ADR DIGEST
-
Upload
karmaranth -
Category
Documents
-
view
134 -
download
6
description
Transcript of ADR DIGEST
-
ADR CASE DIGESTS 2015
pg. 1
Page number 1
Heirs of Augusto Salas v Laperal Realty
Corporation
Upon whom is an agreement to submit to
arbitration binding?
G.R. NO. 135362 (December 13, 1999)
DE LEON, JR., J.:
FACTS:
Augusto Salas, Jr. was the registered owner of a
vast tract of land in Lipa City, Batangas. He
entered into an Owner-Contractor
Agreement with Respondent Laperal Realty
Corporation to render and provide complete
(horizontal) construction services on his land.
Said agreement contains an arbitration
clause, to wit:
ARTICLE VI. ARBITRATION.
All cases of dispute between CONTRACTOR
and OWNERS representative shall be referred
to the committee represented by:
1. One representative of the OWNER;
2. One representative of the CONTRACTOR;
3. One representative acceptable to both
OWNER and CONTRACTOR.
Salas, Jr. then executed a Special Power of
Attorney in favor of Respondent Laperal Realty
to exercise general control, supervision and
management of the sale of his land, for cash or
on installment basis. By virtue thereof,
Respondent Laperal Realty subdivided said land
and sold portions thereof to Respondents
Rockway Real Estate Corporation and South
Ridge Village, Inc. in 1990; to Respondent
spouses Abrajano and Lava and Oscar Dacillo
in 1991; and to Respondents Eduardo Vacuna,
Florante de la Cruz and Jesus Vicente Capalan
in 1996 (Respondent Lot Buyers hereinafter).
Back in 1989, Salas, Jr. left his home in the
morning for a business trip to Nueva Ecija. He,
however, never returned on that unfaithful
morning. Seven years later or in 1996, his wife,
Teresita Diaz-Salas filed with the RTC of Makati
City a verified Petition for the Declaration of
Presumptive Death, which Petition was granted.
In 1998, Petitioners, as heirs of Salas, Jr. filed in
the RTC of Lipa City a Complaint for Declaration
of Nullity of Sale, Reconveyance, Cancellation of
Contract, Accounting and Damages against
Respondents.
Respondent Laperal Realty filed a Motion to
Dismiss on the ground that Petitioners failed to
submit their grievance to arbitration as required
under Article VI of the Owner-Contractor
Agreement. Respondent spouses Abrajano and
Lava and Respondent Dacillo filed a
Joint Answer with Counterclaim and
Crossclaim praying for dismissal of Petitioners
Complaint for the same reason.
-
ADR CASE DIGESTS 2015
pg. 2
Page number 2
The RTC then issued the herein assailed Order
dismissing Petitioners Complaint for non-
compliance with the foregoing arbitration clause.
Hence the present Petition for Review on
Certiorari under Rule 45.
ISSUE:
Whether or not the arbitration clause under
Article VI of the Owner-Contractor Agreement
is binding upon the Respondent Lot Buyers?
ARGUMENTS:
Petitioners argue that (1) their causes of action
did not emanate from the Owner-Contractor
Agreement, (2) that their causes of action for
cancellation of contract and accounting are
covered by the exception under the Arbitration
Law, and (3) that failure to arbitrate is not a
ground for dismissal.
Petitioners claim that they suffered lesion of
more than one-fourth (1/4) of the value of Salas,
Jr.s land when Respondent Laperal Realty
subdivided it and sold portions thereof to
Respondent Lot Buyers. Thus, they instituted
action against both Respondent Laperal Realty
and Respondent Lot Buyers for rescission of the
sale transactions and reconveyance to them of
the subdivided lots. They argue that rescission,
being their cause of action, falls under the
exception clause in Sec. 2 ofRepublic Act No.
876 which provides that such submission [to] or
contract [of arbitration] shall be valid,
enforceable and irrevocable, save upon such
grounds as exist at law for the revocation of any
contract.
-
ADR CASE DIGESTS 2015
pg. 3
Page number 3
RULING: NO. Respondent Lot Buyers are
neither parties to the Agreement nor the latters
assigns or heirs. Consequently, the right to
arbitrate as provided in Article VI of the
Agreement was never vested in Respondent Lot
Buyers. Respondent Laperal Realty, on the
other hand, as a contracting party to the
Agreement, has the right to compel Petitioners
to first arbitrate before seeking judicial
relief. However, to split the proceedings into
arbitration for Respondent Laperal Realty and
trial for the Respondent Lot Buyers, or to hold
trial in abeyance pending arbitration between
Petitioners and Respondent Laperal Realty,
would in effect result in multiplicity of suits,
duplicitous procedure and unnecessary
delay. On the other hand, it would be in the
interest of justice if the trial court hears the
complaint against all herein Respondents and
adjudicates Petitioners rights as against theirs
in a single and complete proceeding.
Petition is GRANTED. The assailed Order of
RTC of Lipa City is NULLIFIED and SET ASIDE.
RATIO DECIDENDI:
In a catena of cases inspired by Justice
Malcolms provocative dissent in Vega v. San
Carlos Milling Co. [1924], the SC has recognized
arbitration agreements as valid, binding,
enforceable and not contrary to public policy so
much so that when there obtains a written
provision for arbitration which is not complied
with, the trial court should suspend the
proceedings and order the parties to proceed to
arbitration in accordance with the terms of their
agreement. Arbitration is the wave of the future
in dispute resolution. To brush aside a
contractual agreement calling for arbitration in
case of disagreement between parties would be
a step backward.
-
ADR CASE DIGESTS 2015
pg. 4
Page number 4
A submission to arbitration is a contract. As
such, the Agreement, containing the stipulation
on arbitration, binds the parties thereto, as well
as their assigns and heirs. But only
they. Petitioners, as heirs of Salas, Jr., and
Respondent Laperal Realty are certainly bound
by the Agreement. If Respondent Laperal
Realty, had assigned its rights under the
Agreement to a third party, making the former,
the assignor, and the latter, the assignee, such
assignee would also be bound by the arbitration
provision since assignment involves such
transfer of rights as to vest in the assignee the
power to enforce them to the same extent as the
assignor could have enforced them against the
debtor or, in this case, against the heirs of the
original party to the Agreement. However,
Respondent Lot Buyers are NOT assignees of
the rights of Respondent Laperal Realty under
the Agreement to develop Salas, Jr.s land and
sell the same. They are, rather, buyers of the
land that Respondent Laperal Realty was given
the authority to develop and sell under the
Agreement. As such, they are NOT assigns
contemplated in Art. 1311 of the New Civil Code
which provides that contracts take effect only
between the parties, their assigns and heirs.
In the same vein, Petitioners contention that
rescission, being their cause of action, falls
under the exception clause in Sec. 2 of Republic
Act No. 876 is without merit. For while
rescission, as a general rule, is an arbitrable
issue, they impleaded in the suit for rescission
the Respondent Lot Buyers who are neither
parties to the Agreement nor the latters assigns
or heirs. Consequently, the right to arbitrate as
provided in Article VI of the Agreement was
never vested in Respondent Lot Buyers.
Tuna Processing Inc v Phil. Kingford Inc.
May a foreign corporation not licensed to do
business in the Philippines, but which collects
royalties from entities in the Philippines, sue
here to enforce a foreign arbitral award?
