Air Quality in Ulan Baatar - Project Report

download Air Quality in Ulan Baatar - Project Report

of 25

Transcript of Air Quality in Ulan Baatar - Project Report

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    1/25

    1

    Universitt Stuttgart

    M.Sc. Study Program WASTE

    Assessment of Particulate Matter in Ulaan Baatar, Mongolia

    Report on Planning, Quality Control and Quality Assurance of

    Measurements

    Summer Semester 2013

    Students:

    Family name First name Matr.-No. E-Mail/phone-No.

    Wildani Nila 2775621 [email protected]

    Venkatachalam Venkateshwaran 2828109 [email protected]

    Suvedi Sukriti 2776374 [email protected]

    Supervisors Name : Prof. Dr.-Ing. G. Baumbach / Dr.-IngU. VogtInstitute of Supervisor : Institute of Combustion and Power Plant

    Technology

    Date of Submission : 30-07-2013

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    2/25

    2

    Contents

    1. INTRODUCTION ............................................................................................................................... 4

    2. PROBLEM ANALYSIS ........................................................................................................................ 4

    2.1 Task Description....................................................................................................................... 4

    2.2 Analysis of Background Information ....................................................................................... 5

    2.3 Geographical Information ....................................................................................................... 6

    2.4 Meteorological Information .................................................................................................... 6

    2.5 Parameters and Limit Values ................................................................................................... 7

    2.6 Effects of Air Pollution ............................................................................................................. 9

    2.7 Assessment of Results of Measurements .............................................................................. 10

    3. MEASUREMENT STRATEGY ........................................................................................................... 11

    3.1 Measurement Locations ........................................................................................................ 11

    3.2 Selection of the measurement locations ............................................................................... 11

    3.3 Significance of the selected locations ................................................................................... 11

    3.4 Measurement Times .............................................................................................................. 12

    3.5 Sampling period and duration of the measurement program .............................................. 12

    3.6 Supplementary Measurements: ............................................................................................ 13

    4. MEASUREMENT TECHNIQUE ........................................................................................................ 14

    4.1 PM Measurement .................................................................................................................. 14

    4.2 Principle ................................................................................................................................. 14

    4.3 Instrument/Equipment .......................................................................................................... 15

    4.4 Operation ............................................................................................................................... 16

    4.5 Maintenance .......................................................................................................................... 17

    4.6 Meteorological data measurement: ...................................................................................... 18

    5. ORGANIZATION ............................................................................................................................. 19

    5.1 Project Management ............................................................................................................. 19

    5.2 Project Administration ........................................................................................................... 19

    5.3 Original Equipment Manufacture .......................................................................................... 19

    5.4 Sampling Personnel ............................................................................................................... 19

    5.5 Scheduling .............................................................................................................................. 19

    5.6 Evaluation Process: ................................................................................................................ 20

    5.7 Evaluation algorithms: ........................................................................................................... 20

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    3/25

    3

    5.8 Uncertainty of Result: ............................................................................................................ 21

    6. QUALITY ASSURANCE .................................................................................................................... 22

    6.1 Calibration.............................................................................................................................. 22

    6.2 DUSTTRAKTM Advanced Calibration using Serial Gravimetric Calibration ........................... 23

    6.3 Step 1: PCF Calibration .......................................................................................................... 24

    6.4 Step 2: SCF Calibration ........................................................................................................... 24

    7. CONCLUSION ................................................................................................................................. 24

    8. REFERENCES .................................................................................................................................. 25

    Figure 1 PM Data, UB, 2012 (Source: Ryan.W.Allen, ACMS, January 2013) ..........................................7

    Figure 2 PM Data of Ulaan Baatar from 2004-2012.....................................................................................8

    Figure 3 Air Pollution in Ulaan Baatar compared to other world cities.......................................................8

    Figure 4 Aerosol size distribution and health effects (Source: S.Lodoysamba.et.al, 2011) ...................9

    Figure 5 Existing Monitoring Stations in Ulaan Baatar.............................................................................. 11

    Figure 6 Proposed Monitoring Stations in Ulaan Baatar (Marked in Red and Green) ......................... 12

    Figure 7 TSI DustTrakTM Model II Aerosol Monitor flow schematic (TSI, 2012).................................. 15

    Figure 8 External Pump of Instrument (TSI, 2012).................................................................................... 16

    Figure 9 Display of mass measurement on the screen (TSI, 2012)........................................................ 17Figure 10 Organizational Chart..................................................................................................................... 20

    Figure 11 Setup for advanced series calculation....................................................................................... 23

    Table 1 Temperature Data in Ulaan Baatar...................................................................................................6

    Table 2 Exceedance factors of Particulate matter in UB.............................................................................9

    Table 3 List of monitoring stations in Ulaan Baatar................................................................................... 12

    Table 4 Specification of DustTrak TMII 8350 (TSI, 2012)......................................................................... 15

