All CMS 30 May07 TSV
1
All CMS 330 May 2007
LHC machineCMS ProgressOverall Schedule
All CMS 30 May07 TSV
2
News on the Machine
Update on Triplets http://user.web.cern.ch/User/QuickLinks/Announcements/2007/LHCInnerTriplet_4.htmlFrom CERN Homepage and Fermilab Today.
Proposed to add to each Q1 magnet and each Q3 magnet a set of four cartridges that can absorb the longitudinal force generated during the pressure test. The solution was presented to a team of experts during a review at CERN on April 24 and 25. Since then the design of the cartridge system has been refined and parts needed for the cartridges and their installation have been ordered.
The installation of the cartridges in the Q1 and Q3 magnet of at least one inner triplet is scheduled to be complete in
early June, in time for the next pressure test.
DG, DDG and LHC Project Leader to meet soon. Most likely will be given information soon afterwards.
All CMS 30 May07 TSV
3
CMS progressUX: 2 DT sectors in YB0 commissioned with cosmics. All 18 EB- SMs inserted, YB0 services installation ongoing (showing ~ 3 week
delay). Started installing tracker radial cable trays this week and start cabling of S1 towards the end of this week/beginning next week.
HF+ commissioned. Conducting a global run now
SX: YB-1 commissioned using cosmics (almost done), RE-2 chambers mounted - testing and commissioning. Cabling of YB-2 will finish soon. RPC HV cabling end-
June.
Tracker: Cosmics data being taken. Started process of going cold last week. Taking cosmics at 10C.
ECAL: EB- installed, 25 SMs integrated (electronics). 20 supercrystals mounted on ‘Dee4’. Over EE 2500 crystals delivered. Finalize schedule for final order (this week).
All CMS 30 May07 TSV
4
SX: DT Commissioning YB-1
The Minus-end Muon Systems in SX5 being commissioned using
cosmics
All CMS 30 May07 TSV
5
UX: DT Commissioning YB0
Sector 12
All CMS 30 May07 TSV
6
HF+ in UX Commissioned
Bunch crossings, 1bx =25ns
Eta towers
Ph
i to
wer
s
Average response of towers to LED signals
Average LED event shape
HF+ connected to FEDs in USC
All CMS 30 May07 TSV
7
EB- Installation Completed (22 May)
All CMS 30 May07 TSV
8
Tracker “Chilling Out”
Thurs 24 May18:00
All CMS 30 May07 TSV
9
All 20 Supercrystals mounted on “Dee4”
All CMS 30 May07 TSV
10
YB0 Services Installation
All CMS 30 May07 TSV
11
Overall CMS Schedule: v35.3
March
April
May
June
July
Aug.
Sep.
Oct.
Nov.
1) Detector Installation, Commissioning & Operation
First Global Readout Test
Barrel ECAL Inserted
Tracker InsertedTrigger/DAQ Ready for System
Commissioning
CMS Ready to Close
2) Preparation of Software, Computing and Physics Analysis
HLT exercise complete
Pre-CSA07 Computing Software Analysis Challenge
2007 Physics Analyses completed
CSA07
All CMS Systems Ready for Data Taking
All CMS 30 May07 TSV
12
Points for DiscussionDiscuss new optimized CMS schedule during MB of 11 June
- also use for AR, CMS Week and CR (involve wide constituency)
Annual Reviews: 13-15 June, agenda sent out this morning.
CMS Week: 18-22 June, Plenary sessions in 2 parts. Under construction.
SLHC: need to prepare the next steps. Formulate a proposal by June MB ?
RPC_RE Workshop: 25, 26 June at CERN - invite all interested parties.
SLIMOS shifts - several incidents point to the need to start such shifts - will now actively canvas for volunteers (must not be solely people usually busy at Point 5 or on other critical path activities)