AFRICAN DEVELOPMENT BANK GROUP rized MULTINATIONAL ... · AFRICAN DEVELOPMENT BANK GROUP rized...

39
AFRICAN DEVELOPMENT BANK GROUP MULTINATIONAL CAMEROON AND CHAD POWER INTERCONNECTION PROJECT RDGC DEPARTMENT November 2017 Translated Document Public Disclosure Authorized Public Disclosure Authorized

Transcript of AFRICAN DEVELOPMENT BANK GROUP rized MULTINATIONAL ... · AFRICAN DEVELOPMENT BANK GROUP rized...

AFRICAN DEVELOPMENT BANK GROUP

MULTINATIONAL

CAMEROON AND CHAD POWER INTERCONNECTION PROJECT

RDGC DEPARTMENT

November 2017

Translated Document

P

ub

lic D

iscl

osu

re A

uth

ori

zed

P

ub

lic D

iscl

osu

re A

uth

ori

zed

TABLE OF CONTENTS

1. STRATEGIC THRUST AND RATIONALE ............................................................................................ 1

1.1. PROJECT LINKAGES WITH COUNTRY STRATEGY AND OBJECTIVES ........................................................ 1 1.2. RATIONALE FOR BANK’S INVOLVEMENT ............................................................................................... 1 1.3 AID COORDINATION ............................................................................................................................... 2

2. PROJECT DESCRIPTION ........................................................................................................................ 3

2.1. PROJECT OBJECTIVES AND COMPONENTS .............................................................................................. 3 2.2. TECHNICAL SOLUTIONS ADOPTED AND ALTERNATIVES EXPLORED ...................................................... 3 2.3. PROJECT TYPE ....................................................................................................................................... 4 2.4. PROJECT COST AND FINANCING ARRANGEMENTS ................................................................................. 4 2.5. PROJECT TARGET AREA AND BENEFICIARIES ........................................................................................ 6 2.6 PARTICIPATORY APPROACH ................................................................................................................... 7 2.7. BANK GROUP EXPERIENCE AND LESSONS REFLECTED IN PROJECT DESIGN .......................................... 8 2.8. KEY PERFORMANCE INDICATORS .......................................................................................................... 8

3. PROJECT FEASIBILITY .......................................................................................................................... 8

3.1. FINANCIAL AND ECONOMIC PERFORMANCE .......................................................................................... 8 3.2. ENVIRONMENTAL AND SOCIAL IMPACT ................................................................................................. 9

4. PROJECT IMPLEMENTATION ............................................................................................................ 12

4.1. IMPLEMENTATION ARRANGEMENTS .................................................................................................... 12 4.2. PROJECT MONITORING AND EVALUATION ........................................................................................... 15 4.3. GOVERNANCE ...................................................................................................................................... 15 4.4. SUSTAINABILITY .................................................................................................................................. 15 4.6. KNOWLEDGE BUILDING ....................................................................................................................... 16

5. LEGAL FRAMEWORK ........................................................................................................................... 17

5.1. LEGAL INSTRUMENT ............................................................................................................................ 17 5.2. CONDITIONS FOR BANK INTERVENTION ............................................................................................... 17 5.3. COMPLIANCE WITH BANK POLICIES ..................................................................................................... 18

6. RECOMMENDATION ............................................................................................................................. 18

ANNEXES

Annex I: Cameroon/Rationale for the Level of Government’s Counterpart Contribution to AfDB

Financing Annex II.1: Cameroon’s Comparative Socio-economic Indicator Annex II.2: Chad’s Comparative Socio-economic Indicators Annex III.1: Table of AfDB Portfolio in Cameroon as at 30 June 2017 Annex III.2: Table of AfDB Portfolio in Chad as at 30 June 2017 Annex IV.1: Similar Projects Financed by the Bank and other Development Partners of Cameroon Annex IV.2: Similar Projects Financed by the Bank and other Development Partners of Chad Annex V: Map of Project Area

i

CURRENCY EQUIVALENTS

[October 2017]

UA 1 = CFAF 785.25

UA 1 = USD 1.4133

UA 1 = EUR 1.1971

FISCAL YEAR

1 January – 31 December

WEIGHTS AND MEASURES

m metre Koe kilo of oil equivalent

cm centimetre = 0.01 metre Ktoe kilo toe = 1 000 toe

mm millimetre = 0.001 metre kV kilovolt = 1 000 volts

km kilometre = 1 000 metres kVa kilovolt ampere (1 000 va)

m² square metre kW kilowatt = 1 000 watts

cm² square centimetre GW gigawatt (1 000 000 kw or 1 MW)

km² square kilometre = 1 000 000 square metres MW megawatt (1 000 000 w or 1 000 kw

ha hectare = 10 000 square metres kWh kilowatt hour (1 000 wh)

t (t) tonne (1 000 kilogrammes) MWh megawatt hour (1 000 kwh)

toe Tonne of oil equivalent GWh gigawatt hour (1 000 000 kwh)

ii

ACRONYMS AND ABBREVIATIONS

ADF African Development Fund

AER Rural Electrification Agency

AFD French Development Agency

AfDB African Development Bank

ARSEL Electricity Sector Regulatory Agency (Cameroon)

CAA “Caisse autonome d’amortissement”

CAPP Central Africa Power Pool

CFAF Franc of the “African Financial Community”

CSP Country Strategy Paper

ECCAS Economic Community of Central African States

ESIA Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

EU European Union

FIRR Financial internal rate of return

GESP Growth and Employment Strategy Paper

HV High Voltage

IDP Internally Displaced Person

IsDB Islamic Development Bank

LV Low Voltage

MV Medium Voltage

PND National Development Plan

NEPAD New Partnership for Africa’s Development

PIU Project Implementation Unit

RAP Resettlement Action Plan

PDER Rural Electrification Masterplan

RISP Regional Integration Strategy Paper

SCP Stakeholders Commitment Plan

SNE National Electricity Corporation (Chad)

SONATREL National Electricity Transmission Corporation (Cameroon)

TFP Technical and Financial Partner

TSF Transition Support Facility

WB World Bank

iii

PROJECT INFORMATION SHEET

Client Information

Borrower/Donee Republic of Cameroun / Republic of Chad

Executing Agencies Cameroon: National Electricity Transmission Corporation (SONATREL)

Chad: National Electricity Corporation (SNE)

Financing Plan

Source of

Financing

Cameroon (million) Chad (million) Total (million) Instrument

EUR UA CFAF

x 1 000 EUR UA

CFAF x 1 000

EUR UA CFAF

x 1 000

ADB 217.91 182.03 142.94 0.00 217.91 182.03 142.94 Loan

ADF 7.18 6 4.71 0.00 7.18 6 4.71 Loan

TSF 0.00 0 32.92 27.5 21.59 32.92 27.5 21.59 Grant

IsDB 50.83 42.46 33.34 50.82 42.45 33.34 101.65 84.91 66.68 Loan

EU 0.00 0 20.00 16.71 13.12 20.00 16.71 13.12 Grant

Gvt. of

Cameroon 19.32 16.14 12.67 0 19.32 16.14 12.67

Counterpart

contribution

Gvt. of Chad 0.00 0 0 0.00 0 0.00 -

Total 295.24 246.63 193.67 103.74 86.66 68.05 398.98 333.29 261.72

Key AfDB Financing Information

Loan Currency: Euro (EUR)

Loan Type: Fully Flexible Loan

Tenor: 25 years

Grace Period: 8 years

Weighted Average Maturity**: Sixteen (16) years and nine (9) months

Repayment: Half-yearly instalments after expiry of the grace period

(thirty-four [34] equal and consecutive half-yearly

payments)

Interest Rate: Base Rate + Financing Margin + Loan Margin + Maturity

Bonus

Base Rate: Floating (six-month EURIBOR, reset on 1 February and 1

August). Floating base rate with a free fixing option.

Financing Margin: Bank financing margin, reset on 1 January and 1 July and

applied on 1 February and 1 August with the base rate.

Loan Margin: 80 basis points (0.8%)

Maturity Bonus: 0.20%

Front-end Fee: 0.25% of the loan amount payable on or before the date of

signature of the Loan Agreement

Commitment Fee: 0.25% per annum on the undisbursed loan amount,

commencing 60 days following the date of signature of the

Loan Agreement and payable on each interest payment date.

*Conversion options and related transaction costs shall be governed by the Bank’s Conversion Guidelines

available on the Bank’s website.

**A weighted average maturity calculator is available on the Bank’s website.

iv

Key ADF Financing Information – Mixed Country Lending Conditions

Loan/Grant Currency Unit of Account (UA)

Interest Rate 1%

Interest Rate Margin Not applicable

Service Charge 0.75% per annum on the disbursed and outstanding loan amount

Commitment Fee 0.5% on the undisbursed loan amount, commencing 120 days

after signature of Loan Agreement

Other Charges Not applicable

Tenor 25 years

Grace Period 5 years

Timeframe - Main Milestones (expected)

Activities (Month/Year)

Concept Note Approval October 2017

Project Approval December 2017

Signing of Loan/Grant Agreements March 2018

Effectiveness May 2018

Last Disbursement June 2022

Project Closure December 2022

v

PROJECT SUMMARY

1. Project Overview

The Cameroon-Chad Power Interconnection Project stems from the desire of both countries to

optimize the use of their energy resources by integrating their power generation, transmission

and distribution infrastructure. It will involve the construction of: (i) a 225 kV high-voltage

(HV) main transmission line between Ngaoundéré and Maroua (Cameroon) and N’Djamena

(Chad); (ii) a 225 kV high-voltage link between Maroua (Cameroon), Bongor, Guelendeng and

N’Djamena (Chad); (iii) related high-voltage (HV)/medium-voltage (MV) transformer

stations; and (iv) rural electrification distribution networks along transmission line corridors.

In total, about 1 024 kilometres of HV transmission lines (786 kilometres in Cameroon and 238

kilometres in Chad) will be constructed and 478 localities along these lines (409 of them in

Cameroun and 69 in Chad) electrified. It is one of Central Africa’s priority integration projects.

The overall project objective is to improve the economic and social development framework

of Member States of the Economic Community of Central African States (ECCAS) through

the supply of adequate quantity and quality of electricity at low cost. The sector objective is to

increase the rate of access to electricity by the population of both countries, and strengthen

cooperation and regional integration in the sub-region through energy trade between the

countries. The total project cost, net of taxes, is estimated at UA 333.29 million (EUR 398.99

million). It will be implemented over a five-year (60-month) period, from 2018 to 2022.

The direct project beneficiaries are the National Electricity Corporation (Société Nationale de

l’Électricité, SNE) in Chad, the National Electricity Transmission Corporation (Société

Nationale de Transport d’Électricité, SONATREL), the Rural Electrification Agency (AER)

and the Cameroon Electricity Corporation (ENEO) in Cameroon, which will operate the

electricity transmission and distribution infrastructure constructed, as well as the population of

the localities along the interconnection lines built. The project will directly affect about 8.9

million people, 6.5 million of them in Cameroon and 2.4 million in Chad. Besides

interconnecting the power generation and transmission infrastructure of Cameroon and Chad,

thus significantly reducing the production costs of national electricity corporations, the project

will, through the electrification of the localities along the interconnection lines, help to increase

the electricity access rate in both countries, thus contributing to improving the living conditions

of the population and reducing poverty. The execution of works will create jobs, of which at

least 15% will be for women/girls. Lastly, it will enable industries in the countries concerned,

in particular, and the sub-region, in general, to develop and expand their commercial and

production activities. It will also promote the regional integration and economic development

of Central Africa.

2. Needs Assessment

Cameroon and Chad face major economic and social development difficulties resulting from

various constraints, including structural deficits and exorbitant energy costs. The electricity

access is about 67% in Cameroon and 3.9% in Chad. The project seeks to: (i) improve the

supply, reliability and accessibility of electricity in both countries through cross-border trade

in cheap and cleaner power; (ii) promote electricity trade and regional integration; and thus (iii)

contribute to Central Africa’s socio-economic transformation.

vi

3. Bank’s Value Added

In July 2003, the Bank approved an ADF grant to finance the Study on the Interconnection of

Power Networks of Member Countries of the Economic Community of Central African States

(EIRE-ECCAS). In October 2013, it also approved a UA 2.5 million ADF grant to finance

further studies on the Cameroon-Chad Section, which is the subject of this project. The Bank

then supported ECCAS and the Central Africa Power Pool (CAPP) to structure the project and

organize the Central Africa Power Sector Donors Round Table held on 17 June 2016 in

Brussels. During this round table, the Bank was designated as the leader of the technical and

financial partners (TFPs) of the Central Africa Power Sector and its intervention has helped to

mobilize other donors to finance the project. Thus, the Bank’s involvement in this investment

project will enable it to give effect to the development outcomes targeted by the study that it

pioneered.