    Table 5 Required maintenance plan during measurement (TSI, 2012) .................................................. 17

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    4/25

    4

    1. INTRODUCTION

    Air Pollution is one of the most important problems that have a great impact on the health and

    environment of the society in the 21st

    century. Combating the effects and finding solutions toprevent and monitor air pollution will be one of the challenging tasks in the present scenario. So

    much of emphasis has been given to monitor the air quality in almost all the world cities mainly

    because of several factors like rise of industries, changing lifestyle of people, increased means of

    transportation and also the climate change. Lots of parameters are taken into account when

    discussing about air pollution, be it physically, chemically or biologically. The main aim is to

    streamline particular parameters that we wanted to consider and generate ideas and suggestions

    to solve the problems involved in the same. In the case of our planning project, the important

    parameter under question is Particulate Matter (PM), as it has gained a prominent place in the

    study of air pollution.

    2. PROBLEM ANALYSIS

    2.1 Task Description

    Ulaan Baatar, the capital city of Mongolia is one of the most polluted cities in the world. The main

    cause of the pollution is by multiple sources like Thermal Power plants, Coal mining stations,

    Domestic stoves, absence of a central heating system and also its topography. The regulation of

    the air pollutants that are dispersed in the city still requires a lot of improvements. Without carefully

    monitoring, sampling and discussing about the pollutants that affect the air quality, theimprovement of the same cantbe achieved. Of all the pollutants that is being frequently monitored

    and reported by the stations set up by their own government, quality of monitoring the Particulate

    Matter (PM10 and PM2.5) is inadequate and not much importance is given compared to major

    pollutants like Carbon monoxide, Nitrogen dioxide and so on. Even the number of monitoring

    stations is low compared to the size of the city and its population.

    Moreover, Ulaan Baatar always exceeds the PM values as prescribed by World Health

    Organization (WHO) and it is even 7-8 times (Source: World Bank) of the standard limit values,

    which result in serious health complications among the public. During the winter season, because

    of the occurrence of the inversions, the ambient air is almost fully dispersed with particulate matter,

    which results in the poor visibility and a lethal effect on the respiratory system of the public there.

    So this planning project strives in setting up monitoring stations at different parts of the city of

    Ulaan Baatar according to its significance and population. They are mainly devoted to the

    continuous on-line monitoring of Particulate matter in the ambient air and comparison of values are

    being done with respect to the 24 hour limit standards set by them for a period of one year. Added

    to that, we also discuss about the spatial and temporal variations of the ambient air quality

    throughout the city of Ulaan Baatar, Mongolia.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    5/25

    5

    2.2 Analysis of Background Information

    Air Pollution has becomes one of the important problems and priorities in the city of Ulaan Baatar.

    Air pollution in Ulaan Baatar is due to inter-related causes and problems like Usage of coal and

    wood for cooking and heating, fugitive dust (both transport and non-transport), construction

    industry, automobiles, garbage burning and so on. These sources are closely associated with the

    industrialization of the city. But it is not keeping the check of the air pollutants up to the

    international standards; blame it on the economy and the development of the country as a whole

    financially. The Air Quality Division of Mongolia operates four monitoring stations in Ulaan Baatar

    for regulating the air pollution. As of 2012, the four stations that are operating have the technical

    support to monitor Nitrogen Dioxide, Carbon Monoxide and Sulphur Dioxide. But they dont have

    adequate technical assistance to continuously monitor Particulate Matter (PM), which can be

    extreme at times (Both PM10 and PM2.5) during winter and during dust storm that have serious

    health implications on the public.

    A number of emission inventories have been prepared for the Ulaanbaatar air shed in order to

    quantify source emissions and contributions to particulate matter air pollution in the city. However,some sources such as fugitive dust from dust storms and local dust generating activities or

    emissions from domestic use of fuels for heating and cooking are difficult to quantify per se or the

    emissions factors and activity estimates have a high uncertainty associated (>50%) [1].

    Fig.1. Geographical Location of Ulaan Baatar

    In order to have a better and an adequate technical assistance for the ambient air quality

    monitoring, we are proposing to setup 8 monitoring stations, that are mainly concerned with the

    measurement and sampling of Particulate matter in the ambient air of Ulaan Baatar, Mongolia. In

    that way, it will make a better understanding with regards to the significance and impacts of

    Particulate Matter not only in few places but the city as a whole.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    6/25

    6

    2.3 Geographical Information

    The capital city of Ulaanbaatar of Mongolia is located in Central Asia with harsh continental climate

    at northern latitude of 47 degrees and 55 minutes and eastern longitude of 106 degrees and 55

    minutes, and lies at 1,500 meters above sea level and occupies 470.4 thousand hectares of land.

    The near Ulaanbaatar region belongs to the earthquake magnitudes from 5 to 7. According to thenatural zone classification, the near Ulaan Baatar region has rocky high mountains, forested

    steppes, steppes, and river valleys and therefore, the biodiversity of the region is very rich and

    beautiful and varies in animals, vegetation and soil types.

