2006 – 2008 Projects

Annual Revenue + Carryover 815,157

Projects

> Upgrade PA system (completed) $36,650 ($36,650)

> Upgrade fire alarm system (postponed) $0 ($0)

> Install security surveillance system (completed) $53,826 ($53,826)

> Upgrade network infrastructure (completed) $21,200 ($21,200)

Annual Total $111,476 ($111,476)

Revenue Carryover $703,681

Cumulative Revenue $815,157

Cumulative Expense In 07/08 Dollars $111,476

Cumulative Expense In Actual Dollars $111,476

Page 3: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2008 – 2009 Projects

Annual Revenue + Carryover $1,418,838

Projects > Flood mitigation & drainage improvements $859,230 ($810,595) > Upgrade fire alarm system $216,990 ($204,707) > Expand updated phone and intercom systems $67,117 ($63,318) > Expand network infrastructure $189,740

($179,000) Annual Total

$1,333,077($1,257,620)

Revenue Carryover $85,761

Cumulative Revenue $1,530,314Cumulative Expense In 07/08 Dollars $1,369,096 Cumulative Expense In Actual Dollars $1,444,553

Page 4: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2009 – 2010 Projects

Annual Revenue + Carryover $800,918

Projects > Repave parking lots & roadways $238,203 ($212,000) > Upgrade electrical distribution system $85,753 ($76,320) > Air condition classrooms (phase 1) $418,231 ($372,224)

Annual Total $742,187 ($660,544)

Revenue Carryover $58,731

Cumulative Revenue $2,245,471Cumulative Expense In 07/08 Dollars $2,029,640 Cumulative Expense In Actual Dollars $2,186,740

Page 5: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2010 – 2011 Projects

Annual Revenue + Carryover $773,888

Projects

> Air condition classrooms (phase 2) $443,325 ($372,724)

Annual Total $443,325 ($372,724)

Revenue Carryover $330,563

Cumulative Revenue $2,960,628

Cumulative Expense In 07/08 Dollars $2,401,864

Cumulative Expense In Actual Dollars $2,630,065

Page 6: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2011 – 2012 Projects

Annual Revenue + Carryover $1,045,720

Projects > Air condition classrooms (phase 3) $489,925 ($372,224)

> Air condition classrooms (phase 4) $489,925 ($372,244)Annual Total $979,850 ($744,448)

Revenue Carryover $65,870

Cumulative Revenue $3,675,785Cumulative Expense In 07/08 Dollars $3,146,312 Cumulative Expense In Actual Dollars $3,609,915

Page 7: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2012 – 2013 Projects

Annual Revenue + Carryover $781,027

Projects

> Air condition auditorium $583,386 ($435,940)

Annual Total $583,386 ($435,940)

Revenue Carryover $197,641

Cumulative Revenue $4,390,942

Cumulative Expense In 07/08 Dollars $3, 582,252

Cumulative Expense In Actual Dollars $4,193,301

Page 8: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2013 – 2014 Projects

Annual Revenue + Carryover $912,798

Projects

> Air condition gym $542,089 ($382,151)

> Roof maintenance/repair $105,254 ($74,200)Annual Total $647,343 ($456,351)

Revenue Carryover $265,455

Cumulative Revenue $5,106,099

Cumulative Expense In 07/08 Dollars $4,038,603

Cumulative Expense In Actual Dollars $4,840,644

Page 9: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2014 – 2015 Projects

Annual Revenue + Carryover $980,612

Projects

> Upgrade interior classroom & corridor lighting $393,680 (261,820)

> Suspended ceiling installation/upgrade (phase 1) $534,130 ($335,120)

Annual Total $927,810 ($617,047)

Revenue Carryover $52,802

Cumulative Revenue $5,821,256

Cumulative Expense In 07/08 Dollars $4,655,650

Cumulative Expense In Actual Dollars $5,768,454

Page 10: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2015 – 2016 Projects

Annual Revenue + Carryover $767,959

Projects

> Suspended ceiling installation/upgrade (phase 2) $566,178 ($355,227)

Annual Total $566,178 ($355,227)

