ALMA Integrated Computing Team Coordination & Planning Meeting #3 Socorro, 17-19 June 2014 New AM...
-
Upload
cathleen-peters -
Category
Documents
-
view
215 -
download
3
Transcript of ALMA Integrated Computing Team Coordination & Planning Meeting #3 Socorro, 17-19 June 2014 New AM...
ALMA Integrated Computing Team
Coordination & Planning Meeting #3 Socorro, 17-19 June 2014
New AM organization and improving the acceptance procedure
Masao Saito (JAO AM)
Daniel Espada (JAO Interim Deputy AM)
ICT-CPM3 17-19 June 2014
2013.12 – 2014.4
AM: Masao Saito
Deputy AM: Itziar de Gregorio
2014.5 – 2014.6
AM: Masao Saito
Interim Deputy AM: Daniel Espada
2014.7 – 2014.8
Interim AM: Daniel Espada
Acceptance Management Organization
ICT-CPM3 17-19 June 2014
Acceptance Since CPM#2
Cycle 2 started on time thanks to all of you!! Acceptance Procedure is established. TRR/ACRV held on Friday 11 am (CLT)
Acceptance Branch Acceptance Date Observatory Milestone
A10.2R 2013-12-02 Cycle 2 APRC
201403-CYCLE2-OFF 2014-03-28 Cycle 2 SB generationstart of Cycle 2
201404-CYCLE2-ON 2014-05-30 start of Cycle 2
201405-CYCLE2-OFF 2014-05-23 start of Cycle 2
201406-CYCLE2-OFF 2014-06-27 start of Cycle 2
ICT-CPM3 17-19 June 2014
1. Integrated Acceptance Calendar: Our Foundation1. Schedule, Scope is clearer than before.
2. Better requirements deadline is given
3. BUT, IT IS NOT EASY TO UNDERSTAND AT A FIRST LOOK
2. Acceptance wiki: Focal point of each acceptance1. Better organized, documents, structures etc.
3. SSG wiki:1. Clear responsibility for each subsystem scientist in each
subsystem
4. AM-RM meeting/regular contact1. Less miscommunication between ICT and JAO science
5. SEQM meeting1. Better quality control for the overall process
Improvement Efforts since CPM#2
ICT-CPM3 17-19 June 2014
Robust process After TRR, the software is tested internally before going public.
After ACRV, the software goes public (e.g. source catalogue) ARC deployment
Invite ARC contacts to TRR to share deployment info. Kanban
Very successful to track status of ICT-tickets. Pipeline Heuristics (originally not in the JAO acceptance)
AM accepts the software with SciOPS approval New Subsystem
Dashboard (Stuartt), Integrated Reporting (Lars)
New things in the acceptance after CPM#2
ICT-CPM3 17-19 June 2014
Bugs are well followed in Kanban if labeled correctly.
Acceptance Status
Acceptance Branch SubmittedAcceptedIn progress
Implemented, Verifying
Resolved, Validating
Closed
201403-CYCLE2-OFF 1 4 3 210
201404-CYCLE2-ON 3 2 5 207
201405-CYCLE2-OFF 2 3 13 108
201406-CYCLE2-OFF 2 5 20 15
ICT-CPM3 17-19 June 2014
Too many PRTSIR tickets assigned to softwareNew procedure is underway
Science Portal RequirementToO triger etc. needed every cycle start.
Pipeline infrastructurePipeline developer team proposed a reasonable
procedure.
ARC deploymentDetailed Procedure is needed. Separate discussion.
Remaining Issues