ADR DIGEST

28
 A D R CASE DIGESTS 2015  pg. 1 Page number 1 Heirs of Augusto Salas v Laperal Realty Corporation Upon whom is an agreement to submit to arbitration binding? G.R. NO. 135362 (December 13, 1999)  DE LEON, JR., J.:  FACTS:  Augusto Salas, Jr. w as the registered owner of a vast tract of land in Lipa City, Batangas. He entered into an Owner-Contractor  Agreement  with Respondent Laperal Realty Corporation to render and provide complete (horizontal) construction services on his land. Said agreement contains an arbitration clause, to wit : ARTICLE VI.  ARBITRATION.  All cases of dispute between CONTRAC TOR and OWNER’S representative shall be referred to the committee represented by: 1. One representative of the OWNER; 2. One representative of the CONTRACTOR; 3. One representative acceptable to both OWNER and CONTRACTOR. Salas, Jr. then executed a Special Power of  Attorney  in favor of Respondent Laperal Realty to exercise general control, supervision and management of the sale of his land, for cash or on installment basis. By virtue thereof, Respondent Laperal Realty subdivided said land and sold portions thereof to Respondents Rockway Real Estate Corporation and South Ridge Village, Inc. in 1990; to Respondent spouses Abrajano and Lava and Oscar Dacillo in 1991; and to Respondents Eduardo Vacuna, Florante de la Cruz and Jesus Vicente Capalan in 1996 (Respondent Lot Buyers hereinafter). Back in 1989, Salas, Jr. left his home in the morning for a business trip t o Nueva E cija. He, however, never returned on that unfaithful morning. Seven years later or in 1996, his wife, Teresita Diaz-Salas filed with the RTC of Makati City a verified Petition for the Declaration of Presumptive Death, which Petition was granted. In 1998, Petitioners, as heirs of Salas, Jr. filed in the RTC of Lipa City a Complaint for Declaration of Nullity of Sale, Reconveyance, Cancellation of Contract, Accounting and Damages against Respondents. Respondent Laperal Realty filed a Motion to Dismiss on the ground that Petitioners failed to submit their grievance to arbitration as required under Article VI of the Owner-Contractor  Agreement . Respondent spouses Abrajano and Lava and Respondent Dacillo filed a Joint Answer with Counterclaim and Crossclaim praying for dismissal of Petitioners’ Complaint for the same reason.

description

Compilation of Digest for the Subject of Alternative Dispute Resolution. I do not claim ownership over this digests, this is just a collated version.

Transcript of ADR DIGEST

  • ADR CASE DIGESTS 2015

    pg. 1

    Page number 1

    Heirs of Augusto Salas v Laperal Realty

    Corporation

    Upon whom is an agreement to submit to

    arbitration binding?

    G.R. NO. 135362 (December 13, 1999)

    DE LEON, JR., J.:

    FACTS:

    Augusto Salas, Jr. was the registered owner of a

    vast tract of land in Lipa City, Batangas. He

    entered into an Owner-Contractor

    Agreement with Respondent Laperal Realty

    Corporation to render and provide complete

    (horizontal) construction services on his land.

    Said agreement contains an arbitration

    clause, to wit:

    ARTICLE VI. ARBITRATION.

    All cases of dispute between CONTRACTOR

    and OWNERS representative shall be referred

    to the committee represented by:

    1. One representative of the OWNER;

    2. One representative of the CONTRACTOR;

    3. One representative acceptable to both

    OWNER and CONTRACTOR.

    Salas, Jr. then executed a Special Power of

    Attorney in favor of Respondent Laperal Realty

    to exercise general control, supervision and

    management of the sale of his land, for cash or

    on installment basis. By virtue thereof,

    Respondent Laperal Realty subdivided said land

    and sold portions thereof to Respondents

    Rockway Real Estate Corporation and South

    Ridge Village, Inc. in 1990; to Respondent

    spouses Abrajano and Lava and Oscar Dacillo

    in 1991; and to Respondents Eduardo Vacuna,

    Florante de la Cruz and Jesus Vicente Capalan

    in 1996 (Respondent Lot Buyers hereinafter).

    Back in 1989, Salas, Jr. left his home in the

    morning for a business trip to Nueva Ecija. He,

    however, never returned on that unfaithful

    morning. Seven years later or in 1996, his wife,

    Teresita Diaz-Salas filed with the RTC of Makati

    City a verified Petition for the Declaration of

    Presumptive Death, which Petition was granted.

    In 1998, Petitioners, as heirs of Salas, Jr. filed in

    the RTC of Lipa City a Complaint for Declaration

    of Nullity of Sale, Reconveyance, Cancellation of

    Contract, Accounting and Damages against

    Respondents.

    Respondent Laperal Realty filed a Motion to

    Dismiss on the ground that Petitioners failed to

    submit their grievance to arbitration as required

    under Article VI of the Owner-Contractor

    Agreement. Respondent spouses Abrajano and

    Lava and Respondent Dacillo filed a

    Joint Answer with Counterclaim and

    Crossclaim praying for dismissal of Petitioners

    Complaint for the same reason.

  • ADR CASE DIGESTS 2015

    pg. 2

    Page number 2

    The RTC then issued the herein assailed Order

    dismissing Petitioners Complaint for non-

    compliance with the foregoing arbitration clause.

    Hence the present Petition for Review on

    Certiorari under Rule 45.

    ISSUE:

    Whether or not the arbitration clause under

    Article VI of the Owner-Contractor Agreement

    is binding upon the Respondent Lot Buyers?

    ARGUMENTS:

    Petitioners argue that (1) their causes of action

    did not emanate from the Owner-Contractor

    Agreement, (2) that their causes of action for

    cancellation of contract and accounting are

    covered by the exception under the Arbitration

    Law, and (3) that failure to arbitrate is not a

    ground for dismissal.

    Petitioners claim that they suffered lesion of

    more than one-fourth (1/4) of the value of Salas,

    Jr.s land when Respondent Laperal Realty

    subdivided it and sold portions thereof to

    Respondent Lot Buyers. Thus, they instituted

    action against both Respondent Laperal Realty

    and Respondent Lot Buyers for rescission of the

    sale transactions and reconveyance to them of

    the subdivided lots. They argue that rescission,

    being their cause of action, falls under the

    exception clause in Sec. 2 ofRepublic Act No.

    876 which provides that such submission [to] or

    contract [of arbitration] shall be valid,

    enforceable and irrevocable, save upon such

    grounds as exist at law for the revocation of any

    contract.

  • ADR CASE DIGESTS 2015

    pg. 3

    Page number 3

    RULING: NO. Respondent Lot Buyers are

    neither parties to the Agreement nor the latters

    assigns or heirs. Consequently, the right to

    arbitrate as provided in Article VI of the

    Agreement was never vested in Respondent Lot

    Buyers. Respondent Laperal Realty, on the

    other hand, as a contracting party to the

    Agreement, has the right to compel Petitioners

    to first arbitrate before seeking judicial

    relief. However, to split the proceedings into

    arbitration for Respondent Laperal Realty and

    trial for the Respondent Lot Buyers, or to hold

    trial in abeyance pending arbitration between

    Petitioners and Respondent Laperal Realty,

    would in effect result in multiplicity of suits,

    duplicitous procedure and unnecessary

    delay. On the other hand, it would be in the

    interest of justice if the trial court hears the

    complaint against all herein Respondents and

    adjudicates Petitioners rights as against theirs

    in a single and complete proceeding.

    Petition is GRANTED. The assailed Order of

    RTC of Lipa City is NULLIFIED and SET ASIDE.

    RATIO DECIDENDI:

    In a catena of cases inspired by Justice

    Malcolms provocative dissent in Vega v. San

    Carlos Milling Co. [1924], the SC has recognized

    arbitration agreements as valid, binding,

    enforceable and not contrary to public policy so

    much so that when there obtains a written

    provision for arbitration which is not complied

    with, the trial court should suspend the

    proceedings and order the parties to proceed to

    arbitration in accordance with the terms of their

    agreement. Arbitration is the wave of the future

    in dispute resolution. To brush aside a

    contractual agreement calling for arbitration in

    case of disagreement between parties would be

    a step backward.

