Alkali 31

5
 April 25, 2 012 IAD REPORT -2012-12-005 FOR : ABETO A. UY  Chairman and CEO FROM : Internal Audit Department RE : Review of Paint Line Cleaning Chemical (ALKALI Cleaner) at PSCC Cabuyao Cc : AVE, BMY, ACY, EDD  _______ ____ We submit the result of the review of Paint Line Cleaning Chemical (Alkali Cleaner) transaction at PSCC Cabuyao Plant. The objectives are as follows: 1. Dete rmin e why PS CC shi fted t o a new c lean ing pr ocess 2. Chec k if supp liers p roto col is fol lowe d duri ng pro duct ion 3. Comp liance to re ceiv ing pro ced ures o f chemical s. Background: PSCC was using a Conventional System with chemical supplied by Philippine HENKEL before 2007. Another system, Dry-in-Place was introduced on February 01, 2007 in which the chemicals were supplied by Philippine Parkerizing Inc until now. Both systems were using chemicals in cleaning the surface of the metal in the pre treatment stage. Audit Findings: 1. We coo rdinated a nd interviewed personnel at the plant, b ut effo rts remain fu tile as of to day in the search for any documentation or memorandum indicating approval by EXCOM in the change of PSCC Cleaning line process. 2. De vi at io n fr om supp li er’ s pr ot oc ol star te d on March 26 , 20 09 ba se d on PSCC QA/QC Department Checklist Form. We did not find any memorandum or recommendations for such deviation duly approved by EXCOM. Prepared by Reviewed by Approved by ED Jao/ TK Y ap Rafael D Salazar Getre Y Pechayco Internal Auditors Senior Audit Supervisor Internal Audit Head  Internal Audit Department

Transcript of Alkali 31

Page 1: Alkali 31

7/28/2019 Alkali 31

http://slidepdf.com/reader/full/alkali-31 1/5

 April 25, 2012IAD REPORT -2012-12-005

FOR : ABETO A. UY  Chairman and CEO

FROM : Internal Audit Department

RE : Review of Paint Line Cleaning Chemical (ALKALI Cleaner) at PSCC Cabuyao

Cc : AVE, BMY, ACY, EDD _____________________________________________________________________________ 

We submit the result of the review of Paint Line Cleaning Chemical (Alkali Cleaner) transaction atPSCC Cabuyao Plant.

The objectives are as follows:

1. Determine why PSCC shifted to a new cleaning process2. Check if suppliers protocol is followed during production3. Compliance to receiving procedures of chemicals.

Background:

PSCC was using a Conventional System with chemical supplied by Philippine HENKEL before2007. Another system, Dry-in-Place was introduced on February 01, 2007 in which the chemicalswere supplied by Philippine Parkerizing Inc until now. Both systems were using chemicals incleaning the surface of the metal in the pre treatment stage.

Audit Findings:

1. We coordinated and interviewed personnel at the plant, but efforts remain futile as of today inthe search for any documentation or memorandum indicating approval by EXCOM in thechange of PSCC Cleaning line process.

2. Deviation from supplier’s protocol started on March 26, 2009 based on PSCC QA/QCDepartment Checklist Form. We did not find any memorandum or recommendations for suchdeviation duly approved by EXCOM.

Prepared by Reviewed by Approved by

ED Jao/ TK Yap Rafael D Salazar Getre Y PechaycoInternal Auditors Senior Audit Supervisor Internal Audit Head  

Internal Audit Department

Page 2: Alkali 31

7/28/2019 Alkali 31

http://slidepdf.com/reader/full/alkali-31 2/5

Details of the Audit Findings

A. Change in Cleaning Process

1. Mr. Nestor I. Cabrera’s (Former PSCC Plant Manager) letter addressed to AGBU bothHENKEL and Parkerizing products underwent DIP process and manifested greatimprovements of the painted products compared to conventional approach in the pretreatment of PLF coils in the continuous color line (CPL) of PSCC. The letter also noted thatthe Philippine Parkerizing Chemicals is cheaper than Henkel.(Refer Annex A)

2. PSCC Quality Control Department conducted a cost comparison between Conventional andDry in Place in the pre treatment stage. Both processes have the same consumption of chemical per metric ton where, cost of chemicals of Philippine Parkerizing was lessexpensive than Henkel. (Refer Annex B)

3.  A fax message on October 9, 2007 shows that Mr. NI Cabrera instructed Ms. EvelinaDiocampo Technical Services Specialist under the office of the Chairman and Ms.Juliet P 

 Alforja PSCC Assistant QC Manager to draft a protocol for protection of PSCC’s interest.(Refer Annex C))

 

 AUDIT FINDINGS Number 1 :

We did not find any documentation or memorandum indicating approval by EXCOM or TopManagement the change to the new process.