G.R. No. 185582 (February 29, 2012)
PEREZ, J.:
FACTS:
Kanemitsu Yamaoka, co-patentee of a US
Patent, Philippine Letters Patent, and an
Indonesian Patent, entered into a Memorandum
of Agreement (MOA) with five Philippine tuna
processors including Respondent Philippine
Kingford, Inc. (KINGFORD). The MOA provides
for the enforcing of the abovementioned patents,
granting licenses under the same, and collecting
royalties, and for the establishment of herein
Petitioner Tuna Processors, Inc. (TPI).
-
ADR CASE DIGESTS 2015
pg. 5
Page number 5
Due to a series of events not mentioned in the
Petition, the tuna processors, including
Respondent KINGFORD, withdrew from
Petitioner TPI and correspondingly reneged on
their obligations. Petitioner TPI submitted the
dispute for arbitration before the International
Centre for Dispute Resolution in the State of
California, United States and won the case
against Respondent KINGFORD.
To enforce the award, Petitioner TPI filed
a Petition for Confirmation, Recognition, and
Enforcement of Foreign Arbitral Award before
the RTC of Makati City. Respondent KINGFORD
filed a Motion to Dismiss, which the RTC denied
for lack of merit. Respondent KINGFORD then
sought for the inhibition of the RTC judge, Judge
Alameda, and moved for the reconsideration of
the order denying the Motion. Judge Alameda
inhibited himself notwithstanding [t]he
unfounded allegations and unsubstantiated
assertions in the motion. Judge Ruiz, to which
the case was re-raffled, in turn, granted
Respondent KINGFORDSs Motion for
Reconsideration and dismissed the Petition on
the ground that Petitioner TPI lacked legal
capacity to sue in the Philippines. Petitioner TPI
is a corporation established in the State of
California and not licensed to do business in the
Philippines.
Hence, the present Petition for Review on
Certiorari under Rule 45.
ISSUE:
Whether or not a foreign corporation not
licensed to do business in the Philippines, but
which collects royalties from entities in the
Philippines, sue here to enforce a foreign arbitral
award?
ARGUMENT:
Petitioner TPI contends that it is entitled to seek
for the recognition and enforcement of the
subject foreign arbitral award in accordance
with RA No. 9285 (Alternative Dispute
Resolution Act of 2004), the Convention on the
Recognition and Enforcement of Foreign Arbitral
Awards drafted during the United Nations
Conference on International Commercial
Arbitration in 1958 (New York Convention), and
the UNCITRAL Model Law on International
Commercial Arbitration (Model Law), as none of
these specifically requires that the party seeking
for the enforcement should have legal capacity
to sue.
RULING:
YES. Petitioner TPI, although not licensed to do
business in the Philippines, may seek
recognition and enforcement of the foreign
arbitral award in accordance with the provisions
of the Alternative Dispute Resolution Act of
2004. A foreign corporations capacity to sue in
the Philippines is not material insofar as the
recognition and enforcement of a foreign arbitral
award is concerned.
-
ADR CASE DIGESTS 2015
pg. 6
Page number 6
The Resolution of the RTC is REVERSED and
SET ASIDE.
RATIO DECIDENDI:
Sec. 45 of the Alternative Dispute Resolution Act
of 2004 provides that the opposing party in an
application for recognition and enforcement of
the arbitral award may raise only those grounds
that were enumerated under Article V of
the New York Convention, to wit:
Article V
1. Recognition and enforcement of the award
may be refused, at the request of the party
against whom it is invoked, only if that party
furnishes to the competent authority where the
recognition and enforcement is sought, proof
that:
a. The parties to the agreement referred to in
Article II were, under the law applicable to them,
under some incapacity, or the said agreement is
not valid under the law to which the parties have
subjected it or, failing any indication thereon,
under the law of the country where the award
was made;
b. The party against whom the award is invoked
was not given proper notice of the appointment
of the arbitrator or of the arbitration proceedings
or was otherwise unable to present his case;
c. The award deals with a difference not
contemplated by or not falling within the terms of
the submission to arbitration, or it contains
decisions on matters beyond the scope of the
submission to arbitration, provided that, if the
decisions on matters submitted to arbitration can
be separated from those not so submitted, that
part of the award which contains decisions on
matters submitted to arbitration may be
recognized and enforced;
d. The composition of the arbitral authority or the
arbitral procedure was not in accordance with
the agreement of the parties, or, failing such
agreement, was not in accordance with the law
of the country where the arbitration took place;
or
e. The award has not yet become binding on the
parties, or has been set aside or suspended by
a competent authority of the country in which, or
under the law of which, that award was made.
2. Recognition and enforcement of an arbitral
award may also be refused if the competent
authority in the country where recognition and
enforcement is sought finds that:
a. The subject matter of the difference is not
capable of settlement by arbitration under the
law of that country; or
-
ADR CASE DIGESTS 2015
pg. 7
Page number 7
b. The recognition or enforcement of the award
would be contrary to the public policy of that
country.
Not one of the abovementioned exclusive
grounds touched on the capacity to sue of the
party seeking the recognition and enforcement
of the award.
Pertinent provisions of the Special Rules of
Court on Alternative Dispute Resolution, which
was promulgated by the Supreme Court,
likewise support this position.
Rule 13.1 of the Special Rules provides that
[a]ny party to a foreign arbitration may petition
the court to recognize and enforce a foreign
arbitral award. The contents of such petition
are enumerated in Rule 13.5. Capacity to sue is
not included. Oppositely, in the rule on local
arbitral awards or arbitrations in instances where
the place of arbitration is in the Philippines, it is
specifically required that a petition to determine
any question concerning the existence, validity
and enforceability of such arbitration agreement
available to the parties before the
commencement of arbitration and/or a petition
for judicial relief from the ruling of the arbitral
tribunal on a preliminary question upholding or
declining its jurisdiction after arbitration has
already commenced should state [t]he facts
showing that the persons named as petitioner or
respondent have legal capacity to sue or be
sued.
Indeed, it is in the best interest of justice that
in the enforcement of a foreign arbitral award,
the Court deny availment
by the losing party of the rule that bars
foreign corporations not licensed to do business
in the Philippines from maintaining a suit in
Philippine courts. When a party enters
into a contract containing a foreign arbitratio
n clause and, as in this case, in fact submits
itself to arbitration, it becomes bound by the
contract, by the arbitration and by the result of
arbitration, conceding thereby the capacity of
the other party to enter into the contract,
participate in the arbitration and cause the
implementation of the result. Although not on all
fours with the instant case, also worthy to
consider is the wisdom of then Associate Justice
Flerida Ruth P. Romero in her Dissenting
Opinion in Asset Privatization Trust v. Court of
Appeals [1998], to wit:
xxx Arbitration, as an alternative mode of
settlement, is gaining adherents in legal and
judicial circles here and abroad. If its tested
mechanism can simply be ignored by an
aggrieved party, one who, it must be stressed,
voluntarily and actively participated in the
arbitration proceedings from the very beginning,
it will destroy the very essence of mutuality
inherent in consensual contracts.
Clearly, on the matter of capacity to sue, a
foreign arbitral award should be respected not
because it is favored over domestic laws and
procedures, but because Republic Act No.
9285 has certainly erased any conflict of law
question.
-
ADR CASE DIGESTS 2015
pg. 8
Page number 8
Finally, even assuming, only for the sake of
argument, that the RTC correctly observed that
theModel Law, not the New York Convention,
governs the subject arbitral award, Petitioner
TPI may still seek recognition and enforcement
of the award in Philippine court, since the Model
Law prescribes substantially identical exclusive
grounds for refusing recognition or enforcement.
Koppel Inc. v Makati Rotary Club Foundation
Inc.
