Advanced Construction Technologies and Further Evolution Towards New Build NPP Projects
International Conference on Opportunities and Challenges forWater Cooled Reactors in the 21st Century
Hitachi-GE Nuclear Energy, Ltd.(HGNE)Junichi Kawahata
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
HGNE’s NPP Construction Experience
NETOUTPUT
TSURUGA - 1* HAMAOKA - 1*
10,000
15,000
(MWe)
1970 1975 1985357
HAMAOKA - 4*
KASHIWAZAKI・KARIWA - 5
SHIMANE - 2
HAMAOKA - 3*
FUKUSHIMA-II-4
FUKUSHIMA Ⅱ-2
FUKUSHIMA Ⅰ-4
TOKAI - 2*
HAMAOKA - 2*
0
5,000
1995 2005
460460540784
1100
840
SHIKA - 1
KASHIWAZAKI・KARIWA 4
1100
1100
1100
820
1100
540
1137
1100
20,000
Advanced BWR phaseImprovement and Standardization phaseDomestic Production Phase
SHIMANE - 1
FUKUSHIMA I-1*
Qinshan III
HGNE’s BWR plantsIn Operation :20 unitsUnder Construction :
1 unit
*) Collaborative Construction
Tsuruga
Shika Kashiwazaki kariwa
HamaokaTokai -II
Fukushima-I
Onagawa
Fukushima-II
Shimane
Oma
Lungmen- 1&2Oversea Projects
11HIGASHI-DORI-1
5 5 ABWRsABWRsContinuousContinuousConstructionConstructionExperienceExperience 1380
1358
KASHIWAZAKI・KARIWA 7*
KASHIWAZAKI・KARIWA 6*
HAMAOKA - 5*
SHIKA - 2
SHIMANE-3
825ONAGAWA - 3*
1356
1356
OMA-1
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
HGNE’s Construction Strategy
Integrated Engineering System
Modularizationwith
Large crane
On-site Work
Reduction
Open-top &
parallel construction
On-site Work
Leveling
Construction Support System
Improvement of On-site
Work Support Efficiency
22
Improvement of On-site Work
Efficiency
Detailedengineering
before on-site work
Engineering &Delivery ScheduleControl System
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
HGNE’s Construction Strategy22
Integrated Engineering System
Modularizationwith
Large crane
On-site Work
Reduction
Open-top &
parallel construction
On-site Work
Leveling
Construction Support System
Improvement of On-site
Work Support Efficiency
Improvement of On-site Work
Efficiency
Detailedengineering
before on-site work
Engineering &Delivery ScheduleControl System
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
History of HGNE’s Module Application
18 27 28 32 3883
194
28
7745
247 235
317
150
322 309
196
76
0
50
100
150
200
250
300
350
400
APlant
Num
ber o
f Mod
ule:
unit
ModulesPipe Blocks
Note:*1). The numbers above include those of mechanical modules and of some large scale civil modules like base mat and top slab
modules on construction critical path in whole plant (N/I and T/I). Note that hundreds of pre-fabricated rebar modules are not included.
*2). For Plant F/G, HGNE’s scope was T/I for Plant F and N/I for Plant G. The numbers are the summation of them.*3). For Plant H, HGNE’s scope was T/I only
*1)
*2) *3)
1990 1995 2000 2005B C D E F/G H I J
0
20
40
60
80
100
Perio
d, S
ite M
anpo
wer
(%)Construction Period
Work Force at site
2-12-1
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
HGNE’s Construction Strategy22
Integrated Engineering System
Modularizationwith
Large crane
On-site Work
Reduction
Open-top &
parallel construction
On-site Work
Leveling
Construction Support System
Improvement of On-site
Work Support Efficiency
Improvement of On-site Work
Efficiency
Detailedengineering
before on-site work
Engineering &Delivery ScheduleControl System
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Strategy-2: On-site Work Leveling Open-top & Parallel Construction2-22-2
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Strategy-2: On-site Work Leveling Floor Packaging MethodConventional MethodConventional Method
Pres.Pres.TestTest1F
B2F Mech. Inst.Mech. Inst.
B1F
2F
B2FB1F
2FSystem Test
1F
System Test
Wor
k Fo
rce
Construction schedule
Floor Packaging Method
Construction schedule
Peak ReductionPeak ReductionPeak Reduction
Remaining Remaining WorkWork
Need to wait for all piping installation
Open Top Parallel Const.
