TIME SCEHEDULE NPPTKB Project - Batam No Description Qty Unit I II II IV 1 2 3 4 1 2 3 4 1 2 3 4 1 2 1 Mobilization of Equipment 1.00 Ls 2 Preparation On Site 1.00 Ls 3 Driving of PC Pile Dia. 60cm = 2880 nos @ ### m 4 Handling of PC Pile Dia. 60 cm ### m 5 Welding of PC Pile dia. 60 cm 2,880.00 Joint 6 Demobilization 1.00 Ls Note : Production 5 pile / day / rig ( We use 8 rig )

description

alat

Transcript of Alat Kabil

Page 1: Alat Kabil

TIME SCEHEDULENPPTKB Project - Batam

No Description Qty Unit I II II IV Remark1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 Mobilization of Equipment 1.00 Ls

2 Preparation On Site 1.00 Ls

3 Driving of PC Pile Dia. 60cm = 2880 nos @ 18m 51,480.00 m

4 Handling of PC Pile Dia. 60 cm 51,480.00 m

5 Welding of PC Pile dia. 60 cm 2,880.00 Joint

6 Demobilization 1.00 Ls

Note : Production 5 pile / day / rig ( We use 8 rig )

Page 2: Alat Kabil

LIST OF EQUIPMENT FOR PILING WORKNPPTKB Project - Batam

No Equipment Brand / Type Capacity Quantity Remark

1 Piling Rig Nissha D408 40 Ton 8

2 Service crane P& H 335 AS 35 Ton 2

3 Diesel Hammer DD 63 6.3 Ton 6

4 Hydraulic Hammer NH 70 7 Ton 2

Note :All of equipment will be prepared for 2 weeks before the Mobilization to project site