AGC-BGM-ITP-010
-
Upload
sachin-soni -
Category
Documents
-
view
14 -
download
0
description
Transcript of AGC-BGM-ITP-010
Boddington Gold Mine Expansion Project
Contract No: 11147/C026A
Job No: B2338
ITP No: Revision: 0
AGC Job No: B2338 Reviewed By: Nagesh S. Approved: K. Deery
CONTROL CATEGORIES: H = Inspection Hold Point (Work must not proceed to the next step until this activity is completed and a signature obtained from the column placing the HOLD; i.e.. QA or Client);
W = Witness Point (Notify to permit witness, work can proceed if witness does not attend at agreed time); S = Surveillance Point (Monitor operations); R = Review Documentation (Sign or Stamp to record review).
1 Document Control
1.1 Receive documents from Client Scope work Contract AFC drawings H
1.2 Welder Qualifications 11147-699-50SP-003 AS3992
ASME B31.3/ASME IX
Weld Register R
1.3 WPS and back up PQRS Approved PQR AS3992 Approved weld procedure
specification
R
2 Material Control 11147-699-50SP-001 AS4041
2.1 Check material physical condition AS4041 Incomming goods material
report
R
2.2 Check for Quantity , Identification AS4041 Incomming goods material
report
R
Site Fabrication
3 Material verification 11147-699-50SP-001 AS4041 Incomming goods material
report
R
3.1 Verify material dimension and specification AS4041 Inspection report R
4 Cutting
4.1 Cut material to required length AS4041
AS4458
Cutting List S
4.2 Prepare edge preparation to WPS requirement Approved PQR AS4041
AS4458
Cutting List S
5 Assembly 11147-699-50SP-003
5.1 Check fit up condition AS4041
AS4458
WPS S
AKCMR
CLIENT: AKCMR/ BGM Management Company Pty.
Ltd.
AGC - BGM - ITP - 010
INSPECTION AND TEST PLAN
Prepared By: M. Delica
PROJECT: BODDINGTON GOLDMINE EXPANSION PROJECT
Contract No. : 11147/C026A
SCOPE: Installation of Piping-Generic
ACT
No. AGCACTIVITY
PROCEDURE or
SPECIFICATION
REFERENCE
ACCEPTANCE
CRITERIA
VERIFYING
DOCUMENTATION
CONTROL POINTREMARKS
Page 1 of 4
Boddington Gold Mine Expansion Project
Contract No: 11147/C026A
Job No: B2338
ITP No: Revision: 0
AGC Job No: B2338 Reviewed By: Nagesh S. Approved: K. Deery
CONTROL CATEGORIES: H = Inspection Hold Point (Work must not proceed to the next step until this activity is completed and a signature obtained from the column placing the HOLD; i.e.. QA or Client);
W = Witness Point (Notify to permit witness, work can proceed if witness does not attend at agreed time); S = Surveillance Point (Monitor operations); R = Review Documentation (Sign or Stamp to record review).
AKCMR
CLIENT: AKCMR/ BGM Management Company Pty.
Ltd.
AGC - BGM - ITP - 010
INSPECTION AND TEST PLAN
Prepared By: M. Delica
PROJECT: BODDINGTON GOLDMINE EXPANSION PROJECT
Contract No. : 11147/C026A
SCOPE: Installation of Piping-Generic
ACT
No. AGCACTIVITY
PROCEDURE or
SPECIFICATION
REFERENCE
ACCEPTANCE
CRITERIA
VERIFYING
DOCUMENTATION
CONTROL POINTREMARKS
5.2 Check dimensional tolerance AS4458 Inspection report S
5.3 Verify pipe fitting identification and record trace-
abilty
11147-699-50SP-001 AS4041 Trace-ability records R
6 Electrode Handling Control
6.1 Monitor Electrode Baking & Holding Condition Approved weld
procedures
AS4041 Electrode issue register R
6.2 Monitor Electrode Consumable Issue Control Approved weld
procedures
Manufacturer's
Recommendation
Electrode issue register R
6.3 Check Electrode Quiver Condition Approved weld
procedures
AS4041 Inspection report R
7 Non Destructive testing required
7.1 NDE Completed as per required 11147-699-50SP-003 AS4037 NATA report R
8 Installation of Pipe work 11147-699-50SP-003 AS3892/AS4041
8.1 Install pipe supports Approved drawing 11147-CC-PIPE1-001 R
8.2 Install pipe spools Approved drawing 11147-CC-PIPE1-001 R
9 Check elevations and orientation Approved drawing 11147-CC-PIPE1-001 R
9.1 Make up Flanges 11147-699-50SP-003 Approved drawing 11147-CC-PIPE1-001 R
9.2 Install valves and ensure correct flow direction 11147-699-50SP-003 Approved drawing 11147-CC-PIPE1-001 R
9.3 Install gaskets 11147-699-50SP-001 Material certificate Incomming goods material
report
S
Page 2 of 4
Boddington Gold Mine Expansion Project
Contract No: 11147/C026A
Job No: B2338
ITP No: Revision: 0
AGC Job No: B2338 Reviewed By: Nagesh S. Approved: K. Deery
CONTROL CATEGORIES: H = Inspection Hold Point (Work must not proceed to the next step until this activity is completed and a signature obtained from the column placing the HOLD; i.e.. QA or Client);
W = Witness Point (Notify to permit witness, work can proceed if witness does not attend at agreed time); S = Surveillance Point (Monitor operations); R = Review Documentation (Sign or Stamp to record review).
