Report No. 10300-84
September 2000
AEi_OJ_--'lr"
IntegratedAdvanced Microwave Sounding Unit-A (AMSU-A)
Monthly Report for August 2000
Contract No: NAS5-32314
CDRL 529: (Including CDRL 004, 203, 204, and 503)
Submitted To:
National Aeronautics and Space Administration
Goddard Space Flight Center
Greenbelt, Maryland 20771
Submitted By:
Aerojet1100 West Hollyvale Street
Azusa, California 91702
Aerojet
https://ntrs.nasa.gov/search.jsp?R=20000097380 2020-04-28T13:35:19+00:00Z
Report No. 10300-84September 2000
Integrated
Advanced Microwave Sounding Unit-A (AMSU-A)
Monthly Report for August 2000
Contract No: NAS5-32314
CDRL 529: (Including CDRL 004, 203, 204, and 503)
Submitted To:
National Aeronautics and Space Administration
Goddard Space Flight Center
Greenbelt, Maryland 20771
Submitted By:
Aerojet
1100 West Hollyvale Street
Azusa, California 91702
Report No. 10300-84September 2000
SECTION
1.0
2.0
3.0
3.1
3.1.1
3.1.2
3.1.3
3.2
3.2.1
4.0
5.0
6.0
7.0
Appendix A
TABLE OF CONTENTS
Introduction
90 Day Window Schedule and Float Report
Status Reports
Program Overview
Program Review Status
Program Priority List
Action Items, Manpower
Weekly Reports
Spare/Task Assignment, System Engineering & Test (SEIT) andPerformance Assurance (CDRL 204)
Drawing Status (not available this report)
Weight and Power Budgets (CDRL 503)
Configuration Management Status Report (CDRL 203)
Document/Data Management Status Report
AMSU-A 90 Day Window Schedule
Float Report
Report No. 10300-84September 2000
Section I
INTRODUCTION
This is the 91st Monthly Report for the Advanced Microwave Sounding
Unit-A (EOS/AMSU-A), Contract NAS5-32314, and covers the period from
01 August through 31 August 2000.
Included in this report are Combined Program Delivery Schedules and
Reports (Section 2); a report from the Product Team Leaders on the status of
all major program elements (Section 3); Contract Data Requirements List
(CDRL) 503, the Weight and Power Budgets (Section 5); CDRL 204,
reporting on the activities of Performance Assurance (Section 3.2.1); CDRL
203, the Configuration Management Status Report (Section 6); and the
Documentation/Data Management Status Report (Section 7).
Report No. 10300-84
September 2000
Section 2
The AMSU-A and Combined Program 90 Day Window Schedule is
presented as Appendix A.
2
;I
L_
llm
m
<
<m
m
o o o _ o o o
<
I,.
I.I._
C
CLG)rr
14.v
(.-
6
>
Z
0
<
.-j
¢0 eO I_
i
h-
E
._-=_I11 < u.
>(p
Z
d
oo
o
c-O
$
0
e-
CD
"0m
mm
m
<_
u)
<_
0
O_
I1.
a
Z
0
¢J)
<I:
"--3
u_
a
Z
0
o
C
._o
Eo
E
i!
ii!i
i l ,-- I
I i °i'
i ' I
• l
I" 'i
i °i I
i I
i "
; oiI "
!1
!
i
!
¢-
_ o
O.
|
EE
m cm< ._0 C
um
_=
e-
gE
0
a
>
.g-i-
n
!ll!.-(_
i
0
"6
g
(/)=E
t
I
,. i
!I
I
II
I ,
I
"I"
II
I
II
I
II
I I
, ,,I
! l
t_
suo!leld,,,oo pelnpeqos
01
_8
_o"3
_oo=E
_oo_8
_ooU.
_=oo
z
o_
u)
==
=E
u.
=._
Z
O_
(3
E
p..
0
P_
¢0
r_
o
E
n-
03
o_.J
l
11
Report No. 10300-84September 2000
3.1.1
3.1.2
Program Review Status
Completed 109 A1 Pre Ship Review; production efforts now
complete.