    2.4 Meteorological Information

    Ulaan Baatar city has an extremely continental climate, including four seasons, and it is one of the

    coldest national capitals in the world. Winter is cold with an average temperature of -26C in

    January. In summer, the warmest month is July with an average temperature of +17C. The

    highest temperature in July reaches up to +39C, and the lowest temperature in January ranges to

    -40C. According to the past decades reports, there have been 56 days registered a year with anaverage daily temperature of -25 C and 55 days with an average temperature of +15C.

    Although the wind blows mostly from the north and northwest in Ulaan Baatar city, it changes

    direction in the mountainous areas, forests and river valleys. In any month of the year the wind is

    observed to be blowing from northwest in 30-40 % of the cases, however, it rarely blows from the

    east. Compared to the rest of Mongolia, the wind speed is lower in Ulaanbaatar city and the

    average yearly wind speed is 0.9-1.5 meters per sec, while in river valleys it reaches up to 2.5-4.8

    meters per sec. The wind speed rarely reaches 20 m/sec and the wind with up to 10 m/sec occurs

    7 or 9 days a year.

    The atmospheric pressure remains constant throughout the year. It is 845-870 gPa in October and

    November, and around 840 gPa in July. The daily difference in atmospheric pressure is 1-4 gPa

    and it does not negatively influence on human health. The atmospheric pressure of 8 gPa which

    influences on the people with cardio vascular problems is observed on only 25 days a year.

    The average annual humidity is 70-75% and in the driest spring season and reaches up to 45-

    55%. The average annual precipitation is 240 mm. In general, 95-97 percent of precipitation falls

    in warm season, including 75-80 percent in the summer. In winter, the precipitation ranges from 1

    to 3 mm, whereas in July it ranges from 100 to 120 mm. It rains 40-70 days a year, 25-30 days

    snows and 140-170 days are observed to be having snow coverage. [2]

    Table 1 Temperature Data in Ulaan Baatar

    Temperature in Ulaan Baatar Precipitation(days)

    Months Normal Warmest Coldest Normal

    January -24.6C -15.6C -26.5C 0February -20.6C -11.4C -24.1C 0

    March -9.8C -2.0C -15.4C 0April 0.3C 8.3C -5.8C 2

    May 8.9C 16.8C 2.7C 3June 14.6C 21.6C 8.3C 9

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    7/25

    7

    July 16.6C 22.7C 11.2C 11August 14.7C 21.5C 9.3C 13

    September 7.3C 15.6C 2.2C 4October -1.1C 6.8C -6.0C 2

    November -13.2C -4.4C -16.2C 1December -21.9C -13.7C -23.8C 1

    (Source:www.yr.no)

    2.5 Parameters and Limit Values

    Ulaan Baatar (UB) ranks second in the worlds most polluted cities. It also has the poorest ambient

    air quality. Air pollution in Ulaan Baatar is caused not only by the general factors like Coal Power

    plants, traffic and so on, but also the burning of coal and wood in the residential areas also known

    as Ger. These Ger areas lack central heating system and almost all of them use the conventional

    and obsolete form of room heating, which contributes greatly to the Particulate matter in the winter

    season. Nearly 27% of mortality in Ulaanbaatar is due to air pollution. PM2.5 mass concentrations

    are in the range of 94343 g/m3which means 78times higher than national annual air quality

    standard and 911 times higher than WHO guidelines.$463 million is spent yearly on health costs

    (mortality, bronchitis, and hospitalizations) in Mongolia as an effect of this air pollution [3]. Another

    important thing to be noted is that the National air quality value limits are set two times more than

    that of WHO Guidelines for the air quality, but still get exceeded up to 5-6 times of the National

    Standards. Some of the data that corresponds to the Particulate matter and the air quality in Ulaan

    Baatar are as follows:

    Figure 1 PM Data, UB, 2012 (Source: Ryan.W.Allen, ACMS, January 2013)

    http://www.yr.no/http://www.yr.no/http://www.yr.no/http://www.yr.no/
  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    8/25

    8

    Figure 2 PM Data of Ulaan Baatar from 2004-2012

    Figure 3 Air Pollution in Ulaan Baatar compared to other world cities

    World Health Organization (WHO) Limits:

    PM2.5:

    10 g/m3, annual mean

    25 g/m3, 24-hour mean

    PM10:

    0.0

    100.0

    200.0

    300.0

    400.0

    500.0

    600.0

    700.0

    800.0

    N

    ov-04

    M

    ar-05

    D

    ec-05

    A

    pr-06

    A

    ug-06

    D

    ec-06

    A

    pr-07

    A

    ug-07

    D

    ec-07

    A

    pr-08

    S

    ep-08

    J

    an-09

    M

    ay-09

    O

    ct-09

    F

    eb-10

    J

    un-10

    O

    ct-10

    F

    eb-11

    J

    un-11

    O

    ct-11

    M

    ar-12

    Jul-12

    PM2.5

    PM10

    PM2.5Avarage (year)