4. Knowledge Management

To draw useful lessons from the project, a monitoring and evaluation system will be established

to document its outcomes and outputs. The lessons will be built on through: (i) project socio-

economic impact monitoring and evaluation reports; (ii) the evaluation of project socio-

economic impact by beneficiaries on project completion; and (iii) the progress reports of

project executing agencies in both countries. These project socio-economic impact monitoring

and evaluation reports will be posted on the Bank’s website and used to improve the

formulation of development policies and the design of similar future projects.

vii

RESULTS-BASED LOGICAL FRAMEWORK

Country and Project Name: Multinational Cameroon – Chad: Cameroon-Chad Power Interconnection Project

Project Goal: Improve the economic and social development framework of the countries by increasing the electricity access rate through cross-border trade in cheap and cleaner power.

RESULTS CHAIN

PERFORMANCE INDICATORS

MEANS OF VERIFICATION RISKS/MITIGATION

MEASURES Indicator

(including CSI) Baseline Situation (2017) Target (2022)

IMP

AC

T

Sustainable economic growth and

improvement of the living

conditions of the population of

both countries

1. GDP growth rate

2. Improved electricity

access rate

3. Drop in the average price

of electricity

1. Cameroon: 3.7%; Chad:

0.6%

2. Cameroon: 67%; Chad:

3.9%

3. Cameroon: CFAF 84.60/

kWh; Chad: CFAF 100/ kWh

1. Cameroon: 5.6%; Chad: 9%

2. Cameroon 75%; Chad: 8 %

3. Cameroon CFAF 79/ kWh; Chad:

CFAF 90/ kWh

Sources:

Chad’s PND (2017-2021);

GESP 2015-2025;

Cameroon: PDER;

Bank’s CSP; IMF reports

ECCAS and CEMAC statistics;

CAPP reports;

SNE, SONATREL and AER

progress reports.

Risk:

1. The main risk relates to the security

situation in Cameroon’s Far-North

Region, facing an influx of refugees fleeing terrorist attacks. Chad is also

grappling with terrorist incursions and

attacks in the same zone. This security situation may stretch the capacity to

implement the project to the limit. In

addition, the influx of refugees may increase social conflicts due to weak

social service delivery capacity. 2. Another risk facing the project is the

current weak capacity of the two

national entities that will be

responsible, each in its own sphere, for the various aspects of project

implementation. 1. Improvement in the supply of

and trade in electricity between both countries

2. Improvement of access to electricity by households in

rural areas

3. Reduction of greenhouse gas

emissions

1. Quantity of power traded

in GWh

2. Number of households connected

3. CO2 emissions avoided

(t/yr)

(0)

- Chad: 75 000 - Cameroon: 1 150 000

(0)

600 - Chad: 131 000, that is 56 000

additional households connected; - Cameroon: 1 444 000, that is 294

000 additional households connected [Total number of

additional households connected:

350 000]

227 291

Sources: SNE, SONATREL and AER progress reports;

Quarterly project reports; Bank supervision reports;

Reports of the ministries in charge of

women’s and youth empowerment

Mitigation Measures:

1. Concerted and coordinated actions in

the region against terrorist groups will help to mitigate the security risk. In

addition, the project will contribute to

enhancing the delivery of social services to the population.

2. The mitigation measures envisaged

concern: (i) the institutional support

that the project will provide to the executing agencies of both countries;

and (ii) the monitoring of the process of

recruiting experts for the agencies to guarantee the optimal performance by

the experts.

OU

TC

OM

ES

viii

OU

TP

UT

S

COMPONENT A

1. Construction of transmission

lines and implementation of the

Environmental and Social Management Plan (ESMP)

2. Construction of HV/MV

substations

3. Electrification of localities in

rural areas

COMPONENT B

4. Project supervision

5. Support for women’s and youth

empowerment (training, sensitization and provision of

production kits)

6. Integration of young graduates

7. Creation of permanent jobs

1. Number of kilometres of

HV transmission lines

constructed

2. Number of HV/MV

substations constructed 3. Number of localities

electrified

4. Number of project implementation and

supervision reports

5. Number of women’s and

youth groups supported in

Cameroon and in Chad

6. Number of youths who

have benefitted from pre-employment internships

7. Number of jobs created

1. 0

2. Idem

3. Idem

4. Idem

5. Idem

6. Idem

7. Idem

1. 1 024

2. 7

3. 478

4. 8 Bank supervision reports; 12 quarterly reports of the Consulting

Engineer; 1 completion report

5. 50 women’s groups (1 500 women) and 50 youth groups (1

500 youths aged between 15 to 35

years) in each country 6. 50 young graduates on internship,

at least 50% of them girls, in Chad

and 100 young graduates on internship, at least 50% of them

girls, in Cameroon.

7. 350 direct temporary jobs, at least 15% of them for women/girls; and

250 direct and indirect permanent

jobs, at least 40 of them for women/girls.

Sources:

SNE and SONATREL progress reports;

Consulting Engineer’s reports;

Bank supervision reports

KE

Y A

CT

IVIT

IES

COMPONENTS Component A: Infrastructure Development: (1) Construction of HV/MV networks; (2) Rural electrification works; and (3) Implementation

of the Environmental and Social Management Plan (ESMP).

Component B: Project Management: (1) Studies, works control and supervision; (2) Support in the form of office equipment and field technical equipment; (3) Training of women’s and youth groups; (4) Recruitment of young graduates; and (5) Project management activities.

Resources: UA 333.29 million

TSF Grant : UA 27.5 million

ADF Loan : UA 6 million

ADB Loan : UA 182.03 million

IsDB : UA 84.91 million

EU : UA 16.71 million

Government of Cameroon: UA 16.14 million Government of Chad : UA 0.00 million

Application of funds: UA 333.29 million

Component A : UA 257.74 million

Component B : UA 44.57 million

Contingencies : UA 30.98 million

ix

10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

Contract award (ToR, consultation,

contract signature)

PROJECT IMPLEMENTATION SCHEDULE

ACTIVITIES2 017 2 018 2 019 2 020 2 021 2 022

Approval/Effectiveness

Project approval

Signature of financing agreements (grant

and loans)

Effectiveness of financing agreements

Fulfilment of disbursement conditions

Training of SNE and SONATREL staff

Consulting engineer

HV lines and substations - Cameroon

HV lines and substations - Chad

Rural electrification

Miscellaneous goods

Project Implementation

Implementation of the RAP

(Resettlement/Expropriation)Rural electrification supplementary

studiesConstruction of HV lines and substations -

CameroonConstruction of HV lines and substations -

ChadRural electrification

Completion Report

Borrowers' Report

ADB/ADF/TAF Report

Women's and Youth Socio-economic

Empowerment Programme

Project Supervision

Supervision missions

Project Audit

Recruitment of the auditor

Services of the auditor

1

REPORT AND RECOMMENDATION OF MANAGEMENT TO THE BOARDS OF

DIRECTORS CONCERNING THE FINANCING OF THE CAMEROON-CHAD

POWER INTERCONNECTION PROJECT (PIRECT)

Management hereby submits the following report and recommendation concerning proposals to

grant (i) a EURO 217.91 million ADB loan and a UA 6 million ADF loan to the Republic of

Cameroon; and (ii) award a UA 27.5 million TSF grant to the Republic of Chad, to finance the

Cameroon-Chad Power Interconnection Project (PIRECT).

1. STRATEGIC THRUST AND RATIONALE

1.1. Project Linkages with Country Strategy and Objectives

1.1.1. The project is in line with energy sector policy and national programme orientations

of Cameroon and Chad, set forth in the letters of sector policies and development strategies of

the electricity sub-sector which place emphasis on the development and strengthening of

energy infrastructure in view of its contribution to improving access to basic social services,

reducing poverty, and promoting economic growth and regional integration.

1.1.2. In Chad, the project is in keeping with the National Development Plan (PND 2017-

2021) and is consistent with the priorities defined in the Country Strategy Paper (CSP 2015-

2020) through Pillar 1: “Develop Infrastructure for Strong and More Diversified Economic

Growth.”

1.1.3. In Cameroon, the project is consistent with the orientations of the CSP 2015-2020

through Pillar 1: “Strengthen Infrastructure for Inclusive and Sustainable Growth” and with

the priorities of the Growth and Employment Strategy Paper (GESP 2010-2020).

1.1.4. The project design is in line with the Bank’s Central Africa Regional Integration

Strategy Paper (RISP 2011-2017) through Pillar 1 on “Infrastructure Development”. The

project is also consistent with the overall framework of the Priority Integration Projects (PIPs)

envisaged by the Central Africa Power Pool (CAPP), which seek to interconnect the power

grids of ECCAS member countries. It will enable the countries of the sub-region to optimize

the use of their energy resources by integrating power infrastructure.

1.2. Rationale for Bank’s Involvement

1.2.1. The Bank’s involvement in this strategic project that has a regional structuring

character is justified by the fact that its implementation will contribute to achieving the

objectives of its Ten-Year Strategy (2013-2022) which aims, among other things, to strengthen

infrastructure financing in its regional member countries (RMCs) and to promote regional

integration. The project is a continuation of actions by the Bank, which approved a UA 2.5

million ADF grant in October 2013 to finance comprehensive studies on this project. The

Bank’s involvement in the investment project ensuing from the studies gives it value added.

1.2.2. The project is in line with four of the Bank’s High 5s, namely “Light up and Power

Africa”, “Industrialize Africa”, “Integrate Africa”, and “Improve the quality of life for the

people of Africa”. It is also in harmony with the Bank’s 2014-2019 Strategy, which aims to

address fragility and build resilience in Africa. The Bank considers that improving equitable

access to basic infrastructure services such as electricity helps to enhance the capacity of States

to provide basic services to the population, thus boosting confidence and social cohesion.

Cameroon and Chad are experiencing fragile situations due to their weak capacity to provide

basic services.

2

1.2.3. The project is in keeping with the priorities of the CSPs of both countries, Cameroon’s

Growth and Employment Strategy Paper (GESP) 2010-2020 and Chad’s National

Development Plan (PND) 2017-2021, whose main pillars are infrastructure development and

strengthening. The Bank also took part in the Donors Round Table on Chad held in Paris last

September, which mobilized pledges of substantial financing from major TFPs, including the

Bank, for the implementation of the PND. In addition, the Bank is considered in the sub-region

as a strategic partner in the energy sector, thanks to previous and current operations in the

sector. Besides supporting the implementation of energy projects at the national level, the Bank

plays a key role in financing multinational projects in Central Africa. For example, during the

Central Africa Energy Sector Donors Round Table (held on 17 June 2016 in Brussels), the

Bank was selected as the leader of the technical and financial partners (TFPs) of the Central

Africa Energy Sector. This project will help to sustainably strengthen the achievements of

previous projects.

1.3 Aid Coordination

1.3.1 In Cameroon, the Ministry of Economy, Planning and Regional Development

(MINEPAT) is in charge of aid coordination and cooperation with donors at the national level.

Its Directorate of Regional Integration (DIR) is the Bank’s focal point for aid coordination. The

technical and financial partners have set up the Multi-Partner Committee (MPC) for GESP

Monitoring, which is a platform for dialogue and discussions on all key development issues in

Cameroon. Technical and thematic sub-committees for the alignment and harmonization

agenda have been set up to support this entity. The Energy Sector Sub-committee is steered by

the World Bank, with AfDB support.

1.3.2 In Chad, the Ministry of Economy and Development Planning (MEPD) is charged

with coordinating donor interventions, in concert with the Technical and Financial Partners

Committee (TFPC). This Committee comprises the Bank, the International Monetary Fund

(IMF, the current chair), the European Union (EU), the World Bank (WB), the Development

Bank of Central African States (BDEAC), the United Nations system organizations, the French

Development Agency (AFD), the Islamic Development Bank (IsDB), Chinese Cooperation,

Swiss Cooperation, and Arab Funds.

