AES/RE/11-11 Optimization of mining and processing for an ...

138
- 1 - AES/RE/11-11 Optimization of mining and processing for an Albanian nickel-laterite mine June 2011 Nicholas Russell

Transcript of AES/RE/11-11 Optimization of mining and processing for an ...

- 1 -

AES/RE/11-11 Optimization of mining and processing for an

Albanian nickel-laterite mine

June 2011 Nicholas Russell

Title : Optimization of mining and processing for an Albanian nickel-laterite mine Author(s) : Nicholas Russell Date : June 2011 Professor(s) : Hans de Ruiter Supervisor(s) : Tanya Law, Piet Hein van der Klein & Mikael Rinne TA Report number : AES/RE/11.11 Postal Address : Section for Resource Engineering Department of Applied Earth Sciences Delft University of Technology P.O. Box 5028 The Netherlands Telephone : (31) 15 2781328 (secretary) Telefax : (31) 15 2781189 Copyright ©2011 Section for Resource Engineering All rights reserved. No parts of this publication may be reproduced, Stored in a retrieval system, or transmitted, In any form or by any means, electronic, Mechanical, photocopying, recording, or otherwise, Without the prior written permission of the Section for Resource Engineering

Acknowledgements It is a pleasure to thank those who made this thesis possible. They have made their support available

number of ways and greatly contributed to this work.

I would like to thank Tanya Law for her supervision during the writing of this thesis. She has

supported me throughout my thesis work and constant source of new ideas and new directions.

This thesis would not have been possible without the support of Hans de Ruiter and the FEMP

organization that gave me the opportunity to study in a truly fantastic programme.

I would also like to show my gratitude to Mikael Rinne and Piet Hein van der Klein for their time and

efforts.

I am indebted to many of my colleagues and friends to support me throughout my studies on the

EMC, in Finland and The Netherlands. I would particularly like to thank Pieter Sturm, Jeroen Sens,

the members of the “de Teerput” – Mathijs Mol, Laurens van der Sluijs, Richard Hontelez, Ruben

Logister and Randy Calis - and the EMC classes of 2009/10 and 2010/11.

Gluck Auf!

Nicholas Russell

June, 2011

- 4 -

1 Executive Summary

The scope of the project was to re-evaluate, optimize and update an existing pre-feasibility study

(PWK Resources, 2010) of European Nickel’s Devolli project in south-eastern Albania. This included,

but was not limited to, the development of the resource estimate; geotechnical assessment of the

different rock zones; investigation of potential mining methods; design and optimization of selected

mining methods including equipment selection and CAPEX and OPEX estimation; development,

optimization and cost estimation of the raw material handling process stream; investigation of

potential processing methods; process plant design and capital and operating expenditure estimate;

environmental impact assessment (EIA); project risk assessment; market analysis; and project

finance.

The Devolli deposit consists of two separate ore bodies; Verniku West and Kapshtica. Verniku West,

located in the north, is approximately 200m underground with a north-south syncline and an

average ore thickness of 4m. Kapshtica is the southern deposit and is deeper at approximately 400m

below the surface. This deposit dips towards the south at an angle of 30 degrees and the ore body

has a thickness ranging from 2m up to 30m in select parts. The project has an indicated resource of

48.7 million tonnes of laterite ore with average grade of nickel of 1.13% and cobalt of 0.04%. Closer

drillhole spacing with increased detailed sampling, geological mapping and geotechnical

understanding of the different laterite zones is required before either ore body can be classified as

proven resources.

The project was designed with two different mine systems; room-and-pillar and longwall mining. A

variation of the room-and-pillar design, referred to as Post room-and-pillar design was also costed.

New software to link Microsoft Excel and Gemcom Surpac was developed for this project to allow

optimization of the mine design. Over 12,000 individual mine configurations were constructed,

validated and measured so that the optimum design was selected. A total of 7 different mining

constructs were designed.

The transportation of the raw material to the surface is achieved with either trucks or conveyors.

The CAPEX and OPEX of mine and/or sized stockpiles were estimated as well as the costs of changing

from conveyor to trucks mid-process. In total, 32 different material handling scenarios were fully

designed and estimated.

The processing technologies for nickel laterite ores were reviewed and heap leaching was selected

as the most appropriate. A slight alternative to the normal heap leach design is the creation of two

leach pads; a quick leach pad for saprolite ore and a long leach pad for mixed ore. Due to

- 5 -

insufficient column test data for acid agglomerated saprolite and limonite samples, this option could

not be fully explored but may be a point of interest in future studies. In addition, it was found that

the cost of processing the nickel laterite ores is many times the mining cost. This is due to the large

amounts of sulphuric acid required; over 500kg per tonne of ore. The economic evaluation

determined the level of sulphuric acid consumption to be a key cost consideration when determining

the potential feasibility of the project. A sulphuric acid plant was recommended to reduce the cost

of acid and lessen project exposure to the risk of large fluctuations in acid prices.

An environmental impact assessment was completed for the Devolli project. It was found that there

are no significant risks to environment that cannot be mitigated with reasonable design choices and

policies.

The combination of 7 different mining strategies and 32 materials handling options gave 72 valid

options in which the deposit could be mined and processed. The net present value for each option

was calculated for production rates ranging from 1000 to 15000 tonnes per day and for cut-of-grade

ranging from 0.0% to 1.3% nickel with an ultimate total of 15,192 net present values being

calculated. The result of the financial analysis was that none of the options were profitable at this

present time. A zero-line graph was constructed showing the nickel-sulphur price that would be

required for the project to break even.

The result of this study is that the Devolli project is not feasible based on current nickel and

sulphuric acid price forecasts using the methods evaluated.

- 6 -

Table of Contents

1 Executive Summary ......................................................................................................................... 4

2 Introduction .................................................................................................................................. 16

3 Project Background ....................................................................................................................... 17

3.1 Site Information .................................................................................................................... 17

3.1.1 Climate .......................................................................................................................... 17

3.1.2 Albanian Culture ........................................................................................................... 18

3.1.3 History of Mining in the Area ........................................................................................ 19

3.2 Project Ownership ................................................................................................................ 19

3.3 Mining lease and exploration concessions ........................................................................... 19

4 Geology ......................................................................................................................................... 21

4.1 Regional Geology .................................................................................................................. 21

4.2 Nickel Laterites ...................................................................................................................... 23

4.2.1 Limonite zone ................................................................................................................ 23

4.2.2 Saprolite zone ............................................................................................................... 24

4.2.3 Transition zone .............................................................................................................. 24

4.2.4 Serpentinite zone .......................................................................................................... 24

4.3 Modelling .............................................................................................................................. 25

4.3.1 Drillhole Database ......................................................................................................... 25

4.3.2 Ore Body Limits ............................................................................................................. 26

4.3.3 Zone Separation ............................................................................................................ 26

4.3.4 Grade Estimate .............................................................................................................. 28

4.4 Seismicity .............................................................................................................................. 28

4.5 Faulting.................................................................................................................................. 29

4.6 Resource Statement .............................................................................................................. 32

5 Mining ........................................................................................................................................... 36

5.1 Geotechnical ......................................................................................................................... 36

- 7 -

5.2 Mine Method Selection ........................................................................................................ 37

5.3 Mine Design .......................................................................................................................... 37

5.3.1 Room and Pillar ............................................................................................................. 37

5.3.2 Longwall ........................................................................................................................ 44

5.3.3 Stope Leaching .............................................................................................................. 50

5.3.4 In-situ Leaching ............................................................................................................. 51

5.4 Mine Equipment ................................................................................................................... 51

5.4.1 Room-and-pillar mining ................................................................................................ 51

5.4.2 Longwall mining ............................................................................................................ 51

5.5 Mine Scheduling .................................................................................................................... 52

5.6 Cost Modelling ...................................................................................................................... 52

6 Raw Ore Handling ......................................................................................................................... 54

6.1 Options .................................................................................................................................. 54

6.1.1 Run-of-Mine (ROM) ...................................................................................................... 56

6.1.2 Transportation to Surface and Surface Transportation ................................................ 57

6.1.3 Mine Stockpile (optional) .............................................................................................. 57

6.1.4 Material Sizing ............................................................................................................... 58

6.1.5 Sized Stockpile (optional) .............................................................................................. 58

6.1.6 Heap Leach Pad Stacking .............................................................................................. 58

6.2 Cost Modelling ...................................................................................................................... 59

7 Processing ..................................................................................................................................... 61

7.1 Options .................................................................................................................................. 61

7.1.1 Direct Transportation of Ore......................................................................................... 61

7.1.2 Ferronickel and matte smelting .................................................................................... 62

7.1.3 Caron Process ................................................................................................................ 63

7.1.4 High Pressure Acid Leaching (HPAL) ............................................................................. 63

7.1.5 Enhanced Pressure Acid Leaching (EPAL) ..................................................................... 64

7.1.6 Atmospheric Tank Leaching (ATL) ................................................................................. 65

- 8 -

7.1.7 Heap Leaching ............................................................................................................... 66

7.1.8 In-situ/Stope Leaching .................................................................................................. 66

7.2 Method Selection .................................................................................................................. 67

7.3 Metallurgy and Test work ..................................................................................................... 69

7.3.1 Test samples .................................................................................................................. 69

7.3.2 Interpretation of Results ............................................................................................... 70

7.4 Heap Leaching ....................................................................................................................... 76

7.5 In-situ Leaching ..................................................................................................................... 77

7.6 Stope Leaching ...................................................................................................................... 78

7.7 Precipitation Plant................................................................................................................. 78

7.7.1 Iron (Fe) Precipitation ................................................................................................... 80

7.7.2 Ion Exchange ................................................................................................................. 81

7.7.3 Nickel Precipitation ....................................................................................................... 81

7.7.4 Iron/aluminium Precipitation ....................................................................................... 82

7.7.5 Nickel/cobalt precipitation ........................................................................................... 82

7.7.6 Product Packing............................................................................................................. 83

7.8 Reclaiming Leached Ore ........................................................................................................ 83

7.9 Cost Modelling ...................................................................................................................... 83

8 Infrastructure ................................................................................................................................ 84

8.1 Offsite Infrastructure ............................................................................................................ 84

8.1.1 Power Supply ................................................................................................................ 84

8.1.2 Water Supply ................................................................................................................. 84

8.1.3 Road and Rail ................................................................................................................ 85

8.2 Onsite Infrastructure ............................................................................................................. 85

8.2.1 Administration Offices and Changing House ................................................................ 87

8.2.2 Warehouse .................................................................................................................... 88

8.2.3 Workshops .................................................................................................................... 88

8.2.4 Oil and Lubricant Store ................................................................................................. 88

- 9 -

8.2.5 Laboratory ..................................................................................................................... 88

8.2.6 Water and Sewage Treatment Plant ............................................................................. 89

8.2.7 Explosive Storage .......................................................................................................... 89

8.2.8 Fuel Storage .................................................................................................................. 89

8.2.9 Accommodation ............................................................................................................ 89

8.3 Sulphuric Acid Plant .............................................................................................................. 89

8.4 Limestone Quarry ................................................................................................................. 90

9 Ventilation ..................................................................................................................................... 91

10 Environmental and Social Management ................................................................................... 93

10.1 Environmental Legislation..................................................................................................... 93

10.2 Environmental Impact Analysis ............................................................................................. 94

10.2.1 Dust ............................................................................................................................... 94

10.2.2 Air Pollution .................................................................................................................. 95

10.2.3 Water ............................................................................................................................ 96

10.2.4 Noise ............................................................................................................................. 96

10.2.5 Vibrations ...................................................................................................................... 97

10.2.6 Land use & Top soil management ................................................................................. 98

10.2.7 Flora and Fauna ............................................................................................................. 98

10.2.8 Waste Material.............................................................................................................. 98

10.3 Cultural Heritage ................................................................................................................... 99

11 Project Scheduling .................................................................................................................. 101

11.1 Pre-production .................................................................................................................... 101

11.2 Production ........................................................................................................................... 102

11.3 Post-production .................................................................................................................. 102

12 Risk Analysis ............................................................................................................................ 103

12.1 Construction and Development .......................................................................................... 105

12.2 Operations .......................................................................................................................... 108

12.3 Closure ................................................................................................................................ 111

- 10 -

13 Mine Closure and Decommissioning ...................................................................................... 112

13.1 Closure Plan Development .................................................................................................. 112

13.1.1 Mine ............................................................................................................................ 113

13.1.2 Heap leach pad ............................................................................................................ 114

13.1.3 Precipitation plant and other mine infrastructure ..................................................... 114

13.1.4 Leached ore dump ...................................................................................................... 114

13.2 Cost of Mine Closure ........................................................................................................... 115

14 Market Analysis ....................................................................................................................... 116

14.1 Nickel ................................................................................................................................... 116

14.1.1 Consumption ............................................................................................................... 116

14.1.2 Production ................................................................................................................... 116

14.1.3 Supply and demand .................................................................................................... 117

14.1.4 Alternatives/Substitutes ............................................................................................. 118

14.1.5 Historical pricing ......................................................................................................... 118

14.1.6 Future price prediction ............................................................................................... 119

14.1.7 Project Pricing ............................................................................................................. 120

14.2 Cobalt .................................................................................................................................. 120

14.2.1 Consumption ............................................................................................................... 120

14.2.2 Production ................................................................................................................... 120

14.2.3 Supply and Demand .................................................................................................... 121

14.2.4 Alternatives and substitutes ....................................................................................... 121

14.2.5 Historical pricing ......................................................................................................... 122

14.2.6 Project pricing ............................................................................................................. 122

15 Economic Appraisal ................................................................................................................. 123

15.1 Currency and Inflation ........................................................................................................ 123

15.2 Net Smelter Return ............................................................................................................. 123

15.3 Financial Model ................................................................................................................... 123

15.3.1 Corporate tax and royalties ........................................................................................ 124

- 11 -

15.3.2 Discount rate ............................................................................................................... 124

15.3.3 Depreciation ................................................................................................................ 124

15.3.4 Pre-production Time ................................................................................................... 124

15.3.5 Value added taxes ....................................................................................................... 125

15.3.6 Summary of discount cash flow model parameters ................................................... 125

15.4 Base Case Results ................................................................................................................ 125

15.5 Financial Appraisal .............................................................................................................. 127

15.6 Sensitivity Analysis .............................................................................................................. 127

15.6.1 Variations in Four Key Cost Factors ............................................................................ 127

15.6.2 Net Present Value zero-line due to nickel and sulphur price ..................................... 129

16 Recommendations .................................................................................................................. 131

17 Conclusion ............................................................................................................................... 132

18 Bibliography ............................................................................................................................ 133

19 Appendix A: Geological map of Albania .................................................................................. 139

20 Appendix B: 3D Figures of the ore body ................................................................................. 140

21 Appendix C Fault modelling cross sections ............................................................................. 141

22 Appendix D Resource Grade-tonnage curves ......................................................................... 142

23 Appendix E Nicholas Method Results ..................................................................................... 143

24 Appendix F Room-and-pillar recovery calculation .................................................................. 144

25 Appendix G Room-and-pillar & longwall input screen ........................................................... 145

26 Appendix H Reserve grade tonnage curves ............................................................................ 146

27 Appendix I Cost Model ............................................................................................................ 147

28 Appendix J Process flow diagrams .......................................................................................... 148

29 Appendix K Project Gantt chart .............................................................................................. 149

30 Appendix L Financial result for all options .............................................................................. 150

- 12 -

List of Figures

Figure 1 Map of the project area (large map) and reference location with regard to Albania (top left)

.............................................................................................................................................................. 17

Figure 2 Average Temperatures for Korce, Albania throughout the year(World Weather Online, 2011;

NASA, 2011) .......................................................................................................................................... 18

Figure 3 Average rainfall throughout the year for Korce(World Weather Online, 2011) ..................... 18

Figure 4 Devolli map showing drill hole collar locations ...................................................................... 21

Figure 5 Extract of geological map of Albania showing Fe-Ni & Ni-Si zones ........................................ 22

Figure 6 Effect of climate on typical nickel laterite profiles(Chan, 1998) ............................................. 23

Figure 7 Ore boundaries of Verniku West (left) and Kapshtica (right) ................................................. 26

Figure 8 Block model showing mineral types calculated using single ore body ................................... 27

Figure 9 Seismicity of Albania(Aliaj, et al., 2004) .................................................................................. 29

Figure 10 Major faulting in Albania(Aliaj, 2007) ................................................................................... 30

Figure 11 Plan of Verniku West - faults in red, possible faults in blue & vertical displacements in

yellow (see Appendix C) ........................................................................................................................ 31

Figure 12 Plan of Kapshtica - possible faults in blue and vertical displacements in yellow (see

Appendix C) ........................................................................................................................................... 32

Figure 13 Grade-tonnage curve for Verniku West deposit ................................................................... 33

Figure 14 Grade-tonnage curve for Kapshtica deposit ......................................................................... 34

Figure 15 Mineral tonnage curve for Verniku West ............................................................................. 34

Figure 16 Mineral tonnage curve for Kapshtica .................................................................................... 35

Figure 17 Classic room-and-pillar mining(Hustrulid, 2001) .................................................................. 38

Figure 18 Post room-and-pillar mining(Hustrulid, 2001) ...................................................................... 39

Figure 19 Step-room mining(Hustrulid, 2001) ...................................................................................... 39

Figure 20 Tributary area calculation for pillars(Brady, et al., 2004) ..................................................... 40

Figure 21 Room-and-pillar room automatically generated - Plan view (top-left), elevation (top right)

and isometric view of pillars and the mined area (bottom left and right respectively) ....................... 41

Figure 22 Room and pillar design for Devolli project ........................................................................... 42

Figure 23 Grade-tonnage curve for room and pillar method ............................................................... 43

Figure 24 Grade-tonnage curve for post room-and-pillar .................................................................... 43

Figure 25 Longwall mining(Hustrulid, 2001) ......................................................................................... 44

Figure 26 Single Pass Longwall method – mine direction to the left of the page(Ozfirat, et al., 2005)45

Figure 27 Multi-Slice Longwall method - mine direction to the right of the page(Ozfirat, et al., 2005)

.............................................................................................................................................................. 45

- 13 -

Figure 28 Longwall Top Coal Caving method ........................................................................................ 46

Figure 29 Layout of longwall panel in plan ........................................................................................... 47

Figure 30 Longwall mine panels created. ±10 deg extraction angle (left) and 10 & 20 deg longwall

angle (right) ........................................................................................................................................... 47

Figure 31 Longwall designs for Verniku West (left and centre) and Kapshtica (right) ......................... 48

Figure 32 Grade-tonnage curve for longwall mining (northern deposit with north-south oriented

longwall panels) .................................................................................................................................... 49

Figure 33 Grade-tonnage curve for longwall mining (northern deposit with east-west oriented

longwall panels) .................................................................................................................................... 50

Figure 34 Example of a raw material handling option .......................................................................... 54

Figure 35 Raw material handling options ............................................................................................. 56

Figure 36 Cost model sheets ................................................................................................................. 59

Figure 37 Cost model example showing CAPEX and OPEX totals ......................................................... 60

Figure 38 Nickel recovery verse leach time .......................................................................................... 71

Figure 39 Acid consumption verse leach time ...................................................................................... 71

Figure 40 Nickel recovery verse leach time using alternative test column ACT-6 ................................ 72

Figure 41 Acid consumption verse leach time using alternative test column ACT-6 ........................... 72

Figure 42 Nickel recovery verse leach time of agglomerated ore ........................................................ 73

Figure 43 Acid consumption verse leach time of agglomerated ore .................................................... 74

Figure 44 Nickel recovery verse leach time with theoretical agglomerated NiSi sample .................... 75

Figure 45 Acid consumption verse leach time with theoretical agglomerated NiSi sample ................ 75

Figure 46 EN precipitation plant flow sheet design (L: liquids and S: solids) (European Nickel, 2010) 78

Figure 47 Alternative precipitation plant flow sheet design ................................................................ 79

Figure 48 Precipitation plant process flow illustration(European Nickel, 2010) .................................. 80

Figure 49 Illustration of Calgon ISEP continuous ion exchange separator(Calgon Carbon Corp., 2004)

.............................................................................................................................................................. 81

Figure 50 Map of Albania and Greece showing major electrical points of interest to the project ...... 84

Figure 51 Site plan showing major infrastructure ................................................................................ 87

Figure 52 Historical sulphuric acid prices(ICIS, 2010) ........................................................................... 90

Figure 53 High-level ventilation design for the Devolli project ............................................................ 91

Figure 54 Location of sites of cultural importance(European Nickel, 2010) ...................................... 100

Figure 55 Mine closure plan development process flow chart........................................................... 113

Figure 56 Nickel by first use(Nickel Institute, 2007) ........................................................................... 116

Figure 57 Nickel by end use(Nickel Institute, 2007) ........................................................................... 116

- 14 -

Figure 58 Nickel Production in 2010 by Countries(US Geological Survey, 2011) ............................... 117

Figure 59 Average price of nickel from 1958 to 2010(Kuck, 1998; LME, 2011; inflationdata.com, 2011)

............................................................................................................................................................ 118

Figure 60 LME spot prices for nickel over last 5 years(LME, 2011) .................................................... 119

Figure 61 Consumption of cobalt(Geovic Mining Corp, 2009) ........................................................... 120

Figure 62 Cobalt producing countries of 2009(US Geological Survey, 2010) ..................................... 121

Figure 63 Cobalt past and predicted future supply and demand needs(Geovic Mining Corp, 2009) 121

Figure 64 Sensitivity analysis for room-and-pillar option ................................................................... 128

Figure 65 Sensitivity analysis for longwall option ............................................................................... 128

Figure 66 NPV zero-line due to nickel and sulphur price for room-and-pillar option ........................ 129

Figure 67 NPV zero-line due to nickel and sulphur price for longwall option .................................... 129

- 15 -

List of Tables Table 1 Albanian mineral tenure law summary(Christopher, 2009) .................................................... 20

Table 2 Relinquish timings for exploration permits(Christopher, 2009) .............................................. 20

Table 3 Resource Statement for Devolli Nickel Project with cut-of-grade of 0.5% Ni .......................... 33

Table 4 Sample of geotechnical results ................................................................................................ 36

Table 5 Shearer and plow properties(Myszkowski, et al., 2010) .......................................................... 46

Table 6 Mining cost model options ...................................................................................................... 52

Table 7 Column test parameters .......................................................................................................... 69

Table 8 Likelihood rating with description and explanation ............................................................... 103

Table 9 Consequence rating for different categories(University of New South Wales, 2010) ........... 104

Table 10 Example of risk matrix(Department of Resources, Tourism and Industry, 2008) ................ 105

Table 11 Potential project risks during construction and development (without mitigation) ........... 106

Table 12 Potential project risks during construction and development (with mitigation) ................ 107

Table 13 Potential project risks during operations (without mitigation) ........................................... 108

Table 14 Potential project risks during operations (with mitigation) ................................................. 110

Table 15 Potential project risks during mine closure (without mitigation) ........................................ 111

Table 16 Potential project risks during mine closure (with mitigation) ............................................. 111

Table 17 Net smelter return parameters ............................................................................................ 123

Table 18 Depreciation allowances ...................................................................................................... 124

Table 19 Discounted cash flow model parameters ............................................................................ 125

Table 20 Valid mining & material handling/processing options ......................................................... 125

Table 21 Financial results for the different mining options ................................................................ 126

Table 22 Financial results for the different mining options with 20% reduction in sulphur price ..... 126

Table 23 Sensitivity analysis key parameters ...................................................................................... 128

- 16 -

2 Introduction

This report examines the feasibility of the European Nickel Devolli deposit and makes

recommendations on future testing and exploration required to classify this deposit as a proven

reserve. It is the continuation of a previous carried out pre-feasibility study (PWK Resources, 2010).

Key project elements such as geology, mining, materials handling, processing and financial analysis

have been completely re-analysed and optimized.

