ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

16
ALASKA NATURAL GAS SYMPOSIUM Regulatory Update J. Mark Robinson, Director Office of Energy Projects Federal Energy Regulatory Commission December 2, 2004 Houston, Texas

description

ALASKA NATURAL GAS SYMPOSIUM Regulatory Update. J. Mark Robinson, Director Office of Energy Projects Federal Energy Regulatory Commission December 2, 2004 Houston, Texas. FERC. Alaska Natural Gas Transportation System and Other Pipelines. Office of Energy Projects. 2. - PowerPoint PPT Presentation

Transcript of ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

Page 1: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

ALASKA NATURAL GAS SYMPOSIUM

Regulatory Update

J. Mark Robinson, DirectorOffice of Energy Projects

Federal Energy Regulatory CommissionDecember 2, 2004

Houston, Texas

Page 2: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

2

AlaskaNatural GasTransportation System andOther Pipelines

Page 3: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

3

FERC and AlaskaAncient History

1976 Congress passes the Alaska Natural Gas Transportation Act (ANGTA)

1977 FERC issues conditional certificates 1979Office of the Federal Inspector (OFI) established.1981Western Leg of the Alaska Natural Gas Transportation

System (ANGTS) – Pacific Gas Transmission – goes into service

1982 Eastern Leg of ANGTS – Northern Border Pipeline – goes into service

The Alaskan portion of ANGTS was not constructed.

1992OFI eliminated

Page 4: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

4

FERC and AlaskaRecent Events

2001 In May, National Energy Policy recommends expedited construction of an Alaskan pipeline to deliver natural gas to the lower 48 states.

2001 Alaska Natural Gas Interagency Task Force formed- Members include: Energy, State, Interior (BLM, MMS), DOT (OPS), FERC (Energy Projects), Joint Pipeline Office

2001 In August, H.R. 4 approved by House2004H.R.4837 with section titled “Alaska Natural Gas

Pipeline Act” approved and signed by President on October 13th.

Page 5: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

5

Alaska Natural GasPipeline Act Presumptions

The Act presumes that:• Public need for Alaskan project

exists• Adequate downstream capacity

exists to move the gas to markets in the Lower 48

Page 6: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

6

• Clarifies legal issue which allows Commission to consider any application for Alaskan natural gas transportation projects

• Clarifies ability to continue to process any modified application under the Alaskan Natural Gas Transportation Act of 1976

Alaska Natural GasPipeline Act

Provisions

Page 7: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

7

• FERC must issue regulations for Alaskan pipeline capacity open season in 4 months

• FERC may order expansion• FERC may allow accommodation

for State of Alaska royalty gas• Only D.C. Circuit has judicial

review of FERC orders

Alaska Natural GasPipeline Act

Provisions

Page 8: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

8

• Federal Coordinator is created for either type of project (i.e., ANGTA or NGA)

• Makes loan guarantee of up to $18 billion available to either type of project.

• If no application is filed in 18 months, then DOE must study alternatives.

Alaska Natural GasPipeline Act

Provisions

Page 9: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

9

• A separate tax bill provides for:– Seven-year amortization of the

cost instead of 15 years– An enhanced oil recovery tax

credit for the cost of a gas conditioning plant on the North Slope

Alaska Natural GasPipeline Act

Provisions

Page 10: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

10

• Must issue regulations governing the conduct of open seasons for Alaska natural gas transportation projects by February 10, 2005.

• Regulations must include procedures for the allocation of capacity.

• Final rule would be subject to rehearing after February 10.

Alaska Natural GasPipeline Act Open Season

Page 11: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

11

The regulations must:• Include the criteria for and timing of any

open seasons;• Promote competition in the exploration,

development, and production of Alaska natural gas; and

• Provide the opportunity for the transportation of natural gas other than from the Prudhoe Bay and Point Thomson units when capacity exceeds the initial capacity during open seasons.

Alaska Natural GasPipeline Act Open Season

Page 12: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

12

The open season regulations apply to:

• Any initial or (voluntary) expansion capacity on any Alaska natural gas transportation project.

• Does not apply to involuntary expansion if one is ordered under the Act.

Alaska Natural GasPipeline Act Open Season

Page 13: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

13

Rulemaking Schedule11/18/04 – Commission issues NOPR12/03/04 – Public technical

conference in Anchorage, Alaska.12/17/04 – Written comments due on

NOPR02/09/05 – Commission issues final

rule.

Alaska Natural GasPipeline Act Open Season

Page 14: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

14

• FERC is designated as the lead agency for NEPA processing.

• FERC is responsible for preparation of the EIS.

• Other federal agencies conducting reviews covered by the EIS shall comply with the deadlines established by FERC.

• The EIS prepared by FERC shall be adopted by the other federal agencies.

Alaska Natural GasPipeline Act

Cooperation in Processing

Page 15: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

15

• NEPA Pre-filing process is expected to take 18 months

• When the formal application is filed:– Draft EIS issued in 12 months– Final EIS issued in 6 more months– Final order in 2 more months ( total

elapsed time 20 months )

Alaska Natural GasPipeline Act

Processing Timeline

Page 16: ALASKA NATURAL GAS SYMPOSIUM Regulatory Update

FERC

Office of Energy Projects

16

Post-CertificationTimeline

• Two to three years of preparation prior to construction– Financing– Fabrication of Equipment and Supplies

• Two to three years for construction– Majority of construction to be

performed in winter• One year of preparation (camps, roads)• Gas treatment plant