  • ADR CASE DIGESTS 2015

    pg. 4

    Page number 4

    A submission to arbitration is a contract. As

    such, the Agreement, containing the stipulation

    on arbitration, binds the parties thereto, as well

    as their assigns and heirs. But only

    they. Petitioners, as heirs of Salas, Jr., and

    Respondent Laperal Realty are certainly bound

    by the Agreement. If Respondent Laperal

    Realty, had assigned its rights under the

    Agreement to a third party, making the former,

    the assignor, and the latter, the assignee, such

    assignee would also be bound by the arbitration

    provision since assignment involves such

    transfer of rights as to vest in the assignee the

    power to enforce them to the same extent as the

    assignor could have enforced them against the

    debtor or, in this case, against the heirs of the

    original party to the Agreement. However,

    Respondent Lot Buyers are NOT assignees of

    the rights of Respondent Laperal Realty under

    the Agreement to develop Salas, Jr.s land and

    sell the same. They are, rather, buyers of the

    land that Respondent Laperal Realty was given

    the authority to develop and sell under the

    Agreement. As such, they are NOT assigns

    contemplated in Art. 1311 of the New Civil Code

    which provides that contracts take effect only

    between the parties, their assigns and heirs.

    In the same vein, Petitioners contention that

    rescission, being their cause of action, falls

    under the exception clause in Sec. 2 of Republic

    Act No. 876 is without merit. For while

    rescission, as a general rule, is an arbitrable

    issue, they impleaded in the suit for rescission

    the Respondent Lot Buyers who are neither

    parties to the Agreement nor the latters assigns

    or heirs. Consequently, the right to arbitrate as

    provided in Article VI of the Agreement was

    never vested in Respondent Lot Buyers.

    Tuna Processing Inc v Phil. Kingford Inc.

    May a foreign corporation not licensed to do

    business in the Philippines, but which collects

    royalties from entities in the Philippines, sue

    here to enforce a foreign arbitral award?

    G.R. No. 185582 (February 29, 2012)

    PEREZ, J.:

    FACTS:

    Kanemitsu Yamaoka, co-patentee of a US

    Patent, Philippine Letters Patent, and an

    Indonesian Patent, entered into a Memorandum

    of Agreement (MOA) with five Philippine tuna

    processors including Respondent Philippine

    Kingford, Inc. (KINGFORD). The MOA provides

    for the enforcing of the abovementioned patents,

    granting licenses under the same, and collecting

    royalties, and for the establishment of herein

    Petitioner Tuna Processors, Inc. (TPI).

  • ADR CASE DIGESTS 2015

    pg. 5

    Page number 5

    Due to a series of events not mentioned in the

    Petition, the tuna processors, including

    Respondent KINGFORD, withdrew from

    Petitioner TPI and correspondingly reneged on

    their obligations. Petitioner TPI submitted the

    dispute for arbitration before the International

    Centre for Dispute Resolution in the State of

    California, United States and won the case

    against Respondent KINGFORD.

    To enforce the award, Petitioner TPI filed

    a Petition for Confirmation, Recognition, and

    Enforcement of Foreign Arbitral Award before

    the RTC of Makati City. Respondent KINGFORD

    filed a Motion to Dismiss, which the RTC denied

    for lack of merit. Respondent KINGFORD then

    sought for the inhibition of the RTC judge, Judge

    Alameda, and moved for the reconsideration of

    the order denying the Motion. Judge Alameda

    inhibited himself notwithstanding [t]he

    unfounded allegations and unsubstantiated

    assertions in the motion. Judge Ruiz, to which

    the case was re-raffled, in turn, granted

    Respondent KINGFORDSs Motion for

    Reconsideration and dismissed the Petition on

    the ground that Petitioner TPI lacked legal

    capacity to sue in the Philippines. Petitioner TPI

    is a corporation established in the State of

    California and not licensed to do business in the

    Philippines.

    Hence, the present Petition for Review on

    Certiorari under Rule 45.

    ISSUE:

    Whether or not a foreign corporation not

    licensed to do business in the Philippines, but

    which collects royalties from entities in the

    Philippines, sue here to enforce a foreign arbitral

    award?

    ARGUMENT:

    Petitioner TPI contends that it is entitled to seek

    for the recognition and enforcement of the

    subject foreign arbitral award in accordance

    with RA No. 9285 (Alternative Dispute

    Resolution Act of 2004), the Convention on the

    Recognition and Enforcement of Foreign Arbitral

    Awards drafted during the United Nations

    Conference on International Commercial

    Arbitration in 1958 (New York Convention), and

    the UNCITRAL Model Law on International

    Commercial Arbitration (Model Law), as none of

    these specifically requires that the party seeking

    for the enforcement should have legal capacity

    to sue.

    RULING:

    YES. Petitioner TPI, although not licensed to do

    business in the Philippines, may seek

    recognition and enforcement of the foreign

    arbitral award in accordance with the provisions

    of the Alternative Dispute Resolution Act of

    2004. A foreign corporations capacity to sue in

    the Philippines is not material insofar as the

    recognition and enforcement of a foreign arbitral

    award is concerned.

  • ADR CASE DIGESTS 2015

    pg. 6

    Page number 6

    The Resolution of the RTC is REVERSED and

    SET ASIDE.

    RATIO DECIDENDI:

    Sec. 45 of the Alternative Dispute Resolution Act

    of 2004 provides that the opposing party in an

    application for recognition and enforcement of

    the arbitral award may raise only those grounds

    that were enumerated under Article V of

    the New York Convention, to wit:

    Article V

    1. Recognition and enforcement of the award

    may be refused, at the request of the party

    against whom it is invoked, only if that party

    furnishes to the competent authority where the

    recognition and enforcement is sought, proof

    that:

    a. The parties to the agreement referred to in

    Article II were, under the law applicable to them,

    under some incapacity, or the said agreement is

    not valid under the law to which the parties have

    subjected it or, failing any indication thereon,

    under the law of the country where the award

    was made;

    b. The party against whom the award is invoked

    was not given proper notice of the appointment

    of the arbitrator or of the arbitration proceedings

    or was otherwise unable to present his case;

    c. The award deals with a difference not

    contemplated by or not falling within the terms of

    the submission to arbitration, or it contains

    decisions on matters beyond the scope of the

    submission to arbitration, provided that, if the

    decisions on matters submitted to arbitration can

    be separated from those not so submitted, that

    part of the award which contains decisions on

    matters submitted to arbitration may be

    recognized and enforced;

    d. The composition of the arbitral authority or the

    arbitral procedure was not in accordance with

    the agreement of the parties, or, failing such

    agreement, was not in accordance with the law

    of the country where the arbitration took place;

    or

    e. The award has not yet become binding on the

    parties, or has been set aside or suspended by

    a competent authority of the country in which, or

    under the law of which, that award was made.

    2. Recognition and enforcement of an arbitral

    award may also be refused if the competent

    authority in the country where recognition and

    enforcement is sought finds that:

    a. The subject matter of the difference is not

    capable of settlement by arbitration under the

    law of that country; or

  • ADR CASE DIGESTS 2015

    pg. 7

    Page number 7

    b. The recognition or enforcement of the award

    would be contrary to the public policy of that

    country.

    Not one of the abovementioned exclusive

    grounds touched on the capacity to sue of the

    party seeking the recognition and enforcement

    of the award.

    Pertinent provisions of the Special Rules of

    Court on Alternative Dispute Resolution, which

    was promulgated by the Supreme Court,

    likewise support this position.

    Rule 13.1 of the Special Rules provides that

    [a]ny party to a foreign arbitration may petition

    the court to recognize and enforce a foreign

    arbitral award. The contents of such petition

    are enumerated in Rule 13.5. Capacity to sue is

    not included. Oppositely, in the rule on local

    arbitral awards or arbitrations in instances where

    the place of arbitration is in the Philippines, it is

    specifically required that a petition to determine

    any question concerning the existence, validity

    and enforceability of such arbitration agreement

    available to the parties before the

    commencement of arbitration and/or a petition

    for judicial relief from the ruling of the arbitral

    tribunal on a preliminary question upholding or

    declining its jurisdiction after arbitration has

    already commenced should state [t]he facts

    showing that the persons named as petitioner or

    respondent have legal capacity to sue or be

    sued.