DividedPressure Test
2-22-2
B2F:Completion of Construction 1F:Hydrostatic
Testing
2F:Peak Construction
Construction
Area Release
▼
-3 3 6 9 12 15 18 21 24 27 30FloorMonth
2F
1F
B2F
▼
Pressure Testing
Insulation & Painting
▼
◆
◆
Disassembly of Scaffoldings
Pre-Operation Test
◆
Earlier Floor Const. Completion
Wor
k Fo
rce
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Strategy-2: On-site Work Leveling Track Record in Work Leveling
Site
Man
pow
er
Construction Time 1 6 11 16 21 26 31 36 41 month
Latest ABWR Completed
On-Site Manpower Leveled OffOnOn--Site Manpower Leveled OffSite Manpower Leveled Off
Peak ReductionPeak ReductionPeak Reduction First ABWR
2-22-2
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
HGNE’s Construction Strategy22
Integrated Engineering System
Modularizationwith
Large crane
On-site Work
Reduction
Open-top &
parallel construction
On-site Work
Leveling
Construction Support System
Improvement of On-site
Work Support Efficiency
Improvement of On-site Work
Efficiency
Detailedengineering
before on-site work
Engineering &Delivery ScheduleControl System
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
High-End IT Systems Applied for Construction
ModuleEngineering
Yard / CraneEngineering
ConstructionSchedule Planning
Index 3
Index 4
Index 5
Index 6
Index 7
Index 8
Index 1
Index 2
Effect 1Effect 2Effect 3Effect 4Effect 5Effect 6Effect 7Effect 8Effect 9Effect 10
Effect 1Effect 2Effect 3Effect 4Effect 5Effect 6Effect 7Effect 8Effect 9Effect 10
3D Module Design Module Evaluation, Improvement Indices
Feedback
Crane, Equipment Model
Simulation
Simulation
Schedule+3D-CAD
2-32-3
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
HGNE’s Construction Strategy22
Integrated Engineering System
Modularizationwith
Large crane
On-site Work
Reduction
Open-top &
parallel construction
On-site Work
Leveling
Construction Support System
Improvement of On-site
Work Support
Efficiency
Improvement of On-site Work
Efficiency
Detailedengineering
before on-site work
Engineering &Delivery ScheduleControl System
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Features
Just in TimeJust in Time
Construction Management
System
•Data Visualization•Process Standardization•Numerical Evaluation
Project Management Office
Drawing
Schedule
Product(Material)
Project Management PDCA
【Plan】
【Problem Prediction】
(HGNE)
Thermal Power Div.
Power & Industrial Div.
Hitachi Plant Tech.
Information &Telecom. Div.
AE Power
Integrated Managem
entBHK
another Subsidiaries
Installation
InspectionTesting
Schedule Control
Product(Material)Control
Document Control Data Data
Just in TimeJust in Time
【OperationPromotion 】
Construction SiteDesign Office
【Visualization】
Construction Management System Concept Integrated System from Design to Construction
・Business Process InnovationInstallation&InspectionProcess StandardizationZero Defect Cost
(Shorten Lead Time)Paperless BusinessUbiquitous Environment(using RFID)
Workforce Leveling・Information Sharing
Design Office - SiteHGNE - Corporate Firms
・Integrated Construction Mgt.Design-Procurement-Delivery-Construction
【Counter- measure】
2-42-4
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Material Control
Material Control
Schedule Control
Schedule Control
Delivery Control
Delivery Control
Product
Schedule
DocumentDocument Control
Document Control
Work Instruction
WarehouseManagement
e.g.) Equipment (Target Date from Design to Site)
Construction Management System Delivery Schedule Control
-25 -18 -8
0-8-13-20
-3
Area ScheduleArea Schedule
Construction Management
System
Shipping Information
SiteSiteReceiveReceive
Requisition
Contract with Vendor
Fabrication Schedule
Material Order
Material Receiving
Fabrication Start
Shipping ListIssue
Carry-in Date ≒Delivery Date
2-42-4
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Work Instruction & Work Record SystemWork Instruction & Work Record System
Construction Management System Work Instruction Function -(ex. Pipe Fit-Up Work)2-42-4
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Input Actual Data using PDA& RFID
RFID Reader
Worker Worker IDID
ProductProduct IDID
Construction Management System Work Instruction Function -(ex. Pipe Fit-Up Work)
PDA:Personal Digital Assistance2-42-4
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Construction Management System - Progress Evaluation Function -2-42-4
Progress Monitoring & Evaluation SystemProgress Monitoring & Evaluation System
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Construction Management System - Creating Electric Construction manual -
ElectricalElectricalInstructionInstructionManual DBManual DB
Know-How
• Accumulating Real Construction Know-How• Easy and Steady Traceability• Further Enhancement of Construction Quality
2-42-4
Ref. CNJ-OG-G056Rev.7.3All Rights Reserved Copyright © 2009, Hitachi-GE Nuclear Energy , Ltd.
Conclusion
• HGNE has continuously constructed 20 BWRs (4 ABWRs) over 35 yrs since 1970’s with NO delay in their planned Commercial Operating Dates (COD’s).
• During this period, various “Advanced Construction Technologies” have been developed based on its accumulated experiences and lessons learned, and they are proven to be effective for Nuclear Power Plants Constructions.
• HGNE is one of the very few companies which can complete NPP construction in “On-schedule” and “On-budget” manner in the world.
33