Alfa-Omega Team Coordination

8
Alfa - Omega T eam Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków

Transcript of Alfa-Omega Team Coordination

Page 1: Alfa-Omega Team Coordination

Alfa-Omega Team CoordinationLS1 Collaboration Seminar, 27th November 2014

Anna Chrul, IFJ PAN Kraków

Page 2: Alfa-Omega Team Coordination

2014-11-27

Alfa-Omega Team

Max. resources during LS1:

36 persons

(4 Staff, 2 FSU, 30 Collaborators)

NTUA (11)WUT (11)

JINR Dubna (7) FSU (2)

LS1 Collaboration Seminar

Page 3: Alfa-Omega Team Coordination

2014-11-27 LS1 Collaboration Seminar

To support management to supervise and coordinate the work of the Alfa-Omega team, i.e.:

- to ensure safety and develop technical trainings, grant access rights to the LHC sites for all team members,

- coordination of weekly and daily activities for all teams,

- technical supervision and problems analysis. Technical link with others sections/groups when necessary, logistic issues…

- following up activities and exchange information with other SMACC teams to identify issues which might have impact to Alfa-Omega work,

- editing of all technical procedures related to A&O activities,

but also:

- follow-up of teams integration, leading the members to become familiar with the environment. In addition, solving every-day problems; helping to get more familiar with CERN, thanks to visits in ATLAS, CMS, ALICE, LHCb...

In general: to lead all Alfa-Omega team responsibles to organize work of the team respecting the schedule but with priority given to safety and quality.

WP4: Follow up of the opening and closure

of the ICs

Page 4: Alfa-Omega Team Coordination

2014-11-27

W-bellows openings/closures

1695 ICs to close Time frame: August 2013 – June 2014

1695 ICs to open(regular openings for the train and performed

in parallel special openings “on request”)

Time frame: April – November 2013

An

dre

a M

usso

-L

SC

Ma

y 1

7th

, 2

01

3

Before LS1:

preparation of procedures and dedicated tooling,

training on mock up in Bld.180.

+ more than 100 ICs to re-open and close

for NCs treatmentTime frame: June – September 2014

LS1 Collaboration Seminar

Page 5: Alfa-Omega Team Coordination

2014-11-27

Thermal Screens UpgradeIn the dedicated workshop in Bld.183 ~1900 thermal screens sets were upgraded (a clamp installed instead of the welded lyra; hinge, aluminum bride and snap fasteners were added between the upper and lower shield)

M-bellows Protections Consolidation

~5000 pcs of M-bellows protections were modified in Workshop (SMI2)

~100 pcs considered as radioactive – modified in Workshop Bld.109

~40800 inserts installed!

In the tunnel ~8500 holes were punched in the cryostat’s thermal screens to prepare the installation

of upgraded shields.

LS1 Collaboration Seminar

Page 6: Alfa-Omega Team Coordination

A.Chrul, 22/10/2014

Safety Relief Valves (DN200) installation

612 missing DN200 installed in sec.23, sec.45 (partially), sec.78, sec.81

17 DN200 installed on cryo-magnets exchanged during LS1

2 additional DN200 installed for CryoBLM (sec.45 and sec.78)

2014-11-27 LS1 Collaboration Seminar

Page 7: Alfa-Omega Team Coordination

2014-11-27

Other activities during LS1 Non-standard openings: undulators QBUI.5L4 and QUBI.5R4; QBQM.4R2

Support for CryoBLM installation: QBBI.9R7 and QQBI.9L5

Support for ELQA

Helium Spill Test in sec.45

Support for CRG Group (Bld.180)

Support for RP samples removal in sec.45

Re-organization of Bld.189 (the storage area for cryo-magnets components)

LS1 Collaboration Seminar

Page 8: Alfa-Omega Team Coordination

Thank you!

2014-11-27 LS1 Collaboration Seminar