Program Priority List for the Month of August
1. Support TRW, Lockheed-Martin and Europeans on
spacecraft integration tasks.
2. Complete checkout of spare components. Visited Filtronics,
and spares are now being worked. Only open item is
performance of-8.
3. Maintain/retest hardware located at Aerojet as required.
12
oo0o
O"ro
,,m,_ _. _ o_
o
<
UJ
<_ d "-
_0 0 _ :_
NI_. _ _rO frO--_ _ O_ _-zo r-, _._ o0.
z _ o _ -'_ILl rr
ui
0
0
o
qo
reLIJ
n-O
<I-
qo
q
qo
r,-
I,J
_1,<I-0I-r_Z,<n-O
< _ -_l.r.1
=,_- N
-- d
_1 0 e-,I-., ,o ¢;
• "_ _ _
< ,,, _:Zg g ,._,.,. u._.- E =_
o "" _
N>. -o
0m
<Z
16
l-irO11.l..IJIr
Ir:DO"1-
!
Z,<
I-.ZIII.--I
>m
:DClIII>--J
III
,,<!
;D
ClIIII-.
Irt_UJI--Zm
O"O
_ I.i.I ,,- ,,- o ,,_
oi=i o ,_l.i _I.
,< ,< _. o. o
>..
I,I.I ,,-
I_ _
(5:D "<_ m. _. ._ "!.,,,_ o © _ ,-irl.U,.J
°D I,-
o oo'o ,5 _
N g
_o _. _ _ <7OC_ o. 0
0
18
I
z0
<
C
<C
DC
<
<
©
<
0
<
<
,- _ -'_
°_
=.= -_
_- ,- 121
f'-I
0
0
ffl
Report No. 10300-84September 2000
3.2 Weekly Reports
3.2.1 Spare/Task Assignment, System Engineering & Test (SEIT)and Performance Assurance (CDRL 204)
Following are the reports for the above.
19
1. Storage TestUnit
AMSU-A1
AMSU-A2
AMSU-A2
S/N
S/N106
S/N107
i ActivityRetest Due Jan '01
Retest Due Jan '01
Retest Due Apr '01S/N 106
AMSU-A1 S/N 108 Retest Due Dec '00
AMSU-A2 S/N 108 Retest Due Dec '00
SpareDrive Motor Retest Due Sept '00
2. Spacecraft SupportS/C
EOS/TRW
METSAT/LMMS
METOP
Description
Continue to support daily integration activities as
required. Support weekly Hardware CPT telecons withTRW and NASA.
Provided inputs to the PLO lock detect anomaly
investigation on NOAA-L.
No significant activity.
3. Spare Status
Channel
5 DRO
8 DRO
7 DRO
Status
In Acceptance retest at Filtronics
Unit returned to Filtronics for troubleshooting and
rework. Awaiting rework plan from Filtronics.
Unit returned to Filtronics for troubleshooting and
rework plan from Filtronics.
ECD
31 Aug
31 Aug
31 Aug
1348351-1 & Kit at Filtronics until completion of DRO 5, 7 and 31 Aug
1336610 Spare Kit 8 rework, P.O. A83000.
4. Performance Assurance Activities
Activity
Test Reports and As-Built Report forAI-109
Fastener action item from NASA HQ
F/ARs
Accomplishment
Completed/delivered reports by 1 August.
Meeting conducted. Reviewing usage on
AMSU-A of any fasteners with > tA"diameter.
8 F/ARs approved by NASA; 3 F/ARs
awaiting NASA approval; 5 F/ARs in work.
SysSC.Soare Wkly.8.02.00 _0
1. Storage Test
Unit S/N
AMSU-A1 S/N 106
AMSU-A2 S/N 107
ActivityRetest Due Jan '01
Retest Due Jan '01
AMSU-A2 S/N 106 Retest Due Apr '01AMSU-A1 SIN 108 Retest Due Dec '00
AMSU-A2 S/N 108 Retest Due Dec '00
SpareDrive Motor/AMSU-A1 Test Completed
2. Spacecraft Support
S/C
EOS/TRW
METSAT/LMMS
METOP
Description
Continue to support daily integration activities as
required. Support weekly Hardware CPT telecons withTRW and NASA.