    PM10 Avarage(year)

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    9/25

    9

    20 g/m3, annual mean

    50 g/m3, 24-hour mean

    Table 2 Exceedance factors of Particulate matter in UB

    2.6 Effects of Air Pollution

    The health effects caused by the Air pollution are one of the most important problems that have

    to be combated in this modern age. There are different health and toxic effects that are directly or

    indirectly by the pollutants dispersed in the atmosphere. As our project deals about the quality of

    particulate matter in the ambient air, some of the types and health effects of Particulate matter in

    the air are as follows:

    Figure 4 Aerosol size distribution and health effects (Source: S.Lodoysamba.et.al, 2011)

    Area PM 10 (g/m3) PM 2.5 (g/m3) Exceedance

    (factor)

    Central Part UB 300 150 6

    Ger Area UB 350-900 300-620 7-18

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    10/25

    10

    Some of the common health effects of Air Pollution are as follows (Source: WHO)

    PM affects more people than any other pollutant (WHO).

    Chronic exposure to PM (Both PM10and PM2.5) contributes to the risk of developing

    cardiovascular and respiratory diseases, as well as of lung cancer. Exposure to pollutants from indoor combustion of solid fuels on open fires or traditional

    stoves increases the risk of acute lower respiratory infections and associated mortality

    among young children.

    Indoor air pollution from solid fuel use is also a major risk factor for chronic obstructive

    pulmonary disease and lung cancer among adults.

    2.7 Assessment of Results of Measurements

    The measured values from the monitoring stations are always assessed and compared to the

    national and the international limit values, test values and recommended values. At the end of the

    duration of measurements, the values are compared and reviewed.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    11/25

    11

    3. MEASUREMENT STRATEGY

    3.1 Measurement Locations

    The first step involves the selection for the measurement locations of the places under

    consideration. The locations must serve the main purpose of continuous monitoring of the

    particulate matter in the city of Ulaan Baatar. The main problem lies in the selection anddistribution of the monitoring locations across the city based on its significance.

    3.2 Selection of the measurement locations

    Though Ulaanbaatar has four existing stations for the air pollution monitoring, they are not widely

    distributed along the whole city. And though the existing stations have the technical expertise to

    monitor major pollutants like Carbon Monoxide, NOx and SOx around the city, inadequate

    technical assurance prevails for the Particulate matter monitoring. So we are planning to increase

    the monitoring stations to eight, all of which serves mainly for the monitoring of the Particulate

    Matter (PM10 and PM2.5) in the ambient air of Ulaan Baatar, Mongolia.

    3.3 Significance of the selected locations

    The locations for the continuous monitoring of the ambient air quality are selected based on their

    residential and commercial significance. As the proposed stations are eight in number, it has been

    given a good balance and distribution among the areas throughout the city. The

    commercial/industrial locations involve areas near Thermal Power plants, City square and

    educational institutions. Added to that, the residential areas are chosen with Ger areas in mind and

    also the International airport, which is just 2.5-3 Kms away from a huge Ger area. In the heavy

    traffic regions of city centre, the instrument for the monitoring is placed on the side of the road and

    with respect to the residential areas; the instrumental setup is done in the top of the buildingsnearby.

    Figure 5 Existing Monitoring Stations in Ulaan Baatar

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    12/25

    12

    Figure 6 Proposed Monitoring Stations in Ulaan Baatar (Marked in Red and Green)

    Table 3 List of monitoring stations in Ulaan Baatar

    Commercial/Industrial Locations (Red) Residential Locations (Green)A1 - BGD Khoroo-5 (Near Thermal Power Plant-4)

    A5 - Chinggis Khan International Airport (Nearto Nisekh)

    A2 - Bayanbogd Plaza (Near SukhbaatarSquare)

    A6Gan Khitis (Ger areas with traffic)

    A3Mongolia International University A7Hospital of Psychics

    A4 - Mongolian Data Centre (near Ash basin ofThermal Power Plant-4

    A8Chemistry Ambulatory

    3.4 Measurement Times

    Continuous supervision of the monitoring station is not required, as the instrument works on itself

    and records continuously. But personnel are employed to supervise several tasks like

    maintenance of the devices every day, check for any flaws, electrical support, monitoring for

    external factors like harsh climate, theft and so on.

