Advancedcostaccounting 140417192903-phpapp02

16
Standard Costing

description

Group presentation of slandered costing

Transcript of Advancedcostaccounting 140417192903-phpapp02

Page 1: Advancedcostaccounting 140417192903-phpapp02

Standard Costing

Page 2: Advancedcostaccounting 140417192903-phpapp02

Standard Cost

1. Standard Costing refers to expected costs under anticipated conditions.

2. Standard cost systems allow for comparison of standard versus actual costs.

3. Differences are referred to as standard cost variances.

4. Variances should be investigated if significant.

Page 3: Advancedcostaccounting 140417192903-phpapp02

Standard Costs and Budgets

1. Standard cost is the standard cost of a single unit.

2. Budgeted cost is the cost, at standard, of the total number of budgeted units.

Page 4: Advancedcostaccounting 140417192903-phpapp02

Target Costing

A target cost is the allowable amount of cost that can be incurred on a product and still earn the required profit from that product. It is a market driven cost that is computed before a product is produced.

Page 5: Advancedcostaccounting 140417192903-phpapp02

Kaizen Costing

Kaizen costing is the process of continual cost reduction that occurs after a product design has been completed and is now in production. It used during implementation of a product in market.

Page 6: Advancedcostaccounting 140417192903-phpapp02

Cost Variances

A cost variance is defined by CIMA as “the difference between a planned, budgeted, or standard cost and the actual cost incurred. The same comparisons may be made for revenues”.

Page 7: Advancedcostaccounting 140417192903-phpapp02

Types of variances

• Favorable Variance (F)• Adverse Variance (A)

When actual results are better than expected results, we have Favorable Variance.

When actual results are worse than expected results, we have Adverse Variance.

Page 8: Advancedcostaccounting 140417192903-phpapp02

Material variances

The material total variance “measures the difference between the standard material cost of the output produced and the actual material cost incurred”.

Material Price variance

Material Usage variance

Materials cost variance

Page 9: Advancedcostaccounting 140417192903-phpapp02

Worked example: Material Variances

Product X has a standard material cost as follows.

10 kilogram of material Y at $10 per kilogram = $100 per unit of X.

During period 4, 1,000 units of X were manufactured, using 11,700 kilograms of material Y which cost $98,631.

Page 10: Advancedcostaccounting 140417192903-phpapp02

Worked example: Material Variances

Requirements:

a)The material total variances

b)The material price variances

c)The material usage variances

Page 11: Advancedcostaccounting 140417192903-phpapp02

Labor Variances

The calculate of labor variances is very similar to the calculation of material variances.

The labor total variance measures the difference between the standard labor cost of the output produced and the actual labor cost incurred.

Labor cost variance

Labor rate variance Labor Efficiency variance

Page 12: Advancedcostaccounting 140417192903-phpapp02

Worked example: Labor Variances

The standard labor cost of product X is as follows.

2 hours of grade Z labor at $10 per hour = $20 per unit of product X.

During period 4, 1,000 units of product X were made, and the labor cost of grade Z labor was $17,825 for 2,300 hours of work.

Page 13: Advancedcostaccounting 140417192903-phpapp02

Worked example: Labor Variances

Requirements:

a)The Labor total variance

b)The Labor rate variance

c)The Labor Efficiency variance

Page 14: Advancedcostaccounting 140417192903-phpapp02

Variable Overhead Variances

Variable production overhead total variance measures the difference between the variable production overhead that should be used for actual output and the variable production overhead actually used”.

Variable Overhead variance

VO Expenditure variance VO Efficiency variance

Page 15: Advancedcostaccounting 140417192903-phpapp02

Worked example: Variable overhead Variances

suppose that the variable overhead cost of product X is as follows.

2 hours at $1.50 = $3 per unit

During the latest period, 400 units of product X were made. The labor force worked 760 hours. The variable overhead cost was $1,672.

Page 16: Advancedcostaccounting 140417192903-phpapp02

Worked example: Variable overhead Variances

Requirements:

a)The variable overhead total varianceb)The variable overhead expenditure

variancec)The variable overhead efficiency variance