AKCMR
CLIENT: AKCMR/ BGM Management Company Pty.
Ltd.
AGC - BGM - ITP - 010
INSPECTION AND TEST PLAN
Prepared By: M. Delica
PROJECT: BODDINGTON GOLDMINE EXPANSION PROJECT
Contract No. : 11147/C026A
SCOPE: Installation of Piping-Generic
ACT
No. AGCACTIVITY
PROCEDURE or
SPECIFICATION
REFERENCE
ACCEPTANCE
CRITERIA
VERIFYING
DOCUMENTATION
CONTROL POINTREMARKS
9.5 Ensure correct bolts installed 11147-699-50SP-001 Approved drawing 11147-CC-PIPE1-001 W
9.6 Minimum 3 threads protruding through nut 11147-699-50SP-003 11147-CC-PIPE1-001 S
10 Field Welds Approved drawing
10.1 Check fit up condition AKCMR approved
PQR
AS4041
AS4458
Approved WPS W
10.2 Check dimensional tolerance 11147-699-50SP-003 AS4458 Inspection report W
10.3 Verify pipe fitting identification and record trace-
abilty
11147-699-50SP-003 AS4041 Trace-ability records R
10.4 Pipe line marking for content and flow direction 11147-699-50SP-003 AS1345 Inspection report W
11 Flushing lines
11.1 Remove sensitive instrument and filters 11147-699-50SP-003 11147-CC-PIPE2-001 R
11.2 Open all valves 11147-699-50SP-003 11147-CC-PIPE2-001 R
11.3 Flush with water until free of dirt, grit, welding slag
and other foreign materials
11147-699-50SP-003 AKCMR approved
Test pack
11147-CC-PIPE2-001 R
11.4 Authorised drainage of water 11147-699-50SP-003 AKCMR approved
Test pack
11147-CC-PIPE2-001 R
12 Pressure testing
12.1 Identify test requirements 11147-699-50SP-003 Approved Test pack 11147-CC-PIPE2-002 R
12.2 Develop test packs and issue to AKCMR for
approval
11147-699-50SP-003 AKCMR approved test pack R
Page 3 of 4
Boddington Gold Mine Expansion Project
Contract No: 11147/C026A
Job No: B2338
ITP No: Revision: 0
AGC Job No: B2338 Reviewed By: Nagesh S. Approved: K. Deery
CONTROL CATEGORIES: H = Inspection Hold Point (Work must not proceed to the next step until this activity is completed and a signature obtained from the column placing the HOLD; i.e.. QA or Client);
W = Witness Point (Notify to permit witness, work can proceed if witness does not attend at agreed time); S = Surveillance Point (Monitor operations); R = Review Documentation (Sign or Stamp to record review).
AKCMR
CLIENT: AKCMR/ BGM Management Company Pty.
Ltd.
AGC - BGM - ITP - 010
INSPECTION AND TEST PLAN
Prepared By: M. Delica
PROJECT: BODDINGTON GOLDMINE EXPANSION PROJECT
Contract No. : 11147/C026A
SCOPE: Installation of Piping-Generic
ACT
No. AGCACTIVITY
PROCEDURE or
SPECIFICATION
REFERENCE
ACCEPTANCE
CRITERIA
VERIFYING
DOCUMENTATION
CONTROL POINTREMARKS
12.3 Prepare Job Hazard Analysis 11147-699-50SP-003 AKCMR Approved JHA R
12.4 Pressure test system as per specification 11147-699-50SP-003 Approved Test pack
AS 4041/AS 4037
11147-CC-PIPE2-002 R
12.5 Vent high and low points as required. 11147-699-50SP-003 Approved Test pack 11147-CC-PIPE2-002 R
12.6 Drain and dry lines. 11147-699-50SP-003 Approved Test pack 11147-CC-PIPE2-002 R
13 Site Surface Treatment
13.1 Touch up site joints after Pressure testing. 11147-699-10SP-006 11147-CC-PIPE1-001 S
14 Final Inspection
14.1 Carry out Final Inspection. 11147-699-50SP-003 11147-699-50SP-003 11147-CC-PIPE1-002 H
15 Finalise Documentation
15.1 Sign off Inspection & Test Plan. 11147-699-50SP-003 Quality Requirements ITP R
15.3 Complete Manufacturers Data Report Project Quality Plan MDR R
Page 4 of 4