Will the disagreement between parties to a
contract be rendered non-arbitrable if, in the
arbitration thereof, the validity of the contract
itself will have to be determined?
May a party to a contract invoke the arbitration
clause thereof and, at the same time, impugn
the validity of the contract itself?
Is it necessary for a party seeking arbitration to
first file a request or an application therefor
with the court to render an arbitration clause
operational?
If parties to a contract already underwent
Judicial Dispute Resolution (JDR) proceedings
before the court, may they still refer their dispute
to arbitration?
G.R. No. 198075 (September 04, 2013)
PEREZ, J.:
FACTS:
In 1975, Fedders Koppel, Incorporated (FKI)
bequeathed a parcel of land exclusive of
improvements thereon in favor of Respondent
Makati Rotary Club Foundation, Inc. by way of
aconditional donation. Respondent accepted the
donation with all of its conditions. On 26 May
1975, FKI and the Respondent executed a Deed
of Donation evidencing their consensus.
-
ADR CASE DIGESTS 2015
pg. 9
Page number 9
One of the conditions of the donation required
the Respondent to lease the subject land back
to FKI under terms specified in their Deed of
Donation. With the Respondents acceptance of
the donation, a lease agreement between them
was, therefore, effectively incorporated in
the Deed of Donation.
Pertinent terms of such lease agreement, as
provided in the Deed of Donation, were as
follows:
1. The period of the lease is for twenty-five (25)
years, or until the 25th of May 2000;
2. The amount of rent to be paid by FKI for the
first twenty-five (25) years is P40,126.00
perannum.
The Deed of Donation also stipulated that the
lease over the subject property is renewable for
another period of twenty-five (25) years upon
mutual agreement of FKI and the Respondent.
In which case, the amount of rent shall be
determined in accordance with item 2(g) of
the Deed of Donation.
In October 1976, FKI and the Respondent
executed an Amended Deed of Donation that
reiterated the provisions of the Deed of
Donation, including those relating to the lease of
the subject land.
Verily, by virtue of the lease agreement
contained in the Deed of
Donation and Amended Deed of Donation, FKI
was able to continue in its possession and use
of the subject land.
Two (2) days before the lease incorporated in
the Deed of Donation and Amended Deed of
Donation was set to expire, or on 23 May 2000,
FKI and Respondent executed another contract
of lease (2000 Lease Contract) covering the
subject land. In this 2000 Lease Contract, FKI
and Respondent agreed on a new five-year
lease to take effect on the 26th of May 2000, with
annual rents ranging from P4M for the first year
up to P4.9M for the fifth year.
The 2000 Lease Contract also contained an
arbitration clause enforceable in the event the
parties come to disagreement about the
interpretation, application and execution of the
lease.
After the 2000 Lease Contract expired, FKI and
Respondent agreed to renew their lease for
another five (5) years. This new lease (2005
Lease Contract) required FKI to pay a fixed
annual rent of P4.2M.In addition to paying the
fixed rent, however, the 2005 Lease
Contract also obligated FKI to make a yearly
donation of money to the Respondent. Such
donations ranged from P3M for the first year up
to P3.9M for the fifth year.
-
ADR CASE DIGESTS 2015
pg. 10
Page number 10
Notably, the 2005 Lease Contract contained an
arbitration clause similar to that in the 2000
Lease Contract, to wit:
19. Governing Law The provisions of this
[2005 Lease Contract] shall be governed,
interpreted and construed in all aspects in
accordance with the laws of the Republic of the
Philippines.
Any disagreement as to the interpretation,
application or execution of this [2005 Lease
Contract] shall be submitted to a board of three
(3) arbitrators constituted in accordance with the
arbitration law of the Philippines. The decision of
the majority of the arbitrators shall be binding
upon [FKI and Respondent]. (Emphasis
supplied)
From 2005 to 2008, FKI faithfully paid the
rentals and donations due it per the 2005
Lease Contract. But in June of 2008, FKI sold all
its rights and properties relative to its business in
favor of herein Petitioner Koppel, Incorporated.
On 29 August 2008, FKI and Petitioner executed
an Assignment and Assumption of Lease and
Donationwherein FKI, with the conformity of
the Respondent, formally assigned all of its
interests and obligations under the Amended
Deed of Donation and the 2005 Lease
Contract in favor of Petitioner.
The following year, Petitioner discontinued the
payment of the rent and donation under the
2005Lease Contract.
Petitioners refusal to pay such rent and
donation emanated from its belief that the
rental stipulations of the 2005 Lease Contract,
and even of the 2000 Lease Contract, cannot be
given effect because they violated one of the
material conditions of the donation of the
subject land, as stated in the Deed of
Donation and Amended Deed of Donation.
According to Petitioner, the Deed of
Donation and Amended Deed of
Donation actually established not only one but
two (2) lease agreements between FKI and
Respondent, i.e., one lease for the first twenty-
five (25) years or from 1975 to 2000, and
another lease for the next twenty-five (25) years
thereafter or from 2000 to 2025. Both leases are
material conditions of the donation of the subject
land.
Petitioner points out that while a definite amount
of rent for the second twenty-five (25) year lease
was not fixed in the Deed of
Donation and Amended Deed of Donation, both
deeds nevertheless prescribed rules and
limitations by which the same may be
determined. Such rules and limitations ought to
be observed in any succeeding lease
agreements between Petitioner and Respondent
for they are, in themselves, material conditions
of the donation of the subject land.
-
ADR CASE DIGESTS 2015
pg. 11
Page number 11
In this connection, Petitioner cites item 2(g) of
the Deed of Donation and Amended Deed of
Donation that supposedly limits the amount of
rent for the lease over the second twenty-five
(25) years to only three percent (3%) of the fair
market value of the [subject] land excluding the
improvements.
For Petitioner then, the rental stipulations of both
the 2000 Lease Contract and 2005 Lease
Contract cannot be enforced as they are clearly,
in view of their exorbitant exactions, in violation
of the aforementioned threshold in item 2(g) of
the Deed of Donation and Amended Deed of
Donation. Consequently, Petitioner insists that
the amount of rent it has to pay thereon is and
must still be governed by the limitations
prescribed in the Deed of
Donation and Amended Deed of Donation.
Respondent then sent Demand Letters to
Petitioners notifying the latter of its default,
demanding for the settlement of the rent and
donations due for the year 2009. Respondent
intimated of cancelling the 2005 Lease
Contract should Petitioner fail to settle the said
obligations. In its last sent Demand Letter,
Respondent demand Petitioner to immediately
vacate the leased premises should it fail to pay
such obligations within seven (7) days from its
receipt of the letter.
Petitioner refused to comply with the demands
of the Respondent. Instead, on 30 September
2009, Petitioner filed with the RTC of Paraaque
City a Complaint for the Rescission or
Cancellation of the Deed of
Donation and Amended Deed of
Donation against the Respondent.
On 5 October 2009, Respondent filed
an Unlawful Detainer case against the Petitioner
before the MeTC of Paraaque City.
On 4 November 2009, Petitioner filed an Answer
with Compulsory Counterclaim.In it, Petitioner
reiterated its objection over the rental
stipulations of the 2005 Lease Contract for being
violative of the material conditions of the Deed of
Donation and Amended Deed of Donation.
On 27 April 2010, the MeTC rendered judgment
in favor of the Petitioner. While the MeTC
refused to dismiss the action on the ground that
the dispute is subject to arbitration, it
nonetheless sided with the Petitioner with
respect to the issues regarding the insufficiency
of the Respondents demand and the nullity of
the 2005 Lease Contract.
The Respondent appealed to the RTC which
reversed the MeTCs decision.