N O significant activity.
No significant activity.
3. Spare StatusChannel Status ECD
5 DRO In Acceptance retest at Filtronics
8 DRO
7 DRO
1348351-1 &
1336610 Spare Kit
Unit returned to Filtronics for troubleshooting and
rework. Awaiting rework plan from Filtronics.
In precap inspection.
Kit at Filtronics until completion of DRO 5, 7 and
8 rework, P.O. A83000.
18 Aug
27 Aug
31 Aug
31 Aug
4. Performance Assurance Activities
Open F/ARs
F/AR No.
233/234
212B
224
225
230
232
Description
A 1-109 (out-of-spec linearity/calibration
accuracy))
Mixer-Amplifier, S/N 7A38 (Spare)
DRO, Channel 5, S/N 85033 (Spare)
DRO, Channel 8, S/N 85074 (Spare)
DRO, Channel 7, S/N 8501:/(Spare)
A 1-107 (Defective Humidity Indicator)
Status
Awaiting NASA approval
Awaiting NASA approval
Awaiting ATP of reworkedDRO
Awaiting troubleshooting/
analysis at Filtronic
Awaiting ATP of reworkedDRO
Final F/AR in preparation
Sys.SC.Spare Wkly.8.09.00 21
1. Storage Test
Unit
AMSU-A1
AMSU-A2
AMSU-A1
AMSU-A2
S/N
S/N 106
S/N 106
S/N108
S/N108
Activi_Re.st Due Jan '01
Retest Due Apr '01Retest Due Dec '00
Retest Due Dec '00
2. Spacecraft SupportS/C
EOS/TRW
METSAT/LMMS
METOP
Description
Continue to support daily integration activities as
required.
No significant activity.
No significant activity.
3. Spare StatusChannel Status
5 DRO In Acceptance retest at Filtronics8 DRO
7 DRO
1348351-1 &
1336610 Spare Kit
Unit returned to Filtronics for troubleshooting and
rework. Awaiting rework plan from Filtronics.
In precap inspection.
Kit at Filtronics until completion of DRO 5, 7 and
8 rework, P.O. A83000.
ECD
18 Aug
27 Aug
31 Aug
31 Aug
.
Open F/ARs
Performance Assurance Activities
F/AR No.
233/234
224
225
230
Description
A 1-109 (out-of-spec linearity/calibration
accuracy)
DRO, Channel 5, S/N 85033 (Spare)
DRO, Channel 8, S/N 85074 (Spare)
DRO, Channel 7, S/N 85017 (Spare)
Status
Awaiting NASA approval
Awaiting ATP of reworkedDRO
Awaiting troubleshooting/
analysis at Filtronic
Awaiting ATP of reworkedDRO
Sys.SC.Spare Wkly.8.16.00 22
1. Storage TestUnit S/N Activity
Retest Due Jan '01AMSU-A1 S/N 106
AMSU-A2 S/N 106 Retest Due Apr '01AMSU-A 1 S/N 108 Retest Due Dec '00
AMSU-A2 S/N 108 Retest Due Dec '00
2. Spacecraft SupportS/C
EOS/TRW
METSAT/LMMS
Description
Continue to support daily integration activities as
required.BAT Test at LMMS.
METOP No significant activity.
3. Spare StatusChannel
5 DRO
8 DRO
7 DRO
1348351-1 &
1336610 Spare Kit
Smms ECD
Complete. Close out of paperwork in process.
Develop rework plan.
Rework and ATP plan submitted..
Kit at Filtronics until completion of DRO 5, 7 and8 rework, P.O. A83000.
18 AugTBD
31 Aug
31 Aug
4. Performance Assurance Activities
Open F/ARsF/AR No.
