TIME SCEHEDULENPPTKB Project - Batam
No Description Qty Unit I II II IV Remark1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Mobilization of Equipment 1.00 Ls
2 Preparation On Site 1.00 Ls
3 Driving of PC Pile Dia. 60cm = 2880 nos @ 18m 51,480.00 m
4 Handling of PC Pile Dia. 60 cm 51,480.00 m
5 Welding of PC Pile dia. 60 cm 2,880.00 Joint
6 Demobilization 1.00 Ls
Note : Production 5 pile / day / rig ( We use 8 rig )
![Page 2: Alat Kabil](https://reader036.fdocuments.us/reader036/viewer/2022083011/5695d0991a28ab9b02931c35/html5/thumbnails/2.jpg)
LIST OF EQUIPMENT FOR PILING WORKNPPTKB Project - Batam
No Equipment Brand / Type Capacity Quantity Remark
1 Piling Rig Nissha D408 40 Ton 8
2 Service crane P& H 335 AS 35 Ton 2
3 Diesel Hammer DD 63 6.3 Ton 6
4 Hydraulic Hammer NH 70 7 Ton 2
Note :All of equipment will be prepared for 2 weeks before the Mobilization to project site