Aggrieved, the Petitioner appealed to the CA
which affirmed the decision of the RTC.
Hence, the present Petition for Review on
Certiorari under Rule 45.
-
ADR CASE DIGESTS 2015
pg. 12
Page number 12
ISSUE:
Whether or not the present dispute is arbitrable
under the Arbitration Clause of the 2005 Lease
Agreement Contract?
ARGUMENTS:
At different points in the proceedings of this
case, the following arguments were offered
against the application of the arbitration clause
of the 2005 Lease Contract:
1. The disagreement between the
Petitioner and Respondent is non-
arbitrable as it will inevitably touch upon
the issue of the validity of the 2005
Lease Contract. It was submitted that
one of the reasons offered by the
Petitioner in justifying its failure to pay
under the 2005 Lease Contract was the
nullity of such contract for being contrary
to law and public policy. The Supreme
Court, in Gonzales v. Climax Mining,
Ltd. [2005], held that the validity of
contract cannot be subject of arbitration
proceedings as such questions are
legal in nature and require the
application and interpretation of laws
and jurisprudence which is necessarily a
judicial function.
2. The Petitioner cannot validly invoke the
arbitration clause of the 2005 Lease
Contract while, at the same time,
impugn such contracts validity.
3. Even assuming that it can invoke the
arbitration clause whilst denying the
validity of the2005 Lease Contract,
Petitioner still did not file a formal
application before the MeTC so as to
render such arbitration clause
operational. Section 24 of Republic Act
No. 9285 requires the party seeking
arbitration to first file a request or an
application therefor with the court not
later than the preliminary conference.
4. Petitioner and Respondent already
underwent JDR proceedings before the
RTC. Hence, a further referral of the
dispute to arbitration would only be
circuitous. Moreover, an ejectment case,
in view of its summary nature, already
fulfills the prime purpose of
arbitration, i.e., to provide parties in
conflict with an expedient method for the
resolution of their dispute. Arbitration
then would no longer be necessary in
this case.
RULING:YES. None of the above-
mentioned arguments have any merit.
The MeTC, RTC and CA all erred in
overlooking the significance of the
arbitration clause incorporated in
the 2005 Lease Contract. As the SC
sees it, that is a fatal mistake.Hence, the
-
ADR CASE DIGESTS 2015
pg. 13
Page number 13
Petition is GRANTED and thus referring
the Petitioner and the Respondent to
arbitration pursuant to the arbitration
clause of the 2005 Lease Contract,
repeatedly included in the 2000 Lease
Contract and in the 1976
Amended Deed of Donation.
RATIO DECIDENDI:
The arbitration clause of the 2005 Lease
Contract stipulates that any disagreement as to
the interpretation, application or execution of
the 2005 Lease Contract ought to be submitted
to arbitration. To the mind of the Court, such
stipulation is clear and is comprehensive enough
so as to include virtually any kind of conflict or
dispute that may arise from the 2005 Lease
Contractincluding the one that presently besets
Petitioner and Respondent.
First. The disagreement between the Petitioner
and Respondent falls within the all-
encompassing terms of the arbitration clause of
the 2005 Lease Contract. While it may be
conceded that in the arbitration of such
disagreement, the validity of the 2005 Lease
Contract, or at least, of such contracts rental
stipulations would have to be determined, the
same would not render such disagreement non-
arbitrable. The quotation from Gonzales case
that was used to justify the contrary position was
taken out of context.
The pivotal issue that confronted the Court in
the Gonzales case was whether the complaint
for arbitration raises arbitrable issues that the
Panel of Arbitrators of the Mines and
Geosciences Bureau (PA-MGB) can take
cognizance of.
-
ADR CASE DIGESTS 2015
pg. 14
Page number 14
Gonzales decided the issue in the negative. In
holding that the PA-MGB was devoid of any
jurisdiction to take cognizance of the complaint
for arbitration, this Court pointed out to the
provisions of R.A. No. 7942, or the Mining Act of
1995, which granted the PA-MGB with exclusive
original jurisdiction only over mining disputes,
i.e., disputes involving rights to mining areas,
mineral agreements or permits, and surface
owners, occupants, claimholders or
concessionaires requiring the technical
knowledge and experience of mining authorities
in order to be resolved. Accordingly, since the
complaint for arbitration in Gonzales did not
raise mining disputes as contemplated under
R.A. No. 7942 but only issues relating to the
validity of certain mining related agreements, SC
held that such complaint could not be arbitrated
before the PA-MGB. It is in this context that SC
made the pronouncement now in
discussion.Arbitration before the Panel of
Arbitrators is proper only when there is a
disagreement between the parties as to some
provisions of the contract between them, which
needs the interpretation and the application of
that particular knowledge and expertise
possessed by members of that Panel. It is not
proper when one of the parties repudiates the
existence or validity of such contract or
agreement on the ground of fraud or oppression
as in this case. The validity of the contract
cannot be subject of arbitration
proceedings. Allegations of fraud and duress in
the execution of a contract are matters within the
jurisdiction of the ordinary courts of law. These
questions are legal in nature and require the
application and interpretation of laws and
jurisprudence which is necessarily a judicial
function. (Emphasis supplied)
-
ADR CASE DIGESTS 2015
pg. 15
Page number 15
SC in Gonzales did not simply base its rejection
of the complaint for arbitration on the ground
that the issue raised therein, i.e., the validity of
contracts, is per se non-arbitrable. The real
consideration behind the ruling was the limitation
that was placed by R.A. No. 7942 upon the
jurisdiction of the PA-MGB as an arbitral
body. Gonzales rejected the complaint for
arbitration because the issue raised therein is
not a mining dispute per R.A. No. 7942 and it is
for this reason, and only for this reason, that
such issue is rendered non-arbitrable before the
PA-MGB. As stated beforehand, R.A. No. 7942
clearly limited the jurisdiction of the PA-MGB
only tomining disputes.Much more instructive for
our purposes, on the other hand, is the recent
case of Cargill Philippines, Inc. v. San Fernando
Regal Trading, Inc [2011]. In Cargill, SC
answered the question of whether issues
involving the rescission of a contract are
arbitrable. The respondent in Cargill argued
against arbitrability, also citing therein Gonzales.
After dissecting Gonzales, SC ruled in favor of
arbitrability. Thus, SC held:Respondent
contends that assuming that the existence of the
contract and the arbitration clause is conceded,
the CAs decision declining referral of the
parties dispute to arbitration is still correct. It
claims that its complaint in the RTC presents the
issue of whether under the facts alleged, it is
entitled to rescind the contract with damages;
and that issue constitutes a judicial question or
one that requires the exercise of judicial function
and cannot be the subject of an arbitration
proceeding. Respondent cites our ruling in
Gonzales, wherein we held that a panel of
arbitrator is bereft of jurisdiction over the
complaint for declaration of nullity/or termination
of the subject contracts on the grounds of fraud
and oppression attendant to the execution of the
addendum contract and the other contracts
emanating from it, and that the complaint should
have been filed with the regular courts as it
involved issues which are judicial in nature.
Such argument is misplaced and respondent
cannot rely on the Gonzales case to support its
argument. (Emphasis ours)
Second. Petitioner may still invoke the
arbitration clause of the 2005 Lease
Contractnotwithstanding the fact that it assails
the validity of such contract. This is due to
the doctrine of separability.
Under the doctrine of separability, an arbitration
agreement is considered as independent of the
main contract. Being a separate contract in
itself, the arbitration agreement may thus be
invoked regardless of the possible nullity or
invalidity of the main contract.