The scope of works for the project includes:

development of resource estimates for two options:

o a single mixed mine project

o two separate mine products

geotechnical assessment of the deposit

investigation of potential mining methods including potential innovative options

optimization of mine design, select equipment and create base schedules for both options

estimation of mining CAPEX and OPEX for both options

research of potential ore processing methods

development and estimation of costs for multiple material transportation options

creation of process flow diagrams

optimization of plant size, reagent consumption and recoveries to maximize overall NPV

estimation of processing CAPEX and OPEX for both options

preliminary environmental impact assessment (EIA)

market analysis and long-term commodity price forecast

project finance and overall profitability

risk assessment based on possible seismic activity in the area and ad-hoc local mining and

develop mitigation plan.

The previous study was a short concept study and many of the design decisions were based on rules-

of-thumb. This study aims to create a relatively detailed cost estimate so that

- 17 -

3 Project Background

3.1 Site Information

The Devolli deposit is located in south-eastern Albania near the small town of Bilishti close the Greek

border. Korce, the principal town in the region, is located approximately 30km by road to the west.

Figure 1 below is a map of south-east Albania showing the deposit location.

Figure 1 Map of the project area (large map) and reference location with regard to Albania (top left)

The licence area is approximately 77km2 and the elevation of the area ranges from 476m to 932m

above sea level. The licence area is primarily private-owned farm land with some areas covered by

scrub. The area above the Devolli deposits is very barren and hilly with some scrub. The deposit lays

just over 8km from the Greek border. Main access to the site is via the main road SH3 which has

been improved in recent years. Other small villages in the vicinity of the project area are Verniku,

Kapshitca, Vishocica, Bitinska and Treni (see Figure 1).

3.1.1 Climate

Albania is located in western part of the Balkan Peninsula and neighbours Greece and FYROM in the

east, Kosovo to the north and Montenegro in the north-west. The climate varies across Albania from

the typical Mediterranean environment in the west to the moderate continental weather in the east.

- 18 -

The climate around Korce is typically Mediterranean with average day temperatures ranging from 7

degrees C in the winter up to 30 degrees C in the summer (see Figure 2). Average temperatures at

night during the winter months are sub-zero so the freezing conditions need to be considered in the

process design.

Figure 2 Average Temperatures for Korce, Albania throughout the year(World Weather Online, 2011; NASA, 2011)

Average precipitation for the year is approximately 550mm which variers throughout the year. As

per Figure 3, there is a trend for summer months to be dryer with wetter months at the end of the

year.

Figure 3 Average rainfall throughout the year for Korce(World Weather Online, 2011)

3.1.2 Albanian Culture

Albania is a male dominant society where it is the norm for women to be caretakers of the home

and their duty is to serve their husbands, sons and any guests. During the 1960’s and 70’s, the

communist party did much to improve women rights but in the decades that followed, much of this

- 19 -

progress was reversed. In recent times, women are increasingly being employed outside of the

home and are finding employment much easier than men. Smoking and drinking alcohol by

Albanian women was once unknown but this is now becoming common place in Tirana (Culture

Crossing). Unemployment for the Albanian population is currently estimated at 13.5%(CIA, 2011).

The education system in Albania is secular and the literacy rate (age 9 and over who can read and

write) of the total population is 98.7% (CIA, 2011). Elementary education is compulsory and most

students continue until completion of their secondary studies. Exams must be passed at the end of

the 9th grade and the 12th grade to continue into high levels of education. At higher education levels,

briberies are common to obtain diploma degrees resulting in many Albanian students applying for

university placements abroad to receive a fair and recognised education.

3.1.3 History of Mining in the Area

The Devolli region is not new to mining. Mining operations, primarily small pits for limestone

excavation, began in the region in the early 20th century. The exploration of nickel commenced in

the1950’s throughout Albania and the first geological exploration in the Devolli region occurred in

1957. The Bitincka nickel laterite open pit mine commenced production in 1988 and reached peak

production in 1988. With the fall of communism in the early 1990’s, many mines in Albania ceased

operating. Near the project area are adits indicating the start of mining activities in Bilisht. This

underground opening was used by Montec to evaluate rock and ore characteristics.

3.2 Project Ownership

Ownership of the Devolli deposit has changed since the previous prefeasibility study(PWK Resources,

2010). In 2009/10, Balkan Resources Inc was working towards a 50% economic interest in the

project by completing a JORC-compliant prefeasibility study on the project. Balkan Resources failed

to raise sufficient funds to fulfil its obligations as part of the joint venture agreement and

surrendered its claim in the Devolli deposit. Thus, the project is now owned and under direct control

of Adriatic Nickel Sh.p.k, an Albanian listed, wholly owned subsidiary of European Nickel plc.

3.3 Mining lease and exploration concessions

New mining legislation was introduced in Albania in 1994 with one of the primary goals to stimulate

foreign investment. Mining leases and exploration concessions are administrated through three

types of permits. The permits and their main properties are given below in Table 1(Christopher,

2009).

- 20 -

Table 1 Albanian mineral tenure law summary(Christopher, 2009)

Type of Tenure Period (years)

Renewals (years)

Maximum Area (km2)

Annual Fees

Prospecting 1 None 400 US$320 per permit registration fee

Exploration Concession 2 3 x 1 year 200 US$320 / 1km2 / year

Mining Concession 20 4 x 5 years 15 US$ 2,000 to US$ 10,000 / 1km2 / year

Although there is a maximum area for exploration and mining concessions, an applicant may hold

more than one mineral tenure and can create a greater combined area. The deposit is currently

covered by an exploration concession. Over the life of the exploration concession, parts of the

original concession must be relinquished by the holder (see Table 2 below).

Table 2 Relinquish timings for exploration permits(Christopher, 2009)

Timing Relinquished portion size

End of first two year period 40% of original concession area

End of first extension 50% of original concession area

End of second extension 70% of original concession area

End of final extension 100% of original concession area excluding approved areas

A concession holder may re-apply for a new concession to cover previously relinquished areas,

however this is subject to approval by the Ministry of Economy, Trade and Energy once again.

Albanian mining law allows mining enterprises to be completely foreign owned. Additionally, the

legal regime remains unchanged for the full term of the mining concession.

- 21 -

4 Geology The nickel deposits investigated in this report are located in the Devolli district in south-east Albania.

The deposits are situated approximately 8 km west of the north-south trending Greek border.

Figure 4 below shows the deposit areas (light blue), the nearby town of Bilishti (brown area, centre

left of figure) and the Albanian-Greek border (black-dotted line, right of figure). The deposit was

originally documented by drilling performed by the Albanian Geological Survey (ABS). These drill

holes (red symbols in the figure) defined the contact depth of sedimentary overburden, lateritic ore

and barren host rock. Further works by European Nickel have confirmed the results from the ABS

drilling and have progressed with the delineation of the ore bearing zones in three dimensions.

Figure 4 Devolli map showing drill hole collar locations

4.1 Regional Geology The project area is the southern part of the Mirdita ophilite tectonic unit. The main geological

structure is a NNW-SSE trending syncline. This is the Albano Thessalian Depression which is also

known locally as the Shkumbini syncline. The syncline includes an Upper-Cretaceous limestone in

the centre and in the west Tertiary sediments. This is flanked by ultramafics on both sides.

Quaternary clastic sedimentary formations of the Devolli plain cover the borders to the south and

- 22 -

west. The north-east of the syncline is adjoined to massive limestone of the Upper Triassic

Korabi tectonic unit. During the Barremian-Aptian age, lateritisation of the ultramafic rock took

place concentrating nickel and cobalt. The ultramafic rock was also weathered during the

Jurrassic age to serpentinite. The area has been altered many times due to intense faulting.

This has occurred during; the Alpine orogeny (late-Jurassic/early-Cretaceous), end of the

Cretaceous, end of the Eocene, during the Oligocene, before Burdigalian, the Tortonian, the end

of the Upper Cretaceous and the end of the Pliocene. The Devolli deposit does not outcrop and

the conglomerate overburden over the ore body ranges in thickness between 150 to 300

meters. Figure 5 below is an extract from the geological map of Albania showing the Fe-Ni & Ni-

Si zones. The entire map is attached in Appendix A.(GBM, 2008; Arkaxhiu, et al.)

Figure 5 Extract of geological map of Albania showing Fe-Ni & Ni-Si zones

- 23 -

4.2 Nickel Laterites Nickel is commonly found in two different mineral groups: sulphides and laterites. Although nickel

laterites represent approximately 70% of the world land based resources, only 40% of the global

annual nickel production originates from these sources(Dalvi, et al., 2004). The current trend is that

nickel production from laterite sources has increased.

Nickel laterites are formed through the extended tropical weathering of ultramafic rocks such as

peridotite or serpentinite(Chan, 1998). Due to the chemical weathering process, laterite deposits

characteristically form in a layered ore profile. Different ore profiles then form depending on the

climate conditions. Figure 6 below shows the two main profiles generally associated with limonitic

ore deposits.

Figure 6 Effect of climate on typical nickel laterite profiles(Chan, 1998)

The Devolli deposit is typical of a humid equatorial climate. Thus, the ore containing body consists

of three separate zones; limonite, saprolite and a transition ore between the two. The separation of

the ore body into these three zones is extremely important because different processing methods

are more suited to different ore types.

4.2.1 Limonite zone

The limonite-lateritic zone is a high ferrous zone consisting of a variety of minerals. Limonite

consists of primarily goethite and may also contain hematite and maghemite. Other secondary

- 24 -

minerals may also be present in the ore body. Limonite, also referred to as ferrous nickels (FeNi),

will typically have grades of:

Fe > 40%

low silica

low magnesia

1.4% Ni

0.15% Co

Limonite ore is generally homogeneous in chemical and mineral composition. (Chan, 1998)

4.2.2 Saprolite zone

Saprolite ore, unlike limonite, tends to contain low amounts of iron. In contrast to the substantial

weathering characteristic of limonite ore, more of the parent rock within the saprolite zone remains

intact. In serpentinized profiles, such as found in the Devolli deposit, boulders of partially weathered

bed-rock are also common. Saprolite is also referred to as nickel silicates because of the high silica

content. Typical grades found in saprolite are:

Fe < 15%

High silica

High magnesia

2.4% Ni

0.05% Co

As can be seen, the saprolite ore tends to have higher nickel grades though the presence of partially-

weathered boulders means less chemical and mineral consistency throughout the ore zone.(Chan,

1998)

4.2.3 Transition zone

The transition zone is the ore plane that is present above the saprolite and below the limonite.

Typically, it will be enriched with magnesium, nickel and cobalt. The zone does not contain any

discrete Ni minerals. Instead, nickel is usually contained within secondary silicate or oxide

minerals(Chan, 1998). The boundaries for the intermediate zone are discussed in detail in the next

section of this report.

4.2.4 Serpentinite zone

The footwall of the ore zone in the Devolli deposit is serpentinite, a rock type that has formed due to

the weathering by sea water of ultramafic rocks. Asbestos is a mineral commonly found in

serpentinite rocks. Asbestos is the general term applied to the group of asbestiform silicate minerals

that are a sub-set of the serpentinite group(Department of Industry and Resource, 2001).

Fortunately, asbestos only forms under rare geological conditions in a crystallized fibrous form that

- 25 -

is a health hazard if inhaled as dust particles. Therefore, only some forms of the asbestos

mineralization are hazardous to underground workers. During mining operations, the presence and

mineralization of asbestos will need to be determined in the current workings and necessary control

measures implemented.

4.3 Modelling In the previous study(PWK Resources, 2010), the importance of differentiating between the three

ore bearing zones was not fully appreciated until near study completion. There was insufficient

time to remodel the entire ore body so tonnages of limonite and saprolite were not accurately

modelled. The re-estimating of the mineral zone resource is a key part of this project to facilitate a

more accurate mine and process design.

The modelling of the Devolli deposit was performed using the Gemcom Surpac software. The steps

involved to create the final block model were:

1. Importing drillhole database

2. Developing ore body limits

3. Ore body generation and ore zone separation

4. Grade estimate using geostatistics

Each of these steps above are described in greater detail below.

4.3.1 Drillhole Database

The drillhole database was supplied by European Nickel and consisted of the following four tables:

Collar

Survey

Geology

Assay

The collar table contained the eastings, northings and elevations for 228 drillholes; 143 for the

northern deposit Verniku West and 85 drillholes for the southern deposit Kapshtica. In total, there

were over 71,000m of drill holes.

The survey table reported the same bearing and dip for all of the drillholes. The dip of every drill

hole was -90 degrees or in other words, perfectly vertical. This would indicate that the deviation of

the drillholes had not been measured on site and that vertical has been assumed. This introduces a

potential quality assurance issue as drillholes can deviate from their vertical alignment considerably,

even in short holes. Therefore, to accurately model the 3D ore body and develop mine plan, the

drillholes will need to be surveyed at a later date. This may not be possible if the holes have

- 26 -

collapsed or if the collars were cemented. In this case, European Nickel will need to perform extra

drilling close to existing drillholes to accurately determine the location of the ore body.

In addition, the geology table, like the survey table, did not contain considerable amounts of

information. For each drillhole that intersected ore, only the depths for the conglomerate, ore

bearing and serpentines zones were provided. Unfortunately, the geology table did not distinguish

between the limonite, transition and saprolite zones.

The final table given in the drillhole database included assay results. For each ore zone, assay values

were given for nickel, cobalt and iron content. For some drillholes, assay values for chromium oxide,

silica, aluminium oxide, magnesia and calcium oxide. These were very sporadic though and could

not be used in the model.

4.3.2 Ore Body Limits

The drillhole database was loaded into Surpac and the first modelling task was the definition of the

ore body limits. This was undertaken in plan view based on whether a drillhole had an ore bearing

zone or not as shown in Figure 7 below.

Figure 7 Ore boundaries of Verniku West (left) and Kapshtica (right)

Verniku West is approximately 2400m in strike length and up to 600m across. Kapshitca is

approximately 1200m in both length and width.

4.3.3 Zone Separation

The separation of the nickel bearing zones is extremely important for the processing of nickel

laterites and the reasons for this are explained in the processing section of the report (Section 7). As

stated previously, the geology table in the drillhole database did not split the ore section into

- 27 -

separate zones. Consequently, using the assay values was the only available methodology to define

the limonite, transition and saprolite ore body limits.

The first method to achieve zone separation was to create a single ore body that included all three

zones. Kriging could then be applied on the nickel, cobalt and Fe values. The Fe content of a block

could then be used to determine the predominate mineralized zones it contained. Figure 8 below

shows the block model results for the northern deposit.

Figure 8 Block model showing mineral zones calculated using single ore body

Figure 8 above should show all three colours throughout the entire ore body. Instead, zones of

limonite and saprolite (red and blue respectively) form around individual boreholes and the entire

“middle ground” consists completely of the transition zone. This is clearly incorrect and modelling

the ore body with a single solid was not going to work. Three separate ore bodies, one for each of

the ore zones, needed to be created so that “hard” boundaries could be established between the

different mineral zones.

To create three separate ore bodies, the database was split into three different sections. Each ore

body was then created separately and Kriging was performed using each solid/database. When

splitting the database, two separate issues became apparent. The first was defining what should be

- 28 -

the Fe cut of grades for each zone. The literature gives typical values of limonite having greater than

40% Fe and saprolite having less than 15% Fe. If these Fe cut-offs were used, sections of a drill hole

that were 16% or 39% iron would be defined as transition zone. The question then is what to do if in

one borehole the Fe grade is 10% for 5m, 16% for 3m and then 8% for another 5m. This led to the

second issue; how to split the ore zone of a drillhole into three separate sections if iron-grade varies

between zones.

The solution to both issues was to use a “softer” boundary for separating the zones. Instead of 15%

and 40%, the transition zone was reduced to between 20% and 35%. To resolve the second

problem, the limonite zone was designated as the length at the top of the borehole that was entirely

over 35% Fe. Similarly, the saprolite zone was set as the length at the bottom of the borehole that

was entirely under 20%.

3D images of the ore body and its different zones are attached in Appendix B.

4.3.4 Grade Estimate

Grades of Ni, Co and Fe were estimated using the Kriging method. Each ore body and individual

zone was calculated independently. The results were verified using the simple Inverse Distance

Method (IDM). No major trends were found in any direction so all Kriging estimates were performed

using a uniaxial search.

4.4 Seismicity Albania is located in an active seismic zone. Probabilistic seismic hazard maps of Albania have been

built in recent years(Aliaj, et al., 2004). The Devolli project lies in the Ohrid-Korca zone (Zone OK

below in Figure 9) which has the highest rate density which is the number of annual earthquakes in

the area exceeding 6.0 on the Richter scale. Based on the probability model built, the largest

earthquake expected in the area is a magnitude 7.0. Such an event would be classified as a major

earthquake and would be large enough to have a destructive zone over 100km across.

In 2009, an earthquake of magnitude 5.5 occurred to the north of the project area near the capital

Tirana. More recently on the 28th May 2011, a 4.5 magnitude earthquake was measured in western

Greece (USGS Earthquakes, 2011).

Based on the Earthquake hazard map of Albania(European Nickel, 2010), the Devolli project is

located in a MSK-64 VII intensity zone (zone IX is the highest risk category). The design of

underground workings, material stockpiles and structures will need to be designed for this category.

- 29 -

Figure 9 Seismicity of Albania(Aliaj, et al., 2004)

4.5 Faulting Albania, being in a seismic zone, has many fault systems. Figure 13 below shows the major faults

throughout Albania. The Devolli project is located in the south-east corner of the country where

there are a considerable number of major faults running NE-SW and NW-SE.

- 30 -

Figure 10 Major faulting in Albania(Aliaj, 2007)

A fault analysis was undertaken on the Verniku West Kapshtica deposits. Faults were located by

assessing large vertical shifts in the ore zone between drill holes. North-south and east-west cross-

section of the deposit were created to perform the analysis and these are attached in Appendix C.

Figure 11 below is a plan view of Verniku West showing the main faults identified.

- 31 -

Figure 11 Plan of Verniku West - faults in red, possible faults in blue & vertical displacements in yellow (see Appendix C)

There are two major faults through the Verniku West deposit. Both a steeply dipping and are

perpendicular to each other (as shown above in Figure 11). However, it is important to note that it is

not possible to identify the exact location of the faulting due to the large space between the

drillholes. A potential fault was also identified across the southern portion of the deposit. More

drillhole data in the area is required before this fault can be confirmed.

Figure 12 below shows the faulting for the Kapshtica deposit.

- 32 -

Figure 12 Plan of Kapshtica - possible faults in blue and vertical displacements in yellow (see Appendix C)

4.6 Resource Statement The JORC code states the following for an “Indicated” resource classification:

“An ‘Indicated Mineral Resource’ is that part of a Mineral Resource for which tonnage,

densities, shape, physical characteristics, grade and mineral content can be estimated with a

reasonable level of confidence. It is based on exploration, sampling and testing information

gathered through appropriate techniques from locations such as outcrops, trenches, pits,

workings and drillholes. The locations are too widely or inappropriately spaced to confirm

geological and/or grade continuity but are spaced closely enough for continuity to be

assumed” (Joint Ore Reserves Committee (JORC), 2004)

The Devolli project is an ‘Indicated’ resource and cannot be classified ‘Measured’ resource for

several reasons. The first is the spacing of the drillholes. The average spacing of the drillholes is

80m and while this is sufficient to give an estimate of grades, they are too distantly spaced to

confirm grade continuity. This also applies to geological continuity, particularly in the fault zones.

Further reason for concern is the source of the drillhole data. More than half of the drillhole data is

historical derived from work undertaken by the Albanian Geological Survey over 4 decades ago. This

would indicate a potential quality assurance issue for these drillholes. The final reason for caution is

- 33 -

the lack of reliable survey data. Without accurate information on the deviation of the drillholes, the

ore body cannot be accurately modelled.

Table 3 below gives JORC compliant resource estimation for the Devolli Nickel Project.

Table 3 Resource Statement for Devolli Nickel Project with cut-of-grade of 0.5% Ni

Category Tonnage (Mt) Ni (%) Ni (t) Co (%) Fe (%)

Verniku West Indicated 24.8 1.12 278,000 0.04 20.57

Kapshtica Indicated 23.9 1.14 274,000 0.04 28.27

Total Indicated 48.7 1.13 552,000 0.04 24.35

The grade-tonnage curves for Verniku West and Kapshtica deposits are below in Figure 13 and Figure

14 respectively. Also, the mineral zone tonnage verse cut-of-grade curve for each deposit are

presented in Figure 15 and Figure 16.

Figure 13 Grade-tonnage curve for Verniku West deposit

- 34 -

Figure 14 Grade-tonnage curve for Kapshtica deposit

The grade-tonnage curves for both deposits are quite similar. Most of the Verniku West deposit

contains a nickel grade of 0.5% Ni or over. Kapshtica, on the other hand, is approximately 20%

smaller with a cut-of-grade of 0.5% Ni. With a cut-of-grade of 1.0% Ni, both deposits are around

60% of their original size. Once the cut-of-grade reaches 1.5% Ni, only 10% of each deposit is

minable. Based on these curves, it can be expected that the mine cut-of-grade will be between 0.5%

and 1.0% nickel.

More importantly for the selection of the processing method, is the tonnage and average grades of

the different ore zones; limonite, transition and saprolite. The grade tonnage curves for each

deposit has been split into the three zones and are shown below in Figure 15 and Figure 16.

Figure 15 Grade- tonnage curve for Verniku West by mineralized zones

- 35 -

Figure 16 Grade-tonnage curve for Kapshtica by mineralized zones

From Figure 15, approximately 60% of the Verniku West deposit is saprolite. The remaining 40% of

the deposit is split evenly between the limonite and transition ore. Between cut-of-grades 0% Ni

and 1.0% Ni, all three mineral zones have a similar average grade of around 1.2% Ni.

The Kapshtica deposit (Figure 16) contains similar amount of saprolite and limonite, around 40%

each. The remaining 20% is transition ore. Similar to the Verniku West deposit, the average nickel

grades between each of the zones is close in range between cut-of-grades of 0% and 1.0% nickel.

More grade-tonnage curves are attached in Appendix D.

- 36 -

5 Mining

The Devolli deposit consists of two separation ore bodies – Verniku West and Kapshtica. The mining

part of the project consists of all plant and equipment to exploit the mineral value from the deposit.

Mining is then followed by the raw handling system and then processing where the ore removed is

upgraded to a saleable product. In this section, the geotechnical properties of the ore and the

surrounding rocks are analysed; different mining options are discussed in brief and then ranked

based on suitability for the Devolli project; and finally the design details for the mining methods

selected are presented.

5.1 Geotechnical

A limited amount of geotechnical testing has been carried out by Germany company MonTec GmbH.

An existing adit system of the Bilishti mine was located in the Verniku West area and was re-opened

to acquire preliminary geotechnical data. Testing was conducted by the University of Bochum

however not all testing could be completed due to insufficient quantities of ore samples.

The total geotechnical data supplied by European Nickel for this study consisted of:

A sketch of the geological map of the Devolli area;

RQD values for 16 boreholes;

Photographs of core samples from drillhole AN-16; and

Laboratory test results on core samples from drillhole AN-61.

The laboratory tests properties measured were tensile, uniaxial compressive and triaxial compressive

strengths. From these results, estimates for strength parameters such as Mohr-Coulomb cohesion

and friction angle, slake durability, uniaxial and triaxial compressive strength, Young’s modulus and

Poisson’s ratio were calculated. Table 4 below gives a summary of some of the main findings.

Table 4 Sample of geotechnical results

Mineral Zone UCS (MPa) RQD RMR

Conglomerate 60 75% 41-60

Ferrous-Nickel 25 45% 21-60

Nickel-Silicates 33 45% 21-60

Serpentinite 21 60% 21-40

Additional geotechnical has not been performed since the previous feasibility study(PWK Resources,

2010). The recommendation made in this report is that more testing is required, particularly to

determine the ore strength, RQD and RMR. Testing should be performed on a variety of core

samples from both deposits so that a representative estimate of geotechnical parameters can be

calculated.