AUDITEE’S COMMENTS:

Mr. Antonio C. Yee – Plant Manger (OIC)

a. Philippine Parkerizing has provided the comparison of the conventional versus the Dry inplace process.

b. Based on the comparison, three (3) activities only for Dry in Place versus five (5) activities for old conventional.

c. Dry in Place - cost of operating is economical versus conventional. No waste is producecompared to old (conventional) with more sludge and chemicals for treatment are needed for waste treatment.

d. Parkerizing and PSCC Protocol was established during the time of Mr. Nestor Cabrerasometimes January 24, 2008.

e. Technical Reports conducted sometimes March 26, 2008 as trial run.f. Another Technical Report conducted sometimes on April 30, 2008 a trial run.g. Commercial run was initiated last July 2008 by ACY and JRA.

(See attached Audit feedback form of Mr. Antonio Yee and its attachments)

Mr. Jenny Anyayahan – Production Manager 

a. We cannot provide the other documents but we have a history during transition of conventional to DIP process. To wit;

Page 3: Alkali 31

7/28/2019 Alkali 31

http://slidepdf.com/reader/full/alkali-31 3/5

• Initial meeting / discussion with HENKEL, Parkerizing and CHEMETAL regarding Dry in

Place January 2007.

• January 30,31,2007 – Simulation test of DIP chemicals made by Parkerizing See attached

report of Parkerizing dated April 19, 2007.

• HENKEL Presentation of DIP Pre- Treatment Process February 7, 2007

• Start of CPL line modification for DIP process February 2007 onwards• Laboratory testing and evaluation of DIP chemicals from three (3) suppliers March 2007

• DIP chemicals from three supplier for trial run arrived at PSCC but trial run was not

materialized due to PMT and water requirement July 2007

• Procurement of Boiler and 8 gallons DI water equipment September 2007

• Boiler and 8 gallons DI water equipment installed December 2007

• Trial run of HENKEL DIP chemicals January 24, 2008

• Trial run of Parkerizing DIP chemicals

B. During that time based from what we have gathered from our paint supplier we are the onlyone Painting company that still using conventional process in CPL pre treatment.

C. We are far behind from our competitor since they are already using Dry in Place treatmentprocess.

D. Before we start the trial run Henkel and Parkerizing there were several study and seminarsconducted by the two suppliers. See attached seminars reading materials, however we cannotprovide the other documents since the one who safe keep or made the documents wasalready resigined from the company. (Ms. Juliet Alforia PSCC –QC Manager).

(See attached Audit Feedback form of Mr. Jenny Anyayahan and its attachment )

AUDIT NOTE:

Internal Audit Department is after the report with recommendation prepared by the

 plant, duly approved by the Top Management. This report is lacking.

B. Compliance to Supplier’s Protocol in the Use of the Chemical Cleaner 

1. Starting March 26, 2009 the ALKALI (Fine Cleaner) concentration was set at below standard against agreed technical protocol. Refer attached samples of Line Clearance Checklist Form(Refer Annex D))

2. Subsequent random sampling of Line Clearance testing by QA/QC of actual production runwas conducted. Out of forty-eight (48) days of line clearance testing on free ALKALI, twenty(20) days of which were below standard per protocol.(Period Covered August 26, 2008 to

May 27, 2011 Refer Annex E )

3. Moreover, Philippine Parkerizing presented summary of their technical evaluation regardingPSCC use of Alkali (Fine Cleaner) from year 2008 to 2011. Based on the summary of Parkerizing, there are applications of Alkali deviating from protocol.

(Refer Summary Parameters and performances of Free Alkali- (Fine Cleaner D 5410)

Page 4: Alkali 31

7/28/2019 Alkali 31

http://slidepdf.com/reader/full/alkali-31 4/5

 AUDIT FINDINGS Number 2:

PSCC deviated from protocols and the supplier has explicit knowledge of the saiddeviation. However, PSCC failed to obtain new or amended protocols to ensure proper performance and safety on the use of the supplied chemicals.

AUDITEE’S COMMENTS:

No comment was obtained from Ms. Evelina Diocampo, Quality Control Manager – QualityControl, as she already resigned from PSCC

Mr. Jenny Anyayahan –Production Manager 

 At initial commercial run of Parkerizing Chemicals using Fine Cleaner D 5410for stage #1 the Free Alkali concentration per protocol was 20 – 26 points, (see attachedprotocol) however as we go along with the commercial run a strong offensive smell comingfrom the stage 1 was complained by our operators. This finding was likewise complained toParkerizing and the supplier revised the stage 1 concentration .(Refer Annex F))

C. Compliance to Materials Receiving

1. Base on the samples examined, results were generally in order. (Refer Annex G) 

AUDIT RECOMMENDATIONS: 1. All changes in production process, parameters, and materials usage (e.g.

concentration) must be supported by extensive study and testing and subsequentlyapproved by EXCOM.

2. Technical protocols from supplier must be properly evaluated by the plant, result of which is reported to Top Management for further comments or deliberations andapproval. 

Prepare by Reviewed by Approved by

ED Jao / TK Yap Rafael D. Salazar Getre Y. PechaycoInternal Auditors Senior Audit Supervisor Internal Audit Head  

Page 5: Alkali 31

7/28/2019 Alkali 31

http://slidepdf.com/reader/full/alkali-31 5/5