Club welcomes the proposal which will
allow it to provide a sailing school and power boat instruction. Members of the club
intend to use the marina.
The sea scouts have been active in and around the harbour since 1908. They support
the development. At present their facilities are almost 500 metres from the water.
This results in the need to transport all equipment by trailer or by hand along a very
busy road with safety concerns.
PL27.EF2016/CF2002 An Bord Pleanála Page 50 of 136
The Greystones Ridge Angling Club is one of the main users of the harbour. The club
is in full support of the location of the club facilities currently proposed. The Wicklow
Aquanauts are based in Greystones and fully support the proposal. At present the club
does not have any facilities at the harbour.
Local fishermen support the proposal as it will have a particularly positive impact. A
number of the group keep their boats in Greystones Harbour but there is significant
difficulty with security, lack of amenities and damage to boats due to the lack of
shelter currently provided by the harbour. Catches have to be landed at Wicklow
Harbour due to the lack of access at Greystones Harbour. This would be greatly
improved if the development is carried out.
The provision of a coastguard station is also welcome.
Councillor D. Mitchell stated that he was a member of Wicklow County Council and
also Mayor or Greystones.
Moving the apartments north and using the height of the side facing the square as well
as reducing the impact of the clubhouses, has made an excellent scheme. It will
produce the best public square in Ireland, larger than Smithfield and overlooking an
excellent community harbour. It will solve 100 year old problems.
8 of the 9 town councillors have consistently supported the plan. Of the objections
about 1,700 came from Delgany which is 10% of the population.
Permission should be granted for the scheme subject to a number of minor
amendments.
The location of the clubhouses is acceptable.
It would be preferable that beach nourishment take place every 5 or 10 years from the
off-shore banks.
PL27.EF2016/CF2002 An Bord Pleanála Page 51 of 136
There have been areas where deposition of beach material has occurred, at south
beach.
While the plan protects the beach at the southern and central part of the cliffs it does
not cover the northern part. Erosion here is occurring at a fast rate. It has resulted in
closure of the cliff walk since last year. If surface water was properly channelled it
would greatly reduce the amount of erosion at the northern and central end of the
beach. A scheme of land drainage would not be particularly expensive however it
would protect the cliffs.
What is proposed is a doubling of the facilities available to Greystones Sailing Club.
This is a major improvement. The proposed sailing clubhouse would be in a prime
position in the harbour.
There should be a boat yard probably in part of the public park where people can store
boats when they are maintaining them. There is a need to place boats on shore and
work on them at any harbour.
There should be an extension of public parking at the harbour area.
For Greystones Sailing Club Mr. G. Cannon stated that he did not wish to make a
special case for the sailing club except insofar as the requirements of the club are
different to those of other organisations using the harbour.
The sailing club currently owns its own clubhouse and boat storage area.
The location of the new clubhouse is really the primary concern of the sailing club.
The location and design of the new premises is crucial to the ongoing success of the
club. The club has not been fully consulted prior to publication of the final proposals.
The plan fails to take account of the needs of the sailing club.
In the current proposal the club will be split between the clubhouse building and the
boat storage yard.
PL27.EF2016/CF2002 An Bord Pleanála Page 52 of 136
The location for the clubhouse is essentially on the sea walls. In some conditions the
club would be subjected to inundations by overtopping waves. The architects have
agreed that the buildings would have to be designed and engineered to withstand the
impacts of overtopping. This is not acceptable, appropriate nor sustainable.
The club insurers have informed them that the likelihood of overtopping would be
likely to preclude flood cover from any insurance policy taken out on the new
clubhouse. This would be a very serious matter for the club which must then be
addressed by adequate provisions being included in the design phase to safeguard the
clubhouse from flood damage.
It is important that the clubhouse and storage areas are sited adjacent to each other.
Because of the relevant locations of the sailing club and the coast yard building, the
use of the harbour entrance and the sailing area to the north of the harbour would be
severely restricted. This is a potentially serious safety issue especially for younger
and less experienced sailors.
A number of alternative locations for the clubs were examined. The sailing club were
not involved in this exercise.
A location other than that currently proposed for the sailing club would provide
uninterrupted oversight of the launch area and the harbour entrance. It would provide
a sheltered site for the clubhouse free from the overtopping that would occur in the
exposed location proposed.
If the sailing club was relocated within the harbour its presence would form a lively
and vital part of the fabric of the harbour.
The sailing club building and pen should be located together in a single location in the
heart of the harbour. The main concern is to do with the actual location of the
clubhouse building. The traditional sailing area is in front of the north beach and up to
Bray Head. This is a safe natural area. The preferred location is centrally in the public
square area. This has been referred to by Councillor Mitchell as in front of the chip
shop. That is the kind of area. It may be near the public square. However what is
PL27.EF2016/CF2002 An Bord Pleanála Page 53 of 136
proposed is a harbour development and is not a public square. It would not be out of
place.
The issue is not about the size of the clubhouse. It is more its location.
There were concerns in relation to title to the premises. The club would request
freehold of any new proposed premises. There is also concern that the club should be
able to apply for a licence to serve intoxicating liqueur to its members. There is
concern in relation to liability to value added tax and/or stamp duty with the club
moving from its existing building to a new building.
There should be insufficient storage facility available and off-street car parking for
club members.
For the Greystones Protection and Development Association Mr. J. Fox stated An
Bord Pleanála in their letter of 14th August 2006, to the developers, requesting further
information, also appear to instruct the developers in certain areas.
On the second page of the letter at Paragraph 6 it is stated:
“In relation to the issues raised in 4 and 5 above, it is considered that Blocks B
and C and adjacent Terrace 13 should be omitted from the proposed
development.”
It is the use of the word “should” and the line that is used in the sentences following
which are a concern to the Greystones Protection and Development Association. It is
not clear if the letter is seeking information or if it is instructional. It has all the
appearance of being instructional.
In reply the Inspector stated that the words “shall” and “should” are the two which
seem to give people the greatest problems in relation to interpretation. “Should”
appears to connote “maybe”. In the use of the word “shall” there is no maybe about it.
“Should” is somewhat directional. “Shall” is totally directional. Use of the word
“shall” in the letter of the 14th August 2006, may have been more appropriate.
PL27.EF2016/CF2002 An Bord Pleanála Page 54 of 136
Continuing Mr. Fox stated that the letter seeks information in accordance with Section
175(5)(a) of the Planning and Development Act 2000.
There has been little or no information furnished by the proposers as to the nature of
the contractual relationship between Sispar and Wicklow County Council, particularly
concerning the acquisition of the foreshore and the gifting of it to a developer. It is
remarkable that An Bord Pleanála has not sought this information in the letter seeking
additional information from the proposers. This is the information which the people
in Greystones and beyond would like to have, the contract and the valuation as to the
foreshore closure of rights of way.
Transparency should be available in public/private partnership arrangements. This is
a precedent acquisition of foreshore and a gift to the developer which is going to have
repercussions right across the country.
The modified proposals do not in any meaningful way address the concerns raised by
objectors.
There is no evidence that the revised development is in an way more acceptable to the
community in Greystones than the original.
The resubmitted development has failed in almost all aspects to address the concerns
of An Bord Pleanála.
For the Greystones Protection and Development Association Mr. O.Reynolds gave
evidence in relation to traffic. The revised traffic arrangements has been reviewed.
An Bord Pleanála requested that the development be redesigned to achieve a
reduction in traffic. However based on the objector’s estimates the reduction in the
overall content of development will not result in a significant reduction in traffic
generated compared with the original scheme.
In traffic engineering terms 10% is considered to represent the expected variation in
traffic conditions on a day-to-day basis. The Institution of Highways and
Transportation Guidelines for Traffic Impact Assessments states in Paragraph 3.1.3
PL27.EF2016/CF2002 An Bord Pleanála Page 55 of 136
“traffic flow on any uncongested road frequently varies by up to 10% on a
day-to-day basis. In congested conditions where flow variations are smaller it
may be difficult, if at all possible, to distinguish these variations from traffic
specifically related to new development.”
The reduction in traffic is not considered to be significant.
The amended Environmental Impact Statement does not appear to have been amended
sufficiently to reflect revised traffic conditions as exist today.
Continuing Mr. Reynolds stated that the traffic survey information on which the
original traffic impact assessment was based was obtained in 2005.
A revised traffic survey was carried out by the objectors during March 2007 to
establish current network flows. This survey confirms that the current 2007 a.m. peak
hour traffic flow on Rathdown Road is 804 vehicles per hour with the peak hour being
8.15 a.m. to 9.15 a.m. and that equates to 884 passenger car units assuming a heavy
goods vehicle content of 5%. This compares with the 485 two-way pcu volume as
used by Arup in the original EIS.
It can be concluded therefore that the original traffic volumes upon which the EIS is
based are wholly unrepresentative of existing network pre-conditions or
traffic growth in Greystones is running at 35% per annum which is doubtful.
A new Traffic Impact Assessment should have been undertaken. In relation to the
new access arrangements to the site, the design manual for roads and bridges has been
referred to. This manual governs all matters such as junction space, sight line,
stopping distance, overtaking distance etc, on public roads. There is no other
standard.
The DMRB has been adopted by the Department of the Environment and Local
Authorities throughout Ireland.
PL27.EF2016/CF2002 An Bord Pleanála Page 56 of 136
Section 7.3.2 of the County Development Plan in relation to roads, design and layout
states:
“The Council’s road requirements would be based on:
Design Manual for Roads and Bridges, Traffic Management
Guidelines and the Cycle Manual.”
The DMRB at TD41/95 sets out the sight line requirements for accesses. The
proposed development was for a 2.4 metre set back distance. This is critical. The
revised access designs do not even meet minimum road design standard in terms of
exit visibility.
Determination of the sight line requires consideration of the set back or X distance
and the Y distance measured along the road, which is in turn related to the design
speed of the major road traffic. In this case Paragraph 2.21 of DMRB requires the set
back or X distance of 4.5 metres and Paragraph 2.22 requires a Y distance of 70
metres in each direction.
Paragraph 2.21 of DMRB states:
“Normally an X of 4.5 metres shall be provided for a direct access where use
in design year is forecast not to exceed 500 AADT. A choice of set back
distance is related to the forecast traffic using the access. For lightly used
accesses, for example those serving a single dwelling or a small cul-de-sac of
a half dozen dwellings, then the set back X may be reduced to 2.4 metres.”
No flexibility is permitted in DMRB in relation to these measurements. They are
mandatory. The required access sight line is clearly 4.5 metres by 70 metres.
Both the proposed sight lines and the necessary design sight lines cross the proposed
bus lay-by.
Section 2.28 of TD41/95 states the following:
PL27.EF2016/CF2002 An Bord Pleanála Page 57 of 136
“The design organisation shall ensure that the position of lay-bys, bus stops,
traffic signs and other street furniture does not interfere with the driver’s
visibility requirements and that the obstructive effect for all road users is
minimised.”
The sight line is impeded by the bus lay-by at both access points.
The required sight line for Access 1 appears to cross third party lands which may not
be in the control of the developers. They also appear to be restricted by a building, a
toilet block.
In reply to a number of questions from the Inspector Mr. Reynolds stated that by
removing the bus lay-by and setting back all hedging etc, and by removing the toilet
block, requisite set back and visibility could be obtained.
In relation to traffic under the railway bridge it is clear that the design manual for
roads and bridges, requirement for minimum forward stopping distance is not
achievable for any vehicle type under the bridge. The minimum distance is 70 metres.
This could be relaxed to 50 metres under certain circumstances but even that is not
achievable. 35 metres is only achievable under the bridge. The forward stopping
distance is measured from the centreline of the approach lane in each direction. It is
not achievable in both directions. This will impact upon the safety of traffic but
particularly cyclists and pedestrians.
The introduction of a pedestrian guard rail may have significant adverse effects on
safety for cyclists because in the event of an accident they will not have a safe buffer
or escape zone in the form of an open footpath. Footpaths without guard rails provide
a means of escape for cyclists in the event of an accident. Cyclists can be pinned to
guard rails increasing the severity of accidents.
In urban areas the normal width of a footpath should be 1.8 metres. A minimum
clearance of 450 metres between the guard rail and the kerb edge should be
maintained as the guardrail could interfere with cyclists on the road. The proposed
PL27.EF2016/CF2002 An Bord Pleanála Page 58 of 136
development allows significantly less than 1.8 metres in the width of the footpath.
The proposed width is 1.5 metres. The provision of a pedestrian guardrail 50
millimetres thick in addition to the 450 millimetre clearance leave just 1 metre of
footway, significantly less than the recommended 1.8 metre minimum width. This
does not provide sufficient space for a wheelchair or a buggy to pass side by side in a
safe manner.
The proposal to further increase traffic under the bridge structure will result in a
significant and adverse impact upon traffic safety.
For the Greystones Protection and Development Association Professor A. Cooper
stated that his expertise was in coastal process and coastal management.
The beach sand at Greystones comes from erosion of the cliffs largely behind the
beach. These beaches are not made of clay but they are made of the mixture of clay,
sand and gravel. That material is reworked by waves to produce beach material.
Beaches are loose accumulations of sand and/or gravel which can adapt their shape to
variations in wave, tide and wind conditions, and dependent sediments supply and
type. Beaches are also bounded headlands or backed by rock of variable resistance to
erosion. A beach adjusts to the combined effects of these parameters in any given
time and achieves a dynamic equilibrium. A change in any one of the factors
affecting the beach may produce a change in the beach itself.
Construction of the harbour changes the framework within which the beach exists.
This changes the physical boundaries and alters wave dynamics and produces a
change in the beach’s shape. There is no accurate way of modelling the likely future
shape of the beach under these dramatic changes to the geological framework of the
changing dynamics.
The models used by the developer are part of the Danish Hydraulic Institute Litpack
Suite. They have been used in the EIS at Appendix 6 to predict shoreline erosion for
different marina scenarios. These are complex numerical models which aim to bring
various predictions regarding coastal dynamics, the volumes of long/shore sediment
PL27.EF2016/CF2002 An Bord Pleanála Page 59 of 136
transport and future shoreline positions under various scenarios. To make accurate
predictions of future shoreline positions and sediment transport the models have to
take account of all variables which impact on sediment transport. There are several
reasons which mean that those models cannot produce accurate simulations. Certain
important parameters have to be left out of the equation for example the packing and
density of sediment.
Not all the model parameters and their interactions are understood. The scientific
understanding of the transport of mixed grain populations such as exists on
Greystones Beach, which is a mixture of sand of gravel, are very limited.
There is a ubiquitous inability to accurately characterise the starting conditions before
a model starts to be run. This includes the grain size, wave conditions, precise beach
shape, the underlying rock depth, resistance to erosion and so on.
Some questionable relationships are used in models for example the relationship
between wave angle and long shore drift rates. The factual situation on the ground is
much more complex than models acknowledged.
Constants are frequently used to adjust model outputs to achieve reasonable
predictions. For example the range of wave theories can be selected as well as bed
roughness parameters, wind or currents can be omitted or included as the operator
chooses. This enables the operator to adjust the model result to match a target value.
The unpredictability of future wave type, weather conditions constrains ones ability to
predict into the future.
The role of extreme but infrequent storms that may strongly influence or even
dominate shoreline behaviour can either be predicted or simulated. Those type of
storms might produce more change in a few days than decades of normal or average
conditions. At Kilpatrick Beach in North Wexford, storms in early December 2006
caused more than 10 metres of erosion on a beach and dune that had been essentially
stable for the previous decade.
PL27.EF2016/CF2002 An Bord Pleanála Page 60 of 136
Using models produces a single quantitative prediction without giving any indication
of the probability such a scenario might actually occur. One can have little
confidence in such a simulation and in the case of Greystones the predicted impact of
the marina derived by modelling is therefore quite uncertain. As a consequence the
volume of material required to remedy the situation cannot be known. The volumes
cited, 6,000 cubic metre per year and an initial 30,000 cubic metres, may be much too
low or much too high. Raising the amount from 4,000 to 6,000 has been done in the
EIS to account for the inaccuracy of the model however this has no basis in reality as
the model itself has no error bands.