- 37 -

5.2 Mine Method Selection

There are many different methods that can be implemented when mining a deposit. Some examples

of mining methods that could be relevant to the Devolli project include open pit mining, longwall

mining, vertical crater retreat, sublevel stoping, room and pillar and cut-and-fill stoping.

Several different methods have been developed to assist engineering in selecting the optimum

mining method(Alpay, et al., 2008). Examples include the Nicholas numerical-based classification

system (Nicholas, 1981) and the selection chart by Morrison (Morrison, 1976). Several books also

give good explanations of different methods and where they are suitable (SME, 1992; Hustrulid,

2001).

The Nicholas method was used for initial analysis of the deposit and the calculation is found in

Appendix E. The top three methods selected by the Nicholas method were:

1. Open pit mining

2. Room and pillar mining

3. Longwall mining

The Nicholas method does not consider the depth of the deposit as part of its classification. For an

open pit, the stripping ratio would be over 25:1 in the northern deposit and over 30:1 in the

southern deposit. However, open pit mining is generally limited to a stripping ratio of 10:1(SME,

1992). Therefore, the open pit option can be excluded immediately.

One of the goals of this project was to look into the possibility of non-standard mining methods for

the exploitation of this deposit. One potential non-standard method is the leaching of the ore while

it is in-situ. There are two methods to achieve this:

In-situ leaching, and

Stope leaching

Thus, there are four different mine options that could be considered for the Devolli project.

5.3 Mine Design

5.3.1 Room and Pillar

Room-and-pillar is a common mining method used worldwide. The main concept of room and pillar

is to leave part of the ore body behind to support the roof. Despite the ore-loss for pillar support,

room and pillar is a popular method for low costs operations.

- 38 -

Figure 17 below shows the classic room and pillar mining method.

Figure 17 Classic room-and-pillar mining(Hustrulid, 2001)

Room-and-pillar operations are suited for flat-lying tabular ore bodies with a thin ore thickness

(usually less than 10 meters). However, as shown in Figure 17, thicker ore bodies can also be

excavated by working at two levels(Hustrulid, 2001). One consideration of implementing such a

design though is that the pillar in these operations become quite long and there is the risk of

buckling. Therefore, the ore needs to be sufficiently competent to resist buckling during extraction.

When a mine area is completed, the supporting pillars can be partially stripped to increase overall

ore recovery. As a result, the load carrying capacities of the pillars is reduced and the likelihood of

failure and hanging wall collapse increases. In areas where the overlying rock (mine roof) is

sufficiently competent rock, it may be possible to progressively recover entire pillars from the back

of the room to the front. Either of these higher extraction methods can only be used if subsidence is

allowed at the surface.

The Devolli deposit, particularly the southern part, is not flat lying. Thus, if this method was to be

applied successfully, a variation of the classical room-and-pillar would need to be used.

5.3.1.1 Variations of the Room-and-Pillar Method

There are two variations of the classical room and pillar that can be considered for the Devolli

project. The first is the post room-and-pillar mining method as shown in Figure 18.

- 39 -

Figure 18 Post room-and-pillar mining(Hustrulid, 2001)

The post room-and-pillar method uses backfill to lift the footwall and can be used for mining ore

bodies with dips up to 55 degrees(Hustrulid, 2001). This is different in ideology to a cut-and-fill

operation where backfill is used to support the hanging wall. In post room-and-pillar methods, the

backfill also supports the base of the pillar so that the risk of buckling is reduced. This also means

that thicker ore bodies can be exploited if the ore is not sufficiently competent. Since most of the

pillar is buried in the backfill, it cannot be recovered using the methods mentioned previously and

this ore is permanently lost.

The second variation of the classical room-and-pillar method that could be considered is the step-

room mining system (Figure 19).

Figure 19 Step-room mining(Hustrulid, 2001)

- 40 -

The step-room mining method is an alternative to the classical room-and-pillar method to extract

ore bodies dipping up to 30 degrees. Special cross-cut adits are developed as shown in Figure 19 so

that the mine vehicles are able to move to different levels.

5.3.1.2 Pillar Calculations

Preliminary pillar calculations were performed using the tributary area method as shown below in

Figure 20. Due to insufficient rock strength data, the Lunder and Palkanis (1997) formulas were used

to estimate the pillar strength (Brady, et al., 2004). The preferable method of estimating rock

strength is Salamon and Munro (1967) as it is more suited to softer rock conditions.

Figure 20 Tributary area calculation for pillars(Brady, et al., 2004)

The ore body changes depth as does the terrain above so not all of the rooms are at the same

depth. For each room, depth was measured and using this value, the extraction ratio was calculated.

The depths in the northern deposit ranged from 74m to 320m which equated to recoveries ranging

from 54% to over 80%. The southern deposit which is deeper has expected recoveries from less

than 20% in the deepest rooms to approximately 50% in the shallower ones. The recovery

calculations for all of the rooms are attached in Appendix F.

A standard height of 4m was used as the basis of the room height and the room width of 3m. This

gave an ideal height to width ratio within the room for support and was sufficient space for mine

vehicle access. The additional lifts were set at 2m each. This was to allow flexibility in the number of

lift whilst leaving sufficient space for the excavation and backfilling to be completed.

5.3.1.3 Room Modelling in Surpac

To develop a more accurate estimate of the Devolli reserve, software was written in Visual Basic for

Applications (VBA) in Microsoft Excel. In a spreadsheet form, mine details such as number of pillars

along and across, room and pillar dimensions and barrier dimensions are entered. 3D DTM files of

- 41 -

the pillars and the room space were automatically created for a variety of angles. Figure 21 below is

of a 12 by 8 pillar room inclined at 0 deg and 10 deg.

Figure 21 Room-and-pillar room automatically generated - Plan view (top-left), elevation (top right) and isometric view of pillars and the mined area (bottom left and right respectively)

The mined room created with the software is a single valid solid. This is used with the block model

to determine the grade and tonnage that can be exploited from this room. Appendix G shows the

input screen for creating the room-and-pillar Surpac solid.

5.3.1.4 Mine Modelling in Surpac

The extension of modelling a single room was to model the entire mine as a collection of rooms.

Figure 22 below shows the full room and pillar mine for Verniku West and Kapshtica.

- 42 -

Figure 22 Room and pillar design for Devolli project

Full-sized rooms are 125m across by 250m long. Barrier pillars of 8 times the room height are

between each room as recommend by Brady, et al. (2004). The mine is separated into rooms for

several reasons. The first is for safety. If the hanging wall starts to collapse in one room, there is the

possibility of the collapse propagating throughout the mine. The barrier pillars prevent this from

occurring room to room. Barrier pillars also provide extra support for the nearby room pillars. This

disadvantage of barrier pillars is the loss of ore.

Because all of the room and pillar dimensions were stored in Excel and the mines could be

automatically generated, this made it possible for the mine design to be optimized. The rooms were

initially set up spatially and given nominal inclination angles. The design was then varied by creating

slightly different combinations of changes in the elevation, inclination angle across and the

inclination angle along the room. The combination that gave the highest grade was selected and the

process started again. Once the optimum mine was found, an additional level was added. This is

because the mining method is post room-and-pillar and so the overall extraction height grows with

each layer of backfill. This was then also optimised. In the northern deposit, the three additional

raises were designed. In the southern deposit, up to 8 additional lifts were designed because of has

the thicker ore body. To create the grade-tonnage curves and find the optimum room position, over

5000 different possible mines were constructed, validated and assessed using the block model.

5.3.1.5 Grade-Tonnage Curves

There are two different grade tonnage curves presented. The first (Figure 23) is for an inclined

room-and-pillar design where backfill has not been used. The second grade tonnage curve in Figure

24 is for a post room-and-pillar mine. Additional grade tonnage curves split by deposit are attached

in Appendix H.

- 43 -

Figure 23 Grade-tonnage curve for room and pillar method

Figure 24 Grade-tonnage curve for post room-and-pillar

The reserve size using room-and-pillar is approximately 8Mt with an average grade of 0.7% nickel if

every room is mined. The reserve size using post room-and-pillar is over 14Mt, an increase of over 6

Mt or 75%. To increase the reserve size by 6Mt, the same amount of backfill is required as shown in

the figure. However, the increased reserve size also has a lower average grade with a reduction

from 0.7% nickel in room-and-pillar to 0.52% in post room-and-pillar. As the cut-of-grade increase,

the difference between the two methods reserve size and the cut-of-grade decreases.

- 44 -

5.3.2 Longwall

Longwall mining is a method of mineral extraction using a long face and is suited for flat-lying,

tabular deposits(Ozfirat, et al., 2005). To support the long face and the large distance between

supporting pillars, shields are used to support the hanging wall. Material is broken by a shearer or a

plough that traverses the face and feeds the material onto an apron or chain feeder. The material is

transported along the face to the main gate where it is transferred to the conveyor system. Figure

25 below is an example of an inclined long wall in coal mining.

Figure 25 Longwall mining(Hustrulid, 2001)

When the ore shearer completes its run, the entire longwall assembly “steps” forward so that new

ore can be extracted. The roof above the shearer is supported by hydraulic legs. These are linked

along the face and they push and pull each other forward to the new position. When this occurs, the

roof that was supported collapses.

The main advantages of longwall mining over a room-and-pillar operation are:

High recoveries because whole face is extracted

High levels of automation

The main disadvantage of longwall mining is the large capital investment required at the start of the

project.

The longwall mining method has primarily been used in coal. The Devolli project is a potential non-

coal application of longwall technology because of the poor geotechnical properties of the ore.

5.3.2.1 Variations of the longwall mining method

The standard longwall excavation is also known as Single Pass Longwall (SPL). Two alternative

designs are Multi-Slice Longwall (MSL) and Longwall Top Coal Caving (LTCC)(Ozfirat, et al., 2005).

- 45 -

The SPL method has been used for many years and shearers are reaching heights of over 4m. Some

of the design issues with constructing taller machines to extract thicker deposits are handling the

logistics of larger and heavy equipment, the support and stability of the footwall and face conditions.

Figure 26 below is an elevation sketch on a SPL operation.

Figure 26 Single Pass Longwall method – mine direction to the left of the page(Ozfirat, et al., 2005)

Multi-slice is a longwall method to extract thicker ore bodies. An example of the MSL method is

shown below in Figure 27.

Figure 27 Multi-Slice Longwall method - mine direction to the right of the page(Ozfirat, et al., 2005)

As shown in Figure 27, the ore panel is mined from top to bottom. In this example, there are two

panels of 2.8m thickness each being extracted and a planned third slice. A wire mesh is installed on

the hydraulic legs to prevent rocks falling through the shield. A thin layer of ore is left between

levels to act as an artificial roof.

The final variation of the longwall mining mentioned is longwall top coal caving and a sketch of the

process is shown below in Figure 28.

- 46 -

Figure 28 Longwall Top Coal Caving method

LTCC is similar to the SPL method in that the ore is mined in one pass. The difference between the

methods is that LTCC is equipped with a second feeder behind the support shields to gather caved

ore in the gob. The LTCC is a much simpler process than MSL because it only travels through the ore

once and there is no need for the wire mesh on the shears. It is reported that the MSL method is up

to twice as expensive as LTCC because of the large amount of labour required to fix and maintain the

wire mesh over the shields(Ozfirat, et al., 2005).

The single pass longwall will be used on the Devolli project with feasibility calculated for 2m, 3m and

4m extraction heights. The LTCC will also be costed for Devolli project will extraction heights of 5m,

6m, 7m and 8m.

The cutting tool on the reciprocating travel head can either be a shearer or a plow. Table 5 below

shows the major differences between the two excavation tools.

Table 5 Shearer and plow properties(Myszkowski, et al., 2010)

The Devolli deposit is classified as a thick ore body when considering a longwall system. For this

reason, the shearer will have to be used so that the most ore is regained. Table above outlines some

important design criteria such as maximum angles and how well the longwall can track the ore body.

- 47 -

5.3.2.2 Panel calculations

The basic layout of a longwall panel is shown below in Figure 29.

Figure 29 Layout of longwall panel in plan

The adit running vertically in the drawing is the main access adit. Material and men enter the

longwall workings through here. It is also along this adit that other panels like this one are

connected. The U-shaped adit around the longwall mining area is constructed first. Structural

support in this area is achieved using steel ribs spaced at 1.5m. The longwall is set-up in the adit first

and then the steel supports are gradually replaced with the longwall shields(Chase, et al., 2006).

Barrier pillars are required between longwall panels for structural support(Brady, et al., 2004). The

barrier pillars shown here are only half-barriers since the panel above and below will also have the

same barrier.

5.3.2.3 Longwall panel modelling in Surpac

Similar to the room-and-pillar design, software was written in Visual Basic for Applications (VBA) in

Microsoft Excel for the automatic creation of long wall panels. Primary dimensions such as adit

height and width, extraction height, longwall panel length and panel width are entered into the

spreadsheet. Angles of extractions and the longwall angles can be adjusted and Surpac 3D dtm files

of the longwall panel will be created. Figure 30 below gives an example of a longwall that has been

automatically created using the code written for this project.

Figure 30 Longwall mine panels created. ±10 deg extraction angle (left) and 10 & 20 deg longwall angle (right)

- 48 -

The longwall model is created as five valid solids as follows:

The longwall mine volume (light blue in Figure 29)

A combined solid of the main access and the U-shaped adits around the longwall mine

volume (dark blue in Figure 29)

A barrier pillar around the U-shaped adits (all barrier pillars are brown in Figure 29)

A barrier pillar along the access adit on the other side of the longwall

A barrier pillar between the access adit and the longwall mine volume. This barrier pillar is

required so that the access adit is structurally stable and can be kept open for the next

panel.

The longwall mine volume can have a different height to the adits so that different sized longwall

machines can be modelled. By using the block model and the longwall mine volume solid, the grade

and tonnage of the ore contained can be calculated. Appendix G shows the input screen for creating

longwall Surpac models from Excel.

5.3.2.4 Longwall mine modelling in Surpac

The longwall panel builder tool described above was expanded so that the entire mine could be

created using Excel. The longwall panel design for Verniku West and Kapshtica are shown below in

Figure 31.

Figure 31 Longwall designs for Verniku West (left and centre) and Kapshtica (right)

There are two different designs proposed for the Verniku West; an approximately N-S aligned

longwall and another design perpendicular in an approximate E-W direction. Only the longwall mine

volumes have been shown for clarity.

- 49 -

The longwall panels are 100m wide and this was chosen for ease of design. The length of the

longwall machine is 60m after space required for the adits and the barrier pillars as recommend by

Brady (2004) is accounted for. Panels range from 200m to 600m in length.

Because all of the longwall panel dimensions were stored in Excel and the mines could be

automatically generated, this made it possible for the mine design to be optimized. The panel were

initially set up spatially and given nominal inclination angles manually. The design was then varied

by creating slightly different combinations of changes in the elevation, inclination angle of

excavation and the inclination angle of the longwall miner. The combination that gave the highest

grade was selected and the process started again. Once the optimum mine was found, the thickness

of extraction was increased and the process re-started. Over 8000 different possible mines were

constructed in order to find the optimum solution.

5.3.2.5 Grade-tonnage curves

The grade-tonnage curves for longwall mining are shown below in Figure 32 and Figure 33. There

are two sets of curves because there were two different mine designs for the northern deposit; a

north-south (NS) design and an east-west (EW) design.

Figure 32 Grade-tonnage curve for longwall mining (northern deposit with north-south oriented longwall panels)

The tonnage difference between the various longwall size options has a large range of reserve sizes

with no cut-of-grade as would be expected. As the cut-of-grade increase, the difference between

the options decreases. After a cut-of-grade of 1.0% Ni, all of the options are within a 1Mt bracket.

The average nickel grades with a low cut-of-grade and a high cut-of-grade are clearly separated. For

- 50 -

cut-of-grades between 0.5% Ni and 1.2% Ni, the average grade between the options is mixed and it

is not clear which option has the highest or lowest average grade.

Figure 33 Grade-tonnage curve for longwall mining (northern deposit with east-west oriented longwall panels)

The greatest difference between the two grade-tonnage curves is the reserve size. An 8m high

longwall extraction with the northern deposit designed orientating north-south has a reserve size of

approximately 19Mt (no cut-off-grade). The equivalent reserve size if the longwall panels are

designed east-west is only 15Mt; a different of 4Mt of ore. The main reason for this is the

limitations of the extraction angle as specified by Bucyrus (Table 5 above). The northern deposit has

a dip of up to 30 degrees along the edges and this is too steep to be mined with the longwall mining

system selected.

5.3.3 Stope Leaching

Stope leaching is the in-situ leaching of the ore from underground workings. There have been some

trials in the copper industry to use stope leaching however there are no currently operating facilities

using this method as their primary extraction technique. Stope leaching has not been tested in

either a sulphide or laterite nickel deposit so there is no historical cases to draw upon in the design

of this system. The use of stope leaching in the Devolli project as the main extraction method

constitutes a significant technical risk to the success of the project.

The mining method has a similar design to conventional stoping method. Cross-cuts are constructed

above and below the stope being mined. In conventional stope mining, the stope is blasted and

mucked from the base adit. Stope leaching, the under-cut is lined with concrete and a channel is

- 51 -

constructed along the floor for the leach solution to flow through. The roof is then blasted and the

rock caved into the undercut. Injection wells are drilled in the blasted zone from adit above the

stope and leach solution is pumped through the stope where it is collected in the undercut and

drains to a central collection point. The blasting needs to be sufficient so that the ore fragments and

the leach solution can extract the nickel. The success of blasting is dependent on the blast design

and the geotechnical properties of the ore. The processing for a stope leaching facility is discussed

in more detail in the processing section of this report (Section 7.6).

Stope leaching is not recommended as the primary mine method for the Devolli project. Where

stope leaching may be useful is in the south of the Kapshtica deposit where the ore shape and depth

of the deposit makes room and pillar or longwall mining extremely difficult and associated

recoveries very low. Stope leaching can also be used in locations that are difficult to access via

traditional methods.

5.3.4 In-situ Leaching

In-situ leaching is the leaching of valuable minerals from in-situ ore from the surface. There is no

such mining involved with in-situ leaching; only drilling of injection and recovery wells. In-situ

leaching is discussed in more detail in the processing section of this report (Section 7.5).

5.4 Mine Equipment

5.4.1 Room-and-pillar mining

The room-and-pillar mining will be performed using a drill, blast and muck system. LHDs will muck

the ore from the room and will either transport the material to a conveyor or to underground rear-

dump trucks. If backfill is being used, LHDs will also be used to place and compact the fill.

Development drives will also be constructed using the same system. The number and size of the

jumbos, LHDs and rear dump trucks has been automatically calculated in the cost model as

described below.

5.4.2 Longwall mining

Longwall mining will be performed using a single shearer longwall miner. For extraction heights up

to 4m, a single-pass longwall method is used and the standard longwall machine will be employed.

When extraction over 4m is required, a LTCC system is required. Although designed originally for

coal, it is anticipated that the LTCC will work with the nickel laterite in Devolli. This should be

discussed and confirmed with the OEM.

- 52 -

5.5 Mine Scheduling

Both the longwall and room-and-pillar methods selected have been designed to detailing the sizes

and shapes of panels and rooms respectively. The longwall mining system has only one extraction

unit so panels will be mined progressively one at a time. The panels will be mined starting with the

Verniku West deposit with panels extracted in order from south to north followed by the Kapshtica

deposit with the panels removed from east to west. Because there is only one unit, selective mining

is not possible and the longwall system can only produce a single mixed mine project.

Room-and-pillar mining is more flexible that longwall mining and allows selective mining to be

performed. Both the north and south deposits will be mined at the same time extracting rooms

outwards from the based on the access adit. Anywhere between 3 and 6 rooms may be operational

at one time depending on the number of products and the number of haulage systems to the

surface. If backfill is being used, the southern deposit will be need to be extracted earlier since most

of the backfill is required there.

5.6 Cost Modelling

A cost model was constructed to cost each of the different mining options. In total, there are seven

different mining scenarios as described below in Table 6.

Table 6 Mining cost model options

Code Description Backfill? Number of Products

No of transport systems to surface

1RP1 Room-and pillar-mining N 1 1

1PP1 Post room-and-pillar mining Y 1 1

1LW1 Longwall mining N 1 1

2RP1 Room-and pillar-mining N 2 1

2PP1 Post room-and-pillar mining Y 2 1

2RP2 Room-and pillar-mining N 2 2

2PP2 Post room-and-pillar mining y 2 2

The cost for each options are constructed as follows:

Number of products

Two letter code for mining options

o RP – room-and-pillar

o PP – Post room-and-pillar

o LW – longwall

Number of transportation systems to the surface

- 53 -

The number of transportation systems is an important parameter because it defines how the

different mine products are sent to the surface. If there are two mine products but only one

transportation system, the mine produces one product for a number of shifts and then the other

product for a specific period of time. This affects the efficiency of the underground operation.

To cost each of the options, the mine was broken into main cost categories. Each cost category was

assigned a letter code as follows:

RDT – read-dump trucks

LHD – load, haul and dump trucks

DRL – drill rigs and jumbos

LWM – longwall machine and accessories

CVS – conveyors

UTE – utility vehicles

DMP – dump and backfill

VNT – ventilation

Each cost category has two separated sheets in the cost model. This first sheet, named with the cost

category code, contained the calculations and CAPEX and OPEX estimate for all the mine options.

The second sheet (named by the cost category code and the letter “i” for inputs) contained all of the

input information relating to that cost category.

The cost model is attached in full in Appendix I.

- 54 -

6 Raw Ore Handling

The raw handling system consists of the equipment, plant and personnel to transport and size

primary raw ore from the run-of-mine to the processing plant area.

The purpose of the raw ore handling system is to

Transport ore from the run-of-mine underground to the process plant

Crush ore to appropriate size for further handling and processing or sale

Provide buffer between independent systems using stockpiles to account for variations in

availability and production rates

6.1 Options

There are numerous options to achieve the above criteria. This includes the method of

transportation to surface, the number of product streams, use of a mine and/or sized stockpile and

shifting to an alternative transportation method mid-process. Figure 34 below is an example of one

of the potential options.

Figure 34 Example of a raw material handling option

The raw product transportation option, shown in Figure 34 above, has the following features:

Two mine adits with one containing the underground to surface conveyor

A mine stockpile to separate the mine production from the crushing circuit

An overland conveyor to the crushing circuit and then sized stockpile

Dump truck stacking onto the heap leach pad

- 55 -

In total, there are 32 different transportation options when considering number of products and

processing options. Each option has a unique code. The example option in Figure 34 has the code

“1Phl2A CVmsssTR”. The code gives many details about the option and is constructed as follow:

The first 6 digits is made up by:

o Number of products (1 or 2) + “P”

o Two letter code for processing option

“no” – Null processing

“hl” – heap leach processing

o Number of Adits (1 to 3) + “A”

The second part of the code is open length and contains the following codes in order of

when they appear in the process flow

o “CV” – conveyor transportation

o “TR” – trucks

o “ms” – mine stockpile

o “ss” – sized stockpile

Using the system described, the code in Figure 34 “1Phl2A CVmsssTR” can then be read as the

option with 1 product using heap leaching and 2 adits – conveyors with mine and sized stockpiles

followed by trucks.

The process flow diagram (PFD) for each of these options, an index of the codes and key of symbols

used is found in Appendix J. Figure 35 below gives an example on how the different options are

connected.

- 56 -

Figure 35 Raw material handling options

The transportation of the ore can be broken into several distinct sub-areas:

Run-of-mine (ROM)

Transportation to surface

Mine stockpiles (optional)

Surface transportation

Material sizing (either a sizing plant or mobile sizing equipment)

Sized stockpiles (optional) and heap leach pad stockpiles.

Each of these sub-areas are described and their purpose explained in more detail below.