1.3.3 At the regional level, the Economic Community of Central African States (ECCAS)

and the Central Africa Energy Pool (CAPP) coordinate donor actions, the mobilization of

financing and the implementation of multinational projects in the energy sector. It is also

important to mention the Bank’s role as leader of the Technical and Financial Partners (TFPs)

of the Energy Sector in Central Africa.

1.3.4 During project identification, preparation and appraisal missions, the Bank team held

discussions with these key TFPs, notably the IsDB and the EU both of which will participate

in project financing. This coordination will be continued during project implementation: (i)

through the coordination of meetings of TFPs operating in the energy sector by the Cameroon

and Chad Country Offices; and (ii) during various project supervision missions.

3

2. PROJECT DESCRIPTION

2.1. Project Objectives and Components

The project objective is to improve the supply, reliability and accessibility of electricity in

Cameroon and Chad. Specifically, it seeks to: (i) enable cross-border trade in cheap and cleaner

electricity; (ii) promote electricity trade and regional integration; and (iii) contribute to Central

Africa’s socio-economic transformation. The table below presents the project components and

costs.

Table 2.1: Project Components and Estimated Cost

No. Component Name

Estimated Cost

(UA million) Component Description

A. Power Infrastructure 257.74

A.1 HV Lines and Substations 204.06 Construction of HV interconnection lines, including environmental and social costs (Cameroon: 785.9 kilometres and

Chad: 238.1 kilometres)

Construction and extension HV/MV substations (Cameroon: 4 substations and Chad: 3 substations)

A.2 Rural Electrification 53.68 Rural electrification (Cameroon: 409 localities; 1 610 kilometres of MV networks and 368 MV/LV substations and Chad: 69

localities; 470 kilometres of MV networks and 58 MV/LV substations)

B. Project Management 44.57 B. 1 Project technical and financial audit

B.2 Environmental and social audit

B. 3 Procedures manual B. 4 Procurement and installation of management software

(accounting and project management) and training

B. 5 Monitoring of project activities - Study monitoring and supervision, manufacturing and

construction of infrastructure (Consulting Engineer)

- Implementation of the ESMP (HV lines) - Implementation of the RAP (HV lines)

- Implementation of the ESMP (Rural Electrification)

- Logistic support to national institutions B. 7 Integration of young graduates

B. 8 Institutional support CHAD (particularly MPE and the SNE)

B. 9 Institutional support CAMEROON (particularly MINEE,

ARSEL, SONATREL and AER)

B. 10 Youth and Women’s Empowerment Programme B. 11 Support for the operation of PIUs

TOTAL BASE COST 302.31

Contingencies (10%) 30.98

TOTAL PROJECT COST 333.29

2.2. Technical Solutions Adopted and Alternatives Explored

2.2.1. The Cameroon-Chad Power Interconnection Project falls within the general

framework for interconnection of the power grids of ECCAS member countries. A 2010

Bank-funded study conducted by ECCAS identified the Cameroon-Chad power

interconnection (via a 225 kV high-voltage transmission line from Maroua to N’Djamena) as

one of the priority regional interconnection projects. However, to enhance project impacts,

additional studies, also still financed by the Bank, were carried out in 2016 to strengthen the

consistency of the Cameroon-Chad Power Interconnection Project by including a 225 kV

Maroua (Cameroon)-Bongor-Guelendeng-N’Djamena (Chad) link, as well as a rural

electrification component along transmission line corridors. The selection of the 225 kV line

option is justified by the need to transport power between Central African countries over long

distances.

4

2.2.2. In the short term, hydropower for the grid interconnection will be generated by the

new Bini à Warak hydropower plant (75 MW) under construction and the existing Lagdo

hydropower plant (72 MW) in Cameroon. In the medium term, the interconnection line will

have access to a greater hydropower capacity, in view of the envisaged link between the

Northern Interconnected Grid (RIS) and the Southern Unconnected Grid (RIN) in Cameroon

given that the southern part of Cameroon has a considerable hydropower potential. For its

part, the Chadian Government is pursuing the development of power generation through: (i)

the exploitation of oil resources, which will provide opportunities for the use of fuel oil (heavy

and light) for power generation in the medium term; and (ii) the development of renewable

energy such as the construction of the Djermaya solar power plant for which Bank financing

is solicited.

Table 2.2: Alternatives Explored and Reasons for their Rejection

Alternative Brief Description Reason for Rejection

Continue to develop national

power systems (with low voltages using thermal generation)

Each country will, using its own energy

generation facilities, continue to address the ever-growing national energy demand using

thermal generation sources (costly) particularly

in Chad and in the northern part of Cameroon.

Very high average per kWh cost

Inadequate security of energy supply

High pollution as power will be largely (for Chad) and partly (for Cameroon) generated from

petroleum products.

2.3. Project Type

This project is an investment operation in the form of loans and grants awarded to the two

countries concerned.

2.4. Project Cost and Financing Arrangements

2.4.1. The total project cost, net of taxes and customs duties, is UA 333.29 million, of which

UA 299.96 million in foreign exchange and UA 33.33 million in local currency. It comprises

a 5% provision for physical contingencies and a 5% provision for price escalation for costs in

foreign exchange and in local currency. The project cost by component and by currency type

is presented in Table 2.3 below.

Table 2.3: Estimated Project Cost by Component (UA million)

Components Foreign Exchange Local Currency Total % Foreign Exchange

1. Works 231.97 25.77 257.74 90%

2. Project Management 40.11 4.46 44.57 70%

Base Cost 272.08 30.23 302.31 90%

Provision for Physical Contingencies 13.60 1.51 15.12 90%

Provision for Price Escalation 14.28 1.59 15.87 90%

Total Project Cost 299.96 33.33 333.29 90%

2.4.2. The Bank Group’s overall contribution will be made through the “public” (ADB, ADF

and TSF) windows as follows: a UA 27.5 million TSF grant [UA 11 million (country

allocation) and UA 16.5 million (regional allocation)] to Chad, and a EUR 217.9 million ADB

loan (UA 182.03 million) and a UA 6 million ADF loan [UA 3 million (country allocation) and

UA 3 million (regional allocation)] to Cameroon. The Islamic Development Bank (IsDB) will

provide a total financing of USD 120 million (approximately UA 84.91 million) shared

equitably between Cameroon and Chad. For its part, the European Union (EU) will provide

EUR 20 million, or about UA 16.14 million to Chad. The project cost by source of financing

and by expenditure category is presented in Tables 2.4, 2.5.1 and 2.5.2 below. The detailed

component cost by source of financing and by procurement method is presented in Technical

Annexes B2 and B5.

5

Table 2.4: Sources of Financing (UA million)

Sources of Financing

CAMEROON CHAD CAMEROON + CHAD

F.E. L.C Total %

Total F.E. L.C Total

%

Total F.E. L.C Total

%

Total

ADB loan 161.36 20.67 182.03 74% 0 0% 161.36 20.67 182.03 55%

ADF Loan 4.60 1.41 6.00 2% 0 0% 4.60 1.41 6.00 2%

TSF Grant 0 0% 21.42

6.08 27.50 32% 21.42 6.08 27.50 8%

IsDB 38.21 4.25 42.46 17% 38.21

4.25 42.45 49% 76.42 8.49 84.91 25%

European Union 0 0% 15.04

1.67 16.71 19% 15.04 1.67 16.71 5%

Government of Cameroon1 11.30 4.84 16.14 7% 0% 11.30 4.84 16.14 5%

Government of Chad2 0 0% 0% 0.00 0.00 0.00 0%

TOTAL 215.47 31.16

246.63 100% 74.67 11.99 86.66 100% 290.14 43.16 333.29 100%

Table 2.5.1: Project Cost by Expenditure Category (UA million)

Expenditure Category F.E. L.C. Total % F.E.

Works 231.97 25.77 257.74 90%

Goods 1.33 0.57 1.90 70%

Services 11.83 5.07 16.90 70%

Sundry 18.04 7.73 25.77 70%

Total Base Cost 263.16 39.14 302.31 87%

Provision for Physical Contingencies 13.16 1.96 15.12 87%

Provision for Price Escalation 13.82 2.06 15.87 87%

Total Project Cost 290.14 43.16 333.29 87%

Table 2.5.2: Project Cost by Expenditure Category and by Source of Financing (UA million)

Expenditure

Category

AfDB ADF TSF IsDB EU Gvt. of

Cameroon Gvt. Chad Total

F.E. L.C Total F.E. L.C Total F.E. L.C Total F.E. L.C Total F.E. L.C Total F.E. L.C Total F.E. L.C Total

Works 138.53 15.39 153.92 1.62 0.18 1.80 8.87 0.99 9.85 69.32 7.70 77.02 13.64 1.52 15.16 0.00 0.00 0.00 0.00 0.00 0.00 257.74

Goods 0.00 0.00 0.00 0.53 0.23 0.76 0.79 0.34 1.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.90

Services 7.83 3.36 11.19 1.04 0.45 1.49 2.95 1.27 4.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.90

Sundry 0.00 0.00 0.00 0.98 0.42 1.40 6.81 2.92 9.73 0.00 0.00 0.00 0.00 0.00 0.00 10.25 4.39 14.64 0.00 0.00 0.00 25.77

Total Base Cost 146.36 18.75 165.11 4.17 1.27 5.45 19.43 5.51 24.94 69.32 7.70 77.02 13.64 1.52 15.16 10.25 4.39 14.64 0.00 0.00 0.00 302.30

Provision for

Physical

Contingencies

7.32 0.94 8.26 0.21 0.06 0.27 0.97 0.28 1.25 3.47 0.39 3.85 0.68 0.08 0.76 0.51 0.22 0.73 0.00 0.00 0.00 15.12

Provision for

Price Escalation 7.68 0.98 8.67 0.22 0.07 0.29 1.02 0.29 1.31 3.64 0.40 4.04 0.72 0.08 0.80 0.54 0.23 0.77 0.00 0.00 0.00 15.87

Total Project

Cost 161.36 20.67 182.03 4.60 1.41 6.00 21.42 6.08 27.50 76.42 8.49 84.91 15.04 1.67 16.71 11.30 4.84 16.14 0.00 0.00 0.00 333.29

Table 2.5.3: Project Cost by Component and by Source of Financing

PROJECT COMPONENT

TOTAL

COST

AfDB Group Financing IsDB EU CAM CHAD

AfDB/CAM ADF/CAM TSF/CHAD

(UAM) (EURM) (UAM) (UAM) (UAM) (UAM) (UAM) (UAM) (UAM)

A. POWER

INFRASTRUCTURE 257.74 184.25 153.92 1.80 9.85 77.02 15.16 - -

Construction of HV

Interconnection Lines 151.11 146.42 122.31 - - 28.80 - - -

Construction and Extension

of HV/MV Substations 52.95 37.83 31.60 - - 9.71 11.64 - -

Rural Electrification 53.68 0.00 - 1.80 9.85 38.51 3.52 - -

B. PROJECT

MANAGEMENT 44.57 13.394 11.19 3.65 15.09 - - 14.64 -

Project Technical and

Financial Audit 0.06 - - 0.03 0.03 - - - -

Environmental and Social

Audit 0.06 - - 0.03 0.03 - - - -

Procedures Manual 0.01 - - - 0.01 - - - -

1 The rationale for the level of counterpart contribution is given in Annex 1. 2 The constraints related to Chad’s budgetary situation owing to the exogenous shock caused by fluctuating oil prices and the heavy dependence of its

economy on this resource have led to the inability of this Category 1 fragile country to pay its counterpart contribution to the project implementation cost. The analysis of the mainstreaming of fragility aspects into the project is presented in the technical annexes (Annex B. 9).