The practice of placing sediment on an erosion beach to replace or augment natural
sediment supply is now a widespread practice in many heavily developed coastal
areas. Because of the complexity of interactions it is not possible to accurately
predict future beach nourishment requirements or the longevity of nourished beaches.
While models are commonly used to make such predictions they suffer from several
fatal shortcomings.
Studies have shown that nourished beaches almost always last for a shorter time
period than predicted. The poor performance is explained by an unexpected storm.
There have been several instances when entire nourished beaches have been eroded
within a few days.
The potential situation whereby nourished material is washed away rapidly by a storm
is not considered in the developers report.
As a result of sea level rising climate change resulting in the likely increased instances
of storms in the Irish Sea, the volume of material required to maintain the beach
position will not remain constant but an even greater volume of material will be
required in the future. There is no commitment to providing a greater volume than
that laid out in the proposals. Any increase in volume would increase the traffic
volume and the level of disturbance on the beach.
The beach at Greystones derives it sediment from the eroding cliffs of fluvio/glacial
sediment at the rear of the beach. The particular packing arrangement is achieved.
PL27.EF2016/CF2002 An Bord Pleanála Page 61 of 136
However using material from a different source for example an inland quarry and
depositing it directly on the beach by a different mechanism, dumping from a lorry,
for use as a different packing arrangement. This will cause the beach to respond
differently to the wave processes. Nourished beaches are usually found to erode more
rapidly than their natural predecessors.
In addition no quantitative analysis of the textural characteristics of the proposed
source material and the natural beach source material has been undertaken to
determine difference. The high incidence of broken stones in the Ballyhorsey quarry
material and its angular nature, contrasts markedly with the smooth and round nature
of the present beach material.
Beach nourishment involves a high level of vehicular and mechanical activity around
and on the beach. This will have adverse impacts on plant and animal life on the
beach. This in turn will impact on the recreational value of the beach. Beach
nourishment is being proposed as an antidote to problems which will arise through
construction of the proposed marina. This is an acknowledgement that an undesirable
impact will be created and this is a proposed mechanism to reduce the impacts.
Management of adverse impact into the future is a concern.
Once humans interfere with the shoreline there is usually no going back. The first
intervention usually produces undesirable impacts which require addition as a
remedy. This in turn produces further impacts and the beach is transformed from a
natural system to an increasingly human influenced system dependant on political
decisions and economics for survival. The artificially nourished beaches of southern
Spain, backed by sea walls and defended by off-shore breakwaters, are the ultimate
expression of this urbanisation of beaches. There, the high volume of beach
dependent tourism provides an economic driver to sustain beach nourishment. No
such driver exists at Greystones.
Nourishing a beach creates an artificial addition and commitment to sustain that beach
forever. This is a major commitment for this and future generations to enter into.
PL27.EF2016/CF2002 An Bord Pleanála Page 62 of 136
In reply to a number of questions from the Inspector, Professor Cooper stated that left
to itself the coast will continue to erode. It needs to erode in order to supply the sand
that is on the beach.
With predicted rises in sea level and predicted increases of storms that rate would be
expected to increase. There is no problem for the beach as long as the material is
capable of being eroded. The waves will continue to do the erosion work and the
beach will continue to exist into the future. It is when man interrupts the supply or
changes the boundary conditions that things can go astray. Natural beach
nourishment is occurring as a result of the erosion. This has been taking place for the
last 10,000 years without any human intervention. Beaches have continued to persist
and will continue to persist into the future without any human intervention.
Building a marina changes those conditions. It accelerates the erosion process and
requires a response to try to undo the rapid changes which take place. That requires
an ongoing commitment for human intervention.
Rainfall contributes to the instability of the cliffs behind the beach. There is quite
porous material forming the cliffs. This can absorb quite a lot of water but during
heavy rainfalls there is an excess of water and that contributes to the erosional
processes. Material which is eroded augments beach material which is partly being
lost by the off-shore currents and transport off-shore.
The coast line is a very dynamic zone a very hazardous zone within which to
undertake development. Very often in the past it was felt that engineering works
might rectify impact. However such works are an open ended commitment into the
future. This begs the question as to whether such sensitive zones should be
developed.
What is proposed is a major intrusion into the natural landscape. Beaches constitute
part of the natural landscape. An alteration or further urbanisation of a beach reduces
its appeal both to locals and to visitors.
PL27.EF2016/CF2002 An Bord Pleanála Page 63 of 136
For the Greystones Protection and Development Association Mr. F. Etchingham
stated that the information in relation to the availability of beach nourishment material
from quarries was very inadequate. Some of the detail submitted is also somewhat
perplexing. For instance stockpiling is mentioned at Wicklow Port however the need
to stockpile on the quay in Wicklow has not been addressed.
Likewise the use of a barge to deliver beach nourishment material directly into the
harbour was discounted as the developers consider that it would constitute a
disruption and closing off of the harbour and would cause damage. Considerable
disruption would also be caused on the beach.
For the Greystones Protection and Development Association Mr. J. O’Sullivan stated
that he was an environmental scientist with considerable experience. His evidence
would deal with the proposal for the excavation and relocation of the town landfill.
In the letter of 14th August 2006 An Bord Pleanála expressed the concern that it might
not be satisfied that the developers overall approach for dealing with the old dump by
redepositing approximately 9,000 square metres of material on the site, might give
rise to environmental damage.
The developers response was to look at four options, retention of all landfill material
on the site, disposal of excavated landfilled material off site, removal of all landfill
material off site and leaving the dump untouched.
The developers consider the first option retention of all landfill material on site to be
preferred.
Removal of approximately 29,000 cubic metres off site was not considered to be
advisable having regard to the amount of traffic generated. The third option which
was the removal of all landfill wastes off the site was furthermore considered
unsuitable.
PL27.EF2016/CF2002 An Bord Pleanála Page 64 of 136
The fourth option was to leave the entire landfill intact. However this would require
deletion of the residential units which it is proposed to build in the location of part of
the dump.
Based on the information from Wicklow County Council there are no details of the
composition of the waste deposited in the original landfill. While the landfill may
have been closed since 1976 illegal dumping may have occurred for a number of
years subsequent to that. It may also be possible that the area is used sporadically for
fly tipping.
Dumps operated in the 1960s, 70s and 80s would have contained a variety of waste
and not only domestic refuse.
The analytical results of the testing of samples taken from the landfill indicate that
many of the samples contained levels of metals which significantly exceed the Dutch
Intervention Values. These are based on the background values for Dutch soils.
Intervention values indicate the levels of contamination of which soil contamination is
considered to be serious.
Site investigations carried out on the landfill were intended to determine the
suitability of ground conditions for construction and other land uses associated with
the proposal. They did not constitute a full environmental investigation of the site.
Nevertheless the investigations found that the composition of materials is quite
variable and included mixtures of rubble, bricks, concrete, glass, cinders and timber.
It is quite possible that very significant portions of deposited wastes were missed in
the sampling programme. As such the programme should not be relied upon as a
definitive indication of environmental condition or as an indicator of the likely
presence or absence of contaminants. There is therefore no proof that the deposited
wastes have fully degraded so as to present no environmental or health hazard. This
is a situation in which the precautionary principle should be invoked.
There are quite high levels of heavy metals within parts of the landfill. There were
also a number of chemicals present. These are materials normally associated with tar
substances which would have been dumped by local authorities following road works.
PL27.EF2016/CF2002 An Bord Pleanála Page 65 of 136
The developers contention that the soil fill material tested was found to be chemically
inert is not accepted. While the metals may be relatively immobile under the existing
conditions beneath the site mobilisation of a proportion of the heavy metal
contaminants would be likely following disturbance of fill material. There is
therefore a risk of environmental contamination if the old landfill wastes are reworked
on the site.
The recommendation in relation to this would be to leave the undisturbed landfill
wastes in place. Any wastes which have to be removed for genuine reasons should be
fully and completely exported from the site. One either removes it from the site or
leaves it in situ.
The option preferred by the developers, to move part of the material to another part of
the site, would lead to mobilisation of contaminants and would on the basis of the
information provided by the developers, create an environmental risk. Disturbance of
the old landfilled waste should be minimised. Undisturbed landfill wastes should be
left in place. Any wastes which have to be removed should be exported from the site.
The amount of waste to be removed from the site should be based on the need to
protect landfill material from coastal erosion caused by rising sea levels. If it is
accepted that sea level is rising there is a need to protect the old landfill from coastal
erosion.
In determining the amount of waste to be removed it should be based on that need and
not on the developers need to maximise the extent of residential development on the
lands available. A study should therefore be undertaken to determine how much
material could safely be left in situ, with adequate coastal protection works to prevent
exposure and erosion of the buried wastes and how much material would have to be
exported from the site.
An Bord Pleanála should also give consideration to the alternative of reducing the
land area to be occupied by housing or other buildings so as to eliminate the need to
excavate any part of the old landfill and the need to refill the void with clean material
PL27.EF2016/CF2002 An Bord Pleanála Page 66 of 136
as a foundation for construction. While the developers state that this option would
lead to a reduction in the number of residential units the extent of this reduction
should be quantified. Such a reduction would not make the overall development
uneconomic and should therefore be considered as a viable option. A reduction in the
number of residential units is a matter which An Bord Pleanála should seek to have
clarified by the developers. If such clarification is not provided they should be
considered by An Bord Pleanála as a reason for refusing permission.
The result of soil analysis described in the Environmental Engineering Assessment,
carried out by the developers, indicated that the former landfill is continuing to create
a definitive, though minor risk to groundwater in the area. Any contamination of
groundwater will be in breach of European Union Directive 80/68/EEC of 1979
relating to the protection of groundwater against pollution by certain dangerous
substances. That directive was transposed into Irish legislation by the Local
Government (Water Pollution) Regulations 1992 later amended by the Local
Government (Water Pollution) (Amendment) Regulations 1999.
The cumulative effect of the directive and the Irish Regulations is to make further
provision for the control of discharges of harmful substances to groundwater and to
prohibit the discharge of certain harmful or polluting substances to an aquifer.
An Bord Pleanála should take this legislation into account before agreeing to any of
the developers proposed options.
To minimise the long-term risk to groundwater either or all of the buried waste should
be left undisturbed or all of the waste should be removed and re-deposited in a
licensed landfill.
The European Council Directive 75/442/EEC of July 1975 on waste, was amended by
the European Council Directive 91/156/EEC. Under this Ireland was taken to the
European Court by the European Commission. In an opinion delivered by the
Advocate General (Geelhoed) in September 2004, it was stated that Ireland had failed
to fulfil its obligations as follows:
PL27.EF2016/CF2002 An Bord Pleanála Page 67 of 136
“The (European) Commission contends that by allowing a significant amount
of waste disposal and recovery operations to take place outside any permanent
framework, Ireland cannot be considered to have taken all the necessary
measures for the implementation of Article 4 of the Waste Directive because
without permits, disposal and recovery methods are not properly conditioned
and controlled. Various complaints submitted to it provide evidence of actual
environmental harm and in view of the objectives set out in Article 4 of the
Directive, waste which has been deposited contrary to the terms of the
Directive must be rendered safe, which means that it must effectively be
cleaned up. It is therefore not sufficient in this light to limit action to bringing
about a cessation of such waste operations.”
Where waste has been deposited without a proper permit system it is not sufficient
merely to stop the deposition. Such sites must effectively be cleaned up.
A waste permit from the EPA is therefore required if waste is causing or is capable of
causing pollution. While this directive does not require all landfills to be excavated
and re-deposited.. it does imply legal responsibility to ensure that any continuing or
further pollution or contamination is not caused by leaving the waste in situ or by
reworking the waste on the original disposal site.
In a letter dated 12th September 2006 from the Environmental Protection Agency to
Arup Consulting Engineers it was stated that:
“The deployment of the 29,000 cubic metres excavated material fill for
landscaping use would be considered a beneficial engineering project
(provided negligible environmental risk) and not landfilling.”
The developer than concluded that as the dump has effectively been stabilised and the
contamination is not mobile there is no environmental risk other than on-going coastal
erosion. The further conclusion of the development document is that the option to
retain the landfill material on site within the boundaries is the best practical
environmental option for the site as confirmed by the EPA. This however was a
considerable worry to the Greystones Protection and Development Association. The
PL27.EF2016/CF2002 An Bord Pleanála Page 68 of 136
Association therefore wrote to the Environmental Protection Agency in January 2007
pointing out that there would be significant environmental adverse consequences
resulting from the developers proposal to excavate and remove a portion of the
landfill.
In a response by the Environmental Protection Agency dated 2nd February 2007, it
was pointed out that the EPA has no licensing function in relation to the proposed
development in Greystones. The agency say they were consulted about a proposal to
use historical fill material, that is material waste, from one area of the landfill in the
landscaping of another area. The agency took the view that this activity would not
constitute landfilling and could be classed as a recovering operation. The agency
however pointed out that this view was based on the important caveat that:
“The pollution risks associated with the fill are negligible in the context of the
solution proposed.”
The EPA did not say that the pollution risk was reduced or mitigated they said
negligible.
The risks are not negligible. They exist. The developer cannot therefore rely on the
view of the EPA. The EPA response to the letter from the Greystones Protection and
Development Association further noted that the burden to prove that pollution risks
are negligible rests with the consultant to the developer and with An Bord Pleanála.
Therefore for this option to be considered a suitable environmental option the
developer has to show that the pollution risks are negligible and An Bord Pleanála has
to be satisfied that the pollution risks are also negligible.
If the developers proposal fails to guarantee compliance with this then any
disturbance of the deposited waste could be considered as a non-recovery activity and
would have to be classified as landfilling.
If the landfill on the site was shown to be actively accepting waste for disposal after
July 1977 it would fall into the category of sites which will be subject to proposed
legislation relating to such sites and would therefore require retrospective assessment
PL27.EF2016/CF2002 An Bord Pleanála Page 69 of 136
and authorisation. The legislation would apply regardless of the proposal for waste
reworking and relocation being proposed on the site. The legislation has not been
brought forward by the government so therefore its requirements are unknown. It is
likely that it will require a detailed assessment and characterisation of the waste
located on old landfills as a requirement in the detailed risk assessments.
It is the submission of the Greystones Protection and Development Association that
An Bord Pleanála, as the competent authority to decide on the proposed development,
should have regard to all existing legislation and court judgements. A grant of
permission for the proposal may inhibit or prevent a proper, full and detailed risk
assessment of the former landfill before anything is done on the landfill site. Such a
permission would be contrary to the European Courts judgement and to the intention
of forthcoming legislation. The European Commission judgement is in the case of
C/494/01. This was taken against the State.
The assessment and characterisation of the former landfill site undertaken by the
developer is inadequate and cannot be relied upon to show that the risk of
environmental pollution arising from the disturbance and reworking of wastes is
negligible. The Board should refuse permission for the proposed partial reworking
and relocation of the landfill wastes within the subject site.
A more appropriate solution and a better practical environmental option would be to
require removal from the site of all deposited wastes by seaborne transport, as already
suggested by the Board. Another option is to leave the deposited waste in place,
undisturbed, with adequate protection from accelerated coastal erosion caused by
rising sea levels. This option should be only considered after a detailed study has been
carried out to show that it is safe and practicable to do so and would prevent any
further or continuing pollution of soil or groundwater.
In reply to a number of questions from the Inspector, Mr. O’Sullivan stated it would
be very difficult to state whether complete removal of all landfill material or leaving it
undisturbed on-site is preferable. If the landfill is to be removed completely that
should be in total compliance with both the spirit of the European Judgement and with
PL27.EF2016/CF2002 An Bord Pleanála Page 70 of 136
the spirit of the Waste Directive. From a legal and waste management perspective that
would be the preferable thing to do.
Removal of all material from the site would result in a considerable amount of
transportation. An Bord Pleanála has suggested that this should be done by sea. In
Ireland this is normally a road transport option which is favoured. However in
Holland or Germany. the relevant authorities would think in terms of seaborne
transport.