Once again instructive is Cargill, wherein SC
held that, as a further consequence of the
doctrine of separability, even the very party who
repudiates the main contract may invoke its
arbitration clause.
-
ADR CASE DIGESTS 2015
pg. 16
Page number 16
Third. The operation of the arbitration clause in
this case is not at all defeated by the failure of
the Petitioner to file a formal request or
application therefor with the MeTC. SC finds that
the filing of a request pursuant to Section 24
of R.A. No. 9285 is not the sole means by which
an arbitration clause may be validly invoked in a
pending suit.
Section 24 of R.A. No. 9285 reads:
SEC. 24. Referral to Arbitration. A court before
which an action is brought in a matter which is
the subject matter of an arbitration agreement
shall, if at least one party so requestsnot later
that the pre-trial conference, or upon the request
of both parties thereafter, refer the parties to
arbitration unless it finds that the arbitration
agreement is null and void, inoperative or
incapable of being performed. [Emphasis ours;
italics original]
The request referred to in the above provision
is, in turn, implemented by Rules 4.1 to 4.3
ofA.M. No. 07-11-08-SC or the Special Rules of
Court on Alternative Dispute Resolution (Special
ADR Rules):
RULE 4: REFERRAL TO ADR
Rule 4.1. Who makes the request. A party to a
pending action filed in violation of the arbitration
agreement, whether contained in an arbitration
clause or in a submission
agreement, may request the court to refer the
parties to arbitration in accordance with such
agreement.
Rule 4.2. When to make request. (A) Where
the arbitration agreement exists before the
action is filed. The request for referral shall be
made not later than the pre-trial conference.
After the pre-trial conference, the court will only
act upon the request for referral if it is made with
the agreement of all parties to the case.
(B) Submission agreement. If there is no
existing arbitration agreement at the time the
case is filed but the parties subsequently enter
into an arbitration agreement, they may request
the court to refer their dispute to arbitration at
any time during the proceedings.
Rule 4.3. Contents of request. The request for
referral shall be in the form of a motion, which
shall state that the dispute is covered by an
arbitration agreement.
Apart from other submissions, the movant shall
attach to his motion an authentic copy of the
arbitration agreement.
The request shall contain a notice of hearing
addressed to all parties specifying the date and
time when it would be heard. The party making
the request shall serve it upon the respondent to
give him the opportunity to file a comment or
opposition as provided in the immediately
succeeding Rule before the hearing. [Emphasis
ours; italics original]
-
ADR CASE DIGESTS 2015
pg. 17
Page number 17
Attention must be paid, however, to the salient
wordings of Rule 4.1. It reads: [a] party to a
pending action filed in violation of the arbitration
agreement x x x may request the court to refer
the parties to arbitration in accordance with such
agreement.
In using the word may to qualify the act of filing
a request under Section 24 of R.A. No. 9285,
the Special ADR Rules clearly did not intend to
limit the invocation of an arbitration agreement in
a pending suit solely via such request. After all,
non-compliance with an arbitration agreement is
a valid defense to any offending suit and, as
such, may even be raised in an answer as
provided in our ordinary rules of procedure.
In this case, it is conceded that Petitioner was
not able to file a separate request of arbitration
before the MeTC. However, it is equally
conceded that the Petitioner, as early as in
its Answer with Counterclaim, had already
apprised the MeTC of the existence of the
arbitration clause in the 2005 Lease
Contract and, more significantly, of its desire to
have the same enforced in this case. This act of
Petitioner is enough valid invocation of his right
to arbitrate.
Fourth. The fact that the Petitioner and
Respondent already underwent through JDR
proceedings before the RTC, will not make the
subsequent conduct of arbitration between the
parties unnecessary or circuitous. The JDR
system is substantially different from arbitration
proceedings.
The JDR framework is based on the processes
of mediation, conciliation or early neutral
evaluation which entails the submission of a
dispute before a JDR judge who shall merely
facilitate settlement between the parties in
conflict or make a non-binding evaluation or
assessment of the chances of each partys
case. Thus in JDR, the JDR judge lacks the
authority to render a resolution of the dispute
that is binding upon the parties in conflict. In
arbitration, on the other hand, the dispute is
submitted to an arbitrator/sa neutral third
person or a group of thereofwho shall have
the authority to render a resolution binding upon
the parties.
Clearly, the mere submission of a dispute to
JDR proceedings would not necessarily render
the subsequent conduct of arbitration a mere
surplusage. The failure of the parties in conflict
to reach an amicable settlement before the JDR
may, in fact, be supplemented by their resort to
arbitration where a binding resolution to the
dispute could finally be achieved. This situation
precisely finds application to the case at bench.
Neither would the summary nature of ejectment
cases be a valid reason to disregard the
enforcement of the arbitration clause of the 2005
Lease Contract. Notwithstanding the summary
nature of ejectment cases, arbitration still
remains relevant as it aims not only to afford the
parties an expeditious method of resolving their
dispute.
-
ADR CASE DIGESTS 2015
pg. 18
Page number 18
A pivotal feature of arbitration as an alternative
mode of dispute resolution is that it is, first and
foremost, a product of party autonomy or the
freedom of the parties to make their own
arrangements to resolve their own disputes.
Arbitration agreements manifest not only the
desire of the parties in conflict for an expeditious
resolution of their dispute. They also represent,
if not more so, the parties mutual aspiration to
achieve such resolution outside of judicial
auspices, in a more informal and less
antagonistic environment under the terms of
their choosing. Needless to state, this critical
feature can never be satisfied in an ejectment
case no matter how summary it may be.
Legal Effect of the Application of the Arbitration
Clause
Since there really are no legal impediments to
the application of the arbitration clause of
the 2005 Contract of Lease in this case, We find
that the instant unlawful detainer action was
instituted in violation of such clause. The Law,
therefore, should have governed the fate of the
parties and this suit:
R.A. No. 876
Section 7. Stay of civil action. If any suit or
proceeding be brought upon an issue arising out
of an agreement providing for the arbitration
thereof, the court in which such suit or
proceeding is pending, upon being satisfied that
the issue involved in such suit or proceeding is
referable to arbitration, shall stay the action or
proceeding until an arbitration has been had in
accordance with the terms of the agreement:
Provided, That the applicant for the stay is not in
default in proceeding with such arbitration.
[Emphasis supplied]
R.A. No. 9285
Section 24. Referral to Arbitration. A court
before which an action is brought in a matter
which is the subject matter of an arbitration
agreement shall, if at least one party so requests
not later that the pre-trial conference, or upon
the request of both parties thereafter, refer the
parties to arbitration unless it finds that the
arbitration agreement is null and void,
inoperative or incapable of being performed.
[Emphasis supplied]
It is clear that under the law, the instant unlawful
detainer action should have been stayed; the
Petitioner and the Respondent should have
been referred to arbitration pursuant to the
arbitration clause of the 2005 Lease Contract.
The MeTC, however, did not do so in violation of
the lawwhich violation was, in turn, affirmed by
the RTC and Court of Appeals on appeal.
-
ADR CASE DIGESTS 2015
pg. 19
Page number 19
The violation by the MeTC of the clear directives
under R.A. Nos. 876 and 9285 renders invalid all
proceedings it undertook in the ejectment
case after the filing by Petitioner of its Answer
with Counterclaimthe point when the
Petitioner and the Respondent should have
been referred to arbitration. This case must,
therefore, be remanded to the MeTC and be
suspended at said point. Inevitably, the
decisions of the MeTC, RTC and the Court of
Appeals must all be vacated and set aside.