233/234
224
225
230
Description
Al-109 (out-of-spec linearity/calibration
accuracy)
DRO, Channel 5, S/N 85033 (Spare)
DRO, Channel 8, S/N 85074 (Spare)
DRO, Channel 7, S/N 85017 (Spare)
Status
Awaiting NASA approval.
DRO passed ATP; awaiting
source inspection.
Develop rework plan.
Rework/retest plan
submitted by Filtronic for
FRB approval.
Sys.SC.Spare Wkly.8.23.0023
1. Storage TestUnit
AMSU-A1
S/N
S/N 106aca /0,Retest Due Jan '01
AMSU-A2 S/N 106 Retest Due Apr '01AMSU-AI S/N 108 Retest Due Dec '00
AMSU-A2 S/N 108 Retest Due Dec '00
2. Spacecraft SupportS/C
EOS/TRW
METSAT/LMMS
METOP
Description
Continue to support daily integration activities as
required.
No significant activity.
No significant activity.
3. Spare Status
Channel Status ECD
5 DRO Received.
8 DRO
7 DRO
1348351-1 &
1336610 Spare Kit
Develop rework plan.
Rework and ATP plan submitted.
Kit at Filtronics until completion of DRO 5, 7 and
8 rework, P.O. A83000.
TBD
31 Aug
31 Aug
4. Performance Assurance Activities
Open F/ARs
F/AR No. Description225
230DRO, Channel 8, S/N 85074 (Spare)
DRO, Channel 7, S/N 85017 (Spare)
Stares
Develop rework plan.
FRB plan approved.
Sys.SC.Spare Wkly.8.23.00 24
!--
C_i
LLI
|
_E
r_
.Q
m
m0ILl
m0ILl
_E
26
_t
a)
¢00
e.-
m
..I
o
ILl
mI11
0qlj
0_rj
,11-,
O)
A
a)o
g
0a) ,_..._1__Z
Section 6
CONFIGURATION MANAGEMENT STATUS REPORT (CDRL 203)
Report 10300-84
September 2000
During this reporting period no drawings were released and submitted to
NASA by Configuration Management.
No Deviations or Waivers were generated during this reporting period. Deviations/Waivers are shown in the Table below.
DEVIATION/WAIVER STATUS
DEV/ PART PART
WAV DATE TITLE NAME NO. EFF
W001 08/14/95 AItVendorCert BrushlessMtrA1 1313921-1/ 105-Up/202-UpBrushless Mtr A2 1333648-1/
Resolver 1331529-1
D001 09/29/97 Conformal Circuit Card Various All CCA's
Coating Assemblies
D001A 11/11/97 Conformal Circuit Card Various All CCA's
STATUS
Disappvd 9/25/95
Resubmit as Rev.A
Cancelled
Configuration Management issued no Engineering Change
Notices (ECN) as shown in Table X.
29
TABLE X
ECN'S PROCESSED DURING AUGUST 2000
Report 10300-84
September 2000
DATE I CAMSU DOCUMENT PCCD I
ISSUED ECN NO. NO./REV. TITLE DATE CLASS.
NONE
3O
Section 7
DOCUMENT/DATA MANAGEMENT STATUS REPORT
7.1 August Submittals. During this reporting period, Data Management
submitted twenty two Contract Documentation Requirements Listing (CDRLs)and two non-CDRLs as shown in Table XI.
