Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall...

39
Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State University GE TRANSPORTATION NO GRID TELECOM BASE STATION ENERGY STORAGE SYSTEM

Transcript of Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall...

Page 1: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

Alex Engler, Andrew Sarcinello, & Zach Mitchell

EDSGN 100.012: Intro. to Engineering Design

Fall 2010 Client – Driven Design Project

The Pennsylvania State University

GE TRANSPORTATION

NO GRID TELECOM BASE STATION ENERGY STORAGE

SYSTEM

Page 2: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

TABLE OF CONTENTS• Customer Needs & Problem Defintion

• Statistical Information of Nicaragua

• Potential Solutions

• Power

• Concept Selection

• Cooling

• Concept Selection

• Power Balance

• Total Energy Equations

• Power Output

• Heat Balance

• Life Cycle

• Cost

• Profit

• Social Implications

Page 3: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

WHAT DOES THE CUSTOMER NEED?

• The telecom company needs a profitable, off-the-grid system to power their “hut”

• The “hut” is a protection building for the equipment used to support the cell tower

Page 4: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

THE PROBLEM• We are working off of any main power grid.

• We must utilize GE’s sodium metal halide batteries

• We must attempt to make the project economically efficient

• The equipment in the building requires a 1.2 kW load

Page 5: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

INFORMATIONWhat are we Dealing With?

Page 6: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

ABOUT THE AREA

Area:total: 129,494 sq km water: 9,240 sq km land: 120,254 sq km

Elevation extremes: lowest point: 0 mhighest point: 2,438 m

Temperature averages by elevation

Day (oC) Night (oC)0-750 m 30-33 21-24750–1600 m 24-27 15-211600-2438 m 22-24 Low of 15

UV Index Average Estimates.

Winter Summer7-8 9-10

Page 7: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• Solar energy can generally be garnered from 6:00 AM – 6:00 PM

• High points from 11:00 AM - 1:00 PM

• From December to April, there is the most solar radiation.

• From May to October, solar radiation drops by about 1/3 average per day.

Month Speed (m/s)January 1.7February 1.8March 2.0April 2.4May 2.1June 1.6July 1.2August 1.6September 1.3October 0.5Novermber 1.3December 0.9

WIND AND SOLAR DATA

Average Daily Wind Speeds by Month Solar Tendencies

Page 8: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

WIRUCA, NICARAGUA• 48 families

• All are coffee growers

• Earn $100 per month per household, $10 disposable income per month

• No electricity

• No cell phone service, but they have cell phones for use when traveling

• Would like to power TV, radio, lights, and fan

• Mountainous area, hurricane and earthquake danger

• Community currently pays 1.7 Cordobas/hr for first 25 kW-hr

• Cell phone service provider - CLARO

Page 9: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

POTENTIAL SOLUTIONSHow to Power the telecom hut, how to cool it, and should energy be sold?

Page 10: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• ENERGY

• Solar

• Wind

• Geothermal

• Sodium Metal Halide Battery

• Micro-Hydro

• Diesel Generator

• Cooling

• Air Conditioning

• Ventilation

• Heat Pumps

• No action

LISTS OF SOLUTIONS

Page 11: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

POWER SOLUTIONSStability and Reliability

Page 12: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

SOLAR ENERGY• Current designs of telecom towers use 32 200 watt solar panels

• GE produces solar panels for solar electricity

• GE Energy GEPV-200, Solar Panel, 200 Watt ($1000 +/- $75)

Page 13: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

WIND ENERGY• Windmill generated energy

• Although GE is preferable, GE models are on a much larger scale than a single building – or even the entire community.

• Skystream offers an affordable, appropriate model

• Skystream 3.7 Grid Tie 1.8kW (Cost = $6,200 +/ $50)

Page 14: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

GEOTHERMAL ENERGY• Geothermal power plants use heat from the Earth to Mass Produce Electricity.

• It is very efficient, and could easily utilize the great volcanic activity in the area.

• Generally used on a large scale, and stations are not manufactured.

• Cost > $10 million on average

Page 15: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

SODIUM METAL HALIDE BATTERY• GE is looking to test this innovative design on the telecom expedition

• Good option for energy storage.

Page 16: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

MICRO HYDRO ENERGY• Using running water to push turbines and provide power can be very efficient and

beneficial.

• The cost of a system can run from $1,000 - $20,000; although maintenance costs are low.

• Availability dependent on running water in the area.

Page 17: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

DIESEL GENERATOR• The diesel generator is not a green or

alternative energy source, but it is reliable, and not dependent on outside conditions like terrain and weather.

• Cost of diesel fuel, $1/liter. About $2.60 per gallon

• We’d want it to be able to power the hut should all of our alternative energy be out of operation.