The Petitioner and the Respondent must then be
referred to arbitration pursuant to the arbitration
clause of the 2005 Lease Contract.
J Plus Asia Corporation v Utility Assurance
Corporation
Does CA have jurisdiction to review arbitral
awards?
G.R. No. 199650 (June 26, 2013)
VILLARAMA, JR., J.:
FACTS:
Petitioner J Plus Asia Development Corporation
and Martin E. Mabunay entered into
aConstruction Agreement on December 24,
2007 whereby the latter undertook to build the
formers 72-room condominium/hotel located in
Boracay Island.
The project, costing P42M, was to be completed
within one year or 365 days reckoned from the
first calendar day after signing of the Notice of
Award and Notice to Proceed and receipt of
down payment (20% of contract price). The
P8.4M down payment was fully paid on January
14, 2008. Payment of the balance of the contract
price will be based on actual work finished within
15 days from receipt of the monthly progress
billings. Per the agreed work schedule, the
completion date of the project was December
2008. Mabunay also submitted the
required Performance Bond issued by
Respondent Utility Assurance Corporation in the
amount equivalent to 20% down payment or
P8.4M.
Mabunay commenced work at the project site on
January 7, 2008. Petitioner paid up to the 7th
monthly progress billing sent by Mabunay. As of
September 16, 2008, Petitioner had paid the
total amount of P15.98M inclusive of the 20%
down payment. However, as of said date,
Mabunay had accomplished only 27.5% of the
project. It was later found out by the joint
inspection and evaluation by the Petitioner and
Mabunay that, as of November 14, 2008, the
project was only 31.39% complete and that the
uncompleted portion was 68.61%.
On November 19, 2008, Petitioner terminated
the contract and sent Demand Letters to
Mabunay and Respondent surety. As its
demands went unheeded, Petitioner filed
a Request for Arbitrationbefore the Construction
Industry Arbitration Commission (CIAC).
-
ADR CASE DIGESTS 2015
pg. 20
Page number 20
In his Answer, Mabunay claimed that the delay
was caused by retrofitting and other revision
works ordered by Petitioner. He asserted that
he actually had until April 30, 2009 to finish the
project since the 365 days period of completion
started only on May 2, 2008 after clearing the
retrofitted old structure. Hence, the termination
of the contract by Petitioner was premature and
the filing of the Complaint against him was
baseless, malicious and in bad faith.
Respondent, on the other hand, filed a Motion to
Dismiss on the ground that Petitioner has no
cause of action and the complaint states no
cause of action against it. The CIAC denied
the Motion to Dismiss.
In its Answer Ex Abundante Ad Cautelam with
Compulsory Counterclaims and Cross-claims,
Respondent argued that the Performance
Bond merely guaranteed the 20% down
payment and not the entire obligation of
Mabunay under the Construction
Agreement. Since the value of the projects
accomplishment already exceeded the said
amount, Respondents obligation under
thePerformance Bond had been fully
extinguished. As to the claim for alleged
overpayment to Mabunay, Respondent
contended that it should not be credited against
the 20% down payment which was already
exhausted and such application by Petitioner is
tantamount to reviving an obligation that had
been legally extinguished by
payment. Respondent also set up a cross-claim
against Mabunay who executed in its favor
an Indemnity Agreement whereby Mabunay
undertook to indemnify Respondent for whatever
amounts it may be adjudged liable to pay
Petitioner under the surety bond.
On February 2, 2010, CIAC rendered its
Decision and made Awards in favor of
Petitioner. CIAC ruled that Mabunay had
incurred delay which entitled Petitioner to the
stipulated liquidated damages and unrecouped
down payment.
Dissatisfied, Respondent filed in the CA
a Petition for Review under Rule 43 of the 1997
Rules of Civil Procedure, as amended, which
reversed the CIACs ruling.
-
ADR CASE DIGESTS 2015
pg. 21
Page number 21
Hence, the present Petition for Review on
Certiorari under Rule 45 seeking to reverse the
CA insofar as it denied its claims under
the Performance Bond and to reinstate in its
entirety the February 2, 2010 CIAC Decision.
ISSUE:
Whether or not the Alternative Dispute
Resolution Act of 2004 and the Special ADR
Rules have stripped the CA of jurisdiction to
review arbitral awards?
ARGUMENT:
Petitioner contends that that with the
institutionalization of alternative dispute
resolution under RA No. 9285, otherwise known
as the Alternative Dispute Resolution Act of
2004, the CA was divested of jurisdiction to
review the decisions or awards of the CIAC.
RULING:
NO. The Petitioners contention is without merit.
Petitioner erroneously relied on the provision
in RA No. 9285 allowing any party to a domestic
arbitration to file in the RTC a petition either to
confirm, correct or vacate a domestic arbitral
award.
The Petition is GRANTED. The assailed
decision of the CA is REVERSED and SET
ASIDE. The Award made in the
Decision rendered by CIAC dated February 2,
2010 is REINSTATED with MODIFICATIONS.
RATIO DECIDENDI:
SC holds that RA No. 9285 did not confer on
RTCs jurisdiction to review awards or decisions
of the CIAC in construction disputes. On the
contrary, Section 40 thereof expressly declares
that confirmation by the RTC is NOT required,
thus:
SEC. 40. Confirmation of Award. The
confirmation of a domestic arbitral award shall
be governed by Section 23 of R.A. 876.
A domestic arbitral award when confirmed shall
be enforced in the same manner as final and
executory decisions of the Regional Trial Court.
The confirmation of a domestic award shall be
made by the regional trial court in accordance
with the Rules of Procedure to be promulgated
by the Supreme Court.
A CIAC arbitral award need not be confirmed by
the regional trial court to be executory as
provided under E.O. No. 1008. (Emphasis
supplied.)
-
ADR CASE DIGESTS 2015
pg. 22
Page number 22
EO No. 1008 vests upon the CIAC original and
exclusive jurisdiction over disputes arising from,
or connected with, contracts entered into by
parties involved in construction in the
Philippines, whether the dispute arises before or
after the completion of the contract, or after the
abandonment or breach thereof. By express
provision of Section 19 thereof, the arbitral
award of the CIAC is final and unappealable,
except on questions of law, which are
appealable to the Supreme Court. With the
amendments introduced by RA No. 7902 and
promulgation of the 1997 Rules of Civil
Procedure, as amended, the CIAC was included
in the enumeration of quasi- judicial agencies
whose decisions or awards may be appealed to
the CA in a Petition for Review under Rule
43. Such review of the CIAC award may
involve either questions of fact, of law, or of fact
and law.Petitioner misread the provisions
of A.M. No. 07-11-08-SC (Special ADR Rules)
promulgated by the SC and which took effect on
October 30, 2009. Since RA No. 9285 explicitly
excluded CIAC awards from domestic arbitration
awards that need to be confirmed to be
executory, said awards are therefore not
covered by Rule 11 of the Special ADR Rules,
as they continue to be governed byEO No.
1008, as amended and the rules of procedure of
the CIAC. The CIAC Revised Rules of
Procedure Governing Construction
Arbitration provide for the manner and mode of
appeal from CIAC decisions or awards in
Section 18 thereof, which reads:
SECTION 18.2 Petition for review. A petition
for review from a final award may be taken by
any of the parties within fifteen (15) days from
receipt thereof in accordance with the provisions
of Rule 43 of the Rules of Court.
NIA V CA
Does the Construction Industry Arbitration
Commission (CIAC) have jurisdiction over
construction contracts entered into between
parties before the creation of said Commission
in 1985?