For the Greystones Protection and Development Association, Mr. S. Fallon stated that
he was a retired Garda. While serving in the Garda Siochana he was stationed at
Greystones between 1967 and 1984. He lived at the harbour during this period and
could see the dump from where he lived. The nature of his work caused him to pay
regular visits to the dump. The purpose of the visits included searching for lost and
stolen property and engaging in regular patrols.
The dump contained large quantities of domestic refuse of all kinds as well as
considerable quantities of commercial refuse. These included car batteries, dry cell
batteries, whole cars, garden waste, food, cooked and uncooked, household chemicals,
bulbs, cosmetics, shoe polish, broken electrical equipment and kitchen appliances.
Among the commercial refuse deposited were paints, oil cans and pharmacy products.
A number of containers were also deposited.
It was common practice for locals when servicing their cars to drive to the dump and
drain the oil into the ground as well as disposing of engine parts which had been
replaced.
There was a large quantity of paint deposited on the site.
The dumping of material on the site continued up until 1984.
For the Greystones Protection and Development Association, Mr. Jim McNulty stated
that he was a planner working with the Grainne Mallon & Associates Company. The
PL27.EF2016/CF2002 An Bord Pleanála Page 71 of 136
company had been working with the Greystones Protection and Development
Association since the proposal came to light.
The additional information submitted does very little to address the issues and fears
raised in the original submission.
Permission should be refused for the proposal on the grounds that it is not in
accordance with the proper planning and sustainable development of the area and also
because of the significant negative impact on the environment which it will have.
The additional information does not meet the Board’s request for a reduction in the
quantum of the development. The commercial element has been reduced by only
12%. The number of residential units has been reduced by 9% from 375 units to 341
units.
The residential population has been reduced by 3% from 2,438 persons to 2,352
persons.
The height of the development is unchanged at four-storeys.
The size of the marina is unchanged.
The changes requested by An Bord Pleanála in the omission of Blocks B and C and
Terrace 13 appear to have been achieved through an increase in the density of the
remaining residential area.
The Greystones/Delgany Local Area Plan 2006 has a new E2 zoning which includes
provision for a district level shopping centre of 20,000 square metres and retail
warehousing of 16,000 square metres. This renders Section 3.1.3 of the amendments
to the EIS relating to economic activities, employment and population, retail impact
assessment as invalid and out of date.
The Local Area Plan also includes for the relocation of the St. David’s Secondary
School and the redevelopment of that. It also includes provision for a primary school
PL27.EF2016/CF2002 An Bord Pleanála Page 72 of 136
in the area to the east of the railway line. This will increase the amount of activity in
the area.
Ms. E. Cawley stated that she was speaking on behalf of the Greystones Protection
and Development Association. There are a number of existing and commercial
properties in the Meridian Centre which are empty. There was no need for the
amount of commercial floorspace proposed.
.
An Bord Pleanála has considered architectural style and development in general and
have referred to this in their own publications such as the Annual Report of 2004
where concern was expressed that the quality of the architectural planning proposals
was a concern in many cases.
In spite of seeking information no figures have been produced in relation to the
valuation of the foreshore. It is not known therefore what value has been put on the
foreshore. This should be available and factored into the figures relating to the public
private partnership.
For the Greystones Protection and Development Association, Mr. D. Flynn stated that
he would address issues relating to the concrete batching plant, the casting yard and
the borrow pit.
It is not clear to what depth the borrow pit would be excavated.
The storage area available for the precast blocks is considerably reduced by the lack
of availability of the area at the northern end of D’Arcy’s Field.
The large concrete blocks to be used in the breakwaters could have been cast off-site
and brought by sea to the site. This form of transport has been favoured by Irish Rail
in regard to all of the reinforcement that they have put in against the railway line
south of Greystones down to Kilcoole.
There seems to be a lack of marine engineering experience in the developers team.
PL27.EF2016/CF2002 An Bord Pleanála Page 73 of 136
Because the option of seaborne transport of materials was not properly explored the
presence of a precasting yard which has the capacity of 800 tonnes per day within 200
metres of existing housing is not justified.
The borrow pit is an effective quarrying operation. It will be less than 25metres of
existing houses.
Some 400,000 tonnes of material is needed to backfill the sea area which is being
reclaimed.
It is a moot point as to whether the backfilling of the borrow pit by dredged material
constitutes a new landfill.
. The only way that one can evaluate noise effects is to see the overlayering of all the
noise emissions sources one on top of the other.
This is something which is missing from the information presented.
A traffic survey carried out by the Greystones Protection and Development
Association found that the peak hour was between 8.15 and 9.15 in the morning.
Trucks would not be able to get through during the peak hours. There would be
difficulty during the lunch time peak hour.
During the off-peak times throughout the rest of the day traffic levels were 80% of
that peak.
Mr. F. Etchingham stated that the developers have accepted that the north and south
breakwaters will be prone to severe wave overtopping during extreme storms. They
also stated that physical model tests were commissioned, at the time of the original
oral hearing and would be completed within 3 months. That was March 2006. In
December 2006 the Greystones Protection and Development Association became
PL27.EF2016/CF2002 An Bord Pleanála Page 74 of 136
aware that the modelling had been completed. The developers had stated that the
modelling showed that the fundamental design of the harbour breakwaters are robust.
Due to the fact that the developers have stated that there will be serve wave
overtopping it would seem that the results of modelling are essential to any appraisal
of the design of the harbour. The harbour design with severe ware overtopping has
potential to be very dangerous. It is unreasonable therefore not to make this
information available to the public in particular and to An Bord Pleanála.
It is also apparently possible that there may be flooding of the public space during
severe weather conditions.
J. Sweeney, Professor of Geography at NUI Maynooth, stated in an article that “for
the east coast of Ireland, we are suggesting that basements of buildings along the
quays and the coast should not be any less than about 4 metres above sea level.”
It is important that a certain element of precaution should be taken in terms of
anticipating future storm surges and high water events.
The basement levels of the car parks within the development do not meet these
criteria as they are lower than 4 metres.
The north and south breakwaters proposed are lower than the breakwaters at Dun
Laoghaire Harbour. The east pier in Dun Laoghaire is overtopped during storm
conditions.
The location of the clubhouses is exposed. It would be regularly overtopped by
waves during storms. The Environmental Impact Statement concedes this point.
At the existing harbour, in 1910, there was a fatality when two locals were washed
into the sea whilst attempting to tend to a moored boat during a storm. Both of them
died.
PL27.EF2016/CF2002 An Bord Pleanála Page 75 of 136
In recent years the coastguards in Greystones have raised the issue of pedestrians
walking on the east pier at Greystones Harbour during storms, to watch the waves.
They correctly referred to the safety hazardous associated with this and suggested the
erection of signage warning the public of the dangers.
There seems to be a serious health and safety issue surrounding the location of the
clubhouses given the statement about severe overtopping.
The inclusion of the sailing club as a two-storey building essentially makes it part of
the breakwater itself. The seaward side of the clubhouse would be exposed to
considerable impacts from waves during storms.
Clubhouses should not be located in such exposed positions unless they have virtually
no windows on their exposed side.
It might be difficult to obtain insurance for the clubhouses given their location.
Ms. L. Bertram stated that she lived at north beach, directly to the west of the site.
The works proposed will give rise to noise, dust, overspill of light and traffic
disturbance. Particular concern was voiced in relation to the concrete batching plant.
An Bord Pleanála requested the developers to consider an alterative option showing
the complete removal of landfill material from the site. It is not acceptable that this
request was not complied with.
An Bord Pleanála also requested that beach nourishment material be possibly brought
in by sea to mitigate any potential negative traffic impacts. If this is not done it will
mean that the residents will be subjected to an unreasonable amount of heavy and
potentially dangerous traffic on an ongoing basis.
While the removal of Blocks B and C and adjacent Terrace 13 is welcomed the
overall reduction in housing numbers is very little. The development will still be
PL27.EF2016/CF2002 An Bord Pleanála Page 76 of 136
visually obtrusive and a dominant form of overdevelopment in relation to its harbour
side setting and existing built fabric including residential properties.
What is proposed now is a large public square. There is concern that it will become a
noisy arena both by day and night which could provide opportunities for anti-social
behaviour. This will have a negative effect on present and proposed residents.
The development will reduce the value of the objector’s property by 30 to 40%.
Mr. P. Walsh, representing the Bertrams stated that the amended development would
result in a devaluation in the residential properties owned by the Bertrams.
Reverend R. Bertram stated that the amount of traffic generated by the proposed
development has not been adequately considered.
The sewerage system serving the area is inadequate.
In reply to a number of questions from Mr. Flanagan, Mr. J. O’Sullivan stated that the
EPA is responsible for matters relating to emissions where the activity causing the
emissions is a licensable one. Where the activity is not licensable by the EPA then
An Bord Pleanála can take emissions into account. It cannot however grant
permission which contains conditions governing emissions.
The reason the Greystones Protection and Development Association wrote to the
Environmental Protection Agency was to clarify what had been asked of them by the
developers and what they had actually said. The reply which they received back from
the EPA differed from the original interpretation of what this development might cost.
Since An Bord Pleanála has both of these communications from the EPA the position
is therefore clarified.
No groundwater testing had been carried out by the Greystones Protection and
Development Association. .
There is no evidence of an aquifer in the area.
PL27.EF2016/CF2002 An Bord Pleanála Page 77 of 136
The European Legislation would not have had in mind that waste which had been
landfilled would then be dug out and recovered.
What the EPA letters have said was that if the waste was totally inert or had become
so by the passage of time, and the risk of environmental contamination or pollution or
the risk to the environment was, negligible, then the operation would not be classified
as landfilling. However if there was any risk to the environment over and above that
which could be regarded as negligible, then it must be a licensable activity. The
removal, disturbance or landfilling of waste which would have been licensable by the
EPA in that case.
There is no evidence of leachate in this landfill.
It is possible that the landfill was used by persons other than the local authority, after
it closed in 1976.
The fact that the executive of a local authority decides to close a dump does not mean
that the letter may have been disregarded. The only evidence before the hearing in
relation to the dump is the evidence of retired Garda Fallon who explicitly stated in
very clear terms, as a Garda, he had on occasions frequently to visit the landfill site
and found it was being actively used. He did not say by whom or by what persons but
I think for the purposes of the hearing what happens is that materials, unwanted waste
materials, were being placed or dumped or deposited on the site for many years
subsequent to the letter of 1976 .
In relation to Judgement C494/01, the European Commission versus Ireland the Court
referred to the fact that Ireland took a period of time before implementing a licensing
system. The Court was concerned that there was no licensing system when there
should have been one as required by the Waste Directive. The Government has now
moved to bring in legislation to fill the gap so that landfills which were in operation,
or may still be in operation, or more particularly those which were in operation at the
time of the coming into force of the Waste Directive, will be affected.
PL27.EF2016/CF2002 An Bord Pleanála Page 78 of 136
An Bord Pleanála in consideration of the matters should take account of the fact that
legislation is not in place in dealing with landfills which are of a considerable age and
which were being used post 1976.
The legislation which is impending will be particularly directed at landfills during the
period 1977 to 1997.
As far as can be ascertained at the moment the landfill on the site poses a minimum
risk. When it is disturbed it is not possible to say whether it would pose a minimum
risk. The letter set out by the EPA is very clear. It is up to the developer to satisfy An
Bord Pleanála that any disturbance in the landfill would pose a negligible risk. In this
case negligible risk is a very strong phrase.
The only surprise in relation to the testing already carried out in the landfill is that
none or very little organic waste was found. In this regard provided that the organic
waste is held or is trapped in an area of very low or zero oxygen, an anaerobic
environment, that is constantly wet, the decaying process more or less stops.
Mr. O’Sullivan stated that he had not carried out any tests on the landfill.
The testing carried out by Arup & Partners was to examine the site from the point of
its suitability for construction. It was not a report which had to address itself to the
question of environmental risk. . The site had been looked at to its suitability from
the point of view of construction of dwellings upon it.
If An Bord Pleanála was minded to grant permission, it would be very important to set
a condition requiring a risk assessment of any disturbance of the site. If such an
assessment proved to show that there was negligible risk then any work carried out or
undertaken would have to be done in such a way that the environmental pollution was
minimised.
The examination of the landfill by the developers was as a result of a fairly
comprehensive brief.
PL27.EF2016/CF2002 An Bord Pleanála Page 79 of 136
In reply to a number of questions from Mr. Flanagan, Professor Cooper stated that he
had carried out modelling studies in a number of locations throughout Ireland.
However he had not used modelling to provide a quantitative prediction of what the
future shoreline would be. He was aware of the type of models that had been used
however these do not deliver a reliable quantitative prediction of the future coastal
state. He had published several papers in international literature that have been peer
reviewed and that have undermined the use of these types of models for beach
purposes.
While the beach nourishment at Bray had been successful success should be measured
in terms of long-term sustainability of many projects and that remains to be seen.
With or without the proposed development there would be coastal erosion.
The beach is reliant on of a source of sediment which is at the back of the beach, the
cliffs. It is important that rates of erosion are not accelerated.
The beach does not necessarily have to be nourished as there are other options which
could be looked at. There could be for example a do nothing scenario which would
allow the coast to respond naturally in which case it will find its own equilibrium.
However it would have undesirable effects on the coastline that would not have
existed had development not been put in place. While there will erosion one way or
the other it would be accelerated if the development was not carried out.
In reply to a number of questions from Mr. Flanagan, Mr. O’Reynolds stated that
traffic calming in an urban environment is a remedial measure which should be based
on history of accidents. An admission that a problem exists on an existing road and
without having any information on accident trends in Greystones and in light of the
very poor geometry that exists under the bridge, traffic calming is something that the
Council should be putting on the ground for existing road conditions. It should not be
to facilitate additional and inappropriate heavy goods traffic.
PL27.EF2016/CF2002 An Bord Pleanála Page 80 of 136
There is no such thing as a 30 kph statutory speed limit in Ireland. There is no such
speed limit in existence in Ireland nor is there provision in any design standard for a
sightline or a forward stopping distance for a 30 kph environment.
A 30 kph speed limit is a low speed environment. The design standard do not allow
one to design for 30 kph roads.
Multiple access points are always better in terms of traffic impact than single points.
A low speed traffic environment would be welcome.
Councillor. T. Fortune stated that he was an elected member of Wicklow County
Council representing the Greystones electoral area.
He was fully in support of the Greystones Protection and Development Association
position.
The Board made four requests in its additional information letter. They required the
removal of a block of apartments. They required a reduction in the scale of the
development having regard to traffic generation. They required consideration of the
complete removal of the dump. They also required consideration of transporting the
beach nourishment by sea.
The developers have complied with only the first of these four items.
In relation to Item No. 1 however the reduction is only about 3.5% less in population
numbers. It is almost the same development as originally proposed.
There are serious health and safety issues in relation to the batching plant.
A square in any town is a great benefit however if the proposed square is too big it
will give rise to more problems than it will solve.
PL27.EF2016/CF2002 An Bord Pleanála Page 81 of 136
Councillor. D. DeBurca stated that she was an active member of Wicklow County
Council.
The revised plans submitted do not in any meaningful way address the concerns
expressed by the community in their submissions on the original development.
The developers have also failed to meet the requests set down by An Bord Pleanála in
its request for further information. To a certain extent they have merely used the
opportunity to defend their original plans.
The proposed batching plant is too close to residential accommodation. Mitigation
measures proposed for this aspect of the development are inadequate.
The contents of the dump include heavy metals, unwanted tar, bitumen, tarmacadam
and general construction materials. The sampling programme carried out by the
developers missed much of the deposited waste. A comprehensive sampling
programme combined with a proper environmental study is necessary.
Moving material from one part of the site to the other should be looked upon as a
new landfill requiring a new EIS and an EPA Waste Licence.
The road network is incapable of dealing with the excess traffic which will be
generated.
The developers appear to have rejected the Board’s request in relation to transporting
beach nourishment by sea largely on grounds of cost.
In extreme weather conditions it would appear that there will be severe wave
overtopping of both the north and south breakwaters. The clubhouses are too close to
the breakwaters and will be at high risk of flooding.
