2006 – 2008 Projects
Annual Revenue + Carryover 815,157
Projects
> Upgrade PA system (completed) $36,650 ($36,650)
> Upgrade fire alarm system (postponed) $0 ($0)
> Install security surveillance system (completed) $53,826 ($53,826)
> Upgrade network infrastructure (completed) $21,200 ($21,200)
Annual Total $111,476 ($111,476)
Revenue Carryover $703,681
Cumulative Revenue $815,157
Cumulative Expense In 07/08 Dollars $111,476
Cumulative Expense In Actual Dollars $111,476
2008 – 2009 Projects
Annual Revenue + Carryover $1,418,838
Projects > Flood mitigation & drainage improvements $859,230 ($810,595) > Upgrade fire alarm system $216,990 ($204,707) > Expand updated phone and intercom systems $67,117 ($63,318) > Expand network infrastructure $189,740
($179,000) Annual Total
$1,333,077($1,257,620)
Revenue Carryover $85,761
Cumulative Revenue $1,530,314Cumulative Expense In 07/08 Dollars $1,369,096 Cumulative Expense In Actual Dollars $1,444,553
2009 – 2010 Projects
Annual Revenue + Carryover $800,918
Projects > Repave parking lots & roadways $238,203 ($212,000) > Upgrade electrical distribution system $85,753 ($76,320) > Air condition classrooms (phase 1) $418,231 ($372,224)
Annual Total $742,187 ($660,544)
Revenue Carryover $58,731
Cumulative Revenue $2,245,471Cumulative Expense In 07/08 Dollars $2,029,640 Cumulative Expense In Actual Dollars $2,186,740
2010 – 2011 Projects
Annual Revenue + Carryover $773,888
Projects
> Air condition classrooms (phase 2) $443,325 ($372,724)
Annual Total $443,325 ($372,724)
Revenue Carryover $330,563
Cumulative Revenue $2,960,628
Cumulative Expense In 07/08 Dollars $2,401,864
Cumulative Expense In Actual Dollars $2,630,065
2011 – 2012 Projects
Annual Revenue + Carryover $1,045,720
Projects > Air condition classrooms (phase 3) $489,925 ($372,224)
> Air condition classrooms (phase 4) $489,925 ($372,244)Annual Total $979,850 ($744,448)
Revenue Carryover $65,870
Cumulative Revenue $3,675,785Cumulative Expense In 07/08 Dollars $3,146,312 Cumulative Expense In Actual Dollars $3,609,915
2012 – 2013 Projects
Annual Revenue + Carryover $781,027
Projects
> Air condition auditorium $583,386 ($435,940)
Annual Total $583,386 ($435,940)
Revenue Carryover $197,641
Cumulative Revenue $4,390,942
Cumulative Expense In 07/08 Dollars $3, 582,252
Cumulative Expense In Actual Dollars $4,193,301
2013 – 2014 Projects
Annual Revenue + Carryover $912,798
Projects
> Air condition gym $542,089 ($382,151)
> Roof maintenance/repair $105,254 ($74,200)Annual Total $647,343 ($456,351)
Revenue Carryover $265,455
Cumulative Revenue $5,106,099
Cumulative Expense In 07/08 Dollars $4,038,603
Cumulative Expense In Actual Dollars $4,840,644
2014 – 2015 Projects
Annual Revenue + Carryover $980,612
Projects
> Upgrade interior classroom & corridor lighting $393,680 (261,820)
> Suspended ceiling installation/upgrade (phase 1) $534,130 ($335,120)
Annual Total $927,810 ($617,047)
Revenue Carryover $52,802
Cumulative Revenue $5,821,256
Cumulative Expense In 07/08 Dollars $4,655,650
Cumulative Expense In Actual Dollars $5,768,454
2015 – 2016 Projects
Annual Revenue + Carryover $767,959
Projects
> Suspended ceiling installation/upgrade (phase 2) $566,178 ($355,227)
Annual Total $566,178 ($355,227)
Revenue Carryover $2-1,781
Cumulative Revenue $6,536,413