When a construction contract contains an
arbitration clause, is it still necessary for the
parties thereto to agree to submit disputes
arising therefrom specifically to the CIAC for the
latter to acquire jurisdiction?
G.R. No. 129169 (November 17, 1999)
DAVIDE, JR., C.J.:
FACTS:
In a competitive bidding held by Petitioner NIA,
Hydro Resources Contractors Corporation
(HYDRO) was awarded Contract for the
construction of the main civil works of the Magat
River Multi-Purpose Project. The contract
provided that Respondent HYDRO would be
paid partly in Philippine pesos and partly in U.S.
dollars. Respondent HYDRO substantially
completed the works under the contract in 1982
and final acceptance by Petitioner NIA was
made in 1984. Respondent HYDRO thereafter
determined that it still had an account receivable
from Petitioner NIA representing the dollar rate
differential of the price escalation for the
contract.
-
ADR CASE DIGESTS 2015
pg. 23
Page number 23
After unsuccessfully pursuing its case with
Petitioner NIA, Respondent HYDRO filed with
the CIAC a Request for Adjudication of the
aforesaid claim. Petitioner NIA filed
its Answer wherein it questioned the jurisdiction
of the CIAC alleging lack of cause of action,
laches and estoppel in view of Respondent
HYDROs alleged failure to avail of its right to
submit the dispute to arbitration within the
prescribed period as provided in the contract.
Later, Petitioner NIA filed a Motion to
Dismiss alleging lack of jurisdiction over the
disputes.
The arbitral body constituted by both parties
issued an order which deferred the
determination of the Motion to Dismiss and
resolved to proceed with the hearing of the case
on the merits as the grounds cited by Petitioner
NIA did not seem to be indubitable. Petitioner
NIA filed a Motion for Reconsideration of the
aforesaid Order. CIAC in denying the Motion for
Reconsideration ruled that it has jurisdiction over
the Respondent HYDROs claim over Petitioner
NIA pursuant to E.O 1008 and that the hearing
should proceed as scheduled. CIAC then
rendered a decision in the main case in favor of
Respondent HYDRO.
Petitioner NIA filed with the CA an Original
Action of Certiorari and Prohibition with prayer
for Restraining Order and/or Injunction which
dismissed the same.
Hence, the present Petition for Certiorari and
Prohibition with urgent prayer for Temporary
Restraining Order and Writ of Preliminary
Injunction.
ISSUE:
Whether or not CIAC has jurisdiction to hear and
try the dispute between the parties?
ARGUMENTS:
Petitioner NIA alleged that CIAC has no
jurisdiction to hear and try the dispute between
the parties as EO No. 1008 had no retroactive
effect. It contended that there was no agreement
with Respondent HYDRO to submit the dispute
to CIAC for arbitration considering that the
construction contract was executed in 1978 and
the project completed in 1982, whereas the
Construction Industry Arbitration Law creating
CIAC was signed only in 1985; and that while
they have agreed to arbitration as a mode of
settlement of disputes, they could not have
contemplated submission of their disputes to
CIAC. Petitioner NIA further argued that records
show that it had not voluntarily submitted itself to
arbitration by CIAC. Petitioner NIA contended
that the CIAC did not acquire jurisdiction over
the dispute since it was only Respondent
HYDRO that requested for arbitration. It asserts
that to acquire jurisdiction over a case, as
provided under E.O. 1008, the request for
arbitration filed with CIAC should be made by
both parties, and hence the request by one party
is not enough.
RULING:YES. Contrary to the claim of Petitioner
NIA, the CIAC has jurisdiction over the
controversy.
-
ADR CASE DIGESTS 2015
pg. 24
Page number 24
The instant Petition is DISMISSED for lack of
merit.
RATIO DECIDENDI:
EO No. 1008, otherwise known as the
Construction Industry Arbitration Law which
was promulgated on 4 February 1985, vests
upon CIAC original and exclusive jurisdiction
over disputes arising from, or connected with
contracts entered into by parties involved in
construction in the Philippines, whether the
dispute arises before or after the completion of
the contract, or after the abandonment or breach
thereof. The disputes may involve government
or private contracts. For the Board to acquire
jurisdiction, the parties to a dispute must agree
to submit the same to voluntary arbitration.
The complaint of Respondent HYDRO against
Petitioner NIA on the basis of the contract
executed between them was filed on 7
December 1994, during the effectivity of E.O.
No. 1008. Hence, it is well within the jurisdiction
of CIAC. The jurisdiction of a court is determined
by the law in force at the time of the
commencement of the action. Petitioner NIAs
argument that CIAC had no jurisdiction to
arbitrate on contract which preceded its
existence is untenable. E.O. 1008 is clear that
the CIAC has jurisdiction over all disputes
arising from or connected with construction
contract whether the dispute arises BEFORE or
AFTER the completion of the contract. Thus, the
date the parties entered into a contract and the
date of completion of the same, even if these
occurred before the constitution of the CIAC, did
not automatically divest the CIAC of jurisdiction
as long as the dispute submitted for arbitration
arose after the constitution of the CIAC. Stated
differently, the jurisdiction of CIAC is over the
dispute, not the contract; and the instant dispute
having arisen when CIAC was already
constituted, the arbitral board was actually
exercising current, not retroactive, jurisdiction.
It is undisputed that the contracts between
Respondent HYDRO and Petitioner NIA
contained anarbitration clause wherein they
agreed to submit to arbitration any dispute
between them that may arise before or after the
termination of the agreement. Consequently, the
claim of Respondent HYDRO having arisen from
the contract is arbitrable. Petitioner NIAs
reliance with the ruling on the case of Tesco
Services Incorporated v. Vera, is misplaced.
-
ADR CASE DIGESTS 2015
pg. 25
Page number 25
The 1988 CIAC Rules of Procedure which were
applied by this Court in the Tesco case had
been duly amended by CIAC Resolutions No. 2-
91 and 3-93, Section 1 of Article III of which read
as follows:
Submission to CIAC Jurisdiction An
arbitration clause in a construction contract or a
submission to arbitration of a construction
contract or a submission to arbitration of a
construction dispute shall be deemed an
agreement to submit an existing or future
controversy to CIAC jurisdiction, notwithstanding
the reference to a different arbitration institution
or arbitral body in such contract or submission.
When a contract contains a clause for the
submission of a future controversy to arbitration,
it is not necessary for the parties to enter into a
submission agreement before the claimant may
invoke the jurisdiction of CIAC.
Under the present Rules of Procedure, for a
particular construction contract to fall within the
jurisdiction of CIAC, it is merely required that the
parties agree to submit the same to voluntary
arbitration. Unlike in the original version of
Section 1, as applied in the Tesco case, the law
as it now stands does not provide that the
parties should agree to submit disputes arising
from their agreement specifically to the CIAC for
the latter to acquire jurisdiction over the same.
Rather, it is plain and clear that as long as the
parties agree to submit to voluntary arbitration,
regardless of what forum they may choose, their
agreement will fall within the jurisdiction of the
CIAC, such that, even if they specifically choose
another forum, the parties will not be precluded
from electing to submit their dispute before the
CIAC because this right has been vested upon
each party by law, i.e., E.O. No. 1008.
Moreover, it is undeniable that Petitioner NIA
agreed to submit the dispute for arbitration to the
CIAC. Petitioner NIA through its counsel actively
participated in the arbitration proceedings by
filing an Answer with Counterclaim, as well as its
compliance wherein it nominated arbitrators to
the proposed panel, participating in the
deliberations on, and the formulation of, the
Terms of Reference of the arbitration
proceeding, and examining the documents
submitted by Respondent HYDRO after
Petitioner NIA asked for the originals of the said
documents.