• Option Kohler 20 KW Compact Diesel Generator

• 40 Gallon Tank

• Only one year warranty

• About $17,000

Page 18: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

CONCEPT SELECTION

Selection Criteria Wind Solar Hydro NaMX Battery Generator GeothermalMaintenance cost + + - + - +Installation cost + + - 0 - -Operating cost + - + + + +Materials cost + - 0 + - -Efficiency 0 0 + + + +Sustainability + + 0 + - +Power output 0 0 + - + +Ease of maintenance + + - + 0 -Installation Time + + - + + -# of materials + + - + - -Size 0 + 0 + + -Adaptability + + - + + -Life Cycle + + + 0 - +Total 10 7 -2 9 0 -1Rank 1 3 6 2 5 4Continue? yes yes no yes no no

Energy Source

Page 19: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

CONCEPT SELECTION

Selection Criteria

Weight RatingWeighted

Score RatingWeighted

Score RatingWeighted

Score Rating Weighted

ScoreMaintenance cost 0.10 3 0.3 3 0.3 4 0.4 2 0.2Installation cost 0.10 3 0.3 3 0.3 3 0.3 2 0.2Operating cost 0.10 4 0.4 5 0.5 3 0.3 5 0.5Materials cost 0.05 3 0.15 1 0.05 4 0.2 2 0.1Efficiency 0.05 2 0.1 2 0.1 4 0.2 4 0.2Sustainability 0.15 4 0.6 5 0.75 4 0.6 1 0.15Power output 0.10 2 0.2 2 0.2 1 0.1 3 0.3Ease of maintenance 0.10 3 0.3 4 0.4 4 0.4 3 0.3Installation Time 0.02 4 0.08 5 0.1 5 0.1 5 0.1# of materials 0.03 3 0.09 4 0.12 4 0.12 3 0.09Size 0.05 2 0.1 5 0.25 4 0.2 3 0.15Adaptability 0.10 3 0.3 4 0.4 5 0.5 4 0.4Life Cycle 0.05 4 0.2 4 0.2 2 0.1 1 0.05Total 1.00RankContinue?

Energy Source

GeneratorNaMX BatterySolarWind

yes yes incorporate incorporate (required)

3.12 3.67 3.52 2.743 1 2 4

Page 20: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

COOLING OPTIONSFighting the Climate

Page 21: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• Would appropriately cool building

• Not Expensive to Install

• Requires extra power.

• GE Options

• AJCQ06LCC Air Conditioner

• $400 - $500

• 6000 BTU = 1.76 Kwh

AIR CONDITIONING

AJCQ06LCC

Page 22: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• Working similarly to an air conditioner, heat pumps heat and cool buildings by transferring heat rather than using fuel.

• Can be economically beneficial, but that would be assuming one uses them for heating and cooling.

• May not adequately cool in Nicaragua’s warm climate.

• Option: Fedder’s CH60ACZ1VF

• Cost $1,100 - $1,400

HEAT PUMPS

Page 23: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• If we feel the hut can operate at any reasonable temperature it could be economically efficient to take no action on limiting the temperature within the hut.

• By maintaining a brisk air flow the and allowing the heat emitted from our materials to exit the building, we may be able to keep the temperature at least somewhat close to that outside

• If one takes this route one must consider that this could lead to insects getting into the building, which could eventually lead to poor effects on the equipment.

NO MECHANICAL COOLING SYSTEM

Ventilation No Cooling

Page 24: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

CONCEPT SELECTION

Selection CriteriaAir Conditioning

Heat Pump Ventilation Nothing

Cost 0 - + +Ease of installation + - + +Effectiveness 0 + - -Sustainability - + + -Ease of maintenance 0 + 0 0Total 0 1 2 0Rank 3 2 1 4Continue? yes yes yes no

Temperature Control

Page 25: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

CONCEPT SELECTION

Selection Criteria

Weight RatingWeighted

Score RatingWeighted

Score RatingWeighted

ScoreCost 0.30 2 0.6 1 0.3 4 1.2Ease of installation 0.10 4 0.4 1 0.1 4 0.4Effectiveness 0.20 3 0.6 5 1 1 0.2Sustainability 0.25 1 0.25 5 1.25 5 1.25Ease of maintenance 0.15 3 0.45 5 0.75 4 0.6Total 1.00RankContinue? no no yes

Temperature Control

2.3 3.4 3.653 1 2

VentilationHeat PumpAir Conditioning

Page 26: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• We will supply energy to the hut using wind energy from a Skystream windmill, six GE solar panels, and a Kohler Diesel Generator; which will charge GE’s new Sodium Metal Halide Batteries.

• To deal with the heat, we will be allowing air flow through ventilation, and using low cost/ power fans to keep consistent air flow.

• We will also try to limit heat given off in the hut with the placement of the electric systems.

OUR SOLUTION

Page 27: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

POWER BALANCES• The balance of power flowing to the hut will change throughout the year.

• The load needed for the huts will be 1.2 kW plus that required for the lights and fans inside the hut. A safe estimate of the maximum energy needed would be 1.4 kW.

• Our power sources, at maximum output, could give 24.8 kW

• Generator – 20 kW

• Solar Panels – 1.2

• Windmill – 2.6 at peak

• Our goal is to limit the amount of work done by the generator, which will fluctuate in respect to time.

