November 17, 2011
Agenda Item #16 – Additional Information
VDOT Presentation to CTAC on
November 10, 2011 Hampton Roads Transportation Planning Organization
![Page 2: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/2.jpg)
Downtown Tunnel/Midtown Tunnel/MLK Extension ProjectPresented by Bradley Weidenhammer, P.E., VDOT Project Traffic Engineer
Geoff Segal, Senior Vice President, Macquarie Capital Advisors, ERC
![Page 3: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/3.jpg)
Project Overview
2
![Page 4: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/4.jpg)
Value to the Regiong
Reduces congestion and travel timeReduces congestion and travel time
Reduces idle time, saving fuel and lowering emissions
C l i I 264Creates seamless connection to I-264
Extends useful life of existing tunnels
Ends bi-directional traffic in MidtownEnds bi directional traffic in Midtown Tunnel
Improves reliability and connectivity
Enhanced p blic t anspo tationEnhanced public transportation services made available throughpartnership with Hampton Roads Transit
3
![Page 5: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/5.jpg)
Value Beyond Traffic Improvementsy p
Direct Promotes Local Job
Over $1 billion in $170 to $254 million Over 500
Direct Economic Stimulus
Promotes Economic Development
Local JobCreation
Over $1 billion in construction worksBuilt by local companiesBuilt by local labor
$170 to $254 million increase in regional productivity1
Long-term economic development
Over 500 construction jobs directly createdOver 1000 jobs indirectly createdBuilt by local labor
Utilizes local suppliers and contractors
developmentAccess to 2,000 more jobs2
Local projects can be prioritized
indirectly created200 facilities maintenance and operations jobsSmall womenbe prioritized Small, women, minority owned business involvementApprenticeship
4
Apprenticeship Programs
(1), (2) Source: The Hartgen Group
![Page 6: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/6.jpg)
Delivering Infrastructure Today
Why is this project developed as a ‘public-private’ partnership?
g y
— Allows the Commonwealth to leverage limited public dollars to deliver a complex project in a timely manner.
— Private partner is making a substantial i t t i th j t ki it litinvestment in the project - making it a reality
— Private partner is bringing innovative construction and operation methods and technologies to ensure sustainable andtechnologies to ensure sustainable and efficient operations for the life of the partnership.
— Private partner assumes risk of deliveringPrivate partner assumes risk of delivering the project on a performance-based, fixed-price, fixed date contract, protecting users and taxpayers from cost overruns and delays.
VDOT will always retain ownership of the assets and oversight of ERC
5
VDOT will always retain ownership of the assets and oversight of ERC
![Page 7: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/7.jpg)
Key Business Termsy
ERC responsible for Tunnels 58 Y
InvestmentEZ PassTolls Terms
ERC responsible for$2.5 billion of construction and operations and maintenance costs
TunnelsAuto off-peak: $1.59; Peak: $1.84Truck1 off-peak: $4 77 P k $7 36
58 Years
maintenance costs
Commonwealth providing contribution of
$4.77; Peak: $7.36
MLK Extension$0.50 for tunnel contribution of
$395 million specifically to lowertoll
users$1.00 for non-tunnel users
661 Truck rate is for 3-axle vehicle; fewer axels will result in lower rates
![Page 8: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/8.jpg)
What determines the toll rates?
A number of factors contribute to determining the toll rates, including scope of the project and how it will be funded initially and in the long-term.
T ll tToll rate:Is used to fund the cost of upfront design and construction, as well as ongoing capital and lifetime operations and maintenance costs.Will not escalate until substantial completion of the new Midtown TunnelWill not escalate until substantial completion of the new Midtown Tunnel.
Toll escalation: Accounts for increases in costs for operations and maintenance asAccounts for increases in costs for operations and maintenance as materials, supplies and labor costs increase.Sets maximum allowable rate.
7
![Page 9: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/9.jpg)
How will tolls be collected?
There will not be toll booths; no cash will beaccepted on-site for payment
Overhead arches, called “gantries,” will electronically accept payment or be used to generate an invoice
This is called “all electronic tolling” and is a proven, safe way to collect tolls without creating congestion
Tolls can be paid via E-ZPassTM or by invoiceE-ZPass is an automatic, electronic toll collection t th t ffi i tl t ffi th h t llsystems that efficiently moves traffic through toll
facilities along much of the East CoastE-ZPass is well established and is used in 14 states,
including Virginia
If a driver does not have E-ZPass, an invoicewill be mailed to them
Invoiced customers will be charged for cost recovery, which by Virginia law is capped at two times base toll
8
which by Virginia law is capped at two times base toll rate.
Payment can be made by mail, online or telephone
![Page 10: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/10.jpg)
How All Electronic Tolling Worksg
The cheapest, easiest way for motorists to interact with All Electronic
An All Electronic Toll Gantrymotorists to interact with All Electronic Tolling is via E-ZPass
E-ZPass can be obtained online, by telephone or in-person:www ezpassva com
Detection & ClassificationLicense Plate
Camera
www.ezpassva.com1-877-762-7824
Th t d ith dh iThe transponder comes with adhesive mounting strips and easy-to-follow instructions to mount it on the interior windshield
The transponder contains an electronic chip that is read by the toll “gantry.” The appropriate toll is electronically debited from your prepaid E-ZPass account
9
from your prepaid E ZPass accountAntennaE-ZPass
Transponder
![Page 11: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/11.jpg)
Timeline for Developmentp
M 2008C ll f t l l
Timetable
September 2008Conceptual proposal submittal
March to June 2009Public Hearings – Independent Review Panel
May 2008Call for conceptual proposals
July 2009Positive CTB RecommendationOctober 2009Key business points presented to CTB
January 2010Signature of Interim Agreement
July 2011Key Business Terms Agreed
January 2011Comprehensive Agreement Negotiations Begin
1Q 2012Comprehensive Agreement/Financial Close
2012Construction Starts
Tolling Commences Q3/Q4 2012
2017Construction Complete
10
2017Construction Complete
![Page 12: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/12.jpg)
What you can expect…y p
Construction impacts will be limitedConstruction impacts will be limited.
Continued outreach through all phases of construction and operations, through:
— Public, community and individual meetings and presentations together with the cities of Norfolk and Portsmouth
— Website postings and updates
— Email subscriber updates
Tolling information through education campaigns
11
![Page 13: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor](https://reader033.fdocuments.us/reader033/viewer/2022060522/6051d35cf8863156414d3524/html5/thumbnails/13.jpg)
Where to get more information
Find out more about the project:
g
p jwww.MidtownTunnel.org
VDOT Contact information:Frank Fabian, [email protected]
Developer Information:www.ERC-Info.com
ERC Contact information:Geoff Segal [email protected]
E-ZPass information and sign-up:www.ezpassva.com1-877-762-7824