The ongoing cost of beach nourishment materials have not bee factored into the
development.
PL27.EF2016/CF2002 An Bord Pleanála Page 82 of 136
The developers should have been requested to submit a revised EIS taking into
account the provisions of the new Greystones/Delgany Local Area Plan.
The amount of building proposed is excessive considering the limited modifications
proposed. The development is inconsistent with the existing pattern of development
and represents overdevelopment of the area east of the railway line.
Wicklow County Council has failed to provide appropriate architectural protection for
the important area of Greystones Harbour. The Council refused to place an
architectural conservation area status on the harbour area in the Local Area Plan,
despite the fact that the area has the highest concentration of protected structures in
the town.
The utterly meaningless designation of a local urban character area was proposed for
the Greystones Harbour. A proper designation of the area as an architectural
conservation area would have precluded a massive and ultra modern development
such as proposed.
Mr. R. Fallon stated that he was a member of the Greystones Harbour Residents
Association. The association welcomed the decision of An Bord Pleanála to reopen
the oral hearing however they would have preferred a refusal of the proposed scheme.
As the local authority would be taking over the project at a date in the future the
public has the right to know the detail of finances. They need to be able to provide
that the project stands up financially.
Given the scale of property price increases since the scheme was first announced, a
further reduction in apartment numbers should have been possible.
The commercial floor space element of the development may not be viable.
The reduction in residential units at 34 would account for less than 100 occupants.
The traffic cannot be accommodated on the local road network.
PL27.EF2016/CF2002 An Bord Pleanála Page 83 of 136
Contained in the new proposal is one of the largest public squares in Ireland. This
could be a mecca for anti-social behaviour.
The design of the development continues to clash with existing buildings in the
environment. The development will obscure views to the mountains behind. The
area is subject of two listed views directly affected by the development.
The clubhouse buildings are now proposed to be moved. While the Harbour
Residents Association support the clubs in their request for better facilities they
should be provided with a proper location.
The clubhouse facilities are the only real community gain in the development as the
marina will largely be open only to fee paying members.
The residents adjoining the clubhouses will be subject to noise day and night from
pulleys, ropes and masts banging day and night as well as the issue of drinks licenses
on the site. It is a cynical move not to place the clubs in front of the new proposed
apartments. They have not done so as they would obviously affect the value of those
new residences.
The clubhouses are isolated in their new position and stick out like a sore thumb.
The development is of national importance for the precedent it will set whereby local
authorities can neglect public amenities and then permit development to the highest
bidder.
The Greystones Protection and Development Association should obtain an award of
costs as previously requested.
An Bord Pleanála should reject the proposal.
Councillor. Kay Kelleher stated that she was a member of Greystones Town Council
and also Wicklow County Council.
PL27.EF2016/CF2002 An Bord Pleanála Page 84 of 136
She welcomed the proposed changes to the plan. Great effort had been made to take
into consideration comments and suggestions made at the oral hearing last year. The
clubhouses have been moved. House numbers have been reduced. The entrance to
the development has been widened. A magnificent public square has been introduced.
Modern architecture has been proposed however it has already been permitted in the
area.
The commercial floorspace will be successful.
The new position for the sailing clubhouse will improve visibility of the water.
The value of houses in the area will increase once the scheme is completed.
Councillor M. O’Callaghan stated that she was a member of Greystones Town
Council.
The utilisation of a beach for commercial development against the wishes of the
community sets a dangerous precedent for the whole country.
The proposed public square would more likely be a vast wasteland for most of the
year and will lead to unwanted anti-social behaviour in the area.
Dr. C. Etchingham stated that he was a lecturer in the Department of History in the
National University of Ireland, Maynooth. He specialised in medieval history in early
Ireland. As a pastime he had been researching the early history of the Greystones area
since 1990. He is a resident of the area.
While the original settlement of Rathdown is quite extensive recent geophysical
survey work carried out by Target Archaeological and Geophysical in September
2006, shows that the settlement extends well south of the designated national
monument at St. Crispin's Cell, into what is known as D’Arcy’s Field.
PL27.EF2016/CF2002 An Bord Pleanála Page 85 of 136
What is proposed in D'Arcy's Field is a borrow pit and a batching plant, both of which
are temporary facilities.
The historical significance of Rathdown in the medieval period was that it was the
centre of the lordship of an important Gaelic aristocratic family which have been in
situ before the Norman invasion. This is the historical significance of the medieval
phase of the archaeology which probably extends into D'Arcy's Field.
Dr. C. Smal stated that the additional information submitted by the developers has
included important information on the archaeology of D'Arcy's Field. This has been
derived from geophysical surveys. The original EIS submitted for the application
included no new historical or archaeological information.
Given the lack of appropriate archaeological assessment of D'Arcy's Field and
historical features on or within the site, the geophysical and other evidence has been
reviewed. The Friends of Historic Rathdown have also employed expert consultants
who have considered and evaluated the information supplied.
They have also been in contact with the National Museum of Ireland in relation to the
important conservation issues at Rathdown.
Following the first EIS as submitted, they considered the proposal to be premature on
the grounds of archaeology as there was a need for detailed archaeological
investigations such as geophysical ground radar, aerial photography and non-intrusive
testing on D'Arcy's Field.
D'Arcy's Field is situated to the south of the registered Rathdown monument site.
Concern was also voiced in relation to archaeology along the coastal fringe where
there could be impacts from the proposed regrading of the cliffs.
The archaeological area of Rathdown is undoubtedly larger than the designated area
under the Monuments Act.
PL27.EF2016/CF2002 An Bord Pleanála Page 86 of 136
The archaeological potential of the site proposed for development should have been
investigated in full prior to the designation of D'Arcy's Field for any purpose
whatsoever.
The EIS should have a contained a true and complete archaeological profile given that
it has a major national monument boundary on its northern perimeter.
The geophysical survey presented as additional information on behalf of the
developers has fully confirmed the expectation of the Friends of Historic Rathdown
that D'Arcy's Field is an integral part of the archaeological area at Rathdown. The
recent investigations have served to confirm the society’s consultants assertions that
the Rathdown site is extensive and that D'Arcy's Field is of substantial archaeological
and historical importance. Previous submissions to An Bord Pleanála in previous
planning appeals in Rathdown since 1990, have all been proved to have been
appropriate and correct in ascertaining the importance of the Rathdown archaeological
area.
An Bord Pleanála should once again refuse the application on the grounds of
prematurity relating to the archaeology of D'Arcy's Field and the Rathdown Historical
and Archaeological Area.
The developers have already conceded that there are very significant archaeological
remains within D'Arcy's Field. They have accepted the necessity in their additional
information to restrict the area of the proposed development to a southern portion of
D'Arcy's Field. This outcome has resulted from their own recent archaeological
investigations.
The Manor of Rathdown extended over 248 to 300 acres. Of this area only 25 acres
has been registered to date under the Monuments Act.
The 300 acre area is likely to include D'Arcy's Field.
PL27.EF2016/CF2002 An Bord Pleanála Page 87 of 136
The field to the north of D'Arcy's Field revealed a significant beaker settlement,
numerous artefacts, prehistoric jars, corn drying kiln and medieval artefacts. This is
in spite of the fact that the geophysical evidence was weak.
The total number of finds at Rathdown based principally from the finds on the
western field is at approximately 2,000 items.
Geophysical investigation is an aid to archaeological assessment however it is not
conclusive or comprehensive.
Geophysical survey cannot usually reveal wooden structures and similar remains.
Such investigation can also be affected by electricity poles, telegraph poles, lighting
etc.
There are almost no boundaries within D'Arcy's Field. The field has been laid out as a
number of playing fields for several decades. Prior to this there were boundaries.
The field has been considerably altered by coastal erosion since 1840. The railway
line at the gap bridge was originally approximately 22 metres further east of the
bridge. Coastal erosion caused a move inland to the position of the bridge. However
with erosion at the gap bridge an entirely new tunnel was built through Bray Head and
a new line created where it is now, well to the west of the coast.
The geophysical survey carried out by the developers in D'Arcy's Field indicates
significant archaeological potential throughout the entire field.
It is fairly clear that the proposed working area at the batching plant and the borrow
pit impacts on Site B and the large ringfort structure and also impacts on Item C.
Although the reduction in the size of the batching plant is supposed to protect the
features which the developers archaeologist indicated Sites A, B and C, they are not
being protected. They will be severely disrupted or damaged.
While the protection afforded to the northern portion of the D'Arcy's Field is
welcome,. these archaeological features will or could in fact be severely damaged
within a protective zone as offered within the map issued to An Bord Pleanála. It
would be premature therefore to grant any permission which allows the
PL27.EF2016/CF2002 An Bord Pleanála Page 88 of 136
archaeological resolution of the remainder of D'Arcy's Field in the manner proposed
by the developers. Significant further testing is required to determine whether the
southern portion of D'Arcy's Field requires the same protection as is now afforded to
the northern portion.
The southern section of D'Arcy's Field as shown by survey carried out by the
developers, contains a striking number of unidentified anomalies and features of
archaeological potential. These should be validated prior to any determination as to
the future status of the field. To do otherwise would be premature.
A written submission from the National Museum, by Dr. A. Halpin states “I am
persuaded by Dr. Clinton’s argument that it would be premature to grant permission t
the excavation of the borrow pit and other works in this field until the nature of the
possible archaeological features revealed by geophysics has been adequately
established. In view of the fact that the proposed development works are purely of a
temporary nature, there can be no possible justification for any assumption that
archaeological features can be removed to facilitate development until the
significance of such archaeological features, if any, is known. I would also strongly
endorse Dr. Clinton’s warning about the potential danger of large scale mechanical
stripping of topsoil over possible archaeological features.
The only other comment I would make relates to concerns raised in the Friends of
Historic Rathdown submission to An Bord Pleanála about the possible or likely
impacts on the archaeology of proposed coastal works. These concerns which I feel
are well founded were not addressed in the revised EIS and consequently have not
been addressed by Dr. Clinton either. Perhaps they have been taken on board by An
Bord Pleanála but if not I would suggest that this is an issue which requires to be
examined closely.”
The developers archaeologist, Dr. Brady, stated that all recommendations that have
been made by the Department of the Environment and the National Museum of
Ireland would be taken on board.
John Oxley, archaeologist to York, in Great Britain, has written stating:
PL27.EF2016/CF2002 An Bord Pleanála Page 89 of 136
“I am in wholehearted agreement with Dr. Mark Clinton’s conclusion and
recommendations of his report.”
In a 1996 report John Oxley and Duncan Browne also an archaeologist, were involved
in a planning appeal in the western field. At that time they stated:
“Rathdown is a site and landscape of national importance which should be
preserved.. All of the scheduled area should be put under a management
agreement which would allow for the conservation of the site and this
preservation to a national and wider audience.”
All of D'Arcy's Field is part of the Rathdown Archaeological Landscape. Objection is
taken to any permission being granted on the site.
At D'Arcy's Field, a historical town, appears to have extended southwards towards
Greystones. Part of the area covered by the landfill, the old dump, has similar
archaeological potential. This is a matter that has not been addressed by Dr. Brady.
The developer has accepted that no works will be permitted or entertained on the
northern part of D'Arcy's Field. The Friends of Historic Rathdown will be seeking to
have this area registered under the National Monuments Act. Dr. Brady has noted this
as a recommendation of merit. The setting and landscape in which a monument is
situated is as important as the monument itself. In the past John Oxley has stated:
“Where nationally important archaeological remains whether resolved
or not, and their settings, are affected by proposed development, there should
be a presumption in favour of their physical preservation. In aesthetic terms
the setting of a monument provides it with its contemporary visual and
emotional context. Medieval Rathdown is essentially an island of intense
activity within a sea of agricultural land and woodland. All too often it is a
setting of a designated monument which is at risk rather than the monument
itself. In a place such as Rathdown, the setting of a monument is almost of
equal importance to the designated site. The utilisation of D'Arcy's Field as a
PL27.EF2016/CF2002 An Bord Pleanála Page 90 of 136
temporary facility only comes about due to constraints imposed on developers
by the Victorian road network. The developers do have the option of sourcing
their completed materials from other locations. They have not presented other
scenarios which would offer proper and sustainable protection to the
Rathdown site and to the coast.”
The archaeologists to the Friends of Historic Rathdown (Clinton, Halpin and Oxley)
have indicated that there is no professional or archaeological justification for the
removal of archaeological features just to facilitate a temporary development.. in the
likely event that any one of the anomalies identified in geophysical investigations
prove to be an extensive feature, as occurred at the western field.
Dr. Smal stated that he did not know at this point in time if any or many of these
features are present. However in such a rich archaeological context it is at least
probable.
Errors occurred in submissions. It is totally unacceptable for a series of maps to be
produced within an EIS with the same map number, the same author and sometimes
with the same preparation date and yet with a different mapping content.
This leads to obfuscation planning, pre-construction and construction phases. It has
already been shown that the maps issued in relation to D'Arcy's Field, the proposed
borrow pit and batching plant, will actually result in the works impinging on and
damaging and not protecting the archaeological features identified in the northern part
of D'Arcy's Field.
Mr. Flanagan interjecting stated that the first map prepared in September was
produced before Dr. Niall Brady’s recommendations were made relating to the
northern section of D'Arcy's Field. The hard copy submitted as additional information
is correct.
Continuing Dr. Smal stated that:
All of the EIS material should have been dated to exclude development to the
northern section of D'Arcy's Field.
PL27.EF2016/CF2002 An Bord Pleanála Page 91 of 136
The Greystones Harbour area should have merited architectural conservation area
status. Equal protection and consideration should be forwarded to the harbour and
listed buildings there.
The revised layout proposed is not appropriate to the Victorian setting and the
seascape. The new layout is equally damaging to the integrity of the coastal
landscape and the harbour as was the previous plan.
The gap bridge and the old culvert of the water of Rathdown have historical
connotations. They are located within the site of a registered historical monument.
Removal of the gap bridge is not required by the present project. However in the
interest of safety Sispar and Wicklow County Council have offered to take the bridge
down. In the event this work is carried out the bridge will be archaeologically
surveyed in detail before works begin and the removal works will be archaeologically
monitored. Recovered stone will be reused as part of the amenity works for the
proposed park. However only the Department of the Environment, Heritage and
Local Government has the power to decide the fate of the structure. The bridge must
be archaeologically surveyed in detail and the appropriate secondary research be
conducted before any such proposal can be properly made or suggested. As one of a
number of structures or sites within a national monument the bridge cannot be
considered as a problem which can be solved by demolition. There may be better
solutions available.
The archaeological complex at Rathdown is a major site of very significant interest
locally and nationally and one of the few positive aspects of the proposal has been to
extend our knowledge of the site. The report submitted by the developers and by the
Friends of Historic Rathdown have confirmed the archaeological value and potential
of D'Arcy's Field as an integral part of the Rathdown archaeological area. The
Friends of Historic Rathdown was established to protect the archaeological and
historical area and to promote its use for the community both locally and nationally.
PL27.EF2016/CF2002 An Bord Pleanála Page 92 of 136
The proposal should be refused on grounds of prematurity in relation to archaeology.
It would impact negatively on the archaeology and landscape setting of the Rathdown
site.
Ms. E. Singleton stated that she too is a member of the Friends of Historic Rathdown.
The EIS is still very much a work in progress.
The proposal is quite varied with 10 very diverse elements which impact in different
ways on different communities around Greystones. It is extremely important
therefore that proper communication should exist between the development agencies
and particularly that proper mapping and a full understanding of the development is
available to the developers to prevent errors being made if the development is to be
carried out.
Presenting evidence on behalf of the Friends of Historic Rathdown,Dr. M. Clinton
stated that he was a graduate of early and medieval history and archaeology. He had
been active in archaeology over a period of 35 years.
There has been a spectacular bounty of finds or artefacts discovered in the area to
date. Included in this are four coin hoards of mostly late 16 th to early 17th century
date. In all 400 to 500 coins have been recovered within the general environs of the
Rathdown complex. However according to the National Museum of Ireland there is a
distinct ambiguity as regards specific find spots. Given the fact that four coin hoards
have already been retrieved from the general environs of the Rathdown site, there is
an active possibility that further finds of this nature may await discovery in any part
of D'Arcy's Field.