    3.5 Sampling period and duration of the measurement program

    The monitoring is done continuously over a time span of one year to get the spatial and temporal

    variations of the air quality in Ulaan Baatar. A complete measurement plan is given by the Projectleader to the team and they are briefed of their tasks during the duration. The instrumental setup is

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    13/25

    13

    installed and the device is programmed to work on the continuous mode. Along with the monitoring

    of the values, the instrument also gives the real time mass concentration of the Particulate matter

    everyday, which can be fed to the system and can be reviewed every now and then. Personnel

    are sent frequently to check the cleanliness of the filter, efficiency and the quality of the instrument

    throughout the program. In the events of snowfall, hail storms or wind storms, the personnel

    should make sure that the device is secured and should not be disturbed while doing theinstrument. Enough battery backup should be made in case of blackouts and power outages.

    3.6 Supplementary Measurements:

    During the course of the measurement program, supplementary measurements like

    Meteorological data, rate of traffic, and so on are collected from the existing stations and are

    acquired on an everyday basis. Some personnel are employed mainly for collecting the data and

    recording them throughout this duration.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    14/25

    14

    4. MEASUREMENT TECHNIQUE

    4.1 PM Measurement

    Two methods, which continuously measure atmospheric PM concentrations, have been officially

    approved by Environment Ministry of the Germany [4]. These two methods are beta radiation

    attenuation and optical (photometric) measuring instrument. The first method monitors theattenuation of beta radiation through a paper filter. Attenuation of beta particles increases as

    particulate matter is deposited on the surface of the paper filter. While the second method,

    monitors the light absorption caused by the particulate matter.

    In respect to the economical affordability, a relatively cheap and user friendly continues PM

    monitoring tool based on photometric particle measurement principle such as DustTrakTM II 8530

    EP will be used in this project. The DustTrakTM II 8530 EP is a real time monitoring for

    segregated aerosol mass concentration and is manufactured by TSI Incorporated, USA.

    Some of the advantages of using DustTrakTM II 8530 EP for our measurement are:

    1. It measures PM2.5 and PM 10 simultaneously, thus no need for multiple instruments for

    different size fraction measurements.

    2. It is handheld (highly portable), therefore it is easier to be installed.

    3. It gives real time reading of segregated aerosol mass concentration (data acquisition rate up

    to once per second).

    4. Data-logging allow for data analysis during and after sampling.

    5. It is battery operated but also able to be connected to AS power supply, therefore in case of

    electricity shut down the measurement could be run with back up battery.

    6. It is equipped with low power consumption external pump. The external pump is able to work

    continuously for the whole year, which makes unattended monitoring in remote outdoorlocations easier.

    7. It is relatively inexpensive compare to beta attenuation method and TEOM equipment.

    8. It easy to operate and to program.

    9. Easy-to-use graphical user interface with color touch-screen for effortless operation.

    10. Automatic zeroing (with optional zero module) to minimize the effect of zero drift.

    4.2 Principle

    By using the selective inlet conditioners it is possible to measure the size segregated mass fraction

    of particle simultaneously. In accordance to the objective of the project, selective inlet conditionerfor PM2.5 and PM10 will be used. The mass concentration of particulates in a sampled airstream is

    determined based on photometric principle. As the light emitted from the laser diode is scattered by

    particles drawn through the instrument, the amount of light scatter determines the particle mass

    concentration.

    Sensor type used in this series of instrument is 90 light scattering. As the air sample enters the

    instrument it is then split into two parts. One half of the sampled air is passed through a HEPA filter

    to remove particulates and used for sheath flow. The sheath flow keeps particulate contained in a

    steady stream and reduces contamination of the optics. The other half of the sampled air passes

    through an optics chamber.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    15/25

    15

    As shown in Figure 8, the optics chamber consists of a laser diode, gold plated mirror, and photo

    detector. The light from the laser diode passes through two lenses to create a sheet of light. The

    sheet of light then passes through the sample air stream. A fraction of that light is diverted by the

    particles in the sample and reflected off the gold plated mirror to the photo detector. The voltage

    across the photo detector is multiplied by a calibration constant to determine the mass

    concentration of the sample [5].

    Figure 7 TSI DustTrakTM Model II Aerosol Monitor flow schematic (TSI, 2012)

    4.3 Instrument/Equipment

    The instrument of DustTrakTM II 8350 EP has a mass resolution of 0.1% of reading or 0.001

    mg/m3 and a detection range of 0.001400 mm. Particle size which can be measured rangebetween 0.1 and 10 m. The specifications of the instrument are summarized in the Table.

    Table 4 Specification of DustTrak TMII 8350 (TSI, 2012)

    No. Specification1 Sensor Type 90 light scattering2 Particle Size Range 0.1 to 10 m3 Aerosol Concentration Range 0.001 to 400 mg/m34 Resolution 0.1% of reading or 0.001 mg/m35 Zero Stability 0.002 mg/m3 per 24 hours at 10

    second time constant

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    16/25

    16

    6 Flow Rate 3.0 L/min set at factory, 1.4 to3.0 L/min user adjustable

    7 Flow Accuracy 5% of factory set point, internalflow controlled

    8 Temperature Coefficient 0.001 mg/m3 per C9 Storage Temperature -20 C to 60 C

    10 Operational Humidity 0 to 95% RH, non-condensing11 Time Constant User adjustable, 1 to 60 seconds12 Data Logging 5 MB of on-board memory

    The external pump module provided with Model 8530EP is designed to run continuously for about

    a year (8760 hours). There are two HEPA filters that protect the pump from contamination; one on

    the suction side of the pump and the other on the discharge side of the pump [6]. The discharge

    side of the pump collects particles shedding from the vanes of the pump and will turn black over

    time. The HEPA filters will have to be replaced once a year.