    Indeed, it is in the best interest of justice that

    in the enforcement of a foreign arbitral award,

    the Court deny availment

    by the losing party of the rule that bars

    foreign corporations not licensed to do business

    in the Philippines from maintaining a suit in

    Philippine courts. When a party enters

    into a contract containing a foreign arbitratio

    n clause and, as in this case, in fact submits

    itself to arbitration, it becomes bound by the

    contract, by the arbitration and by the result of

    arbitration, conceding thereby the capacity of

    the other party to enter into the contract,

    participate in the arbitration and cause the

    implementation of the result. Although not on all

    fours with the instant case, also worthy to

    consider is the wisdom of then Associate Justice

    Flerida Ruth P. Romero in her Dissenting

    Opinion in Asset Privatization Trust v. Court of

    Appeals [1998], to wit:

    xxx Arbitration, as an alternative mode of

    settlement, is gaining adherents in legal and

    judicial circles here and abroad. If its tested

    mechanism can simply be ignored by an

    aggrieved party, one who, it must be stressed,

    voluntarily and actively participated in the

    arbitration proceedings from the very beginning,

    it will destroy the very essence of mutuality

    inherent in consensual contracts.

    Clearly, on the matter of capacity to sue, a

    foreign arbitral award should be respected not

    because it is favored over domestic laws and

    procedures, but because Republic Act No.

    9285 has certainly erased any conflict of law

    question.

  • ADR CASE DIGESTS 2015

    pg. 8

    Page number 8

    Finally, even assuming, only for the sake of

    argument, that the RTC correctly observed that

    theModel Law, not the New York Convention,

    governs the subject arbitral award, Petitioner

    TPI may still seek recognition and enforcement

    of the award in Philippine court, since the Model

    Law prescribes substantially identical exclusive

    grounds for refusing recognition or enforcement.

    Koppel Inc. v Makati Rotary Club Foundation

    Inc.

    Will the disagreement between parties to a

    contract be rendered non-arbitrable if, in the

    arbitration thereof, the validity of the contract

    itself will have to be determined?

    May a party to a contract invoke the arbitration

    clause thereof and, at the same time, impugn

    the validity of the contract itself?

    Is it necessary for a party seeking arbitration to

    first file a request or an application therefor

    with the court to render an arbitration clause

    operational?

    If parties to a contract already underwent

    Judicial Dispute Resolution (JDR) proceedings

    before the court, may they still refer their dispute

    to arbitration?

    G.R. No. 198075 (September 04, 2013)

    PEREZ, J.:

    FACTS:

    In 1975, Fedders Koppel, Incorporated (FKI)

    bequeathed a parcel of land exclusive of

    improvements thereon in favor of Respondent

    Makati Rotary Club Foundation, Inc. by way of

    aconditional donation. Respondent accepted the

    donation with all of its conditions. On 26 May

    1975, FKI and the Respondent executed a Deed

    of Donation evidencing their consensus.

  • ADR CASE DIGESTS 2015

    pg. 9

    Page number 9

    One of the conditions of the donation required

    the Respondent to lease the subject land back

    to FKI under terms specified in their Deed of

    Donation. With the Respondents acceptance of

    the donation, a lease agreement between them

    was, therefore, effectively incorporated in

    the Deed of Donation.

    Pertinent terms of such lease agreement, as

    provided in the Deed of Donation, were as

    follows:

    1. The period of the lease is for twenty-five (25)

    years, or until the 25th of May 2000;

    2. The amount of rent to be paid by FKI for the

    first twenty-five (25) years is P40,126.00

    perannum.

    The Deed of Donation also stipulated that the

    lease over the subject property is renewable for

    another period of twenty-five (25) years upon

    mutual agreement of FKI and the Respondent.

    In which case, the amount of rent shall be

    determined in accordance with item 2(g) of

    the Deed of Donation.

    In October 1976, FKI and the Respondent

    executed an Amended Deed of Donation that

    reiterated the provisions of the Deed of

    Donation, including those relating to the lease of

    the subject land.

    Verily, by virtue of the lease agreement

    contained in the Deed of

    Donation and Amended Deed of Donation, FKI

    was able to continue in its possession and use

    of the subject land.

    Two (2) days before the lease incorporated in

    the Deed of Donation and Amended Deed of

    Donation was set to expire, or on 23 May 2000,

    FKI and Respondent executed another contract

    of lease (2000 Lease Contract) covering the

    subject land. In this 2000 Lease Contract, FKI

    and Respondent agreed on a new five-year

    lease to take effect on the 26th of May 2000, with

    annual rents ranging from P4M for the first year

    up to P4.9M for the fifth year.

    The 2000 Lease Contract also contained an

    arbitration clause enforceable in the event the

    parties come to disagreement about the

    interpretation, application and execution of the

    lease.

    After the 2000 Lease Contract expired, FKI and

    Respondent agreed to renew their lease for

    another five (5) years. This new lease (2005

    Lease Contract) required FKI to pay a fixed

    annual rent of P4.2M.In addition to paying the

    fixed rent, however, the 2005 Lease

    Contract also obligated FKI to make a yearly

    donation of money to the Respondent. Such

    donations ranged from P3M for the first year up

    to P3.9M for the fifth year.

  • ADR CASE DIGESTS 2015

    pg. 10

    Page number 10

    Notably, the 2005 Lease Contract contained an

    arbitration clause similar to that in the 2000

    Lease Contract, to wit:

    19. Governing Law The provisions of this

    [2005 Lease Contract] shall be governed,

    interpreted and construed in all aspects in

    accordance with the laws of the Republic of the

    Philippines.

    Any disagreement as to the interpretation,

    application or execution of this [2005 Lease

    Contract] shall be submitted to a board of three

    (3) arbitrators constituted in accordance with the

    arbitration law of the Philippines. The decision of

    the majority of the arbitrators shall be binding

    upon [FKI and Respondent]. (Emphasis

    supplied)

    From 2005 to 2008, FKI faithfully paid the

    rentals and donations due it per the 2005

    Lease Contract. But in June of 2008, FKI sold all

    its rights and properties relative to its business in

    favor of herein Petitioner Koppel, Incorporated.

    On 29 August 2008, FKI and Petitioner executed

    an Assignment and Assumption of Lease and

    Donationwherein FKI, with the conformity of

    the Respondent, formally assigned all of its

    interests and obligations under the Amended

    Deed of Donation and the 2005 Lease

    Contract in favor of Petitioner.

    The following year, Petitioner discontinued the

    payment of the rent and donation under the

    2005Lease Contract.

    Petitioners refusal to pay such rent and

    donation emanated from its belief that the

    rental stipulations of the 2005 Lease Contract,

    and even of the 2000 Lease Contract, cannot be

    given effect because they violated one of the

    material conditions of the donation of the

    subject land, as stated in the Deed of

    Donation and Amended Deed of Donation.

    According to Petitioner, the Deed of

    Donation and Amended Deed of

    Donation actually established not only one but

    two (2) lease agreements between FKI and

    Respondent, i.e., one lease for the first twenty-

    five (25) years or from 1975 to 2000, and

    another lease for the next twenty-five (25) years

    thereafter or from 2000 to 2025. Both leases are

    material conditions of the donation of the subject

    land.

    Petitioner points out that while a definite amount

    of rent for the second twenty-five (25) year lease

    was not fixed in the Deed of

    Donation and Amended Deed of Donation, both

    deeds nevertheless prescribed rules and

    limitations by which the same may be

    determined. Such rules and limitations ought to

    be observed in any succeeding lease

    agreements between Petitioner and Respondent

    for they are, in themselves, material conditions

    of the donation of the subject land.

  • ADR CASE DIGESTS 2015

    pg. 11

    Page number 11

    In this connection, Petitioner cites item 2(g) of

    the Deed of Donation and Amended Deed of

    Donation that supposedly limits the amount of

    rent for the lease over the second twenty-five

    (25) years to only three percent (3%) of the fair

    market value of the [subject] land excluding the

    improvements.

    For Petitioner then, the rental stipulations of both

    the 2000 Lease Contract and 2005 Lease

    Contract cannot be enforced as they are clearly,

    in view of their exorbitant exactions, in violation

    of the aforementioned threshold in item 2(g) of

    the Deed of Donation and Amended Deed of

    Donation. Consequently, Petitioner insists that

    the amount of rent it has to pay thereon is and

    must still be governed by the limitations

    prescribed in the Deed of

    Donation and Amended Deed of Donation.