The survey conducted by Target Archaeological Geophysics in September 2006 has
established the presence of substantial archaeological remains in the northern section
of D'Arcy's Field. In addition to a series of potential archaeological finds in the
central and southern part of the field it is possible that coins or some of the coins
could have come from D'Arcy's Field.
Dr. Clinton fully endorses the recommendations contained in Dr. Brady’s research
that the northern section of D'Arcy's Field should be excluded from any construction
PL27.EF2016/CF2002 An Bord Pleanála Page 93 of 136
activities. It should be formally acknowledged as a total exclusion zone and therefore
exempt from any extraneous interference. The coastal pathway along the eastern
flank of the area should be recognised as being integral especially given its known
archaeologically investigated status.
The provision of a 25 metre cordon sanitaire should be established south of the most
southern feature which is Feature C as denoted on the geophysical survey. The faint
representations of some features illustrates how easy it is to miss the presence of
additional associated features when relying on geophysical detection methods alone.
The physical setting and environment of a monument is integral to its proper
understanding and enjoy protection under the National Monuments Act.
The southern perimeter of the cordon sanitaire should be protected by a robust wire
fence.
Section 2 of the National Monuments Act states:
“In addition to the monument itself, the site of the monument and the means of
access thereto and also portion of land adjoining such sites as may be required
to fence, cover in or otherwise preserve from injury, the monument, or to
preserve the amenities thereof.”
When a monument is to be protected it is not just the monument itself but a significant
band around it.
The creation of an exclusion zone is fully warranted on the basis of the results of the
geophysical survey conducted by Target Archaeological Geophysics. The
identification of three definitive and one probable archaeological anomalies in this
area is of prime importance. Their siting to the south of the river, the water of
Rathdown and towards the old coastline raises the possibility that these features were
integral to the moated castle, church, settlement complex position to the immediate
north of the river.
Features A, C and A2 could alternatively be of pre-historic date.
PL27.EF2016/CF2002 An Bord Pleanála Page 94 of 136
Should that prove to be the case then it could be a cemetery of late Bronze Age or
Iron Age. The major discoveries in the field that lies to the immediate west of St.
Crispin’s Cell firmly establish that there is a high concentration of pre-historic activity
in the general area of D'Arcy's Field.
Feature B, an enclosed site within the region of 40 by 50 metres, lying to the
immediate south of the confluence of the water of Rathdown and the sea, raises the
possibility of proving to be the original dwelling place of the occupants of the early
medieval site known to have existed at Rathdown. As there has been a continuity of
occupancy it has always been expected that the original homestead would be present
in the general vicinity of the complex.
In relation to the central and southern sections of D'Arcy's Field it is imperative that
the precise nature of the myriad of potential archaeological features be ascertained in
advance of any planning decision regarding development related activities in these
areas. Any topsoil stripping in D'Arcy's Field would be counter-productive in the
preparation of accurate and comprehensive analysis and subsequent interpretation of
the archaeology present in the area. Topsoil stripping will inevitably lead to the
removal of artefacts from their original association related context.
The dumping elsewhere of topsoil with these finds would contaminate and thus distort
the archaeological profile of the receiving area. The materials which have represented
the Mesolithic, manifest themselves in the form of stone artefacts and the waste from
the preparation of these objects. The same holds true for the non-ceramic material
from the Neolithic period. This material which represents the earliest human activity
on the island, often comes to light in the context of ploughed fields. Material is
therefore contained in the topsoil. The fact that there is material of this description in
the area was proven by Cafferky in the form of the flints recovered from the ploughed
fields to the north of the moated castle complex.
An archaeological excavation remains a journey into the unknown and the
unexpected.
In other cases up to 80% of all surviving artefacts are present in the topsoil.
PL27.EF2016/CF2002 An Bord Pleanála Page 95 of 136
The National Monuments Act, (Amendment) 2004, make specific provision for the
preservation of archaeological objects. Section 25.1 of the Act states:
“It shall not be lawful for any person to injure, deface or destroy, clean, restore
or sample by cutting, drilling or other process any archaeological object nor
shall it be lawful for any person to alter any archaeological object otherwise
than under and in accordance with the licence that they have granted under
this section.”
The use of a mechanical digger either to remove the topsoil or to dig trenches would
almost certainly lead to a direct contravention of the National Monuments Act
because of the likelihood of interfering with an archaeological object.
Until the true and complete archaeological profile of D'Arcy's Field has been
scientifically investigated and determined the granting of permission for any
development related activities will be premature.
Heritage is a finite resource and a finite national recourse. It should not be diminished
for the sake of what is after all only a temporary local facility.
Geophysical surveys have been carried out at other sites in the recent past.
The Department of the Environment, Heritage and Local Government have not
adopted any stance on the extent of the cordon sanitaire safety margin. 25 metres
would appear to be acceptable. Erring on the side of caution would seem reasonable.
The Department of the Environment, Heritage and Local Government in relation to
the proposed development have stated:
“It should be further noted that should potential archaeology be discovered or
impacted during the course of the construction phase, avoidance, preservation
in situ, archaeological test, excavation or full archaeological investigation
would be the preferred mitigation.”
PL27.EF2016/CF2002 An Bord Pleanála Page 96 of 136
The option of preservation in situ is of note.
Section 3.4 of the Department of the Environment, Heritage and Local Government
publication “Framework and Principles for the Protection of the Archaeological
Heritage” states:
“Preservation in situ refers to the actual physical preservation of
archaeological sites and monuments including archaeological deposits,
features and structures. There should also be a presumption in favour of
avoiding developmental impacts on archaeological heritage.
Preservation in situ must always be the first option to be considered rather
than preservation by record in order to allow development to proceed and
preservation in situ must also be presumed to be the preferred option. Above
any other considerations all developments must be compliant with the
National Monuments Act and particularly in this case with Section 25.1.”
The National Monuments Act is the law and therefore must be fully complied with. It
is well within the remit of this oral haring to evaluate whether the Act and stated
government policy is being advanced here or not.
Ms. M. Egan stated that she was a resident of the area living at 1 Triton House, The
Harbour.
She had grave concerns particularly in relation to noise, dust, traffic and concrete
batching. Transportation of materials to and from the site would be very disruptive.
The entire development does not fit with both the Victorian Harbour and the natural
landscape.
The Planning Authority had not adequately addressed the batching plant, the removal
of the dump, traffic generation and beach nourishment.
PL27.EF2016/CF2002 An Bord Pleanála Page 97 of 136
The size, scale and design of the square is excessive. Noise generated from the square
would make it impossible to live within the area. During the annual Greystones Arts
Festival the witness has to vacate her home for between 18 and 21 hours a day due to
constant noise. There is also unacceptable anti-social behaviour.
The design of the proposed square is a hotch/potch of various designs. It is
completely at odds with the Victorian structure of the harbour.
The location of the clubs in one area would be intrusive to the residents. The design
of the clubhouses is ugly and incongruent in terms of the old Victorian harbour and
the surrounding houses.
Mr. C. Demery stated that he lived at North Beach. His home was closest to the
development planned on the site.
The additional information submitted has only added to fears over the construction.
The new layout still obstructs the view from his house. The four-storey blocks are
still only feet away from the house.
The developers have underestimated the amount of waste material dumped on the old
landfill site.
There was an old sandpit on the site. The pit was the last area of the dump to be filled
in and it is more than likely the source of any contaminated waste.
In reply to a number of questions from Mr. Flanagan, Dr. Clinton stated that the new
discovered sites in the northern section of D'Arcy's Field may well qualify for national
monument status in the future either structurally or by associated finds. It is
important to preserve their integrity until they are finally designated. Geophysical
surveys are an opening gambit. The archaeology of a site would never be published
on the basis of a geophysical survey. A 25 metre corridor should be maintained from
the nearest feature southwards. There may be associated features so therefore one has
to err on the side of caution. However features could be extending into the central
and southern part of the field.
PL27.EF2016/CF2002 An Bord Pleanála Page 98 of 136
The geophysicist John Pickles, who carried out the geophysical survey of D'Arcy's
Field, although being aware of the sewerage disturbance through the field, still
declared a feature in the central part of the field to be of possible potential
archaeological significance.
If a feature in the middle or the central or southern part of the field turned out to be
a bona fide, good, important archaeological find, either from its structural or
associated form, then one could have, right in the middle of the central or the southern
part of the field, another feature that had to be preserved in situ. That would very
much render the borrow pit unviable.
The legislation provides for input for both the Department of the Environment,
Heritage and Local Government and for the National Museum of Ireland. The
National Museum of Ireland have come out clearly and said that the development is
premature.
Under advice from the National Museum of Ireland it is a function of the Department
of the Environment, Heritage and Local Government to statutorily regulate any forms
of resolution in relation to archaeology.
Precedent has illustrated that if the National Museum of Ireland has serious
reservations in relation to the development of a site, the Department of the
Environment, Heritage and Local Government will alter their stance.
The Department of the Environment, Heritage and Local Government must be
compliant with the legislation and especially Article 25(1) of the National Monuments
Act 2000. Anything which they do must comply with the article or else they are
subjected to judicial review. Section 25 relates to a licence issued by the Department
of the Environment, Heritage and Local Government.
The department has a certain track record now in consistency. At an oral hearing in
Waterford, the Department of the Environment, Heritage and Local Government
officials were advocating that the archaeology of the site had been resolved and that
no further work was needed. This however was later overturned by the Minister for
the Environment, Heritage and Local Government.
PL27.EF2016/CF2002 An Bord Pleanála Page 99 of 136
In reply to a question from the Inspector, Dr. Clinton said that he gave expert
evidence at the hearing in the Waterford case. In that case it was stated by Dr.
Clinton that approving the alternative road past the site would be premature because
the entire perimeters of the site had not been fully defined. In spite of this the
Department of the Environment, Heritage and Local Government officials who were
present at the oral hearing, did not provide any evidence that there might be additional
archaeological investigations required. However within a couple of months the
Minister for the Environment, Heritage and Local Government considered that no
more excavation was required.
In reply Mr. Flanagan stated that the amount of information available in relation to the
instant site was way beyond that available in the Woodstown site in Waterford.
In reply Dr. Clinton stated that a full geophysical survey, just like the one carried one
on the instant site, had been done at Woodstown. It was being advocated at the time
that the archaeological finds were only minor stuff. It was also advocated that there
was no need for full excavation, a proper explanation. On the day that was the
attitude adopted. It is available in the record of the case in the files of An Bord
Pleanála. However within a month or two the Minister reversed the whole thing and
said no new excavation should be carried out.
Mr. Flanagan stated that the developers fully bought into the requirements of the
Department of the Environment, Heritage and Local Government.
In reply to number of questions from Mr. D. Flynn, Mr. S. Mason stated that in
relation to truck movements into and out of the site, the amount of such movement
was estimated on the basis of the amounts of material to be moved in and out of the
site. Because the development has been reduced material to be moved would be
approximately 10%.less.. Traffic movement reduction of between 9 and 13% would
occur.
It was shown at the previous oral hearing that, unusually, the peak hour in the
morning for traffic movement was later than one might expect. It was at the school
PL27.EF2016/CF2002 An Bord Pleanála Page 100 of 136
delivery period around 9.00 whereas one might normally expect the peak hour to be 7
to 8 or 8 to 9.
Delivery times were an 8 hour period per day. There would be no delivery at times of
peak traffic flow.
Dr. I. Shanahan stated that there would be a traffic management plan put into place
which would provide the specifics as to what would happen on the ground.
Continuing in reply to questions from Mr. Flynn, Mr. Mason stated that there would
be sufficient space for trucks to manoeuvre within the site. Large numbers of trucks
will not be parked overnight on the site. A small number of vehicles would be
required to remain on site. These would be used in moving material from the
batching plant to the casting yard.
Fuel storage would also be provided for on-site. This would be for the refuelling of
vehicles and would contain a couple of hundred litres as is normal on a construction
site. Such facilities are bunded and protected. Measures would be in place to deal
with any spillages etc.
Dr. Shanahan stated that it was intended that there would be four mixer trucks
transporting concrete on site. These would take concrete from the batching plant and
transfer it into the casting yard for pouring into moulds. There would be an excavator
operating on the site transporting materials from the storage bins into the hoppers.
There would also be a number of crawler cranes.
Specific procedures have been put in place for the delivery, transport, handling and
general management of fuels and other materials on site. Appendix 6 of the further
information submitted to An Bord Pleanála in October 2006 contains a detailed
manual dealing with all aspects of the environmental management practices which
will be implemented on the site.
In reply to a number of further questions from Mr. Flynn, Mr. Mason stated that there
were no plans to physically stockpile dredged materials unless there was something
PL27.EF2016/CF2002 An Bord Pleanála Page 101 of 136
dug out that was considered to be unsuitable by virtue of the type of material. The
general plan is that as material is dredged it would be brought to its point of
deposition.
The bulked value of dredged material resulting from the operation proposed is in the
order of 130,000 cubic metres.
In relation to the suitability of the dredged material, all evidence to date would
indicate that it is suitable as fill in the borrow pit. There is no indication as to why it
would not be suitable.
The borrow pit does not need to be licensed as a landfill.
The area of the borrow pit now currently proposed is 12,000 square metres. At an
average depth of borrow material of 8 – 9 metres, the amount of material to be
excavated would be approximately 100,000 cubic metres.
In reply to a number of questions from Mr. Flynn, Dr. Shanahan stated that it was not
specifically planned to have lights around the perimeter of the borrow pit. It would be
fenced off for security and safety reasons. There are no plans to light the perimeter.
The only continuous lighted area would be at the batching plant and the pre-casting
area, on the eastern part of D'Arcy's Field.
Appendix 4 of the further information submission of October 2006 provides figures
which relate to all of the noise generating activity associated with the batching plant
and the casting yard.
A separate assessment was made of the borrow pit in Section 5.4.13 in the body of the
report. The first sentence of Section 5.4.13 is as follows:
“The assessment showed that the borrow pit would result in an addition of
approximately 3 dB to the noise levels associated with this phase of the
development at the nearest residences to the site. This would lead to an Laeq
1 hour which is the noise that people would experience over a period of 1 hour
PL27.EF2016/CF2002 An Bord Pleanála Page 102 of 136
at the nearest residences, of 62 dB, which is still well within the acceptable
noise level assessment criteria of 70 dB(A) for the construction phase of the
development.
The borrow pit is only going to be in use occasionally. . Even the worst hour
that it is operating would not add more than 3 dB to noise levels.
If there is a change in noise levels of 3 dB, that will not be a significant change
in terms of what people can understand and perceive.
At no time are noise levels going to exceed 70 dB. The maximum noise level
will vary depending on the activity taking place and its locations.”
In reply to a number of questions from Mr. Flanagan, Mr. S. Fallon stated that he was
a member of An Garda Siochana for 25 years and retired from the force in 1984. He
had been based in Greystones all of that time. He had however moved from
Greystones to Delgany around 1978 as he had built a house in Delgany and moved
from Greystones because of the dump.
There has always been comings and goings to and from the dump. Fly tipping as it is
now called took place the whole time. He had observed activities at the dump on an
official and unofficial basis.
When illegal dumping was occurring on the site it was not his duty as a Garda to
pursue the dumpers.
In reply to a number of questions from Mr. F. Etchingham, Dr. I. Shanahan stated that
she did not have any reservations about objectivity on any of the work carried out for
the developers.
In reply to a number of questions from Mr. Etchingham Mr. Mason stated that
Ballyhorsey was originally named as the source of beach nourishment material in the
original EIS. It was also specifically named in the additional information.
PL27.EF2016/CF2002 An Bord Pleanála Page 103 of 136
Ballyhorsey contains enough material over the next 10 years or so and an assurance in
this regard has been obtained by the developer.
There are many other sand and gravel pits which will have a similar type of
geological material. A number of these would be available for use in the future.
There has however been no direct assessment of sources other than those indicated in
the additional information.