6.1.1 Run-of-Mine (ROM)

The ROM is the connection point between the mine and the ore transportation system. Its location

and construction depends on the mining method, mode of underground transportation and/or

mode of surface transportation.

Run-of-mine

LOCATION

Underground

Mobile Sizing Equipment

Near Mine

Access

Between

Mine Access

& Processing

Plant

Conveyor/s

Conveyor/s

Haul Trucks

Haul Trucks

Processing

Plant Dump Stacker/s

Conveyor/s

Haul Trucks

Intermediate Raw Stockpile

Sizing Plant

Sized Stockpile

Conveyor/s

Conveyor/s

RAW HANDLING OPTIONS

- 57 -

In the case of longwall mining with conveyors to the surface, there is no ROM as material is

transported directly from the cutting face to the surface. For this study though, the ROM is

considered to the loading point of the underground to surface conveyor/s.

For other mining methods where transport through the mine is achieved using dump trucks and

then loaded onto conveyors for transportation to the surface, the ROM is the dump point. At this

location, single-dimension primary crushing is usually done and the material is loaded onto the

conveyors.

The ROM of a truck-only mine is where loading occurs. For the cost estimate, only infrastructure to

the base of the adit has been included.

6.1.2 Transportation to Surface and Surface Transportation

There are two transportation methods considered in this study for bringing material from

underground to the surface. These are troughed conveyors and underground haul trucks.

The option of a single mine product or two mine products should be considered. For a two product

mine, the troughed conveyors can be either organized as two separate systems or as a single system

with shift-based product supply. The use of two separate systems to the surface requires three

adits; two conveyor adits and one main access. For a single mine product or shift-based

transportation of two products, a single conveyor system with two adits is required.

Transportation once on the surface can be achieved by:

continuing the use of the underground haul trucks;

transferring material onto surface conveyors either via transfer chute or stockpiles

transferring to surface haul trucks using stockpiles

6.1.3 Mine Stockpile (optional)

The mine stockpile is a temporary ore storage site located in close vicinity to the access point of the

mine. The mine stockpile provides a buffer between the mine and the sizing and processing plant

hence delays or stoppages in the mine or the plant do not impact on the operation of the other.

Conveyors are continuous systems with a fixed maximum capacity. Different mining methods with

identical average capacities can have vastly different peak capacities. For instance, longwall mining

can produce peak loading capacities at twice the average rate. The use of a mine stockpile

smoothes out these peak loads. Without the mine stockpile, the conveyors and sizing equipment

after the stockpile need to be designed large enough to support the peak load from the mine. By

- 58 -

using a mine stockpile, the equipment only needs to be sized for average loading conditions and is

smaller and therefore less expensive.

If the mine utilises underground haul trucks, a mine stockpile is beneficial if there is a considerable

distance between the portal and the processing plant. In this way, underground haul trucks can

operate almost exclusively underground and surface vehicles can be used for the remaining

transportation.

Material can be reclaimed from the raw stockpile using chain feeders onto conveyors or truck and

shovel.

6.1.4 Material Sizing

Part of the raw handling system requires the sizing of ore. The output size requirement depends on

the mineral processing method and the ease of material handling. For example, a high pressure acid

leaching (HPAL) plant requires the ore to be ground before being fed into the autoclaves. Fine

particles are extremely difficult to handle, specifically in stockpiling and reclaiming, so the ore will be

sized to approximately 50mm. Heap leaching, on the other hand, requires a stockpile feed size of

8mm. In the conveyor system, the ore is sized using between one and three transfer stations

containing crushers and screening equipment. For the haul truck system, sizing is performed by

mobile sizing units.

6.1.5 Sized Stockpile (optional)

The sized stockpile is located directly after the sizing circuit. For heap leaching, a sized stockpile is a

buffer between the sizing equipment and the stacking equipment. Thus, the downtime of one set of

equipment will not impact on the other set.

Automated stacking equipment for the heap leach pad represents a large capital investment.

Instead of using these, the cheaper capital option of trucks can be utilized. A sized stockpile is then

required in order that the trucks can be loaded by front-end loaders.

6.1.6 Heap Leach Pad Stacking

The final stage in the raw ore material handling process is stacking at the process plant. This can be

achieved in either of two ways; using large automated stacking equipment or using trucks and

dozers. The heap leach stockpile, depending on the mineral type, needs to be extremely large as ore

may need to be leached for up to 300 days. To use automated stacking equipment, the heap leach

pad is two modules wide with a centre line conveyor. The stacking machine travels along one side of

the conveyor, turns at the end and then stacks the opposite side. Sufficient space is required for the

stacker turnaround at each end of the pad.

- 59 -

6.2 Cost Modelling

A cost model was constructed to individually cost each option in order to determine the optimum

transportation system. There are several different cost elements in a materials handling system and

for the purpose of this study, the cost model was split into a set of cost categories. Also included in

this cost model was the costing for processing because of the close link between the two systems.

Each cost category was given a two or three letter code as follows:

AD - Adits

HR - Haul Roads

CV - Conveyors

TS - Transfer Stations

MSR - Mobile Sizing Rigs

SP - Stockpiles

ST - Stackers

HV - Heavy Vehicles

UG – Underground materials handling

RT – road transportation

HL - Heap Leaching

PP - PLS Precipitation Plant

P&P - Pumping and Pipes

The cost model was built in Microsoft Excel. Each different cost category consisted of two sheets

(excluding the precipitation plant – the reason for this is explained later). The first sheet is named by

the category code (e.g. “CV”) and the second sheet is named by the category code with the letter “i”

(e.g. “CVi”). Figure 36 below is a screen shot of the model and shows the different sheets.

Figure 36 Cost model sheets

The first sheet contains all size and cost calculations. Each transportation option has its own column

and the calculation proceeds down the sheet. The CAPEX and OPEX of major plant or equipment

items in that cost category are summarised at the end of the sheet (see Figure 37 below).

- 60 -

Figure 37 Cost model example showing CAPEX and OPEX totals

As seen in Figure 37, each row contains an explanation field which usually contains information such

as the corresponding sheet containing input data or the formula for the calculation. Each option has

a code designated to it.

The second sheet contains all of the input information for that category. This included sizes,

assumptions, CAPEX and OPEX information and any other miscellaneous information required.

The “Participation Plant” required an extra sheet named “PPc” – short for chemistry. This sheet

contains process formulas that calculate the process flow and recoveries.

The cost model is attached in full in Appendix I.

- 61 -

7 Processing

Processing follows from the raw handling system and includes all plant and equipment up to product

backing and waste/tailings handling. In this section, the different processing options for nickel

laterites are discussed in brief and are then ranked based on suitability for the Devolli project. The

metallurgy and test work to date have also analysed and the design details for the chosen processing

method is detailed.

7.1 Options

In the late 1940’s, the process research department of Inco gathered different nickel laterite

samples from ten countries worldwide and tested various pyro-metallurgical and hydro-metallurgical

processing techniques on them. The result of the research was that no one process is suitable for all

laterite ore types(Chan, 1998).

Thus, there are a number of varying process methods which are individually suited to different nickel

laterite ore profiles. The different process methods are(Dalvi, et al., 2004):

Direct transportation of ore to another facility (null processing)

Ferronickel and matte smelting (pyro-metallurgical)

High pressure acid leaching (HPAL) (hydrometallurgical)

Caron process (hydrometallurgical)

Enhanced pressure acid leaches (EPAL) (hydrometallurgical)

Atmospheric tank leaching (ATL) (hydrometallurgical)

Heap leaching (HL) (hydrometallurgical)

In-situ/stope leaching(hydrometallurgical)

The different processing options and their suitability for use in the Devolli project are examined

below.

7.1.1 Direct Transportation of Ore

Direct transportation of the ore to another facility is the simplest method of processing. The ore,

once mined, is crushed and sized to a specified limit and then transported via road trucks to the

smelter.

The advantages of this method are:

Minimum on-site dump since all of the ore is transported to another facility

Low CAPEX since expensive processing and stockyard plants are not required

Little technical risk

- 62 -

The disadvantages of this method are:

Heavily reduced revenue per tonne of ore;

As there is no reliable rail network in the project vicinity, all ore would need to be

transported by road trucks. This would make the processing costs dependent on the price of

fuel; and

A poor corporate carbon footprint from running a large fleet of road trucks

For the Devolli project, the main factor that makes this option especially difficult is the lack of good

quality transportation infrastructure and the distance to the nearest nickel smelting plants. There is

no reliable rail system and the closest port is approximately 200km away. The nearest smelters are

in Kosovo and Greece and are both over 300km by road. Additionally, the road infrastructure

around the Devolli area is not of high quality and therefore time spent via transportation by road

trucks will be slow.

The null processing option should not be considered a complete solution for the Devolli project.

Mindoro Resources Ltd, another company looking to develop a nickel laterite mine, is considering

the option of direct shipping of ore while the HPAL plant is being constructed and

commissioned(Mindoro Resources Ltd., 2010). A similar process should be considered for the

Devolli project so that revenue could be sought while the plant is being constructed. This option is

particularly attractive and should be investigated in more depth, in particular if difficulty is

experienced in generating start-up capital.

7.1.2 Ferronickel and matte smelting

Ferronickel and matte smelting use a flow sheet involving drying, calcining and electric furnace

smelting. This process favours low-Fe, high-Ni saprolite ores (Wedderburn, 2009). The process is

very energy intensive since all moisture needs to be removed and the ore must be melted to form a

slag. The difference between matte smelting and ferronickel processing is that sulphur is added to

the feed in matte smelting to form nickel and iron sulphides. Recoveries are very good with 90-95%

of nickel and approximately 50% of cobalt being recovered (Dalvi, et al., 2004).

Advantages of ferronickel and matte smelting are:

produces final product sellable directly to stainless steel manufacturers

high recoveries

Disadvantages of ferronickel and matte smelting are:

restricts the amount of usable Devolli ore

- 63 -

high feed grades required

very energy intensive process

heavy capital investment required

This option has been discounted because the Devolli ore deposit is not suitable in terms of ore type

and average grades for this process and is not large enough to justify constructing a new plant. A

very energy intensive process is also a major project risk considering the frequency of electrical

black-outs in the project area.

7.1.3 Caron Process

The Caron process is essentially a hybrid process that is part hydrometallurgical and part pyro-

metallurgical. It is also known as ammonia leaching and was developed in the 1920’s by Professor

Caron of TU Delft, Netherlands. The process is suitable to process a mixture of both saprolite and

limonite ores, though recoveries do increase with a greater proportion of saprolite (Dalvi, et al.,

2004). Typical recoveries are approximately 80% for nickel and 55% for cobalt (King, 2005).

The advantages of the Caron Process are:

temperatures are lower than required for ferronickel smelting or HPAL so less energy

intensive

can process both saprolite and limonite ores

can tolerate higher Mg values than pressure acid leaching processes.

The disadvantages of the Caron Process are:

still energy intensive

lower recoveries

high reagent costs

The Caron Process was originally developed to process limonitic type ores. However, high energy

demands and low recoveries have restricted the use of the process globally. Internationally, there

are no plans to create a new plant of this type (Wedderburn, 2009). This method of processing has

also been surpassed by other hydro-metallurgical processes in terms of recoveries, capital costs and

operating costs. Therefore, this option should not be considered for the Devolli deposit.

7.1.4 High Pressure Acid Leaching (HPAL)

High pressure acid leaching (HPAL) has been significant researches and refined over the past decade

(King, 2005). Generally, HPAL requires a feed of predominately limonite feed although some

saprolite is acceptable (Dalvi, et al., 2004).

- 64 -

The advantages of HPAL are:

high recoveries;

can produce intermediate hydroxide products; and

similar operating costs compared with atmospheric leaching and heap leaching

(Wedderburn, 2009).

The disadvantages of HPAL are:

higher capital expenditure compared with atmospheric leaching and heap (Wedderburn,

2009);

suitable for low amounts of saprolite in feed. This greatly reduces the amount of Devolli ore

that can be processed;

still a high technical risk since other projects have failed to achieve design capacities and

recoveries (King, 2005);

higher energy requirements compared with atmospheric leaching and heap leaching for

heating and pressure; and

Tailing dump required.

The greatest disadvantage of this option is the large technical risk involved. This processing option

has been implemented at numerous nickel laterite sites and plants have failed to perform inline with

initial predictions.

There are other disadvantages of this process such as high energy requirements and that it can only

treat a fraction of the deposit. It is for these reasons high pressure acid leaching is not as an

attractive solution compared to alternatives for the Devolli project.

7.1.5 Enhanced Pressure Acid Leaching (EPAL)

Enhanced pressure acid leaching (EPAL) as the name suggest is an improvement on the high pressure

acid leaching process. The process has an additional stage where the output of the HPAL system is

re-leached at atmospheric pressure to process further the saprolite in the feed(Dalvi, et al., 2004).

The advantages of EPAL are:

able to process both saprolite and limonite ores

greater recoveries from a mixed feed

able to produce a mixed hydroxide product

The disadvantages of EPAL are:

- 65 -

higher capital cost than HPAL

much higher acid consumption than HPAL and therefore higher operating cost

still a high technical risk since other projects have failed to achieve design capacities and

recoveries

tailing dump required

high energy consumption

Enhanced pressure acid leaching is an attractive option since it can process both saprolite and

limonite ores. However, this advantage is countered by the high capital cost and higher acid

consumption when compared with HPAL. This process, like HPAL, consumes a large amount of

energy which essentially discounts it as a processing option considering the power reliability in

Albania. BHP Billiton, the largest mining company in the world, spent millions of the dollars on its

EPAL plant on the Ravensthorpe Nickel Project(Sharples, 2008). Despite the large investment, BHP

Billiton sold the project to First Quantum for a reduced price due to poor nickel prices and inability

to fully exploit the nickel laterite deposit(WA Today, 2009).

Although EPAL is able to process saprolite and limonite ores, the high acid consumption and large

technical risk removes this process as an option for the Devolli project.

7.1.6 Atmospheric Tank Leaching (ATL)

Atmospheric tank leaching (ATL) is a process that does not require high pressures to be generated as

in HPAL or EPAL. Also known as atmosphere pressure acid leaching (APAL) or atmospheric leaching

(AL), leaching is performed in open air tanks on milled ore feed.

The advantages of atmospheric leaching are:

able to process both limonite and saprolite

process is robust

approximately 80% of capital cost required for HPAL(Wedderburn, 2009)

similar operating costs to HPAL

The disadvantages of atmospheric leaching are:

mineralogy dependent requiring blending of limonite and saprolite

sensitive to iron (Fe) chemistry

high acid consumption

grinding of the ore is required

tailings dump is required

- 66 -

Atmospheric leaching is suitable for the Devolli ore deposit. It can process both limonite and

saprolite ore and is not a heavy energy consuming process.

7.1.7 Heap Leaching

Heap leaching was originally limited to only saprolite ores (Dalvi, et al., 2004) but further test work

has suggested that it is suitable to process both saprolite and limonite ores (GBM, 2008).

The advantages of heap leaching are:

able to process both limonite and saprolite(GBM, 2008)

process far less complex than HPAL or AL (Wedderburn, 2009)

lower capital intensity

does not require grinding of the ore

European Nickel have expertise and experience with heap leaching technology

The disadvantages of heap leaching are:

acid consumption varies with mineralogy (GBM, 2008)

heap permeability is critical (Wedderburn, 2009)

it is sensitive to iron chemistry

Heap leaching is suitable for the Devolli ore deposit. There are numerous advantages to using this

system but the most critical reasons are it can process both limonite and saprolite, it is a simple and

robust process and European Nickel have technical experience with this method.

7.1.8 In-situ/Stope Leaching

In-situ leaching is the leaching of minerals from in-situ ore from the surface. Stope leaching,

similarly to in-situ leaching, is the leaching of in-situ ore. The difference between the two methods

is stope leaching is performed from adits above and/or below the ore body underground as opposed

to from the surface. Neither of these options were considered in the previous study(PWK

Resources, 2010). From a processing perspective, these options are most closely linked with heap

leaching. All of the other processing methods require the grinding of the ore to be performed

before further processing. The high acid leach solution is pumped repeatedly through the ore body

until the acid is consumed. The leach solution would then be further processed and the nickel

extracted in a precipitation plant like the one used for heap leaching.

The main advantages of in-situ/stope leaching are:

leach pad not required

- 67 -

removes the cost of transporting ore to surface and sizing it

only small waste dump required (iron solids from the precipitation plant)

The main disadvantages of this option are:

high technical risk – this method has not been used with nickel laterites before

unknown recoveries

Environmentally, there are positive and negative aspects to this method. Heap leaching pads

require large amounts of sulphuric acid on the surface. This creates an environmental risk of acid

solution entering waterways or the water table if the protection measures are not adequate. In-situ

leaching does not present this particular risk since all leaching is performed underground, however,

it does potentially pose other environmental risks. When in-situ leaching (from the surface) is

utilized, it is critical for there to be an impermeable layer below the ore body and preferably above

as well(Bartlett, 1992). The serpentinite has low permeability because of its wax-like texture but

environmental risks are greater being in a highly seismic area where there are many fractures

through which the leach solution can escape. Perhaps of greater concern than the acid, are the

heavy minerals that are dissolved in the solution. Stope leaching provides greater control to avert

potential losses primarily because the works are in the vicinity of the ore zone being leached,

however, there is still a risk of solution loss to the environment.

7.2 Method Selection

Based on the descriptions above and the comparative difference between the advantages and

disadvantages of each method, the preferential processing methods of mined ore are ranked as

follows:

1. Heap Leaching (HL)

2. Atmospheric Tank Leaching (ATL)

3. Enhanced Pressure Acid Leaching (EPAL)

4. High Pressure Acid Leaching (HPAL)

All four of these options are suitable to process the Devolli ore deposit. HPAL ranked last since it can

only process small amounts of saprolite and EPAL ranked under ATL and HL because of its high

energy requirements.

HL and ATL are both suitable for the Devolli deposit and are not energy intensive. HL ranked higher

than ATL for two main reasons. The first is that heap leaching does not require a tailings dump since

wastes are of an aggregate size and can be dumped as a solid. The second is that European Nickel

- 68 -

has much more experience in heap leaching and thus this option presents a much smaller technical

risk.

This is the same recommendation that was made during the previous feasibility study(PWK

Resources, 2010). A potential option that was suggested in that report, but never fully investigated,

was the potential for using dual processing methods. The primary driver behind this suggestion was

that heap leaching and atmospheric tank leaching processes prefer saprolite feed. These could be

coupled with a complimenting plant for a limonite feed such as high pressure acid leaching.

The dual processing methods are being considered at another deposit in Indonesia (Mindoro

Resources Ltd., 2010). The main advantages of using two methods are:

Higher recoveries

Smaller plant size

The main disadvantages of using two processing methods are:

Greater degree of difficulty when mining as two different ores have to be processed

separately

Larger raw ore stockpiles required

Higher technical risk caused by optimising two different processes. This is particularly an

issue in Albania where foreseen difficulties acquiring skilled labour exists

The use of two different methods should not be considered for the Devolli project. As shown in the

previous study (PWK Resources, 2010) the project is already marginal and to implement two

different processing methods introduces additional technical and financial risks.

What was not considered in the previous study was the using two heaps leach pads; one for quick

leach saprolite ore and another for the long leaching of mixed saprolite-limonite ore.

The advantages of this option are:

Smaller heap leach pad (lower CAPEX)

Less acid consumption

Single precipitation plant

Shared high acid and low acid pregnant leach solution dams (HA PLS Dam & LA PLS Dam)

The disadvantages of this option are:

More difficult mining condition as products need to be separated

- 69 -

More complex raw ore handling system for two products

In addition to the single and dual heap leach option, the in-situ and stope leaching method will be

considered. There is a large associated risk with these methods but if the design is significantly less

expensive and a high NPV is achieved with even low recoveries, further research into this method

would be recommended.

Based on literature research and conclusions made, the following four processing designs were

investigated:

Heap leaching of single product

Heap leaching of two products on separate pads

In-situ leaching

Stope leaching

7.3 Metallurgy and Test work

The Devolli project has two primary ore types that are investigated. The first is a nickel silicate (NiSi)

ore and the second is ferronickel (FeNi). As detailed in the geology section of this report (Section ),

nickel silicates are found in the mineral saprolite and are characterised by low Fe content (<15%) and

relatively high magnesium (>5%). Saprolite forms the lower layer of the ore zone. Limonite,

conversely, has a high iron content (>40%) and only small amounts of magnesium, typically less than

1%. Generally speaking, nickel can be leached from nickel silicate ore much quicker and with less

sulphuric acid than from ferronickel ore. The purpose of the test work was to develop estimates of

acid consumption and required leach time. It should be noted that no new test work has been

performed since the previous feasibility report(PWK Resources, 2010). However, the test work has

been reviewed again because of the two product heap leach processing option.

7.3.1 Test samples

Over 300kg of various Devolli ore was set to the European Nickel operation in Caldağ pilot plant in

Turkey so that initial heap leach test work could be carried out. A total of 8 columns of ore were

tested each having various ore, irrigation rates, acid strength and agglomeration methods. Table 7

below shows the different parameters tested in each.

Table 7 Column test parameters

Test

Column

Ore Diameter

(mm)

Irrigation Rate

(L/m2/hr)

Free Acid

(g/L)

Agglomeration Details

ACT-1 NiSi 150 40 75 N/A

ACT-2 FeNi 150 10 75 N/A

- 70 -

ACT-3 NiSi 150 10 75 N/A

ACT-4 50-50 150 10 75 N/A

ACT-5 50-50 150 10 75 Process Water

ACT-6 50-50 250 5 60 N/A

ACT-7 50-50 250 5 60 RCW and 75 kg/t H2SO4

ACT-8 50-50 250 5 120 RCW and 75 kg/t H2SO5

The column is a Perspex pipe with a diameter of 150mm for column tests 1 through 5 and 250mm

for tests 6 to 8 and they all start with material filled to a height of 1500mm. The 150mm columns

contain a sample weight between 28kg and 34kg and the 250mm columns hold between 85kg and

95kg ore. Leach acid is continuously circulated from the collection point at the base of the column

to the feed point at the top. Frequently, acid levels are measured and topped up to the test level as

required. Periodically, samples are taken and assayed for valuable and non-valuable minerals.

The column test work results should give an approximation of many of the key parameters required

in the flow sheet design including acid consumption, ore percolation, agglomerate use and type,

expected recoveries of valuable and waste minerals, leach time required, irrigation rates and

leaching kinetics.

7.3.2 Interpretation of Results

With only eight (8) test columns, it is impossible to make accurate estimates of the leach

characteristics of the entire deposit. Despite this, base assumptions are required so this analysis

focuses on the two critical elements of the heap leach design: nickel recovery verse leach time and

acid consumption verse leach time.

The first step to analysing the heap leaching kinetics is to look at the difference the ore type has on

the recovery and acid consumption. For this, ACT-2, ACT-3 and ACT-4 were selected since the only

difference between these tests was the ore used. This is shown below in Figure 38 and Figure 39.

- 71 -

Figure 38 Nickel recovery verse leach time

Figure 39 Acid consumption verse leach time

Figure 38 shows the nickel recovery verse leach time and the results are not surprising based on the

literature. ACT-3 leaches the most nickel in the shortest time because it is a nickel-silicate feed

which the heap leaching method is preferential to. ACT-2 being only ferrous nickel has the worst

recoveries and the 50%:50% mix ore fits generally in between these two. The acid consumption

verse leach time (Figure 39) does contain unexpected results. What was anticipated is that the

ferrous nickel ore (ACT-2) would have the lowest acid consumption and that ACT-3 would have a

much larger consumption. The unexpected result is that the mixed ore has a much larger

- 72 -

consumption than either of the individual ores. In fact, the acid consumption of ACT-4 is

approximately equal to combined consumption of ACT-2 and ACT-3. There is one other test, ACT-6,

that is a 50%:50% mix of ores with no agglomeration. To see if the conclusions that can be drawn

from above are consistent, the nickel recovery and acid consumption verse leach time graphs for

ACT-3, ACT-3 and ACT-6 are shown below in Figure 40 and Figure 41.