Revenue Carryover $2-1,781

Cumulative Revenue $6,536,413

Cumulative Expense In 07/08 Dollars $5,010,877

Cumulative Expense In Actual Dollars $6,334,632

Page 11: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2016 – 2017 Projects

Annual Revenue + Carryover $992,395

Projects

> Replace windows & exterior doors (phase 1) $743,202 ($439,900)

Annual Total $743,202 ($439,900)

Revenue Carryover $173,736

Cumulative Revenue $7,251,570

Cumulative Expense In 07/08 Dollars $5,450,777

Cumulative Expense In Actual Dollars $7,077,834

Page 12: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2017 – 2018 Projects

Annual Revenue + Carryover $888,893

Projects

> Replace windows & exterior doors (phase 2) $787,794 ($439,900)

Annual Total $787,794 ($439,900)

Revenue Carryover $101,099

Cumulative Revenue $7,966,727

Cumulative Expense In 07/08 Dollars $5,890,677

Cumulative Expense In Actual Dollars $7,865,628

Page 13: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2018 – 2019 Projects

Annual Revenue + Carryover $816,256

Projects

> Replace restroom fixtures & partitions $704,269 ($371,000)

Annual Total $704,269 ($371,000)

Revenue Carryover $111,987

Cumulative Revenue $8,681,884

Cumulative Expense In 07/08 Dollars $6,346,477

Cumulative Expense In Actual Dollars $8,569,897

Page 14: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2019 – 2020 Projects

Annual Revenue + Carryover $827,144

Projects

> Interior & exterior painting $170,634 ($84,800)

> Replace interior floor surfaces (partial) $191,964 ($95,400)

> Resurface track $287,945 ($143,100)

Annual Total $650,543 ($323,300)

Revenue Carryover $176,601

Cumulative Revenue $9,397,041

Cumulative Expense In 07/08 Dollars $6,669,777

Cumulative Expense In Actual Dollars $9,220,440

Page 15: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2020 – 2021 Projects

Annual Revenue + Carryover $891,758

Projects

> Replace baseball field lighting $418,267 ($196,100)

Annual Total $418,267 ($196,100)

Revenue Carryover $473,491

Cumulative Revenue $10,112,198

Cumulative Expense In 07/08 Dollars $6,865,877

Cumulative Expense In Actual Dollars $9,638,707

Page 16: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2021 – 2022 Projects

Annual Revenue + Carryover $1,188,648

Projects

> Renovate auditorium stage $958,623 ($424,000)

Annual Total $958,623 ($424,000)

Revenue Carryover $230,025

Cumulative Revenue $10,827,355

Cumulative Expense In 07/08 Dollars $7,289,877

Cumulative Expense In Actual Dollars $10,597,330

Page 17: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2022 – 2023 Projects

Annual Revenue + Carryover $945,182

Projects

> None $0 ($0)

Annual Total $0 ($0)

Revenue Carryover $945,182

Cumulative Revenue $11,542,512

Cumulative Expense In 07/08 Dollars $7,289,877

Cumulative Expense In Actual Dollars $10,597,330

Page 18: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2023 – 2024 Projects

Annual Revenue + Carryover $1,660,339

Projects

> None $0 ($0)

Annual Total $0 ($0)

Revenue Carryover $1,660,339

Cumulative Revenue $12,257,669

Cumulative Expense In 07/08 Dollars $7,289,877

Cumulative Expense In Actual Dollars $10,597,330

Page 19: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

2024 – 2025 Projects

Annual Revenue + Carryover $2,375,496

Projects

> Construct athletic field house $2,019,580 ($795,000)

Annual Total $2,019,580 ($795,000)

Revenue Carryover $355,916

Cumulative Revenue $12,972,826

Cumulative Expense In 07/08 Dollars $8,084,877

Cumulative Expense In Actual Dollars $12,616,910

Page 20: ALLEGHANY HIGH SCHOOL Facility Improvement Plan 8/12/08.

Recap

> $8,084,877 total estimated cost in 2007-2008 dollars

> 17 years to accomplish with pay-as-you-go

> Assumes a 6% annual inflation

> $12,616,910 total estimated cost in actual dollars due to completion over 17

years

> No contingency included for unknown problems (behind the walls and

under the floors)

> Life cycles on some components will be reached before the plan is completed