6

Procurement and Installation

of Management Software

(accounting and project

management) and Training

0.05 - - 0.01 0.04 - - - -

Study Monitoring and

Supervision, Manufacturing and Construction of

Infrastructure (Consulting

Engineer)

16.21 13.39 11.19 1.25 3.77 - - - -

ESMP Implementation (HV

Network) 2.23 0.000 - - 0.96 - - 1.28 -

ESMP Implementation (Rural

Electrification) 1.64 0 - - 0.74 - - 0.90 -

RAP Implementation

(Resettlement/Expropriation) 17.98 - - 5.52 - - 12.46 -

Trainees (young graduates) 0.06 - - 0.03 0.03 - - - -

Institutional Support CHAD 0.40 0.000 - - 0.40 - - - -

Institutional Support CAMEROON

0.32 0.00 - 0.32 - - - - -

Support to PIUs: SNE (Chad)

and SONATREL (Cameroon) 3.36 0.00 - 1.11 2.25 - - - -

Support to CAPP 0.66 0.000 - 0.34 0.32 - - - -

Youth and Women’s Socio-

economic Empowerment

Programme

1.52 0.000 - 0.53 0.99 - - - -

BASE COST 302.31 197.65 165.11 5.45 24.94 77.02 15.16 14.64 -

Provision for Physical

Contingencies (5%) 15.12 9.88 8.26 0.27 1.25 3.85 0.76 0.73 -

Provision for Price Escalation

(5%) 15.87 10.38 8.67 0.29 1.31 4.04 0.80 0.77 -

TOTAL COST 333.29 217.91 182.03 6.00 27.50 84.91 16.71 16.14 -

Table 2.6: Expenditure Schedule by Component (UA million)

Components 2 018 2 019 2 020 2 021 2 022 Total

1. Works 56.83 85.25 85.25 28.42 28.42 284.16

2. Project Management 14.74 12.28 9.83 7.37 4.91 49.13

Total 71.57 97.53 95.07 35.79 33.33 333.29

2.5. Project Target Area and Beneficiaries

Project Impact Area

2.5.1. In Chad, the project impact area comprises 9 cantons in 4 divisions (“départements”)

and 3 regions, namely: (i) Mayo-Kebbi Est, which had a population of about 775 000 in 2009

(representing 7% of the total population of Chad), (ii) Chari-Baguirmi, which had about

580 000 inhabitants in 2009 (that is 5% of the country’s total population), and (iii) N’Djamena,

which had a population of close to 1 million in 2009 (or 9 % of Chad’s population), representing

a total population of 2 355 000. At the country level, the incidence of poverty is relatively low

in N’Djamena and Mayo-Kebbi East Regions, and moderate in the Chari-Baguirmi Region.

2.5.2. In Cameroon, the project impact area covers 30 counties (“communes”) in 8 divisions

(“départements”) and 3 regions, namely: (i) the Adamaoua Region, which had a population of

more than 1 million in 2010 (or 5% of the total population of Cameroon); (ii) the North Region,

which had more than 2 million people in 2010 (representing 11% of the country’s total

population); and (iii) the Far-North Region, which had close to 3.5 million inhabitants in 2010

(that is 18% of Cameroon’s population), bringing the total to 6.5 million. The project area is

characterized by extreme poverty, particularly in rural areas.

7

Project Beneficiaries

2.5.3. The power transmission and distribution infrastructure will directly benefit the SNE

in Chad, and SONATREL, AER and ENEO in Cameroon, which will operate it. In Chad, the

project will significantly contribute to improving the financial and economic viability of the

SNE. The replacement of thermal power with hydropower will lead to a substantial drop in

production cost, which currently stands at CFAF 240/kWh against an average tariff of CFAF

100/kWh. Therefore, the project could contribute to reducing State subsidies to the SNE and

cutting tariffs by about 10%. These benefits will be strengthened as the development plans of

the SNE, SONATREL, AER and ENEO are implemented, but also as the projects to reinforce

and extend the N’Djamena power network being prepared together with the French

Development Agency (AFD), Banque Sahelo-Saharienne pour l’Industrie et le Commerce

[Sahel-Saharan Bank for Industry and Commerce (BSIC)] and Chinese Cooperation are

implemented.

2.5.4. The project will allow for the electrification of 478 villages, 409 of them in Cameroon

and 69 in Chad, and will benefit 350 000 households that will have access to electricity and

thus improve their living conditions. The execution of works will create no fewer than 350

temporary jobs, at least 15% of them for women/girls and about 250 permanent direct and

indirect jobs, at least 15% of them for women/girls. Regarding socio-professional integration,

about 150 young graduates, at least 50% of them girls (50 in Chad and 100 in Cameroon) will

be able to undertake pre-employment internships to enhance their employability. Regionally,

in each country, the project will enable the industries of the respective regions to develop and

increase their production and commercial activities, in addition to improving their

competitiveness. It will also promote regional integration and the economic development of

Central Africa.

2.6 Participatory Approach

2.6.1. Consultations were conducted as part of project design and the preparation of ESIAs

and FRPs in Cameroon and in Chad, in compliance with domestic legislation and the

requirements of AfDB’s Operational Safeguards 1 and 2. Consultations were conducted

publicly (in the regions crossed by the project) and individually with PAPs. Overall, the

population expressed concern about the following main aspects: (i) the right-of-way of the new

line; (ii) the project implementation period; (iii) the identification of persons likely to be

affected and the time when compensation will be paid to them; (iv) the terms and conditions

for compensating for affected property (buildings, crops, land, etc.); (v) project benefits for

villages not electrified; and (vi) the specific needs of women. The main fears expressed by the

PAPs consulted individually concerned the terms and conditions for compensation and

resettlement. The expectations expressed during public consultations and by the PAPs

consulted individually are quite similar. All the people consulted expect positive impacts from

rural electrification.

2.6.2. In Chad and in Cameroon, this participatory approach will be maintained and

reinforced during the project implementation phase through a regional Stakeholder

Engagement Plan (SEP). This SEP will be implemented by the Project Implementation Unit

(PIU) in close collaboration with project-impacted communities, local authorities and

authorities of decentralized and external institutions. It will help to establish a social peace and

transparency drive and will consist in: (i) operationalizing the system for recording and

processing complaints and grievances as well as a mechanism for managing grievances by

providing all stakeholders or citizens with the possibility of making their comments, voicing

their concerns, acceding to information and, where necessary, lodging an appeal and seeking

8

redress under the redress mechanism. The Bank posted the summary of the ESIA and FRP on

its website on 11 August 2017.

2.7. Bank Group Experience and Lessons Reflected in Project Design

2.7.1. The recent review of the Bank’s portfolio performance in the two countries concerned

and the Bank’s portfolio in the Central African Region revealed the following main weaknesses

in project implementation: (a) poor quality at entry due to lack of technical studies and poor

cost estimates; (b) relatively long timeframes for effectiveness and fulfilment of conditions

precedent to first disbursement; (c) weak capacity of executing agencies; and (d) project start-

up delays.

2.7.2. The proposed project takes into account lessons drawn during the implementation of

national and multinational projects, particularly: (i) the coordination of regional operations

(with regard to the Study on the Cameroon-Chad Power Interconnection Project); (ii) quality

at entry (particularly in relation to the Lom Pangar Hydropower Project – PAHLP – in

Cameroon); and (iii) delays in the launching of works, the financing of compensation, the

mobilization of counterpart contributions, and procurement and financial management

provisions (in relation to the Lom Pangar Hydropower Project and the Project to Strengthen

and Extend Electricity Transmission and Distribution Networks – PRERETD – in Cameroon).

2.7.3. To overcome these weaknesses and reflect the lessons learned, this project will: (i)

establish a decentralized management entity to ensure better project ownership by beneficiaries

and stakeholders; (ii) build the capacity of PIUs; (iii) use advance contracting to reduce

procurement timeframes; and (iv) simplify conditions of compensation payment. Furthermore,

the project is underpinned by recent comprehensive studies (preliminary design study, ESIA,

RAP, ESMP and BDs).

2.8. Key Performance Indicators

Project performance will be measured using the performance indicators outlined in the results-

based logical framework. The key project performance indicators are: (i) the quantity of power

traded through the power interconnection; (ii) the electricity access rate in the rural areas

covered; (iii) the CO2 emissions avoided; and (iv) the number of direct and indirect jobs

created. The main project outputs in 2022 will be: (i) the construction of 1 024 kilometres of

225 kV power transmission lines; (ii) the construction of 7 HV/MV substations; and (iii) the

electrification of 478 localities along the power transmission lines. The project performance

indicators will be included in the periodic project progress reports to be prepared by PIUs. As

the project is implemented, these indicators will be analysed and compared with the project

target values, and regional and international standards.

3. PROJECT FEASIBILITY

3.1. Financial and Economic Performance

3.1.1. Key Financial and Economic Performance Indicators

Table 3.1: Key Project Financial and Economic Performance Indicators

Baseline scenario

FIRR: 23.6 % FNPV: CFAF 184 million

ERR: 43 % ENPV: CFAF 448 million

NB: The detailed assumptions and calculations are presented in Technical Annex B.6

9

3.1.2. Financial performance: the financial internal rate of return (FIRR) and the net

present value (NPV) were calculated based on the cost-benefit method for the construction and

operation of the power interconnection infrastructure. The financial benefits taken into account

are revenue from the transmission of power through the transmission line and the share of

earnings from the sale of power imported by Chad from Cameroon, thus replacing thermal

power with hydropower, attributable to the line. The project cost includes investments in

infrastructure and operation and maintenance costs estimated at 2% of the investment cost. The

analysis covers a 30-year period corresponding to a 4-year project implementation period and

a 26-year project infrastructure operation period.

3.1.3. Economic performance: the economic costs used to calculate the economic rate of

return (ERR) and the economic net present value (ENPV) are project investment costs net of

taxes and provision for price escalation, deflated by appropriate conversion factors for

equipment, works, services and labour. Maintenance and operating costs were also estimated

at 2% of the investment cost. Other economic benefits are presented in the technical annexes

(see B.6).

3.1.4. Sensitivity analysis: the analysis of results of sensitivity tests shows that the project

can resist: (i) a 10% increase in project costs; (ii) a 10% increase in operating costs; and (iii) a

10% drop in electricity rates. The FIRR are 22%, 24% and 19%, respectively. Therefore, the

project is more sensitive to a decrease in sales that could result from: (a) a drop in electricity

rates; or (b) a decline in household consumption. Regarding the latter assumption, it is

necessary to adopt a shrewd connection policy, particularly for the “rural electrification”

component.

3.2. Environmental and Social Impact

Environment

3.2.1. The project has been classified under Category 1 in accordance with the Bank’s

Environmental and Social Assessment Procedures (ESAP) for the following reasons: (i) its

scope (1 024 kilometres of 225 kV transmission lines); and (ii) the major impacts and risks it

will generate, particularly regarding sensitive ecosystems and a large number of project

affected persons (more than 200). Environmental and Social Impact Assessment (ESIA)

reports, including Environmental and Social Management Plans (ESMPs) and Full

Resettlement Plans (FRPs) were prepared in February 2017 in Chad and in May 2017 in

Cameroon, in accordance with national regulations and the requirements of the Bank’s

Integrated Safeguards System (ISS). These reports were validated at the national level and

compliance certificates issued for Chad on 30 August 2017. Issuance of the certificates for

Cameroon is ongoing. ESIA and FRP summaries were posted on the Bank’s website on 11

August 2017. Although the choice of the transmission line layout is ideal from the

environmental and social standpoints compared with the alternative analysed, the chosen layout

will generate the following major positive and negative impacts and risks during the

construction and operation phases:

- Negative impacts during the pre-construction, construction and operation phases will

include: (i) the felling of trees along the transmission line right-of-way covering a total 4 733

hectares in Cameroon and 1 455 hectares in Chad; (ii) the loss, modification and fragmentation

of wildlife habitats and the degradation of ecosystem services, particularly around the Benue

National Park in Cameroon and the Mandélia National Park and Toupouri lowlands (RAMSAR

site) in Chad; (iii) health and safety risks for workers and neighbouring populations; (iv) loss

10

of assets and income by project affected persons (see section on resettlement for details); and

(v) various forms of water and soil pollution. The main cumulative negative impacts will be

the reduction of natural habitats and the disruption of ecosystem-based services.

- Positive impacts: the main positive project impacts on the environment will be: (i)

contribution to the reduction of greenhouse gas (GHG) emissions by the Chadian network,

which mainly depends on thermal sources; and (ii) benefits associated with increased access to

“cleaner” energy in contrast to fuel wood used by the households in the project area. Measures

will be implemented to mitigate all the negative impacts and risks identified. The mitigation of

the negative impacts identified during the implementation phase will mainly concern the

organization of work, as recommended in specifications for contractors. Such organization

will be based on binding clauses for contractors and the consulting engineer, the obligation to

implement a Health, Safety and Environmental Plan including emergency provisions, as well

as an environmental protection plan for sensitive environments. The total cost of the ESMP

(excluding the FRP) is estimated at EUR 4.8 million, of which: (a) EUR 2.7 million for

Cameroon; and (b) EUR 2.135 million for Chad.