    Respondent then sent Demand Letters to

    Petitioners notifying the latter of its default,

    demanding for the settlement of the rent and

    donations due for the year 2009. Respondent

    intimated of cancelling the 2005 Lease

    Contract should Petitioner fail to settle the said

    obligations. In its last sent Demand Letter,

    Respondent demand Petitioner to immediately

    vacate the leased premises should it fail to pay

    such obligations within seven (7) days from its

    receipt of the letter.

    Petitioner refused to comply with the demands

    of the Respondent. Instead, on 30 September

    2009, Petitioner filed with the RTC of Paraaque

    City a Complaint for the Rescission or

    Cancellation of the Deed of

    Donation and Amended Deed of

    Donation against the Respondent.

    On 5 October 2009, Respondent filed

    an Unlawful Detainer case against the Petitioner

    before the MeTC of Paraaque City.

    On 4 November 2009, Petitioner filed an Answer

    with Compulsory Counterclaim.In it, Petitioner

    reiterated its objection over the rental

    stipulations of the 2005 Lease Contract for being

    violative of the material conditions of the Deed of

    Donation and Amended Deed of Donation.

    On 27 April 2010, the MeTC rendered judgment

    in favor of the Petitioner. While the MeTC

    refused to dismiss the action on the ground that

    the dispute is subject to arbitration, it

    nonetheless sided with the Petitioner with

    respect to the issues regarding the insufficiency

    of the Respondents demand and the nullity of

    the 2005 Lease Contract.

    The Respondent appealed to the RTC which

    reversed the MeTCs decision.

    Aggrieved, the Petitioner appealed to the CA

    which affirmed the decision of the RTC.

    Hence, the present Petition for Review on

    Certiorari under Rule 45.

  • ADR CASE DIGESTS 2015

    pg. 12

    Page number 12

    ISSUE:

    Whether or not the present dispute is arbitrable

    under the Arbitration Clause of the 2005 Lease

    Agreement Contract?

    ARGUMENTS:

    At different points in the proceedings of this

    case, the following arguments were offered

    against the application of the arbitration clause

    of the 2005 Lease Contract:

    1. The disagreement between the

    Petitioner and Respondent is non-

    arbitrable as it will inevitably touch upon

    the issue of the validity of the 2005

    Lease Contract. It was submitted that

    one of the reasons offered by the

    Petitioner in justifying its failure to pay

    under the 2005 Lease Contract was the

    nullity of such contract for being contrary

    to law and public policy. The Supreme

    Court, in Gonzales v. Climax Mining,

    Ltd. [2005], held that the validity of

    contract cannot be subject of arbitration

    proceedings as such questions are

    legal in nature and require the

    application and interpretation of laws

    and jurisprudence which is necessarily a

    judicial function.

    2. The Petitioner cannot validly invoke the

    arbitration clause of the 2005 Lease

    Contract while, at the same time,

    impugn such contracts validity.

    3. Even assuming that it can invoke the

    arbitration clause whilst denying the

    validity of the2005 Lease Contract,

    Petitioner still did not file a formal

    application before the MeTC so as to

    render such arbitration clause

    operational. Section 24 of Republic Act

    No. 9285 requires the party seeking

    arbitration to first file a request or an

    application therefor with the court not

    later than the preliminary conference.

    4. Petitioner and Respondent already

    underwent JDR proceedings before the

    RTC. Hence, a further referral of the

    dispute to arbitration would only be

    circuitous. Moreover, an ejectment case,

    in view of its summary nature, already

    fulfills the prime purpose of

    arbitration, i.e., to provide parties in

    conflict with an expedient method for the

    resolution of their dispute. Arbitration

    then would no longer be necessary in

    this case.

    RULING:YES. None of the above-

    mentioned arguments have any merit.

    The MeTC, RTC and CA all erred in

    overlooking the significance of the

    arbitration clause incorporated in

    the 2005 Lease Contract. As the SC

    sees it, that is a fatal mistake.Hence, the

  • ADR CASE DIGESTS 2015

    pg. 13

    Page number 13

    Petition is GRANTED and thus referring

    the Petitioner and the Respondent to

    arbitration pursuant to the arbitration

    clause of the 2005 Lease Contract,

    repeatedly included in the 2000 Lease

    Contract and in the 1976

    Amended Deed of Donation.

    RATIO DECIDENDI:

    The arbitration clause of the 2005 Lease

    Contract stipulates that any disagreement as to

    the interpretation, application or execution of

    the 2005 Lease Contract ought to be submitted

    to arbitration. To the mind of the Court, such

    stipulation is clear and is comprehensive enough

    so as to include virtually any kind of conflict or

    dispute that may arise from the 2005 Lease

    Contractincluding the one that presently besets

    Petitioner and Respondent.

    First. The disagreement between the Petitioner

    and Respondent falls within the all-

    encompassing terms of the arbitration clause of

    the 2005 Lease Contract. While it may be

    conceded that in the arbitration of such

    disagreement, the validity of the 2005 Lease

    Contract, or at least, of such contracts rental

    stipulations would have to be determined, the

    same would not render such disagreement non-

    arbitrable. The quotation from Gonzales case

    that was used to justify the contrary position was

    taken out of context.

    The pivotal issue that confronted the Court in

    the Gonzales case was whether the complaint

    for arbitration raises arbitrable issues that the

    Panel of Arbitrators of the Mines and

    Geosciences Bureau (PA-MGB) can take

    cognizance of.

  • ADR CASE DIGESTS 2015

    pg. 14

    Page number 14

    Gonzales decided the issue in the negative. In

    holding that the PA-MGB was devoid of any

    jurisdiction to take cognizance of the complaint

    for arbitration, this Court pointed out to the

    provisions of R.A. No. 7942, or the Mining Act of

    1995, which granted the PA-MGB with exclusive

    original jurisdiction only over mining disputes,

    i.e., disputes involving rights to mining areas,

    mineral agreements or permits, and surface

    owners, occupants, claimholders or

    concessionaires requiring the technical

    knowledge and experience of mining authorities

    in order to be resolved. Accordingly, since the

    complaint for arbitration in Gonzales did not

    raise mining disputes as contemplated under

    R.A. No. 7942 but only issues relating to the

    validity of certain mining related agreements, SC

    held that such complaint could not be arbitrated

    before the PA-MGB. It is in this context that SC

    made the pronouncement now in

    discussion.Arbitration before the Panel of

    Arbitrators is proper only when there is a

    disagreement between the parties as to some

    provisions of the contract between them, which

    needs the interpretation and the application of

    that particular knowledge and expertise

    possessed by members of that Panel. It is not

    proper when one of the parties repudiates the

    existence or validity of such contract or

    agreement on the ground of fraud or oppression

    as in this case. The validity of the contract

    cannot be subject of arbitration

    proceedings. Allegations of fraud and duress in

    the execution of a contract are matters within the

    jurisdiction of the ordinary courts of law. These

    questions are legal in nature and require the

    application and interpretation of laws and

    jurisprudence which is necessarily a judicial

    function. (Emphasis supplied)

  • ADR CASE DIGESTS 2015

    pg. 15

    Page number 15

    SC in Gonzales did not simply base its rejection

    of the complaint for arbitration on the ground

    that the issue raised therein, i.e., the validity of

    contracts, is per se non-arbitrable. The real

    consideration behind the ruling was the limitation

    that was placed by R.A. No. 7942 upon the

    jurisdiction of the PA-MGB as an arbitral

    body. Gonzales rejected the complaint for

    arbitration because the issue raised therein is

    not a mining dispute per R.A. No. 7942 and it is

    for this reason, and only for this reason, that

    such issue is rendered non-arbitrable before the

    PA-MGB. As stated beforehand, R.A. No. 7942

    clearly limited the jurisdiction of the PA-MGB

    only tomining disputes.Much more instructive for

    our purposes, on the other hand, is the recent

    case of Cargill Philippines, Inc. v. San Fernando

    Regal Trading, Inc [2011]. In Cargill, SC

    answered the question of whether issues

    involving the rescission of a contract are

    arbitrable. The respondent in Cargill argued

    against arbitrability, also citing therein Gonzales.