Page 28: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

EQUATION OF TOTAL ENERGYGeneratorOutput + SolarOutput + WindOutput + NaMxOut = Load / hr + NaMxCharge

[Gmax * F / hr] + [Panels * Smax / hr * Esol] + [Pmax (Betz limit) (K)] + NaMxOut = Load / hr + NaMxCharge

[ (40kW / Gallon / hr) * F ] + [ 6 * 0.2kW / hr * E sol ] + [ 2.6 kW * 0.59 K ] + NaMxOut = Load / hr + NaMxCharge

• Where

• F is fuel in gallons

• Esol is solar efficiency

• K is a constant limiting wind output by including inefficiencies in the windmill system.

Page 29: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• Solar and wind power also fluctuate by month, so more or less diesel fuel will be required based on our windmill and solar panels’ outputs.

• The solar power available to us will fluctuate by hour each day, and the wind will be difficult to predict on an hourly basis, but we should have a basic idea of how much diesel fuel we’ll need.

EFFICIENCY DIFFERENCES IN POWER OUTPUT

From Day to Day From Month to Month

Page 30: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

Solar Panels

Generator Wind

January – May

Very Strong Not a large part of process

Very Strong

June – August

Weak Somewhat important

Strong

September - December

Grows stronger

More important Grows weaker

Solar Panels

Generator Batteries

6:00 AM – 9:00 AM

Weak but functioning

Used in absence of wind

Final discharging in cycle

9:00 AM – 3:00 PM

Strong, providing majority of energy

Shouldn’t be needed.

Charges off of wind energy

3:00 PM – 6:00 PM

Weak but functioning

Used in absence of wind

Charges or discharges based on wind

6:00 PM – 6:00 AM

Off due to lack of sunlight

Maintains electric output w/ batteries

Discharges, primary

TIME DIFFERENCES IN POWER OUTPUTFrom Day to Day From Month to Month

Janua

ry

Februa

ry

March

April

MayJun

eJul

yAug

ust

Septem

ber

Octobe

r

Novembe

r

Decembe

r

Solar

Wind

Generator

Page 31: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

HEAT BALANCES• We know the station will be placed in a mountainous region

• This should yield a temperature difference of at least 6o C from that in lower areas.

• Because the temperature should be averaging 77-800F, an expensive cooling system should not be required.

• We will be putting small fans in the hut as well as proper ventilation to maintain an acceptable temperature.

• To limit heat produced from equipment, we will place the batteries and generator outside of the hut in an area enclosed with fencing for security.

Page 32: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

LIFECYCLESCosts Over Time

Page 33: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

• Windmill: Turbines should last 20 – 25 years. Maintenance is minimal.

• Generators: aside from the cost of fuel, filters must be cleaned and oil must be changed regularly. Lifetime is potentially limitless, however.

• Solar panels: last anywhere from 25 to 50 years. Maintenance is minimal and pertains mainly of removing debris from surface and keeping line of sight clear of shade.

• Windmill – 5 year limited

• Generator – 1 year limited

• Solar Panels – 25 year limited on power output, 5 year limited on materials and workmanship

PARTS LIFECYCLES

Warranties Reliability Over Time

Page 34: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

ESTIMATED COSTS OVER TIME.• The generator will most likely run between 0.5-2 hours per day depending on the time of

year, so

• 182.5 – 730 gallons per year

• $481.80 - $1927.20

• Based on the three sections of the year shown earlier, we can estimate

• 481.8 * 5/12 + 963.6 * 3/12 + 1927.2 * 4/12 = about $1084.05 / year

• Maintenance for panels and windmill should be under $100/year.

Page 35: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

SELLING POWER• There is interest among many of the villagers to sell extra power produced to the villagers

as a business.

• This would be a very beneficial action for the community

• However, it would not be economically sound

• Nearby villages have recently put in solar plants for a power source, and thus would not require power

• The village consists of 48 families with $10 / month disposable income, and after their cellular coverage expenses, would not be able to make our venture profitable.

Page 36: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

POTENTIAL PROFITS• Initial expenses are $29,210 for fuel sources plus fencing and ventilation costs.

• Costs per year should range from $1,100 - $1,200

• The telecom company will be selling to a village with 48 families, who average $10/ month disposable income.

• Approximately $5,760 / year.

• Bearing unknown interest rates, this project seems to present nothing but a high risk long term investment. If GE is paid 25% of the profits, they will cover expenses after

29,210 / ( 5,760 *.25 – 1,150) = 100.725 years with our model.

Page 37: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

SOCIAL IMPLICATIONS • There are great social benefits by having the telecom infrastructure build in Nicaragua, it

helps to modernize the community and give them the necessary resources to keep up with vastly growing modern technology.

• The telecom station will also add job’s to the small community, again giving opportunity for growth.

• Cell phone usage will go up, allowing for more communication between the civilians leading to a safer and more unified village.

Page 38: Alex Engler, Andrew Sarcinello, & Zach Mitchell EDSGN 100.012: Intro. to Engineering Design Fall 2010 Client – Driven Design Project The Pennsylvania State.

CONCLUSION

• In conclusion, will we use a heat powered by both solar and wind energy, with a reserve diesel generator used if the wind and solar are in a time of malfunction or low efficiency. The hut will cooled with an installed ventilation system used to draw the hot stagnant air out of the building. We will not sell power to the community due to the lack of economic potential.