3.2.2 ESMP implementation monitoring and supervision: the Project Implementation

Unit (SNE in Chad and SONATREL in Cameroon) will include an environmentalist

responsible for monitoring the implementation of the ESMP. He/she will be assisted by a young

environmentalist on internship during project implementation phase. The SNE and

SONATREL will benefit from the technical assistance provided by the consulting engineer on

environmental and social safeguards and the monitoring of ESMP implementation. The

ministries in charge of the environment of both countries will monitor and control compliance

with environmental and social standards during ESMP implementation. This will be the subject

of a protocol agreement concluded between each PIU and the ministry. The protocol agreement

will define actions to be undertaken and the logistical and financial arrangements.

Climate Change

3.2.3 As regards the climate, the project has been classified under Category 2 (average risk)

in accordance with the Bank’s Climate Safeguards System. The crossing of erodible zones and

rugged terrain, as well as the erosion of the banks of rivers crossed were considered under

layout alternatives. The design and determination of the layout retained took into account

erosion and flood risk prevention and adjustment measures. Hence, less than 30% of the layout

is situated in erodible terrain and a few flood-prone zones. The working designs will fine-tune

the construction details and secure the final routes.

3.2.4 The project technical design takes into account: (i) the installation and erection of

pylon supports outside flood-prone zones; (ii) the installation of substations outside flood-

prone/erodible areas and backfills; and (iii) the sizing of pylon foundations taking into account

the appropriate prevailing wind speeds. Concerning mitigation, a compensatory reforestation

plan will be implemented to mitigate deforestation and ensure a positive net gain in relation to

what will be destroyed. This surplus will contribute to carbon sequestration. In addition, the

energy to be generated in the short and medium term will be exclusively of water origin, thus

contributing to reducing the carbon footprint of the power grid, particularly in Chad.

11

Gender Issues

3.2.5 Although women represent about 52% of the total population in Chad, their education

level, which is often lower than that of men, their day-to-day household chores (which are time

consuming) and their low mobility constitute obstacles or impediments to their participation in

consultations and dealing with the changes that may be induced by the project. Women and

youths experience a very fragile socio-economic existence or none at all.

3.2.6 In Cameroon, women represent 51% of the total population in the project area.

Although they constitute an undeniable development force, about 75% of women are still far

from having access to the same rights, the same economic benefits and the same resources as

men3.

3.2.7 In view of the socio-economic realities of the PIA in Chad and Cameroon, the project

will support the socio-economic empowerment of women and youths (girls and boys). Thus,

in each of the two countries, the main aim will be to support: (i) at least 50 women economic

interest groups/associations comprising about 1 500 women in the development of income-

generating activities; and (ii) 50 youth groups/associations comprising about 1 500 youths aged

between 15 and 35 years in the development of productive entrepreneurial projects.

Specifically, the project will help these groups to better organize themselves (technical training,

association management, financial management, and support), to equip themselves with

production materials and to generate income, thus enabling members to improve their living

conditions by satisfying their family needs. The project will procure production equipment and

materials based on the list of requirements of associations and deliver them once the operational

capacity of the groups/associations would have been built.

3.2.8 In addition, the project will seek to contribute to efforts to improve access to basic

social services in Chad and Cameroon by: (i) supporting the decentralized services of the

ministries in charge of youth affairs and women’s empowerment (women’s empowerment

centres and multipurpose youth empowerment centres) in the project area; (ii) building the

civic and moral capacity of youths and women; (iii) providing literacy education for women

and youths with no schooling; and (iv) organizing awareness-raising and mobilization

campaigns on the rational use of energy, the fight against electrical accidents, gender-based

violence (VBG), HIV and AIDS and rational access to basic social services.

3.2.9 The Ministry of Youth Affairs and Civic Education (Directorate of Youth Socio-

economic Empowerment) and the Ministry of Women’s Empowerment and Family

(Directorate of Women’s Socio-economic Empowerment) will be involved in implementing

the project in Cameroon. In Chad, the Ministry of Youth Affairs, Sports and Leisure

(Directorate of Youth Affairs) and the Ministry of Women’s Affairs, Protection of Early

Childhood and National Solidarity (Directorate of Women’s Socio-economic Empowerment

and Directorate of Social Action) will be involved. In each country, a protocol agreement will

be concluded between these ministries and the respective PIUs.

Employment

3.2.10 During the high-voltage transmission line, substation and rural electrification

infrastructure construction phase, no fewer than 350 temporary direct jobs will be created, at

least 15% of them for women/girls, and 250 permanent direct and indirect jobs, at least 40 of

them for women/girls. It will be necessary to identify and mobilize skilled and unskilled local

workforce to fill these job vacancies within the prescribed timelines. The National Employment

3 BUCREP, National Population Status Report, 2014 Edition.

12

Promotion Authority (ONAPE) in Chad and the Ministry of Youth Affairs and Civic Education

(MINJEC) in Cameroon will provide assistance to the respective PIUs in recruiting and

supporting this local workforce. A protocol agreement for assistance will be concluded between

these bodies and the PIUs.

3.2.11 To foster the employability of young graduates hunting for jobs, the project will recruit

50 young graduates for internship, at least 50% of them girls, in Chad and 100 young graduates

for internship, at least 50% of them girls, in Cameroon. The recruitment will be done in two

streams of 25 trainees for a six-month period renewable once in Chad, and three streams of

trainees in Cameroon for a six-month period renewable once. These pre-employment trainees

will serve as expert assistants in the Project Management Unit, the Consulting Engineering

Firm, the electricity companies of both countries, and the enterprise recruited. The National

Employment Promotion Authority (ONAPE) in Chad and the Ministry of Youth Affairs and

Civic Education (MINJE) and the Ministry of Employment and Vocational Training

(MINEFOP) in Cameroon will support the PIUs under an assistance agreement.

Involuntary Resettlement

3.2.12 The project will affect 990 persons in Chad and 1 311 in Cameroon. The affected

property will be mainly buildings, dwellings, trees, community property (wells and boreholes)

and graves. Each country prepared and submitted a full resettlement plan (FRP) to the Bank.

The summary of the full resettlement plans was posted on the AfDB website on 11 August

2017.

3.2.13 In Chad, the Resettlement Plan valued at EUR 6 604 995 (CFAF 4 345 391 731) will

be financed by the Bank, considering the country’s economic and financial situation. In

Cameroon, the Resettlement Plan worth EUR 14 914 961 (CFAF 9 812 474 100) will be

financed by the Government of Cameroon.

4. PROJECT IMPLEMENTATION

4.1. Implementation Arrangements

Institutional Arrangements

4.1.1 Both countries will be responsible for project implementation on their territory

through their respective national entities, notably SONATREL for Cameroon and SNE for

Chad. The project will finance the support needed by the national entities to enable them to

effectively play their respective roles.

4.1.2 The National Electricity Corporation (SNE) will be Chad’s Project Executing Agency.

The SNE’s duties include the management of the rural electrification sub-sector. It will set up

a Project Implementation Unit (PIU) under the direct responsibility of the Director General,

which will coordinate all project activities. The PIU will be headed by a Coordinator who will

be a Power Engineer with a rich experience in project management. The composition of the

Unit is provided in Annex B.3. Considering the inadequate number of skilled SNE staff, the

PIU will be strengthened by experts who will be recruited through an open call for candidature.

The PIU will be assisted by the other SNE directorates in handling legal, technical, economic

and financial issues as well as those relating to communication and public relations. Special

emphasis will be laid on the capacity building of the SNE whose staff will work in collaboration

with experts for the transfer of skills through apprenticeship. The Government will provide

functional premises for the PIU and supply water and electricity.

13

4.1.3 The National Electricity Transmission Corporation (Société Nationale de Transport

de l’Electricité, SONATREL) will be the Project Executing Agency for Cameroon’s

component. It will set up a Project Implementation Unit (PIU) within the Corporation. A

distribution expert from the Rural Electrification Agency (AER) will join the PIU team to

monitor rural electrification activities. He/she will be AER’s project implementation focal

point. The composition of the Unit is provided in Annex B.3. The AER expert, as well as the

rest of the PIU’s senior officers will come from SONATREL, which already has highly

qualified staff from ENEO. Their CVs will be approved beforehand by the Bank. The PIU will

be assisted by the other SONATREL directorates in handling legal, technical, economic and

financial issues as well as those relating to communication and public relations. The AER focal

point will be assisted in the implementation of the project’s rural electrification component by

one (1) engineer and two (2) topographers and graphic designers who will also be designated

from among AER staff after approval of their CVs by the Bank. The focal point will be

supported by the other AER directorates from time to time. The Government, through

SONATREL, will provide functional premises for the PIU. The project will provide

SONATREL and AER with logistic support for efficient project implementation.

4.1.4 Proper project coordination at the multinational level will be ensured by the Inter-

State Steering Committee for the Cameroon-Chad Power Interconnection Project and the

Project for the Electrification of Border Towns and Localities in both Countries established on

10 February 2009. The Committee is a forum for consultation on operations in charge of

organizing necessary consultations between project stakeholders. It will be responsible for

taking strategic decisions at the supranational level. The Central Africa Power Pool (CAPP)

will provide secretarial services for the Committee and facilitate strategic discussions requiring

arbitration by the two countries. It will also recruit and monitor the Consulting Engineer and

the project accounts Auditor, both of whom will work exclusively for the project.

4.1.5 A National Steering Committee will be established in each country. The National

Steering Committees will be responsible for taking strategic decisions at the national level,

monitoring effective project implementation and ensuring the achievement of set objectives.

They will ensure: (i) the review and approval of the annual budgets of PIUs; (ii) synergy

between project actions and the other national sector policies; (iii) the reinforcement of the

participatory approach; and (iv) coordination between all national stakeholders for effective

project implementation, especially with regard to cross-cutting issues.

4.1.6 Chad’s National Steering Committee will comprise the representatives of the

ministries in charge of energy, planning, finance, regional development, public security,

women’s empowerment and social affairs, youth affairs, education, health, environment and

public service, as well as the SNE that will provide secretarial services for the Committee.

Cameroon’s National Steering Committee will comprise the representatives of the ministries

in charge of energy, planning, finance, regional development, public security, women’s

empowerment, social affairs, youth affairs, education, health, environment and public service,

the Electricity Regulatory Agency, ENEO, AER and SONATREL, which will provide

secretarial services for the Committee.

Procurement Arrangements

4.1.7 Applicable procurement policy and framework: the procurement of goods, works

and consultancy services financed by the Bank under the project will be in accordance with the

“Methodology for Implementation of the Procurement Policy of the African Development

Bank” approved in October 2015, and the provisions set forth in the Financing Agreement.

Pursuant to this policy and after reviewing the available assessments of the procurement

systems in the countries and the sector, all procurements under the project will be in accordance

with the Bank’s procurement methods and procedures (BPMPs), using appropriate Bank

standard bidding documents (SBDs).

14

4.1.8 Organization of procurements: project procurements will be carried out by three

different entities, depending on the type of procurement. Procurements in Cameroon will be

carried out by SONATREL’s Project Implementation Unit. Procurements in Chad will be the

responsibility of SNE’s PIU. Procurements common to the two countries (mostly the selection

of consulting firms) will be the responsibility of CAPP. A procurement specialist will be

recruited for the SONATREL and SNE PIUs, and will provide support to CAPP as appropriate.

4.1.9 Procurement capacity and risk assessment (PCRA): to take project specificities into

account, the Bank assessed the country, sector and project risks as well as the capacity of

SONATREL (Cameroon), SNE (Chad) and CAPP. The outcomes of these assessments showed

a substantial risk level for procurement4 and were used to guide the choice of a procurement

system (Borrower, Bank or Third Party) for specific activities, and to determine the appropriate

mitigation measures proposed in the PERCA Action Plan shown in Paragraph B.5.9 of Annex

B5. The resources required to implement these measures will be derived from the Bank grant

and loan.

Financial Management, Disbursements and External Audit

4.1.10 Fiduciary risk assessment and proposed mitigation measures: through its executing

agency, each country will be responsible for establishing a satisfactory budget, financial and

accounting management system and preparing financial reports. However, the external audit

of PIRECT will be the responsibility of the Central Africa Power Pool (CAPP). At the end of

the assessment mission, the PIRECT implementation fiduciary risk was deemed substantial,

given the inexperience of SNE (Chad) and SONATREL (Cameroon) in implementing Bank

Group operations and little knowledge of the management procedures of development

institutions. The technical capacity of SNE’s fiduciary team was assessed and deemed low

owing to the lack of appropriate management tools that meet the Bank’s requirements.