Table Xl August Document Submittali
CDRL Submitted
No. Description Due to NASA to NASA
Aug-00
32 PSR Data Pkg-Bkl, Rpt 11820
Report 11820A, Book 2
Report 11820A, Book 1
203 C.M. Status Rpt (Included in CDRL 529)204 Performance Assurance Status
Report (Included in CDRL 529)
208 Perf. Verif. Rpt., Report 11490B
211 Problem/Failure Rpt Close-Out:
F/AR-227
F/AR 212B
F/AR 232
F/AR 227A
F/AR 224
215 Trend Data, Rpt 11672
222 Calib Data SIN 109/A1, Rpt 11667
305 Engrg Telemetry Rpt, Rpt 10377C
503 Wgt/Pwr Budgets (Included in CDRL 529)
518 Indentured Drawing Lists:
SIN 109/A1, Rpt 11859
521 Weekly Status Report
523 Performance Measurement Status
Report (Included in CDRL 534)
525 As-Built Matl List, S/N 109/A1
526 Acpt Data Pkg,S/N 109/A1 ,V. 1,4-5
527 As-Des Pts List (EEE),Rpt 10385D
529 Reports of Work (Mo Status Rpt)
534 Mo./Qtly. Financial Mgmt. Report
(NASA Fro. 533M/533Q)
08/03/00 08/02/00
08/22/00 08/21/00
08/23/00 08122100
08/15/00 08/14/00
08/15/00 08/14/00
09/01/00 9/31/00
08/02/00 08/01/00
08/10/00 08/09/00
08/15/00 08/14/00
08/18/00 08/17/00
08/30/00 08/20/00
08102100 08/02/00
08103100 08/02/00
08/30/00 08/20/00
08/15/00 08/14/00
08/09/00 08/09/00
Weekly 8/4, 8/11,8/18 & 8/25/00
08/28/00 08/22/00
08/03/00 08/02100
08/03/00 08/02/00
08/03/00 08/02/00
08/15/00 08/14/00
08/28/00 08/22/00
None Calibration Log Books: 08/03/00 08/02/00
None Aerojet Self Evaluation 08/22/00 08/21/00
Report 10300-84
September 2000
32
7.2 Schedules Submittals. In accordance with the METSAT Master
CDRL, the CDRL items listed in Table XII will be submitted to NASA during the
months of September and October 2000.
Table Xll September Document Submittal
CDRL Submitted
No. Description Due to NASA to NASA
Sep-O0
203 Configuration Management
Status Rpt (Included in CDRL 529)
204 Performance Assurance Status
Report (Included in CDRL 529)
208 Performance Verification Reports:
Report 11155A
503 Weight/Power Budgets
(Included in CDRL 529)
521 Weekly Status Report523 Performance Measurement Status
Report (Included in CDRL 534)
529 Reports of Work (Mo Status Rpt)
534 Moo/Qtly. Financial Mgmt. Report
(NASA Fro. 533M/533Q)
09/14/OO
09/14/00
09/12/00
09/14/00
Weekly
09/25/00
09/14/00
09/25/00
09/11/00
Report 10300-84
September 2000
CDRL
No.
Oct-00
203
204
5O3
521
523
529
534
Table XU October Document Submittal
Description Due to NASA
Configuration Management
Status Rpt (Included in CDRL 529)
Performance Assurance Status
Report (Included in CDRL 529)
Weight/Power Budgets
(Included in CDRL 529)
Weekly Status Report
Performance Measurement Status
Report (Included in CDRL 534)
Reports of Work (Mo Status Rpt)
Mo./Qtly. Financial Mgmt. Report
(NASA Fm. 533M/533Q)
10/13/00
10/13/00
10/13/0O
Weekly
10/23/00
10/13/00
10/23/00
Submitted
to NASA
V
33
,_z
8_o _ooooo oo o ooooooo
_O ZZ ZZZZZZZ ZZZ
I,LI I_.ZO_
e_
o_z__z<z_z
o_<_<<<< <<<ZZZZZZZZZ
_u_ o O o o o 7, o!o o
"" 03 D- II. O0 "" O0 I_.. O.. COzZ zZu) co
36
_0
8
_ _ W _,_ W W W W _ W _ W WiW _ WlW W W W W W W W W
0000:0000000000: O0000iO000000 0 0 O0 0 0 0 O0 0 0 00' 0 0 0 0 010 00iO _ 0
_Z Z Z Z Z Z Z Z Z Z Z Z _ _ Z Z Z Z Z!Z Z _ Z_o
w_ o_o_ oooooo_o ooo o= o_OOOz o o o_o
oooo,oo,ooo,o,oooooooo-o-oo_ooo
m_ ooooooN_oooNoo= ,°°,°
w _ _
w W _ _ _ _'w w _i
_z _ _.<<_ . _ _ z__<<_
W_ D_w__
_z o__w _ _ _ _z O'-z_O_'_
zZ V
37
Report No. 10300-84September 2000
August '00 Monthly AnalysisSEIT Team
Current Status
EOS S/N 202 A 1 has been delivered.