Cumulative Expense In 07/08 Dollars $5,010,877
Cumulative Expense In Actual Dollars $6,334,632
2016 – 2017 Projects
Annual Revenue + Carryover $992,395
Projects
> Replace windows & exterior doors (phase 1) $743,202 ($439,900)
Annual Total $743,202 ($439,900)
Revenue Carryover $173,736
Cumulative Revenue $7,251,570
Cumulative Expense In 07/08 Dollars $5,450,777
Cumulative Expense In Actual Dollars $7,077,834
2017 – 2018 Projects
Annual Revenue + Carryover $888,893
Projects
> Replace windows & exterior doors (phase 2) $787,794 ($439,900)
Annual Total $787,794 ($439,900)
Revenue Carryover $101,099
Cumulative Revenue $7,966,727
Cumulative Expense In 07/08 Dollars $5,890,677
Cumulative Expense In Actual Dollars $7,865,628
2018 – 2019 Projects
Annual Revenue + Carryover $816,256
Projects
> Replace restroom fixtures & partitions $704,269 ($371,000)
Annual Total $704,269 ($371,000)
Revenue Carryover $111,987
Cumulative Revenue $8,681,884
Cumulative Expense In 07/08 Dollars $6,346,477
Cumulative Expense In Actual Dollars $8,569,897
2019 – 2020 Projects
Annual Revenue + Carryover $827,144
Projects
> Interior & exterior painting $170,634 ($84,800)
> Replace interior floor surfaces (partial) $191,964 ($95,400)
> Resurface track $287,945 ($143,100)
Annual Total $650,543 ($323,300)
Revenue Carryover $176,601
Cumulative Revenue $9,397,041
Cumulative Expense In 07/08 Dollars $6,669,777
Cumulative Expense In Actual Dollars $9,220,440
2020 – 2021 Projects
Annual Revenue + Carryover $891,758
Projects
> Replace baseball field lighting $418,267 ($196,100)
Annual Total $418,267 ($196,100)
Revenue Carryover $473,491
Cumulative Revenue $10,112,198
Cumulative Expense In 07/08 Dollars $6,865,877
Cumulative Expense In Actual Dollars $9,638,707
2021 – 2022 Projects
Annual Revenue + Carryover $1,188,648
Projects
> Renovate auditorium stage $958,623 ($424,000)
Annual Total $958,623 ($424,000)
Revenue Carryover $230,025
Cumulative Revenue $10,827,355
Cumulative Expense In 07/08 Dollars $7,289,877
Cumulative Expense In Actual Dollars $10,597,330
2022 – 2023 Projects
Annual Revenue + Carryover $945,182
Projects
> None $0 ($0)
Annual Total $0 ($0)
Revenue Carryover $945,182
Cumulative Revenue $11,542,512
Cumulative Expense In 07/08 Dollars $7,289,877
Cumulative Expense In Actual Dollars $10,597,330
2023 – 2024 Projects
Annual Revenue + Carryover $1,660,339
Projects
> None $0 ($0)
Annual Total $0 ($0)
Revenue Carryover $1,660,339
Cumulative Revenue $12,257,669
Cumulative Expense In 07/08 Dollars $7,289,877
Cumulative Expense In Actual Dollars $10,597,330
2024 – 2025 Projects
Annual Revenue + Carryover $2,375,496
Projects
> Construct athletic field house $2,019,580 ($795,000)
Annual Total $2,019,580 ($795,000)
Revenue Carryover $355,916
Cumulative Revenue $12,972,826
Cumulative Expense In 07/08 Dollars $8,084,877
Cumulative Expense In Actual Dollars $12,616,910
Recap
> $8,084,877 total estimated cost in 2007-2008 dollars
> 17 years to accomplish with pay-as-you-go
> Assumes a 6% annual inflation
> $12,616,910 total estimated cost in actual dollars due to completion over 17
years
> No contingency included for unknown problems (behind the walls and
under the floors)
> Life cycles on some components will be reached before the plan is completed
> This plan does not address routine maintenance and repair (depreciation)