-
ADR CASE DIGESTS 2015
pg. 26
Page number 26
LM POWER ENGINEERING CORP V CAPITOL
INDUSTRIAL
Is there a need to file first a Formal Request for
Arbitration with the Construction Industry
Arbitration Commission (CIAC) in order to vest it
with jurisdiction to decide a construction
dispute?
G.R. No. 141833 (March 26, 2003)
PANGANIBAN, J.:
FACTS:
Petitioner and Respondent entered into a
Subcontract Agreement involving electrical
work at the Third Port of Zamboanga. Two years
thereafter, Respondent took over some of the
work contracted to Petitioner. Allegedly, the
latter had failed to finish it because of its inability
to procure materials.
Upon completing its task under the Contract,
Petitioner billed Respondent in the amount of
P6.7M. Respondent, however, refused to pay
and contested the accuracy of the amount of
advances and billable accomplishments listed by
Petitioner. Respondent also took refuge in the
termination clause of the Agreement. That
clause allowed it to set off the cost of the work
that Petitioner had failed to undertake due to
termination or take-over against the amount it
owed the latter.
Because of the dispute, Petitioner filed with the
RTC of Makati a Complaint for Collection of the
amount representing the alleged balance due it
under the Subcontract. Instead of submitting
anAnswer, Respondent filed a Motion to
Dismiss, alleging that the Complaint was
premature because there was no prior recourse
to arbitration.
RTC denied the Motion to Dismiss on the
ground that the dispute did not involve the
interpretation or the implementation of the
Agreement and was, therefore, not covered by
the arbitral clause. The RTC ruled that the take-
over of some work items by Respondent was not
equivalent to a termination, but a mere
modification, of the Subcontract. The latter was
ordered to give full payment for the work
completed by Petitioner.
On appeal, the CA reversed the RTC and
ordered the referral of the case to arbitration.
The CA held as arbitrable the issue of whether
Respondents take-over of some work items had
been intended to be a termination of the original
contract under Letter K of the Subcontract.
Hence, this Petition for Review on
Certiorari under Rule 45.
ISSUES:
1. Whether or not there exists a
controversy/dispute between Petitioner
and Respondent regarding the
interpretation and implementation of the
Subcontract Agreement that requires
prior recourse to voluntary arbitration?;
2. In the affirmative, whether or not there is
a need to file a request first with the
CIAC in order to vest it with jurisdiction
to decide a construction dispute?
-
ADR CASE DIGESTS 2015
pg. 27
Page number 27
ARGUMENTS:
1.
Petitioner claims that there is no conflict
regarding the interpretation or the
implementation of the Agreement. Thus, without
having to resort to prior arbitration, it is entitled
to collect the value of the services it rendered
through an ordinary action for the collection of a
sum of money from Respondent.
On the other hand, Respondent contends that
there is a need for prior arbitration as provided in
the Agreement. This is because there are some
disparities between the parties positions
regarding the extent of the work done, the
amount of advances and billable
accomplishments, and the set off of expenses
incurred by Respondent in its take-over of
Petitioners work.
2.
According to Petitioner, assuming arguendo that
the dispute is arbitrable, the failure to file a
formal request for arbitration with the CIAC
precluded the latter from acquiring jurisdiction
over the question.
RULING:
The Petition is unmeritorious; hence,
DENIED. The assailed Decision of the CA is
AFFIRMED.
1.
YES. SC sides with Respondent. The instant
case involves technical discrepancies that are
better left to an arbitral body that has expertise
in those areas.
2.
NO. SC is not persuaded with Petitioners
contention. Section 1 of Article III of the NEW
Rules of Procedure Governing Construction
Arbitration has dispensed with the requirement
to submit a request for arbitration. Recourse to
the CIAC may now be availed of whenever a
contract contains a clause for the submission of
a future controversy to arbitration.
RATIO DECIDENDI:
1.
In the instant case, the Subcontract has the
following arbitral clause:
6. The Parties hereto agree that any dispute or
conflict as regards to interpretation and
implementation of this Agreement which cannot
be settled between [respondent] and [petitioner]
amicably shall be settled by means of arbitration
x x x.
Clearly, the resolution of the dispute between
the parties herein requires a referral to the
provisions of their Agreement. Within the scope
of the arbitration clause are discrepancies as to
the amount of advances and billable
accomplishments, the application of the
provision on termination, and the consequent
set-off of expenses.
A review of the factual allegations of the parties
reveals that they differ on the following
questions, the resolutions of which lies in the
interpretation of the provisions of the
Subcontract Agreement:
1. Did a take-over/termination occur?
2. May the expenses incurred by
Respondent in the take-over be set off
against the amounts it owed Petitioner?
3. How much were the advances and
billable accomplishments?
-
ADR CASE DIGESTS 2015
pg. 28
Page number 28
Being an inexpensive, speedy and amicable
method of settling disputes, arbitration along
with mediation, conciliation and negotiation is
encouraged by the SC. Aside from unclogging
judicial dockets, arbitration also hastens the
resolution of disputes, especially of the
commercial kind. It is thus regarded as the
wave of the future in international civil and
commercial disputes. Brushing aside a
contractual agreement calling for arbitration
between the parties would be a step backward.
Consistent with the above-mentioned policy of
encouraging alternative dispute resolution
methods, courts should liberally construe
arbitration clauses. Provided such clause is
susceptible of an interpretation that covers the
asserted dispute, an order to arbitrate should be
granted. Any doubt should be resolved in favor
of arbitration.
2.
Section 1 of Article III of the NEW Rules of
Procedure Governing Construction Arbitration
provides:
SECTION 1. Submission to CIAC Jurisdiction
An arbitration clause in a construction
contract or a submission to arbitration of a
construction dispute shall be deemed an
agreement to submit an existing or future
controversy to CIAC jurisdiction, notwithstanding
the reference to a different arbitration institution
or arbitral body in such contract or submission.
When a contract contains a clause for the
submission of a future controversy to arbitration,
it is not necessary for the parties to enter into a
submission agreement before the claimant may
invoke the jurisdiction of CIAC.
As clearly explained in China Chang Jiang
Energy Corporation (Philippines) v. Rosal
Infrastructure Builders et al. (an extended
unsigned Resolution) and reiterated in National
Irrigation Administration v. Court of Appeals
[1999], from which SC quote thus:
Under the present Rules of Procedure, for a
particular construction contract to fall within the
jurisdiction of CIAC, it is merely required that the
parties agree to submit the same to voluntary
arbitration unlike in the original version of
Section 1, as applied in the Tesco case, the law
as it now stands does not provide that the
parties should agree to submit disputes arising
from their agreement specifically to the CIAC for
the latter to acquire jurisdiction over the same.
Rather, it is plain and clear that as long as the
parties agree to submit to voluntary arbitration,
regardless of what forum they may choose, their
agreement will fall within the jurisdiction of the
CIAC, such that, even if they specifically choose
another forum, the parties will not be precluded
from electing to submit their dispute before the
CIAC because this right has been vested upon
each party by law, i.e., E.O. No. 1008.
Clearly, there is no more need to file a request
with the CIAC in order to vest it with jurisdiction
to decide a construction dispute.
The arbitral clause in the Agreement is a
commitment on the part of the parties to submit
to arbitration the disputes covered therein.
Because that clause is binding, they are
expected to abide by it in good faith. And
because it covers the dispute between the
parties in the present case, either of them may
compel the other to arbitrate.