EOS S/N 202 A2 has been delivered.
METSAT S/N 105 A1 has been delivered.
METSAT S/N 105 A2 has been delivered.
METSAT S/N 106 A1 has been delivered.
METSAT S/N 107 A2 has been delivered.
METSAT S/N 107 A1 has been delivered.
METSAT S/N 109 A2 has been delivered.
METSAT S/N 106 A2 has been delivered.
METSAT S/N 108 A1 has been delivered.
METSAT S/N 108 A2 has been delivered.
METSAT S/N 109 A1 has been delivered.
Major Float Changes
None.
Existing Problem Areas
None.
Potential Problem Areas
None.
38
NFSD 89-0 (June 30, 1989) FORMS 53-55
Report Documentation PageNational Aeronautics andSpace Admin|_ration
1. Report No. 2. Government Accession No.
3. Title and Subtitle
Integrated Advanced Microwave Sounding Unit-A(AMSU-A), Monthly Report for August 2000
7. Author(s)
A. Nieto
9. Performing Organization Name and Address
Aerojet
1100 W. HollyvaleAzusa, CA 91702
12. Sponsoring Agency Name and Address
NASA
Goddard Space Flight CenterGreenbelt, Maryland 20771
3 Recipient's Catalog No.
.=.
5. Report Date
September 2000
6. Performing Organization Code
8. Performing Organization Report No.
10300-84
10. Work Unit No.
11. Contract or Grant No.
NAS 5-32314
13. Type of Repo;'t and Period Covered
Monthly
14, Sponsoring Agency Code
15. Supplementary Notes
16. ABsTRAcT (Maximum 200
words )
This is the Monthly Report for the Integrated Advanced Microwave Sounding Unit-A
(AMSU-A).
17. KeyWords (Suggested by Author(s))
EOS
Microwave System
'i9. Security Classif. (of this report)
Unclassified
NASA FORM 1626 OCT 86
NASA FAR SUPPLEMENT
1"8. Distribution Statement
20. Security Classif. (of this page)
Unclassified
Unclassified --- Unlimited
'21. No. of pages 22. Price
18-53.303-1626
39
53-56 FORMS (June 30, 1989) NFSD 89-0
PREPARATION OF THE REPORT DOCUMENTATION PA_E
The last page of a rePort facing the third cover is the Report Documentation Page, RDP. Information presented on this page isused in announcing and r_,_loging re,go,rts as wel! as preparing the cover and title page. Thus, it is important that the informat=onoe correct. Instrucsens ror riling in each DIOCKof the form are as rollOWS;
Block 1. Re_d._.__ NASA rePort series number, if
preassigned,
Block 2. Government Accession No. Leave blank.
Block 3. Recioient's Catalog No.. Reserved for use by each
report recipient.
Block 4. Titlo _n_ Subtitle. Typed in caps and lower case with
dash or period separating subtitle from title.
Block 5. Reood _)ate. Approximate month and year the report
will be published.
Block 6. P_rforrnina Organization Code. Leave blank.
Block 7. _ Provide full names exactly as they are to
appear on the title page. If applicable, the word editor should
follow a name.
Block 8. P@rformino Organization Re_dNo. NASA installation
report control number and, if desired, the non-NASA performing
organization report control number.
Block 9. Performing Organization Name and Address. Provide
affiliation (NASA program office, NASA installation, or contractor
name) of authors.
Block 10. Wo_ __N_. Provide Research and Technology
Objectives and Plants (RTOP) number.
Block 11. (_0ntr@_;tor Grant Nq. Provide when applicable.
Block 12. SPonsoring Agency Name and Address. National
Aeronautics and Space Administration, Washington, D.C. 20546-
0001. If contractor report, add NASA installation or HQ program
office.