Figure 40 Nickel recovery verse leach time using alternative test column ACT-6

Figure 41 Acid consumption verse leach time using alternative test column ACT-6

The nickel recovery verse leach time with ACT-6 (Figure 40) is very similar to previous one with ACT-

4 (Figure 38). The fitting lines in this graph are exponentially decaying functions. Separate

- 73 -

equations were optimized for to fit ACT-2 and ACT-3. The curve for ACT-6 is the average of these

two functions and fits well.

The acid consumption verse leach time with ACT-6 (Figure 41) is considerably different with the

mixed ore test fitting in between the two different ore tests. Two exponentially decaying functions

were also optimized to fit ACT-2 and ACT-3. The ACT-6 is a combination of the two these two

functions with 75% consumption for ACT-3 and 25% from ACT-3.

The final leach characteristic to consider is the effect of agglomeration. The nickel recovery and acid

consumption verse leach time for ACT3, ACT-6 and ACT-8 are shown below in Figure 42 and Figure

43.

Figure 42 Nickel recovery verse leach time of agglomerated ore

- 74 -

Figure 43 Acid consumption verse leach time of agglomerated ore

The results of Figure 42 and Figure 43 are significant. They show that by using agglomeration, a

mixed ore can have similar nickel recoveries using the same amount of acid as a pure saprolite feed.

This result justifies the listing of the entire Devolli deposit as a resource/reserve as opposed to only

the saprolite proportion of it.

One of the options that was intended to investigate was the use of two separate mine products; a

saprolite product and a mixed product. The mixed product would contain some saprolite ore and all

of the transition and limonite ore. However, there has not been a test sample of agglomerated

nickel silicate ore performed and so the leach behavior has to be extrapolated from the results

provide. Figure 44 and Figure 45 below show how agglomerated saprolite ore may act and has been

designated ACT-X. This has been calculated by taking the ACT-3 figures and adding the difference in

recovery and acid consumption between ACT-8 and ACT-6.

- 75 -

Figure 44 Nickel recovery verse leach time with theoretical agglomerated NiSi sample

Figure 45 Acid consumption verse leach time with theoretical agglomerated NiSi sample

The predictions in Figure 44 and Figure 45 estimate that the agglomerated NiSi would have a 70%

nickel recovery in 90 days with an acid consumption of approximately 590 kg/t. For comparison,

ACT-3 reached a 70% extraction after 154 days with 540 kg/t acid consumed. The advantage of

agglomeration is then questionable. Although the leach time and therefore leach pad size is

approximately 40% smaller, the cost is an extra 10% in acid consumption. Sulphuric acid is the single

most expensive cost element in the operation of the heap leach plant and an additional 10% per

- 76 -

tonne is significant as will be shown in the finance section (Section) of this report. The method to

estimate to the leach rates for agglomerated nickel silicates above is incorrect and new test work

must be completed. For this study, a conservative estimate of 20% reduction in acid consumption

and a 30% reduction in leach time for a 70% recovery has been assumed.

In conclusion, there is not enough information to accurately predict the nickel recovery and the acid

consumption at the Devolli plant. The differences between ACT-2 and ACT-6 show the effect of

leach rate, acid strength and also the variation between what are both classified as 50%:50%

samples of mixed laterite ore. The best estimate available is the one supplied in the test work report

(European Nickel, 2010) of 72% nickel extraction in 200 days with an acid consumption of 560 kg/t

because it is also based on column and pilot leach pile test results from the European Nickel Caldag

project that was not available for this study.

7.4 Heap Leaching

Heap leaching is performed on a large stockpile pad. The pad is split into separate leach modules.

The total number of leach modules is dependent on the production rate and leach time. The leach

pad is two modules wide with the stacking feed conveyor situated through the centre if an

automated stacking system is employed. If haul trucks are used, a inbound haul road is construction

along the centre line of the heap leach pad.

The pad is a dynamic or “on/off” style pad. At any given time, one module is being stacked with new

ore, one is being reclaimed of waste material (leached ore) and one is completing secondary

leaching before being rinsed and washed. The remaining modules are undergoing either primary or

secondary leaching.

A multiple lift pad is advantageous as it would remove the need for reclaiming and dumping the

material. However, there are three reasons why this method has not been selected. The first is that

there are no test results to indicate if a multiple lift pad would allow acid to percolate though and

function correctly. The second is that part of the feed acid will consume leached waste minerals

from the underlying leached ore. The final reason is that leached laterites are an extremely low

strength material and it is unlikely that a large multi-stack pile will be able to safely support a

conveyor-stacker system or dump trucks on its surface.(Steemson, et al., 2009)

The leach pad is designed with a 6mm HDPE liner to prevent acid solution entering the ground.

Below the HDPE liner is a 300mm layer of clay as a secondary seal. Protecting the liner is a 500mm

layer of course aggregate which also allows drainage of the leach medium. It has been assumed that

- 77 -

on average 100mm of the course aggregate will need to be replaced each cycle. The modules will

have a 1% - 2% slope away from the centre of the pad towards individual leach ponds.

Each module feeds into its own leach pond. The leach ponds run the length of the modules and

have capacity to store an additional 24 hours of acid medium in case of a pump breakdown. Each

leach pond has its own pump which through a manifold can send the leach material to either the top

of the heap or to various other locations on site. The leach ponds will also be lined with the same

HDPE liner as the leach pad. Several separate leach ponds, in lieu of a single large dam, were

selected as it offers greater versatility in the plant operation.

Leach modules have a capacity of 30 days operation. This is because the estimated time for primary

leaching to occur is 60 days ensuring there is always 2 modules undergoing primary leaching and

feeding the precipitation plant. Older material will undergo secondary leaching with high acid

pregnant leach solution (HA PLS) continuously and this solution will be periodically checked for acid

levels. Part of this HA PLS will be circulated to the primary leach cycle where it is expected that high

recoveries of nickel silicate ores will cause much of the solution to neutralise. Solution from this

leach pond will be pumped to the low acid pregnant leach solution (LA PLS) dam adjacent to the

precipitation plant.

Before leached ore can be reclaimed as waste, a period of washing and de-acidification must occur

for environmental reasons. This involves continuously running raw water though the module and

periodically adding lime to the leach pond to keep pH levels in an acceptable range. It is anticipated

that 30 days of washing is sufficient to remove most of the free acid residing in the ore post-

leaching.

In the case of two mine products, one saprolite ore for quick leaching and a second mixed ore for

regular leaching, there will be two individual heap leach pads with the design detailed above. These

two pads, however, will share the HA PLS dam and LA PLS dam feeding the plant.

7.5 In-situ Leaching

In-situ leaching requires a HA PLS dam and a low LA PLS dam similar to the ones used in heap

leaching. In-situ leaching also requires a large dam of mine water to make up extra leach solution

and to create a pressure barrier surrounding the leach injection well to prevent loss of leach

solution. Additional infrastructure required for in-situ leaching is predominately pumps, pipes and

wells.

- 78 -

Like the heap leaching option, the LA PLS from the in-situ leaching is processed by the precipitation

plant.

7.6 Stope Leaching

Stope leaching has almost exactly the same infrastructure requirements as in-situ leaching. A HA PLS

dam and LA PLS dam are both required. It also requires a mine water dam, however, this will be

considerably smaller than the in-situ mine water dam. Stope leaching also requires a large quantity

pumps and pipes but these will be significantly different than those selected for in-situ leaching. In-

situ leaching requires the continual pumping of large quantities of leach solution to the surface. To

achieve this, large pumps and thick diameter pipes are required. In stope leaching, leach solution is

recirculated underground. The only solutions exchanged between the surface and the underground

are top up HA PLS for new stopes and LA PLS from leached stopes to the precipitation plant.

The LA PLS from the stope leaching is processed by the precipitation plant.

7.7 Precipitation Plant

The precipitation plant processes the low acid PLS into final nickel and cobalt saleable products.

Figure 46 below shows the process flow sheet supplied by European Nickel in the study introduction

document(European Nickel, 2010).

Figure 46 EN precipitation plant flow sheet design (L: liquids and S: solids) (European Nickel, 2010)

The following two final products are produced using the European Nickel precipitation are:

a primary nickel hydroxide product (NHP)

a secondary mixed nickel/cobalt product (MHP)

LA PLS

Iron Precipitiation

Ion Exchange (IX)

Nickel Precipitation

Tailings

Fe/Al Precipitation

Cobalt Precipitation

NHP Recycle Water MHP

S

S S

S L

L

L L

Elluate

Raffinate

- 79 -

An alternative process design recommended for a similar deposit in Albania is presented below in

Figure 47 (GBM, 2008).

Figure 47 Alternative precipitation plant flow sheet design

The main difference between the two processes options is the production of a single mixed

hydroxide product verse producing a nickel hydroxide product and a mixed hydroxide product. The

disadvantage of the second option is there is a feedback loop meaning larger equipment is required.

Another disadvantage is the loss of revenue from not producing a high cobalt hydroxide product.

Thus, the European Nickel design as shown in Figure 46was selected for use on the Devolli project.

The precipitation plant has six major processing blocks as follows:

1. Iron precipitation

2. Ion exchange (IX)

3. Nickel precipitation (NHP stream)

4. Iron/aluminium precipitation (MHP stream)

5. Nickel/cobalt precipitation (MHP stream)

6. Product packing (both streams)

Figure 48 below is an illustration of the precipitation plant process as described above.

LA PLS

Add Recyle Leach

Iron Precipitation

Mixed Hydroxide

Precipitation 1

Recycle Water

Tailings

Manganese

Precipitation

Mixed Hydroxide

Precipitation 2

MHP S

S

S L

L

L

L S

- 80 -

Figure 48 Precipitation plant process flow illustration(European Nickel, 2010)

7.7.1 Iron (Fe) Precipitation

The first stage of processing the low acid pregnant leach solution is iron precipitation. The purpose

of this stage is to remove a majority of impurity elements. Along with the main impurity of iron (Fe),

other impurities such as aluminium (Al) and chromium (Cr) are partially precipitated and removed.

Additionally, any free acid remaining in the solution is also neutralised during the iron precipitation

stage(European Nickel, 2010).

Precipitation of the waste elements is achieved via the addition of limestone in large tanks. Ferric

iron removal will occur when the solution has a pH between 2.5 and 3.5. Aluminium and ferrous

iron precipitate at higher pH ranges of 4 to 5 and 4 to 5.5 respectively which is in the range at which

nickel and cobalt will also precipitate. This leads to an unacceptable level of product loss. Thus, only

ferric iron is targeted during this stage and ferrous iron and aluminium are completely removed at

later stages. (Steemson, et al., 2009)

It is estimated that approximately 100 kg of limestone per tonne of dry ore will be required for first

stage iron precipitation(GBM, 2008). Once the impurity metals form into mineral hydroxides, a

solid-liquid separation process is used to separate the waste from the nickel and cobalt. A thickener

is used in conjunction with flocculent chemicals to produce slurry. The liquid overflow from the

thickener is collected in tanks. It then proceeds to the ion exchange for further processing.

The slurry is passed through a horizontal vacuum belt feeder to separated liquid and solids. The

solid waste, also known as iron filter cake, can be disposed of as normal waste on the waste

stockpile or can be used as a binder for underground backfill. Soluble nickel and cobalt are

- 81 -

recovered during the belt filter process and are collected in the same tanks as the thickener

overflow.

7.7.2 Ion Exchange

The ion exchange separates the leach solution from the iron precipitation stage into two streams; a

nickel hydroxide product stream and a mixed hydroxide product stream. The nickel hydroxide

stream will contain a large majority of the nickel from the PLS as well as trace amounts of iron and

other elements. The mixed hydroxide stream will consist of most of the cobalt, iron, aluminium and

magnesium from the feed.

The ion exchange works by trapping the desired element using resins and flushing it out separately

at a later stage. Figure 49 below is an illustration of the Calgon ISEP continuous separator proposed

for this plant.

Figure 49 Illustration of Calgon ISEP continuous ion exchange separator(Calgon Carbon Corp., 2004)

The PLS is fed into the top of the blue coloured cylinders in Figure 49. As the solution percolates

through, nickel is trapped by resin contained in the cylinders. Nickel-free solution passes out

through the base of the unit and is called the IX raffinate. The IX raffinate reports to the secondary

iron removal stage.

After the nickel-free solution has drained, regenerant is added to liberate the nickel from the resin

(yellow cylinders in the figure). The nickel-bearing solution, called the IX eluate, is pumped from

here to the nickel precipitation stage. The final stage of ion exchange is the cleaning of the exchange

beds (green cylinders in Figure 49) using rinse water to removed any excess regenerant.

7.7.3 Nickel Precipitation

- 82 -

The first stage of nickel precipitation is the precipitation of trace ferrous iron in the IX solution. This

process is similar to the first-stage iron precipitation where limestone is added, thickened using

flocculent and liquid-solid separated in a belt filter. The overflow of the thickener proceeds to the

nickel precipitation tanks. The solids from the belt filter can be used as backfill or disposed of at the

leached ore dump.

Nickel can be precipitated using either soda ash or magnesia. The main advantage of using magnesia

is that it is more efficient at precipitating the nickel than soda ash. Disadvantages of using magnesia

are that it is not as readily and cheaply available as soda ash and, depending on customer product

requirements, an additional manganese removal section may be required. Soda ash has been

selected for the precipitation of nickel considering the location of the mine and the supply

requirements.

After precipitation, the solution is thickened and separated using a belt filter. Liquid recovered from

the solid-liquid separation is pumped to the leach ponds as it may contain trace amounts of nickel.

The solids are the nickel hydroxide product and proceed to the final stage of the precipitation plant;

product packing.

7.7.4 Iron/aluminium Precipitation

The nickel-free IX raffinate is first processed using iron/aluminium precipitation. This is to remove

the remaining impurities in the leach solution and is achieved using a bleed neutralisation process.

Not all of the IX raffinate reports to the bleed neutralisation tanks. In some plants, only

approximately half of the solution proceeds to final mixed hydroxide product whereas the other half

is re-circulated back to the leach ponds(Steemson, et al., 2009). There are several advantages to

using this feedback process including:

An increase of the average cobalt grades in the solution

A higher final cobalt grades in the MHP

Smaller sized equipment required for iron/aluminium and MHP precipitation stages as only

half the throughput is being processed. This equates to a smaller plant and lower CAPEX.

This design has been used for this plant. The bleed neutralisation removes a majority of the ferric

iron and aluminium remaining in the solution as well as neutralises any remaining free acid. Similar

to the other iron precipitation processes in the plant, the main agent used in limestone. The

solution is thickened and filtered. Solids are waste or backfill material and the cobalt-containing

liquor is pumped to the final precipitation stage.

7.7.5 Nickel/cobalt precipitation

- 83 -

The remaining nickel, cobalt and manganese in the leach solution are precipitated using soda ash.

The solution is then thickened and filtered to form a mixed hydroxide product. The water from the

belt filtering is recycled back to the heap leach pond.

7.7.6 Product Packing

Nickel hydroxide product (NHP) and the mixed hydroxide product (MHP) are packed into 2 tonne

bulk bags. The product can then be moved using a forklift and stored in the warehouse until

transportation to the consumer. 10 bulk bags will be loaded into 20 foot containers and taken from

site via trucks. More bags can physically fit into a container however more than 10 bags will exceed

the container’s safe working weight limit. The proportion of NHP bags to MHP bags in each

container will depend on the customer requirements.

7.8 Reclaiming Leached Ore

Once the ore is leached and has been neutralised, it is then reclaimed and transported to the

leached ore surface dump. There are the two following methods for reclaiming the ore from the

leach pad:

1. Using automated machines such as bucket wheel reclaimers to load the ore onto conveyors.

A series of conveyors transfers the material to the waste dump where shiftable conveyors

and a stacking machine are used to progressively build the dump

2. Using shovels, most likely front end loaders, to load the material into trucks where it is

transported to the dump and tipped. Dozers can then be used to shape the dump.

The second method has been chosen because there are issues with the stability of a leached ore

dump. The heap pile will not be able to support the stacking machine and the shiftable conveyor.

Thus the first option is not possible for technical reasons.

Depending of the transportation option, surface trucks may already be used for transporting and

stacking material onto the leach pad. In these cases, the same trucks will be used for taking material

to the dump and the process will be optimized.

Leached ore may also be used for backfill depending on the mining method. The chute through

which leached ore is transported to the mine works is located close to the dump.

7.9 Cost Modelling

The cost model for the processing plant was constructed as part of the raw material handling cost

model (refer Section 5.6). The results of the cost model are presented in the financial section of this

report (Section 15.4).

- 84 -

8 Infrastructure

8.1 Offsite Infrastructure

8.1.1 Power Supply

The total electrical supply on the Albania network is 1,450 MW from three large hydro-power plants

in the north of the country(CEZ, 2011). High voltage power is transmitted nationally and

internationally at either 220kV or 400kV (Energy Community Regulatory Board, 2008). Frequent

blackouts are a common occurrence throughout the country though privatization of the electrical

power plants and network and infrastructure funding from the World Bank has improved the

consistency of supply in recent years.

There exists a 400kV power line from Elbasan (A) to Zemblak (B) (see Figure 50 for locations). The

line continues to Kardia (C) in Greece and is one of only four existing cross border connections. At

Zemblak, there is a 400kV/100kV substation. It is the intension that a 100kV network will be built in

southern Albania from this substation, however due to funding shortages since 2008 this has not

progressed. The distance from Zemblak to Bilisht (D), the town closest to the deposit, is

approximately 15km and it is unknown whether power lines have been built in the area to date.

(Energy Community Regulatory Board, 2008)

Figure 50 Map of Albania and Greece showing major electrical points of interest to the project

8.1.2 Water Supply

Albania is a water rich country with large rainfalls in all regions of the country. The supply of water is

affected by uneven seasonal distribution and during the dry summer months, the availability of

adequate surface water and possibly ground water may be an issue.

- 85 -

The Devolli project will require a large quantity of water to maintain a heap leach operation. A large

proportion of water is recycled as part of the processing and mine de-watering will be sufficient to

supply make-up water.

8.1.3 Road and Rail

Transportation infrastructure in Albania is far below the standards of other European countries. The

road quality between major centres has improved in recent years. In April 2011, a new road project

was approved to build a highway between the capital Tirana and the town of Elbasan, located 40km

in the south. In 2010, another major project was completed with the construction of highway

joining Albania and Kosovo(AlbanianEconomy.com, 2011). The closest road to the Devolli project is

the SH3 which runs from Tirana to Kapshtice in Greece via nearby Korce. This road is in average

condition but should be suitable for delivery of equipment to site and for transportation of nickel

concentrate.

The rail system during the communist era was frequently used because of the ban on private

vehicles. With the fall of communism in the early 1990’s, the rail system has fallen into a dilapidated

state of disrepair as a consequence of more and more Albanians using private vehicles instead of

rail. The network is 435km of single, standard gauge track with no international connections(alba

global, 2009). The closest rail line to the project area is in Korce and there is no direct connection to

a port if this transportation were to be considered. Thus, rail is not considered an option for use in

this project.

8.2 Onsite Infrastructure

Figure 51 below is a drawing showing the location of the following onsite infrastructure:

1. Administration offices and changing house

2. Warehouse

3. Workshop

4. Oil and lubricant store

5. Laboratory

6. Water and sewage treatment plant

7. Explosive storage

8. Fuel storage

9. Accommodation

Each of these 9 items are described in more detail below. Additionally, the following items are also

shown on the map for clarity:

- 86 -

10. Main mine adit

11. Ventilation shafts

12. Roads

13. Heap leach pad and ponds

14. Precipitation plant

15. Sulphuric acid plant

16. Leached material dump

All infrastructures items are numbered as above in Figure 52 below.

- 87 -

Figure 51 Site plan showing major infrastructure

8.2.1 Administration Offices and Changing House

The administration office will provide working space for the mine management, engineering staff

and administration personnel. A large meeting room will also be incorporated for meetings with

1

2 3 4

8

5

7

6

9 10

11

12

13

14

15

16

- 88 -

mine/process employee groups and visitors. Common areas, rest rooms and smaller meeting rooms

will also be required. The offices will be demountable constructions and a gravel car park will be

required at the building entrance. The office will be located near the exit on the northern side of the

main road.

A changing house will be provided for underground staff. Facilities include sex-separated showers

and toilet areas and individual lockers. The changing house will also include the cap lamp room and

tag-in/tag-out board. The change house is located near the mine portal and employees leaving the

change house will enter mine light vehicles and proceed to the mine main level.

8.2.2 Warehouse

The project warehouse will be used to store consumable items, PPE, spare parts and maintenance

equipment. The warehouse will be attached to the precipitation plant as it will also be used to store

packaged concentrate before it is dispatched offsite. The warehouse will have a rail and hoist

system for the movement of heavy items that cannot be shifted using a forklift. A large drop off

zone will be constructed next to the warehouse to allow sufficient room for loading and unloading of

concentrate and goods.

Elemental sulphur, oil and lubricants will not be stored in the warehouse.

8.2.3 Workshops

The site will have two workshops; a primary surface workshop and a secondary underground

workshop. The surface workshop will be large enough to service 4 machines at one time – either

surface or underground vehicles - and to store the large amount of tools and daily consumables. The

surface workshop will be located in the vicinity of the heap leach pad.

The underground workshop will provide a service to the underground vehicles. It will be located

either near the mine entrance or preferably, if rock conditions allow, underground near the

extraction level.

8.2.4 Oil and Lubricant Store

The oil and lubricant store is a fully- concrete bunded, roofed area next to the surface workshop.

Oils and lubricants are stored in 1m3 bulk bins and can be transported using forklifts. There will be

sufficient space for new and old lubricants to be stored. Old lubricants will be collect by trucks for

proper disposal off-site.

8.2.5 Laboratory

An onsite laboratory will be constructed to perform grade assaying of mine and process material.

The laboratory will be located close to the administration office to facilitate close workings and

- 89 -

result sharing with engineering personnel. The laboratory will measure samples from core samples

of future panels to be mined and samples from various stages of the heap leach process i.e. at the

ROM, after agglomeration, after primary leaching and fully leached ore.

8.2.6 Water and Sewage Treatment Plant

A small water and sewage treatment plant will also be included in onsite facilities. The reverse-

osmosis sewage plant will treat all sewage from the mine accommodation, changing house and

offices. Treated water will be pumped to the mine water dam. The water treatment plant is

required to produce potable water for staff consumption and for supply to the changing house and

on-site accommodation.

8.2.7 Explosive Storage

The explosive storage will be located in relatively close proximity to the mine portal. The storage will

be surrounded by large material bunds and a security fence. The facility will have 24hr CV-

monitoring and access will be restricted to authorised personnel only. A second smaller explosive

storage unit, with similar security measures, will be located underground.

8.2.8 Fuel Storage

Fuel will be delivered by tankers and stored in two large fuel tanks with a combined capacity of

200kL. Nearby there will be an H/V and L/V re-fuelling station. Fuel storage must be maintained

above a minimum level so that ventilation fans and fire pumps can be run for a safe time in case of

power failure.

8.2.9 Accommodation

It is planned that the majority of the workforce will be from the local community. Onsite

accommodation will be minimal to provide for fly-in/fly-out staff. The accommodation will be a

series of interconnected demountables. Each room will contain a single bed and en-suite shower

and toilet. The facilities will also contain a common mess and recreation room. At mine closure, the

accommodation will be dismantled and relocated to a new site.

8.3 Sulphuric Acid Plant

The main consumable in the Devolli project is sulphuric acid for the heap leaching process. The price

of sulphuric acid remained stable for many years at prices lower than 80 US$/tonne until it

skyrocketed in 2008 from prices to over 250 US$/tonne for industrial sulphuric acid and over 400

US$/tonne for spot sulphuric acid (see Figure 52). Due to the global financial crisis, sulphuric acid

prices crashed in 2009, similar to many other commodities, but since then it has been slowly

recovering.

