2
Data Type Resources Actual Work Remaining Work Budget Work Budget Cost Cost Work Unassigned 0 0 0 0 0 Kavita 112 0 0 0 28000 Ravi 80 0 0 0 20000 Srini 56 0 0 0 14000 Venkat 0 0 0 0 0 $0.00 0 0 0 0 0 $10 136 376 0 0 0 000.00 136 376 0 0 0 Work Total 520 752 0 0 62000 Grand Total 520 752 0 0 62000

description

adr21

Transcript of adr21

Page 1: adr21

DataType Resources Actual Work Remaining Work Budget Work Budget Cost CostWork Unassigned 0 0 0 0 0

Kavita 112 0 0 0 28000Ravi 80 0 0 0 20000Srini 56 0 0 0 14000Venkat 0 0 0 0 0$0.00 0 0 0 0 0$10 136 376 0 0 0000.00 136 376 0 0 0

Work Total 520 752 0 0 62000Grand Total 520 752 0 0 62000

Page 2: adr21

Overtime Cost Baseline Cost Regular Work Remaining Cost Work Variance0 0 0 0 00 54000 112 0 -1040 24000 80 0 -160 74000 56 0 -2400 20000 0 0 -800 0 0 0 00 0 512 0 5120 0 512 0 5120 172000 1272 0 5840 172000 1272 0 584