Block 13. TYPe of Reoort and Period Covered. NASA formal
report series; for Contractor Report also list type (interim, final)
and period covered when applicable.
Block 14. $12on,_orino Agency Code. Leave blank.
Block 15. Suoolementarv Notes. Information not included
elsewhere: affiliation of authors if additional space is required
for Block 9, notice of work sponsored by another agency, monitor
of contract, information about supplements (file, data tapes, etc.)
meeting s_te and date for presented papers, journal to which an
article has been submitted, note of a report made from a thesis,
appendix by author other than shown in Block 7.
Block 16. _ The abstraci should be infom'_ative rather
than descriptive and should state the objectives of the
investigation, the methods employed (eg, simulation,
experiment, or remote sensing), the results obtained, and the
conclusions reached.
Block 17. Key Words. Identifying words or phrase,'; to be used
in cataloging the report.
Block 18. Distribution _ Indicate whether rePort is
available to public or not. If not to be controlled, use
"Unclassified-Unlimited." If controlled availability is required,
list the category approved on the Document Availability
Authorization Form (see NHB 2200.2, Form FF4.27). Also
specify subject category (see "Table of Contents" in a current
issue of STAR) in which report is to be distributed.
Block 19. Security Classification h._(g.[_,rt). Self-
explanatory.
Block 20. Security Classification (of this Da(_..L Self-
explanatory.
Brock 21, No. of Pages. Count front matter pages beginning with
iii, text pages including internal blank pages, and the RDP, but
not the title page or the back of the title page.
Block 22. Pd_ Code. If Block 18 shows "Unclassified-
Unlimited," provide the NTIS price code (see "NTIS Price
Schedules" in a current issue of STAR) and at the bottom of the
form add either "For sale by the National Technical Information
Service, Springfield, VA 22161-2171" or "For sale by the
Superintendent of Documents, U.S. Government Pdnting Office,
Washington, D.C. 20402-0001 ," whichever is appropriate,
V
4O
pART 53 - FORMS R___N1-2g£
Form
ApprovedREPORT DOCUMENTATION PAGE OMBNo.
0704-0188
Public reporting burden f_this collectionof information is estimated to average 1 hour per response,including the ttmelor reviewing instructions,searching existing data sourcesgathering andmainta_mngthedata needed, and completing andreviewing thecollection information Send comments regardthgthis burden esbmate or any taher aspect o#thiscollection of inlormadon thclu_ng soggestior_r reducing this burden,to Washington Headquarters Serwcas,Directorata tot Information Operattonsand Reports, 1215 JeffersonDavis Highway, Suite 1204, Arlington, VA 22202-4302, and to theOffice o Management and Budget, Paperwork Reduct on Pro_ect (0704-0188) Washington, DC 20503,
1, AGENCY USE ONLY ( Leave 2. REPORT DATE
blank )
4. TITLE AND SUBTITLE
Integrated Advanced Microwave Sounding Unit-A(AMSU-A), Monthly Report for August 2000
6, AUTHOR(S)
A. Nieto
7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES)
Aerojet
1100 W. Hollyvale
Azusa, CA 91702
9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES)NASA
Goddard Space Flight Center
Greenbelt, Maryland 20771
3, REPORT TYPE AND DATES COVERED
5. FUNDING NUMBERS
NAS 5-32314
8, PERFORMING ORGANIZATION
REPORT NUMBER
10300-84
September 2000
10, SPONSORING/MONITORING
AGENCY REPORT NUMBER
11. SUPPLEMENTARY NOTES
12a. DISTRIBUTION/AVAILABILITY STATEMENT 12b. DISTRIBUTION CODE
13. ABSTRACT (Maximum 200
words )
This is the Monthly Report for the Integrated Advanced Microwave Sounding Unit-A(AMSU-A).