    After dissecting Gonzales, SC ruled in favor of

    arbitrability. Thus, SC held:Respondent

    contends that assuming that the existence of the

    contract and the arbitration clause is conceded,

    the CAs decision declining referral of the

    parties dispute to arbitration is still correct. It

    claims that its complaint in the RTC presents the

    issue of whether under the facts alleged, it is

    entitled to rescind the contract with damages;

    and that issue constitutes a judicial question or

    one that requires the exercise of judicial function

    and cannot be the subject of an arbitration

    proceeding. Respondent cites our ruling in

    Gonzales, wherein we held that a panel of

    arbitrator is bereft of jurisdiction over the

    complaint for declaration of nullity/or termination

    of the subject contracts on the grounds of fraud

    and oppression attendant to the execution of the

    addendum contract and the other contracts

    emanating from it, and that the complaint should

    have been filed with the regular courts as it

    involved issues which are judicial in nature.

    Such argument is misplaced and respondent

    cannot rely on the Gonzales case to support its

    argument. (Emphasis ours)

    Second. Petitioner may still invoke the

    arbitration clause of the 2005 Lease

    Contractnotwithstanding the fact that it assails

    the validity of such contract. This is due to

    the doctrine of separability.

    Under the doctrine of separability, an arbitration

    agreement is considered as independent of the

    main contract. Being a separate contract in

    itself, the arbitration agreement may thus be

    invoked regardless of the possible nullity or

    invalidity of the main contract.

    Once again instructive is Cargill, wherein SC

    held that, as a further consequence of the

    doctrine of separability, even the very party who

    repudiates the main contract may invoke its

    arbitration clause.

  • ADR CASE DIGESTS 2015

    pg. 16

    Page number 16

    Third. The operation of the arbitration clause in

    this case is not at all defeated by the failure of

    the Petitioner to file a formal request or

    application therefor with the MeTC. SC finds that

    the filing of a request pursuant to Section 24

    of R.A. No. 9285 is not the sole means by which

    an arbitration clause may be validly invoked in a

    pending suit.

    Section 24 of R.A. No. 9285 reads:

    SEC. 24. Referral to Arbitration. A court before

    which an action is brought in a matter which is

    the subject matter of an arbitration agreement

    shall, if at least one party so requestsnot later

    that the pre-trial conference, or upon the request

    of both parties thereafter, refer the parties to

    arbitration unless it finds that the arbitration

    agreement is null and void, inoperative or

    incapable of being performed. [Emphasis ours;

    italics original]

    The request referred to in the above provision

    is, in turn, implemented by Rules 4.1 to 4.3

    ofA.M. No. 07-11-08-SC or the Special Rules of

    Court on Alternative Dispute Resolution (Special

    ADR Rules):

    RULE 4: REFERRAL TO ADR

    Rule 4.1. Who makes the request. A party to a

    pending action filed in violation of the arbitration

    agreement, whether contained in an arbitration

    clause or in a submission

    agreement, may request the court to refer the

    parties to arbitration in accordance with such

    agreement.

    Rule 4.2. When to make request. (A) Where

    the arbitration agreement exists before the

    action is filed. The request for referral shall be

    made not later than the pre-trial conference.

    After the pre-trial conference, the court will only

    act upon the request for referral if it is made with

    the agreement of all parties to the case.

    (B) Submission agreement. If there is no

    existing arbitration agreement at the time the

    case is filed but the parties subsequently enter

    into an arbitration agreement, they may request

    the court to refer their dispute to arbitration at

    any time during the proceedings.

    Rule 4.3. Contents of request. The request for

    referral shall be in the form of a motion, which

    shall state that the dispute is covered by an

    arbitration agreement.

    Apart from other submissions, the movant shall

    attach to his motion an authentic copy of the

    arbitration agreement.

    The request shall contain a notice of hearing

    addressed to all parties specifying the date and

    time when it would be heard. The party making

    the request shall serve it upon the respondent to

    give him the opportunity to file a comment or

    opposition as provided in the immediately

    succeeding Rule before the hearing. [Emphasis

    ours; italics original]

  • ADR CASE DIGESTS 2015

    pg. 17

    Page number 17

    Attention must be paid, however, to the salient

    wordings of Rule 4.1. It reads: [a] party to a

    pending action filed in violation of the arbitration

    agreement x x x may request the court to refer

    the parties to arbitration in accordance with such

    agreement.

    In using the word may to qualify the act of filing

    a request under Section 24 of R.A. No. 9285,

    the Special ADR Rules clearly did not intend to

    limit the invocation of an arbitration agreement in

    a pending suit solely via such request. After all,

    non-compliance with an arbitration agreement is

    a valid defense to any offending suit and, as

    such, may even be raised in an answer as

    provided in our ordinary rules of procedure.

    In this case, it is conceded that Petitioner was

    not able to file a separate request of arbitration

    before the MeTC. However, it is equally

    conceded that the Petitioner, as early as in

    its Answer with Counterclaim, had already

    apprised the MeTC of the existence of the

    arbitration clause in the 2005 Lease

    Contract and, more significantly, of its desire to

    have the same enforced in this case. This act of

    Petitioner is enough valid invocation of his right

    to arbitrate.

    Fourth. The fact that the Petitioner and

    Respondent already underwent through JDR

    proceedings before the RTC, will not make the

    subsequent conduct of arbitration between the

    parties unnecessary or circuitous. The JDR

    system is substantially different from arbitration

    proceedings.

    The JDR framework is based on the processes

    of mediation, conciliation or early neutral

    evaluation which entails the submission of a

    dispute before a JDR judge who shall merely

    facilitate settlement between the parties in

    conflict or make a non-binding evaluation or

    assessment of the chances of each partys

    case. Thus in JDR, the JDR judge lacks the

    authority to render a resolution of the dispute

    that is binding upon the parties in conflict. In

    arbitration, on the other hand, the dispute is

    submitted to an arbitrator/sa neutral third

    person or a group of thereofwho shall have

    the authority to render a resolution binding upon

    the parties.

    Clearly, the mere submission of a dispute to

    JDR proceedings would not necessarily render

    the subsequent conduct of arbitration a mere

    surplusage. The failure of the parties in conflict

    to reach an amicable settlement before the JDR

    may, in fact, be supplemented by their resort to

    arbitration where a binding resolution to the

    dispute could finally be achieved. This situation

    precisely finds application to the case at bench.

    Neither would the summary nature of ejectment

    cases be a valid reason to disregard the

    enforcement of the arbitration clause of the 2005

    Lease Contract. Notwithstanding the summary

    nature of ejectment cases, arbitration still

    remains relevant as it aims not only to afford the

    parties an expeditious method of resolving their

    dispute.

  • ADR CASE DIGESTS 2015

    pg. 18

    Page number 18

    A pivotal feature of arbitration as an alternative

    mode of dispute resolution is that it is, first and

    foremost, a product of party autonomy or the

    freedom of the parties to make their own

    arrangements to resolve their own disputes.

    Arbitration agreements manifest not only the

    desire of the parties in conflict for an expeditious

    resolution of their dispute. They also represent,

    if not more so, the parties mutual aspiration to

    achieve such resolution outside of judicial

    auspices, in a more informal and less

    antagonistic environment under the terms of

    their choosing. Needless to state, this critical

    feature can never be satisfied in an ejectment

    case no matter how summary it may be.

    Legal Effect of the Application of the Arbitration

    Clause

    Since there really are no legal impediments to

    the application of the arbitration clause of

    the 2005 Contract of Lease in this case, We find

    that the instant unlawful detainer action was

    instituted in violation of such clause. The Law,

    therefore, should have governed the fate of the

    parties and this suit:

    R.A. No. 876

    Section 7. Stay of civil action. If any suit or

    proceeding be brought upon an issue arising out

    of an agreement providing for the arbitration

    thereof, the court in which such suit or

    proceeding is pending, upon being satisfied that

    the issue involved in such suit or proceeding is

    referable to arbitration, shall stay the action or

    proceeding until an arbitration has been had in

    accordance with the terms of the agreement:

    Provided, That the applicant for the stay is not in

    default in proceeding with such arbitration.

    [Emphasis supplied]

    R.A. No. 9285

    Section 24. Referral to Arbitration. A court

    before which an action is brought in a matter

    which is the subject matter of an arbitration

    agreement shall, if at least one party so requests

    not later that the pre-trial conference, or upon

    the request of both parties thereafter, refer the

    parties to arbitration unless it finds that the

    arbitration agreement is null and void,

    inoperative or incapable of being performed.

