AGC PresentationFebruary 10, 2020
![Page 2: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/2.jpg)
Project List
• Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track• Ridge View Elementary Remodel/Replacement
![Page 3: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/3.jpg)
Kamiakin High School23,000sf - 12 Classroom Addition
Improve Athletic FacilitiesNew artificial turf fieldNew storage, team and concession buildingsNew tennis courts
Expand Parking Lots
Anticipated Construction Cost - $13M
ScheduleBid Documents Posted 2/24/2020Bid Date 3/19/2020NTP April 2020Project Completion June 2021
![Page 4: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/4.jpg)
Kamiakin High School
![Page 5: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/5.jpg)
Kamiakin High School
![Page 6: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/6.jpg)
Kamiakin High School
![Page 7: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/7.jpg)
Kamiakin High School
![Page 8: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/8.jpg)
Kamiakin High School
![Page 9: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/9.jpg)
Southridge High School30,000sf - 12 Classroom Addition
New Bus Entrance
Improve Athletic Facilities• Add a weight training room• Replace grass field with artificial turf• Add track storage
Replace Existing HVAC Equipment
Anticipated Construction Cost $19M
GC/CM Delivery – Bouten Construction
ScheduleTrade Partner Bidding 3/9/20 – 4/3/20Construction May 2020 – June 2021
![Page 10: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/10.jpg)
Southridge High SchoolOpens: 2021
GC/CM Contractor: Bouten
![Page 11: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/11.jpg)
Southridge High School
![Page 12: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/12.jpg)
Southridge High School
![Page 13: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/13.jpg)
Southridge High School
![Page 14: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/14.jpg)
Southridge High School
![Page 15: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/15.jpg)
Highlands MS TrackEstimated Construction Cost $1MBid Documents Posted 2/17/20Bids Due 3/16/20Construction March ‘20 – Aug ’20
![Page 16: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/16.jpg)
Ridge View ElementaryEstimated Construction Cost $23MBid 2023Open 2024
![Page 17: AGC Presentation - Microsoft...AGC Presentation February 10, 2020 Project List • Kamiakin High School Addition • Southridge High School Addition • Highlands Middle School Track](https://reader035.fdocuments.us/reader035/viewer/2022062603/5f02cc8d7e708231d406113a/html5/thumbnails/17.jpg)
Questions?