14. SUBJECT TERMS
LOS
Microwave System
17. SECURITY CLASSIFICATIONOF REPORT
Unclassified
NSN 7540-01-280-5500
18. SECURITY CLASSIFICATIONOF THIS PAGE
Unclassified
19. SECURITY CLASSIFICATIONOF ABSTRACT
Unclassified
15. NUMBER OF PAGES
16, PRICE CODE
m.
i 20. LIMITATION OFABSTRACT
SAR
Stat_dardForm298 (FI.ev2-89)pre=criedby ANSI Std 239-182g_l-102
41
53-:_01-298 FEDERAL A(_(_VISlTIQN REGI_LATION (FAR)
GENERAL INSTRUCTIONS FOR COMPLETING SF 298
The Report Documentation Page (RDP) is used in announcing and cataloging reports. It is important that this information beconsistent with the rest of the report particulady the cover and title page. instructions for filing in each block of the formTOOW. t S mportant to stay within the lines to meet opticat scanning requirements.
Block 1. Aoencv Use Only(Leave blank)
Block 2. ReDort Date. Full publication date including day,
month, andyear, if available (e.g., 1 Jan 88). Must cite at least
the year.
Block 3. Tvoe of Report 0rid Dates Covered. State whether
report is interim, final, etc. If applicable, enter inclusive report
dates (e.g., 10 Jun 87 - 30 Jun 88).
Block 4. Title and Subtitle A title is taken from the part of the
report that provides the most meaningful and complete
information. When a report i=prepared in more than one volume
report the primary title, add volume number, and include subtitle
for the specific volume. On classified documantsenter the title
classification in parentheses.
Block 5. Fundina Numbers To include contract and grant
numbers; may include program element number(s), project
number(s), tasks number(s), andwork unit number(s). Use the
following labels:
C Contract PR ProjectG Grant TA Task
PE Program WU Work UnitElement Accession No.
Block 6. _. Name(s) of person(s) responsible for
writing the report, performing the research, or credited with the
content of thereport. If editor or compiler, this should follow the
name(s).
Block 7. Performino Oroanization Name(s) and Addressees1.
Self-explanatory.
Block 8. Performing Oroanization Reoort Number. Enter the
unique alphanumeric report number(s) assigned by the
organization performing the report.
Block 9. Soonsorina/Monitoring Agency Namefs) and
Address(esl Self-explanatory.
Block 10. SDon,sorina/MonitorinaAoencv RePorts Nvmber. (ff
known).
Block 1t. SuDolementarvNotes. Enter informationnet included
elsewhere such as: Prepared in cooperation with ...; Trans. of
...; To be published in ... When a report is revised, include a
statemantwhether the new report supersedes or supplements
the older report.
Block 12.a Distribution/Avaitabilitv Statement. Denotes public
availability or limitations. Cite any availability to the public.
Enter additional limitations or special markings in all capitals
(e.g., NOFORN, REL, ITAR).
DOD See DoDD 5230.24 Distribution Statement orl
Technical Documents
DOE See authorities.
NASA - See Handbook NHB 2200.2.
NTIS Leave blank.
Block 12.b Distribution _.-,Od@.
DOD Leave blank.
DOE Enter DOE distribution categories from the
standard Distribution for Unclassified
Scientific and Technical Reports.
NASA - Leave blank.
NTIS Leave blank.
Block 13. _ Include a bdef _aximum 200 word_
factual summary of the most significant information contained in
the report.
Block 14. Subiect Terms. Keywords or phases identifying major
subjects in the report.
Block 15. Number of Paoes. Enter the total number of pages.
Block 16. Price Code. Enter appropriate price code_lTIS
only).
Block 17 - 19. Security Classifications. Self-explanatory. Enter
U.S. Security Classification in accordance with U.S. Security
Regulations (i.e., UNCLASSIFIED). If form contains classified
information, stamp classification on the top and bottom of the
page.
Block 20. Limitation of Abstract. This block must be completed
to assign a limitation to the abstract. Enter either UL (unlimited)
or SAR (same as report). An entry in this block is necessary if
the abstract is to be limited. If blank, the abstract is assurncd to
be unlimited.
53-86
Standard Form 298 Back (Rev 2-89)
42