SONATREL, which was established in October 2015, is still having its management manuals

validated and the level of implementation of activities transferred to it is very low. CAPP’s

performance in the recruitment of auditors and submission of audit reports within the

prescribed timeframes is quite poor. The major risks identified, as well as the mitigation

measures, are summarized in the fiduciary risk assessment table in Annex B.4 (Technical

Annexes).

4.1.11 Disbursement arrangements: the disbursement of Bank Group (ADB/ADF/TSF)

resources under this project will be in accordance with the provisions of the disbursement

manual in force at the Bank. The disbursement methods proposed for the project are: (a) the

special account method for operating expenditure, management of partnership agreements and

capacity building activities; (b) the direct payment method for services, works and goods

contracts; and (c) the reimbursement method in case of pre-financing with counterpart

contributions of expenditure to be borne by the Bank Group (such pre-financing shall be

authorized beforehand by the Bank). Cameroon’s counterpart contributions will be disbursed

annually in a single tranche. In Cameroon, the “Caisse Autonome d’Amortissement (CAA)”

will be responsible for opening special accounts. It will open the following local currency

(XAF) special accounts in the name of PIRECT in a commercial bank acceptable to the Bank:

(i) a special account to receive ADF resources; and (ii) a special account to receive the

counterpart contributions of the Government of Cameroon for project activities. In Chad, the

special account will be opened by the PIU/SNE and its operation will require double signature

jointly with the Ministry of Economy and Development Planning (MEPD).

4.1.12 External audit: pursuant to Bank rules, project accounts will be audited annually by an

external audit firm recruited on a competitive basis and in accordance with Bank standard terms

of reference (ToR). The external audit will be adapted to the specific project risks and the audit

4 For further details, consult the Technical Annexes.

15

terms of reference agreed with the Bank. The audit reports of each financial year will be

submitted to the Bank latest six months following the closure of the financial year to which

they relate. CAPP will be responsible for recruiting and supervising the external auditor.

4.2. Project Monitoring and Evaluation

The main project phases are presented in Table 4.2 below. Project activities will be carried out

based on the project implementation schedule. Each of the two PIUs has a

monitoring/evaluation expert whose main duty will be to define measurable outcomes

(including those contained in the results-based logical framework) as well as the methodologies

and resources to be used to achieve such outcomes. He/she will have a monitoring and

evaluation module incorporated into the project management software. The

monitoring/evaluation expert will contribute to improving performance and accountability

based on clearly defined principles.

Table 4.2: Main Project Implementation Phases

Period Phases Monitoring Activities/Feedback Loop

December 2017 –

May 2018 Approval and effectiveness

Grant and loan approval

General Briefing Note

Signature of financing agreements and effectiveness

AfDB launching mission

December 2017 –

November 2018 Contract award

Preparation of bidding documents

Bidding and contract award

Signature of consulting firm contracts

Signature of works contracts

May 2019 – May

2021

Physical project

implementation

Execution of contracts

Preparation of periodic project progress reports

Bank supervision missions

Project environmental and social monitoring

Bank mid-term review

150 days spread over

5 financial year

closures

Audit of project accounts

Recruitment of the auditor to conduct annual audits

Conduct of annual audits

January 2022 – May

2022 Project completion

Borrower’s project completion report

Preparation of the Bank’s project completion report

4.3. Governance

The governance risk under this project is moderate and could arise during the establishment of

implementation units, particularly the selection of staff and their position within the

institutional mechanism of the entities hosting them. However, it will be mitigated by the fact

that the Bank will be involved in the competitive recruitment of the SNE/SONATREL PIUs

staff. In addition, under its new procurement policy, the Bank still has the means to ensure pre-

contract signature control.

4.4. Sustainability

4.4.1 The project is technically, economically and financially sustainable. Its technical

sustainability is guaranteed by the use of a simple technology that has been extensively tested

in the two countries. Chad runs a 90 kV transmission network around N’Djamena, maintained

by the SNE. Project implementation will build SNE’s capacity to maintain power transmission

infrastructure. The new facilities will be given special attention, considering the important role

that they will play in power supply in Chad. In Cameroon, project facilities will contribute to

consolidating the national power transmission network. This major infrastructure will be

maintained by SONATREL, which is responsible for the development, management and

maintenance of power transmission networks. Rural electrification is managed in both

16

countries by dedicated entities. Thus, the development of facilities will comply with relevant

national policies.

4.4.2 Project economic and financial sustainability will be based on increasing demand for

electricity in the two countries and the region. Interconnection provides an opportunity,

especially for Chad, to import hydropower from Cameroon at a more competitive price

compared to thermal generation, which is currently the main source of power. The project’s

impact on SNE’s service delivery and financial sustainability is indisputable (see technical

annexes).

4.4.3 Project sustainability will also be impacted by the quality of the agreements that will

be signed for the operationalization of facilities set up under the project. A purchase contract

will be signed between the Supplier and the customer for the sale of power by the Supplier and

purchase of same by the customer that is the supply of power by one party to the other party.

The contract will also cover, as appropriate, the delivery of the following associated services:

power storage, mutual assistance, sharing of opportunities and power transfer.

4.4.4 Lastly, an interconnection operators’ agreement shall be signed between the SNE,

SONATREL and ENEO aimed at ensuring the reliability and operability of interconnection

facilities through their coordinated programming. This agreement shall also cover pricing,

accounting management and procedures for emergency services and unintended exchanges

between interconnection networks. The signing of these two agreements, to the satisfaction of

the Bank and the Fund latest 31 December 2020, will be another loan/grant condition.

4.5. Risk Management

4.5.1 The major risk faced by the project is the security situation in Cameroon’s Far North

due to terrorist incursions and threats, as well as the ensuing influx of refugees. Chad is also

facing terrorist incursions and attacks in the same area. This situation may stretch project

implementation capacity to the limit. Moreover, the influx of refugees poses the risk of

increased social conflicts resulting from the low capacity to deliver social services. Concerted

and coordinated actions against terrorists in the region will help to mitigate the security risk.

Furthermore, investments under the project should largely contribute to enhancing the delivery

of social services through greater access to power, which could contribute to mitigating social

conflicts.

4.5.2 Another risk facing the project is the current weak capacity of the two national entities

that will be responsible, each in its own sphere, for various aspects of implementation. The

planned mitigation measures are: (i) the institutional support that the project will provide to the

executing agencies of the two countries; and (ii) the monitoring of the process of recruiting

experts for both entities to ensure optimal performance by the experts.

4.6. Knowledge Building

4.6.1 The project is an opportunity to disseminate new knowledge for the Bank and the

Governments of Cameroon and Chad. For the Bank, it is an example of support to a State in

transition, namely Chad, in implementing an anchor project in a complex sector. This project

will help to start the establishment of a power transmission network in Chad by providing

experience in the operation of this type of infrastructure. For Cameroon, which is already

involved in many interconnection projects under review, this project will be the first experiment

in the management of energy trade with a neighbouring country. It will also contribute to

operationalizing SONATREL through the management of a major project. Furthermore, it is

an experiment in collaboration between technical and financial partners. Lastly, the contracts

17

for construction works and consultancy services will include specific provisions to ensure the

training of SNE, SONATREL, ENEO and AER staff.

4.6.2 The Bank will play a key role in implementing the project and, through regular

consultation with other partners and beneficiaries, learn lessons from this experience for similar

future projects. The documentation from these meetings and supervision missions, periodic

progress reports and reports from various controls will constitute a basis for knowledge

building.

5. LEGAL FRAMEWORK

5.1. Legal Instrument

To finance this project, the Bank will: (i) grant a UA 182.03 million ADB loan and a UA 6

million ADF loan to the Republic of Cameroon; and (ii) award a UA 27.5 million TSF grant to

the Republic of Chad.

5.2. Conditions for Bank Intervention

5.2.1. Conditions precedent to effectiveness of the ADB and ADF Loan Agreements

Effectiveness of ADB and ADF Loan Agreements shall be subject to their signature by the

Bank and the Borrower, and fulfilment by the Borrower of the conditions set forth in Section

12.01 of the General Conditions Applicable to Loan Agreements and Guarantee Agreements

of the African Development Fund.

5.2.2. Conditions precedent to effectiveness of the TSF Grant Protocol Agreement

Effectiveness of the TSF Grant Protocol Agreement shall be subject to its signature by the

Donee and the Bank.

5.2.3. Conditions precedent to first disbursement of loan and grant resources

In addition to entry into force of the Loan/Grant Agreements, the first disbursement of each

loan/grant shall be subject to fulfilment by the Borrower/Donee of the following conditions to

the full satisfaction of the Bank:

(i) Provide evidence of establishing the National Steering Committee and

designating its members.

5.2.4. Other conditions:

In addition, the Borrower/Donee shall:

(i) Provide to the Bank, latest six (6) months before works start-up, evidence of

project financing closure, by presenting proof of approval of financing by other

donors, notably the Islamic Development Bank (IsDB) and the European Union

(EU);

(i) Provide to the Bank before or with the first request for disbursement from the

special account, evidence of opening a special account in a bank deemed

acceptable to AfDB, into which the loan/grant resources allocated for to the

operation of the project management units will be lodged;

(ii) Provide, as the works progress and, at any event, prior to any commencement

of works in a given area, evidence of compensating project-affected persons in

the area, in accordance with the Resettlement Action Plan (RAP) and the Bank’s

relevant rules and procedures, especially its Involuntary Resettlement Policy

18

and Integrated Safeguards System; or evidence of replenishing an escrow

account for compensation of PAPs;

(iii) Provide, latest six months following first disbursement, evidence of establishing

a satisfactory accounting and financial management mechanism within the PIU,

especially with: (a) the recruitment of its accounting and financial staff; (b) the

establishment of its computerized financial management and financial

information production system; and (c) the preparation of draft project progress

reports and quarterly financial reports acceptable to the Bank; and

(iv) Provide evidence of signing: (a) a power purchase and exchange contract; and

(b) an interconnection operators agreement, to the satisfaction of the Bank and

the Fund, latest 31 December 2020.

5.2.5. Commitments

The Borrower/Donee undertakes, to the satisfaction of the Bank, to:

(i) Provide the Bank with any document reasonably required to monitor project

implementation;

(ii) Have the PIU prepare project implementation and administrative and financial

management procedures manuals;

(iii) Have the PIU and its contractors implement the project, the RAP and the ESMP,

in accordance with national laws, environmental and social safeguard

recommendations, requirements and procedures, as well as relevant Bank rules

and procedures; and

(iv) Provide the Bank with quarterly ESMP implementation reports, including, as

appropriate, the weaknesses noted and corrective actions taken or to be taken.

5.3. Compliance with Bank Policies

The Chad-Cameroon Power Interconnection Project is consistent with all Bank policies in

force.

6. RECOMMENDATION

Management recommends that the Boards of Directors approve (i) an ADB loan of EUR 217.91

million and an ADF loan of UA 6 million to the Republic of Cameroon; (ii) a TSF grant of UA

27.5 million to the Republic of Chad.

I

ANNEXES

AnnexI: CAMEROON/Rationale for the Level of Government’s Counterpart

Contribution to AfDB Financing

1. The project will be financed by the Bank Group through a EUR 217.9 million ADB

loan and a UA 6 million ADF loan to Cameroon. The counterpart contribution is

estimated at UA 16.14 million, representing 6.54% of the total project cost

(Cameroon’s share, that is UA 246.63 million). This amount of counterpart financing

represents the current level of contribution affordable by the country.

2. The level of counterpart contribution to AfDB financing is below the minimum rate

of 50% of total project cost, as stipulated by Section 4.2.2 of the Policy on Expenditure

Eligible for Bank Group Financing. Thus, in accordance with the provisions of Section

4.2.2 of the above Policy (revised version of 19 March 2008), the level of counterpart

financing for AfDB Window was determined based on the following four criteria: (i)

the country’s commitment to implement its overall development programme;(ii) the

financing allocated by the country to the sector targeted by Bank assistance;(iii) the

country’s fiscal situation and debt level; and (iv) the upper cost-sharing limit and

guidelines laid down in the country financing parameters.