- 90 -

Figure 52 Historical sulphuric acid prices(ICIS, 2010)

One of the issues with sulphuric acid production is that the primary feedstock is elemental sulphur

which is a bi-product from the smelting and oil and gas industry. Thus, the production of sulphur is

inelastic and does not respond to the changing supply/demand balance(ICIS, 2010).

In order to protect this deposit from fluctuating sulphuric acid prices, a sulphuric acid plant will be

constructed. One tonne of elemental sulphur will produce almost 3 tonnes of sulphuric acid so

producing acid onsite removes the costly and risky task of transporting large quantities of highly

corrosive solution. Another advantage of using an onsite sulphuric acid plant is that the process

produces a large amount of steam which can be used to generate electricity. The generated

electricity can be used to power the mine or if there is an excess, to sell to the grid.

8.4 Limestone Quarry

The final additional infrastructure that could be considered is a limestone quarry. The precipitation

plant requires a large amount of limestone for the precipitation of waste elements such as iron from

the leach solution. This option was not investigated due to unknown variables such as quantity and

quality of the limestone onsite and whether there exists a local market for this product as well. It

has been assumed that limestone is being produced locally and can be purchased at a reasonable

rate for use at the processing plant.

- 91 -

9 Ventilation

Mine ventilation provides a flow of fresh air to the underground workings of a mine. The primary

purposes of mine ventilation are to deliver sufficient oxygen to workers and remove noxious gases.

Noxious gases are from underground diesel engines, blast fumes from explosives and, depending on

the mineralogy, from within the rock itself.

The ventilation system has been designed based on the following SME recommendations(SME,

1992):

2 m3/min of fresh air per person underground

4 m3/min of fresh air per hp of installed diesel power

It is also recommended the maximum air flow through any drifts or adits is 6 m/s. When the air flow

exceeds this value, airborne dust particles become a health hazard to the workforce. The following

plan in Figure 53 shows the high-level ventilation design for the Devolli project including location of

the intake and outtake air paths.

Figure 53 High-level ventilation design for the Devolli project

- 92 -

The adit to the surface will be the main air outlet for the ventilation system. Depending on the

transportation option, there may be up to main three adits. In the case of three adits, the two adits

which contain conveyors will be outtakes and the main access adit will be an intake outlet.

There are three ventilation shafts planned for the Devolli project. The first shaft (numbered 1 in

Figure 53) is located in close vicinity to the main access and will be constructed as part of the pre-

production development. This intake shaft will be used for first production in Verniku West. It will

also be the main air supply to allow the main access adit that the runs the length of Verniku West to

be constructed followed by Ventilation shaft #2. Ventilation shaft #2 will then be the main source of

clean air for the northern deposit. Development work can then commence to link the mine working

with the southern deposit Kapshtica and shaft # 1 will be used to supply air for this. Ventilation shaft

#3 will be constructed last and when constructed, production can commence in the southern

deposit. Once ventilation shaft #2 and #3 are operational, ventilation shaft #1 will be used either as

an intake or outtake vent depending on mine requirements.

The ventilation calculations are part of the mine costing calculation and are attached in Appendix I.

- 93 -

10 Environmental and Social Management

Protection of the environment and improvement of the local socio-economy are both of vital

importance to European Nickel to achieve its vision of being a world-class sustainable mining

company. Any mining operation has the potential to cause irreversible damage to the environment

if not properly controlled and monitored.

Potential environmental and social impacts are identified in this section and mitigating strategies are

developed to prevent their occurrence. Albanian legislation relating to the environment is also

identified. Mine closure and the associated works that will need to be carried out at end of the mine

life are detailed further in this paper.

10.1 Environmental Legislation

The management and enforcement of environmental law is the joint responsibility of a number of

government departments and agencies. The different organisations the Devolli project may need to

cooperate and work with include:

The Ministry of Environment, Forestry and Water Administration

The Inspectorate of the Environment

Directorate of Environmental Impact Assessment

Ministry of Public Works and Tourism (permits for construction).

Ministry of Agriculture and Food (MAF) (agricultural land)

Directorate General of Forests and Pastures (DGFP)

In addition to national organisations, the Devolli project will also need to work need to work closely

with the local communities.

The Ministry of Environment, Forest and Water Administration is the main environmental law

forming body and the Law on Environmental Protection (2002) is the primary environmental

protection legislation for Albania. The Inspectorate of the Environment consists of regional agencies

and enforces and ensures compliance with the national environmental legislation. In order to apply

for a mining permit, an environmental impact assessment must first be submitted and approved by

the Directorate of Environmental Impact Assessment. The Devolli project will also need to apply for

a construction permit from the Ministry of Public Works and Tourism. Any proposed changes to

agricultural land may need to be approved first by the Ministry of Agriculture and Food. Forestry

permits, if required, are organised through the Directorate General of Forests and Pastures.

- 94 -

Other than the Law on Environmental Protection (2002), additional Albanian laws may also need to

be considered for the Devolli project including:

Law on Protected Areas (2002)

Law on the Land Protection (2001)

Law on assessment of the impact on environment (2003)

Law on Treatment of Pollute Waters (2003)

Law on Plant Protection Service (1993)

Law on Marine Environment Pollution and Damage (2002)

Law on the Protection of Air from pollution (2002)

Law on the Forests and the Forest Service Police (1992)

Law on Environmental Treatment Of Solid Waste (2003)

Implementation of the environmental in Albania remains weak. However, Albania has aspirations to

join the European Union so the environmental law and enforcement are expected to become stricter

in the future. Thus, all environmental aspects of this project need to designed to satisfy both

Albanian law and European Union policy(European Nickel, 2010).

10.2 Environmental Impact Analysis

The environment impact analysis (EIA) has been performed by individually assessing the potential

impact on the following eight areas:

1. dust

2. air pollution

3. water

4. noise

5. vibrations

6. land use and top soil management

7. flora and fauna

8. waste material

The following sections detail the cause of potential impacts for each of the above identified area and

makes recommendations to prevent or reduce these impacts.

10.2.1 Dust

The main sources of dust during mine operations will be:

ore and waste transportation by trucks and/or conveyors

- 95 -

ore communition

blasting

wind erosion of waste dump and top soil stockpile

Dust emissions are especially of concern during the summer months where the temperatures are

high and the surface is dry. To control dust emissions, the following systems and design

requirements will be used:

spray jets on all surface crushers and screens

spray jets on long conveyors

permanent covers high transfer conveyors

material stacking and transportation to be stopped during high wind events

transfer heights to be minimised

mobile water trucks to spray roads especially during the summer

frequently used roads to be paved and kept clean

waste dump to be recultivated as soon as possible

top soil stockpiles to be compacted and vegetated

ventilation system to designed to minimise dust pick up in the mine. Dust-filter to be

considered if emissions become excessive

10.2.2 Air Pollution

The major source of air pollution other than dust as discussed above will come from vehicles and

blasting. Mine pollution from underground will be found in the exhausting air from the ventilation

shafts or adits. This air may be contaminated with CO2, CO, NO2 and SO2. Proper maintenance of

underground vehicles and minimum use of explosives will be vital to minimizing air pollution from

the underground.

During the development phase of the project, surface drilling and blasting may be required on the

surface to construct the main adit, the leach pads and waste material dump. Wind strength and

direction will need to be considered to prevent blast fumes and dust affecting the local water

sources and local communities.

Air pollution from surface facilities is expected to be minor. There will be diesel and welding fumes

from the workshops and backup generators. Transportation of the mine product will achieve using

road trucks so there will be an increase in local traffic.

- 96 -

A major source of air pollution that is common to Albania is the burning of garbage as the most

efficient method to removed industrial waste. It is not known if this practice is common in the

Devolli region. Regardless, no garbage on site will be burnt. If local dumps are not available, an on-

site non-mine material dump will be constructed. The dump will need to be located so that it won’t

affect ground water and will have minimum impact on potential future use of the land. Ground

testing will be required to judge the suitability of a location for a waste dump.

10.2.3 Water

Heap leaching requires a large amount of acidic water and other processes such as dust suppression

and fire water also needs a significant amount of clean water. This can have an effect on the

environment in two different ways. The first way is the sourcing of the water and the second is the

risk of mine water escaping to the environment at large.

Water for processing will be collected and stored from rain run–off and de-watering. It is expected

that this will be sufficient to cover any make up water required. Where ever possible in the

processing plant, thickeners and solid-liquid separation have been used to recycle a large amount of

water. If more water is required, back-up boreholes will provide additional needs. There is the

nearby Devolli river and creeks, however it is preferential to not use these sources as the water

quality is expected to be poor due to local garbage pollution. Any water that is extracted will be

done so in accordance with Albanian mining law which states that all water taken must be returned

free of any contamination that will adversely affect human health or flora and fauna.

To prevent the escaping of mine and process water, sufficient dam capacities will be constructed. If

either of the HA PLS dam or LA PLS dam overflow, they will, by design, flow into the barren water

dam. This will then overflow into the mine water dam and finally to the evaporation ponds. The

evaporation ponds are flat lying dams designed for rain-water that flows from mine workings to be

contained and eventually evaporate. During dry times, the evaporation ponds can be cleaned with a

front-end loader to take any heavy metal sediment that will have been deposited to the waste

dump.

The local villages use bore water as the primary supply of drinking water. Thus, it is essential that

leach solution does not leak into the groundwater aquifers. Testing and inspections will be

performed periodically to confirm the heap leach pad and ponds barriers have not been breached.

A small water treatment and sewage treatment plant will be onsite to re-use as much water as

possible and to produce clean potable water for human consumption.

10.2.4 Noise

- 97 -

Noise can have a detrimental effect on the health of both employees and the local community. The

Bilishti village is located approximately 1km from the mine site. The major sources of noise from the

mine will be:

transportation of ore and waste by trucks and/or conveyors

ore communition

mine construction activities

ventilation

During construction, there will be drilling and blasting performed at the surface as well as raise

boring for the ventilation shafts. These activities will produce more noise than during usual mining

operations and will be restricted to day-time to limit impact on the local community.

For operations, noise will be limited by:

optimisation of site layout including location of mine portal, processing plant and waste

dump to limit amount of roads and conveyors in vicinity to existing towns and villages;

installing noise barriers on the crushing and sizing stations;

installing balanced, low-noise idler rolls on long conveyors. Conveyors can be shielded if

further noise reduction is required;

proper maintenance of trucks and other surface vehicles;

majority transportation of ore transportation from site during work hours; and

ventilation shafts will have noise barriers if found to be excessively loud.

Ear plugs and headphones will be part of standard PPE to protect company employee and visitors.

10.2.5 Vibrations

The Devolli project can cause ground vibrations that may be large enough to concern local residence.

Ground vibrations can be caused by blasting, mine room collapsing and material sizing. Because of

the weak rock strength, blasting during the operating will be minimum and will not be noticeable in

nearby villages. Blasting during construction may cause large vibrations depending of overburden

rock strength. All blasts need to be designed to minimise excess ground vibrations and fly rock.

Where appropriate, locals need to be informed of upcoming large blasts.

Crushing of ore can also cause ground vibrations. All crushers will be mounted onto large steel

springs to damper vibrations.

- 98 -

The collapse of the roof in a mine will also cause large ground vibrations. In both the longwall and

room and pillar mining options, it is expected that the roof will collapse. However, it is intended for

this to be gradual and vibrations experienced on the surface will be minor. The uncontrolled

collapse of a large portion of roof strata in the underground mine is a significant safety risk to

underground miners due to the air blast. Thus, the controlled collapsing of mine sections is

extremely important and will be monitored closely.

10.2.6 Land use & Top soil management

The use of a heap leach plant requires a significant amount of land that will have large amount of

sulphuric acid concentrated on it. Although the waste material is washed and neutralised at the end

of the mine life, there is the potential for pools of acids to remain. Before closure, the entire leach

pad will require neutralisation. Once tests show the area to be uncontaminated, top soil will be

returned to the pad which will be converted to farm land. Leach ponds and dams will also be

neutralised and cleaned and will be remain for use with the farms.

The waste dump will be covered progressively with top soil and transformed into a permanent forest

using native flora. The waste dump will be shaped to match the lay of the land.

Top soil will be reclaimed from all land be used at the start of the project. This will be stockpiled

separately and maintained until it can be returned and re-planted.

The final major land use is the area above the underground mine workings. Because caving methods

are used, the land above will subside. This will occur during the life of the mine as controlled

collapses and the land above after the mine will remain stable.

10.2.7 Flora and Fauna

The mine is underground so mining activities will not affect the flora and fauna of the area. The

processing plant is large and there will be a large amount of water on-site that is not suitable for

animal consumption. In lined dams, like the ones of this project, it is often the case that animals will

drown if they fall into the dam because the HDPE lining is too slippery to crawl up. The area is

agricultural so it is not expected that many animals will be at risk however the site is fenced to also

prevent larger animals from entering the site.

Stripping of the land during construction has a permanent effect on native flora and fauna in loss of

habitat. After mining, a majority of the land will be returned to its previous state.

10.2.8 Waste Material

Waste rock will be stock piled on site in a permanent dump zone along with the leached ore. All

tailing from the plant will is thickened so it can be dumped at this location or can used a backfill

- 99 -

within the mine. Dust blow off is a risk with the waste dump so it will be built to full height and

reclaimed as forestry progressively. The waste dump should be located to minimise visual and dust

in wind impact to the local villages.

As detailed in the air pollution section of this EIS, other wastes from the mine and plant, such as

used machinery parts and canteen and office waste will be collected and disposed of at a dump of

the local authorities. If a legal dump is not in the vicinity, a permanent on-site dump will be

constructed to EU standards.

Process agents and wastes will be stored on site in a manner that minimises exposure to employees

and the environment in operation and in case of failure. A oil collected will used in the workshop

and all old oils and lubricants will be collected into 1m3 bulk containers and trucked offsite for

correct disposal.

10.3 Cultural Heritage

European Nickel places great importance into building a nondependent relationship with the local

community. The operation should have a positive impact on the lives of locals and protect sites of

cultural importance.

There are a number of environmental and man-made sites in the vicinity of the project area that

must be protected. Figure 54 below shows the location of the following sites that require protection

from project impacts:

1. Prespa Lake

2. Treni Cave

3. Mummy stones of Treni

4. Vërniku Churches & Cemetery

5. Vërniku Natural spring

6. Kapshtica Churches & Cemetery

7. Kapshtica Natural spring

- 100 -

Figure 54 Location of sites of cultural importance(European Nickel, 2010)

Prespa Lake (1) is a national park located approximately 3km north of the Verniku West deposit.

Treni Cave (2) and the Mummy Stones of Treni (3) are registered geo-monuments and form part of

the Prespa park tourism area. All three of these sites are located a considerable distance from the

deposit and should not be affected by the mine activities.

Verniku and Kapshtica are two villages close to the deposit that have sites of cultural and religious

significance (4 – 7). All mining activities should not adversely impact the villages or their cultural

sites. The mining methods selected using some caving but the free height being collapsed, the depth

of the mine and the distance should mean that the villages and monuments remain unaffected. This

will need to be reviewed based on further testing of the overburden so that the area of subsidence

can be accurately predicted. The area around the deposit has a extremely long history with artefacts

dated to be the bronze age being found locally. There is a possibility that during the project

particularly with large earthworks being moved for the heap leach pad and dams that undiscovered

archaeological sites may be found within the mine area.

- 101 -

11 Project Scheduling

With any project, the schedule forms one of the four key measurements of project achievement and

success with budget, quality and health and safety being the other three. The life of Devolli project

can be sectioned into three separate phases; pre-production, production and post-production. Pre-

production includes all of the activities from before and including the pre-feasibility study until the

end of commissioning and the commencement of full production. Post-production is the closure

and restoration of the mine site.

11.1 Pre-production

The pre-production stage has two main phases; the engineering and procurement phase and the

construction phase. These phases aren’t separated by a date but by where project decisions are

being made. During the engineering and procurement phase, most work is being performed in

offices at locations that are not necessarily the mine location. As the engineering and procurement

phase shifts to the construction phase, more and more work is onsite at the mine. It is during the

construction phase that most of the project capital expenditure is required.

The activities that occur during the engineering and procurement phase include:

Pre-feasibility

Environmental impact study

Further drilling and core testing

Permit application

Feasibility study

Detailed design

Procurement of major equipment

Financing

Legal Issues

The construction phase of the project includes:

Site preparation

Construction of access and haul roads

Construction of the leach pad, ponds and dams

Construction of the precipitation plant and other infrastructure

Underground access developments

Ventilation shaft #1 development

- 102 -

A detailed pre-production Gantt chart is attached in Appendix J. It is anticipated that the total pre-

production will be 3.5 years long with 1.5 years in the engineering and procurement phase and 2

years spent in construction and development.

11.2 Production

The production schedule is dependent on the mining method, mine design, the number of products,

cut-of-grade and the production rate. Generally speaking, the underground production schedule is

split into development and production activities. Development is required to open and prepare new

areas for mining. Development also includes ventilation related workings such as the addition of an

intake shaft. Production activities are also processes related to removing of ore from processing at

the plant. For some mining methods, backfill is also required this forms a third sub-heading for

activities under production. On the surface, the production schedule includes timings for the heap

leach pad for example what modules are currently being primary leached, secondary leached,

neutralized, reclaimed, stacked or are empty. It also shows the surface dump pre-development and

restoration.

11.3 Post-production

Post-production includes all activities that occur once the mine stops producing a saleable product.

It is anticipated that the majority of mine closure and reclamation works will be completed within six

months of the mine close date. Some small expenses such as periodic testing of the waste dump

and water testing from various locations around the mine will continue for several more years until

the project area can be returned.

- 103 -

12 Risk Analysis

The risk analysis forms an important part of any feasibility study. It is a formal, structured analysis of

each asset during each stage of the project. As projects progress from pre-feasibility to execution,

the risk assessment details less general site wide risks in favour for more comprehensive and

focused items.

There are several ways that risk assessments can be performed. A common approach in the mining

industry is to identify a risk and assign a consequence and a likelihood factor. The product of these

two factors form the risk value and items are ranked and analysed based this value. Another risk

assessment method is the combination of three factors; likelihood of the risk occurring,

consequence of the risk occurring and likelihood of detecting the risk before occurrence. The risk

factor is the product of the three factors.

The likelihood of an event occurring is assigned a rating between 1 and 5 or from A to E. Table 8

below shows an example definition of the event occurring as used in the Australian state of

Queensland mining industry (Human, et al., 2006).

Table 8 Likelihood rating with description and explanation

Rating Descriptor Description Quantification

1 or A Rare The event may only occur in exceptional circumstances

The employees are exposed to the event occurring to its final outcome greater than 5 times in 5 years

2 or B Unlikely The event could occur at some time

The employees are exposed to the event occurring to its final outcome greater than once per year but no more than 5 times in 5 years

3 or C Occasional The event should occur at some time

The employees are exposed to the event occurring to its final outcome greater than once per month but no more than 12 times per year

4 or D Likely The event will probably occur in most circumstances

The employees are exposed to the event occurring to its final outcome greater than once per week but no more than 4 times per month

5 or E Almost certain

The event is expected to occur in most circumstances

The employees are exposed to the event occurring to its final outcome daily

The consequence is also given a rating between 1 and 5 where 1 refers to a minor or insignificant

consequence whereas a 5 is a catastrophic event. The consequence rating is not an assessment of

the worst possible outcome. It is a judgement of the consequence that is reasonably likely to occur.

- 104 -

Table 9 below displays different consequence categories and the meaning of a rating 1 and rating 5

for both of them. Descriptions for consequences of ratings 2, 3 and 4 can be made by interpolating

logically between the two extremes supplied.

Table 9 Consequence rating for different categories(University of New South Wales, 2010)

Category

Consequence Rating

1 (insignificant) 5 (catastrophic)

Health and Safety Minor scratch Multiple or single fatalities

Revenue/Costs US$ 100 order of magnitude US$ 1 mil. order of magnitude

Schedule Hours Months or years

Social Minor complaints Complete degradation of living standards

Environmental Small oil spill Permanent damage/loss of native fauna and

flora

Company Reputation Minor complaints International headlines

The likelihood can be rated in two different ways; 1 to 5 or A to E. If the 1 to 5 system is used, the

risk rating is calculated by taking the product of the likelihood rating and the consequences rating.

This gives a range of risk ratings from 1 to 25. A risk rating of 1 is an event which is highly unlikely to

occur with insignificant consequences. At the other end of the scale, a risk rating of 25 signifies an

event which is highly likely to occur with catastrophic consequences. The risk ratings are ranked

from highest to lowest.

If the likelihood is an A to E rating then a table (see Table 10 below for an example) is used to obtain

the risk rating.

- 105 -

Table 10 Example of risk matrix(Department of Resources, Tourism and Industry, 2008)

The advantage of using a risk matrix instead is that different likelihood/consequence combinations

may have the same score but require different levels of attention. For example if an incident is

unlikely to occur (e.g. probably more than one during the mine life) but the most reasonably likely

consequence will be catastrophic (e.g. a fatality), the risk score is only 10 whereas the risk matrix

ranks this event as extreme. The mining industry does not accept the likelihood of a fatality as an

acceptable risk. A risk rating of 10 can also be an event almost certain to occur but with only minor

consequences (e.g. a twisted ankle). Although this is not desirable, this risk cannot be classified as

extreme.

Risks that are deemed too high and are therefore unacceptable require mitigation strategies to

downgrade the risk. Once these mitigation strategies have been identified, the risk analysis can be

performed again to re-rate the risk and possibly identify further risks associated with the mitigation

method.

Risks for the Devolli project were individually identified during the three different phases of the

project; construction and development, operations and closure. Significant risks that were identified

are analysed individually at the end. The risk ratings given in the table for each section are

considering if no mitigation strategies are employed. Many of the risks detailed below were already

identified in the previous study (PWK Resources, 2010) and have been included for completeness.

12.1 Construction and Development

- 106 -

The major project risks during the construction and development phase of the mine are presented in

Table 11.

Table 11 Potential project risks during construction and development (without mitigation)

Risk Likelihood Consequence Risk Rating

Seismic events 3 5 15

Unknown geology 3 4 12

Accidents due to unskilled labour 3 4 12

Copper and steel prices 3 3 9

Strikes from locals 2 4 8

The risk of a large-scale seismic event occurring affects the mine during its entire life-cycle. Seismic

events affect both the surface and underground facilities of the mine. The risk during construction is

the potential collapse of only partially completed structures. To mitigate this risk, structures should

be assembled as much as possible on the ground before final construction. This minimises the

amount of time unfinished structures are left standing.

Unknown geology is a considerable risk during the construction of the underground access adits and

facilities. When coupled with the seismic risk in the area, the potential of a collapse occurring is

significant and the consequence in terms of costs, schedule variances and possible health and safety

is unacceptable. The geotechnical properties of the rock along the entire path of the adit need to be

established by core sampling, logging and testing so that the tunnel can be appropriately designed.

If incorrect geotechnical data is used, the tunnel may be under-designed which constitutes a major

construction and operating risk or it may be over-designed which will increase costs considerably.

The only place of major risk remains during construction is the working face. Strict work procedures

need to be adopted to ensure that no persons are in places of risk of rock fall or rock burst.

Two major construction items in the building of a mine are structural steel and electrical cabling and

wiring. The price of raw steel and copper directly affect the total cost of the project. The cost of

iron ore, the major component of steel, has fluctuated considerably over the past decade. This is

largely due to domination of the iron-ore industry by only a few producers and consumers. In recent

years, a new contracting system of 3-month price contracts based on market spot price was

introduced in lieu of the previous system of 1-year contracts at a negotiated price. Although this

new contract system has brought some stability to prices, there still remain significant fluctuations.