Given the nature of the deposits which are required, glacial outwash, comprising stone
from the Wicklow area generally, these types of deposits are available elsewhere
within County Wicklow.
The developers comments in relation to beach nourishment specifically referred to
information required in relation to seaborne deliveries of nourishment material. It
was in that context that the proposed delivery by land from local quarries was
included as an option.
In reply to a number of questions from Mr. Flanagan, Mr. Etchingham stated that he
was a trustee of the sailing club. He was aware that the sailing club was the only one
of the clubs which has outstanding concerns.
There was an issue in relation to VAT. If the proposal to the Council to grant a long-
term lease on the site was successful, that could trigger a VAT liability. If such a
liability arose the club would effectively have been unable to occupy the premises as
the sums of money involved would be too great for them to pay. Wicklow County
Council would not indemnify the club against a VAT liability.
Mr. Etchingham said that he was not representing the sailing club.
For Wicklow County Council Mr. S. Quirke stated that there had been a number of
meetings with the sailing club. The advice given to the Council in relation to VAT
was that the provision of a lease should not attract VAT. Changes in the legislation
are due this year however therefore a cast iron guarantee could not be given in
relation to a lease and the possibility that it might attract VAT.
PL27.EF2016/CF2002 An Bord Pleanála Page 104 of 136
In reply to a number of questions from Mr. Etchingham, Ms. S. Walsh stated that the
primary function of an architectural conservation area is to protect. Such an area is a
place, area, group of structures or town scheme of special architectural, historical,
archaeological, artistic, cultural, scientific, social or technical value.
Such a designation relates more to buildings but rather to a wider area that has some
characteristics worth preserving. At the initial oral hearing a reference was made to
the old Burnaby which is designated an architectural conservation area. It is more
than just the buildings themselves which give the area character, it is the street
pattern, the trees and the setback of buildings to the road and so on.
It was not agreed, during the making of the Local Area Plan, that the coastal area at
Greystones represented a coherent entity similar to the old Burnaby. That was the
advice proffered by the professional planners. The county manager and the
councillors ultimately decided the status of the harbour area.
The main reason it did not achieve ACA status was that it was not considered to
represent a coherent entity.
The area contains a number of street patterns. A number of the roads could possibly
have been mews roads or lanes initially and were not part of the original Victorian
fabric.
There has also been considerable intervention in the area by modern buildings and
structures which considerably interrupt the character of the area, including St. David’s
School and the Telecom building. There are also a number of modern buildings on
Trafalgar Road.
Even with the designation of an architectural conservation area, there would be
nothing in that designation which would preclude developments at just the harbour
and marina proposed particularly with the considerable distance now between Block
D and the Victorian seafront buildings. Even if this area were to be given an
architectural conservation status this would not prevent new buildings, new
interventions once they respect the character of the area.
PL27.EF2016/CF2002 An Bord Pleanála Page 105 of 136
The Local Area Plan states:
“The designation of an architectural conservation area does not prejudice
innovative and contemporary design. On the contrary, in principle design of
contemporary minimalist style could be encouraged within architectural
conservation areas provided it does not detract from the character of the area.
It is considered that new buildings should be of their own time and appearance
and should not replicate the style and detailing of heritage buildings.
The replication of historic architectural styles is considered to be counter-
productive to heritage conservation and principle, as it blurs the distinction
between what is historic and what is contemporary and leads to the emergence
of poorly considered buildings.”
Ms. Quinn from the Department of the Environment, Heritage and Local Government,
in the initial oral hearing stated that there were a number of protected buildings in the
area. She also made certain comments regarding the design of the proposed
development. These were taken on board by An Bord Pleanála in particular in the
further information request. There was an issue of proximity to the older buildings.
These were fully addressed through An Bord Pleanála in the revised proposed.
Mr. Etchingham stated that for the record the Department of the Environment,
Heritage and Local Government did actually state that the area would appear to merit
architectural conservation area status.
In reply the Inspector stated that that is on the record. However it was possible that
Ms. Walsh was not actually attending the original hearing at that particular time.
Continuing Mr. Etchingham stated that the Manager’s Report on the Local Area Plan
in July 2006 stated:
“Designating the harbour as an architectural conservation area would be in
conflict with the objectives of the Action Plan Z1 to provide a high quality
PL27.EF2016/CF2002 An Bord Pleanála Page 106 of 136
integrated harbour, marina, mixed development.” That would tie in within the
evidence given by Ms. Walsh in this regard.
ACA status is quite an important status. It is important in achieving objectives and
preserving areas of architectural significance. It would appear that the area was not
afforded that status for the simple reason that it would have precluded or might have
precluded the construction of the harbour and the marina.
In reply to a question in relation to wave modelling by Mr. Etchingham, Mr. Flanagan
stated that at the initial oral hearing a commitment was given by the developers in
relation to over topping. In terms of physical structures there would be no more than
potentially a 0.5 metre increase in height of the breakwater. The developers are not
relying on physical modelling to offer any changes to the proposed works.
In reply to a question from Mr. Flynn, Mr. Quirke of Wicklow County Council stated
that discussions were held with the clubs because the facilities were being provided .
Only a short space of time was available to submit information to An Bord Pleanála.
It was not feasible to hold further public meetings within that time newsletters were
delivered to.
In reply to a number of questions from Mr. Etchingham, Mr. M. Hussey stated that
View 15 submitted with the additional information is the correct one.
In reply to a number of questions from Ms. Cawley, Mr. Quirke stated that the value
of the foreshore is essentially a matter which will become pertinent if the Compulsory
Purchase Order is confirmed. Wicklow County Council have an assessment of what
they are prepared to pay for the foreshore. It is understood that the Minister for
Finance also has such an assessment. Wicklow County Council will not enter into
negotiations until such time as the Compulsory Purchase Order is confirmed and a
notice to treat is served on the Minister for Finance. The Minister for Finance has
received a valuation from the Valuation Office. It is not for Wicklow County Council
to reveal what valuation has been put on the foreshore although Wicklow County
Council are aware of the figure.
PL27.EF2016/CF2002 An Bord Pleanála Page 107 of 136
In reply to a number of questions from Dr. Smal, Mr. Mason stated that the physical
modelling which was done in relation to the beach, do not include any coastal process
modelling. The beach nourishment scheme is founded on the numerical modelling
and not on any physical modelling of coastal erosion.
It is the developers intention to remove all beach shingle. When the harbour is
completed it will be reinstated as the natural shingle beach in the harbour. The precise
storage would be subject to the Construction Management Plan. It will be somewhere
within the overall site.
The initial works to be undertaken will be the establishment of the sides to build the
breakwater. Until such time as the breakwater is in place anything that is done behind
it would be under threat from adverse sea and storm weather conditions. This would
be obviated when the breakwater is in place.
The operation of the borrow pit does not come into the equation until well into the
coastal marine works. The breakwaters would be substantially in place prior to the
start of reclamation and until such time as the developers are confident that it is not
going to be exposed to any erosion or displacement by sea conditions no such work
will be carried out. There is no need to dredge the harbour material until the
breakwater is in place.
Injecting the Inspector stated that it should be pointed out that material may need to
be moved a number of times around the site as various processes are undertaken.
Mr. Mason stated that one of the fundamental principles, with the entire design, is to
minimise the amount of materials brought in and out of the site so there is a very
conscious effort to utilise material on site. The double handling or greater amount of
handling of materials where at all possible will be avoided. This is a commercial
consideration.
Mobile refuelling systems would be used on the site as far as possible. This would
obviate the need for on-site storage.
PL27.EF2016/CF2002 An Bord Pleanála Page 108 of 136
In a concluding submission Mr. Etchingham stated that the plan is wrong for
Greystones as it does not fit.
The minor modifications undertaken in the additional information do nothing to
render the development more acceptable.
Despite the removal of two blocks the development is still enormously intrusive on
the landscape. Its design is in such conflict with its surroundings that it was necessary
for the Council to withhold architectural conservation area status from the harbour
area. To have accorded such status would have highlighted the unsuitability of the
design of the housing and caused a greater risk that the development would be refused
permission. The receiving environment cannot cope with the traffic the development
will generate. No amount of tweaking of access junctions or traffic calming measures
will overcome this problem.
It is necessary to disturb the old dump and contaminate previously uncontaminated
land to complete the development. The coastline is unsuitable for this type of
development. Erosion will be massively accelerated. The Council will be committed
to costly beach nourishment in perpetuity. This would place a massive drain on the
resources of the local authority and cause silting problems elsewhere as the
nourishment material is washed away each year.
The results of the wave modelling are unknown.
It is not known where all the material for the beach nourishment will come from or
indeed whether it will be suitable.
It is not known if the project is financially viable.
It is not known what will happen if certain parts of the plan for example the borrow
pit proved not to be feasible.
It is unknown if there will be a sailing club. The premises may be unsuitable.
PL27.EF2016/CF2002 An Bord Pleanála Page 109 of 136
It is not known whether the transport of materials on and off site by sea is practical or
whether this option is simply being dismissed to save money.
The project lacks any significant level of public support.
The only supporters of the proposals are harbour users whose motivations are entirely
understandable.
It should be possible to provide a plan for the area which regards its outstanding
natural beauty, its cultural heritage, the constraints from the infrastructure particularly
in relation to traffic and the potential damage to the adjacent foreshore.
The proposal obliterates what the community treasures most. An Bord Pleanála is
requested to refuse permission for the development.
In closing Mr. Flanagan stated that he was not aware of any environmental protection
agency legislation relating to separation distances from batching plants.
An Bord Pleanála sought information in relation to the batching plant. A very high
level of information has been supplied.
The investigation of the old dump carried out by Arup & Partners was sufficient.
Wicklow County Council have consulted with the Environmental Protection Agency,
who are the competent authority in relation to the question of waste and
environmental pollution. In their opinion what is proposed is a recovery operation.
There is no evidence of any interference with groundwater. There is no leachate.
It is equally acceptable in terms of negligible environmental risk to allow part of the
landfill to be removed subject to an ongoing monitoring situation.
The position in relation to beach nourishment is that the Planning Authority will
pursue an application for a licence in relation to the Codling Bank.
PL27.EF2016/CF2002 An Bord Pleanála Page 110 of 136
A sea to shore solution for the required beach nourishment is the most acceptable in
terms of traffic impact. That solution requires transfer of material from the Codling
Bank. That in turn requires a licence. The outcome of that statutory process cannot
be predicted. If a licence is granted it is the preferred solution for beach nourishment.
The remaining options are road based or a part road part sea solution. In relation to a
part road, part sea solution, the road element will involve a round trip of up to 59
kilometres instead of 19 kilometres. To that extent the situation from a disbenefit
point of view is that the disbenefit is more widely spread throughout the locality. This
solution outweighs the disbenefits associated with a road only solution. That is
recommended on current knowledge.
The delivery of material via the leisure harbour itself would be completely unsuitable
in terms of adverse disruption and limitation on vessel size.
If a road solution is to be implemented the Board should consider extending the
duration of the road based solution from four weeks to eight weeks. This would
effectively mean that the number of additional truck deliveries would not exceed 15
per day.
If An Bord Pleanála is minded to incorporate an option in relation to a licence for the
Codling Bank the wording could possibly be as follows:
“Within 12 months of the commencement of development, Wicklow County
Council shall make an application for a foreshore licence to the Department of
the Marine, Communications and Natural Resources to provide the necessary
beach nourishment material from the Codling Bank.”
In relation to archaeology and D'Arcy's Field the developers entirely endorse the
contents of the Department of the Environment, Heritage and Local Government’s
letter of 29th January 2007.
PL27.EF2016/CF2002 An Bord Pleanála Page 111 of 136
Any archaeological monitoring would be subject to the detailed requirements
contained in the letter from the Department of the Environment, Heritage and Local
Government.
This would result in licensed excavation in accordance with the licence granted.
With effect from the 17th October 2006 the Strategic Infrastructure Bill came in to
place. Section 143 of the 2000 Act has been amended as follows:
“The Board shall, in performing its functions have regard to
(a) The policies and objectives for the time being of the Government, State
Authority, the Minister, Planning Authorities and any other body
which is a public authority whose functions have or may have a
bearing on the proper planning and sustainable development of cities,
towns or other areas whether urban or rural.
(b) The national interest and any effect the performance of the Board’s
functions may have on issues of strategic, economic or social
importance to the State and,
(c) The National Spatial Strategy and any Regional Planning Guidelines for
the time being in force.”
Subsection (c) clearly affirms National Spatial Strategy and Regional Planning
Guidelines as being of overriding consideration for An Bord Pleanála in the exercise
of its functions.
Mr. J. O’Sullivan and Professor Cooper did not base their conclusions on their own
evidence. A proffered opinions based on their own view of the evidence.
The level of information in this proposal is way over and above that which is
normally associated with development .
PL27.EF2016/CF2002 An Bord Pleanála Page 112 of 136
In relation to traffic what is proposed is a low speed environment in an already low
speed area. That low speed environment and the separation of traffic movements from
vulnerable road users was extensively discussed at the first oral hearing and has been
amplified and looked at again. In two significant ways mitigation has been carried
out. This is done by the provision of an additional access point. It will also be
considerably added to with the provision of a 30 kph speed environment.
The design manual for roads and bridges related to trunk roads. It is not correct to use
it to deal with low speed environments such as proposed.
The additional information contained two fundamental elements. The first was the
creation of a public square to establish a transition between the old and the new. This
has been wholeheartedly achieved in the revised proposal.
Beach nourishment emanating from the Codling Bank, subject to licence, is a
mitigation measure.
In the Dietcarton Limited versus An Bord Pleanála case the High Court decided,
Quirke J. on 13/10/2004 that a request for detailed additional information and a
redesign to the then proposed Balgaddy Centre, was a valid request by An Bord
Pleanála.
Approval should be granted to the proposal subject to the mitigation measures
outlined during the course of the hearing and in the written submissions.
As this concluded the evidence the hearing was formally closed.
ASSESSMENT
The submission of revised drawings and particulars to An Bord Pleanála, by the
developers, resulted from the request for further information contained in the letter of
14th August 2006 from An Bord Pleanála to Wicklow County Council.
PL27.EF2016/CF2002 An Bord Pleanála Page 113 of 136
Following the submission of further information the public was given access to this
information. The submissions objecting to and supporting the proposal amounted to in
excess of 130.
An Bord Pleanála acceded to the request from the objectors to reopen the oral hearing.
The proceedings of the reopened oral hearing, which lasted for three days, are on file
and a precise of the hearing, containing all relevant sections, constitutes part of this
report. This report also constitutes an addendum to my report of the 11th July 2006.
An Bord Pleanála request for further information:
The request for further information is contained in a letter to Wicklow County
Council amounting to approximately three pages. The letter was issued to the local
authority in accordance with Section 175(5)(a) of the Planning and Development Act
2000. 6 no. issues were referred to. These issues outline the views of An Bord
Pleanála in relation to certain aspects of the proposal. In general Items 1-6 required
the submission of further information. However there was a certain amount of
direction contained in the six points. In relation to Items 4 and 5 direction was
specifically given requiring the omission of Blocks B and C and adjacent Terrace 13.
Direction was also given requiring the redesign of Block D.
In relation to Item 6 it was stated that the redesign of the scheme may require the
relocation of the clubhouses and ancillary facilities to an alternative location on the
overall site.
Finally it was directed that the redesign undertaken shall result in a reduction in the
quantum of the overall development and associated traffic generation. It was stated
that this may require some redesign of other elements within the overall proposed
development, whilst maintaining the integrity of the overall proposal.
In order to address the issues raised in the letter of An Bord Pleanála dated 14 th
August 2006 considerable information has been submitted by the developers.
PL27.EF2016/CF2002 An Bord Pleanála Page 114 of 136
Considerable information has also been submitted by objectors to the proposal.
Support forthe proposal has also been voiced both in written form and at the reopened
oral hearing.
I consider that the further information, as well as all the other information, including
the proceedings of the reopened oral hearing, can best be dealt with using the
sequence contained in the letter of 14th August 2006, requesting further information.