The country’s commitment to implement its overall development programme

3. Drawing lessons from implementation of its Poverty Reduction Strategy following the

achievement of the HIPCI completion point in 2006, the Government, in 2010,

formulated a vision for its development by 2035. This long-term vision seeks to

transform Cameroon into an emerging and democratic country united in its diversity.

Specifically, Vision 2035 is a benchmark for: (i) substantially reducing the poverty

level; (ii) achieving middle-income country status; (iii) becoming a newly

industrialized country; and (iv) consolidating the democratic process and national

unity.

4. These objectives have guided the orientations of the Growth and Employment

Strategy Paper (GESP) for the period 2010-2020, covering the first ten years of Vision

2035. The main issue concerning the implementation of GESP will be to focus on

growth acceleration, formal job creation and poverty reduction. Therefore, there are

plans to: (i) increase growth to an annual average of 5.5% over the period 2010-2020;

(ii) reduce under-employment from 75.8% to below 50% in 2020; and (iii) reduce the

poverty rate from 39.9% in 2007 to 28.7% in 2020.

5. To achieve these objectives, the Government has opted to implement a three-pronged

strategy in a coherent and integrated manner, with the support of Technical and

Financial Partners (TFPs), including the Bank. The strategy comprises: (a) a growth

strategy; (b) a governance and strategic State management strategy; and (c) an

employment strategy.

6. The presentation of this operation to the Board is taking place in a special context

marked by Cameroon’s graduation to ADB-window Blend Country status. Based on

its recent macro-economic performance, Cameroon graduated in 2014 to the non-

concessional windows of the World Bank and the AfDB Group. This dual graduation

reflects the confidence of multilateral institutions and enables the country to benefit

from the resources of both the concessional and non-concessional windows of the

II

AfDB Group. It should allow the country to finance its development, especially its

ambitious infrastructure programme, in a more cost-effective manner. The country’s

new ambition is to graduate from a "Blend Country" to “ADB Country” status.

Financing allocated by the country to the sector targeted by Bank assistance

7. The current public portfolio in Cameroon comprises two investment projects and one

energy sector project study for a total UA 77.820 million, representing 8.5% of the

portfolio. The operations are: (i) the Project for the Rehabilitation and Extension of

Power Transmission and Distribution Networks (PRERETD) approved in September

2010; (ii) the Lom Pangar Hydropower Project (PAHLP) approved in November

2011; and (iii) the Cameroon-Chad Power Interconnection Project Study approved in

October 2013. The first project seeks to construct and extend power networks, and

increase the number of power connections. The second project aims at increasing the

country’s power generation. The third project financed engineering studies for the

preparation of this investment project.

8. With this new operation, the Bank will consolidate the achievements of previous

projects in order to achieve the objectives set in the country’s infrastructure

development strategy.

9. Based on the foregoing, and at the request of the Government, it is proposed that the

AfDB Window limit the counterpart funding to 6.54% of the total project cost, net of

taxes, for the partial financing of works, and the full payment of expropriation costs

and the operating expenses of the implementation unit as well as programme-related

tax expenditure resulting from exemptions from custom duties and other taxes.

The country’s fiscal situation and debt level

10. Fiscal policy over the past three years has been moderately expansionary to bridge

the infrastructure gap, especially in the energy and transport sectors. These

anchor projects have been financed with external borrowing and oil revenue.

11. The signature of a three-year programme backed by an Extended Credit Facility

(ECF5) with the IMF is expected to contribute to stabilizing the macroeconomic

framework in the medium term. For 2016, growth was scaled down slightly from

4.7 % to 4.5 %. For 2017, it should reach 3.7%, while inflation is expected to remain

low (0.5 %). The fiscal deficit should stand at 3.1% of GDP in 2017 and 2.3 % in

2018. Public investment expenditure should stabilize progressively, dropping from

about 8.8% of GDP in 2016 to 7.3% in 2017, then to 6.7% in 2019 at the end of the

programme. Revenue (including grants) will increase moderately from 16.3% of GDP

in 2016 to 16.7% in 2017 and 17.6% in 2019.

12. A more prudent and rigorous debt management is required considering the

deterioration of debt ratios. According to the last debt sustainability analysis carried

out by the International Monetary Fund (IMF) and the World Bank in 2015 and 2016,

the country’s risk of debt distress has moved from "moderate to high". The sharp drop

in crude oil prices, which is the country’s main export product, has since 2015 led to

the deterioration of the ratio of net present value of debt to exports of goods and

5 The Extended Credit Facility (ECF) concluded on 26 June 2017 with the IMF over a three-year period (2017-2019), more than ten years after the previous

one which led to the achievement of the HIPCI completion point in 2006, shows a financing need estimated at CFAF 1302 billion. This financing gap should be bridged by budget support operations implemented by TFPs, including the IMF, AfDB, the World Bank, the EU and AFD.

III

services. Despite a debt ratio below the community ceiling of 70% of GDP, the

financing of anchor infrastructure projects with commercial loans has led to a sharp

increase in public debt, which reached 34.1% of GDP in 2016, against 15.6% in 2012.

These findings call for a more prudent and rigorous debt management. To mitigate the

risk of debt distress, the debt management institutional mechanism has been

reinforced. The opinion of the National Public Debt Committee (CNDP), which had

an advisory capacity at its inception, became compulsory in 2016 and is a pre-requisite

for any loan decision. The measures to be taken by the Government will help to

stabilize public debt at the 2017 baseline (36.1%) over the period 2017-2029, while

avoiding the accumulation of arrears, especially internal debt arrears.

Upper cost-sharing limit and guidelines laid down in the country financing

parameters

13. The country’s financing parameters (CFPs) on cost sharing highlight the country’s

commitment and ownership with respect to activities financed by the Bank under the

project. These parameters also allow for some flexibility in determining the

percentage of counterpart contribution. The Bank reviewed the level of commitment

and ownership using the criteria, which include: (i) the contribution of project

activities to achieving the country’s development goals as outlined in the Growth and

Employment Strategy Paper (GESP) covering the period 2010-2020; and (ii) the

alignment and linkage with the strategic pillars of the Bank’s Country Strategy Paper

(CSP) for Cameroon approved in July 2015 for the period 2015-2020, as well as the

inclusion of the project financed by the Bank and the other technical and financial

partners in the State budget.

14. The CFPs specify that the percentage of the total cost financed by the Bank will be

estimated on a case-by-case basis according to project context and considerations, the

expression of Government’s commitment and ownership of project implementation,

the level of co-financing with the other TFPs and the country’s fiscal situation. It

should be noted that the parameters are consistent with the World Bank’s CFPs in

Cameroon prepared in 2005 while the country was still eligible for concessional

resources only. These CFPs showed that World Bank financing could reach 100% of

the total project cost (tax inclusive), despite the fact that co-financing could be

obtained for some projects, notably in the transport sector. These parameters have not

changed despite Cameroon’s graduation to the status of IBRD/IDA “Blend Country”

in April 2014 at the World Bank and ADB/ADF “Blend Country” in July 2014.

15. In light of the foregoing, and at the request of the Government, it is proposed

that the counterpart contribution be set at 6.54%of the total project cost, net of

taxes. This level of counterpart contribution also takes into account the size of co-

financing mobilized by the Bank and the Government from the other TFPs. Therefore,

Cameroon’s counterpart contribution to the project (UA 16.14 million) will mainly be

used to finance expropriation costs and project-related tax expenditure resulting from

exemptions from customs duties and other taxes.

IV

Annex II.1: Cameroon’s Comparative Socio-economic Indicator

Year Cameroon Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2016 475 30 067 97 418 36 907Total Population (millions) 2016 23,9 1 214,4 6 159,6 1 187,1Urban Population (% of Total) 2016 55,1 40,1 48,7 81,1Population Density (per Km²) 2016 50,6 41,3 65,1 33,8GNI per Capita (US $) 2015 3290 2 153 4 509 41 932Labor Force Participation *- Total (%) 2016 76,1 65,7 63,5 60,0Labor Force Participation **- Female (%) 2016 71,1 55,7 48,9 52,1Sex Ratio (per 100 female) 2016 100,0 100,1 106,0 105,0Human Dev elop. Index (Rank among 187 countries) 2015 153 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2014 24,0 ... ... ...

Demographic Indicators

Population Grow th Rate - Total (%) 2016 2,5 2,5 1,3 0,6Population Grow th Rate - Urban (%) 2016 3,5 3,6 2,4 0,8Population < 15 y ears (%) 2016 42,3 40,9 27,9 16,8Population 15-24 y ears (%) 2016 20,2 19,3 16,9 12,1Population >= 65 y ears (%) 2016 3,2 3,5 6,6 17,2Dependency Ratio (%) 2016 83,6 79,9 54,3 52,0Female Population 15-49 y ears (% of total population) 2016 24,0 24,0 25,7 22,8Life Ex pectancy at Birth - Total (y ears) 2016 56,4 61,5 69,9 80,8Life Ex pectancy at Birth - Female (y ears) 2016 57,6 63,0 72,0 83,5Crude Birth Rate (per 1,000) 2016 35,7 34,4 20,7 10,9Crude Death Rate (per 1,000) 2016 10,9 9,1 7,6 8,6Infant Mortality Rate (per 1,000) 2015 57,1 52,2 34,6 4,6Child Mortality Rate (per 1,000) 2015 87,9 75,5 46,4 5,5Total Fertility Rate (per w oman) 2016 4,6 4,5 2,6 1,7Maternal Mortality Rate (per 100,000) 2015 596,0 476,0 237,0 10,0Women Using Contraception (%) 2016 34,1 31,0 62,2 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2005-2015 8,3 41,6 125,7 292,2Nurses and midw iv es (per 100,000 people) 2005-2015 52,0 120,9 220,0 859,4Births attended by Trained Health Personnel (%) 2010-2015 64,7 53,2 69,1 ...Access to Safe Water (% of Population) 2015 75,6 71,6 89,4 99,5Access to Sanitation (% of Population) 2015 45,8 39,4 61,5 99,4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2015 4,5 3,4 ... ...Incidence of Tuberculosis (per 100,000) 2015 212,0 240,6 166,0 12,0Child Immunization Against Tuberculosis (%) 2015 74,0 81,8 ... ...Child Immunization Against Measles (%) 2015 79,0 75,7 83,9 93,9Underw eight Children (% of children under 5 y ears) 2010-2015 14,8 18,1 15,3 0,9Prev alence of stunding 2010-2014 31,7 33,3 25,0 2,5Prev alence of undernourishment (% of pop.) 2015-2016 9,9 16,2 12,7 ...Public Ex penditure on Health (as % of GDP) 2014 0,9 2,6 3,0 7,7

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2016 117,1 101,2 104,9 102,4 Primary School - Female 2010-2016 110,7 98,4 104,4 102,2 Secondary School - Total 2010-2016 58,1 52,6 71,1 106,3 Secondary School - Female 2010-2016 53,5 50,2 70,5 106,1Primary School Female Teaching Staff (% of Total) 2010-2016 54,2 47,1 59,8 81,0Adult literacy Rate - Total (%) 2010-2015 75,0 66,8 82,3 ...Adult literacy Rate - Male (%) 2010-2015 81,2 74,3 87,1 ...Adult literacy Rate - Female (%) 2010-2015 68,9 59,4 77,6 ...Percentage of GDP Spent on Education 2010-2015 3,0 5,0 4,0 5,0

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2014 13,1 8,7 11,2 10,3Agricultural Land (as % of land area) 2014 20,6 41,7 37,9 36,4Forest (As % of Land Area) 2014 40,3 23,2 31,4 28,8Per Capita CO2 Emissions (metric tons) 2014 1,6 1,1 3,5 11,0