    Figure 8 External Pump of Instrument (TSI, 2012)

    4.4 Operation

    The instrument was located with an inlet height of around 2 m - 3 m installed on the top of the roof

    and attached to the rigid pipe to avoid vertical and horizontal displacement. The flow set point is

    factory set to 3 L/min total flow whereas 2 L/min of the total flow is measured aerosol flow while 1L/min of total flow is split off, filtered, and used for sheath flow.

    During the measurement period, as it more than 30 days, instead of using the batteries the AC

    power will be used for the operation of instrument. However batteries will also be a power back up

    in case of electricity shut down. Measurements are started and controlled from the main screen.

    Prior to starting a measurement the instrument should be zeroed and the run mode should be

    configured and selected. While taking a measurement the screen will display the current measured

    mass concentration. The display of the screen is shown in the Figure.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    17/25

    17

    Figure 9 Display of mass measurement on the screen (TSI, 2012)

    Data were logged at 10 minutes intervals and averaged middaymidday to match data from theother reference monitoring method which is gravimetric method. Since the test length of the

    instrument is from 1 minute to the limit of the data storage and it has 5 MB on board memory

    (could store more than 60000 data points) then logged data will be downloaded from the

    instrument after the measurement has done (at the end of the year 2014).

    4.5 Maintenance

    The DustTrakTM II 8530 requires maintenance on a regular basis. Some maintenance items are

    required each time the DustTrakTM monitor is used or on an annual basis. Apart from the annualmaintenance, which will be done before the measurement start, some maintenance such as inlet

    cleaning and replacement of internal filter are scheduled every two weeks during the measurement

    period.

    Within the measurement cleaning the inlet is supposed to be scheduled according to how much

    aerosol is drawn through the instrument. TSI recommends cleaning the inlet sample tube after 350

    hours of sampling a 1 mg/m3 concentration of aerosol. Replacement of the internal filters is also

    recommended by TSI to be done in 350 hours at 1 mg/m3 or when the filter indicator on the main

    screen changes to red. Refers to the background information of existing PM concentration, which

    is around 350 - 900 g/m3, then the inlet cleaning and the replacement of internal filter will be

    conducted every two weeks. All the required maintenance is listed on the Table.

    Table 5 Required maintenance plan during measurement (TSI, 2012)

    No. Maintenance Period1 Cleaning the inlet Twice in a month2 Replacing internal filter Twice in a month3 Perform zero check Before every time of use4 Cleaning calibration impactor Before every time of use

    5 Calibration Annually

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    18/25

    18

    4.6 Meteorological data measurement:

    Since the particulate matter concentration is a parameter that varies with respect to seasons,

    supporting meteorological data over the measurement period is needed for further assessment

    analysis. Meteorological data such as such as wind direction, wind speed, temperature andpressure will be collected from the existing meteorological station in Ulaan Baatar, since the

    DustTrakTM are not able to measure those data during the measurement time. The existing

    meteorological stations are Takhilt meteorological site, Choir weather station, Maanti weather

    station and Ulaan-Baatar weather station.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    19/25

    19

    5. ORGANIZATION

    5.1 Project Management

    Well qualified personnel with a background of minimum master in Environmental Engineering and

    experienced in air quality monitoring will be appointed as Project Manager. The Project Manager is

    responsible for

    1. Facilitate the definition of project missions, goals, tasks, and resource requirements.

    2. Creates work standards for project; establishes and defines roles and responsibilities,

    specific outcomes, and clear measures for quality and success of the team.

    3. Lead planning and implementation of projects.

    4. Responsibility for assembling the project staff; for their technical or functional development

    during the project period.

    5. Ensures that project status, issues and successes are communicated to project team,

    stakeholders, and all levels of management and documented appropriately.

    5.2 Project Administration

    One project administration with minimum education in bachelor of Environmental Engineering and

    experience in air quality monitoring will assist the project leader to manage some legal &

    communication tasks as follow:

    1. Manage communication with the local & national government of Mongolia.

    2. Manage communication with the original equipment manufacturer personnel.

    3. Manage project budget and resource allocation.

    5.3 Original Equipment Manufacture

    Original equipment manufacturer refers to the personnel from TSI, with whom the engaged with the

    project team. She/he will be responsible for providing training and development for sampling

    personnel. The training for the sampling personnel involves calibration, operation, maintenance,

    data record management.

