http://nodal.ercot.com 1Lead from the front
Texas Nodal
Texas Nodal Market Management System
Requirement Documents
November 7, 2006
Sai Moorty
MMS Project Engineer
http://nodal.ercot.com 2Lead from the front
Texas Nodal
Agenda - Tuesday
Introduction
MMS Requirements Documents
Upcoming White Papers
MMS Requirements Approval Plan
ERCOT contacts
http://nodal.ercot.com 3Lead from the front
Texas Nodal
Introduction
ERCOT and Vendor (ABB) Team started work together in July 2006.
Sub teams formed for preparing requirements documents on the following major functional areas
Day-Ahead Market (DAM) and Supplementary Ancillary Service Market (SASM)
Reliability Unit Commitment (RUC)
Security Constrained Economic Dispatch (SCED)
Constraint Competitiveness Test (CCT)
Other Processes
Market Management System (MMS) Requirements Documents have been written with reference to the May 2006 version of the Texas Nodal Protocols.
Informal review (October 2006) by some Market Participants of DAM/SASM, RUC and SCED requirements documents.
http://nodal.ercot.com 4Lead from the front
Texas Nodal
Introduction
Where we are today
Market Management System (MMS) Requirement Documents submitted for TPTF
review and approval as compliant to the Texas Nodal Protocols of May 2006
http://nodal.ercot.com 5Lead from the front
Texas Nodal
Introduction
List of MMS Requirements Documents:
Texas Nodal Market Management Systems (MMS) Requirement Specification For Overall MMS System and Other Processes
Texas Nodal Market Management Systems (MMS) Requirement Specification For Day-Ahead Market (DAM) and Supplemental Ancillary Service Market (SASM)
Texas Nodal Market Management Systems (MMS) Requirement Specification For RUC
Texas Nodal Market Management Systems (MMS) Requirement Specification For SCED and Real-Time MMS Processes
Texas Nodal Market Management Systems (MMS) Requirement Specification For Constraint Competitiveness Test (CCT)
http://nodal.ercot.com 6Lead from the front
Texas Nodal
MMS Requirements Documents
Texas Nodal Market Management Systems (MMS) Requirement Specification For Overall MMS System and Other Processes
Topics covered
Overview of MMS System
System Requirements, AS Deployment for Load Resources, DC Tie processes, COP monitoring/validation.
Operator Alerts, QSE Notification and MIS posting
http://nodal.ercot.com 7Lead from the front
Texas Nodal
MMS Requirements Documents
Texas Nodal Market Management Systems (MMS) Requirement Specification For Day-Ahead Market (DAM) and Supplemental Ancillary Service Market (SASM)
Topics covered
Overview of DAM and SASM subsystems
Inputs and Outputs of the DAM and SASM subsystems
Processing of Market Participants submissions
DAM Processes (Credit check, AS insufficiency check, Oversold CRR determination, CRR Option derating, DAM Clearing)
AS evaluation in Adjustment Period
SASM Process
Mathematical Formulation presented in Appendix
http://nodal.ercot.com 8Lead from the front
Texas Nodal
MMS Requirements Documents
Texas Nodal Market Management Systems (MMS) Requirement Specification For RUC
Topics covered
Overview of RUC subsystem
Inputs and Outputs of RUC
RUC modes (DRUC, HRUC, WRUC)
RUC Input processing
RUC Operator Controls
RUC processes
Mathematical formulation presented in Appendix
http://nodal.ercot.com 9Lead from the front
Texas Nodal
MMS Requirements Documents
Texas Nodal Market Management Systems (MMS) Requirement Specification For SCED and Real-Time MMS Processes
Topics covered
Overview of Adjustment Period and Real-Time Operations related to MMS
Inputs and Outputs of SCED
SCED Input processing
SCED Process and Settlement Point Price Calculation
Mathematical formulation presented in Appendix
http://nodal.ercot.com 10Lead from the front
Texas Nodal
MMS Requirements Documents
Texas Nodal Market Management Systems (MMS) Requirement Specification For Constraint Competitiveness Test (CCT)
Topics covered
Overview of CCT (Annual, Monthly, Daily)
Inputs and Outputs of CCT
CCT Processes
http://nodal.ercot.com 11Lead from the front
Texas Nodal
Upcoming White Papers
Requirement Analysis of Real-Time Operations related to Load Frequency Control (LFC) and its interaction with Security Constrained Economic Dispatch (SCED) has raised issues.
Subsequent discussions between ERCOT, Vendors (AREVA and ABB) and Floyd Trefny (Consultant) resulted in decision to submit White Papers to TPTF for review.
The topics covered in the white papers primarily impacts the EMS Generation Subsystem. The main topics of the White Papers are listed below:
Responsive Reserve deployment and recall
Non-Spinning Reserve deployment and recall
Handling of inconsistent High Dispatch Limit (HDL) and Low Dispatch Limit (LDL)
Ramping of Base Points through telemetered desired generation
Resource Ancillary Service telemetry requirements
http://nodal.ercot.com 12Lead from the front
Texas Nodal
Upcoming White Papers
Potential impact of White Papers on MMS conceptual design are in the following areas:
Requirements related to use of Resource Ancillary Service telemetry
Responsive Reserve deployment and recallSCED Ramp Rate CalculationSCED Generation Requirement
Important: While these whitepapers may affect MMS conceptual design, they do not affect the submitted MMS requirements documents or this review process.
Planned next steps
November 17, 2006: Planned submission of White Papers to TPTF
November 27, 2006: TPTF comments on White Papers due to ERCOT
November 28-30, 2006: Discussion on White Papers
http://nodal.ercot.com 13Lead from the front
Texas Nodal
MMS Requirements Approval Plan
1. November 16, 2006: TPTF comments due to ERCOT
ERCOT would encourage comments to be submitted when ready
MMS team (ERCOT and Vendors) will be available for clarification
2. November 28, 2006: ERCOT presents status update on and possible discussion of TPTF comments.
3. December 1, 2006*: ERCOT submits updated MMS Requirements Documents and response to TPTF comments.
4. December 4, 2006*: TPTF approves MMS Requirements Documents
*These items are target dates, and will be greatly dependent on the quantity of comments and magnitude of changes required.
http://nodal.ercot.com 14Lead from the front
Texas Nodal
ERCOT Contacts
Sai MoortyMMS Project [email protected](512) 431-9648
Brandon WhittleLead, Real Time Market [email protected](512) 248-6588
Bill [email protected](512) 248-6663
http://nodal.ercot.com 15Lead from the front
Texas Nodal
Questions & Answers