    [Emphasis supplied]

    It is clear that under the law, the instant unlawful

    detainer action should have been stayed; the

    Petitioner and the Respondent should have

    been referred to arbitration pursuant to the

    arbitration clause of the 2005 Lease Contract.

    The MeTC, however, did not do so in violation of

    the lawwhich violation was, in turn, affirmed by

    the RTC and Court of Appeals on appeal.

  • ADR CASE DIGESTS 2015

    pg. 19

    Page number 19

    The violation by the MeTC of the clear directives

    under R.A. Nos. 876 and 9285 renders invalid all

    proceedings it undertook in the ejectment

    case after the filing by Petitioner of its Answer

    with Counterclaimthe point when the

    Petitioner and the Respondent should have

    been referred to arbitration. This case must,

    therefore, be remanded to the MeTC and be

    suspended at said point. Inevitably, the

    decisions of the MeTC, RTC and the Court of

    Appeals must all be vacated and set aside.

    The Petitioner and the Respondent must then be

    referred to arbitration pursuant to the arbitration

    clause of the 2005 Lease Contract.

    J Plus Asia Corporation v Utility Assurance

    Corporation

    Does CA have jurisdiction to review arbitral

    awards?

    G.R. No. 199650 (June 26, 2013)

    VILLARAMA, JR., J.:

    FACTS:

    Petitioner J Plus Asia Development Corporation

    and Martin E. Mabunay entered into

    aConstruction Agreement on December 24,

    2007 whereby the latter undertook to build the

    formers 72-room condominium/hotel located in

    Boracay Island.

    The project, costing P42M, was to be completed

    within one year or 365 days reckoned from the

    first calendar day after signing of the Notice of

    Award and Notice to Proceed and receipt of

    down payment (20% of contract price). The

    P8.4M down payment was fully paid on January

    14, 2008. Payment of the balance of the contract

    price will be based on actual work finished within

    15 days from receipt of the monthly progress

    billings. Per the agreed work schedule, the

    completion date of the project was December

    2008. Mabunay also submitted the

    required Performance Bond issued by

    Respondent Utility Assurance Corporation in the

    amount equivalent to 20% down payment or

    P8.4M.

    Mabunay commenced work at the project site on

    January 7, 2008. Petitioner paid up to the 7th

    monthly progress billing sent by Mabunay. As of

    September 16, 2008, Petitioner had paid the

    total amount of P15.98M inclusive of the 20%

    down payment. However, as of said date,

    Mabunay had accomplished only 27.5% of the

    project. It was later found out by the joint

    inspection and evaluation by the Petitioner and

    Mabunay that, as of November 14, 2008, the

    project was only 31.39% complete and that the

    uncompleted portion was 68.61%.

    On November 19, 2008, Petitioner terminated

    the contract and sent Demand Letters to

    Mabunay and Respondent surety. As its

    demands went unheeded, Petitioner filed

    a Request for Arbitrationbefore the Construction

    Industry Arbitration Commission (CIAC).

  • ADR CASE DIGESTS 2015

    pg. 20

    Page number 20

    In his Answer, Mabunay claimed that the delay

    was caused by retrofitting and other revision

    works ordered by Petitioner. He asserted that

    he actually had until April 30, 2009 to finish the

    project since the 365 days period of completion

    started only on May 2, 2008 after clearing the

    retrofitted old structure. Hence, the termination

    of the contract by Petitioner was premature and

    the filing of the Complaint against him was

    baseless, malicious and in bad faith.

    Respondent, on the other hand, filed a Motion to

    Dismiss on the ground that Petitioner has no

    cause of action and the complaint states no

    cause of action against it. The CIAC denied

    the Motion to Dismiss.

    In its Answer Ex Abundante Ad Cautelam with

    Compulsory Counterclaims and Cross-claims,

    Respondent argued that the Performance

    Bond merely guaranteed the 20% down

    payment and not the entire obligation of

    Mabunay under the Construction

    Agreement. Since the value of the projects

    accomplishment already exceeded the said

    amount, Respondents obligation under

    thePerformance Bond had been fully

    extinguished. As to the claim for alleged

    overpayment to Mabunay, Respondent

    contended that it should not be credited against

    the 20% down payment which was already

    exhausted and such application by Petitioner is

    tantamount to reviving an obligation that had

    been legally extinguished by

    payment. Respondent also set up a cross-claim

    against Mabunay who executed in its favor

    an Indemnity Agreement whereby Mabunay

    undertook to indemnify Respondent for whatever

    amounts it may be adjudged liable to pay

    Petitioner under the surety bond.

    On February 2, 2010, CIAC rendered its

    Decision and made Awards in favor of

    Petitioner. CIAC ruled that Mabunay had

    incurred delay which entitled Petitioner to the

    stipulated liquidated damages and unrecouped

    down payment.

    Dissatisfied, Respondent filed in the CA

    a Petition for Review under Rule 43 of the 1997

    Rules of Civil Procedure, as amended, which

    reversed the CIACs ruling.

  • ADR CASE DIGESTS 2015

    pg. 21

    Page number 21

    Hence, the present Petition for Review on

    Certiorari under Rule 45 seeking to reverse the

    CA insofar as it denied its claims under

    the Performance Bond and to reinstate in its

    entirety the February 2, 2010 CIAC Decision.

    ISSUE:

    Whether or not the Alternative Dispute

    Resolution Act of 2004 and the Special ADR

    Rules have stripped the CA of jurisdiction to

    review arbitral awards?

    ARGUMENT:

    Petitioner contends that that with the

    institutionalization of alternative dispute

    resolution under RA No. 9285, otherwise known

    as the Alternative Dispute Resolution Act of

    2004, the CA was divested of jurisdiction to

    review the decisions or awards of the CIAC.

    RULING:

    NO. The Petitioners contention is without merit.

    Petitioner erroneously relied on the provision

    in RA No. 9285 allowing any party to a domestic

    arbitration to file in the RTC a petition either to

    confirm, correct or vacate a domestic arbitral

    award.

    The Petition is GRANTED. The assailed

    decision of the CA is REVERSED and SET

    ASIDE. The Award made in the

    Decision rendered by CIAC dated February 2,

    2010 is REINSTATED with MODIFICATIONS.

    RATIO DECIDENDI:

    SC holds that RA No. 9285 did not confer on

    RTCs jurisdiction to review awards or decisions

    of the CIAC in construction disputes. On the

    contrary, Section 40 thereof expressly declares

    that confirmation by the RTC is NOT required,

    thus:

    SEC. 40. Confirmation of Award. The

    confirmation of a domestic arbitral award shall

    be governed by Section 23 of R.A. 876.

    A domestic arbitral award when confirmed shall

    be enforced in the same manner as final and

    executory decisions of the Regional Trial Court.

    The confirmation of a domestic award shall be

    made by the regional trial court in accordance

    with the Rules of Procedure to be promulgated

    by the Supreme Court.

    A CIAC arbitral award need not be confirmed by

    the regional trial court to be executory as

    provided under E.O. No. 1008. (Emphasis

    supplied.)

  • ADR CASE DIGESTS 2015

    pg. 22

    Page number 22

    EO No. 1008 vests upon the CIAC original and

    exclusive jurisdiction over disputes arising from,

    or connected with, contracts entered into by

    parties involved in construction in the

    Philippines, whether the dispute arises before or

    after the completion of the contract, or after the

    abandonment or breach thereof. By express

    provision of Section 19 thereof, the arbitral

    award of the CIAC is final and unappealable,

    except on questions of law, which are

    appealable to the Supreme Court. With the

    amendments introduced by RA No. 7902 and

    promulgation of the 1997 Rules of Civil

    Procedure, as amended, the CIAC was included

    in the enumeration of quasi- judicial agencies

    whose decisions or awards may be appealed to

    the CA in a Petition for Review under Rule

    43. Such review of the CIAC award may

    involve either questions of fact, of law, or of fact

    and law.Petitioner misread the provisions

    of A.M. No. 07-11-08-SC (Special ADR Rules)

    promulgated by the SC and which took effect on

    October 30, 2009. Since RA No. 9285 explicitly

    excluded CIAC awards from domestic arbitration

    awards that need to be confirmed to be

    executory, said awards are therefore not

    covered by Rule 11 of the Special ADR Rules,

    as they continue to be governed byEO No.