    5.4 Sampling Personnel

    Four sampling personnel will be assigned for the technical measurement activity. Each personnel

    are responsible for two sampling points. Their tasks are setting up and operate the sampling

    equipment according to the procedure, undertaking the maintenance and reporting the finding of

    measurement activity.

    5.5 Scheduling

    The monitoring time period covers a full year, from January 2014 to December 2014, in order to

    cover all the seasons and to provide the peak and annual average concentrations needed for thefurther/ health effects assessment.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    20/25

    20

    Figure 10 Organizational Chart

    5.6 Evaluation Process:

    The rules of calculus used when evaluating the measurement data are generally required [7]:

    - To obtain measured values from the measured signals;

    - To determine the air quality characteristics in question from the measured values, and

    - To estimate measurement uncertainties.

    In order to ensure that the measurement process is reproducible, the analytical functions used theirparameters and the associated standard deviations and covariance are documented and included

    in the measurement report [8].

    5.7 Evaluation algorithms:

    To determine the air quality characteristics, mathematical algorithms are used. To ensure theat the

    evaluation are reproducible, the evaluation algorithms used are documented and included in the

    measurement report [9]. To cross check, that the Dust Trak is functioning appropriately and

    without with minimum deviations, periodic random gravimetric measurement is carried out and the

    results are noted down.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    21/25

    21

    Detection Limits is the lowest quantity of a substance that can be distinguished from the absence

    of that substance (a blank value) within a statedconfidence limit (generally 1%). The detection limit

    is estimated from themean of the blank, thestandard deviation of the blank and some confidence

    factor. From the past records and seasonal measurements done in Mongolia, there are lower risks

    that the measurement values will be below detection limit.

    The Dust Trak will be using AC power and some spare batteries will be kept available in all times,

    just be sure that the power cut would not lead to gap in measurement. As far as possible, all the

    measured values will be continuous, but if in any case there is some discontinuity or outliers that

    cannot be incorporated into the readings, it will be ignored and the next data in procession will be

    taken into account.

    5.8 Uncertainty of Result:

    The uncertainty of the values measured is heavily influenced by the spatial distribution of

    measurement locations as well as the number of such measurements carried out in order to obtain

    representative mean values.

    In the planning of measurement random samples are taken from gravimetric measurement and as

    well as the periodic data from the local authority (i.e. Mongolian Government) is taken into account

    to verify that the measurement station are working on proper order. The Gravimetric measurement

    is done at least once in each seasonal variation and other random checks are done as per

    requirement. Thus, at least one reliable data to check for seasonal variation is provided. The

    standard deviations and variances are also calculated to keep in view of the uncertainty of results

    obtained.

    http://en.wikipedia.org/wiki/Confidence_intervalhttp://en.wikipedia.org/wiki/Meanhttp://en.wikipedia.org/wiki/Standard_deviationhttp://en.wikipedia.org/wiki/Standard_deviationhttp://en.wikipedia.org/wiki/Meanhttp://en.wikipedia.org/wiki/Confidence_interval
  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    22/25

    22

    6. QUALITY ASSURANCE

    The air quality monitoring station should be within a tightly controlled and documented quality

    assurance and quality control system. The elements covered within this system include:

    - definition of monitoring objectives,

    - equipment selection,- site selection,

    - protocols for instrument operation calibration,

    - service and maintenance

    - integrity of calibration gas standards

    - data review

    - validation

    All the calibration standards used for calibration will be certified by the instrument provider and

    special trained personnel from the company will be available in case of malfunctioning. Verification

    of calibration and instrumental techniques is achieved by regular participation. In order to avoid anyerrors of procedures, routine random samples are taken and analyzed in gravimeter. Since, the

    measurement is done continuous in a period of one year, initial calibration is supposed to be

    enough for the whole measurement period.

    The main task of quality assurance is to:

    To check the instruments and the site infrastructure.

    To recalibrate the transfer gas standards routinely used on-site, using standards recently

    checked in the calibration laboratory. In addition, the air intake sampling system is cleaned

    and checked

    Data are compared with corresponding results from National Monitoring Network stations and with

    expected air pollutant concentrations under the prevailing meteorological conditions. This review

    process rapidly highlights any unusual or unexpected measurements, which may require further

    investigation. When such data are identified, attempts are made to reconcile the data against

    known or possible local air pollution sources or local meteorology, and to confirm the correct

    operation of all monitors.

    Afterwards, the data are fully validated and finalized, for compilation in planning of measurements

    report. Following these requirements data checking and review procedures allows the overall

    accuracy and precision of the data to be calculated. Wind speed and wind direction data from the

    measurements within the Ulan Baatar area are checked by comparing against results from othernearby monitoring locations.