My report of 11th August 2006 covered all issues relating to the development as then
formulated. Having regard to this it is proposed to comment only on the changes to
the proposal, resulting from the request for further information. I also propose to
comment upon the objectors reaction to this further information.
Batching Plant/Casting Yard and Borrow Pit:
Batching Plant:
Considerable detail had been submitted in relation to the batching plant, in the
original proposal. The batching plant is similar to batching plants provided throughout
the country on construction sites. It is also similar to such plants provided in mainly
gravel pits, to utilise the raw material at source and to provide readymix concrete for
transport to construction sites. In this regard I consider that the batching plant
constitutes a standard piece of construction equipment. The installation, and
operation, including servicing, by raw material, has been fully clarified in the
submitted information. The plant itself is located a considerable distance from the
nearest residences. Its presence on site and its operation, will not give rise to any
injury to residential amenity. As such I consider that it is a fully acceptable standard
piece of industrial equipment necessitated by the construction proposals on the site.
Casting Yard:
The casting yard was also outlined in considerable detail in the original submission.
Further information has been submitted in relation to the casting plant. I consider that
PL27.EF2016/CF2002 An Bord Pleanála Page 115 of 136
the casting plant is necessary in order, literally, to provide the building blocks for the
breakwater particularly and other parts of the development. It adjoins the batching
plant. Its presence on site obviates the need to cast large concrete structures
elsewhere and transport them to the site. I consider that the batching plant in both
design and operation, would not result in any injury to the residential amenities of
property in the vicinity. Like the batching plant it is located a reasonable distance
from the nearest residential accommodation. The location is visually cut off from
residential accommodation by the railway embankment. This acts not only as a visual
barrier but also a noise attenuator.
Noise and Air Impacts:
Both of these issues have been dealt with in some detail in the original Environmental
Impact Statement and in the additional information. Reference has also been made to
them during the course of the reopened oral hearing.
Noise:
As indicated in my report of July 2006 the highest levels of noise generation would be
during the construction phase. Noise generation will not constitute an issue of
concern once the construction works have been completed. The length of the
construction period, at five years in the original proposal, has been slightly reduced by
the reduction in the amount of development proposed.
Marine engineering works would, in the initial period, constitute the greatest noise
generation with the construction of the harbour. Works such as dredging, piling and
fabrication of the very large concrete blocks and their transport on site would
constitute sources of the greatest noise generation. Heavy truck movements would
also generate considerable noise.
Hours of operation are critical in relation to noise.
PL27.EF2016/CF2002 An Bord Pleanála Page 116 of 136
The details submitted by the developers has indicated that no element of works
resulting from the development will cause an increase of greater than 3 dB and that
the maximum noise generation would not in any event be greater than 70 dB.
In relation to noise generation I consider that what is proposed is acceptable.
In relation to noise generally I consider that that hours of operation are critical. In this
regard Condition 10 of my original report was as follows:
“Demolition and construction works shall be confined between the hours of
08.00 and 18.00 hours Monday to Friday and 08.00 and 16.30 on Saturdays.
Construction shall not take place on Sundays and Bank Holidays.
Reason: To protect the amenities of residential properties in the vicinity
during the course of the works.
Air Impacts:
Both the batching plant and the casting yard operations, have been outlined, as noted
above, in some detail in the original EIS and in the details submitted as a result of the
request for further information.
I do not consider that either plant would result in an impact upon air quality or give
rise to dust. In this regard mitigation measures have been outlined in considerable
detail particularly in relation to the batching plant and to the transport of raw material
to the plant.
Light Impacts:
This constituted a point referred to in Item 1 of the letter of 14 th August, 2006 from
An Bord Pleanála. Detail in relation to lighting of the site has been provided in both
written and oral form. I am satisfied that measures proposed in relation to lighting the
construction site will mitigate any potential disamenity to residences in the area.
PL27.EF2016/CF2002 An Bord Pleanála Page 117 of 136
In relation to traffic disturbance, also referred to in Item No. 1, it is of note, that the
provision of a batching plant and casting yard on the site constitutes a major
mitigation/reduction of heavy goods vehicles travelling to and from the site as both
uses are on site. I consider that the traffic disturbance resulting from the proposed
development has been proposed to be sufficiently mitigated by the developer.
It is their intention that construction activities on the site will give rise to as little
traffic generation as possible. While there will be an element of traffic disturbance
resulting from development, I am satisfied that the measures proposed by the
developers, at the construction phase, constitute the best practicable means by which
traffic disturbance can be mitigated.
It should be noted that the location proposed for the batching plant and the casting
yard have been moved southwards by 10 metres. This follows the advice given by
Dr. N. Brady, Archaeologist for the developers, following the archaeological
investigations carried out in D'Arcy's Field, subsequent to my report of July 2006.
These investigations noted a number of anomalies. Reference has been made in the
objectors detailed submission, by Dr. Clinton, to the necessity to provide a widened
area of 25 metres between the southernmost anomaly as opposed to the 10 metre
cordon sanitaire, as proposed by Dr. Brady. The objectors furthermore consider that
until such time as resolution has been fully implemented in archaeological terms, in
all of D'Arcy's Field, the development should be considered to be premature.
I am in agreement with the position adopted by Dr. Clinton that a strip of land, 25
metres in length for the full width of the site, in this section of D'Arcy's Field, should
remain undisturbed, as opposed to the 10 metre band proposed by Dr. Brady. Over
the remainder of D'Arcy's Field it is of considerable importance, in my opinion, that
archaeological testing be implemented prior to the commencement of any
development on this part of the site. In particular I do not consider that a batching
plant or casting yard should be established until such time as sufficient knowledge is
obtained in relation to the archaeology of D'Arcy's Field. I furthermore consider that
it would be seriously ill advised to permit the removal of material as proposed in the
PL27.EF2016/CF2002 An Bord Pleanála Page 118 of 136
borrow pit, until such time as the area covered by the proposed pit has been fully
resolved archaeologically.
It is of some note that the northern part of D'Arcy's Field, the subject of research by
Dr. Brady, has revealed the presence of what appear to be important anomalies. The
possibility of other finds is stated, by the objectors, to be likely having regard to the
history of finds in the area further north. I fully accept this position. I also consider
that the position adopted by the objectors in relation to what is proposed in the borrow
pit is the correct one and requires support. Their basic position on the borrow pit is
that it is a temporary proposal involving the removal of material, from a site of
considerable archaeological potential. This removed material would be replaced by
dredged material. The removed material would be used as fill, as it would be more
suitable for that purpose than parts of the dredged material.
In relation to D'Arcy's Field therefore I consider that no disturbance by way of
development of any plant on the site should occur north of a line running east/west, 25
metres to the south of the recognised archaeological features in the northern section of
the field, the discovery of which resulted from the geophysical survey carried out on
the part of the developers.
I consider that the evidence submitted by Dr. Clinton in relation to topsoil stripping is
of considerable relevance having regard to the possibility that archaeological features
or finds would be more than likely close to the surface.
The25 metre cordon sanitaire, is required therefore to the south of Feature C, as
outlined in the geophysical survey. I furthermore consider that preservation in situ
should be the first option to be considered, being preferable to preservation by record.
Preservation by record is normally implemented in order to allow development to
proceed. However in this case as the development proposal is basically the removal
of material, such removal, is not a necessary part of permittin the overall
development to proceed. It is not a vital element in relation to the implementation of
the proposed development.
Condition No. 9 of my original report was as follows:
PL27.EF2016/CF2002 An Bord Pleanála Page 119 of 136
“The establishment of the batching plant and the casting yard shall be
monitored by a suitably qualified archaeologist. Both plans should be located
as far south as possible in D'Arcy's Field. A report on the monitoring shall be
submitted to the Department of the Environment, Heritage and Local
Government and a copy shall be made available for inspection in the offices of
the local authority.
Reason: To protect the archaeological and cultural heritage of the area.”
I consider that Condition No. 9 above requires to be amended in order to provide for a
25 metre cordon sanitaire and also to provide for the adequate archaeological
investigation of D'Arcy's Field.
THE OLD DUMP
Item 2 contained in the letter of 14th August 2006 dealt specifically with the old dump.
The developers were requested to consider an alternative option showing the complete
removal of landfill material from the site, preferably by sea, to ensure that any long-
term environmental impact is avoided.
The developers were also requested, in their response to outline the position regarding
any necessary waste licenses required.
Item 2 has resulted in the submission of a considerable amount of material both in
written form and at the oral hearing. The objectors introduced a new witness, Mr.
O’Sullivan and provided details that had not been referred to by them in their original
submission.
The developers position would appear to be as follows. There is no particular need to
deviate from the developers original proposal to move 9,000 cubic metres of material
from one end of the site, southern section, to another, the northern section, in spite of
the fact that the Board, in Item No. 2 referred to the fact that it might not be satisfied
PL27.EF2016/CF2002 An Bord Pleanála Page 120 of 136
with the overall approach in dealing with the old dump by redeposition, and capping,
having regard to potential environmental impacts resulting from such works.
The developers proposal is to implement the original removal of approximately 9,000
cubic metres from the southern sector of the dump and to position it to the north of the
existing dump area. This results from the fact that it is intended to construct houses on
the southern part of the existing landfill.
The evidence produced at the reopened oral hearing by the objectors is to the effect
that the old dump should either remain undisturbed or should be entirely removed
from the site, by sea.
While the developers have carried out testing of the landfill, I find myself in
agreement with the objectors that, having regard to the variety of materials, which
was deposited in old landfills, both legally and illegally, removing part of the landfill
for deposition elsewhere on the site, does not constitute an acceptable solution. It
should be noted that the developers do not consider that a waste licence is required for
this activity. On the other hand the objectors consider that if legislation currently in
the pipeline is implemented such activity would be licensable.
Condition 14 of my report of July 2006 was as follows:
“The proposed development shall provide for the complete removal of landfill
material from the site. The material shall be removed prior to the occupation
of any dwellings. Material shall be trucked to the berth at the northern
breakwater, being provided in compliance with Condition No. 6 above, for
shipment off the site. Details relating to this requirement shall be submitted to
the Planning Authority prior to the commencement of development. These
details shall comply with the requirements of the authority in relation to
method of removal, shipment and location of final disposal.
Reason: In order to ensure that landfill material on-site is dealt with in
accordance with the best modern practice and to ensure that any long-term
adverse environmental impact is avoided.”
PL27.EF2016/CF2002 An Bord Pleanála Page 121 of 136
If the landfill remains undisturbed, it would result in a loss of a number of houses, at
the northern part of the residential development.
I do not consider that removal of material for deposition on another part of the site,
constitutes an acceptable approach. I furthermore do not consider that the examples
given by the developers, at Fairview, Pottery Road /Johnstown Road and the N11 at
Bromley, are in any way comparable to what is proposed on the subject site. In none
of those cases was it proposed to build on land which had been stripped of landfill.
None of the sites immediately adjoin residential accommodation. The Fairview site is
located some distance from residential accommodation. The Pottery Road site is an
industrial development and does not relate to residential accommodation in any way.
The Bromley site is located on the eastern side of the N11 and again does not relate in
any way to residential accommodation. It is removal of landfill for the provision of a
road interchange.
I consider that the landfill requires removal from the site in full. This can best be
achieved by seaborne transport. It could be done in the immediate period following
the provision of the harbour and a berth development which would have the dual
usage of not only providing for the removal of the landfill by sea but also, if required,
the importation of beach nourishment material. This is referred to below.
I do not consider that the arguments put forward by the developers in relation to the
landfill are in any way convincing. While it would be possible to retain the landfill on
site I consider its removal would be far preferable having regard to the fact that
residential accommodation would be constructed immediately adjoining it. It is also
of some importance that any danger of erosion of the landfill, by the sea, is obviated.
Removal is, in my opinion, required. I know of no other site where it has been
proposed to retain a landfill, reposition part of it and build residential accommodation
on an original part of the landfill which has been removed to another position on the
same site. The proposed development provides an ideal opportunity to
comprehensively deal with a landfill, the contents of which are largely unknown and
which is located immediately on a coastline.
PL27.EF2016/CF2002 An Bord Pleanála Page 122 of 136
The developers statement that if the landfill was removed a similar amount of material
would be required to provide the existing land shape/contours that exist as a result of
the landfill, is not in my opinion, a requirement. Removal of the landfill will result
in reversion to the original contours. It would also result in the possibility of
archaeological investigation of this part of the site, which would otherwise remain
under the landfill.
In relation to the position regarding any necessary waste licenses, I consider that this
has been correctly outlined by the developers as not being required in relation to the
repositioning of 9,000 cubic metres from one part of the site to another. The
Environmental Protection Agency has been requested to comment to various aspects
by both the developers and by the objectors. I do not consider that the position
adopted by the Environmental Protection Agency lends any weight to the developers
argument for repositioning of waste material on site.
BEACH NOURISHMENT
Turning to Point No. 3 of the additional information request, An Bord Pleanála noted
the already restricted access to the site. An Bord Pleanála also expressed itself not
satisfied on the basis of submissions made that the required beach nourishment could
not be brought in by sea in order to mitigate any potential negative traffic impacts
resulting from transport by road.
Considerable detail was provided in written form and at the reopened oral hearing.
In relation to Point No. 3, Condition No. 6 of my report of 11th July 2006 was as
follows:
“Material required for beach nourishment shall be shipped to the harbour. For
this purpose a berth shall be provided adjoining the north breakwater, to
permit the discharge of nourishment material, for transport to the required
beach locations. Details of the berth and the haul route shall be submitted to
the Planning Authority for compliance with their requirements.
PL27.EF2016/CF2002 An Bord Pleanála Page 123 of 136
Reason: In order to reduce the impact of heavy goods vehicles in their annual
beach nourishment campaign.”
The option preferred by the developers is the nourishment of the beach by the
pumping of material, from barges, directly onto the beach, as occurred with the beach
nourishment already carried out to Bray Beach. The material for that nourishment at
Bray was obtained from the Codling Bank. A similar proposal has been put forward
by the developers. If such a method of beach nourishment was possible, I consider it
to be the ideal nourishment method. It does not require road transport. It does not
require transportation over extended distances and it has the distinct advantage of
constituting the same type of material, or very similar material as exists on Greystones
Beach at present. In this regard a suggested condition by the developer is, in my
opinion, reasonable, provided the requisite licence is obtainable.
In the event that a licence is not forthcoming from the Department of the Marine,
Communications and Natural Resources, I consider that beach nourishment should be
carried out with the importation of material by sea. Having considered all of the
detail submitted this, in my opinion, is the only satisfactory method of preventing the
continual incursion of heavy goods vehicles, on an annual basis, for a period of
several weeks, through a residential area, leading to a large area of public open space
and a public beach. The importation by sea and the transportation from a harbour
berth to the site, would, apart from the Codling Bank option, constitute the most
acceptable form of beach nourishment. The sourcing of material would appear to
have resulted in the developers considering that Ballyhorsey was the preferred option.
Having regard to the details submitted I consider that this constitutes a reasonable
proposition however the trucking of material through Greystones and through the site
itself to nourish the beach, would be highly undesirable.
While I consider the evidence of Professor Cooper to be of importance, that evidence
was based, in the main, on the development not being implemented. It pointed more
to the objectors opposition to the development rather than to the optimum mitigation
possible assuming the development was carried out.
PL27.EF2016/CF2002 An Bord Pleanála Page 124 of 136
The provision of a suitable berth and vessels to transport beach nourishment material,
does not, in my opinion, constitute an insurmountable problem. On the contrary I
consider that the use of seaborne transport, in the implementation of beach
nourishment, constitutes the only realistic nourishment method, obviously discounting
the Codling Bank alternative.
POINTS 4, 5 AND 6
Point 4.
This section of the letter of 14th August 2006, relates to Courtyard 1 and in particular
Blocks B and C and adjacent Terrace 13. The letter states that:
“The proposed development in this location would result in significant traffic
generation and a congested form of overdevelopment in this area of the site.
This would seriously impinge upon any meaningful use of the space as a
public square and result in a visually intrusive and dominant form of
development in relation to its harbour side setting and existing built fabric,
including residential properties.”