Frequent fluctuation in copper prices is also common. Contracts for purchasing bulk quantities of

steel and cabling should be made well ahead of the project construction start date to remove this

- 107 -

risk. Alternatively, fixed price construction contracts will also remove this risk as the cost of

procuring the steel and copper shifts to the contractor.

Another major risk to the project if not managed appropriately stems from the use of unskilled local

labour. Local labour will need to be trained by experts in correct work procedures, particularly

related to workplace health and safety. The use of local labour is desirable for multiple reasons. In

particular, it brings jobs to the local community which is important in building mine and local

community relationship. European Nickel’s is committed to social improvement associated with all

its projects. Further, it is financially unviable to use a complete expatriate workforce. There may

also be legal obligation for a percentage of the workforce to be Albanian. Allowances need to be

made in terms of budget and schedule for the training and education of the local workforce.

The final major risk identified during construction and mine development is strikes and protesting by

the local communities. The risk is potential disruption to scheduling and degradation of European

Nickel’s reputation at an international level. Although, the area has a history of mining and the key

way to mitigate this risk is provide open and clear information to the local communities on the mine

and its expected impacts on the environment and the nearby villages, offer priority employment to

locals and use local businesses wherever possible.

Table 12 below shows the reassessment of the project risks after mitigation has been considered.

Table 12 Potential project risks during construction and development (with mitigation)

Risk Likelihood Consequence Risk Rating

Seismic events 3 3 9

Unknown geology 2 3 6

Accidents due to unskilled labour 2 3 6

Copper and steel prices 3 2 6

Strikes from locals 1 3 3

- 108 -

12.2 Operations

The major project risks during mine operations are presented in Table 13.

Table 13 Potential project risks during operations (without mitigation)

Risk Likelihood Consequence Risk Rating

Seismic events 4 5 20

Poor extraction rates 3 5 15

Low commodity prices 3 5 15

High acid/sulphur prices 3 5 15

Asbestos & silica dust 3 4 12

Rock/ore stability 3 4 12

Power Failures 4 3 12

Accidents due to unskilled labour 3 4 12

Mine acid run-off 2 5 10

Dump failure 2 4 8

Subsidence 4 2 8

Environmental and mining law changes

3 2 6

Flooding 1 5 10

Political instability 1 5 5

Seismic events have been identified as the single, greatest risk to the Devolli project during

operations. The risks during operations due to a seismic event are significantly different to those

during construction. For example, there is a much larger ´workforce underground during production

than during development. Design of underground adits need to be able to withstand a large scale

earthquake. Ventilation raises also double as emergency exit points for workers. Seismic event also

affect key surface infrastructure. This includes the heap leach pad, the leach ponds and the

permanent dump and each of these plant items need to be designed to ensure acid leaks out to the

atmosphere.

Poor extraction rates, also identified in the processing section of this report, are a major risk to the

financial success of the project. This represents the greatest technical risk of the project as many

other nickel laterite projects have failed to achieve predicted production rates and recoveries. The

sensitivity analysis section of this report determined the financial effects of inaccuracies in correctly

determining leach chemistry. The only mitigation for this risk is to undertake further test work on

Devolli ore as recommended in Section 4.3. The success of the European Nickel Caldag mine in

Turkey will also give much greater confidence in the heap leaching technology and its use in Devolli.

From the sensitivity analysis (Section 15.6), it can be seen that commodity prices, in particular nickel

prices, have the largest impact on the profitability of this project. A strategy to protect the mine

- 109 -

from low nickel prices is to hedge part or all of the produced nickel for the life of the mine. This has

the advantage of removing the risk of low nickel prices. However, peaks in nickel price are lost and

with it, a considerable amount of profit. During the feasibility or detail design stage of this project, a

baseline nickel hedge level should be established. This hedge would be only for part of the

maximum amount of nickel the mine can produce per year. The production and hedge value should

reflect the minimum production possible to not make a loss and preferably keep all employees at

reduced workloads (e.g moving from 3 to 1 shift per day). The mine should be able to maintain this

position until prices recover. Leaching times should also be reduced so that sulphuric acid

consumption is minimised.

Sulphuric acid is the highest operating cost factor in the heap leaching process. Part of the strategy

to minimise exposure to fluctuating acid prices is to construct a sulphuric acid plant. The advantages

of the sulphuric acid plant are it removes risk of high sulphuric acid prices, it produces enough

electricity to power the mine and removes environmental and personnel risk of transporting large

quantities of a highly corrosive solution to site. Disadvantages are that the OPEX is now dependent

on sulphur prices and skilled workers are required to operate the plant. One kilogram of sulphur

when processed produces approximately 2.9 kilograms of sulphuric acid. Thus, transportation to site

requirements is reduced by over 60%. A long-term sulphur contract should be established to further

remove the risk of high prices.

Asbestos crystals are found in the footwall of the mine working. Asbestos and silica dust can be

liberated during any stage of blasting, sizing or transporting the ore. These dust elements may be a

significant risk to the health of employees if it is inhaled(Department of Industry and Resource,

2001). Where blasting is done, extra ventilation needs to be used to clear the work area. Spray jets

will be used to prevent dust generation at the crusher and along the conveyors.

For the remaining risks identified, the following mitigation methods are recommended:

Rock/Ore stability o More testing of ore body

Power failures o Sulphuric acid plant powers the site and if it is down then the national grid is used.

In the unlikely circumstance of both operations being out of order, backup diesel generators are installed for ventilation until the entire workforce vacates the mine. Power can then be switched to the heap leach pond pumps until power is restored.

Accidents due to unskilled labour o Unskilled local labour will be go through education and training programs

particularly in safety before commencing on-site work

Mine acid run-off o Heap leach pad drains into oversized leach ponds. The leach ponds then overflow

progressively into the different onsite dams

- 110 -

o To prevent acid run-off from the waste stockpile, testing of waste material before reclaiming is performed and rehabilitation is completed progressively on the main dump. Water from the dump also drains to a large evaporation pond.

Dump failure

o Low wall angles have been used in the design to give very stable design. The dump will also be environmentally restored as forest land progressively throughout the mine life.

Subsidence o Subsidence is likely to occur with room and pillar (stripping of pillars) ming and will

occur with longwall mining. There is no existing infrastructure above the mine area and all mine infrastructure (particularly the dump) is designed to be located outside of the subsidence area. Subsidence area calculations can be performed after more rock quality and strength data has been collected

Environmental and mining law changes o Original design to EU standards should be sufficient.

Flooding o Although no flooding has occurred in recent years, the processing plant is located in

a large flat area near the river. The design of the area will be suited for a once in a 1000 year flood through the area.

Political instability o Albania has aspirations to join the European Union and in recent years has been

politically stable. It is very unlikely for a political situation to occur that will

dramatically affect the mine

Based on the implementation of the recommended mitigation strategies, the new project risks are

shown below in Table 14.

Table 14 Potential project risks during operations (with mitigation)

Risk Likelihood Consequence Risk Rating

Seismic events 4 2 8

Poor extraction rates 2 4 8

Low commodity prices 3 3 9

High acid/sulphur prices 3 3 9

Asbestos & silica dust 2 3 6

Rock/ore stability 2 3 6

Power Failures 1 2 2

Accidents due to unskilled labour 2 3 6

Mine acid run-off 1 5 5

Dump failure 1 4 4

Subsidence 4 1 4

Environmental and mining law changes

1 2 2

Flooding 1 3 3

Political instability 1 5 5

- 111 -

12.3 Closure

The major risks to successful closure of the mine and rehabilitation of the area are presented below

in Table 15.

Table 15 Potential project risks during mine closure (without mitigation)

Risk Likelihood Consequence Risk Rating

Mine acid run-off 2 5 10

Adverse effect on community 3 3 9

Dump failure 2 4 8

Subsidence 4 2 8

Once again, mine acid run-off has been identified as a major project risk. The same mitigation

strategies recommended in the operations phase of the mine apply here. There is also the

additional risk of the left over acid in the HA PLS and LA PLS dam. These will be diluted and

neutralised at the end of mine life. Tests of the water will be conducted to confirm it is safe for

release into the environment. Periodic testing of the dams and the water run of from the waste

dump should be carried for a number of years following mine closure.

Another risk of the mine closure is the affect it will have on the local communities; particularly in loss

of direct and indirect employment. The opening of a mine in the area will create many opportunities

for locals but upon closure, the reverse is true. The cut back of staff numbers needs to be gradual

and the staff kept aware of the mine situation. If possible, equivalent positions should be made

available to staff in other European Nickel mines. A closure of the mine should be a gradual ramp

down instead of an abrupt stop. The local community is largely agricultural based prior to mining

and there is the potential to establish new local industries post-mining in the area.

Dump failure and subsidence were also risks identified during operations and the same mitigation

strategies recommended for that period also apply during closure.

The following table shows the re-assessed project risks when considering mitigation during mine

closure.

Table 16 Potential project risks during mine closure (with mitigation)

Risk Likelihood Consequence Risk Rating

Mine acid run-off 1 5 5

Adverse effect on community 2 2 4

Dump failure 1 4 4

Subsidence 4 1 4

- 112 -

13 Mine Closure and Decommissioning

At the end of the financial exploitation of a mineral deposit, the land must be returned to a

condition as close as possible to the state it was in pre-mining. The restored land can then be

returned for public use. Mine closure and restoration plans must be developed to comply with the

Mining Law of Albania and form an integral part of the permitting process. The restoration of the

project area requires equipment and labour which both cost money. Thus, plans must be made that

sufficient funds are kept from each year of production to cover mine closure expenses. At a pre-

feasibility level, mine closure and decommission is considered at a high level. A more detailed mine

closure plan is developed during the feasibility stage of a project.

13.1 Closure Plan Development

When developing a mine closure plan, the following four main objectives constantly need to be

considered:

Protect public health and safety

Eliminate or alleviate environmental damage

Return land to its original condition or an acceptable alternative. Examples of possible

acceptable alternatives including changing original forestry into agricultural land or addition

of dams and large water bodies

Provide sustainable social and economic benefits to the local community as a result of mine

development and operations

Figure 55 below is an example of the process steps required to develop a mine closure plan.

- 113 -

Figure 55 Mine closure plan development process flow chart

As shown in Figure 55, the development of a mine closure plan is not linear and requires several re-

iterations to optimize and balance the impacts and costs.

The Devolli project was separated into the following four sub-areas for planning the

decommissioning of the mine:

1. Mine

2. Heap leach pad

3. Precipitation plant other mine infrastructure

4. Dump

Each of the sub-areas have been individually analysed and closure recommendations are detailed

below.

13.1.1 Mine

The following mine closure actives are recommended for the successful decommissioning of the

mine area:

Mine equipment will be removed and resold or decommissioned

All reagents, fuel, oil and lubricants will be removed and properly disposed

Where appropriate, hanging structures will be progressive caved to prevent sudden large-

scale collapse in the future

The adit entries and ventilation shafts will be filled with 8-10m of waste material and then

capped with concrete to prevent people entering in the future

- 114 -

13.1.2 Heap leach pad

The heap leach pad, ponds and dams will required the following decommissioning activities:

Neutralization of all areas

Surface of the leach pad with be covered with 0.5m of soil and compacted

Leach ponds and dams will be treated so that water stored can be used by future agriculture

Subsoil and then top soil will be replaced separately. Either plantation of grass for livestock

or preparation for crops will be carried out depending on community consultation and

future land owners

Because of the leach times required for the ore, the decommissioning of the heap leach pad will

occur 4 to 6 months after the mine.

13.1.3 Precipitation plant and other mine infrastructure

The precipitation plant is a large capital expenditure item that will require, at the end of the mine

life, cleaning, dismantlement and finally sold for scrap. There are two options to extend the useable

life of the precipitation plant. The first is that ore is purchased from other deposits in the area. The

second is the precipitation plant is designed to be not one large process stream but a series of

smaller, containerized units. The logic in this second design is that each part of the precipitation

plant is built into containers. This greatly simplifies the construction and decommissioning of the

plant. At the end of the mine life, the precipitation plant is disconnected and shipped to the OEM.

After refurbishment and modification in-line with latest technology, European Nickel can use the

plant at a new nickel laterite deposit for a fraction of the cost to construct a new plant.

Other closure activities that are required are:

buildings will be demolished and removed from site

equipment will be salvaged or disposed offsite

In-ground concrete pipes will be drained, crushed and buried in place

HDPE pipes and electrical power lines will be disconnected, dismantled and removed from

site

All waste material, reagents, oil and lubricants will be disposed of correctly or sold back to

the supplier if possible

Roads will remain if required based on consultation with the local community

13.1.4 Leached ore dump

Nickel laterites when freshly agglomerated can have relatively good strength and permeability but as

the ore is leached, the geotechnical properties of the ore become very poor. In particular, the

- 115 -

material’s shear strength substantially decreases and permeability often decreases by up to a factor

of 100(Steemson, et al., 2009). This has a large impact on the final design of the material dump and

slope stability. The surface dump will be re-cultivated progressively throughout the mine life as

forestry. A periodic monitoring program for measuring the performance of the dump and the

quality of the water run-off will also be necessary.

13.2 Cost of Mine Closure

Mine closure costs should be reviewed annually during production to adjust for changes in mine and

plant design and rehabilitation rates. Legislation changes and expectations of the community should

also be re-considered annually to ensure the mine closure is plan is current. Re-sale of assets and

salvage values are also difficult to estimate so they should not be considered when estimating mine

closure costs. A mine closure guideline (Steffen, Robertson and Kirsten Inc., 1992) gives the estimate

mine closure cost as US$200 per hectare and this has been used for the Devolli project. As stated

previously, a more detailed mine closure plan needs to be developed during the feasibility study and

part of this includes a detailed cost breakdown.

- 116 -

14 Market Analysis

14.1 Nickel

Nickel is a vital element used extensively in the alloying of stainless steels and in special steels for

the chemical and aerospace industry. In pure form, nickel has a shiny, silvery, metallic appearance

and is malleable and corrosion resistive (Mineral Information Institute, 2011). This transition

element has both ferrous and non-ferrous properties (US Geological Survey, 2011). In fact, nickel

is one of only three elements, the others being iron and cobalt, known to be ferro-

magnetic(Mineral Information Institute, 2011).

14.1.1 Consumption

From the smelter, nickel is generally sold for first use either as a ferronickel product or as a refined

metal (US Geological Survey, 2011). Figure 56 and Figure 57 below show the first and final uses of

nickel in the industry.

Nickel First Uses

Figure 56 Nickel by first use(Nickel Institute, 2007)

Nickel End Uses

Figure 57 Nickel by end use(Nickel Institute, 2007)

From Figure 56, it can be seen that over 60% of all nickel is used for stainless steels. A further 22% is

used for non-ferrous and other steal alloys. Part of this 22% would be for nickel-base superalloys

which are used primarily in the aerospace industry for critical jet parts such as turbine blades and in

the power industry for parts in combustion turbines (US Geological Survey, 2011). Other uses for

nickel are in rechargeable batteries, coins, catalysts and plating (US Geological Survey, 2011).

14.1.2 Production

Nickel is produced from two main deposit classifications; laterites and sulphides. Laterite ores were

the initial source of nickel when it was first produced in the last 19th century in New Caledonia.

- 117 -

However, sulphide deposits quickly became the primary nickel source in the early 20th century and

have continued to primary focus of development until the last decade(Dalvi, et al., 2004).

Total production worldwide of nickel for 2010 was 1.55 Mt (US Geological Survey, 2011). The source

of this nickel is approximately evenly split between laterite and sulphide deposits. It is estimated the

remaining surface nickel resources (with average grades of over 1.0% Ni) contain 130 million tonnes

of nickel. Of this 130 million tonnes, 60% is located in laterite sources and the remaining 40% in

sulphide deposits(US Geological Survey, 2011). Figure 58 below identifies the major nickel

producing countries.

Figure 58 Nickel Production in 2010 by Countries(US Geological Survey, 2011)

14.1.3 Supply and demand

Supply of nickel is predicted to increase based upon several large projects coming online and moving

towards full capacity including (US Geological Survey, 2011):

At the Toamasina complex in Madagascar, the Ambatovy laterite deposit is expected to

produce 60kt of nickel per annum from 2011 onwards

the Goro laterite project in New Caledonia is scheduled to reach full production of 60kt Ni

per annum in 2013

expansion projects at the Vale Onca Puma mine in Brazil and the First Quantum

Ravensthorpe mine to 53kt and 39kt of nickel per annum respectively

Despite this increased supply, it is expected that rising demand for nickel will outstrip this surplus

supply and that the introduction of the Devolli project will not significantly impact the market.

China continues to be a major consumer of mineral product, including an ever-increasing demand

for stainless steel. It is also anticipated that countries such as India, Russia and Brazil will add

- 118 -

further pressure to the demand for stainless steel to meet their rising modernisation needs

(eResearch Corporation, 2009).

Other sources of increased nickel consumption are the automotive industry and the aeronautical

industry (US Geological Survey, 2011).

14.1.4 Alternatives/Substitutes

The large fluctuation of nickel prices in recent times has directly influenced the price of stainless

steels. It has been reported that construction companies are substituting stainless steel with other

low-nickel steels. Nickel-free speciality steels and titanium alloys are being used more frequently to

avoid high-nickel products(US Geological Survey, 2011).

The greatest risk to the price of nickel is the use of Chinese nickel pig iron (NPI) for the production of

low grade stainless steels. NPI is produced from high-iron laterite ores containing a low nickel grade.

Costs in China to produce NPI were predicted to be between US$ 7 and US$ 8 per pound including

credits from extra iron production and high iron ore costs at the time(Louiseize, 2008). The article

goes on to predict a nickel ceiling price of US$8/lb. Total NPI production capability in China is just

under 100kt of nickel per annum which is a significant addition to the market(Reuters, 2010).

14.1.5 Historical pricing

The price of nickel, as noted earlier, has greatly fluctuated in recent years. Figure 59 below shows

the average price of nickel from 1958 to 2010 in terms of actual value in that year and value in

today’s currency.

Figure 59 Average price of nickel from 1958 to 2010(Kuck, 1998; LME, 2011; inflationdata.com, 2011)

- 119 -

The global economic recession in late 2008 and 2009 significantly impacted on the price of nickel as

reported in the graph above (US Geological Survey, 2011). In mid-May 2007, nickel prices reached

an all time high on the London Metal Exchange (LME) with the buyer’s spot price exceeding

US$54,000 per tonne or US$24.5 per pound (Figure 60 below). Over the following three month

period the price dropped back to approximately US$12.7 per pound, almost half of the peak price

and in October 2010, the spot price for nickel fell as low as US$4.5 per pound. Since then, the price

of nickel has recovered rising to and remaining over US$9 per pound since June 2010. The average

nickel spot price on the London Metal Exchange for the month of April, 2011 was US$12 per pound.

Figure 60 LME spot prices for nickel over last 5 years(LME, 2011)

14.1.6 Future price prediction

The following price predictions for nickel have been forecast for the coming years:

Jim Lennon, executive director in commodities research with Macquarie Bank Limited in

London predicts a nickel ceiling price of US$8/lb due to the cost to produce Chinese nickel

pig iron as an alternative (Louiseize, 2008)

IGE Resources recently released the results of Preliminary Economic Assessment for their

nickel-sulphide Rönnbäcken project in Sweden. A nickel price of 9 US$/lb was used for the

base case economic analysis (IGE, 2011).

eResearch Corporation, based on expected demand in China, India, Russia and Brazil, have

predicted a 5-year nickel forecast nickel price ranging from 10 - 15 US$/lb (eResearch

Corporation, 2009).

Mindoro Resources recently completed the Preliminary Economic Assessment for the Agata

Nickel-laterite project in the Philippines. A nickel price of US$10/lb was used for the base

case economic analysis (Mindoro Resources Ltd., 2011).

- 120 -

Credit Suisse forecast a 2010 spot price of US$5.50/lb and long-term spot price of

US$6.50/lb(Credit Suisse, 2009). This price estimate was based on predicted over-supply

with several new projects coming online.

14.1.7 Project Pricing

Based on the market analysis and on recently completed studies for other nickel deposits, a nickel

price of US$9 /lb has been selected for this project.

14.2 Cobalt

Cobalt is a transition element that is bluish-white in appearance. It is a hard, brittle metal and is also

ferromagnetic. Since ancient times, cobalt compounds have been used to produce the colour blue in

ceramics and glass and in more recent-times, cobalt has been used extensively in alloys, batteries,

and as catalysts.

14.2.1 Consumption

Cobalt is primarily used for alloying in aircraft engine parts as well as wear and corrosion resistant

metals (Chermicool, 2011). Other uses for cobalt include rechargeable battery compounds and in

superalloys(US Geological Survey, 2011). Figure 61 below shows the variety of industries and

applications of cobalt.

Figure 61 Consumption of cobalt(Geovic Mining Corp, 2009)

14.2.2 Production

Cobalt is produced worldwide typically as a bi-product of either nickel or copper. In 2009, a total of

62,000 tonnes of cobalt was produced. The source of the cobalt is displayed below in Figure 62.

- 121 -

Figure 62 Cobalt producing countries of 2009(US Geological Survey, 2010)

14.2.3 Supply and Demand

The demand of cobalt is expected to increase over the next ten years and increased supply will be

needed to meet this demand (see Figure 63). By 2013, it is expected an additional 22,000 t of cobalt

per annum will be sold on the market with nickel-cobalt and copper-cobalt plants starting up in the

DRC, Australia, Indonesia, New Caledonia, PNG and Zambia(Geovic Mining Corp, 2009). This extra

capacity is inadequate to meet the rising demand that is predicated.

Figure 63 Cobalt past and predicted future supply and demand needs(Geovic Mining Corp, 2009)

14.2.4 Alternatives and substitutes

Substitution of cobalt depends on the particular application. In alloys, the substitution of cobalt will

result in a lower-grade product. Barium or nickel-iron alloys are potential alternatives for cobalt in

- 122 -

magnets. Nickel-based alloys or ceramics could be considered for engine parts. Cobalt is also used

in the oil and gas industry as a catalyst however nickel and hydroformylation catalysts are also

options.(US Geological Survey, 2010)

14.2.5 Historical pricing

Historically, cobalt prices have been determined by private contracts. On February 23, 2010, the

London Metal Exchange listed cobalt as a traded minor metal. Since listing, prices for the

commodity have generally floated between 36,000 and 39,000 US$/tonne though it has briefly

reached extreme maximum and minimum values of 44,500 and 34,000 US$/tonne(LME, 2011).

14.2.6 Project pricing

Based on the market research and price history, the cobalt price used for the project has been set at

a conservative US$ 37500/t (US$17/lb).

- 123 -

15 Economic Appraisal

15.1 Currency and Inflation

All CAPEX and OPEX estimates have been calculated in US Dollars. Nickel and cobalt pricing, as well

as smelter and refining charges, are also defined in US dollars. This means there is no significant

currency conversions for this project. During the feasibility study, the effects of Euro-US$ exchange

rate may should be considered if a significant amount of steel or machinery is being purchased from

within Europe.

As is common practice, inflation has not been incorporated in the discounted cash flow model. The

use of a discount rate covers reasonable future inflation.

15.2 Net Smelter Return

The net smelter return (NSR) costs were based on information supplied by Outotec(Lovén, 2009).

Table 17 summarises the key cost and pay elements.

Table 17 Net smelter return parameters

Payable Metals:

Nickel (Ni) 100% payable after 1.3% unit deduction

Copper (Cu) 90% payable

Cobalt (Co) 45% payable

Treatment Charge: 1.1 US$/lb payable nickel

Refining Charge:

Copper (Cu) 30% of copper price

Cobalt (Co) 35% of cobalt price

Penalty Elements: MgO, As,

15.3 Financial Model

The financial model used to evaluate this project was “discounted cash flow”. There are several key

variables to this model including:

Taxation rates and royalties

Discount rate

Depreciation

Pre-production time

Each of these parameters are analysed in detail below.