    1008, as amended and the rules of procedure of

    the CIAC. The CIAC Revised Rules of

    Procedure Governing Construction

    Arbitration provide for the manner and mode of

    appeal from CIAC decisions or awards in

    Section 18 thereof, which reads:

    SECTION 18.2 Petition for review. A petition

    for review from a final award may be taken by

    any of the parties within fifteen (15) days from

    receipt thereof in accordance with the provisions

    of Rule 43 of the Rules of Court.

    NIA V CA

    Does the Construction Industry Arbitration

    Commission (CIAC) have jurisdiction over

    construction contracts entered into between

    parties before the creation of said Commission

    in 1985?

    When a construction contract contains an

    arbitration clause, is it still necessary for the

    parties thereto to agree to submit disputes

    arising therefrom specifically to the CIAC for the

    latter to acquire jurisdiction?

    G.R. No. 129169 (November 17, 1999)

    DAVIDE, JR., C.J.:

    FACTS:

    In a competitive bidding held by Petitioner NIA,

    Hydro Resources Contractors Corporation

    (HYDRO) was awarded Contract for the

    construction of the main civil works of the Magat

    River Multi-Purpose Project. The contract

    provided that Respondent HYDRO would be

    paid partly in Philippine pesos and partly in U.S.

    dollars. Respondent HYDRO substantially

    completed the works under the contract in 1982

    and final acceptance by Petitioner NIA was

    made in 1984. Respondent HYDRO thereafter

    determined that it still had an account receivable

    from Petitioner NIA representing the dollar rate

    differential of the price escalation for the

    contract.

  • ADR CASE DIGESTS 2015

    pg. 23

    Page number 23

    After unsuccessfully pursuing its case with

    Petitioner NIA, Respondent HYDRO filed with

    the CIAC a Request for Adjudication of the

    aforesaid claim. Petitioner NIA filed

    its Answer wherein it questioned the jurisdiction

    of the CIAC alleging lack of cause of action,

    laches and estoppel in view of Respondent

    HYDROs alleged failure to avail of its right to

    submit the dispute to arbitration within the

    prescribed period as provided in the contract.

    Later, Petitioner NIA filed a Motion to

    Dismiss alleging lack of jurisdiction over the

    disputes.

    The arbitral body constituted by both parties

    issued an order which deferred the

    determination of the Motion to Dismiss and

    resolved to proceed with the hearing of the case

    on the merits as the grounds cited by Petitioner

    NIA did not seem to be indubitable. Petitioner

    NIA filed a Motion for Reconsideration of the

    aforesaid Order. CIAC in denying the Motion for

    Reconsideration ruled that it has jurisdiction over

    the Respondent HYDROs claim over Petitioner

    NIA pursuant to E.O 1008 and that the hearing

    should proceed as scheduled. CIAC then

    rendered a decision in the main case in favor of

    Respondent HYDRO.

    Petitioner NIA filed with the CA an Original

    Action of Certiorari and Prohibition with prayer

    for Restraining Order and/or Injunction which

    dismissed the same.

    Hence, the present Petition for Certiorari and

    Prohibition with urgent prayer for Temporary

    Restraining Order and Writ of Preliminary

    Injunction.

    ISSUE:

    Whether or not CIAC has jurisdiction to hear and

    try the dispute between the parties?

    ARGUMENTS:

    Petitioner NIA alleged that CIAC has no

    jurisdiction to hear and try the dispute between

    the parties as EO No. 1008 had no retroactive

    effect. It contended that there was no agreement

    with Respondent HYDRO to submit the dispute

    to CIAC for arbitration considering that the

    construction contract was executed in 1978 and

    the project completed in 1982, whereas the

    Construction Industry Arbitration Law creating

    CIAC was signed only in 1985; and that while

    they have agreed to arbitration as a mode of

    settlement of disputes, they could not have

    contemplated submission of their disputes to

    CIAC. Petitioner NIA further argued that records

    show that it had not voluntarily submitted itself to

    arbitration by CIAC. Petitioner NIA contended

    that the CIAC did not acquire jurisdiction over

    the dispute since it was only Respondent

    HYDRO that requested for arbitration. It asserts

    that to acquire jurisdiction over a case, as

    provided under E.O. 1008, the request for

    arbitration filed with CIAC should be made by

    both parties, and hence the request by one party

    is not enough.

    RULING:YES. Contrary to the claim of Petitioner

    NIA, the CIAC has jurisdiction over the

    controversy.

  • ADR CASE DIGESTS 2015

    pg. 24

    Page number 24

    The instant Petition is DISMISSED for lack of

    merit.

    RATIO DECIDENDI:

    EO No. 1008, otherwise known as the

    Construction Industry Arbitration Law which

    was promulgated on 4 February 1985, vests

    upon CIAC original and exclusive jurisdiction

    over disputes arising from, or connected with

    contracts entered into by parties involved in

    construction in the Philippines, whether the

    dispute arises before or after the completion of

    the contract, or after the abandonment or breach

    thereof. The disputes may involve government

    or private contracts. For the Board to acquire

    jurisdiction, the parties to a dispute must agree

    to submit the same to voluntary arbitration.

    The complaint of Respondent HYDRO against

    Petitioner NIA on the basis of the contract

    executed between them was filed on 7

    December 1994, during the effectivity of E.O.

    No. 1008. Hence, it is well within the jurisdiction

    of CIAC. The jurisdiction of a court is determined

    by the law in force at the time of the

    commencement of the action. Petitioner NIAs

    argument that CIAC had no jurisdiction to

    arbitrate on contract which preceded its

    existence is untenable. E.O. 1008 is clear that

    the CIAC has jurisdiction over all disputes

    arising from or connected with construction

    contract whether the dispute arises BEFORE or

    AFTER the completion of the contract. Thus, the

    date the parties entered into a contract and the

    date of completion of the same, even if these

    occurred before the constitution of the CIAC, did

    not automatically divest the CIAC of jurisdiction

    as long as the dispute submitted for arbitration

    arose after the constitution of the CIAC. Stated

    differently, the jurisdiction of CIAC is over the

    dispute, not the contract; and the instant dispute

    having arisen when CIAC was already

    constituted, the arbitral board was actually

    exercising current, not retroactive, jurisdiction.

    It is undisputed that the contracts between

    Respondent HYDRO and Petitioner NIA

    contained anarbitration clause wherein they

    agreed to submit to arbitration any dispute

    between them that may arise before or after the

    termination of the agreement. Consequently, the

    claim of Respondent HYDRO having arisen from

    the contract is arbitrable. Petitioner NIAs

    reliance with the ruling on the case of Tesco

    Services Incorporated v. Vera, is misplaced.

  • ADR CASE DIGESTS 2015

    pg. 25

    Page number 25

    The 1988 CIAC Rules of Procedure which were

    applied by this Court in the Tesco case had

    been duly amended by CIAC Resolutions No. 2-

    91 and 3-93, Section 1 of Article III of which read

    as follows:

    Submission to CIAC Jurisdiction An

    arbitration clause in a construction contract or a

    submission to arbitration of a construction

    contract or a submission to arbitration of a

    construction dispute shall be deemed an

    agreement to submit an existing or future

    controversy to CIAC jurisdiction, notwithstanding

    the reference to a different arbitration institution

    or arbitral body in such contract or submission.

    When a contract contains a clause for the

    submission of a future controversy to arbitration,

    it is not necessary for the parties to enter into a

    submission agreement before the claimant may

    invoke the jurisdiction of CIAC.

    Under the present Rules of Procedure, for a

    particular construction contract to fall within the

    jurisdiction of CIAC, it is merely required that the

    parties agree to submit the same to voluntary

    arbitration. Unlike in the original version of

    Section 1, as applied in the Tesco case, the law

    as it now stands does not provide that the

    parties should agree to submit disputes arising

    from their agreement specifically to the CIAC for

    the latter to acquire jurisdiction over the same.

    Rather, it is plain and clear that as long as the

    parties agree to submit to voluntary arbitration,

    regardless of what forum they may choose, their

    agreement will fall within the jurisdiction of the

    CIAC, such that, even if they specifically choose

    another forum, the parties will not be precluded

    from electing to submit their dispute before the

    CIAC because this right has been vested upon

    each party by law, i.e., E.O. No. 1008.