Point 5.
This also refers to Blocks B and C of adjacent Terrace 13 which:
“By reason of its design, scale and bulk fails to create an acceptable form of
urban/architectural treatment of this transitional area located between the
proposed new development and its receiving environment of generally smaller
scale Victorian seafront buildings, which include residential properties.”
The letter continued that:
“In relation to the issues raised at 4 and 5 it is considered that Blocks B and C
and adjacent Terrace 13 should be omitted from the proposed development.
The resultant free area should form a meaningful and open aspect of
PL27.EF2016/CF2002 An Bord Pleanála Page 125 of 136
harbourside public space. Block D should consequently be redesigned to
address both the enlarged public space and Basin 1, with commercial activity
on the ground floor facing the public space. Proposed underground car
parking at this location may be retained.”
The developers have responded to Points 4 and 5 and the requirement that Block B
and C and Terrace 13 be omitted from the proposed development by firstly omitting
these blocks and terrace and secondly by redesigning Block D. Finally the very much
enlarged public space has been redesigned.
Two vehicular access points onto the site are now proposed instead of the one
originally proposed. The eastern access point provides access to the eastern section of
the harbour including off-street car parking, the clubhouse compounds and the
clubhouses themselves.
The western access provides vehicular access to the remainder of the site.
In relation to the access points I consider that the splitting of vehicular access onto the
site is a considerable improvement over the provision of a single access point. It
responds positively to significant traffic generation and a congested form of
development, made in the letter of 14th August, at Point 4.
I do not consider that there would be any difficulty in relation to visibility from either
of the access points. It is, in my opinion, a splitting of traffic and as such a
segregation of traffic away from the large area of public open space resulting from the
omission of Blocks B and C and Terrace 13.
I consider that Block D has been successfully redesigned. It reasonably addresses the
enlarged public area and also Basin 1.
The large area of public open space created by the omission of development has
provided the opportunity for the effective splitting up of this area of open space into
distinct visual units with a coherence provided by a variety of devices such as
planting, mounding, street furniture and surface varation.
PL27.EF2016/CF2002 An Bord Pleanála Page 126 of 136
Removal of Blocks B and C and Terrace 13 has, in my opinion, permitted an adequate
separation of the proposed development from the receiving environment with
particular reference to the smaller scale Victorian seafront buildings, referred to at
Point 5 of the letter of August 2006. I think this aspect of the proposal has had the
most beneficial impact relative to the overall scheme fitting in to the receiving
environment.
Point 6.
This relates to the proposed clubhouses. It refers to their design, scale, height and
location in close proximity to the site boundary and existing residential property.
Reference is made to the clubhouses resulting in individually obtrusive forms of
development at the location. Reference is also made to a form of development that
might seriously injure the visual amenities of the area and residential amenities of
property in the vicinity.
In relation to the clubhouses generally it should be noted that they have been
redesigned and moved eastwards from the originally proposed position. They have
not been relocated on site. They are still located in close proximity to the site
boundary. This however is somewhat mitigated by the difference in level between the
site and the adjoining public road. The redesign of the buildings has largely obviated
any visual obtrusion at the location. As such the form of development would not, in
my opinion, seriously injure the visual amenities of the area.. Furthermore I do not
consider that the clubhouses as presently proposed would seriously injure the
residential amenities of property in the vicinity.
The letter of 14th August 2006 referred to the clubhouses as follows:
“The redesign of the scheme should also address the issues raised at 6 above,
which may require the relocation of the clubhouses and ancillary facilities to
an alternative location on the overall site.”
PL27.EF2016/CF2002 An Bord Pleanála Page 127 of 136
No proposal was put forward to relocate the clubhouses to an alternative location on
the site.
In my report of 11th July 2006 the following, in relation to the clubhouse development
is of relevance:
“Removing the clubhouses and associated boat yards from this section of the
site opens up the public domain to provide something akin to what exists at the
harbour at present, a reasonably large area of public open space addressing the
harbour and separating it from the protected structures on the southern side of
Beach Road/Cliff Road. This preserves the existing spatial relationship
between protected buildings and the harbour and the water. It also preserves
an extremely important element of public open space which would be lost if
the clubhouses and open storage areas were provided as proposed.
There is an ample amount of space available by the omission of Block 1, for
the erection of two-storey clubhouses, with a combined floor space of the
order of 1,200 square metres, and attendant open storage of boats. This
constitutes a desirable land use in replacement of Block 1. It has the benefits
of protecting the character and spatial arrangement of the harbour with
protected structures. It removes the development from too close proximity to
the protected structures. It provides the element of public open space referred
to earlier. It also provides a development which is acceptable relative to the
four dwellings on the western side of North Beach Road, which would
otherwise have been severely impacted by the erection of Block 1.”
It should be noted that, with the exception of the Greystones Sailing Club, all of the
other clubs which it is proposed to accommodate at the harbour, are satisfied with the
revised arrangements.
The sailing club have considerable concern in relation to the location of what is
proposed as their clubhouse. They are concerned with wave overtopping primarily.
They are also concerned that the main sailing areas will not be overseen from the
clubhouse.
PL27.EF2016/CF2002 An Bord Pleanála Page 128 of 136
In relation to wave overtopping this could, in my opinion, constitute a problem
however the developers have indicated that the design of the structure has taken this
into account. The issue of overseeing the sailing areas is not one which is amenable
to resolution. In this regard the existing situation is that the sailing club has
unrestricted visibility of the sailing areas. This will not obtain from the proposed
position within the harbour however it would not obtain from any position within the
harbour other than locating the sailing club directly on or adjoining the northern
breakwater. This is quite clearly not proposed.
In general I consider that the clubhouse proposal is acceptable, with the exception of
the sailing club. However as the sailing club constitutes part of the harbour users it is,
in layout terms, far preferable to have the clubhouse located with the remainder of the
clubhouses, having regard to the direct harbour side position, the availability of an
adjoining slipway and boat storage areas and off-street car parking. Therefore while I
considered that the omission of Block 1 in its entirety, would have provided an ideal
opportunity to relocate the clubhouses and attendant storage areas to that position, this
was not accepted in the letter of 14th August 2006 in which it was required that Block
D be retained and redesigned. Bearing this in mind I consider that the location of the
clubhouses is acceptable.
The final element of the letter of the 14th August 2006 relating to the redesign stated:
“The redesign undertaken in relation to the above shall result in a reduction in
the quantum of the overall development and associated traffic generation and
may require some redesign of other elements within the overall proposed
development whilst maintaining the integrity of the overall proposal.”
I consider that the integrity of the overall proposal has been fully maintained. The
quantum of development has been reduced. The reduction has not been great. While
Blocks B and C and adjacent Terrace 13 have been omitted, the reduction in the
number of residential units is approximately 9% of the total originally proposed.
There has also been a reduction in the amount of commercial floor space proposed.
PL27.EF2016/CF2002 An Bord Pleanála Page 129 of 136
As a result of the reduction in the quantum of the overall development there would be
an associated reduction in traffic generation. I consider that this is generally in line
with what was contained in Points 1 – 6 of the letter of 14th August 2006.
Therefore while the objectors consider that the overall reduction is not sufficient to
reduce traffic generation, nevertheless I consider that the scheme has been
considerably revised and that the quantum of both residential and commercial
development while not being greatly reduced, results in the integrity of the overall
proposal being maintained, as required by An Bord Pleanála.
While the reopened oral hearing dealt largely with issues raised in the additional
information requirement of An Bord Pleanála, there was reference to many aspects of
the development which had already been, in my opinion, sufficiently aired in the
initial hearing in 2006. In this regard I consider that reference to these issues is not
required as they have been sufficiently dealt with in the previous hearing and in
particular in my report of 11th July 2006.
CONCLUSION
I have already assessed the proposed Compulsory Purchase Order. My previous
assessment of the overall development, the subject of approval had been a
recommendation, to An Bord Pleanála, to approve the overall development under
Section 175 of the 2000 Act.
Having regard to the further information submitted, to the written submissions and to
the reopened oral hearing, I consider that the approval sought under Section 175 of
the Planning and Development Act 2000 should be granted subject to a number of
conditions.
The amended scheme does not conflict with the statutory planning documents
prepared by the Local Authority in relation to the development proposal. The proposal
as amended does not conflict with the proper planning and sustainable development of
the area or detrimentally affect the local environment, subject to appropriate
conditions.
PL27.EF2016/CF2002 An Bord Pleanála Page 130 of 136
Having regard to the requirements of An Bord Pleanála contained in the letter of 14 th
August 2006 the following reasons, considerations and conditions are considered
appropriate.
REASONS AND CONSIDERATIONS
Having regard to:
(a) The existing condition of Greystones Harbour,
(b) the central location of the site relative to the town of Greystones and its
rail line,
(c) the existing pattern and character of development in the vicinity,
(d) the provisions of the current Wicklow County Development Plan,
including the variation of that Plan and the provisions of the variation relating
to the site,
(e) the provisions of the Greystones/Delgany Local Area Plan,
it is considered that subject to compliance with conditions set out hereunder, the
proposed development;
(1) would not have significant adverse effects on the environment,
(2) constitutes an appropriate development proposal in terms of land
use, scale and visual amenity,
and would therefore be consistent with the proper planning and sustainable
development of the area.
PL27.EF2016/CF2002 An Bord Pleanála Page 131 of 136
CONDITIONS
1. Points of access to the site from the adjoining public road, Beach Road/Cliff
Road, shall be redesigned in accordance with the requirements of the planning
authority. In this regard prior to the commencement of development, a traffic
calming scheme shall have been implemented by the planning authority. The
scheme shall operate within the confines of the site, and on the surrounding
road network, within a 200 metre radius of Victoria Road/Beach Road. The
scheme shall commence on the R761, immediately to the west of the junction
of Victoria Road, New Road, Church Road. It shall provide for adequate
vehicular speed reduction and cyclist and pedestrian safety measures,
including adequate road signage and road and footpath surface design.
Reason: In the interest of pedestrian, cyclist and vehicular safety.
2. Prior to the commencement of development, Wicklow County Council shall
make an application for a Foreshore Licence to the Department of the Marine,
Communications and Natural Resources, to provide the necessary beach
nourishment material from the Codling Bank. Beach nourishment, from this
source, if available, shall be pumped from ship to shore, in accordance with
the requirements of the planning authority.
Reason: In the interest of the sustainment of the beach in a satisfactory
condition.
3. In the event that a Foreshore Licence, to provide for beach nourishment, as
required by Condition No. 2 above, is not capable of implementation, material
required for beach nourishment shall be shipped to the harbour. For this
purpose a berth shall be provided adjoining the north breakwater, to permit the
discharge of nourishment material, for transport to the required beach
PL27.EF2016/CF2002 An Bord Pleanála Page 132 of 136
locations. Details of the berth and the haul route shall be submitted to the
planning authority for compliance with their requirements.
Reason: In order to reduce the impact of heavy goods vehicles during their
annual beach nourishment campaign.
4. Boat maintenance and/or storage shall not be undertaken on either breakwater.
Reason:I n order to maintain the breakwaters for public use.
5. All excavations for the purposes of the construction of the development, shall
be monitored by a suitably qualified archaeologist. A monitoring report shall
be prepared in accordance with the requirements of the planning authority. A
copy of the report shall be submitted to the Department of the Environment,
Heritage and Local Government and to the Department of Marine,
Communications and Natural Resources. A copy shall also be made available
for inspection at the offices of the Local Authority.
Reason: To protect the archaeological and cultural heritage of the area.
6. The establishment of the batching plant and the casting plant shall be
monitored by a suitably qualified archaeologist. Both plants shall be located a
minimum of 25 metres to the south of Feature C, as denoted on the
geophysical survey of D'Arcy's Field. There shall be no removal of material
whatsoever from this part of the field. Removal of material from the
remainder of the field, with the establishment of a proposed borrow pit, shall
not occur unless and until a detailed archaeological investigation has been
carried out, the results of which are known, and made available to the
Department of the Environment, Heritage and Local Government. No work
shall be carried out by way of removal of material without a specific permit
from the Department of the Environment, Heritage and Local Government, if,
the detailed archaeological survey carried out as a requirement of this
condition, results in the discovery of archaeological material.
Reason: To protect the archaeological and cultural heritage of the area.
PL27.EF2016/CF2002 An Bord Pleanála Page 133 of 136
7. Demolition and construction works shall be confined between the hours of
08.00 and 18.00 hours Monday to Friday and 08.00 and 16.30 on Saturdays.
Construction shall not take place on Sundays and Bank Holidays.
Reason: To protect the amenities of residential properties in the vicinity
during the course of the works.
8. Prior to the commencement of demolition and construction works, detailed
codes of practice in relation to dust suppression, shall be drawn up by suitably
qualified personnel, in accordance with the requirements of the planning
authority. Contractors employed in the demolition and construction phases of
the development shall be required, by contract, to comply with these detailed
codes of practice. Prior to demolition works commencing, a detailed
inventory shall be carried out of all demolition materials, in order to identify
materials for reuse on site in the construction works. Demolition material shall
be reused to the maximum extent possible in the construction phase of the
development. Reusable materials, not used on site, shall be recycled
elsewhere, rather than being disposed of to a landfill. Details of the codes of
practice and the inventory of demolition materials required by this condition
shall be available for public inspection at the office of the Local Authority.
Reason: To protect the amenities of property in the vicinity and in the interest
of sustainable development.
9. The Gap Bridge shall be removed from the site in accordance with the
requirements of the planning authority and generally in accordance with any
requirements which the Department of the Environment, Heritage and Local
Government may have. Demolition material from the bridge shall be reused
to the maximum extent possible in the construction phase of the development.
Reusable material not used on site shall be recycled elsewhere rather than
being disposed of to landfill.
PL27.EF2016/CF2002 An Bord Pleanála Page 134 of 136
Reason: In the interest of public safety, having regard to the condition of the
bridge.
10. Details of water supply and drainage arrangements, including the disposal of
surface water, shall comply in full with the requirements of the planning
authority in the provision of such services.
Reason: In the interest of public health.
11. The proposed development shall provide for the complete removal of landfill
material from the site. The material shall be removed prior to the
commencement of the construction of dwellings. Materials shall be trucked to
a berth at the north breakwater, for shipment off the site. Details relating to
this requirement shall be submitted to the planning authority prior to the
commencement of development. These details shall comply with the
requirements of the authority in relation to method of removal, shipment and
location of final disposal.
Reason: In order to ensure that landfill material on-site is dealt with in
accordance with the best modern practice and to ensure that any long-term
adverse environmental impact is avoided.
12. The marina control building shall be reduced in height to one-storey. Details
of compliance with this condition shall be submitted to the planning authority.
Reason: In the interest of visual amenity.
13. Walling to the inner harbour and on the inner side of the northern and southern
breakwaters shall not be more than 0.5 metres in height. Alternatively the
proposed walling may be replaced with metal rails or chains, in accordance
with details to be submitted to the planning authority.
Reason: In the interest of visual amenity.
PL27.EF2016/CF2002 An Bord Pleanála Page 135 of 136
14. Nautical hazard lights shall be placed in the harbour, as required by the
Department of Marine, Communications and Natural Resources.
Reason: In the interest of marine safety.
15. Measures to permit public access to the Cliff Walk, during the course of the
works, shall be implemented, in accordance with the requirements of the
planning authority.
Reason: To maintain the recreational utility of the area during the
construction period.
16. Prior to the commencement of development, the local authority shall establish
a locally based liaison committee, which shall act as a forum for disseminating
information of planning and construction work relating to the overall
development. The committee shall be represented by the local authority, their
consultants and contractors and local residential and business interests.
Reason: To facilitate and promote the involvement of the local community in
ensuring that the development is being provided in accordance with
appropriate standards.
17. Sea kale on the site shall be relocated to a position to be agreed with the
planning authority.
Reason: In the interest of maintaining the species as local to the area.
_______________________
James Carroll
Planning Inspector
May, 2007. sg
PL27.EF2016/CF2002 An Bord Pleanála Page 136 of 136