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Cameroon

June 2017

0

10

20

30

40

50

60

70

80

90

100

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

C am er o on A fr i ca

0

500

1000

1500

2000

2500

3000

3500

4000

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

GNI Per Capita US $

C am er o on A fr i ca

0,0

0,5

1,0

1,5

2,0

2,5

3,0

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

C am er oon A fr ic a

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

C am er o on A fr i ca

V

Annex II.2 : Chad’s Comparative Socio-economic Indicators

Year Chad Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2016 1 284 30 067 97 418 36 907Total Population (millions) 2016 14,5 1 214,4 6 159,6 1 187,1Urban Population (% of Total) 2016 21,9 40,1 48,7 81,1Population Density (per Km²) 2016 11,51 41,3 65,1 33,8GNI per Capita (US $) 2015 880 2 153 4 509 41 932Labor Force Participation *- Total (%) 2016 71,6 65,7 63,5 60,0Labor Force Participation **- Female (%) 2016 64,0 55,7 48,9 52,1Sex Ratio (per 100 female) 2016 100,3 100,1 106,0 105,0Human Dev elop. Index (Rank among 187 countries) 2015 186 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2011 38,4 ... 15,9 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2016 3,3 2,5 1,3 0,6Population Grow th Rate - Urban (%) 2016 3,6 3,6 2,4 0,8Population < 15 y ears (%) 2016 47,6 40,9 27,9 16,8Population 15-24 y ears (%) 2016 20,3 19,3 16,9 12,1Population >= 65 y ears (%) 2016 2,5 3,5 6,6 17,2Dependency Ratio (%) 2016 100,1 79,9 54,3 52,0Female Population 15-49 y ears (% of total population) 2016 22,1 24,0 25,7 22,8Life Ex pectancy at Birth - Total (y ears) 2016 52,2 61,5 69,9 80,8Life Ex pectancy at Birth - Female (y ears) 2016 53,3 63,0 72,0 83,5Crude Birth Rate (per 1,000) 2016 44,3 34,4 20,7 10,9Crude Death Rate (per 1,000) 2016 13,6 9,1 7,6 8,6Infant Mortality Rate (per 1,000) 2015 85,0 52,2 34,6 4,6Child Mortality Rate (per 1,000) 2015 138,7 75,5 46,4 5,5Total Fertility Rate (per w oman) 2016 5,9 4,5 2,6 1,7Maternal Mortality Rate (per 100,000) 2015 856,0 476,0 237,0 10,0Women Using Contraception (%) 2016 6,9 31,0 62,2 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2005-2015 4,4 41,6 125,7 292,2Nurses and midw iv es (per 100,000 people) 2005-2015 30,9 120,9 220,0 859,4Births attended by Trained Health Personnel (%) 2010-2015 24,3 53,2 69,1 ...Access to Safe Water (% of Population) 2015 50,8 71,6 89,4 99,5Access to Sanitation (% of Population) 2015 12,1 39,4 61,5 99,4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2015 2,0 3,4 ... ...Incidence of Tuberculosis (per 100,000) 2015 152,0 240,6 166,0 12,0Child Immunization Against Tuberculosis (%) 2015 70,0 81,8 ... ...Child Immunization Against Measles (%) 2015 62,0 75,7 83,9 93,9Underw eight Children (% of children under 5 y ears) 2010-2015 28,8 18,1 15,3 0,9Prev alence of stunding 2010-2014 38,7 33,3 25,0 2,5Prev alence of undernourishment (% of pop.) 2015-2016 34,4 16,2 12,7 ...Public Ex penditure on Health (as % of GDP) 2014 2,0 2,6 3,0 7,7

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2016 101,4 101,2 104,9 102,4 Primary School - Female 2010-2016 88,0 98,4 104,4 102,2 Secondary School - Total 2010-2016 22,4 52,6 71,1 106,3 Secondary School - Female 2010-2016 14,0 50,2 70,5 106,1Primary School Female Teaching Staff (% of Total) 2010-2016 15,4 47,1 59,8 81,0Adult literacy Rate - Total (%) 2010-2015 40,0 66,8 82,3 ...Adult literacy Rate - Male (%) 2010-2015 48,4 74,3 87,1 ...Adult literacy Rate - Female (%) 2010-2015 31,8 59,4 77,6 ...Percentage of GDP Spent on Education 2010-2015 2,9 5,0 4,0 5,0

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2014 3,9 8,7 11,2 10,3Agricultural Land (as % of land area) 2014 39,7 41,7 37,9 36,4Forest (As % of Land Area) 2014 4,0 23,2 31,4 28,8Per Capita CO2 Emissions (metric tons) 2014 0,0 1,1 3,5 11,0

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Chad

June 2017

0

20

40

60

80

100

120

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

Chad Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

GNI Per Capita US $

Chad Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

4,0

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

Chad Africa

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

Chad Africa

VI

Annex III.1: Table of AfDB Portfolio in Cameroon as at 30 June 2017

SECTOR PROJECTS ADB

loan

ADF/ NTF

Loan ADF Grant

Governance

Support Project for the Modernization of

the Land Registration System and

Business Climate (PAMOCCA 1).

7.00

Support Project for the Modernization of

the Land Registration System and

Business Climate (PAMOCCA 2).

5.00

Transport

Kumba-Mamfe Road Project 47.26

Road Programme 1: Batchenga-Léna 126.43 12.45

Road Programme 2: Yaounde-Bafoussam 221.71 12.82

Info-Com

Tech Central African Backbone 30.61 1,24

Water and

Sanitation

Yaounde Sanitation Project (PADY 2) 20.99 2,89

Semi-urban DWSS Project 33.77

Storm water Harnessing Studies

PEMVEP 1,06

Energy

Project for the Rehabilitation and

Extension of Power Transmission and

Distribution Networks (PREREDT)

31.64

Lom Pangar Hydroelectric Project 44.93

Agriculture Rural Infrastructure Support - Grassfield 2 13.61 3,19

Agricultural Value Chain Development

Project (AVC –DP)

73.28

Total Public National Operations 452.03 229.47 8.38

Private

Sector

Cameroon Shipyard and Industrial

Engineering Company (CNIC) 32.64

AES-SONEL Investment Programme 49.24

Dibamba Thermal Power Plant 18.27

Kribi Thermal Power Plant 23.45

Total Private National Operations 123.60

Regional

Environment

Central Africa Biodiversity Conservation

Programme -Protecting Central Africa’s

Elephants

0.25

Programme to Rehabilitate and Strengthen

the Resilience of Lake Chad Basin

Systems (PRESIBALT)

12.5

Regional

Energy

Study on the Chad – Cameroon 225 kV

Power Interconnection Project 1.25

Regional

Transport

Transport Facilitation on the Bamenda -

Enugu Corridor 90.39

Transport Facilitation on the Brazzaville -

Yaounde Corridor (Ketta –Djoum 1) 59.27

Transport Facilitation on the Brazzaville -

Yaounde Corridor (Ketta –Djoum 2) 50.92

Total Public Multinational Operations 50.92 3.66

TOTAL OVERALL PORTFOLIO

(UA 1.028 billion = USD 1.43 billion) 626.55 393.13 8.38

VII

Annex III.2: Table of AfDB Portfolio in Chad as at 30 June 2017

SECTOR PROJECTS ADF Commitment (UA)

Governance

Business Climate Improvement and Economic

Diversification Support Project (PACADET) - LOAN 3 970 000

Business Climate Improvement and Economic

Diversification Support Project (PACADET) -

GRANT 1 920 000

Round Table 650 000

Budget Support Programme - ADF GRANT 11 866 000

Budget Support Programme II - ADF LOAN 4 280 700

Budget Support Programme II – TSF GRANT 15 000 000

Achievement of HIPCI Completion Point - Grant 1 400 000

Total Governance (Institutional Support and Capacity Building) 39 086 700

Social Project to Promote the Education of Girls and

Literacy 1 000 000

Total Social 1 000 000

Transport

Algeria/Niger/Chad Road Project - Multinational

(LOAN) 20 900 000

Algeria/Niger/Chad Road Project - Multinational

(GRANT) 20 400 000

Kyabe-Singako Road Tarring Project (GRANT) 12 846 000

Total Transport 54 146 000

Water and

Sanitation

DWSS Programme for 15 Secondary Centres

(GRANT) 6 900 000

DWSS Programme for 15 Secondary Centres

(RWSSI GRANT) 2 460 569

DWSS Programme for 15 Secondary Centres

(LOAN) 10 710 000

Total Water and Sanitation 20 070 569

Energy Study on the Chad-Cameroon 225 kV Power

Interconnection Project (GRANT) 1 250 000

Total Energy 1 250 000

Agriculture

Lake Chad Basin Sustainable Development

Programme/ MULTINATIONAL (GRANT) 30 000 000

Rural Infrastructure Support Project (LOAN) 5 200 000

Rural Infrastructure Support Project (GRANT) 5 200 000

Programme to Build Resilience to Recurrent Food and

Nutritional Insecurity in the Sahel (P2RS) 9 770 000

Programme to Rehabilitate and Strengthen the

Resilience of Socio-ecological Systems

(PRESIBALT) (GRANT) 5 350 000

Biodiversity Conservation Programme in Central

Africa (GRANT) 250 000

Total Agriculture 55 770 000

TOTAL OVERALL PORTFOLIO

(Loans: UA 45 060 700 million & Grants: UA 126 262 569

million)

171 323 269

VIII

Annex IV.1: Similar Projects Financed by the Bank and other Development Partners of

Cameroon

Donor Project Name Approval Date Amount of

Financing Implementation Status

IBRD Upgrading the

Transmission Grid and

Reform of the Sector

June 2017 USD

116 million

Financing process

finalized. Final design

studies ongoing

IsDB

Strengthening Grids USD 110.3

million

Identification mission

fielded by IsDB in

November 2015 and

confirmation of financing

subject to PDSs/FDSs and

ESIA.

Financing of PDSs/FDSs

and ESIA by IBRD under

PMDRTERS

Société

Générale-

Coface /

BOUYGUES

Strengthening Networks

in Douala

Decree of the

President of the

Republic

pending

USD 154.27

million

Financing under review

Cameroon

Deutsche

Bank + Bank

Spain/

ELECNOR

Access Roads and Loops

in Yaoundé

August 2017 EUR 45 million Financing agreement

signed. Studies finalized.

Start of works in 2018

EXIMBANK

India Reinforcement of RIS In 2017 USD 115.15

million

Authorization decree

signed and financing

agreement signed

EU/

Cameroon ERD RUMPI Project (Studies and construction

of a mini-hydro-electric

plant and related power

networks, and rural

electrification of 59 rural

localities)

2011 CFAF 11945

million

70%

ADF of the

Kingdom of

Spain

PUROIL Project

Studies and construction of

135. 288 kilometres of

three-phase medium-

voltage grids, 15. 965

kilometres of single-phase

medium-voltage grids 5.26

kilometres of three-phase

low-voltage grids, 24.237

kilometres of single-phase

low-voltage grids,

electrification of 29 rural

localities and

establishment of 650

connections

2005 CFAF 4 707

million

100%

IsDB IsDB Project Phase 1

Studies and construction of

479.57 kilometres of three-

phase medium-voltage

grids, 192.795 kilometres

of single-phase low-

voltage grids, 211.31

kilometres of three-phase

low-voltage grids, 309.84

kilometres of single-phase

low-voltage grids,

2011 CFAF 6 290

million

100%

IX

Donor Project Name Approval Date Amount of

Financing Implementation Status

electrification of 62 rural

localities and

establishment of 3 778

connections

World Bank

(IDA)

PDSEN Project Studies and construction of

227.285 kilometres of

three-phase medium-

voltage grids, 109.297

kilometres of single-phase

medium-voltage grids,

83.423 three-phase low-

voltage grids, 146.852

kilometres of single-phase

low-voltage grids,

electrification of 80 rural

localities and

establishment of 10374

connections

2011

CFAF

8 877 million

100%

IsDB IsDB Project PHASE 2

Electrification of 102 rural

localities

2016 CFAF 21 506

million Project ongoing

BADEA BADEA Projects

Electrification of 50 rural

localities

2016 CFAF 7 076

million

Project ongoing

European

Union /

Cameroon

PLAN VER Projects

Construction of two mini-

hydroelectric plants in

Ngoro and Batié

2016 CFAF 12 000

million

Project ongoing

Annex IV.2: Similar Projects Financed by the Bank and other Development Partners of

Chad

Donor Project Name Approval Date Amount of

Financing

Implementation

Status

AfDB Study on the Chad-

Cameroon Power

Interconnection Project

7/10/2013 UA 1 250 000

(share of Chad)

Studies completed in

May 2017

IsDB Solar Energy Project for

Rural Development

(3MW photovoltaic solar

plant & medium-voltage

and low-voltage

distribution network)

Financing request

being negotiated

with the IsDB

USD 22.90

million

Pre-feasibility study

ongoing

TBEA

Exim Bank of

China

Construction of a crude

oil-fired power plant (90

MW)

Commercial

contract signed

USD 146

million

Pre-feasibility study

ongoing

X

Annex V: Map of Project Area