Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG)...

23
Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating Distributed Resources

Transcript of Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG)...

Page 1: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

Aidan TuohyTechnical Leader/Project Manager, EPRI

ERCOT Emerging Technology Working Group (ETWG)09/24/2014

Transmission System Considerations for Integrating Distributed Resources

Page 2: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

2© 2014 Electric Power Research Institute, Inc. All rights reserved.

Overview

• Background and Potential Bulk System Impacts of Distributed Energy Resources (DER)

• Benefit/Cost Assessment Framework for Integration of DER

• Interconnection Requirements for DER

Page 3: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

3© 2014 Electric Power Research Institute, Inc. All rights reserved.

How much PV Is Possible? DOE SunShot Initiative Scenarios…

Source: NREL, “Sensitivity of Rooftop PV Projections in the SunShot Vision Study to Market Assumptions”

Optimistic, but policy objective PV assumptions, leads toRooftop PV of 120 GW in 2030 & 240 GW in 2050.

Optimistic, but policy objective PV assumptions, leads toRooftop PV of 120 GW in 2030 & 240 GW in 2050.

Page 4: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

4© 2014 Electric Power Research Institute, Inc. All rights reserved.

Inverter – Role in Power System

Page 5: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

5© 2014 Electric Power Research Institute, Inc. All rights reserved.

• Increasing amounts of distributed energy resources– Solar PV,

– Electric Vehicles

– Demand Response

– Distributed storage

– Other distributed generation

• As penetration level of these resources increases, they may impact on bulk system reliability- impacts may include:

– Ramping and Variability Impacts

– Reactive Power Control

– Loss of DR During Low Frequency and Voltage Conditions

– System Protection Considerations

– Under Frequency and Under Voltage Load Shedding (UFLS/UVLS)

– Visibility/Controllability of DR at Bulk System Level

Distributed energy resources will impact bulk system operations

Page 6: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

EPRI Integrated Grid

Assessing Costs and Benefits of DER

Page 7: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

7© 2014 Electric Power Research Institute, Inc. All rights reserved.

Integrated Grid – Phase II3 Key Areas & Research Challenges

Benefit - Cost Framework

Benefit - Cost Framework

Interconnection Technical Guidelines

Interconnection Technical Guidelines

Grid Planning & Operations

Grid Planning & Operations

Completed Draft of Benefit-Cost Framework Presently under Internal EPRI Review

Completed Draft of Benefit-Cost Framework Presently under Internal EPRI Review

Page 8: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

8© 2014 Electric Power Research Institute, Inc. All rights reserved.

HostingHosting EnergyEnergy

CapacityCapacity

Distribution System

Bulk System

Customer or Owner

Cost/Benefits

Customer or Owner

Cost/Benefits

Societal Costs/Benefits

Societal Costs/Benefits

Benefit/Cost

1 4

5

3

2

6

Core Assumptions

Adoption/ Deployment Scenarios

Adoption/ Deployment Scenarios

Market Conditions

Market Conditions

Resource AdequacyResource Adequacy

FlexibilityFlexibility

Operational Practices & Simulation Operational Practices & Simulation

Transmission PerformanceTransmission Performance

Transmission Expansion

Transmission Expansion

System Net CostsSystem

Net Costs

System BenefitsSystem Benefits

ReliabilityReliability

Integrated Grid: Benefit Cost Framework

DRAFT

Page 9: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

9© 2014 Electric Power Research Institute, Inc. All rights reserved.

Integrated Grid: Bulk System Analysis

Transmission System

Performance Studies

DER Scenarios

Resource Adequacy

Existing SystemModel(s)

Load Forecasts

Variability Profiles

Existing Generation

Existing Network Model

Resource Epxansion

LOLE/Reserve Margin & Capacity

Credit

New Resources/Expansion

Plan

Thermal / Voltage Impacts

Operational Simulations

Resource Dispatches

Transmission System

Upgrades

Technology options

Transmission Expansion

Losses

Reliability ImpactsReserve &

Operational Changes

LOLE/Reserve Margin & Capacity

Credit

New Reserve & Operational

Modes

Integrated GridBulk System

Analysis Framework

Costs of new resources

Production Costs & Marginal

Costs

Costs of mitigation/upgrades

Cost of Losses

Cost of Base Case

Cost of Scenario

System Flexibility

Assessment

Flexibility Metrics

Line Type LegendData InputFinal ResultFeed-Forward ResultFeed Back Result

Frequency Impacts

Hosting Capacity PV & Demand

Profiles (See Fig. 5.3)

1 RESOURCE ADEQUCY

2 FLEXIBILITY

3 OPERATIONAL SIMULATION

4 TRANSMISSION PERFORMANCE

5 TRANSMISSION EXPANSION

DRAFT

Page 10: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

10© 2014 Electric Power Research Institute, Inc. All rights reserved.

How Will Future Electricity Resource Needs Change?

Ancillary services and capacity may become more valuable to operators causing a shift in market design

Ancillary services and capacity may become more valuable to operators causing a shift in market design

Before After?EirGrid Considerations

•Irish Simulation Study+ 40% renewable scenario+ w/ & w/o add’l A/S set (inertia, ramp, VAR res)

•Change in A/S Costs$60M $300M

•Regulator rejected study, but gives ballpark of potential

changes

EirGrid Considerations

•Irish Simulation Study+ 40% renewable scenario+ w/ & w/o add’l A/S set (inertia, ramp, VAR res)

•Change in A/S Costs$60M $300M

•Regulator rejected study, but gives ballpark of potential

changes

Page 11: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

Interconnection Requirements

Examples of Potential Requirements and Performance from DER

Page 12: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

12© 2014 Electric Power Research Institute, Inc. All rights reserved.