    6.1 Calibration

    The DUSTTRAK TM monitor is calibrated with Arizona Road Dust (or ISO 12103-1, A1 test

    Dust) at TSI [10]. Usually, Arizona Road Dust calibration is appropriate because it is representative

    of a wide variety of ambient aerosols. But, since the test is being carried out in Mongolia with

    different particle size and on site condition, which is significantly different from the A1 test dust, a

    custom calibration with the aerosol of interest is needed to achieve improved accuracy for mass

    and size differentiation.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    23/25

    23

    The Dust Trak monitor has two calibration factors: a photometric calibration factor (PCF) and a size

    calibration factor (SCF) [11]. The PCF accounts for the photometric response difference between

    A1 test dust and the aerosol being measured. The SCF accounts for the differences between

    aerodynamic size and optical response. The factory default values for PCF and SCF are 1 [12].

    For greater accuracy along with gravimetric sampling, the advanced calibration is done to ensure

    an accurate result. The advanced calibration involves two gravimetric filter measurements and is

    more accurate than the standard method of calibration.

    The Dust Trak monitor combines photometry with single particle sizing for mass measurement.

    Both photometry (PCF) and size (SCF) needs to be calibrated. If SCF is not calibrated, the

    DUSTTRAK TM monitor assigns particles an incorrect size, which result in incorrect size

    segregated mass concentrations. The one gravimetric calibration will only work when the aerosol

    being measured is less than 2.5 m.

    6.2 DUSTTRAKTM Advanced Calibration using Serial Gravimetric Calibration

    The advanced calibration method is employed to yield high size segregated mass concentration

    accuracy for PM1.0, PM2.5, Respirable and PM10 size fractions. It involves two gravimetric

    measurements to obtain PCF and SCF.

    The measurement is being done with only one gravimetric sampling device hence the calibration is

    carried out in two serial steps. The experimental setup is in Figure 2. The calibration steps are

    outlined below.

    Figure 11 Setup for advanced series calculation

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    24/25

    24

    6.3 Step 1: PCF Calibration

    A PM2.5 impactor at the inlet of the external gravimetric filter is installed.

    The gravimetric sample and Dust Trak monitor is simultaneously collocated and run to

    collect enough mass on the gravimetric filter.

    The PM2.5 mass concentration (PM2.5_Grav) is calculated, from the gravimetric filter

    based on the net mass collected on the filter, sampling time, flow rate, and total litres of air

    sampled.

    The Dust Trak monitor average PM2.5 mass concentration (PM2.5_DRX) is read, from the

    screen.

    The new PCF in user calibration settings is updated.

    The new PCF is calculated using the formula:

    6.4 Step 2: SCF Calibration

    PM10 impactor at the inlet of the external gravimetric filter is installed.

    The gravimetric sample and Dust Trak monitor are simultaneously collocated and run, to

    collect enough mass on the gravimetric filter.

    The PM10 mass concentration (PM10_Grav) from the gravimetric filter is calculated based

    on the net mass collected on the filter, sampling time, flow rate, and total liters of air

    sampled.

    The Dust Trak monitor average PM2.5 (PM2.5_DRX) and PM10 (PM10_DRX) mass

    concentration from the screen is read. The new SCF is calculated using the formula:

    The new SCF in user calibration settings is updated.

    7. CONCLUSION

    The continuous measurement of PM10 and PM2.5 will be done throughout the year across the city

    of Ulaan Baatar. The measured values are compared with the limit values as prescribed by WHO

    and Mongolian Government for clarity on air quality. The data acquired from the Dust Trak at the

    eight stations give us an understanding of the nature and the quality of ambient air in Ulaan Baatar

    and the data can be correlated with other factors that contribute to the Air Pollution. Dust Trak,

    being an inexpensive direct reading dust monitor, helps reducing the technicalities with respect to

    measurement and monitoring, thereby reducing the human interference.

  • 7/21/2019 Air Quality in Ulan Baatar - Project Report

    25/25

    8. REFERENCES

    [1]Sereeter Lodoysamba.et.al: Air Particulate matter pollution in Ulaan Baatar, Mongolia;determination of composition, source contributions and source locations, 2010

    [2]National Environmental Agency, Mongolia, 2012

    [3]Ryan.W.Allen: American Centre of Mongolian Studies, January 2013

    [4]Gnter Baumbach: Air Quality Control, Springer Verlag, 1996

    [5]TSI Inc, USA, 2012

    [6]TSI Inc, USA, 2012

    [7] - VDI 4280, Part 1General Rules of the Planning of ambient air quality measurement, 1996

    [8] - VDI 4280, Part 1General Rules of the Planning of ambient air quality measurement, 1996

    [9] - VDI 4280, Part 1General Rules of the Planning of ambient air quality measurement, 1996

    [10] - Manual for DUSTTRAK TM Aerosol monitor calibration methods

    [11] - VDI 4280, Part 1General Rules of the Planning of ambient air quality measurement, 1996

    [12] - Manual for DUSTTRAK TM Aerosol monitor calibration methods