AMS-02 Ground Handling Equipment (GHE) and Assembly Operations for the GHE. Ground Safety Review – Phase II September 8-10, 2008 Phil Mott. KHB 1700.7C Space Shuttle Payload Ground Safety Handbook SW-E-0002E Ground Support Equipment General Design Requirements - PowerPoint PPT Presentation

Transcript of AMS-02 Ground Handling Equipment (GHE) and Assembly Operations for the GHE

  • AMS-02 Ground Handling Equipment (GHE) andAssembly Operations for the GHEGround Safety Review Phase IISeptember 8-10, 2008Phil Mott

    AMS-02 Phase II Safety Review

  • Documents Governing GHE Design

    KHB 1700.7CSpace Shuttle Payload Ground Safety HandbookSW-E-0002EGround Support Equipment General Design RequirementsNASA-STD 8719.9 formerly NSS/GO-1740.9BStandard for Lifting Devices and Equipment

    AMS-02 Phase II Safety Review

  • Primary Support Stand (PSS)Used for payload integration and shippingTwo configurations: Low & HighConstructed with Aluminum 6061Covers are Alumalite (painted aluminum face sheet with plastic corrugate)Factors of Safety2 on yield3 on ultimate

    AMS-02 Phase II Safety Review

  • Primary Support Stand (PSS) Low ConfigurationShipping Configuration195 x 125 x 117 highTop Cover is removed as one piece

    AMS-02 Phase II Safety Review

  • Primary Support Stand (PSS) High ConfigurationAssembly/Integration Configuration195 x 125 x 166 high

    AMS-02 Phase II Safety Review

  • Primary Lifting Fixture (PLF)Used to lift the PSS and AMS-02Welded steel A36 structureWLL: 26,800 lbsFactors of Safety3 on yield5 on ultimateInitial proof load to 2X WLLAnnual load test to 1X WLL

    AMS-02 Phase II Safety Review

  • Multi Purpose Lifting Fixture (MPLF)Used to lift the Lower USS (LUSS) into place on the Upper USS and to lift the PAS into place for attachmentWelded steel A36 structureWLL: 7000 lbsFactors of Safety:3 on yield5 on ultimateInitial proof load to 2X WLLAnnual load test to 1X WLL

    AMS-02 Phase II Safety Review

  • Lower USS (LUSS) Shipping FixtureUsed to ship/move/install the Lower USSCan be moved with forklift or crane/MPLFWelded steel A36 structure

    AMS-02 Phase II Safety Review

  • Other HardwareCan be moved with forklift, crane, air pallet, hand carts, or by handAll lifting hardware will meet NASA-STD 8719.9

    TRD GSEAir Supply/CompressorK Bottles

    AMS-02 Phase II Safety Review

  • Assembly Operations

    AMS-02 Phase II Safety Review

  • Arrival at KSC Unload/Prep in the SSPF AirlockCrane PSS/Upper USS-02.Fork/Crane Lower USS-02Fork/Crane all other Hardware including CGSE

    AMS-02 Phase II Safety Review

  • Arrival at KSC Unload/Prep in the SSPF Airlock (cont)

    AMS-02 Phase II Safety Review

  • Move Into SSPF Footprint 7Crane or air pallet PSS/USS-02Crane, fork, or air pallet all other hardware

    AMS-02 Phase II Safety Review

  • UnpackingRemove the upper cover from the PSS using the MPLF or slingsRemove the side panels from the PSSRemove the cover from the LUSS Shipping FixtureSet up Cryosystem GSE (CGSE)

    AMS-02 Phase II Safety Review

  • PSS Preparation for AMS-02 Assembly/IntegrationInstall Upper Columns and Beams on the PSS

    AMS-02 Phase II Safety Review

  • PSS Preparation for AMS-02 Assembly/IntegrationRaise the PSS/Upper USS-02 to the high positionInstall supports

    AMS-02 Phase II Safety Review

  • Installation of the Lower USS onto the Upper USSFork the Lower USS under the Upper USS in the PSS

    AMS-02 Phase II Safety Review

  • Installation of the Lower USS onto the Upper USS (cont)Lift the Lower USS into position using the MPLFPosition hydraulic jacks under the Lower USS for support and final positioningAttach Lower USS to Upper USS with pins and bolts

    AMS-02 Phase II Safety Review

  • Installation of the PASWeight of PAS = 220 lbsPAS will be installed using the LUSS, overhead crane, and bottle jacksEBCSPAS

    AMS-02 Phase II Safety Review

  • Installation of the PAS (cont)Procedure similar to Lower USS installation Details in workPlace PAS on top of LUSS Shipping FixturePlace under payload using forkliftRaise and rotate using bottle jacks

    AMS-02 Phase II Safety Review

  • Installation of the KeelWeight of Keel = 67 lbsKeel will be a 2 person manual lift and bolts installed by a 3rd person

    AMS-02 Phase II Safety Review