General Reliability Concerns

Reliability Functions• Reactive power/voltage control• Active power control

– inertia/primary freq response• Disturbance performance

– voltage & frequency ride through

Other Considerations• Inverter capabilities• Available headroom for wind/PV• Distributed

Inverter-Based Inverter-Based Generators must Generators must supply Reliability supply Reliability Services as they Services as they

Displace Displace Conventional Conventional

Sources of those Sources of those reliability services!reliability services!

Inverter-Based Inverter-Based Generators must Generators must supply Reliability supply Reliability Services as they Services as they

Displace Displace Conventional Conventional

Sources of those Sources of those reliability services!reliability services!

Page 13: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

13© 2014 Electric Power Research Institute, Inc. All rights reserved.

Can Inverter-Based Generation be equipped with Grid Support Functionality?

What functionalities are needed and how should they be required?

Can Inverter-Based Generation be equipped with Grid Support Functionality?

What functionalities are needed and how should they be required?

Key Questions

Page 14: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

14© 2014 Electric Power Research Institute, Inc. All rights reserved.

Low Voltage Ride Through Impact (PJM)

Source: Mahendra Patel, PJM.

Page 15: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

15© 2014 Electric Power Research Institute, Inc. All rights reserved.

Updated Interconnection Rules Reduces Risk of Frequency Instability

50.8

50.6

50.4

50.2

50.0

49.8

49.6

49.4

49.2

Grid

Fre

quen

cy in

Hz

Time in Seconds

0 10 20 30 40 50 60

Source: T. K. Vrana (2011)

Previous Interconnection Rules

Updated Interconnection Rules

German Operating Frequency Limit

Germany

15,000 PV systems

Sized 10kW+

9 GW Nominal Power

Over 3 – 4 years

Costing €70 – 180 Million

Retrofitting/ Replacing

Page 16: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

16© 2014 Electric Power Research Institute, Inc. All rights reserved.

Dynamic Assessment of potential impacts

Impact on Voltages :

Delay in voltage recovery

With and without voltage ride-thru

Impact on Voltages :

Delay in voltage recovery

With and without voltage ride-thru

Impact on Frequency:

Reduction in system inertia due to change in generation mix

PV drop out due to large voltage disturbance (as per IEEE 1547)

Impact on Frequency:

Reduction in system inertia due to change in generation mix

PV drop out due to large voltage disturbance (as per IEEE 1547)

Page 17: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

17© 2014 Electric Power Research Institute, Inc. All rights reserved.

Changes in “Response to Abnormal Voltages”

IEEE 1547-2003

IEEE 1547a

Similar Similar requirement requirement

for for frequencyfrequency

Similar Similar requirement requirement

for for frequencyfrequency

Page 18: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

18© 2014 Electric Power Research Institute, Inc. All rights reserved.

Voltage Regulation – Reactive Power Support

• Power factor setting

• Constant VAR consumption/injection

• Volt-VAR control

• Voltage Setpoint

Can support Can support distribution distribution

and/or and/or transmissiontransmission

Can support Can support distribution distribution

and/or and/or transmissiontransmission

Page 19: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

19© 2014 Electric Power Research Institute, Inc. All rights reserved.

Real power control, ramping, and curtailment

050

100150200250300350400450

4.5 6.5 8.5 10.5 12.5 14.5 16.5 18.5 20.5

DC

Volta

ge &

Cur

rent

Time (s)

Vdc Idc Modbus

-400

-300

-200

-100

0

100

200

300

400A

C Vo

ltage

& C

urre

ntVa Ia

390Vdc

3 Phase Output current ramp(only phase A shown)

DC Current ramp for 100%-25%-75% Curtailment

Modbus Signal(not actual voltage)

Modbus Signal(not actual voltage)

100% 75%25% In 4 secondsIn 6 seconds

Page 20: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

20© 2014 Electric Power Research Institute, Inc. All rights reserved.

Today’s Smart Inverter TechnologyEnabling Changes in Grid Codes

Inverters converts DC energy to AC energy and interface the generating plant with electricity grid

Traditional Inverter Functionality Smart Inverter Functionality

• Matching plant output with grid voltage and frequency

• Providing safety by providing unintentional islanding protection

• Disconnect from grid based on V/f set points

• Active power reduction in case of over-frequency

• Fault Ride Through (FRT)• Reactive power and voltage

support• Communication with grid• Many more

DC Power AC Power

Page 21: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

21© 2014 Electric Power Research Institute, Inc. All rights reserved.

What if Standards are not Changed?

Source: DOE SunShot Vision Study (Total PV Capacity in U.S. 2008 – 2030)

Not changing is

not an option!

Question is

when?

Retrofitting inverters in a later date could be pretty expensive

Page 22: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

22© 2014 Electric Power Research Institute, Inc. All rights reserved.

Summary

• Increasing levels of Distributed Energy Resources– Getting out ahead is important to be able to fully utilize

these new resources

• Need framework to understand costs/benefits– EPRI Integrated Grid effort developing framework– Should inform market development

• Inverter based generation can behave in ways desirable to system operations– Need to specify requirements– EPRI white paper series coming out soon

Page 23: Aidan Tuohy Technical Leader/Project Manager, EPRI ERCOT Emerging Technology Working Group (ETWG) 09/24/2014 Transmission System Considerations for Integrating.

[email protected]

Together…Shaping the Future of Electricity