- 124 -

15.3.1 Corporate tax and royalties

The corporate taxation rate in Albania is a fixed rate of 10%(European Nickel, 2010). Tax is applied

on corporate profits after interest, depreciation and amortization.

Royalties are defined in the Mining Law of Albania to be 2% of the market value of the overall sold

mineral quantity. The 2% royalty is paid on all payable minerals before smelter/treatment charges

and deductions are considered.

15.3.2 Discount rate

A discount rate of 12% was selected for valuing the net present value (NPV) of the project. This

project is not without risk however it is in a politically stable country that actively encourages foreign

investment into the mining industry. The future outlook for nickel is positive with a favourable

deficit in sufficient future supply being anticipated. The discount rate is slightly to those used in

other nickel-laterite projects or for projects in Albania.

15.3.3 Depreciation

Depreciation is calculated using the straight line method (European Nickel, 2010). This is to be in

accordance with the Albanian tax regulations. Table 18 below shows the allowable rates for

different assets.

Table 18 Depreciation allowances

Asset Type Rate

Buildings and equipment 5%

Intangible assets 15%

Computers & IT systems 25%

Other depreciable assets 20%

Buildings include the cost to purchase or construction and any restoration or renovation

expenditure. It also includes the purchase of all long term fixtures and fittings.

Most of the depreciable capital expenditure is on infrastructure and equipment. Only a small

percentage of depreciable assets fall outside of this category. Thus, the depreciation rate of 5% will

be used.

15.3.4 Pre-production Time

Pre-production has been estimated at 2 years based on the schedule. Within this two year

timeframe, the mine design will be finalised; all mining equipment purchased and delivered; the

adit/s to the underground completed; and all ponds and the majority of the leach pad constructed.

Mining can commence before the completion of the precipitation plant due to the long leach times

and thus is not included in calculating the pre-production time.

- 125 -

15.3.5 Value added taxes

Albania has a value-added tax (VAT) rate of 20%. It has been stated by the client that the project will

be entitled to exemption from this tax for a majority of the imported equipment (European Nickel,

2010). Thus, VAT is not considered for any equipment and no percentage rate is applied.

15.3.6 Summary of discount cash flow model parameters

The key parameters required for the cash flow model are summarized below in Table 19.

Table 19 Discounted cash flow model parameters

Parameter Value

Corporate taxation rate 10%

Royalties 2%

Depreciation 5%

Discount rate 12%

Value-added tax 0%

Pre-production time 2 years

15.4 Base Case Results

There were seven different mining scenarios and 32 different raw material handling/processing

options that were costed for this project. Table 20 below shows the valid relationship between the

two sets. The mining codes are explained in Section 5.6 and the raw material handling/processing

options are detailed in Section 6.2.

Table 20 Valid mining & material handling/processing options

OPTIONS MINE

PROCESS 1RP1 1PP1 1LW1 2RP1 2PP1 2RP2 2PP2

1Pno1A TR y y

1Pno2A TR y y

1Pno2A CV y y y

1Phl1A TR y y

1Phl2A TR y y

1Phl1A TRms y y

1Phl2A TRms y y

1Phl2A CV y y y

1Phl2A CVms y y y

1Phl2A CVss y y y

1Phl2A CVmsss y y y

1Phl2A CVmsTR y y y

1Phl2A CVssTR y y y

1Phl2A CVmsssTR y y y

2Phl1A TR y y

2Phl2A TR y y

- 126 -

2Phl1A TRms y y

2Phl2A TRms y y

2Phl2A CV y y

2Phl2A CVms y y

2Phl2A CVss y y

2Phl2A CVmsss y y

2Phl2A CVmsTR y y

2Phl2A CVssTR y y

2Phl2A CVmsssTR y y

2Phl3A CV y y

2Phl3A CVms y y

2Phl3A CVss y y

2Phl3A CVmsss y y

2Phl3A CVmsTR y y

2Phl3A CVssTR y y

2Phl3A CVmsssTR y y

There are in total 72 valid combinations. The NPV was calculated for each of these options with cut-

of-grades ranging between 0.0% nickel and 1.3% nickel and production rates between 1000 and

15000 tonnes per day. The full list of results is attached in Appendix L. Table 21 below is a

summary of each of the mining options with their most financially profitable raw material handling

and processing method.

Table 21 Financial results for the different mining options

Mine Option

RMH/Process Option Cut-of-Grade (%Ni)

Production Rate (tpd)

NPV (M$)

IRR Payback Period

1RP1 1Phl2A CVmsTR 0.8 2000 -34 -6% -

1PP1 1Phl1A TRms 0.8 2000 -42 -6% -

1LW1 1Phl2A CVmsTR 0.7 5000 -21 7% 5

2RP1 2Phl2A CVmsTR 0.8 2000 -49 -14% -

2PP1 2Phl2A CVmsTR 0.9 2000 -58 -18% -

2RP2 2Phl3A CVmsTR 0.8 2000 -69 - -

2PP2 2Phl3A CVmsTR 0.9 2000 -77 - -

One of the largest OPEX items for the Devolli project is the cost of sulphur to produce sulphuric acid.

Table 22 below is a summary of key financial parameters for each mining method with a 20%

reduction in the sulphur price.

Table 22 Financial results for the different mining options with 20% reduction in sulphur price

Mine Option

RMH/Process Option Cut-of-Grade (%Ni)

Production Rate (tpd)

NPV (M$)

IRR Payback Period

1RP1 1Phl2A CVmsTR 0.5 4000 -23.0 5% 5

1PP1 1Phl2A CVmsTR 0.7 4000 -27.8 3% 5

1LW1 1Phl2A CVms 0.5 10000 15.6 15% 4

- 127 -

2RP1 2Phl2A CVmsTR 0.6 3000 -36.5 0% -

2PP1 2Phl2A CVmsTR 0.7 3000 -53.9 -8% -

2RP2 2Phl3A CVmsTR 0.6 4000 -58.9 -7% -

2PP2 2Phl3A CVmsTR 0.7 4000 -68.5 -9% -

15.5 Financial Appraisal

For a project to be considered for further development at the end of the pre-feasibility stage, the

following criteria usually need to be met:

A positive NPV

IRR over 20% or 25%

Undiscounted payback period of 2 or 3 years

Based on Table 21 above, none of the mine options have a positive NPV and thus are unsuitable for

further development. The results were re-run with sulphur price reduced by 20%. In this case, the

longwall mining option produced a positive NPV. The payback period of 4 years and only an IRR of

15% meant that this option was still unacceptable.

Two options were selected for sensitivity analysis. The first in the longwall option with conveyors to

the heap leach pad via a mine stockpile (1Phl2A CVms) since it was the only option that gave a

positive NPV. The second option analysed in more detail is the single product room-and-pillar option

(1RP1) with conveyors from underground to the mine stockpile and the remaining transportation by

surface trucks (1Phl2A CVmsTR).

15.6 Sensitivity Analysis

The sensitivity analyses were performed to give an indication of the effect different variables have

on the profitability of the project. The following two analyses were performed for the two options

selected above:

Net Present Value verse Variations in Four Key Cost Factors

Net Present Value zero-line due to nickel and sulphur price

15.6.1 Variations in Four Key Cost Factors

The first sensitivity analysis is a study on the effect four key cost elements have on the total project.

The spider graph produced will give a reasonable indication on when this project will become

financially interesting. The four parameters identified as having the largest effect on the project

NPV, their base values and their maximum and minimum values are summarised in Table 23 below.

The minimum and maximum values were calculated using ±25% of the base value.

- 128 -

Table 23 Sensitivity analysis key parameters

Parameter Unit Min Value Base Value Max Value

Nickel Price US$/lb 6.75 9 11.25

Sulphur Price US$/tonne 150 200 250

Heap leach recovery % 52.5 70 87.5

Treatment charges US$/lb Ni 0.825 1.1 1.375

Figure 64 below shows the result of the sensitivity analysis for the longwall mine and Figure 65 for

the room and pillar mine.

Figure 64 Sensitivity analysis for room-and-pillar option

Figure 65 Sensitivity analysis for longwall option

The sensitivity analyses were quite similar for both options and the scale of the effect due to each

parameter is comparable. Nickel price has the largest impact on the overall project profitability. The

second most critical factor was the price of sulphur which altered the final NPV of longwall option by

- 129 -

more than ± USM 150 with only a change of 25% in the price. Sulphur prices have been more than

±50% from the base price in the past. Nickel recovery did not have such a large impact on the NPV

although this was anticipated the acid consumption is directly linked to nickel recovery.

15.6.2 Net Present Value zero-line due to nickel and sulphur price

Although the project is no feasible now, there will be a time in the future that it will be. The NPV

zero-line is a graph that is designed to give some indication of what nickel/sulphur price the project

once again becomes a possibility. The results are shown below in Figure 66 and Figure 67.

Figure 66 NPV zero-line due to nickel and sulphur price for room-and-pillar option

Figure 67 NPV zero-line due to nickel and sulphur price for longwall option

- 130 -

The zero-line is the blue line in both Figures and it represents at what point the project has a positive

NPV. The project needs to be below and right of this line to make money. To give a concept of

scale, lines showing NPVs of US$ 50, 100 and 150 million have also be included. Thus for the

longwall project to make over US$150M will a sulphur price of US$ 200 / tonne, a long-term nickel

price of over US$11.50 per pound is required.

- 131 -

16 Recommendations

Unfortunately, at the present time the Devolli nickel project is not financially viable in the

foreseeable future unless there is a rise in nickel prices or a sharp drop in sulphur prices. It is the

recommendation of this report that European Nickel ceases investigation into this deposit.

In the future if market conditions are favourable to the reassessment of the Devolli project, it is

strongly recommended that the following test work be completed before the project enters

feasibility:

Closer-spaced, surveyed drilling throughout the deposit particular to confirm ore boundaries

and to identify and accurately map faults

Mapping of the different laterite zones (saprolite, transition and limonite) is completed by an

onsite geologist

Geotechnical core tests on more samples from different areas around the deposit to form a

representative estimate of conglomerate, ore and serpentinite geotechnical parameters

Additional leach column tests on both mixed and saprolite ore so that an accurate model of

leach kinetics can be constructed and optimized

Leach testing should be performed to imitate a stope leaching operation as it is anticipated that

operating costs and available resource will be favourable compared to traditional methods

- 132 -

17 Conclusion

This report concludes that mining the Devolli deposit is not feasible and that the project should not

be progressed further in the design stage in the foreseeable future.

The project has an indicated resources of 48.7 million tonnes of laterite ore with average grade of

nickel of 1.13% and cobalt of 0.04%. Closer drillholes sampling and mapping of the different laterite

zones is required before this resource could be upgraded.

The project was designed with two different mine systems; room-and-pillar and longwall mining.

The variation of the room-and-pillar design Post room-and-pillar was also costed. The geotechnical

information supplied by the Client may have been excessively conservative due to the lack of quality

assurance information for the samples. This led to a conservative design for the room-and-pillar

method and low level of extraction.

The processing technologies for nickel laterite ores were reviewed and heap leaching was selected

as the most appropriate. The main reasons heap leaching was viewed as the most appropriate was

it suited the Devolli ore, has a low power consumption and European Nickel have a history with this

type of plant. A slight alternative to the normal heap leach design is the creation of two leach pads;

a quick leach pad for saprolite ore and a long leach pad for mixed ore. Due to insufficient column

test data, this option could not be fully explored but may be a point of interest in future studies. The

cost of processing the nickel laterite ores is many times the mining cost. This is due to the large

amounts of sulphuric acid required; over 500kg per tonne of ore. A sulphuric acid plant was

recommended for the project to reduce the cost of acid and risk of large fluctuations in acid prices.

Despite this, sulphur still is the largest cost for the operation of the mine and a long term supply

contract may be the most suitable way to mitigate this risk.

An environmental impact assessment was completed for the Devolli project. It was found that there

are no significant risks to environment that cannot be mitigated with reasonable design choices and

policies.

- 133 -

18 Bibliography

alba global Railroads in Albania [Online] // alba global. - 2009. -

http://www.albaglobal.com/modules.php?name=Albania&pa=list_pages_categories&cid=22&where

=Moving%20to%20Albania/Transport.

AlbanianEconomy.com Albania government starts new mammoth road project [Online] //

AlbanianEconomy.com. - 29 April 2011. -

http://www.albanianeconomy.com/news/2011/04/29/albania-government-starts-new-mammoth-

road-project/.

Aliaj S [et al.] PROBABILISTIC SEISMIC HAZARD MAPS FOR ALBANIA [Conference] // 13th World

Conference on Earthquake Engineering. - Vancouver : [s.n.], 2004.

Aliaj Shyqyri SEISMOGENIC MODELS FOR ALBANIA:OVERVIEW OF RELEVANT DATA [Conference] //

HARMONIZATION OF SEISMIC HAZARD MAPS FOR THE WESTERN BALKAN COUNTRIES. - Ljubljana :

[s.n.], 2007.

Alpay Serafettin and Yavuz Mahmut Underground mining method selection by decision making

tools [Article] // Tunnelling and Underground Space Technology. - 2008. - Vol. 24.

Arkaxhiu F and Onuzi K IRON-NICKEL AND NICKEL SILICATE ORES OF ALBANIA [Journal]. - Tirana :

[s.n.].

Bartlett R. Solution mining; leaching and fluid recovery of materials [Book]. - [s.l.] : Gordon and

Breach, 1992.

Brady B. H. G. and Brown E. T. Rock Mechanics for underground mining [Book]. - Dordrecht, The

Netherlands : [s.n.], 2004.

Calgon Carbon Corp. Calgon [Online] // ISEP System: Continuous ion exchange separations. - 2004. -

http://www.calgoncarbon.com/carbon_equipment/documents/ISEP_System.pdf.

CEZ Electricity Market in Albania [Online] // CEZ. - 2011. - http://www.cez.al/en/prices/electricity-

market-in-albania.html.

Chan Guizhen Pressure Acid Leaching of Nickel Laterite [Report]. - [s.l.] : The University of British

Columbia, 1998.

Chan Guizhen Pressure Acid Leaching of Nickel Laterite [Report]. - [s.l.] : The University of British

Columbia, 1998.

- 134 -

Chase Frank, Worley Phyllip and McComas Allen Longwall Shield Recovery Using Mobile Roof

Supports [Conference]. - 2006.

Chermicool Cobalt Element Facts [Online] // Chemicool. - 21 February 2011. -

http://www.chemicool.com/elements/cobalt.html.

Christopher Peter A TECHNICAL SUMMARY REPORT GJEGJAN PROJECT, ALBANIA [Report]. -

Vancouver : [s.n.], 2009.

CIA Central Intelligence Agency [Online] // World Factbook: Albania. - May 17, 2011. -

https://www.cia.gov/library/publications/the-world-factbook/geos/al.html.

Credit Suisse Australian Junior Nickels [Online] // Scribd. - March 26, 2009. -

http://www.scribd.com/doc/37056779/Nickel-Market.

Culture Crossing Albania [Online] // Culture Crossing. -

http://www.culturecrossing.net/basics_business_student_details.php?Id=12&CID=2.

Dalvi Dr. Ashok D., Bacon Dr. W. Gordon and Osborne Mr. Robert C. The Past and the Future of

Nickel Laterites [Conference] // PDAC 2004 International Convention. - Ontario, Canada : [s.n.], 2004.

Dalvi Dr. Ashok D., Bacon Dr. W. Gordon and Osborne Mr. Robert C. The Past and the Future of

Nickel Laterites [Conference] // PDAC 2004 International Convention. - 2004.

Dalvi Dr. Ashok D., Bacon Dr. W. Gordon and Osborne Mr. Robert C. The Past and the Future of

Nickel Laterites [Conference] // PDAC 2004 International Convention. - Ontario, Canada : [s.n.], 2004.

Department of Industry and Resource MANAGEMENT OF ASBESTOS IN MINING OPERATIONS

[Report]. - Perth : [s.n.], 2001.

Department of Resources, Tourism and Industry Risk Assessment and Management [Online] //

Department of Resources, Tourism and Industry. - May 2008.

Energy Community Regulatory Board National Report: Albania [Report]. - 2008.

eResearch Corporation eResearch: The Nickel Market [Online] // http://www.investorideas.com. -

February 2009. - http://www.investorideas.com/Research/PDFs/Nickel_Feb_2009.pdf.

European Nickel EMC Case Study - Student Introduction [Report]. - 2010.

GBM SCOPING STUDY FOR NICKEL LATERITE OPTIONS IN ALBANIA FOR BALKAN RESOURCES

[Report]. - 2008.

- 135 -

Geovic Mining Corp Cobalt Mining & Cobalt Demand [Online] // Geovic Mining Corp. - 2009. -

http://www.geovic.net/cobalt_mining.php.

Human L, Doolan J and Potts L Mine Wide Risk Assessment – What is the State of your Arteries

[Conference] // Queensland Mining Industry Health and Safety Conference. - Brisbane : [s.n.], 2006.

Hustrulid William A. Underground mining methods: engineering fundamentals and international

case studies [Book]. - [s.l.] : SME, 2001.

ICIS Sulfuric acid market seeks balance [Online] // ICIS.com. - Sep 3, 2010. -

http://www.icis.com/Articles/2010/09/06/9390780/sulfuric-acid-market-seeks-balance.html.

IGE Updated Preliminary Economic Assessment adds resources and value to the Rönnbäcken Nickel

Project [Online] // IGE. - 30 March 2011. - http://www.ige.se/pressreleases.aspx?r_id=558796.

inflationdata.com Historical Inflation [Online] // inflationdata.com. - Apr 2011. -

http://inflationdata.com/inflation/Inflation_Rate/HistoricalInflation.aspx?dsInflation_currentPage=4

.

Joint Ore Reserves Committee (JORC) The JORC Code: Australasian Code for Reporting of

Exploration Results,Mineral Resources and Ore Reserves. - 2004.

King M. Nickel Laterite Technology - Finally a New Dawn? [Journal] // Journal of the Minerals, Metals

and Materials Society. - 2005.

Kuck Peter H. Nickel [Online] // USGS Minerals: Nickel. - 1998. -

http://minerals.usgs.gov/minerals/pubs/commodity/nickel/500798.pdf.

LME Cobalt Price Graph [Online] // London Metal Exchange. - May 22, 2011. -

http://www.lme.com/minormetals/cobalt_graph.asp.

LME LME Nickel price graph [Online] // London Metal Exchange. - 22 May 2011. -

http://www.lme.com/nickel_graphs.asp.

Louiseize Kelly Creating a ceiling for future nickel prices: China's solution to high-priced nickel

[Online] // Northern Ontairo Business. - 15 December 2008. -

http://www.northernontariobusiness.com/Industry-News/mining/Creating-a-ceiling-for-future-

nickel-prices.aspx.

Lovén Pekka Outotec: Mining Technology and Economics Lectures [Report]. - Helsinki, Finland :

[s.n.], 2009.

- 136 -

Mindoro Resources Ltd. Mindoro Commences Agata Nickel Pre-Feasibility Study and Makes Key

Appointments [Online] // Mindoro Resources Ltd. Press Releases. - 21 April 2011. -

http://www.mindoro.com/s/PressReleases.asp?ReportID=452910&_Type=Press-

Releases&_Title=Mindoro-Commences-Agata-Nickel-Pre-Feasibility-Study-and-Makes-Key-

Appointm....

Mindoro Resources Ltd. Mindoro Commences Infill Drilling of High Grade Nickel Laterite at Agata

Project. [Online] // Mindoro Resources Ltd.. - 09 04 2010. -

http://www.mindoro.com/s/PressReleases.asp?ReportID=394204&_Title=Mindoro-Commences-

Infill-Drilling-of-High-Grade-Nickel-Laterite-at-Agata-Pr.

Mineral Information Institute Mineral Photos - Nickel [Online] // MII: Mineral Information

Institute. - 2011. - http://www.mii.org/Minerals/photonickl.html.

Morrison R.G.K. AW Philosophy of Ground Control [Journal]. - McGill University, Montreal, Canada :

[s.n.], 1976.

Myszkowski M and Paschedag U Longwall mining in seams of medium thickness [Report]. - [s.l.] :

Bucyrus, 2010.

NASA GISS Surface Temperature Analysis (GISTEMP) [Online] // National Aeronautics and Space

Administration: Goddard Institute for Space Studies. - 2011. -

http://data.giss.nasa.gov/work/gistemp/STATIONS//tmp.601136290000.1.1/station.txt.

Nicholas D.E. Method Selection – A Numerical Approach. Design andOperation of Caving and

Sublevel Stoping Mines [Conference] // SME-AIME. - New York : [s.n.], 1981.

Nickel Institute Nickel and its Uses [Online] // Nickel Institute. - 2007. -

http://www.nickelinstitute.org/index.cfm/ci_id/13.htm.

Ozfirat M and Gonen S A brief comparison of longwall methods used at mining of thick coal seams

[Conference]. - Izmir, Turkey : [s.n.], 2005.

PWK Resources Devolli Nickel Feasibility Study [Report]. - Delft, The Netherlands : [s.n.], 2010.

PWK Resources Devolli Nickel Feasibility Study [Report]. - Delft, The Netherlands : [s.n.], 2010.

PWK Resources Devolli Nickel Feasibility Study [Report]. - Delft, The Netherlands : [s.n.], 2010.

PWK Resources Feasibility of Devolli Nickel Project [Report]. - Delft, The Netherlands : [s.n.], 2010.

- 137 -

Reuters China's nickel pig iron output rises on price, demand [Online] // Reuters. - 27 April 2010. -

http://www.reuters.com/article/2010/04/27/china-nickel-idUSTOE63Q08420100427.

Sharples B. tehage.com.au [Online] // BHP to tackle Ravensthorpe's laterite. - May 20, 2008. -

http://news.theage.com.au/business/bhp-to-tackle-ravensthorpes-laterite-20080520-2ga0.html.

SME SME Mining Engineering Handbook [Book]. - 1992. - Vol. 2ed.

Steemson ML and Smith ME THE DEVELOPMENT OF NICKEL LATERITE HEAP LEACH PROJECTS

[Conference] // ALTA 2009 Nickel/Cobalt Conference. - Perth, Australia : [s.n.], 2009.

University of New South Wales UNSW Risk Consequence Assessment Tool [Online] // UNSW. - 19

March 2010. -

http://www.fin.unsw.edu.au/files/forms/rmu/UNSW_Risk_Risk_Assessment_Tool.pdf.

US Geological Survey Cobalt [Online] // USGS. - 18 May 2011. -

http://minerals.usgs.gov/minerals/pubs/commodity/cobalt/.

US Geological Survey Cobalt (2010 report) [Online] // USGS. - January 2010. -

http://minerals.usgs.gov/minerals/pubs/commodity/cobalt/mcs-2010-cobal.pdf.

US Geological Survey Nickel [Online] // USGS: Minerals. - 18 April 2011. - 21 May 2011. -

http://minerals.usgs.gov/minerals/pubs/commodity/nickel/.

US Geological Survey Nickel (2011 report) [Online] // USGS: Minerals. - January 2011. - 21 May

2011. - http://minerals.usgs.gov/minerals/pubs/commodity/nickel/mcs-2011-nicke.pdf.

USGS Earthquakes Albania [Online] // USGS Earthquakes. - May 28, 2011. -

http://earthquake.usgs.gov/earthquakes/recenteqsww/Quakes/us2009lfb6.php.

WA Today watoday.com.au [Online] // BHP sells Ravensthorpe mine for $376 million. - Dec 9,

2009. - http://www.watoday.com.au/business/bhp-sells-ravensthorpe-mine-for-376-million-

20091209-kio7.html.

Wedderburn B. Nickel Laterite Processing: A shift towards heap leaching [Conference] // ALTA

Conference. - Sydney : [s.n.], 2009.

World Weather Online KORCE, ALBANIA WEATHER AVERAGES [Online] // World Weather Online. -

2011. - http://www.worldweatheronline.com/weather-

averages/Albania/50709/Korce/56988/info.aspx.

- 138 -