November 17, 2011 Agenda Item #16 – Additional Information VDOT Presentation to CTAC on November 10, 2011 Hampton Roads Transportation Planning Organization

Transcript of Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation...

Page 1: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

November 17, 2011

Agenda Item #16 – Additional Information

VDOT Presentation to CTAC on

November 10, 2011 Hampton Roads Transportation Planning Organization

Page 2: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Downtown Tunnel/Midtown Tunnel/MLK Extension ProjectPresented by Bradley Weidenhammer, P.E., VDOT Project Traffic Engineer

Geoff Segal, Senior Vice President, Macquarie Capital Advisors, ERC

Page 3: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Project Overview

2

Page 4: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Value to the Regiong

Reduces congestion and travel timeReduces congestion and travel time

Reduces idle time, saving fuel and lowering emissions

C l i I 264Creates seamless connection to I-264

Extends useful life of existing tunnels

Ends bi-directional traffic in MidtownEnds bi directional traffic in Midtown Tunnel

Improves reliability and connectivity

Enhanced p blic t anspo tationEnhanced public transportation services made available throughpartnership with Hampton Roads Transit

3

Page 5: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Value Beyond Traffic Improvementsy p

Direct Promotes Local Job

Over $1 billion in $170 to $254 million Over 500

Direct Economic Stimulus

Promotes Economic Development

Local JobCreation

Over $1 billion in construction worksBuilt by local companiesBuilt by local labor

$170 to $254 million increase in regional productivity1

Long-term economic development

Over 500 construction jobs directly createdOver 1000 jobs indirectly createdBuilt by local labor

Utilizes local suppliers and contractors

developmentAccess to 2,000 more jobs2

Local projects can be prioritized

indirectly created200 facilities maintenance and operations jobsSmall womenbe prioritized Small, women, minority owned business involvementApprenticeship

4

Apprenticeship Programs

(1), (2) Source: The Hartgen Group

Page 6: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Delivering Infrastructure Today

Why is this project developed as a ‘public-private’ partnership?

g y

— Allows the Commonwealth to leverage limited public dollars to deliver a complex project in a timely manner.

— Private partner is making a substantial i t t i th j t ki it litinvestment in the project - making it a reality

— Private partner is bringing innovative construction and operation methods and technologies to ensure sustainable andtechnologies to ensure sustainable and efficient operations for the life of the partnership.

— Private partner assumes risk of deliveringPrivate partner assumes risk of delivering the project on a performance-based, fixed-price, fixed date contract, protecting users and taxpayers from cost overruns and delays.

VDOT will always retain ownership of the assets and oversight of ERC

5

VDOT will always retain ownership of the assets and oversight of ERC

Page 7: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Key Business Termsy

ERC responsible for Tunnels 58 Y

InvestmentEZ PassTolls Terms

ERC responsible for$2.5 billion of construction and operations and maintenance costs

TunnelsAuto off-peak: $1.59; Peak: $1.84Truck1 off-peak: $4 77 P k $7 36

58 Years

maintenance costs

Commonwealth providing contribution of

$4.77; Peak: $7.36

MLK Extension$0.50 for tunnel contribution of

$395 million specifically to lowertoll

users$1.00 for non-tunnel users

661 Truck rate is for 3-axle vehicle; fewer axels will result in lower rates

Page 8: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

What determines the toll rates?

A number of factors contribute to determining the toll rates, including scope of the project and how it will be funded initially and in the long-term.

T ll tToll rate:Is used to fund the cost of upfront design and construction, as well as ongoing capital and lifetime operations and maintenance costs.Will not escalate until substantial completion of the new Midtown TunnelWill not escalate until substantial completion of the new Midtown Tunnel.

Toll escalation: Accounts for increases in costs for operations and maintenance asAccounts for increases in costs for operations and maintenance as materials, supplies and labor costs increase.Sets maximum allowable rate.

7

Page 9: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

How will tolls be collected?

There will not be toll booths; no cash will beaccepted on-site for payment

Overhead arches, called “gantries,” will electronically accept payment or be used to generate an invoice

This is called “all electronic tolling” and is a proven, safe way to collect tolls without creating congestion

Tolls can be paid via E-ZPassTM or by invoiceE-ZPass is an automatic, electronic toll collection t th t ffi i tl t ffi th h t llsystems that efficiently moves traffic through toll

facilities along much of the East CoastE-ZPass is well established and is used in 14 states,

including Virginia

If a driver does not have E-ZPass, an invoicewill be mailed to them

Invoiced customers will be charged for cost recovery, which by Virginia law is capped at two times base toll

8

which by Virginia law is capped at two times base toll rate.

Payment can be made by mail, online or telephone

Page 10: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

How All Electronic Tolling Worksg

The cheapest, easiest way for motorists to interact with All Electronic

An All Electronic Toll Gantrymotorists to interact with All Electronic Tolling is via E-ZPass

E-ZPass can be obtained online, by telephone or in-person:www ezpassva com

Detection & ClassificationLicense Plate

Camera

www.ezpassva.com1-877-762-7824

Th t d ith dh iThe transponder comes with adhesive mounting strips and easy-to-follow instructions to mount it on the interior windshield

The transponder contains an electronic chip that is read by the toll “gantry.” The appropriate toll is electronically debited from your prepaid E-ZPass account

9

from your prepaid E ZPass accountAntennaE-ZPass

Transponder

Page 11: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Timeline for Developmentp

M 2008C ll f t l l

Timetable

September 2008Conceptual proposal submittal

March to June 2009Public Hearings – Independent Review Panel

May 2008Call for conceptual proposals

July 2009Positive CTB RecommendationOctober 2009Key business points presented to CTB

January 2010Signature of Interim Agreement

July 2011Key Business Terms Agreed

January 2011Comprehensive Agreement Negotiations Begin

1Q 2012Comprehensive Agreement/Financial Close

2012Construction Starts

Tolling Commences Q3/Q4 2012

2017Construction Complete

10

2017Construction Complete

Page 12: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

What you can expect…y p

Construction impacts will be limitedConstruction impacts will be limited.

Continued outreach through all phases of construction and operations, through:

— Public, community and individual meetings and presentations together with the cities of Norfolk and Portsmouth

— Website postings and updates

— Email subscriber updates

Tolling information through education campaigns

11

Page 13: Agenda Item #16 – Additional Information VDOT Presentation ... · Development Local Job Creation Over $1 billion in construction works Built by local companies Builtbylocallabor

Where to get more information

Find out more about the project:

g

p jwww.MidtownTunnel.org

VDOT Contact information:Frank Fabian, [email protected]

Developer Information:www.ERC-Info.com

ERC Contact information:Geoff Segal [email protected]

E-ZPass information and sign-up:www.ezpassva.com1-877-762-7824