    Moreover, it is undeniable that Petitioner NIA

    agreed to submit the dispute for arbitration to the

    CIAC. Petitioner NIA through its counsel actively

    participated in the arbitration proceedings by

    filing an Answer with Counterclaim, as well as its

    compliance wherein it nominated arbitrators to

    the proposed panel, participating in the

    deliberations on, and the formulation of, the

    Terms of Reference of the arbitration

    proceeding, and examining the documents

    submitted by Respondent HYDRO after

    Petitioner NIA asked for the originals of the said

    documents.

  • ADR CASE DIGESTS 2015

    pg. 26

    Page number 26

    LM POWER ENGINEERING CORP V CAPITOL

    INDUSTRIAL

    Is there a need to file first a Formal Request for

    Arbitration with the Construction Industry

    Arbitration Commission (CIAC) in order to vest it

    with jurisdiction to decide a construction

    dispute?

    G.R. No. 141833 (March 26, 2003)

    PANGANIBAN, J.:

    FACTS:

    Petitioner and Respondent entered into a

    Subcontract Agreement involving electrical

    work at the Third Port of Zamboanga. Two years

    thereafter, Respondent took over some of the

    work contracted to Petitioner. Allegedly, the

    latter had failed to finish it because of its inability

    to procure materials.

    Upon completing its task under the Contract,

    Petitioner billed Respondent in the amount of

    P6.7M. Respondent, however, refused to pay

    and contested the accuracy of the amount of

    advances and billable accomplishments listed by

    Petitioner. Respondent also took refuge in the

    termination clause of the Agreement. That

    clause allowed it to set off the cost of the work

    that Petitioner had failed to undertake due to

    termination or take-over against the amount it

    owed the latter.

    Because of the dispute, Petitioner filed with the

    RTC of Makati a Complaint for Collection of the

    amount representing the alleged balance due it

    under the Subcontract. Instead of submitting

    anAnswer, Respondent filed a Motion to

    Dismiss, alleging that the Complaint was

    premature because there was no prior recourse

    to arbitration.

    RTC denied the Motion to Dismiss on the

    ground that the dispute did not involve the

    interpretation or the implementation of the

    Agreement and was, therefore, not covered by

    the arbitral clause. The RTC ruled that the take-

    over of some work items by Respondent was not

    equivalent to a termination, but a mere

    modification, of the Subcontract. The latter was

    ordered to give full payment for the work

    completed by Petitioner.

    On appeal, the CA reversed the RTC and

    ordered the referral of the case to arbitration.

    The CA held as arbitrable the issue of whether

    Respondents take-over of some work items had

    been intended to be a termination of the original

    contract under Letter K of the Subcontract.

    Hence, this Petition for Review on

    Certiorari under Rule 45.

    ISSUES:

    1. Whether or not there exists a

    controversy/dispute between Petitioner

    and Respondent regarding the

    interpretation and implementation of the

    Subcontract Agreement that requires

    prior recourse to voluntary arbitration?;

    2. In the affirmative, whether or not there is

    a need to file a request first with the

    CIAC in order to vest it with jurisdiction

    to decide a construction dispute?

  • ADR CASE DIGESTS 2015

    pg. 27

    Page number 27

    ARGUMENTS:

    1.

    Petitioner claims that there is no conflict

    regarding the interpretation or the

    implementation of the Agreement. Thus, without

    having to resort to prior arbitration, it is entitled

    to collect the value of the services it rendered

    through an ordinary action for the collection of a

    sum of money from Respondent.

    On the other hand, Respondent contends that

    there is a need for prior arbitration as provided in

    the Agreement. This is because there are some

    disparities between the parties positions

    regarding the extent of the work done, the

    amount of advances and billable

    accomplishments, and the set off of expenses

    incurred by Respondent in its take-over of

    Petitioners work.

    2.

    According to Petitioner, assuming arguendo that

    the dispute is arbitrable, the failure to file a

    formal request for arbitration with the CIAC

    precluded the latter from acquiring jurisdiction

    over the question.

    RULING:

    The Petition is unmeritorious; hence,

    DENIED. The assailed Decision of the CA is

    AFFIRMED.

    1.

    YES. SC sides with Respondent. The instant

    case involves technical discrepancies that are

    better left to an arbitral body that has expertise

    in those areas.

    2.

    NO. SC is not persuaded with Petitioners

    contention. Section 1 of Article III of the NEW

    Rules of Procedure Governing Construction

    Arbitration has dispensed with the requirement

    to submit a request for arbitration. Recourse to

    the CIAC may now be availed of whenever a

    contract contains a clause for the submission of

    a future controversy to arbitration.

    RATIO DECIDENDI:

    1.

    In the instant case, the Subcontract has the

    following arbitral clause:

    6. The Parties hereto agree that any dispute or

    conflict as regards to interpretation and

    implementation of this Agreement which cannot

    be settled between [respondent] and [petitioner]

    amicably shall be settled by means of arbitration

    x x x.

    Clearly, the resolution of the dispute between

    the parties herein requires a referral to the

    provisions of their Agreement. Within the scope

    of the arbitration clause are discrepancies as to

    the amount of advances and billable

    accomplishments, the application of the

    provision on termination, and the consequent

    set-off of expenses.

    A review of the factual allegations of the parties

    reveals that they differ on the following

    questions, the resolutions of which lies in the

    interpretation of the provisions of the

    Subcontract Agreement:

    1. Did a take-over/termination occur?

    2. May the expenses incurred by

    Respondent in the take-over be set off

    against the amounts it owed Petitioner?

    3. How much were the advances and

    billable accomplishments?

  • ADR CASE DIGESTS 2015

    pg. 28

    Page number 28

    Being an inexpensive, speedy and amicable

    method of settling disputes, arbitration along

    with mediation, conciliation and negotiation is

    encouraged by the SC. Aside from unclogging

    judicial dockets, arbitration also hastens the

    resolution of disputes, especially of the

    commercial kind. It is thus regarded as the

    wave of the future in international civil and

    commercial disputes. Brushing aside a

    contractual agreement calling for arbitration

    between the parties would be a step backward.

    Consistent with the above-mentioned policy of

    encouraging alternative dispute resolution

    methods, courts should liberally construe

    arbitration clauses. Provided such clause is

    susceptible of an interpretation that covers the

    asserted dispute, an order to arbitrate should be

    granted. Any doubt should be resolved in favor

    of arbitration.

    2.

    Section 1 of Article III of the NEW Rules of

    Procedure Governing Construction Arbitration

    provides:

    SECTION 1. Submission to CIAC Jurisdiction

    An arbitration clause in a construction

    contract or a submission to arbitration of a

    construction dispute shall be deemed an

    agreement to submit an existing or future

    controversy to CIAC jurisdiction, notwithstanding

    the reference to a different arbitration institution

    or arbitral body in such contract or submission.

    When a contract contains a clause for the

    submission of a future controversy to arbitration,

    it is not necessary for the parties to enter into a

    submission agreement before the claimant may

    invoke the jurisdiction of CIAC.

    As clearly explained in China Chang Jiang

    Energy Corporation (Philippines) v. Rosal

    Infrastructure Builders et al. (an extended

    unsigned Resolution) and reiterated in National

    Irrigation Administration v. Court of Appeals

    [1999], from which SC quote thus:

    Under the present Rules of Procedure, for a

    particular construction contract to fall within the

    jurisdiction of CIAC, it is merely required that the

    parties agree to submit the same to voluntary

    arbitration unlike in the original version of

    Section 1, as applied in the Tesco case, the law

    as it now stands does not provide that the

    parties should agree to submit disputes arising

    from their agreement specifically to the CIAC for

    the latter to acquire jurisdiction over the same.

    Rather, it is plain and clear that as long as the

    parties agree to submit to voluntary arbitration,

    regardless of what forum they may choose, their

    agreement will fall within the jurisdiction of the

    CIAC, such that, even if they specifically choose

    another forum, the parties will not be precluded

    from electing to submit their dispute before the

    CIAC because this right has been vested upon

    each party by law, i.e., E.O. No. 1008.

    Clearly, there is no more need to file a request

    with the CIAC in order to vest it with jurisdiction

    to decide a construction dispute.

    The arbitral clause in the Agreement is a

    commitment on the part of the parties to submit

    to arbitration the disputes covered therein.

    Because that clause is binding, they are

    expected to abide by it in good faith. And

    because it covers the dispute between the

    parties in the present case, either of them may

    compel the other to arbitrate.